Ocean Beach Sand Backpass Project Relocating Sand from N Ocean Beach to Erosion Hotspot S Ocean Beach
A collaborative project between the National Park Service and the
City and County of San Francisco
July 17, 2012
National Park Serviceand
City and County of San Francisco
(San Francisco Public Utilities Commission / Department of Public Works)
![Page 2: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/2.jpg)
Ocean Beach Sand Backpass Project
• Project Location
• Project Description
• Existing Conditions
• Project Goals
• Design Concept
• Approvals
• Schedule
• Contact
Information
![Page 3: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/3.jpg)
![Page 4: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/4.jpg)
Project Objectives
• Remove sand from in front of
the O'Shaughnessy Seawall in
order to reduce future sand
maintenance efforts;
• Maintain public access on
promenade and stairwells
that have been blocked by
sand aggredation;
• Enhance beach access in the
erosion hotspot area;
• Provide for bluff protection in
high risk areas that threaten
CCSF infrastructure;
• Reduce the need to
implement more engineered
bluff protection measures in
the short-term.
![Page 5: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/5.jpg)
Existing Conditions
South of Sloat Area
O'Shaughnessy Seawall Area
![Page 6: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/6.jpg)
Existing Conditions
![Page 7: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/7.jpg)
![Page 8: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/8.jpg)
Scope of Work
• Survey beach and define volume of
sand available and prepare final design
• Determine placement locations and
configuration of relocated sand
placement in erosion hotspot area
(End-dump plan)
• Excavate and transport approximately
100,000 + cu yds of sand from in front
of O'Shaughnessy seawall
• Create a sacrificial sand berm at the
area south of Sloat for bluff protection
for CCSF infrastructure
• Monitor sand movement both
nearshore and longshore to inform
future beach nourishment efforts
![Page 9: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/9.jpg)
Seawall Profile
De
pa
rtme
nt o
f Pu
blic W
ork
s
Its over 13 feet
from top of
seawall to first
bleacher step
![Page 10: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/10.jpg)
Diagram of Excavation design
![Page 11: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/11.jpg)
Dune Design
![Page 12: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/12.jpg)
Dune DesignSand Berm
Placement
Sand Berm
Placement
Rubble Fill
Sandbags
1996 EQR
2010 Rock
Revetment
![Page 13: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/13.jpg)
Reviews and Approvals
1. NEPA / CEQA
2. Regulatory Approvals
• USFWS (Snowy Plover)
• California Coastal Commission (CD)
• USACE (404/401 ; Section 10)
• MTA-SF (traffic plans)
![Page 14: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/14.jpg)
Consultation / Coordination
• California Coastal Commission
• Regional Sediment Management Group
• NPS Project Review
• Golden Gate Audubon
![Page 15: Ocean Beach Sand Back Passing Program 120717 JLO](https://reader033.vdocument.in/reader033/viewer/2022050816/55349cc94a795968588b4c05/html5/thumbnails/15.jpg)
Schedule
Conduct Public Outreach –July
Regulatory Agency Review / Concurrence – July 13, 2012
Complete Environmental Compliance – CEQA / NEPA
Award Contract - July 20, 2012
Notice to Proceed - Late July / Early August
Project Completed – Early September 2012