Council’s 2nd Quarterly Report October – December 2013
Annexure 25 - Item D4 - February 2014
1
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Airport
Strategic
Focus
Area:
2 Infrastructure - Efficient and reliable infrastructure that supports and protects production, services and lifestyle.
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.3 Airport Master Plan
START DATE
2.1.3.4 Day to day
administrative activities.
Ongoing 1st Quarter: Day to day administration has been undertaken in a
timely manner, duties include aircraft landings/passenger and fees,
OHS reports, drug and alcohol reports, Airport Manual updates and
bird hazard reporting and documenting.
2nd Quarter: Additional to normal administrative activities, in this
quarter we have also developed a new Transport Security Program.
This ensures that we comply with Department of Transport
Regulations as well as providing a safe and secure environment for
all Airport users.
In December 2013 a technical inspection was undertaken during
which several issues were identified as needing attention in order to
comply with the standards of being a Certified Airport . These tasks
are currently being undertaken.
30/06/2014Airport Manager 1/07/2013
2.1.3.5 Seek the sale and
removal of the "house" building
from the Airport and ensure the
site is remediated as part of
sale conditions to allow for an
alternative future use of the
site.
In Progress 1st Quarter: Due to bad weather, the site has been inaccessible for
inspection. Council will seek tenders for the sale, removal and
remediation of the site during the second quarter.
2nd Quarter: Council will seek tenders for this project as soon as
practicable.
30/11/2013Airport Manager10% 1/07/2013
February 06, 2014 Page 2 of 3
Annexure 25 - Item D4 - February 2014
2
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Airport
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.3 Airport Master Plan
START DATE
2.1.3.6 Fund the construction
of a dedicated undercover
patient transfer facility for the
Royal Flying Doctor Service
(RFDS) to the west of the
terminal building as per the
capital works program.
In Progress 1st Quarter: Funds have been allocated for the construction of the
RFDS Patient Transfer Station and all planning approvals have been
granted. Due to a delayed grant approval for the apron extension
works which are required to access the proposed Patient Transfer
Station, this project has been delayed.
2nd Quarter: Due to funding delays, the original site for this project
has now changed and a new site for the Patient Transfer Station has
been identified. A planning approval amendment will be forthcoming
early in the next quarter, allowing the project to commence.
30/06/2014Airport Manager30% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.4 Capital Works Program
START DATE
2.1.4.1 Ensure a minimum of
85% of the capital works
program agreed for the Airport
is achieved.
In Progress 1st Quarter: In ground drainage works have been completed and
further open drainage works alongside both runways will be renewed
as part of the continued upgrade over coming months. Works to the
solar panels have taken place and planning for the apron and
taxiway extensions is complete.
2nd Quarter: New Airport vehicle has arrived and has been fitted
with bird siren, new hi-vis stripes and a light bar. Drainage works to
the open drains around the apron extension have been completed
and drainage works on the main runway have been partially
completed.
30/06/2014Airport Manager75% 1/07/2013
February 06, 2014 Page 3 of 3
Annexure 25 - Item D4 - February 2014
3
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Asset Management
Strategic
Focus
Area:
1 Environment and Natural Asset Management - An environment that maintains its diversity, uniqueness and
attractiveness while supporting sustainable production and lifestyle.
Strategic
Direction:
1.1 Promote environmentally sustainable practice
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.1.4 Environmental sustainability of Council programs and operations
START DATE
1.1.4.1 Weed management
within council land improved
and work towards best practice
approach within the confines of
budget allocations available.
In Progress 1st Quarter: Control of the following weeds has been successfully
undertaken on road reserves for this growing season:
- Onion Weed Asphodelus Fistulosus (Declared)
- Espartillo Amelichloa Caudata (Declared)
- African Lovegrass Eragrostis Curvula (Declared)
- Mullein/Aarons Rod Verbascum Thapsus (a significant
environmental weed of pastures & disturbed areas)
Trials on numerous weeds and control methods are ongoing and
much work has been done to develop a geo referencing system for
weeds and rare/threatened species on road reserves across the
island.
2nd Quarter: A casual Works Officer has been employed for
roadside and quarry weed control and options are being explored for
the contracting of roadside weed management.
30/06/2014Infrastructure
Manager
50% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.1.5 Transition to sustainable Solid Waste Management Systems
START DATE
1.1.5.1 Initiate recycling
programs that are financially
sustainable, user friendly and
environmentally appropriate for
our remote situation.
In Progress 1st Quarter: Glass and aluminium can separation is now in place
and being utilised by the community. This builds upon other areas
where separation of waste streams are already in place such as
tyres, white goods and e waste. Recycling of these goods will occur
when financially viable.
2nd Quarter: Solar powered compacting rubbish bins have been
purchased for installation at barbeque and popular remote areas
and should be operational next quarter.
30/06/2014Infrastructure
Manager
60% 1/07/2013
February 06, 2014 Page 2 of 8
Annexure 25 - Item D4 - February 2014
4
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Asset Management
Strategic
Direction:
1.1 Promote environmentally sustainable practice
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.1.5 Transition to sustainable Solid Waste Management Systems
START DATE
1.1.5.2 Provide new waste
management facility and
service level agreement for the
Cape Barren Island
Community.
In Progress 1st Quarter: Site Planning and flora and fauna assessments are now
complete. A series of test bores have been developed to scope
ground water levels. CBIAA and ALCT continue to be closely
engaged in the project.
2nd Quarter: An aerial survey of the site has been undertaken by an
unmanned aerial drone which took high quality images and contour
survey. This data will be used to begin the design of the new facility.
30/06/2014Infrastructure
Manager
50% 1/07/2013
1.1.5.3 Close landfill at Lady
Barron and implement a new
waste transfer station. Engage
with the community on the
proposed change, reasons for
such and new operations.
In Progress 1st Quarter: The continued burning of the Lady Barron tip and the
ongoing compliance issues associated with the site requires its
immediate closure. Council waste management consultants
provided a briefing to Council at a workshop on the 3rd of October
on the item and put forward a series of options for consideration.
Action on this item will commence in the next reporting period.
2nd Quarter: A cost benefit analysis of the options for the proposed
transfer stations is currently being developed and should be
provided to Council in the third quarter.
30/06/2014Infrastructure
Manager
40% 1/07/2013
1.1.5.4 The Northern Regional
Waste Management Group has
agreed to fund a Waste
Management Strategy for the
islands. Staff to present the
strategy when complete.
Not Started 1st Quarter: Council staff and consultants have requested the
Northern Tasmania Waste Management Group (NTWMG) delay any
action on this item until our own explorations and strategies are
complete.
2nd Quarter: This action remains unchanged as Council
explorations are still ongoing.
30/12/2013Infrastructure
Manager
0% 1/07/2013
February 06, 2014 Page 3 of 8
Annexure 25 - Item D4 - February 2014
5
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Asset Management
Strategic
Direction:
1.1 Promote environmentally sustainable practice
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.1.5 Transition to sustainable Solid Waste Management Systems
START DATE
1.1.5.5 The Northern Regional
Waste Management Group has
agreed to fund a fluorescent
tube landfill diversion project at
no cost to Council. Facilities for
the disposal and the removal of
fluorescent tube lights from the
Islands will be provided to the
community.
Completed Facilities for the disposal of fluorescent tubes have now been
provided.
30/06/2014Infrastructure
Manager
100% 1/07/2013
1.1.5.6 Communicate and
educate the community of the
changes to waste management
services, the reasons for the
changes and how they can
work with Council to improve
environmental outcomes from
the management of waste.
In Progress 1st Quarter: Major changes to waste management systems are
currently being explored and consultation and education will occur
as the process and systems are agreed.
2nd Quarter: Grant from Australian Packaging Covenant (APC) is
almost finalised. Some timeline issues require re-negotiation but the
commitment is forthcoming. Community education will play a major
role in the utilisation of the new system. Community engagement
and awareness formed part of the grant provisions from APC.
30/06/2014Development
Services
Officer/EHO
40% 1/07/2013
1.1.5.7 Explore green waste
reuse options.
In Progress 1st Quarter: Council waste management consultants provided a
briefing to Council at a workshop on the 3rd of October on the item.
Scoping of equipment and staff required is underway as is
exploration of what products could be developed from the waste
stream to offset costs.
2nd Quarter: Council waste management consultants are waiting on
data from the Residential Waste Assessment to develop an overall
waste reuse strategy.
30/06/2014Infrastructure
Manager
35% 1/07/2013
February 06, 2014 Page 4 of 8
Annexure 25 - Item D4 - February 2014
6
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Asset Management
Strategic
Direction:
1.1 Promote environmentally sustainable practice
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.1.5 Transition to sustainable Solid Waste Management Systems
START DATE
1.1.5.8 Undertake a feasibility
study into the use of waste
furnaces as opposed to landfill
into the future. Assess costs
and environmental outcomes
and provide a report to Council.
In Progress 1st Quarter: Council waste management consultants provided a
briefing to Council at a workshop on the 3rd of October on the item.
Scoping on two furnace systems has been undertaken and further
work is required from a systems management perspective before a
full feasibility study is required.
2nd Quarter: The study is in progress and will be delivered before
the end of the financial year.
30/06/2014Development
Services
Officer/EHO
50% 1/07/2013
February 06, 2014 Page 5 of 8
Annexure 25 - Item D4 - February 2014
7
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Asset Management
Strategic
Focus
Area:
2 Infrastructure - Efficient and reliable infrastructure that supports and protects production, services and lifestyle.
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.4 Capital Works Program
START DATE
2.1.4.2 Ensure a minimum of
75% of the Capital Works
program agreed is achieved.
In Progress 1st Quarter: Vertical slashing has been completed and Marshall Bay
is substantially complete with some minor works to undertake once
the road dries out.
2nd Quarter: Some gravel road resheeting has taken place and 75%
of components for Samphire River Bridge have been manufactured.
The reseal program has been deferred due to unavailability of local
blue metal supplies. As Council now contracts the bitumen spraying,
considerable savings can be made by adjusting the reseal program
from annual to possibly tri-annual.
Port Davies Boat Ramp has been completed to design standards.
Capital Plant purchased has included a Hilux 4x4 dual cab utility, an
Izuzu light truck and a JCB backhoe.
30/06/2014Infrastructure
Manager
50% 1/07/2013
2.1.4.3 Day to day
administrative activities.
Ongoing 1st Quarter: Administration duties are being undertaken as required.
2nd Quarter: The warm, wet spring kept town and roadside
vegetation maintenance crews busy due to the pronounced growing
season. A casual Works Officer was employed during the quarter
specifically for town maintenance duties.
30/06/2014Infrastructure
Manager
2/09/2013
February 06, 2014 Page 6 of 8
Annexure 25 - Item D4 - February 2014
8
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Asset Management
Strategic
Direction:
2.4 Pursue “best practice” delivery model that balances cost and outcomes
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.4.2 Review infrastructure management and operational procedures as basis of introduction of continuous improvement system
START DATE
2.4.2.1 Undertake assessment
with Works Manager of how to
improve bitumen sealing works
via a partnership approach with
skilled service providers/
access to modern equipment.
Completed 1st Quarter: With the introduction of the new Workplace Safety Act
on January 1st 2013, a risk assessment highlighted that the existing
equipment used by Council staff for bituminous sealing was very old
and of extreme risk to operators. This combined with the average
outcomes of the preceding years sealing program has seen action
taken to bring in outside contractors to undertake the tasks required
this year.
30/06/2014Infrastructure
Manager
100% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.4.3 Service standards are provided in line with asset management plan and budget allocations provided by Council.
START DATE
2.4.3.1 Roads, bridges and
culverts are maintained and
managed in line with budget
allocations provided.
In Progress 1st Quarter: Bridge and culvert maintenance has been undertaken
as per AusSpan schedule. Dry weather will allow for the construction
of the detour road at Samphire Creek and contractors are now
starting to manufacture beams for the bridge. Construction will begin
as soon as weather permits, component manufacture is complete
and contractor availability is secured. Vertical slashing has been
completed and the Marshall Bay road has been substantially
completed.
2nd Quarter: Approximately 75% of components have been made
for the Samphire Creek Bridge and installation and road detour
works are on target for the end of February should weather
conditions allow. Road maintenance consisted mainly of bitumen
patching and edging, gravel road grading and potholing as well as
vegetation control.
30/06/2014Infrastructure
Manager
50% 1/07/2013
2.4.3.2 Develop works
program, levels of service
specifications and associated
procedures in line with long
term asset management plan.
Not Started 1st Quarter: The Long Term Asset Management Plan is still under
development.
2nd Quarter: Staff continued to work with the Corporate Services
Manager and the General Manager to develop this plan.
30/06/2014Infrastructure
Manager
0% 1/07/2013
February 06, 2014 Page 7 of 8
Annexure 25 - Item D4 - February 2014
9
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Asset Management
Strategic
Direction:
2.4 Pursue “best practice” delivery model that balances cost and outcomes
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.4.3 Service standards are provided in line with asset management plan and budget allocations provided by Council.
START DATE
2.4.3.3 Maintain all Council
owned assets to the current
legislation/regulations and
applicable standards, so that
these assets are kept to the
appropriate service levels
expected within our
community.
In Progress 1st Quarter: When the results from the Community Infrastructure
Audit are obtained, work can then commence on completing Asset
Management Plans for all community assets. This is required before
completion of the Long Term Financial Plan can be achieved.
2nd Quarter: The Community Infrastructure Audit Report is to be
presented at the Councillor's Workshop on 27th February. From
there the Asset Management Plan will be able to progress.
30/06/2014Corporate Services
Coordinator
35% 1/07/2013
February 06, 2014 Page 8 of 8
Annexure 25 - Item D4 - February 2014
10
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Focus
Area:
2 Infrastructure - Efficient and reliable infrastructure that supports and protects production, services and lifestyle.
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.2 Review community facility portfolio with the view of developing a profile that matches contemporary and emerging needs
START DATE
2.1.2.1 Enable and assist the
local Scout Group to identify an
alternative venue and any grant
funding that is available for
their support.
Completed 1st Quarter: Council has assisted scouts to relocate to the Lions
Lodge.
30/06/2014Community
Development
Coordinator
100% 1/07/2013
2.1.2.2 Community Services
Hub: Work with DPAC to
develop a Community Services
Hub in Whitemark that
provides community benefit for
the access of State and
Council services.
In Progress 1st Quarter: DPAC has submitted an application to Treasury to move
the project to the next phase.
2nd Quarter: DPAC was informed prior to Christmas that the
submission had been considered and was with the Minister awaiting
a decision. To date, no decision has been made. It is expected the
State Government will go into caretaker mode when Parliament is
dissolved (expected to be on 12th February). If no decision has been
made prior to this point then the Project will need to be considered
post the election.
30/06/2014General Manager50% 1/07/2013
February 07, 2014 Page 2 of 19
Annexure 25 - Item D4 - February 2014
11
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.2 Review community facility portfolio with the view of developing a profile that matches contemporary and emerging needs
START DATE
2.1.2.3 Whitemark Foreshore:
Collaborate with the PWS,
Landcare, NRM North and
other community groups and
individuals to create further
community facilities on the
Whitemark foreshore such as
the Exersite gym equipment
and extension of the Bluff
Track so to further encourage
access to health promotion
activities; and the development
of the barbeque area to assist
to build further social inclusion
and engagement.
In Progress 1st Quarter: Site Masterplan is being developed. Regular
communication with Tasmania Medicare Local (TML) Program staff
and Fitness Trails Principal regarding the fabrication, delivery and
installation of the TML/HIP (Healthy Islands Project)donated
'Exersite' permanent outdoor exercise equipment. Successful
application of Rural Health Week grant to provide a series of free
exercise classes for the community using the exercise equipment.
Regular communication with TML staff to collaboratively launch the
HIP: 30 Stories in 3 Years publication at the launch of the Exersite.
Liaised with Council staff in the preparation of the Crown Land
Services Works Application and Council's Development Application.
Meetings with stakeholders on an as needs basis.
2nd Quarter: Decision was made to include planning for future
amenities and as such, a master planning approach has been taken.
This approach will also lessen the future workload of producing ad
hoc planning and building applications. The working group has met
a number of times within this planning phase, both onsite and off.
The Whitemark Foreshore has been surveyed, identifying a number
of anomalies with regards to the boundary of Council leased land
and TasPorts owned land which will require further investigation prior
to any planning or building applications being submitted.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
February 07, 2014 Page 3 of 19
Annexure 25 - Item D4 - February 2014
12
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.2 Review community facility portfolio with the view of developing a profile that matches contemporary and emerging needs
START DATE
2.1.2.4 Complete an audit of
Council's community and
recreational assets and provide
a report to Council indicating
costs to keep/upgrade to a
standard safe for community
use.
In Progress 1st Quarter: Data collection on all community assets is nearing
completion. Working with Resonance Consulting and relevant
Council staff to help inform the report.
2nd Quarter: All is progressing well. The Consultant has been
working with Council staff and relevant stakeholders to finalise the
population, financial and asset data analysis. The preliminary
community consultation with user groups to ascertain any future
needs and/or aspirations to inform the report is also being
undertaken. It is planned that the report will be tabled at the
Councillor Workshop in February.
01/12/2013Community
Development
Coordinator
70% 1/07/2013
February 07, 2014 Page 4 of 19
Annexure 25 - Item D4 - February 2014
13
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
2.4 Pursue “best practice” delivery model that balances cost and outcomes
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.4.1 Further refine the long term asset management plan to inform sustainable service delivery and standards.
START DATE
2.4.1.1 Community Halls:
Working with Council staff to
assist to facilitate the hall
maintenance process so to
comply with all relevant
standards for the future
multi-use requirements of the
community. Support the
community to: assist in the
maintenance of the hall
through working bees; develop
future events and activities at
Emita hall; and liaise with the
Hall Committee to ensure all
health & safety, maintenance
and usage procedures are
compliant with Council's
policies.
In Progress 1st Quarter: Submission of grant application to Regional
Development Australia Round 5 for $40, 000 towards the Emita Hall
upgrade and kitchen facilities. Ongoing communication to the Emita
Hall Committee members which has included the opportunity to
volunteer in the upgrade of the Emita Hall and explain the processes
around this. Ongoing updates and engagement with the Emita Hall
Committee via email, phone, face-to-face and attendance at
meetings. Established a register of interested volunteers. Assisted to
develop the Council's Volunteer Handbook. Assisted to develop
Volunteer Registration Form. Facilitated the Volunteer Induction
session; letters and email reminders to registered volunteers.
2nd Quarter: Assisting to coordinate with the Development Services
Coordinator all planning and building processes relating to the
upgrade. Ongoing updates on the project through the Chair of the
Emita Hall Special Committee of Council on the status of the project.
Regular meetings with Council staff to develop policy and
procedures relating to community halls, usage, bookings, risk
management and maintenance. Meetings and regular
communication with the Secretary of the Lady Barron Hall
Committee regarding impending changes to past processes and
procedures of the Lady Barron Hall Special Committee of Council.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
February 07, 2014 Page 5 of 19
Annexure 25 - Item D4 - February 2014
14
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Focus
Area:
4 Community Safety, Engagement and Enterprise - Through positive Council-Community partnerships, enhance
people’s security, inclusion and well-being.
Strategic
Direction:
4.2 Support effective and timely incident & emergency management planning and response
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.2.1 In conjunction with other emergency response groups, have appropriate plans and resources in place to mitigate and respond to
identified risks and incidents
START DATE
4.2.1.2 SES Ongoing 1st Quarter: Currently working with Andrew Cox from Tasmania Fire
Service (TFS) on a fire plan for Flinders Island as well as fire trail
updates for the Island for the new Emergency Services map book.
Another Municipal Emergency Management Committee meeting is
planned for the near future, this hasn't happened over the past 3
months due to the of the Northern Region SES Manager's
unavailability.
2nd Quarter: A Flinders Island Municipal Emergency Management
Meeting was held on the 19/12/2013. Council and local emergency
services will soon receive Satellite phones which will enhance the
communication capacity in the event of a major emergency on the
island. The local Police are also set to receive a VHF radio to be
placed in each of the police vehicles, giving Police the ability to
communicate efficiently with the Ambulance, SES and Fire Service
at incidents. The safety page on Council's new website is nearly
completed. It will include what to do in different emergencies as well
as contact lists etc.
30/06/2014Emergency
Management
Coordinator
1/07/2013
February 07, 2014 Page 6 of 19
Annexure 25 - Item D4 - February 2014
15
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.1 Engage with, as necessary support and integrate into Flinders Council plans key community based service providers.
START DATE
4.3.1.2 Liaise with the Flinders
Island District High School to
develop a MOU, or an
appropriate agreement, for
Council to facilitate the
Austswim Learn to Swim
program for youth benefit.
Completed 1st Quarter: Have met with the School Principal to confirm Council’s
future involvement and coordination of the Austswim Learn to Swim
Program for the summer season 2013/14. The Principal is looking
into what process and procedures will need to be in place for
Council's involvement. It was noted that Learn to Swim Program will
need to be held during School Hours.
2nd Quarter: Ultimately the new OH&S legislation has created some
serious issues for the School around standards for community use.
The Community Development Coordinator provided Council with an
update and briefing on this, and the impacts on staff resources, for
Council to continue actively working to facilitate the Learn-to-Swim
program with the School. Council staff raised the issues facing
Flinders Island potentially not delivering a Learn-to-swim program
with the Royal Life Saving Society of Australia (Tasmania) (RLSSA)
and consequently, RLSSA made contact with the Principal of the
School in an attempt to take up the facilitation of this Program in
partnership with the School. From this point, Council staff have
absolved themselves from reaching an appropriate agreement with
the School for the delivery of the Learn-to-swim program and has
ultimately left this to the School and the RLSSA.
30/06/2014Community
Development
Coordinator
100% 1/07/2013
4.3.1.3 Implement a
Community Road Safety
Partnership.
In Progress 1st Quarter: Liaised with DIER's Community Road Safety
Partnership Officer to confirm potential project funding and process .
Met with stakeholders to review proposed actions and identify 2-3
community projects. Action Plan developed and submitted to DIER
for confirmation to move forward and available funding.
2nd Quarter: No further action to report.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
February 07, 2014 Page 7 of 19
Annexure 25 - Item D4 - February 2014
16
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.1 Engage with, as necessary support and integrate into Flinders Council plans key community based service providers.
START DATE
4.3.1.6 Rural Primary Health
Service: Administer the funding
to deliver the Community
Nurse and Podiatrist services
and work with Tas Medicare
Local to identify future
community health needs that
could be funded under this
scheme.
In Progress 1st Quarter: New funding arrangements with Tasmania Medicare
Local (TML) confirmed.
Successful negotiation with new podiatry service provider and
Services Agreement drafted and signed.
2013-14 RPHS Service Delivery Plan complete.
Drafted Service Agreement - TML/Council/Tasmanian Health
Organisation North (THO-N) for community nursing component of
RPHS. Submitted to TML for approval in August. Currently awaiting
a reply from TML to move forward.
12 month report 2012-13 submitted with audited financials.
Working with TML staff to revise the Community Health Needs
Assessment with data collected early 2013 from the Health Needs
Survey. Researching Population Health Programs to assist in the
development of the revised Community Health Needs Assessment .
2nd Quarter: The Services Agreement for community nursing
provision between THO-N (Flinders Island Multi-Purpose Centre)
and Council has not yet been signed. This was stalled due to
Council seeking a tripartite agreement between Council, TML and
THO-N, as advised by Council’s solicitor, and the lengthy period
Council was waiting for a response from TML with respect to the
proposition. This delay resulted in Council being unable to present
the Services Agreement to THO-N until mid-November, 2013. The
Crown Solicitor is currently reviewing the Services Agreement. It is
anticipated that the Services Agreement for community nursing with
THO-N will be forthcoming. Irrespective of this delay, the service
delivery of community nursing to the Flinders municipality on both
Cape Barren and Flinders Islands, have not been affected.
The community Health Needs Assessment has not been completed
as stipulated in Schedule 2 of the Services Agreement between TML
and Council. Council staff look forward to receiving further guidance,
support and direction from TML in the development of the
community health needs report in the coming months to inform
30/06/2014Community
Development
Coordinator
50% 1/07/2013
February 07, 2014 Page 8 of 19
Annexure 25 - Item D4 - February 2014
17
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.1 Engage with, as necessary support and integrate into Flinders Council plans key community based service providers.
START DATE
service delivery and funding arrangements for RPHS post June
2014. It is concerning that the delay in the development of our
Health Needs report may inturn affect the ideal time frames required
to secure a podiatry service provider if this service is to continue in
its current funding arrangement.
The new podiatrist firm has been delivering services to the Flinders
community as per the Service Delivery plan.
The 6-month RPHS report (July 2013 - Dec 2013) was submitted on
time.
February 07, 2014 Page 9 of 19
Annexure 25 - Item D4 - February 2014
18
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.1 Engage with, as necessary support and integrate into Flinders Council plans key community based service providers.
START DATE
4.3.1.7 Future Preventative
Health Initiatives (PHI): In
collaboration with stakeholders
assist to develop project
funding submissions to
Medicare Local to facilitate and
support an annual calendar of
PHI initiatives such as Bloke's
Day Out, Womens Health Day,
Pedometer Challenge, Flinders
Island Running Festival, Parks
& Wildlife/Heart Foundation
Walks.
In Progress 1st Quarter: Provided support for the Flinders Island Running
Festival. Successful grant application for Rural Health Week (RHW)
to provide a series of free community exercise classes planned
using the permanent outdoor exercise equipment to be installed on
the Whitemark foreshore. Convening of Health Promotion Network
meetings.
2nd Quarter: RHW activities, through a successful grant submission,
was delivered successfully to the Flinders community; a grant
submission to Tasmania Medicare Local (TML) for $12,000 to
deliver PHI to the Flinders community has been successful. It is
planned that free exercises will be delivered utilising the yet to be
installed outdoor exercise equipment on the Whitemark foreshore.
This will also enable community to learn how to utilise the equipment
best for their individual needs. The format will be similar to the
Actively Ageing Program delivered in 2013. No other funding
opportunities for PHI have been made available to Flinders from
TML at this point.
The Medibank Active Tasmania Awards 2013 awarded TML both the
overall Gold award and the Partnership award for the Healthy Island
Project (HIP) program. It has been noted that this award money will
be allocated to the Flinders community for preventative health
activities. To date, despite Council staff's best efforts to engage with
TML on this, they have failed to outline how this will be spent in the
community.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
February 07, 2014 Page 10 of 19
Annexure 25 - Item D4 - February 2014
19
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.1 Engage with, as necessary support and integrate into Flinders Council plans key community based service providers.
START DATE
4.3.1.8 Identify further
opportunities for, and assist the
Flinders Island District Hiigh
School with the Transition
Program.
In Progress 1st Quarter: Council and School staff have met to discuss future
areas that Council can assist with the School's Transition Program.
Business case currently being developed by Council and School
staff working collaboratively.
2nd Quarter: The Transition Program Business Plan has been
developed between Council and School staff and is currently waiting
to be reviewed by the School Principal before being submitted to the
General Manager for consideration.
Council staff have been liaising with TAFE Drysdale staff to explore
the potential of a future course to be delivered on the Island in Event
Management and Hospitality for young people who may decide not
to pursue College/University off-island.
Meander Valley Council (MVC) have generously provided Flinders
Council with funding towards 2 flight tickets for young people to
attend the leadership camp Stepping Stones. Council staff continue
to liaise with MVC staff with this opportunity.
30/06/2014Community
Development
Officer
50% 1/07/2013
4.3.1.9 Identify and assist to
provide further community
engagement with the Flinders
Island Sports & RSL Club.
In Progress 1st Quarter: Worked with the Sports Club to facilitate the Flinders
Island Running Festival weekend events.
2nd Quarter: Council staff have proposed that the Sports Club be
utilised for community group meetings due to the need for another
after hours meeting space in Whitemark. The proposal will go to the
next Sports Club Committee meeting.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
February 07, 2014 Page 11 of 19
Annexure 25 - Item D4 - February 2014
20
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.1 Engage with, as necessary support and integrate into Flinders Council plans key community based service providers.
START DATE
4.3.1.10 Liaise and engage
with the Flinders Island
Aboriginal Association Inc. to
identify and support as
necessary areas which Council
and FIAAI can collaborate for
community benefit.
In Progress 1st Quarter: Met with yadas (Young Aboriginal Drug & Alcohol
Services) and FIAAI to identify youth programs. Regular
communication to FIAAI with regards to Council's youth School
Holiday Program to ensure no duplication of youth activities and to
help promote Council's programs to FIAAI members.
2nd Quarter: Regular communication with FIAAI staff with regards to
Council's community programs such as School Holiday and Rural
Health Week to work cooperatively.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.2 Build civic engagement and increase civic pride through evidence based research, agreed events, programs and improved
communication with the community.
START DATE
4.3.2.1 Manage Council's
online activities and re-develop
the website
In Progress 1st Quarter: The management of Council's online and social media
activities are ongoing. The website upgrade is in progress with the
wireframe, sitemap and build complete. Current work is being
undertaken on the content development and sourcing of new
imagery.
2nd Quarter: The Council website upgrade is nearing completion,
including upgrading the community calendar. A community
engagement plan for the community calendar is being developed.
The management of Council's online and social media activities are
ongoing.
30/06/2014Communications
Officer
90% 1/07/2013
4.3.2.2 Planning and
executing the new community
calendar and integrating into
the new website. The content
of events will be managed by
community development. A
report will be produced
measuring community uptake.
In Progress 1st Quarter: The planning and build of the community calendar is
well progressed. Final refinements are being undertaken and this
will then be integrated with the upgraded Council website. This will
be rolled out and promoted once the website is launched.
2nd Quarter: The Council's upgrade to the community calendar is
nearing completion. A community engagement plan for the
community calendar is being developed.
30/06/2014Communications
Officer
85% 1/07/2013
February 07, 2014 Page 12 of 19
Annexure 25 - Item D4 - February 2014
21
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.2 Build civic engagement and increase civic pride through evidence based research, agreed events, programs and improved
communication with the community.
START DATE
4.3.2.3 Develop and
implement a Community-wide
Volunteer Strategy
In Progress 1st Quarter: Council Volunteer Handbook has been developed.
Council Community Development staff and Risk Management
Officer are working collaboratively to ensure all Council Volunteers
have completed the Council Volunteer Induction program.
Community Organisations' contact list is currently being updated.
Liaised with Employment Service Providers to assist in identifying
key volunteer opportunities within the community. Delivered Council
Volunteer Induction to the Emita Hall Committee.
2nd Quarter: Regular meetings with Council staff to ensure the
consistent development of policy and procedures relating to
Council's Special Committees and the communication engagement
plan around this.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
4.3.2.4 Council Community
Communication Strategy:
Develop a council
communication strategy that
clearly identifies the role of the
Council, staff (including the role
of the community development
officer) within the community
and can be clearly
communicated. This will
include the projected tools,
internal and external strategic
directions that will align with
other council departments.
In Progress 1st Quarter: Initial work has been completed holding a staff
communications workshop which formulated initial ideas for the
development of the community communication strategy. Further
work on this will be undertaken in the coming period.
2nd Quarter: Research and initial preparation of the communication
strategy is under way. This is expected to be completed prior to the
end of the financial year.
30/06/2014Communications
Officer
45% 1/07/2013
February 07, 2014 Page 13 of 19
Annexure 25 - Item D4 - February 2014
22
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.2 Build civic engagement and increase civic pride through evidence based research, agreed events, programs and improved
communication with the community.
START DATE
4.3.2.5 Establish and manage
a digital image library and
related compliance
documentation for public
relations, promotion and
advertising use by Council.
Completed 1st Quarter: The Image Library and compliance documentation are
established and functioning well. Images are added to the library as
and when recieved. Overall management and data entry will be
ongoing.
30/06/2014Executive Officer100% 1/07/2013
4.3.2.6 Provide support to the
community organisation
Fitness on Flinders with
regards to health benefit
related community events such
as the Flinders Island Running
Festival.
In Progress 1st Quarter: Provided support to Fitness on Flinders with the
Flinders Island Running Festival events.
2nd Quarter: Ongoing engagement with Fitness on Flinders on an
as needs basis.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
February 07, 2014 Page 14 of 19
Annexure 25 - Item D4 - February 2014
23
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.2 Build civic engagement and increase civic pride through evidence based research, agreed events, programs and improved
communication with the community.
START DATE
4.3.2.7 Promote liveability and
economic viability of the
Flinders Municipality.
In Progress 1st Quarter: Successful submission to present at the inaugural
Australian Age-Friendly Cities and Communities Conference
(AFCC). Completion of Conference presentation material by
Community Development staff.
Community Development staff prepared a submission to the
Medibank Active Tasmania Awards; facilitated, promoted and
assisted in the coordination of the community screening of the 72
Hours footage with the Flinders Island Tourism Association; assisted
with the coordination of the National Plant a Tree Day activity held at
the Bluff Fitness Trail with organisations Parks & Wildlife Services,
Council and Landcare and liaised with the East Coast Odyssey crew
to assist to facilitate a School education cleanup the beach program
with organisation Two Hands; and the screening of the East Coast
Odyssey. Unfortunately, the planned events were cancelled due to
the ship not being able to dock at Flinders Island.
2nd Quarter: Successfully coordinated First Aid courses delivered by
St John Ambulance to community members. Support provided to
Tourism Tasmania, Sharp Airlines and Flinders Island Tourism
Association in the development of the spring campaign to regional
Victoria. Regular support provided to Flinders Island Tourism
Association to promote the Islands and region which has provided
good exposure in particular in the UK
(http://www.theguardian.com/travel/2014/jan/05/winter-survival-guide
-travel-destinations . Regular active engagement and involvement
with the Flinders Island Regional Arts branch in the development of
future arts activities. Regular updates in the Island News that
includes community grant opportunities.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
February 07, 2014 Page 15 of 19
Annexure 25 - Item D4 - February 2014
24
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.2 Build civic engagement and increase civic pride through evidence based research, agreed events, programs and improved
communication with the community.
START DATE
4.3.2.8 Explore and provide
recommendations to Council
on Flinders delivering the
Australian Small Islands Forum
in 2014.
Completed 1st Quarter: A Scoping Report on the feasibility and practicalities of
Flinders Council hosting the Australian Small Islands Forum in 2014
was presented to Council at a Councillor workshop and at the
Ordinary Council Meeting on 15 August 2013.
30/10/2013Executive Officer100% 10/07/2013
4.3.2.9 Event Policy: Assist to
develop an event policy for
community organisations and
individuals that gives a clear
direction of relevant
compliance and policy when
putting on community events
so as to assist in encouraging
a greater number of events on
the islands.
In Progress 1st Quarter: Working with Council staff to initiate and develop an
accounting structure that captures Council's donations to community
groups for event assistance. Further work on a specific policy will be
undertaken as the year progresses and initial scoping is completed.
2nd Quarter: Council staff have been working on the development of
a customer service model regarding Hall and community space
bookings. This project relates to the Volunteer Strategy which is
currently being carried out. This will inform the Event Strategy.
Council staff have assisted to support a number of community
events.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
February 07, 2014 Page 16 of 19
Annexure 25 - Item D4 - February 2014
25
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.4 Facilitate the provision and enhancement of critical health and education facilities and service levels by state and federal
agencies and NGOs
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.4.1 Collaborate with incorporated bodies associated with key facilities and services to retain and enhance scope and level of service,
including implementation of innovative responses
START DATE
4.4.1.2 Actively participate in
the Cancer Council's Steering
group of the supportive care
model for rural and remote
communities project with other
health stakeholders and
community members to
support and facilitate future
Cancer Support Services to the
Flinders Municipality.
In Progress 1st Quarter: Actively engage in regular meetings with all
stakeholders to develop the support care model for cancer support
services in the Flinders municipality. Promoted and assisted in the
Cancer Council of Tasmania Cancer Support Information Sessions
held at both Lady Barron and Whitemark. Promoted and provided
assistance to identify community members interested in being
involved in the Cancer Council of Tasmania's Volunteer Ambassador
Program.
2nd Quarter: Continued active engagement in the Steering group
meetings and continued support and facilitation provided for public
meetings held by the Cancer Council. Development underway for
referral pathway and associated materials including Living with
Cancer Information Pack to give to newly diagnosed patients.
Planning is underway for training to be made available to all
community members and Health Professionals offering a basic level
of knowledge, skills and communication to provide cancer support to
friends and family. This is planned to be delivered in March.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.4.2 Deliver and/or facilitate delivery of health and activity based programs and events for community and youth.
START DATE
February 07, 2014 Page 17 of 19
Annexure 25 - Item D4 - February 2014
26
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.4 Facilitate the provision and enhancement of critical health and education facilities and service levels by state and federal
agencies and NGOs
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.4.2 Deliver and/or facilitate delivery of health and activity based programs and events for community and youth.
START DATE
4.4.2.1 Deliver an integrated
school holiday activities
program.
In Progress 1st Quarter: School Holiday Program questionnaire developed, sent
and collated to assist in identifying and ranking activities and
programs for Council's School Holiday Program. Activities towards
the delivery of the October School Holiday program - Rock Climbing
Abseiling - include: Coordinating professional instructors;
development and collation of all registration forms; completion of the
Risk Management Plan; promotion and publicity material for the
activity.
Assisted the Regional Arts branch with the Flinders Flicks promotion
of workshops and events during the July School Holidays.
2nd Quarter: Successfully delivered the October School Holiday
Program. An annual 2014 program of School Holiday activities was
developed and released to the community in December which
includes the one application and permission form for the year in an
attempt to cut down on administration for staff and also for parents
whilst also giving an indication of participant numbers and interest
which can assist to inform the 2014 budget planning processes.
Coordinated bronze medallion certificate and training for surf school
staff including surf coaches.
30/06/2014Community
Development
Coordinator
50% 1/07/2013
4.4.2.2 Provide support to the
community organisation, the
Flinders branch of the
Tasmanian Regional Arts, with
arts & culture related
community events such as the
Flinders Flicks Festival.
In Progress 1st Quarter: Assisted and provided support to the following Regional
Arts Branch activities and events: Flinders Flicks and Australia's
Unsung Heroes.
2nd Quarter: Council have actively sought to support the Flinders
Island branch of Regional Arts which has included the purchase of
the art gallery in Whitemark, active promotion of events and regular
attendance at meetings.
30/06/2014Community
Development
Coordinator
75% 1/07/2013
February 07, 2014 Page 18 of 19
Annexure 25 - Item D4 - February 2014
27
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Community Development
Strategic
Direction:
4.5 Support capacity building in community organisations and facilitate the development of community enterprise
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.5.1 Identify opportunities to enhance the delivery and governance skills of community organisations and establishment of community
responses to opportunities and challenges
START DATE
4.5.1.1 Day to day
administrative activities.
In Progress 1st & 2nd Quarters: All administrative duties completed successfully
during the period.
30/06/2014Community
Development
Coordinator
50% 2/09/2013
February 07, 2014 Page 19 of 19
Annexure 25 - Item D4 - February 2014
28
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Corporate Services
Strategic
Focus
Area:
2 Infrastructure - Efficient and reliable infrastructure that supports and protects production, services and lifestyle.
Strategic
Direction:
2.4 Pursue “best practice” delivery model that balances cost and outcomes
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.4.2 Review infrastructure management and operational procedures as basis of introduction of continuous improvement system
START DATE
2.4.2.2 Develop and deliver a
Risk Management Framework,
Risk Management Policy and
an integrated Risk Register to
inform the treatment of risk
across the organisation and to
mitigate risk for employees,
Councillors and the community.
In Progress 1st Quarter: Draft Risk Management Framework has been
completed and will be discussed at the December Councillor
Workshop.
2nd Quarter: The draft Risk Management Framework agenda item
was deferred until the January Councillor workshop. In the interim,
the Framework document was reviewed by an external consultant
and some minor changes included.
01/02/2014OH&S Risk
Management
Officer
50% 1/07/2013
February 07, 2014 Page 2 of 6
Annexure 25 - Item D4 - February 2014
29
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Corporate Services
Strategic
Focus
Area:
5 Corporate Governance and Intergovernmental Relations - decisions are professionally and transparently made,
communicated and implemented to achieve defined outcomes in the interest of the community
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.1 Design and implement an integrated governance; strategic and operational planning & service delivery system
START DATE
5.1.1.1 Design and implement
a revised grant and contract
management system.
In Progress 1st Quarter: Review of current Grant and Contract Management
System has been completed. Discussions with staff members
outlining key areas for improvement has taken place.
2nd Quarter: A draft Contract Management Plan has been
completed. Further discussions were held with staff regarding areas
to focus on and implement. The next stage will be to apply the
template to a funding agreement to iron out any problems and fine
tune the process.
30/06/2014Corporate Services
Coordinator
30% 1/07/2013
5.1.1.4 Review all Council’s
long term strategic documents
within the 3 year review
timeframe.
Not Started 1st Quarter: With the end of year processing now complete and the
Tasmania Audit Office report on road asset treatment due for
publication in November, these documents will be reviewed and
updated in the next quarter.
2nd Quarter: This task is pending the outcome of the Draft
Ministerial Order, which will provide the Council with direction as to
the minimum requirements for the Financial Management Strategy
and the Asset Management Strategy. The Council has lodged a
submission with regards to their concerns surrounding the Draft
Ministerial Orders and are waiting on the outcome.
30/06/2014Corporate Services
Coordinator
0% 1/07/2013
February 07, 2014 Page 3 of 6
Annexure 25 - Item D4 - February 2014
30
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Corporate Services
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.1 Design and implement an integrated governance; strategic and operational planning & service delivery system
START DATE
5.1.1.5 Maintain Council’s
Property and Rates program as
and when required.
In Progress 1st Quarter: The Property System is currently up to date with the
rates being raised during August. A supplementary rate notice will be
generated in October to reflect any changes to properties
concerning their valuation, subdivisions & change of owners etc.
The first rates instalment is due on 22nd October 2013.
2nd Quarter: The second instalment rate notices have been
generated and posted. The final instalment is due on the 18th
February 2014.
30/06/2014Corporate Services
Coordinator
50% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.3 Achieve a sustainable balance of income, investment and recurrent expenditure
START DATE
5.1.3.1 Develop Long Term
Financial Management Plan.
In Progress 1st Quarter: The end of financial year work is now complete with the
Tasmanian Audit Office and again the treatment of our gravel road
surface depreciation schedules has proven problematic. The
Tasmanian Audit Office will issue a report on the treatment of road
assets in November, at which time our asset management plan can
be updated to reflect these changes and model the long term
implications at an asset and financial level. Further detailed work is
also being undertaken in relation to our building and community
facilities, this information is also critical to the development of the
long term asset management plan and consequently the long term
financial plan. As this information comes to hand these critical long
term plans will be further refined and developed.
2nd Quarter: The Long Term Financial Management Plan is on track
to be completed by April 2014.
30/06/2014Corporate Services
Coordinator
50% 1/07/2013
February 07, 2014 Page 4 of 6
Annexure 25 - Item D4 - February 2014
31
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Corporate Services
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.3 Achieve a sustainable balance of income, investment and recurrent expenditure
START DATE
5.1.3.2 Work collaboratively
with the Tasmanian Audit Office
to address depreciation issues
relating to residual values
applied to the road network.
In Progress 1st Quarter: During the reporting period a significant amount of staff
time and resources were dedicated to working with the Tasmanian
Audit Office on our depreciation treatment of gravel road surfaces .
Late advice from the Auditor General directed Officers to maintain
the same approach to the item as utilised in the previous financial
year despite there being no specific reasoning provided that the
approach taken by Council was not in compliance with the current
accounting standard or the engineering reality of the assets service
life. Given that the Tasmanian Audit Office will deliver a report on the
matter in November, all Tasmanian Councils will then have a clear
direction on how to treat these assets in the future.
2nd Quarter: Council is working through this issue with the
assistance of Brighton Council.
30/06/2014Corporate Services
Coordinator
50% 1/07/2013
5.1.3.3 Deliver the new Budget
Estimates for the proceeding
financial year.
Not Started 1st Quarter: Work has not commenced as this will be started in
2014 during the third quarter.
2nd Quarter: Work to begin in March 2014.
30/06/2014Corporate Services
Coordinator
0% 1/07/2013
5.1.3.4 Review the current
Budget Estimates as and when
directed.
In Progress 1st Quarter: Work has not commenced during this quarter. A half
yearly budget review will be done at the beginning of 2014.
2nd Quarter: The half yearly budget review has commenced and will
be presented at the February 2014 Council Meeting.
30/06/2014Corporate Services
Coordinator
40% 1/07/2013
5.1.3.5 Deliver financial
reports as and when directed.
In Progress 1st Quarter: The first quarterly financial report will be submitted to
Council at its October meeting. This will be prepared by Council's
financial consultant in the absence of the Corporate Services
Manager.
2nd Quarter: The second quarterly financial report has been
completed and will be submitted to Council at the February Council
Meeting.
30/06/2014Corporate Services
Coordinator
50% 1/07/2013
February 07, 2014 Page 5 of 6
Annexure 25 - Item D4 - February 2014
32
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Corporate Services
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.3 Achieve a sustainable balance of income, investment and recurrent expenditure
START DATE
5.1.3.6 Deliver financial
services including and not
limited to creditors, debtors,
rates receivables and
investments.
In Progress 1st Quarter: All financial functions are running smoothly and all
statutory requirements being complied with.
2nd Quarter: Financial functions continue to run smoothly and all
statutory requirements have been complied with. Staff have been
planning how best to minimise challenges in the third quarter when
Corporate Services Manager Kim Hossack relocates to Brighton and
Sophie Pitchford takes up the position of Corporate Services
Coordinator.
30/06/2014Corporate Services
Coordinator
50% 1/07/2013
5.1.3.8 Day to day
administrative activities.
In Progress 1st Quarter: All day to day administrative functions are running
smoothly, even though it has been very challenging for all staff at
times due to long term staff sickness and absences.
2nd Quarter: Corporate Service Manager Kim Hossack has decided
to relocate back to Brighton. Kim will be assisting Council three days
a week as a Consultant with Brighton. Sophie Pitchford will come on
board as the Corporate Services Coordinator in February working
three days a week. Staff have been planning how best to undertake
the transition period in order to minimise challenges. Di Walsh has
been training Kelly Blundstone in the accounts payable area to
relieve the pressure on Di while staff members are on leave.
30/06/2014Corporate Services
Coordinator
50% 1/07/2013
February 07, 2014 Page 6 of 6
Annexure 25 - Item D4 - February 2014
33
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Focus
Area:
1 Environment and Natural Asset Management - An environment that maintains its diversity, uniqueness and
attractiveness while supporting sustainable production and lifestyle.
Strategic
Direction:
1.3 Enhance access to and use of environmental assets to ensure values are recognised
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.3.1 Protect and as required formalise public access to coastal and inland areas
START DATE
1.3.1.1 Work with Landowner
and Crown Land Services to if
possible secure coastal access
at Pot Boil Road White Beach,
Lady Barron.
In Progress 1st Quarter: No progress to date. This will be actioned in the second
quarter of the financial year.
2nd Quarter: This land has been included in a list of all Crown Land
that Council wishes to purchase/ have transferred. Once Crown
Land Services, via Parks and Wildlife Services as the land manager,
are able to direct us as to which properties can be purchased and
the process involved, this action will be progressed further. The land
owner has not been engaged to date while staff await further
direction/information from Crown Land Services.
30/06/2014Development
Services
Officer/EHO
20% 1/07/2013
February 07, 2014 Page 2 of 11
Annexure 25 - Item D4 - February 2014
34
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Focus
Area:
2 Infrastructure - Efficient and reliable infrastructure that supports and protects production, services and lifestyle.
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.2 Review community facility portfolio with the view of developing a profile that matches contemporary and emerging needs
START DATE
2.1.2.1 Complete annual
health & safety audits of
Council's built assets.
In Progress 1st Quarter: Annual Maintenance Statements issued and current for
all Council facilities, dated until 6/8/2014.
2nd Quarter: Place of Assembly Licences issued until Feb 2014.
30/06/2014Development
Services
Officer/EHO
50% 1/07/2013
2.1.2.2 Explore the provision
of drinking water/bottle filling
stations at Whitemark and
Lady Barron and provide a
report to Council on
establishment and operational
costs associated.
In Progress 1st Quarter: Recent meetings with TasWater regarding their plans to
provide treated water to Whitemark and Lady Barron has impinged
on this project somewhat. There may still be the need for drinking
water to be provided to town and tourists alike, however this will
depend on the scope and quality of water that TasWater provide .
2nd Quarter: Have met with TasWater's senior engineer who has
advised that, in his opinion, the water of both towns would be
relatively easy to clean up. The alarming levels of Whitemark lead
appear to be primarily from poor sampling practices as the results
were too inconsistent to indicate a water quality issue. He also
believes that the lead levels were relatively low and could be easily
minimised. Discolouration from both Whitemark and Lady Barron
should be simply addressed with small package treatment plants at
each town with no need for a new bore to supply both towns. Council
awaits further advice on water quality before this item can be
actioned. Deferred until that time.
30/06/2014Development
Services
Officer/EHO
20% 1/07/2013
February 07, 2014 Page 3 of 11
Annexure 25 - Item D4 - February 2014
35
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Direction:
2.2 Optimise infrastructure to support existing settlements and enhance sustainable development opportunities and remove
impediments to growth
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.2.1 Identify, research, design and implement key infrastructure projects and programs to meet the economic and environmental needs of
Council and the community.
START DATE
2.2.1.1 Finalise Feasibility
Study into the development of
a Waste Effluent Processing
facility.
In Progress 1st Quarter: The project has been scoped and a feasibility proposal
is nearing completion.
2nd Quarter: The pre-feasibility study has been presented with two
options. One boasted a very low purchase cost but had very high
running costs (package plant) while the option of waste water
lagoons, although expensive to build initially, was found to provide
good longevity, was simple and efficient to operate and with many
other waste water lagoon systems operating in Tasmania it means
that the expertise, training and maintenance liaison would be
available, which is of great benefit to our isolated Municipality. The
lagoons system is the preferred option and further investigation into
siting and building the system is being investigated. TasWater
offered their engineer to review the study and provide comment . He
will meet with our Consultant in Melbourne in mid February.
30/06/2014Development
Services
Officer/EHO
50% 1/07/2013
February 07, 2014 Page 4 of 11
Annexure 25 - Item D4 - February 2014
36
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Focus
Area:
3 Land use, Development and Building - A productive system of land and building development that promotes
investment and activity while protecting people and the environmental characteristics of the Flinders municipal area.
Strategic
Direction:
3.1 Utilise best practice planning principles in conjunction with Flinders Councils Strategic Plan to guide detailed planning policy
and planning tools
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 3.1.1 Apply and refine as necessary the classification structure and planning principles defined in the Flinders Planning Scheme to key areas
while directly engaging with the community to further the consultation commenced with the draft Interim Planning Scheme. This will ensure
planning principles and outcomes reflect community needs and desires and provide timely strategic planning for future economic and
community development.
START DATE
3.1.1.2 Review evidence and
develop a Sea Level Rise
Policy to provide direction to
Council and planning staff on
the risk and liability issues
surrounding proposed sea level
rise and the State Coastal
Policy.
Not Started 1st Quarter: Information still being provided to Council re this topic.
Consultant Senior Town Planner, Jo Oliver, is Council's
representative on this project and will provide documentation and
updates as more information comes to hand.
2nd Quarter: This item has been deferred due to the other demands
on the Senior Town Planners time. This is a strategic policy which
will require the collation of data from State mapping and from
Council to form a policy that is in keeping with the State Coastal
Policy and any other overarching planning requirements.
30/06/2014Development
Services
Officer/EHO
0% 1/07/2013
February 07, 2014 Page 5 of 11
Annexure 25 - Item D4 - February 2014
37
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Direction:
3.5 Prepare a contemporary planning system, supporting development and people to achieve their goals while protecting
environmental values
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 3.5.1 Complete and implement the new Flinders Planning Scheme.
START DATE
3.5.1.1 Particular Purpose
Zones for Cape Barren Island
and other outer islands are
prepared, consulted and
finalised for inclusion within the
draft Interim Planning Scheme.
In Progress 1st Quarter: Cape Barren Island Aboriginal Association Incorporated
(CBIAAI) has been contacted about times/places suitable to hold the
final round of interviews on the island for private land owners.
The Aboriginal Land Council of Tasmania (ALCT) has been engaged
in the process and a community information session was held in
Launceston in the previous reporting period.
2nd Quarter: This process has delayed due to the current work load
of the Senior Town Planner. A time to re-establish the project is
unknown at this stage. Council may need to consider the
engagement or employment of another Town Planner in the near
term if this project is to be completed.
30/06/2014Development
Services
Officer/EHO
30% 1/07/2013
3.5.1.2 Specific Area Plans to
be developed with individual
communities to ensure that
planning controls are relevant
and pertinent to the area and
communities.
Not Started 1st Quarter: To commence after scheme is declared
2nd Quarter: This process has been delayed due to the current work
load of the Senior Town Planner. A time to re-establish the project is
unknown at this stage. Council may need to consider the
engagement or employment of another Town Planner in the near
term if this project is to be completed.
30/06/2014Development
Services
Officer/EHO
0% 1/07/2013
3.5.1.3 Finalise all supporting
documentation required to be
submitted to the Tasmanian
Planning Commission for
Interim Planning Scheme
assessment to ensure time
delays are negated and
scheme is compliant.
In Progress 1st Quarter: Particular Purpose Zones to be completed.
Interviewing of the private land owner community residing on Cape
Barren Island is still to be undertaken.
2nd Quarter: This process has been delayed due to the current work
load of the Senior Town Planner. A time to re-establish the project is
unknown at this stage. Council may need to consider the
engagement or employment of another Town Planner in the near
term if this project is to be complete.
30/10/2013Development
Services
Officer/EHO
20% 1/07/2013
February 07, 2014 Page 6 of 11
Annexure 25 - Item D4 - February 2014
38
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Direction:
3.6 Provide professional application and inspection approval processes
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 3.6.1 Provide qualified advice and excellent customer service to facilitate applications, advice, approvals and inspection processes.
START DATE
3.6.1.1 Find efficiencies, both
financial and time wise, in the
processing of Development
Applications and planning
administration while
maintaining quality customer
liaison and qualified advice as
required.
Ongoing 1st Quarter: New Development Application process in place. A
major time saving has been noted since its implementation in July.
The majority of the reports are now provided to a briefing standard
and not a full agenda item saving significant time and expense.
Time delays to applicants have been greatly improved by the revised
process.
2nd Quarter: Time and financial efficiencies have been achieved
with the implementation of the revised discretionary application
process. Meander Valley Council have advised that they have
insufficient staff to continue the provision of planning services post
March 2014. Alternatives are being investigated.
30/06/2014Development
Services
Officer/EHO
1/07/2013
3.6.1.2 Standard Operating
Procedures are developed and
implemented to mitigate risk
and to ensure timelines are
met / exceeded and legal non
compliance is removed.
In Progress 1st Quarter: Standard Operating Procedures have been developed
for planning and building administration, levy reporting, and dog
notices.
2nd Quarter: Further Standard Operating Procedures have been
documented. Some are very standard while others take the
appearance of a 'working' document that may continually be
amended when new efficiencies are found.
30/06/2014Development
Services
Officer/EHO
80% 1/07/2013
3.6.1.3 Day to day
administrative activities.
Ongoing 1st Quarter: The majority of Standard Operating Procedures have
been drafted and are implemented as 'live' documents in a Manual.
This will allow for periods of leave or sickness of the Development
Services Co-ordinator to ensure that progression of day-to-day
activities remains.
2nd Quarter: All day to day administrative activities are undertaken
by either the Development Services Coordinator or planning/building
administration assistance at Meander Valley Council . This is
ongoing and working well at this stage.
30/06/2014Development
Services
Officer/EHO
2/09/2013
February 07, 2014 Page 7 of 11
Annexure 25 - Item D4 - February 2014
39
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Focus
Area:
4 Community Safety, Engagement and Enterprise - Through positive Council-Community partnerships, enhance
people’s security, inclusion and well-being.
Strategic
Direction:
4.1 Provide professional environmental and public health services
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.1.1 Provide a program of structured inspection, compliance management, education and immunisation.
START DATE
4.1.1.1 Provide a structured
inspection program for all EHO
related facilities and activities.
Ongoing 1st Quarter: Food inspections ongoing. Most food handlers have
taken advantage of Safe Food Handler training. All food premises
found to be of high standard at this point in time.
2nd Quarter: Food inspections continue to be of a high standard,
although some issues have crept in that are being dealt with.
Inspections for Place of Assembly licensing have been scheduled
via liaison with the Risk Management Officer and Essential Health
and Safety measure inspections of Council buildings is scheduled
between EHO and Works Manager.
30/06/2014Development
Services
Officer/EHO
1/07/2013
4.1.1.2 Business specific EHO
advice and assistance provided
via routine inspection program.
Ongoing 1st Quarter: Food inspections are conducted on an annual basis
with any matters being addressed with the applicants at the time of
inspection and subsequent follow up. Food handlers courses are
ongoing on an as needs basis.
2nd Quarter: Liaison with food handlers and business owners alike
has continued and a good repour has formed. Inspections are
random in nature with each business gaining annual inspections and
time to discuss future options, training and procedures.
30/06/2014Development
Services
Officer/EHO
1/07/2013
February 07, 2014 Page 8 of 11
Annexure 25 - Item D4 - February 2014
40
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Direction:
4.1 Provide professional environmental and public health services
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.1.1 Provide a program of structured inspection, compliance management, education and immunisation.
START DATE
4.1.1.3 Education program
such as the food handlers
course continue in partnership
with the school. Other
programs developed to
mitigate major EHO identified
risks as required.
Ongoing 1st Quarter: The school is very accommodating of holding food
handler courses on their site, however the next one is planned to be
conducted in a food premises and be more tailored to their needs.
Other programs will be developed as need and therefore this action
is ongoing.
2nd Quarter: The current principal remains supporting of the
volunteer and student food handler course being held at the school.
Larger businesses have asked for tailored programs and this has
been accommodated. Other identified public health risks are
identified on an as-needs basis.
30/06/2014Development
Services
Officer/EHO
1/07/2013
4.1.1.4 Immunisation program
implemented and participants
registered.
Ongoing 1st Quarter: This program was delivered in January - February of
this calendar year and Council's Environmental Health Officer (EHO)
liaised closely with the nurse from the Doctor's Surgery to ensure
that the program was correct and concise. An immunisation
workshop, put on by the State Government, was attended to by both
the EHO and Doctors Nurse.
2nd Quarter: The State Immunisation Schedule has been received
for the 2014 year. More support packs and school information have
been provided in this year than in other years. Liaison will
commence with the surgery nurse and the school, as soon as
students return, to ascertain the number of students and the
dates/times of immunisation.
30/06/2014Development
Services
Officer/EHO
1/07/2013
4.1.1.5 EHO to provide advice
to the Health Special
Committee of Council as
required.
Ongoing 1st Quarter: The Special Health Committee of Council see no need
to have the EHO present at their meetings and have agreed to call
on this advice when/as needed.
2nd Quarter: No advice provided during this reporting period.
30/06/2014Development
Services
Officer/EHO
1/07/2013
February 07, 2014 Page 9 of 11
Annexure 25 - Item D4 - February 2014
41
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Direction:
4.1 Provide professional environmental and public health services
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.1.1 Provide a program of structured inspection, compliance management, education and immunisation.
START DATE
4.1.1.6 Seek to integrate
public health and immunisation
programs and goals with the
community health plan when it
is developed and delivered.
Not Started 1st Quarter: Community Health Plan is under development and until
completed this action is on hold.
2nd Quarter: The Community Health Plan is still under development
so work has not started on this action.
30/06/2014Development
Services
Officer/EHO
0% 1/07/2013
4.1.1.7 Support new food
businesses (or food related
product development) within
the Municipality.
Ongoing 1st Quarter: 3 new food businesses came on line in the last period
and the EHO continues to work with new proprietors and community
groups to achieve their 'food' outcomes.
2nd Quarter: The EHO continues to provide support as and when
required.
30/06/2014Development
Services
Officer/EHO
1/07/2013
4.1.1.8 Support School
Kitchen Garden as required.
Ongoing 1st Quarter: No activity on this action during this quarter.
2nd Quarter: Two recent meetings with the Head of School have
reconfirmed Council's Environmental Health Officer's support of the
garden and school programs.
30/06/2014Development
Services
Officer/EHO
1/07/2013
4.1.1.9 Implement a
recreational water sampling
program.Undertake beach
water sampling at major
swimming areas and areas of
stormwater outfall in the
summer period to ensure safe
recreational water use by the
community.
In Progress 1st Quarter: The program will be delivered during the months of
December-March. Recreation beaches to be nominated and
sampling undertaken for the period.
2nd Quarter: December samples have been taken from
Killiecrankie, All Ports Beach, Whitemark Foreshore Beach and
Lady Barron Beach (near the slip and stormwater outfall). All have
shown satisfactory results.
30/06/2014Development
Services
Officer/EHO
50% 1/07/2013
February 07, 2014 Page 10 of 11
Annexure 25 - Item D4 - February 2014
42
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Development Services
Strategic
Direction:
4.4 Facilitate the provision and enhancement of critical health and education facilities and service levels by state and federal
agencies and NGOs
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.4.1 Collaborate with incorporated bodies associated with key facilities and services to retain and enhance scope and level of service,
including implementation of innovative responses
START DATE
4.4.1.1 Support Immunisation
programs.
Ongoing 1st & 2nd Quarter: Supported by EHO. 30/06/2014Development
Services
Officer/EHO
1/07/2013
February 07, 2014 Page 11 of 11
Annexure 25 - Item D4 - February 2014
43
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Focus
Area:
1 Environment and Natural Asset Management - An environment that maintains its diversity, uniqueness and
attractiveness while supporting sustainable production and lifestyle.
Strategic
Direction:
1.2 Design land use and development policies that balance environmental, economic and social outcomes
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.2.2 Apply the strategic objectives and criteria to specific opportunities and proposals and integrate into the marketing strategies
START DATE
1.2.2.1 Renewable Energy
Plan - continue to seek funding
and implementation of plan.
Ongoing 1st Quarter: Australian Renewable Energy Agency (ARENA) have
now reviewed the Expression of Interest put forward by Hydro
Tasmania and have invited Hydro Tasmania to submit a full
Application. The full application preparation will be progressed over
the coming months targeting late 2013, early 2014 for submission
pending state discussions. Discussion with State Treasury has
formally commenced regarding CSO impact.
2nd Quarter: Hydro Tasmania has submitted to Council a
development application for a series of projects and measures to
improve the island's energy systems. It should be noted that the
projects proposed are not in line with the Council endorsed
Renewable Energy Plan. If approval is gained then Hydro will submit
the projects to ARENA for funding.
30/06/2014General Manager 1/07/2013
February 06, 2014 Page 2 of 15
Annexure 25 - Item D4 - February 2014
44
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
1.3 Enhance access to and use of environmental assets to ensure values are recognised
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.3.1 Protect and as required formalise public access to coastal and inland areas
START DATE
1.3.1.2 Partner with other
Government agencies to
improve access and
maintenance of tracks in key
coastal areas.
Completed 1st Quarter: Officers continue to work closely with local Parks and
Wildlife staff to improve access and maintenance of tracks in coastal
areas.
2nd Quarter: The Bluff Track redevelopment is completed.The
Marshall Bay track is complete. Works proposed for this year are
now complete.
30/06/2014General Manager100% 1/07/2013
February 06, 2014 Page 3 of 15
Annexure 25 - Item D4 - February 2014
45
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Focus
Area:
2 Infrastructure - Efficient and reliable infrastructure that supports and protects production, services and lifestyle.
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.3 Airport Master Plan
START DATE
2.1.3.1 Seek the inclusion of
the Airport runway
rebuild/reseal project (as
outlined in the Airport Master
Plan) to be included in State
and Federal Government
Transport Priority Plans to
assist with future funding
submissions.
Completed 1st Quarter: The runway rebuild/reseal project is now included as a
key regional priority of the Northern Councils within the NTD Priority
Projects document. It is also a key project within the State
Governments Northern Integrated Transport Plan. Efforts continue
to seek Federal Government support, the project is shovel ready, is
supported by the Region and the State and as such should align well
to receive Federal support when funds are available.
2nd Quarter: Building upon the projects inclusion in the NTD Priority
Projects list as a project of regional importance, the State
Government has now included it in the Northern Integrated
Transport Plan as a key project of significance. It should be noted
that grant funds at both the State and Federal level are extremely
tight and the likelihood of this project being funded in full in the near
future is unlikely.
30/06/2014General Manager100% 1/07/2013
February 06, 2014 Page 4 of 15
Annexure 25 - Item D4 - February 2014
46
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.3 Airport Master Plan
START DATE
2.1.3.2 Seek government
funding for the Airport runway
rebuild/reseal project as
outlined in the Airport Master
Plan.
In Progress 1st Quarter: To secure funding for a project of this scale Council
must follow an evidence based process of scoping the required
works, outlining the critical nature of the proposal to the ongoing
viability of not just the runway itself but the airline operators, the
community and the island's businesses. With the Airport Master Plan
complete and the runway/pavement assessment finalised, Council
staff have been actively seeking the support of the Region and the
State to list the project as a priority to support. I can confirm that
these efforts have now seen the project listed by the Northern
Regional Councils via Northern Tasmania Development as a key
priority project and it is referenced in the Department of
Infrastructure Energy and Resources "Northern Integrated Transport
Plan". Staff have initiated discussions with the new Federal Member
for Bass about the critical nature of the project to the islands and
efforts in this area will be ongoing over the coming period .
2nd Quarter: Building upon the work outlined in the first progress
update, the General Manager has now met with the new Federal
Member for Bass and discussed the project's importance. Funds are
extremely limited at a Federal level but the project's importance to
the community was well recognised. Further lobbying prior to the
State election is critical in the coming period.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 5 of 15
Annexure 25 - Item D4 - February 2014
47
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.3 Airport Master Plan
START DATE
2.1.3.3 Seek Federal and
State Government funding to
complete the Apron and
Taxiway project at the Airport.
In Progress 1st Quarter: A grant application has been submitted to the Federal
Department of Infrastructure.
2nd Quarter: With the change of Government, the Department has
been unable to provide advice as to the status of these funds at this
time. With time passing by and no notification forthcoming it will no
longer be possible to secure contractors for this sealing season
even if we are informed the grant has been successful in the coming
weeks. The project will not be completed this year but staff are
confident that funding will be forthcoming in the next quarter and
works will then be planned for next year.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 6 of 15
Annexure 25 - Item D4 - February 2014
48
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
2.2 Optimise infrastructure to support existing settlements and enhance sustainable development opportunities and remove
impediments to growth
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.2.1 Identify, research, design and implement key infrastructure projects and programs to meet the economic and environmental needs of
Council and the community.
START DATE
2.2.1.2 Airport business plan is
developed, consulted and
adopted.
In Progress 1st Quarter: The Airport Master Plan and the Draft Airport Business
Plan have been completed. Resonance Consulting has been
engaged to undertake a detailed investigation and analysis of the
following three options to determine business cases:
1. Paid parking
2. Storage sheds
3. 24 hour fuel facility
Once completed, this information will be used to inform the
finalisation of the Airport Business Plan.
2nd Quarter: The Business Plan is under development.
30/06/2014General Manager60% 1/07/2013
2.2.1.3 Undertake required
works to complete the Port
Davies Boat
Ramp.
In Progress 1st Quarter: Marine & Safety Tasmania (MAST) funding has been
secured. The designs have been finalised, the Development
Application approved and the Contractors have been engaged.
Work has now started on the project.
2nd Quarter: Work is now substantially complete with only signage
and some minor gravel works to be undertaken and installed in the
coming month.
01/02/2014General Manager95% 1/07/2013
February 06, 2014 Page 7 of 15
Annexure 25 - Item D4 - February 2014
49
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
2.3 Lobby utility and access providers to meet obligations for infrastructure policy and service provision to provide for relative
equity
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.3.1 Develop base positions, identify key players, lobby and as necessary respond to opportunities and incidents
START DATE
2.3.1.1 Develop, submit and
secure annual shipping
contingency funding via DIER.
Manage the implementation of
projects funded in the
preceding years allocations.
In Progress 1st Quarter: The grant was submitted as per Council resolution and
funding has been secured for the 2012/2013 year. Equipment and
projects from this funding will be purchased in the 2013/2014 year.
The General Manager has made preliminary enquires with TasPorts
and Furneaux Freight as to a suitable ownership model or lease
agreement to support the purchase of the funded equipment.
Discussions are ongoing until such time as this can be resolved.
This will be actioned in the next reporting period.
2nd Quarter: Council has completed the following projects funded
under the Shipping Contingency Fund in conjunction with TasPorts :
demolition of the "super shed" and the purchase of stock races. At
the time of writing quotes are being prepared for the bull and horse
crates and the Shipping Committee Chair is liaising with Furneaux
Freight on their need for Forklifts. No action to date has been taken
on the vessel monitoring system.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 8 of 15
Annexure 25 - Item D4 - February 2014
50
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Focus
Area:
3 Land use, Development and Building - A productive system of land and building development that promotes
investment and activity while protecting people and the environmental characteristics of the Flinders municipal area.
Strategic
Direction:
3.1 Utilise best practice planning principles in conjunction with Flinders Councils Strategic Plan to guide detailed planning policy
and planning tools
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 3.1.1 Apply and refine as necessary the classification structure and planning principles defined in the Flinders Planning Scheme to key areas
while directly engaging with the community to further the consultation commenced with the draft Interim Planning Scheme. This will ensure
planning principles and outcomes reflect community needs and desires and provide timely strategic planning for future economic and
community development.
START DATE
3.1.1.1 Continue the
development and
implementation of the Rural
Living Strategy.
In Progress 1st Quarter: Council staff and consultant planners continue to
develop the strategy in conjunction with a revised Structure Plan.
The plan's finalisation is based upon the availability of the consultant
planner over the coming months. The Minister for Planning recently
advised Council that he has signed revisions to the Regional Land
Use Strategy whereby Flinders now has support to inform zonings
based on "localised strategy". This change is a major achievement
and will allow for the Draft Interim Scheme as consulted with the
community to be enacted, subject to any revisions that the TPC may
make post the formal consultation process. The delivery of a revised
Structure Plan and Rural Living Strategy will be the key localised
strategic documents utilised to inform the Draft Interim Planning
Scheme prior to submission to the Minister.
2nd Quarter: Council Senior Planner has advised that the
implementation of Meander Valley Council's (MVC) new Planning
Scheme has been far more complex and time consuming than
expected. The Officer simply has not had the time to assist Flinders
over the past quarter and hence these critical documents remain
incomplete. Furthermore MVC now may well not have the capacity
to continue to assist Flinders with the complexities they are facing.
This is a critical juncture for Council and the concept of employing a
locally based town planner may well be an option worthy of
consideration if the Rural Living Strategy and Interim Planning
Scheme are to be completed in the near future.
30/06/2014General Manager40% 1/07/2013
February 06, 2014 Page 9 of 15
Annexure 25 - Item D4 - February 2014
51
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Focus
Area:
6 Furneaux Future - A thriving, self reliant community offering opportunities for current and following generations
while maintaining core values and attributes.
Strategic
Direction:
6.1 Implement a dynamic strategic plan and development framework to define our future and guide strategic decisions
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.2 Tourism
START DATE
6.1.2.1 Work collaboratively
with Northern Regional Tourism
Organisation to drive brand
recognition, visitation and
tourism development.
In Progress 1st Quarter: The Tourism Northern Tasmania (TNT)/Council funding
agreement was finalised. A Draft Destination Management Plan is
under development with a specific Flinders approach included.
TNT is working on branding initiatives with local businesses and the
Tourism Association. A partnership based marketing campaign has
been developed between Sharp Airlines, Flinders Island Tourism
Association (FITA), TNT, Tourism Tasmania and Council. A request
for funding is included in the October Council Agenda.
2nd Quarter: TNT has secured Flinders being presented on the new
www.discovertasmania.com website as a stand-alone destination.
There will be a primary link direct from the home page of this
website directing people to flinders plus dedicated pages on Flinders
Island with links. This is a major achievement and satisfies a request
from local operators and Council that has been ongoing now for
many years. TNT also in the reporting period secured a piece on
Flinders in The Guardian newspaper (UK)
http://www.theguardian.com/travel/2014/jan/05/winter-survival-guide-
travel-destinations whereby Flinders was highlighted as a hot spot to
get away from the winter in the UK. TNT continues to develop as an
organisation but have to date delivered far more than expected for
the small investment made by Council annually to support their
efforts.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 10 of 15
Annexure 25 - Item D4 - February 2014
52
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.1 Implement a dynamic strategic plan and development framework to define our future and guide strategic decisions
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.2 Tourism
START DATE
6.1.2.2 Establish and build a
collaborative relationship with
key personnel at Sharp Airlines
to increase visitation, holiday
packages, review passenger
tax to drive returns to both
Council and Sharp Airlines.
Ongoing 1st Quarter: The Sharp Airlines CEO and the General Manager have
regular meetings to discuss areas of interest and strategies to
increase visitation. The passenger tax is an ongoing area of interest
for both parties and differing scenarios are being explored .
2nd Quarter: Council resolved to support a combined marketing
campaign between Sharp Airlines, Flinders Island Tourism
Association (FITA) and Tourism Tasmania. The Spring campaign
has seen increased bookings and increases in visitation to the
partnership group's collective websites. Sharp Airlines has recently
changed flight schedules with growing numbers coming from
Melbourne facilitating further flights being made available. Sharp
Airlines continue to be an active participant in the brand and
marketing working group discussions and meetings.
30/06/2014General Manager 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.3 Investment Attraction
START DATE
6.1.3.1 Provide assistance as
required to any investment
enquiries.
In Progress 1st Quarter: Assistance has been provided to scope the
establishment of an essential oil business on the island. Initial
discussions are very promising with a small scale operation still
proposed to be established on the island in the coming months. The
proponents have requested assistance in leasing a site for a short
term trial. Staff will continue to engage with the proponents and seek
to assist.
2nd Quarter: Assistance has been provided to two primary
producers and a company that is exploring the establishment of a
high value crop on the island.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 11 of 15
Annexure 25 - Item D4 - February 2014
53
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.1 Implement a dynamic strategic plan and development framework to define our future and guide strategic decisions
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.3 Investment Attraction
START DATE
6.1.3.2 Liaise with potential
investors/developers.
In Progress 1st Quarter: Met with several private business proponents in
confidential discussion regarding business development.
2nd Quarter: Provided direct support to a number of potential
investors.
30/06/2014General Manager60% 1/07/2013
February 06, 2014 Page 12 of 15
Annexure 25 - Item D4 - February 2014
54
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.2 Achieve high recognition of a “Flinders” brand to support population growth, product sales, business development and
investment, tourism and lobbying
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.2.1 Support increased brand recognition and communications
START DATE
6.2.1.1 Work with Sharp
Airlines and FITA on cross
promotional activities that will
drive brand recognition and
conversion.
In Progress 1st Quarter: Actively involved in assisting and partnering with
Flinders Island Tourism Association (FITA), Tourism Northern
Tasmania, Sharp Airlines and Tourism Tasmania in relation to a
marketing and promotion campaign which is included in the October
Council Meeting Agenda for funding consideration.
2nd Quarter: Council resolved to support the marketing efforts of the
partnership group and staff have actively engaged with the process
since that decision. The marketing campaign has increased
visitation to websites and conversion numbers provided by Sharp
Airlines post the Spring campaign have been exceptional. Forward
bookings for the summer season also appear to be very strong.
30/06/2014General Manager75% 1/07/2013
6.2.1.2 Develop and manage
the Flinders Island Brand
Working Group with industry
and interested community
members. Prepare a project
brief and seek Council support
for specific brand projects to
deliver a Singular Flinders
Island Brand in 2014/2015.
In Progress 1st Quarter: Initial work on the brand-working group has been
undertaken but activities have been delayed due to the scoping
required for the Australian Small Islands Forum. More work on this
will be forthcoming in the next quarter.
2nd Quarter: The brand working group has now met twice and is
functioning well with some great ideas and discussion being
generated. A key outcome has been the recognition that many of the
partnership groups activities and promotions can be quite easily
aligned to generate better and more cost effective outcomes. A full
review is being undertaken of the spring marketing campaign and
this information will inform a report to Council in the near future. All
initial information would suggest it has been successful.
30/06/2014Communications
Officer
50% 1/07/2013
February 06, 2014 Page 13 of 15
Annexure 25 - Item D4 - February 2014
55
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.4 Encourage catalytic development that is consistent with the strategic objectives and contributes to Council’s Vision
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.4.1 Develop and implement specific projects that will strategically advance economic opportunities for Council and Community
START DATE
6.4.1.1 Review priority projects
with and revise business cases
as required/directed.
Not Started 1st Quarter: No action on this item to date.
2nd Quarter: With the State election approaching in the next quarter
the revision of Council priority projects is an important action.
To date no specific direction has been provided to revise but this
should be an action for the February workshop.
Council has a series of projects that have existing evidence based
assessment/ reports which are already actively used to lobby for
State and Federal support such as the Renewable Energy Plan,
airport taxiway and apron extensions and the airport runway rebuild.
The Airport runway rebuild is included already on the Northern
Regional priority projects list for State and Federal consideration and
is also on the State Government Integrated Transport Plan for the
region. Further reports such as the Community Infrastructure Audit ,
Waste Water Feasibility Study and Waste Management Strategy are
nearing completion and will, if and when adopted, provide the
required evidence base to be considered for State or Federal
funding support.
While the existing priority projects list does include some projects
that have been superseded, this list has been provided to all political
parties and interested politicians to inform policy development in the
past and more recently when requested. Staff continue to actively
lobby for the funding and implementation of the Renewable Energy
Plan, are confident that work undertaken prior to the last Federal
election will see the apron and taxiway funding secured in the near
future with the help of the current Member for Bass and will lobby all
parties to consider funding the rebuild of the runway at the airport
prior to the next State election. This will be combined with projects
already on the State Government agenda such as the Community
Services Hub, maintenance of the Shipping Contingency Funding
and upgrades to the Lady Barron Main Road.
30/06/2014General Manager0% 1/07/2013
February 06, 2014 Page 14 of 15
Annexure 25 - Item D4 - February 2014
56
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.4 Encourage catalytic development that is consistent with the strategic objectives and contributes to Council’s Vision
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.4.1 Develop and implement specific projects that will strategically advance economic opportunities for Council and Community
START DATE
6.4.1.2 Develop formal
partnership with a University for
ongoing activities and research
on Flinders Island.
Not Started 1st & 2nd Quarters: No action on this item to date. 30/06/2014General Manager0% 1/07/2013
6.4.1.3 Work in partnership
with Department of Primary
Industries, Parks, Water and
Environment (DPIPWE) to
deliver the Flinders Island
Enterprise Suitability mapping
project to further inform the
Rural Living Strategy.
Completed 1st Quarter: Agreement has been reached with the DPIPWE and the
Enterprise Suitability Mapping Project will begin in early November
2013.
2nd Quarter: Council staff assisted DPIPWE in delivering the first
stage of the project in early December 2013. All temperature and
data loggers are now in place. DPIPWE staff will now collect data
over the 12 month assessment period. No action will be required on
this item by Council until December 2014 and Council's involvement
for this financial year is now complete.
30/06/2014General Manager100% 1/07/2013
6.4.1.4 Assist the Flinders Trail
committee in further
developing the project and
seeking grant funding for its
implementation.
In Progress 1st Quarter: The T-QUAL Grant for the Flinders Trail was
unsuccessful. Options for other funding will be explored with the
Committee.
2nd Quarter: Staff met with the Committee this quarter but no
agreed direction came from the meeting.
30/06/2014Communications
Officer
75% 1/07/2013
February 06, 2014 Page 15 of 15
Annexure 25 - Item D4 - February 2014
57
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Focus
Area:
1 Environment and Natural Asset Management - An environment that maintains its diversity, uniqueness and
attractiveness while supporting sustainable production and lifestyle.
Strategic
Direction:
1.2 Design land use and development policies that balance environmental, economic and social outcomes
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.2.2 Apply the strategic objectives and criteria to specific opportunities and proposals and integrate into the marketing strategies
START DATE
1.2.2.1 Renewable Energy
Plan - continue to seek funding
and implementation of plan.
Ongoing 1st Quarter: Australian Renewable Energy Agency (ARENA) have
now reviewed the Expression of Interest put forward by Hydro
Tasmania and have invited Hydro Tasmania to submit a full
Application. The full application preparation will be progressed over
the coming months targeting late 2013, early 2014 for submission
pending state discussions. Discussion with State Treasury has
formally commenced regarding CSO impact.
2nd Quarter: Hydro Tasmania has submitted to Council a
development application for a series of projects and measures to
improve the island's energy systems. It should be noted that the
projects proposed are not in line with the Council endorsed
Renewable Energy Plan. If approval is gained then Hydro will submit
the projects to ARENA for funding.
30/06/2014General Manager 1/07/2013
February 06, 2014 Page 2 of 15
Annexure 25 - Item D4 - February 2014
58
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
1.3 Enhance access to and use of environmental assets to ensure values are recognised
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.3.1 Protect and as required formalise public access to coastal and inland areas
START DATE
1.3.1.2 Partner with other
Government agencies to
improve access and
maintenance of tracks in key
coastal areas.
Completed 1st Quarter: Officers continue to work closely with local Parks and
Wildlife staff to improve access and maintenance of tracks in coastal
areas.
2nd Quarter: The Bluff Track redevelopment is completed.The
Marshall Bay track is complete. Works proposed for this year are
now complete.
30/06/2014General Manager100% 1/07/2013
February 06, 2014 Page 3 of 15
Annexure 25 - Item D4 - February 2014
59
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Focus
Area:
2 Infrastructure - Efficient and reliable infrastructure that supports and protects production, services and lifestyle.
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.3 Airport Master Plan
START DATE
2.1.3.1 Seek the inclusion of
the Airport runway
rebuild/reseal project (as
outlined in the Airport Master
Plan) to be included in State
and Federal Government
Transport Priority Plans to
assist with future funding
submissions.
Completed 1st Quarter: The runway rebuild/reseal project is now included as a
key regional priority of the Northern Councils within the NTD Priority
Projects document. It is also a key project within the State
Governments Northern Integrated Transport Plan. Efforts continue
to seek Federal Government support, the project is shovel ready, is
supported by the Region and the State and as such should align well
to receive Federal support when funds are available.
2nd Quarter: Building upon the projects inclusion in the NTD Priority
Projects list as a project of regional importance, the State
Government has now included it in the Northern Integrated
Transport Plan as a key project of significance. It should be noted
that grant funds at both the State and Federal level are extremely
tight and the likelihood of this project being funded in full in the near
future is unlikely.
30/06/2014General Manager100% 1/07/2013
February 06, 2014 Page 4 of 15
Annexure 25 - Item D4 - February 2014
60
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.3 Airport Master Plan
START DATE
2.1.3.2 Seek government
funding for the Airport runway
rebuild/reseal project as
outlined in the Airport Master
Plan.
In Progress 1st Quarter: To secure funding for a project of this scale Council
must follow an evidence based process of scoping the required
works, outlining the critical nature of the proposal to the ongoing
viability of not just the runway itself but the airline operators, the
community and the island's businesses. With the Airport Master Plan
complete and the runway/pavement assessment finalised, Council
staff have been actively seeking the support of the Region and the
State to list the project as a priority to support. I can confirm that
these efforts have now seen the project listed by the Northern
Regional Councils via Northern Tasmania Development as a key
priority project and it is referenced in the Department of
Infrastructure Energy and Resources "Northern Integrated Transport
Plan". Staff have initiated discussions with the new Federal Member
for Bass about the critical nature of the project to the islands and
efforts in this area will be ongoing over the coming period .
2nd Quarter: Building upon the work outlined in the first progress
update, the General Manager has now met with the new Federal
Member for Bass and discussed the project's importance. Funds are
extremely limited at a Federal level but the project's importance to
the community was well recognised. Further lobbying prior to the
State election is critical in the coming period.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 5 of 15
Annexure 25 - Item D4 - February 2014
61
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
2.1 Identify infrastructure objectives, standards for assets and develop a viable, asset lifecycle management and operational
model
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.1.3 Airport Master Plan
START DATE
2.1.3.3 Seek Federal and
State Government funding to
complete the Apron and
Taxiway project at the Airport.
In Progress 1st Quarter: A grant application has been submitted to the Federal
Department of Infrastructure.
2nd Quarter: With the change of Government, the Department has
been unable to provide advice as to the status of these funds at this
time. With time passing by and no notification forthcoming it will no
longer be possible to secure contractors for this sealing season
even if we are informed the grant has been successful in the coming
weeks. The project will not be completed this year but staff are
confident that funding will be forthcoming in the next quarter and
works will then be planned for next year.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 6 of 15
Annexure 25 - Item D4 - February 2014
62
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
2.2 Optimise infrastructure to support existing settlements and enhance sustainable development opportunities and remove
impediments to growth
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.2.1 Identify, research, design and implement key infrastructure projects and programs to meet the economic and environmental needs of
Council and the community.
START DATE
2.2.1.2 Airport business plan is
developed, consulted and
adopted.
In Progress 1st Quarter: The Airport Master Plan and the Draft Airport Business
Plan have been completed. Resonance Consulting has been
engaged to undertake a detailed investigation and analysis of the
following three options to determine business cases:
1. Paid parking
2. Storage sheds
3. 24 hour fuel facility
Once completed, this information will be used to inform the
finalisation of the Airport Business Plan.
2nd Quarter: The Business Plan is under development.
30/06/2014General Manager60% 1/07/2013
2.2.1.3 Undertake required
works to complete the Port
Davies Boat
Ramp.
In Progress 1st Quarter: Marine & Safety Tasmania (MAST) funding has been
secured. The designs have been finalised, the Development
Application approved and the Contractors have been engaged.
Work has now started on the project.
2nd Quarter: Work is now substantially complete with only signage
and some minor gravel works to be undertaken and installed in the
coming month.
01/02/2014General Manager95% 1/07/2013
February 06, 2014 Page 7 of 15
Annexure 25 - Item D4 - February 2014
63
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
2.3 Lobby utility and access providers to meet obligations for infrastructure policy and service provision to provide for relative
equity
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 2.3.1 Develop base positions, identify key players, lobby and as necessary respond to opportunities and incidents
START DATE
2.3.1.1 Develop, submit and
secure annual shipping
contingency funding via DIER.
Manage the implementation of
projects funded in the
preceding years allocations.
In Progress 1st Quarter: The grant was submitted as per Council resolution and
funding has been secured for the 2012/2013 year. Equipment and
projects from this funding will be purchased in the 2013/2014 year.
The General Manager has made preliminary enquires with TasPorts
and Furneaux Freight as to a suitable ownership model or lease
agreement to support the purchase of the funded equipment.
Discussions are ongoing until such time as this can be resolved.
This will be actioned in the next reporting period.
2nd Quarter: Council has completed the following projects funded
under the Shipping Contingency Fund in conjunction with TasPorts :
demolition of the "super shed" and the purchase of stock races. At
the time of writing quotes are being prepared for the bull and horse
crates and the Shipping Committee Chair is liaising with Furneaux
Freight on their need for Forklifts. No action to date has been taken
on the vessel monitoring system.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 8 of 15
Annexure 25 - Item D4 - February 2014
64
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Focus
Area:
3 Land use, Development and Building - A productive system of land and building development that promotes
investment and activity while protecting people and the environmental characteristics of the Flinders municipal area.
Strategic
Direction:
3.1 Utilise best practice planning principles in conjunction with Flinders Councils Strategic Plan to guide detailed planning policy
and planning tools
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 3.1.1 Apply and refine as necessary the classification structure and planning principles defined in the Flinders Planning Scheme to key areas
while directly engaging with the community to further the consultation commenced with the draft Interim Planning Scheme. This will ensure
planning principles and outcomes reflect community needs and desires and provide timely strategic planning for future economic and
community development.
START DATE
3.1.1.1 Continue the
development and
implementation of the Rural
Living Strategy.
In Progress 1st Quarter: Council staff and consultant planners continue to
develop the strategy in conjunction with a revised Structure Plan.
The plan's finalisation is based upon the availability of the consultant
planner over the coming months. The Minister for Planning recently
advised Council that he has signed revisions to the Regional Land
Use Strategy whereby Flinders now has support to inform zonings
based on "localised strategy". This change is a major achievement
and will allow for the Draft Interim Scheme as consulted with the
community to be enacted, subject to any revisions that the TPC may
make post the formal consultation process. The delivery of a revised
Structure Plan and Rural Living Strategy will be the key localised
strategic documents utilised to inform the Draft Interim Planning
Scheme prior to submission to the Minister.
2nd Quarter: Council Senior Planner has advised that the
implementation of Meander Valley Council's (MVC) new Planning
Scheme has been far more complex and time consuming than
expected. The Officer simply has not had the time to assist Flinders
over the past quarter and hence these critical documents remain
incomplete. Furthermore MVC now may well not have the capacity
to continue to assist Flinders with the complexities they are facing.
This is a critical juncture for Council and the concept of employing a
locally based town planner may well be an option worthy of
consideration if the Rural Living Strategy and Interim Planning
Scheme are to be completed in the near future.
30/06/2014General Manager40% 1/07/2013
February 06, 2014 Page 9 of 15
Annexure 25 - Item D4 - February 2014
65
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Focus
Area:
6 Furneaux Future - A thriving, self reliant community offering opportunities for current and following generations
while maintaining core values and attributes.
Strategic
Direction:
6.1 Implement a dynamic strategic plan and development framework to define our future and guide strategic decisions
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.2 Tourism
START DATE
6.1.2.1 Work collaboratively
with Northern Regional Tourism
Organisation to drive brand
recognition, visitation and
tourism development.
In Progress 1st Quarter: The Tourism Northern Tasmania (TNT)/Council funding
agreement was finalised. A Draft Destination Management Plan is
under development with a specific Flinders approach included.
TNT is working on branding initiatives with local businesses and the
Tourism Association. A partnership based marketing campaign has
been developed between Sharp Airlines, Flinders Island Tourism
Association (FITA), TNT, Tourism Tasmania and Council. A request
for funding is included in the October Council Agenda.
2nd Quarter: TNT has secured Flinders being presented on the new
www.discovertasmania.com website as a stand-alone destination.
There will be a primary link direct from the home page of this
website directing people to flinders plus dedicated pages on Flinders
Island with links. This is a major achievement and satisfies a request
from local operators and Council that has been ongoing now for
many years. TNT also in the reporting period secured a piece on
Flinders in The Guardian newspaper (UK)
http://www.theguardian.com/travel/2014/jan/05/winter-survival-guide-
travel-destinations whereby Flinders was highlighted as a hot spot to
get away from the winter in the UK. TNT continues to develop as an
organisation but have to date delivered far more than expected for
the small investment made by Council annually to support their
efforts.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 10 of 15
Annexure 25 - Item D4 - February 2014
66
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.1 Implement a dynamic strategic plan and development framework to define our future and guide strategic decisions
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.2 Tourism
START DATE
6.1.2.2 Establish and build a
collaborative relationship with
key personnel at Sharp Airlines
to increase visitation, holiday
packages, review passenger
tax to drive returns to both
Council and Sharp Airlines.
Ongoing 1st Quarter: The Sharp Airlines CEO and the General Manager have
regular meetings to discuss areas of interest and strategies to
increase visitation. The passenger tax is an ongoing area of interest
for both parties and differing scenarios are being explored .
2nd Quarter: Council resolved to support a combined marketing
campaign between Sharp Airlines, Flinders Island Tourism
Association (FITA) and Tourism Tasmania. The Spring campaign
has seen increased bookings and increases in visitation to the
partnership group's collective websites. Sharp Airlines has recently
changed flight schedules with growing numbers coming from
Melbourne facilitating further flights being made available. Sharp
Airlines continue to be an active participant in the brand and
marketing working group discussions and meetings.
30/06/2014General Manager 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.3 Investment Attraction
START DATE
6.1.3.1 Provide assistance as
required to any investment
enquiries.
In Progress 1st Quarter: Assistance has been provided to scope the
establishment of an essential oil business on the island. Initial
discussions are very promising with a small scale operation still
proposed to be established on the island in the coming months. The
proponents have requested assistance in leasing a site for a short
term trial. Staff will continue to engage with the proponents and seek
to assist.
2nd Quarter: Assistance has been provided to two primary
producers and a company that is exploring the establishment of a
high value crop on the island.
30/06/2014General Manager50% 1/07/2013
February 06, 2014 Page 11 of 15
Annexure 25 - Item D4 - February 2014
67
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.1 Implement a dynamic strategic plan and development framework to define our future and guide strategic decisions
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.3 Investment Attraction
START DATE
6.1.3.2 Liaise with potential
investors/developers.
In Progress 1st Quarter: Met with several private business proponents in
confidential discussion regarding business development.
2nd Quarter: Provided direct support to a number of potential
investors.
30/06/2014General Manager60% 1/07/2013
February 06, 2014 Page 12 of 15
Annexure 25 - Item D4 - February 2014
68
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.2 Achieve high recognition of a “Flinders” brand to support population growth, product sales, business development and
investment, tourism and lobbying
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.2.1 Support increased brand recognition and communications
START DATE
6.2.1.1 Work with Sharp
Airlines and FITA on cross
promotional activities that will
drive brand recognition and
conversion.
In Progress 1st Quarter: Actively involved in assisting and partnering with
Flinders Island Tourism Association (FITA), Tourism Northern
Tasmania, Sharp Airlines and Tourism Tasmania in relation to a
marketing and promotion campaign which is included in the October
Council Meeting Agenda for funding consideration.
2nd Quarter: Council resolved to support the marketing efforts of the
partnership group and staff have actively engaged with the process
since that decision. The marketing campaign has increased
visitation to websites and conversion numbers provided by Sharp
Airlines post the Spring campaign have been exceptional. Forward
bookings for the summer season also appear to be very strong.
30/06/2014General Manager75% 1/07/2013
6.2.1.2 Develop and manage
the Flinders Island Brand
Working Group with industry
and interested community
members. Prepare a project
brief and seek Council support
for specific brand projects to
deliver a Singular Flinders
Island Brand in 2014/2015.
In Progress 1st Quarter: Initial work on the brand-working group has been
undertaken but activities have been delayed due to the scoping
required for the Australian Small Islands Forum. More work on this
will be forthcoming in the next quarter.
2nd Quarter: The brand working group has now met twice and is
functioning well with some great ideas and discussion being
generated. A key outcome has been the recognition that many of the
partnership groups activities and promotions can be quite easily
aligned to generate better and more cost effective outcomes. A full
review is being undertaken of the spring marketing campaign and
this information will inform a report to Council in the near future. All
initial information would suggest it has been successful.
30/06/2014Communications
Officer
50% 1/07/2013
February 06, 2014 Page 13 of 15
Annexure 25 - Item D4 - February 2014
69
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.4 Encourage catalytic development that is consistent with the strategic objectives and contributes to Council’s Vision
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.4.1 Develop and implement specific projects that will strategically advance economic opportunities for Council and Community
START DATE
6.4.1.1 Review priority projects
with and revise business cases
as required/directed.
Not Started 1st Quarter: No action on this item to date.
2nd Quarter: With the State election approaching in the next quarter
the revision of Council priority projects is an important action.
To date no specific direction has been provided to revise but this
should be an action for the February workshop.
Council has a series of projects that have existing evidence based
assessment/ reports which are already actively used to lobby for
State and Federal support such as the Renewable Energy Plan,
airport taxiway and apron extensions and the airport runway rebuild.
The Airport runway rebuild is included already on the Northern
Regional priority projects list for State and Federal consideration and
is also on the State Government Integrated Transport Plan for the
region. Further reports such as the Community Infrastructure Audit ,
Waste Water Feasibility Study and Waste Management Strategy are
nearing completion and will, if and when adopted, provide the
required evidence base to be considered for State or Federal
funding support.
While the existing priority projects list does include some projects
that have been superseded, this list has been provided to all political
parties and interested politicians to inform policy development in the
past and more recently when requested. Staff continue to actively
lobby for the funding and implementation of the Renewable Energy
Plan, are confident that work undertaken prior to the last Federal
election will see the apron and taxiway funding secured in the near
future with the help of the current Member for Bass and will lobby all
parties to consider funding the rebuild of the runway at the airport
prior to the next State election. This will be combined with projects
already on the State Government agenda such as the Community
Services Hub, maintenance of the Shipping Contingency Funding
and upgrades to the Lady Barron Main Road.
30/06/2014General Manager0% 1/07/2013
February 06, 2014 Page 14 of 15
Annexure 25 - Item D4 - February 2014
70
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Economic Development
Strategic
Direction:
6.4 Encourage catalytic development that is consistent with the strategic objectives and contributes to Council’s Vision
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.4.1 Develop and implement specific projects that will strategically advance economic opportunities for Council and Community
START DATE
6.4.1.2 Develop formal
partnership with a University for
ongoing activities and research
on Flinders Island.
Not Started 1st & 2nd Quarters: No action on this item to date. 30/06/2014General Manager0% 1/07/2013
6.4.1.3 Work in partnership
with Department of Primary
Industries, Parks, Water and
Environment (DPIPWE) to
deliver the Flinders Island
Enterprise Suitability mapping
project to further inform the
Rural Living Strategy.
Completed 1st Quarter: Agreement has been reached with the DPIPWE and the
Enterprise Suitability Mapping Project will begin in early November
2013.
2nd Quarter: Council staff assisted DPIPWE in delivering the first
stage of the project in early December 2013. All temperature and
data loggers are now in place. DPIPWE staff will now collect data
over the 12 month assessment period. No action will be required on
this item by Council until December 2014 and Council's involvement
for this financial year is now complete.
30/06/2014General Manager100% 1/07/2013
6.4.1.4 Assist the Flinders Trail
committee in further
developing the project and
seeking grant funding for its
implementation.
In Progress 1st Quarter: The T-QUAL Grant for the Flinders Trail was
unsuccessful. Options for other funding will be explored with the
Committee.
2nd Quarter: Staff met with the Committee this quarter but no
agreed direction came from the meeting.
30/06/2014Communications
Officer
75% 1/07/2013
February 06, 2014 Page 15 of 15
Annexure 25 - Item D4 - February 2014
71
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Focus
Area:
4 Community Safety, Engagement and Enterprise - Through positive Council-Community partnerships, enhance
people’s security, inclusion and well-being.
Strategic
Direction:
4.2 Support effective and timely incident & emergency management planning and response
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.2.1 In conjunction with other emergency response groups, have appropriate plans and resources in place to mitigate and respond to
identified risks and incidents
START DATE
4.2.1.1 Provide administrative
support and coordination in the
event of an emergency.
Ongoing 1st & 2nd Quarters: Fortunately there have been no emergencies to
date.
30/06/2014Executive Assistant
to General
Manager
1/07/2013
February 07, 2014 Page 2 of 17
Annexure 25 - Item D4 - February 2014
72
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
4.3 Maintain and develop productive, constructive relationships with the community and organisations involved in delivery of
strategic services and activities in the islands
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 4.3.1 Engage with, as necessary support and integrate into Flinders Council plans key community based service providers.
START DATE
4.3.1.4 Manage contributions
to the Island Employment
section of the Council website.
Not Started 1st & 2nd Quarters: Work associated with this action will not
commence until the new Council website goes live in early 2014.
30/06/2014Executive Officer0% 1/07/2013
4.3.1.5 Coordinate advertising
and administration of the
Citizens Awards program.
Completed 1st Quarter: The Citizens Award was advertised in Island News with
a closing date for applications 30 August. Three nominations were
received and these were considered at the September Council
Meeting. Successful nominees will be awarded at the Flinders Show
on 18 October.
2nd Quarter: Citizens Awards were presented by the Mayor at the
Flinders Show to successful nominees - Kim Murphy & Colleen
Patterson - in recognition of their outstanding service to the
community. A Special Award was also presented to Kathleen
Ives-Heap & David Heap for outstanding services to the
community’s health and well- being. The awards were promoted on
Council's website.
30/10/2013Executive Officer100% 1/07/2013
February 07, 2014 Page 3 of 17
Annexure 25 - Item D4 - February 2014
73
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Focus
Area:
5 Corporate Governance and Intergovernmental Relations - decisions are professionally and transparently made,
communicated and implemented to achieve defined outcomes in the interest of the community
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.1 Design and implement an integrated governance; strategic and operational planning & service delivery system
START DATE
5.1.1.2 Develop and
implement an organisational
business planning process.
Completed An organisational business planning process was adopted by
Council at the July 2013 Ordinary Meeting. The details associated
are now being implemented across the organisation and will provide
a platform to ensure key dates and outputs are met by the relevant
staff members and Councillors.
30/06/2014General Manager100% 1/07/2013
5.1.1.3 Support Council
Managers in the preparation
and distribution of governance
reports including plans,
policies, reports and other
governance related
publications.
Ongoing 1st Quarter: Provision of assistance and support of Council
Managers to prepare and distribute Governance reports is ongoing,
occurring in a timely fashion as and when required.
2nd Quarter: Assistance continues to be provided in a timely fashion
as and when required.
30/06/2014Executive Officer 1/07/2013
5.1.1.6 Review and revise
Council’s Policy Manual.
Ongoing 1st Quarter: Policies from the Council Policy Manual are reviewed by
Councillors on an ongoing basis.
2nd Quarter: The Private Tenancy Policy was rescinded during this
quarter and the Citizen of the Year Award Policy was adopted.
30/06/2014Executive Officer 1/07/2013
February 07, 2014 Page 4 of 17
Annexure 25 - Item D4 - February 2014
74
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.1 Design and implement an integrated governance; strategic and operational planning & service delivery system
START DATE
5.1.1.7 Review current records
management practices and
develop new procedures that
are compliant with legislative
requirements. Oversee
implementation of
recommendations.
In Progress 1st Quarter: Before commencing the overall review of current
records management practices within Council, the Image library was
identified as being of high priority. Consequently efforts were
concentrated on establishing the Image Library during this quarter.
The overall review will commence in the second quarter.
2nd Quarter: Work has continued on establishing the Image Library
during this quarter. A review of current records management
practices has commenced and records management training for
Council Office Staff and Managers has been organised for February
2014.
30/06/2014Executive Officer25% 1/07/2013
5.1.1.8 Complete an audit of
all Information Technology
systems and accounts. Collate
findings and provide
recommendations for improved
service standards and cost
minimisation.
In Progress 1st Quarter: The audit has been completed and upgrades on all
systems over three years have been rolled out. Currently issues are
being solved with the Airport networks and setup.
2nd Quarter: A full IT report was delivered to Management in
December 2013 and recommendations for the next budget period.
New and improved systems are hoping to be rolled out in the next
quarter.
30/06/2014Communications
Officer
70% 1/07/2013
5.1.1.9 Develop and
implement communication and
social media procedures and
policies to ensure accurate,
effective and compliant
communications to key
stakeholders.
In Progress 1st Quarter: Development of a social media strategy has
commenced and already internal processes are taking place to
ensure the accuracy of disseminated council posts.
2nd Quarter: The communication and social media procedures will
be rolled out with the Flinders Council Communication Strategy.
30/06/2014Communications
Officer
15% 1/07/2013
February 07, 2014 Page 5 of 17
Annexure 25 - Item D4 - February 2014
75
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.1 Design and implement an integrated governance; strategic and operational planning & service delivery system
START DATE
5.1.1.10 Develop and
implement integrated internal
communication tools. This to
include brand guidelines,
e-newsletter, email signatures,
reporting templates, publication
templates, signage etc.
Completed 1st Quarter: The brand guidelines and new templates have been
rolled out to all internal staff.
30/06/2014Communications
Officer
100% 1/07/2013
5.1.1.11 In conjunction with the
Sub Regional Alliance and
DPAC, seek to develop a
legislative compliance audit.
In Progress 1st Quarter: This item was originally put forward by the Sub
Regional Alliance to the Local Government Division of the
Department of Premier and Cabinet (DPAC) in June of this year.
Since this time the Local Government Association of Tasmania and
the Sub Regional Alliance have been working with DPAC to develop
the mechanism to deliver either annual audits or a checklist for each
Council to internally audit against. Consideration is now also being
given to a "portal" where all legislative changes/revisions and new
legislation applicable to local government can be updated and
disseminated out to the sector to ensure the sector is aware of
responsibilities and implications.
2nd Quarter: The project is nearing completion.
30/06/2014General Manager80% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.2 Design and implement a continued professional development & productivity Improvement Program
START DATE
5.1.2.1 Finalise Enterprise
Agreement.
Completed 2nd Quarter: The new Enterprise Agreement became operational on
the 1st October 2013 and is now complete. All staff have new
position descriptions and contracts. Individual Flexibility Agreements
have been revised and agreed. A suite of efficiencies in payroll and
leave management have been implemented. Fair Work Australia
have the required documentation and compliance with process has
been confirmed.
30/06/2014General Manager100% 1/07/2013
February 07, 2014 Page 6 of 17
Annexure 25 - Item D4 - February 2014
76
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.2 Design and implement a continued professional development & productivity Improvement Program
START DATE
5.1.2.2 Revise the employee
induction process to add
greater depth and detail around
risk, Council processes and
projects, organisational
structure and relationships to
Councillors to engender
knowledge and organisational
pride.
In Progress 1st Quarter: The existing Employee Induction Process has been
reviewed and a revised model is under development.
2nd Quarter: The induction process is being developed but has been
delayed due to the requirement of the General Manager to actively
support the Corporate Services functions of Council over the past 4
months.
30/06/2014General Manager50% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.4 Provide best practice management and administrative support to Council decision making, implementation and evaluation
START DATE
5.1.4.1 All agenda papers and
reports provided to elected
members in compliance with
legislated time fames.
Ongoing 1st & 2nd Quarters: All agendas, minutes and reports have been
prepared and distributed within legislated time frames.
30/06/2014Executive Officer 1/07/2013
5.1.4.2 Provide secretarial and
administrative support to
Council and its Special
Committees including
coordinating the preparation
and distribution of agendas and
minutes and acting as minute
secretary.
Ongoing 1st & 2nd Quarters: Provision of secretarial and administrative
support to Council and its Special Committees is ongoing, occurring
in a timely fashion as and when required.
30/06/2014Executive Assistant
to General
Manager
1/07/2013
5.1.4.3 Provide General
Manager, Corporate Services
Manager, and Elected
Members with secretarial,
administrative and research
support relating to the civic and
administrative functions for
Council.
Ongoing 1st & 2nd Quarters: Provision of secretarial, administrative and
research support to Council Managers and Elected Members is
ongoing, occurring in a timely fashion as and when required.
30/06/2014Executive Assistant
to General
Manager
1/07/2013
February 07, 2014 Page 7 of 17
Annexure 25 - Item D4 - February 2014
77
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.4 Provide best practice management and administrative support to Council decision making, implementation and evaluation
START DATE
5.1.4.4 Update Council
website with current Council
publications, meeting agendas
and minutes and council news.
Ongoing 1st Quarter: Council website is updated with current Council
publications, meeting agendas and minutes and council news in a
timely manner, as and when required.
2nd Quarter: Council website continues to be updated as and when
required. A considerable amount of new content has also been
created to populate Council's new website, due to go live early 2014.
30/06/2014Executive Assistant
to General
Manager
1/07/2013
5.1.4.5 Assist Councillors to
regularly submit reports on
their activities to Council
meetings and to Council’s
social media platforms.
Not Started 1st & 2nd Quarter: Work will not commence on this action until the
new Council website goes live in early 2014.
30/06/2014Executive Assistant
to General
Manager
0% 1/07/2013
5.1.4.6 Develop a revised and
comprehensive post-election
induction program for
Councillors – roles and
responsibilities, organizational
structure, annual plans and
departmental presentations,
governance, communications,
Council meetings (Agenda and
Notices of Motion) and Code of
Conduct.
Not Started 1st Quarter: Work will not commence on this action until the third
quarter.
2nd Quarter: The Sub-Regional Alliance has engaged consultant
Excellent Outcomes to develop a program for Councillor Induction
and ongoing development. Support for this project will be provided to
the consultant as and when required.
30/06/2014Executive Officer0% 1/07/2013
February 07, 2014 Page 8 of 17
Annexure 25 - Item D4 - February 2014
78
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.1 Support the capacity and productivity of our organisation and a culture of professionalism, compliance, innovation and
service
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.1.4 Provide best practice management and administrative support to Council decision making, implementation and evaluation
START DATE
5.1.4.7 Research, plan and
prepare for development of a
new/updated strategic plan and
4 year Council Business Plan
post the 2014 “all in all out”
election. This is a critical
process to mitigate risk
associated with the State
electoral reform process and
will provide Council with an
opportunity to engage the
community early post the
election process and develop a
new long term strategic and
operational plan.
Not Started 1st & 2nd Quarters: Work will not commence on this action until the
third quarter.
30/06/2014General Manager0% 1/07/2013
5.1.4.8 Provide on call
Information Technology setup
and training/support for
Councillors and staff.
Ongoing 1st Quarter: Significant work in this area has been completed and
this task will be ongoing.
2nd Quarter: There has been ongoing support for all Councillors and
staff in the second quarter. The Airport's computer systems and
coverage have been dramatically improved, increasing their
productivity.
30/06/2014Communications
Officer
1/07/2013
February 07, 2014 Page 9 of 17
Annexure 25 - Item D4 - February 2014
79
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.2 Develop and maintain an influential network of external stakeholders who understand the needs and direction of Flinders
Council and are supportive
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.2.1 Identify key external stakeholders and decision makers and actively introduce Flinders opportunities, issues and proposals to them in a
timely and professional manner
START DATE
5.2.1.1 Assist with the
implementation of Council’s
Communication Strategy within
Council and the community.
In Progress 1st Quarter: Assisted the Communications Consultant to
communicate Council's Annual Plan to the community and
stakeholders.
2nd Quarter: Continued working on this project with the relevant
staff.
30/06/2014Executive Assistant
to General
Manager
25% 1/07/2013
5.2.1.2 Proof all
communications related
content including web content,
communications, social media
procedures and new resident’s
kit.
Ongoing 1st & 2nd Quarter: Communications related content is proofed in a
timely manner as and when required.
30/06/2014Executive Officer 1/07/2013
5.2.1.3 Source good news
stories about Council activities
and promote locally, regionally
and nationally.
Ongoing 1st Quarter: Good news stories about Council activities are
forwarded to the Communication Consultant for promotion as and
when they are sourced.
2nd Quarter: Council's Annual Report was promoted via Council's
website and Facebook page.
30/06/2014Executive Assistant
to General
Manager
1/07/2013
February 07, 2014 Page 10 of 17
Annexure 25 - Item D4 - February 2014
80
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.3 Actively participate in local government, industry and regional organisations
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.3.1 Actively participate in key strategic organisations, groups and alliances that provide value for the Flinders community and Council.
START DATE
5.3.1.1 Actively engage with
Northern Tasmania
Development.
In Progress 1st Quarter: Northern Tasmania Development (NTD) continue to
actively serve Council through a range of projects including:
- Planning reform process
- Northern Integrated Transport Plan
- Freight review
- Priority Projects development (Airport)
2nd Quarter: Council continues to be well served on the list of
projects outlined in the 1st quarter.
30/06/2014General Manager50% 1/07/2013
5.3.1.2 Actively engage with
the Sub Regional Alliance
Group.
In Progress 1st Quarter: The Sub Regional Alliance is functioning very well with
key outputs involving Risk Management, the Corporate Business
Planning process and Legislative Audit having now been delivered
across the partner organisations. November will see the Sub
Regional General Managers visit Flinders for the next meeting.
2nd Quarter: Flinders hosted the Sub Regional Alliance members in
November where the quarterly meeting was followed by a tour of the
island, Airport and Council assets. The Alliance has been active in
the areas of Risk Management, Councillor Training and Induction,
Legislative Audits and most recently in discussions around shared
service provision.
30/06/2014General Manager50% 1/07/2013
February 07, 2014 Page 11 of 17
Annexure 25 - Item D4 - February 2014
81
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.3 Actively participate in local government, industry and regional organisations
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.3.1 Actively participate in key strategic organisations, groups and alliances that provide value for the Flinders community and Council.
START DATE
5.3.1.3 Actively engage with
the Local Government
Association of Tasmania.
In Progress 1st Quarter: During the reporting period the Local Government
Association of Tasmania (LGAT) has actively sought input into the
following areas/projects:
- Code of Conduct Review
- Dog Control Act
- Long term Financial and Asset Management Planning
- General Manager's Roll
- Handrails in public toilets and buildings
- Review of Liquor Licensing Act
- Cat Management Legislation
- Changes to Private Certification - Permitted Use or Development
- Optional Conduct of Annual General Meetings
- Draft Audit Panel Orders
- Award Modernisation
- Role of Local Government
- Constitutional Recognition
2nd Quarter: Council provided a submission on the Draft Ministerial
Orders proposed under the amendments to the Local Government
Act 1993. Staff also hosted Dr Ketrena Stephenson on the island as
part of the Sub Regional Alliance visit.
30/06/2014General Manager50% 1/07/2013
5.3.1.4 Attend all Office of the
Energy Regulator Customer
Consultative Committee
meetings.
In Progress 1st Quarter: The General Manager continues to be actively engaged
in this area. During the reporting period projects of interest have
included competitive neutrality of State Government and Local
Government enterprises, reform of the energy sector in Tasmania
and pricing principles and service standards for TasWater .
2nd Quarter: Reform of the energy sector and TasWater continue to
be key topics.
30/06/2014General Manager50% 1/07/2013
February 07, 2014 Page 12 of 17
Annexure 25 - Item D4 - February 2014
82
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.3 Actively participate in local government, industry and regional organisations
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.3.1 Actively participate in key strategic organisations, groups and alliances that provide value for the Flinders community and Council.
START DATE
5.3.1.5 Liaise regularly with
the Aboriginal Land Council
Tasmania (ALCT), Flinders
Island Aboriginal Association
(FIAA) and Cape Barren Island
Aboriginal Association
(CBIAA).
In Progress 1st Quarter: Regular discussions have taken place with ALCT in
relation to Wybalena, waste management on Cape Barren Island
and the draft Interim Planning Scheme. FIAAI have been engaged
on the renewable energy plan and the Hydro Tas Australia
Renewable Energy Agency (ARENA) application. Regular
discussions with CBIAA on a range of locally based topics have
occurred.
2nd Quarter: The General Manager has been active in attempting to
finalise the transfer of properties on Cape Barren Island with the
Deputy Premier. The goal of the transfer if/when complete is to see
the land returned to Aboriginal ownership and a great deal of work
has been ongoing on this matter for some years. The transfer does
now appear to be close to finalisation and further action will be
required in the next reporting period.
30/06/2014General Manager50% 1/07/2013
February 07, 2014 Page 13 of 17
Annexure 25 - Item D4 - February 2014
83
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.3 Actively participate in local government, industry and regional organisations
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.3.1 Actively participate in key strategic organisations, groups and alliances that provide value for the Flinders community and Council.
START DATE
5.3.1.6 Liaise with
Government Ministers,
advisers and Agencies,
Secretaries State &
Federal.
In Progress 1st Quarter: The reporting period was notable for the change of
Government that occurred at a Federal level. The new Federal
Member for Bass has been actively engaged and made aware of the
priority projects and opportunities that exist in the islands and is a
keen advocate on our behalf. Greens Senator Peter Whish-Wilson
also visited the island during the period and showed a keen interest
in the renewable energy plan and the efforts of island producers to
build niche markets for our premium products.
The announcement of a shipping subsidy to King Island cattle
producers saw a direct approach to the Minister seeking clarification
as to why Flinders producers had not been consulted or considered.
The State was notably unaware that the cost for Flinders procurers
to transport stock off island is now on par with those of King Island .
Staff are exploring if the subsidy could be deemed anti competitive
under the National Competition Policy.
Senior TasPorts executives visited to view the redevelopment of the
port area.
A visit by the Secretary of the Department of Infrastructure, Energy
and Resources resulted in Council and DIER now moving away from
tendering on a 3 year basis for the maintenance of the Lady Barron -
Whitemark State Road to a 10 year Deed of Agreement. This is a
significant achievement which provides Council with an assured
revenue stream over an extended period of time and mitigates the
amount of staff time and reporting required under the current
arrangements.
2nd Quarter: During the reporting period a number of important
submissions were required to be developed, discussed with the
Councillor group and submitted. Most notably the Productivity
Commission review into Bass Strait Shipping and the Draft
Ministerial Orders proposed by the State Government under Section
70F, 84(2A) and 85B of the Local Government Act 1993.
The Draft Orders, as presented, are best practice for a large urban
30/06/2014General Manager50% 1/07/2013
February 07, 2014 Page 14 of 17
Annexure 25 - Item D4 - February 2014
84
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
5.3 Actively participate in local government, industry and regional organisations
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 5.3.1 Actively participate in key strategic organisations, groups and alliances that provide value for the Flinders community and Council.
START DATE
Council with the staff capacity and financial resources to comply . For
small rural and remote Council's this level of direction, oversight and
compliance will be a major impost at a staff and cost level and will
need to be funded through decreased on ground services and
standards. Put simply, this “gold plated” approach is beyond our
community's needs or capacity to fund without significant and
ongoing financial assistance from the State. Council continues to
lobby for further consolation on this matter before they are
implemented.
Management spent a good deal of time liaising with Tasports in
relation to shipping and port related challenges and matters which
appear to have now been resolved.
Management has also lobbied politicians in the lead up the
upcoming State election outlining key projects for consideration and
funding. This will be require further direct approaches in the coming
months to ensure the islands priority needs are considered. It should
be noted that any project that is put forward for consideration for
State funding requires well developed evidence based proposals
and Council has actively prepared projects such as the renewable
energy plan, apron and taxiway expansion and airport runway
rebuild to such a level over the past two years. It should also be
noted that the Tasmanian economy is the worst performing in the
Commonwealth and discretionary funding for the upcoming election
will be minimal at best. A focus on the critical projects that require
support should be front of mind when approaches to the differing
parties are made.
February 07, 2014 Page 15 of 17
Annexure 25 - Item D4 - February 2014
85
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Focus
Area:
6 Furneaux Future - A thriving, self reliant community offering opportunities for current and following generations
while maintaining core values and attributes.
Strategic
Direction:
6.1 Implement a dynamic strategic plan and development framework to define our future and guide strategic decisions
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.1 Implement and continually evaluate the Council's strategic plan
START DATE
6.1.1.1 Undertake quarterly
annual plan review meetings
with Council and key staff and
provide departmental and staff
based reports on a quarterly
basis into the Council agenda
and meeting process.
In Progress 1st & 2nd Quarters: The quarterly annual plan assessment and
review is this report provided for Council information and
consideration. Staff have delivered all reports within specified
timeframes and utilising the new performance management and
reporting system now in place.
30/06/2014General Manager50% 1/07/2013
6.1.1.2 Assist with research
and preparation of a new or
revised strategic plan post the
2014 election.
Not Started 1st & 2nd Quarters: Work on this action will not commence until the
third quarter.
30/06/2014Executive Officer0% 1/07/2013
6.1.1.3 Planning a 'Furneaux
Vision' campaign that will be
available to all community
members to have input in to
the development of a new
council strategic plan in
2013/2014.
In Progress 1st & 2nd Quarters: Initial work has been carried out drafting the
Flinders Council brand pillars, however work will not commence on
this action until the third quarter.
30/06/2014Communications
Officer
20% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.4 Organisational collaboration and strengthening
START DATE
February 07, 2014 Page 16 of 17
Annexure 25 - Item D4 - February 2014
86
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Governance
Strategic
Direction:
6.1 Implement a dynamic strategic plan and development framework to define our future and guide strategic decisions
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.4 Organisational collaboration and strengthening
START DATE
6.1.4.1 Provide input into other
Council areas where required
such as Planning, Works and
Services, Community
Development and Corporate
Management.
In Progress 1st Quarter: Significant amounts of time have been required in all
areas. In particular Corporate Services and Human Resource
Management have required levels of oversight and assistance
beyond what would normally be expected.
2nd Quarter: The ongoing requirement for the General Manager to
directly manage Corporate Services, Building and Planning and
Human Resource Management functions when combined with the
economic development functions of Council are unsustainable and
require a full review. While the expectation that wage costs must be
constrained is admirable the complexity and growth of regulatory
compliance combined with the increasing work outputs expected
from management level staff can't be sustained within the existing
allocations provided without staff burning out. The recent resignation
of the Corporate Service Manager is but one example of such. A full
review of staff and corporate structures will be undertaken in the
next quarter to inform budget submissions for the 2014/2015
financial year.
30/06/2014General Manager50% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 6.1.5 Government Relations
START DATE
6.1.5.1 Liaise and lobby
Australian and State
Government Departments and
personnel on specific projects
and programs approved by the
Council.
Ongoing 1st & 2nd Quarters: Management continue to liaise with Ministers
and staff on a range of topics such as renewable energy , health,
shipping and transport, roads, runways, place of assembly licensing,
building regulations and community safety. The projects that have
existing Council endorsement will continue to be a focus of efforts in
the lead up to the State election.
30/06/2014General Manager 1/07/2013
February 07, 2014 Page 17 of 17
Annexure 25 - Item D4 - February 2014
87
BUSINESS UNIT QUARTERLY PROGRESS AGAINST OPERATIONAL PLAN (December 13/14)Flinders Council
Business Unit Quarterly Progress Report Against Operational Plan
Natural Resource Management
Strategic
Focus
Area:
1 Environment and Natural Asset Management - An environment that maintains its diversity, uniqueness and
attractiveness while supporting sustainable production and lifestyle.
Strategic
Direction:
1.1 Promote environmentally sustainable practice
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.1.1 Community education and communication.
START DATE
1.1.1.1 A series of programs
and projects delivered to
increase community
engagement and awareness of
NRM.
Not Started 1st Quarter: Council and Natural Resource Management (NRM)
North to date have been unable to agree on a funding model to
support an on island facilitator.
2nd Quarter: The General Manager has met with the NRM North
CEO and discussed a range of funding options to support the
position. NRM North wish to keep the existing funding model which
sees Council exposed to all staff related oncosts. Be that as it may,
NRM North are keen to assess how the position, if filled, could
deliver more localised and tailored outcomes for the Furneaux
Islands. The suggestion of developing a more tailored approach has
been agreed to be explored by the General Manager and the NRM
North CEO over January and February.
30/06/2014General Manager0% 1/07/2013
1.1.1.2 Four community
groups (including indigenous)
engaged in NRM on ground
projects.
Not Started 1st Quarter: Council and NRM North to date have been unable to
agree on a funding model to support an on island facilitator.
2nd Quarter: An on island facilitator has not yet been appointed.
30/06/2014General Manager0% 1/07/2013
ACTIONS STATUS % COMP PROGRESS COMMENTS COMP DATERESP. OFFICER
Output: 1.1.2 Farm and business based planning, project implementation & evaluation
START DATE
1.1.2.1 Continuing support for
existing Property Management
Planning clusters.
Not Started 1st Quarter: Council and NRM North to date have been unable to
agree on a funding model to support an on island facilitator.
2nd Quarter: An on island facilitator has not yet been appointed.
30/06/2014General Manager0% 1/07/2013
February 07, 2014 Page 2 of 2
Annexure 25 - Item D4 - February 2014