odot building contract: 28123 exh a

26
 DAS General Conditions (1/1/08) GENW2509 EXHIBIT A STATE OF OREGON GENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS NOTICE TO STATE AGENCIES AND PUBLIC IMPROVEMENT CONTRACTORS January 1, 2008 Edition The attached "State of Oregon General Conditions for Public Improvement Contracts" applies to all designated public improvement contracts. These provisions are intended for use within an agency’s own procurement documents and contracts, and do not contain the certifications and other forms required by particular public contracting agencies. Changes to the General Conditions (including any additions, deletions or substitutions) should only be made by Supplemental General Conditions, unless the General Conditions are specifically modified in the Public Improvement Agreement (which has a higher order of precedence under Section A.3 of the General Conditions). The text of these General Conditions should not otherwise be altered. For guidance, see the separate document entitled “Guidelines for Development of Supplemental General Conditions” . Electronic copies of the General Conditions, the Guidelines for Development of Supplemental General Conditions and a form for the Supplemental General Conditions are available at the Oregon Department of Administrative Services web site at: http://www.oregon.gov/DAS/SSD/SPO/purchasing-links.shtml#Public_Improvement  

Upload: statesman-journal

Post on 07-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 1/26

 

DAS General Conditions (1/1/08) GENW2509

EXHIBIT A

STATE OF OREGON

GENERAL CONDITIONS

FOR

PUBLIC IMPROVEMENT

CONTRACTS

NOTICE TO STATE AGENCIES AND PUBLIC IMPROVEMENT CONTRACTORS

January 1, 2008 Edition

The attached "State of Oregon General Conditions for Public ImprovementContracts" applies to all designated public improvement contracts. These provisions

are intended for use within an agency’s own procurement documents and contracts,and do not contain the certifications and other forms required by particular publiccontracting agencies.

Changes to the General Conditions (including any additions, deletions or substitutions)should only be made by Supplemental General Conditions, unless the GeneralConditions are specifically modified in the Public Improvement Agreement (which has ahigher order of precedence under Section A.3 of the General Conditions). The text ofthese General Conditions should not otherwise be altered. For guidance, see theseparate document entitled “Guidelines for Development of Supplemental GeneralConditions”. Electronic copies of the General Conditions, the Guidelines for

Development of Supplemental General Conditions and a form for the SupplementalGeneral Conditions are available at the Oregon Department of Administrative Servicesweb site at:

http://www.oregon.gov/DAS/SSD/SPO/purchasing-links.shtml#Public_Improvement 

Page 2: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 2/26

 

DAS General Conditions (1/1/08) GENW2509

NOTE:

THE FOLLOWING GENERAL CONDITIONS HAVE BEEN REVIEWED AS TOFORM BY THE OREGON DEPARTMENT OF JUSTICE. THE LEGALSUFFICIENCY AND APPROVAL REQUIREMENTS OF ORS 291.047 ARESTILL APPLICABLE FOR INDIVIDUAL PROCUREMENTS OF STATEAGENCIES, UNLESS AN EXEMPTION HAS BEEN GRANTED PURSUANT TO

THAT STATUTE AND ADMINISTRATIVE RULES AT OAR CHAPTER 137,DIVISION 45.

Page 3: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 3/26

 

DAS General Conditions (1/1/08) GENW2509

STATE OF OREGONGENERAL CONDITIONS FOR PUBLIC IMPROVEMENT CONTRACTS

JANUARY 1, 2008

TABLE OF SECTIONS

SECTION AGENERAL PROVISIONS 

A.1 DEFINITION OF TERMSA.2 SCOPE OF WORKA.3 INTERPRETATION OF CONTRACT

DOCUMENTSA.4 EXAMINATION OF PLANS, SPECIFICATIONS,

AND SITEA.5 INDEPENDENT CONTRACTOR STATUSA.6 RETIREMENT SYSTEM STATUS AND TAXESA.7 GOVERNMENT EMPLOYMENT STATUS

SECTION BADMINISTRATION OF THE CONTRAC T

B.1 OWNER’S ADMINISTRATION OF THECONTRACT

B.2 CONTRACTOR'S MEANS AND METHODSB.3 MATERIALS AND WORKMANSHIPB.4 PERMITSB.5 COMPLIANCE WITH GOVERNMENT LAWS AND

REGULATIONSB.6 SUPERINTENDENCEB.7 INSPECTIONB.8 SEVERABILITYB.9 ACCESS TO RECORDSB.10 WAIVERB.11 SUBCONTRACTS AND ASSIGNMENTB.12 SUCCESSORS IN INTERESTB.13 OWNER'S RIGHT TO DO WORKB.14 OTHER CONTRACTS

B.15 GOVERNING LAWB.16 LITIGATIONB.17 ALLOWANCESB.18 SUBMITTALS, SHOP DRAWINGS, PRODUCT

DATA AND SAMPLESB.19 SUBSTITUTIONSB.20 USE OF PLANS AND SPECIFICATIONSB.21 FUNDS AVAILABLE AND AUTHORIZEDB.22 NO THIRD PARTY BENEFICIARIES

SECTION CWAGES AND LABOR 

C.1 MINIMUM WAGES RATES ON PUBLIC WORKSC.2 PAYROLL CERTIFICATION; ADDITIONAL

RETAINAGE; FEE REQUIREMENTS

C.3 PROMPT PAYMENT AND CONTRACTCONDITIONS

C.4 PAYMENT FOR MEDICAL CAREC.5 HOURS OF LABOR

SECTION DCHANGES IN THE WORK

D.1 CHANGES IN THE WORKD.2 DELAYSD.3 CLAIMS REVIEW PROCESS

SECTION EPAYMENTS 

E.1 SCHEDULE OF VALUESE.2 APPLICATIONS FOR PAYMENTE.3 PAYROLL CERTIFICATION REQUIREMENTE.4 DUAL PAYMENT SOURCESE.5 RETAINAGEE.6 FINAL PAYMENT

SECTION FJOB SITE CONDITIONS 

F.1 USE OF PREMISESF.2 PROTECTION OF WORKERS, PROPERTY

AND THE PUBLICF.3 CUTTING AND PATCHINGF.4 CLEANING UPF.5 ENVIRONMENTAL CONTAMINATIONF.6 ENVIRONMENTAL CLEAN-UPF.7 FORCE MAJEURE

SECTION GINDEMNITY, BONDING AND INSURANCE 

G.1 RESPONSIBILITY FOR DAMAGES/INDEMNITYG.2 PERFORMANCE AND PAYMENT SECURITY;

PUBLIC WORKS BONDG.3 INSURANCE

SECTION HSCHEDULE OF WORK 

H.1 CONTRACT PERIODH.2 SCHEDULEH.3 PARTIAL OCCUPANCY OR USE

SECTION ICORRECTION OF WORK 

I.1 CORRECTIONS OF WORK BEFORE FINALPAYMENT

I.2 WARRANTY WORK

SECTION J

SUSPENSION AND/OR TERMINATION OF THE WORK 

J.1 OWNER'S RIGHT TO SUSPEND THE WORKJ.2 CONTRACTOR'S RESPONSIBILITIESJ.3 COMPENSATION FOR SUSPENSIONJ.4 OWNER'S RIGHT TO TERMINATE CONTRACTJ.5 TERMINATION FOR CONVENIENCEJ.6 ACTION UPON TERMINATION

Page 4: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 4/26

 

DAS General Conditions (3/1/2004) GENI1443

SECTION KCONTRACT CLOSE-OUT 

K.1 RECORD DRAWINGSK.2 OPERATION AND MAINTENANCE MANUALSK.3 AFFIDAVIT/RELEASE OF LIENS AND CLAIMSK.4 COMPLETION NOTICESK.5 TRAININGK.6 EXTRA MATERIALSK.7 ENVIRONMENTAL CLEAN-UPK.8 CERTIFICATE OF OCCUPANCYK.9 OTHER CONTRACTOR RESPONSIBILITIESK.10 SURVIVAL

SECTION LLEGAL RELATIONS AND RESPONSIBILITY 

TO THE PUBLIC 

L.1 LAWS TO BE OBSERVEDL.2 FEDERAL AGENCIESL.3 STATE AGENCIESL.4 LOCAL AGENCIES

A.1 DEFINITION OF TERMS

In the Contract Documents the following terms shall beas defined below:

ARCHITECT/ENGINEER, means the Person appointed bythe Owner to make drawings and specifications and, toprovide contract administration of the Work contemplated bythe Contract to the extent provided herein or bysupplemental instruction of Owner (under which Owner maydelegate responsibilities of the Owner’s AuthorizedRepresentative to the Architect/Engineer), in accordancewith ORS Chapter 671 (Architects) or ORS Chapter 672(Engineers) and administrative rules adopted thereunder.

CHANGE ORDER, means a written order issued by theOwner's Authorized Representative to the Contractorrequiring a change in the Work within the general scope ofthe Contract Documents, issued under the changesprovisions of Section D.1 in administering the Contract,including Owner's written change directives as well as

changes reflected in a writing executed by the parties to thisContract and, if applicable, establishing a Contract Price orContract Time adjustment for the changed Work.

CLAIM, means a demand by Contractor pursuant to SectionD.3 for review of the denial of Contractor’s initial request foran adjustment of Contract terms, payment of money,extension of Contract Time or other relief, submitted inaccordance with the requirements and within the time limitsestablished for review of Claims in these GeneralConditions. 

CONTRACT, means the written agreement between theOwner and the Contractor comprised of the ContractDocuments which describe the Work to be done and theobligations between the parties.

CONTRACT DOCUMENTS, means the SolicitationDocument and addenda thereto, the State of Oregon PublicImprovement Agreement Form, General Conditions,Supplemental General Conditions, if any, the accepted Offer,Plans, Specifications, amendments and Change Orders.

CONTRACT PERIOD, as set forth in the ContractDocuments, means the total period of time beginning withthe issuance of the Notice to Proceed and concluding uponFinal Completion.

CONTRACT PRICE, means the total of the awarded Offeramount, as increased or decreased by the price of approvedalternates and Change Orders.

CONTRACT TIME, means any incremental period of timeallowed under the Contract to complete any portion of theWork as reflected in the project schedule.

CONTRACTOR, means the Person awarded the Contractfor the Work contemplated.

DAYS, are calendar days, including weekdays, weekendsand holidays, unless otherwise specified.

DIRECT COSTS, means, unless otherwise provided in theContract Documents, the cost of materials, including salestax, cost of delivery; cost of labor, including social security,old age and unemployment insurance, and fringe benefitsrequired by agreement or custom; worker's compensationinsurance; project specific insurance; bond premiums, rentalcost of equipment, and machinery required for execution ofthe work; and the additional costs of field personnel directlyattributable to the Work. 

FINAL COMPLETION, means the final completion of allrequirements under the Contract, including ContractCloseout as described in Section K but excluding WarrantyWork as described in Section I.2, and the final payment andrelease of all retainage, if any, released.

FORCE MAJEURE, means an act, event or occurrencecaused by fire, riot, war, acts of God, nature, sovereign, or

public enemy, strikes, freight embargoes or any other act,event or occurrence that is beyond the control of the party tothis Contract who is asserting Force Majeure. 

NOTICE TO PROCEED, means the official written noticefrom the Owner stating that the Contractor is to proceed withthe Work defined in the Contract Documents.Notwithstanding the Notice to Proceed, Contractor shall notbe authorized to proceed with the Work until all initialContract requirements, including the Contract, performancebond and payment bond, and certificates of insurance, havebeen fully executed and submitted to Owner in a suitableform.

OFFER, means a bid in connection with an invitation to bidand a proposal in connection with a request for proposals.

OFFEROR, means a bidder in connection with an invitationto bid and a proposer in connection with a request forproposals.

OVERHEAD, means those items which may be included inthe Contractor's markup (general and administrativeexpense and profit) and that shall not be charged as DirectCost of the Work, including without limitation such Overheadexpenses as wages or salary of personnel above the level offoreman (i.e., superintendents and project managers), andexpenses of Contractor's offices at the job site (e.g. jobtrailer) including expenses of personnel staffing the job siteoffice.

OWNER, means the State of Oregon acting by and throughthe governmental entity identified in the Solicitation

Document.

OWNER'S AUTHORIZED REPRESENTATIVE, meansthose individuals identified in writing by the Owner to act onbehalf of the Owner for this project. Owner may elect, bywritten notice to Contractor, to delegate certain duties of theOwner’s Authorized Representative to more than one party,including without limitation, to an Architect/Engineer.However, nothing in these General Conditions is intended toabrogate the separate design professional responsibilities ofArchitects under ORS Chapter 671 or of Engineers underORS Chapter 672.

PERSON, means an entity doing business as a soleproprietorship, a partnership, a joint venture, a corporation, a

Page 5: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 5/26

 

CM/GC Contract Form (4/09) (574022)

limited liability company or partnership, or any other entitypossessing the legal capacity to contract.

PLANS, means the drawings which show the location, type,dimensions, and details of the Work to be done under theContract.

PUNCHLIST, means the list of Work yet to be completed ordeficiencies which need to be corrected in order to achieveFinal Completion of the Contract.

RECORD DOCUMENT, means the as-built Plans,Specifications, testing and inspection records, product data,samples, manufacturer and distributor/supplier warrantiesevidencing transfer to Owner, operational and maintenancemanuals, shop drawings, Change Orders, correspondence,certificate(s) of occupancy, and other documents listed inSubsection B.9.1 of these General Conditions, recording allServices performed.

SOLICITATION DOCUMENT, means an invitation to bid orrequest for proposal or request for quotes.

SPECIFICATION, means any description of the physical orfunctional characteristics of the Work, or of the nature of asupply, service or construction item. Specifications mayinclude a description of any requirement for inspecting,testing or preparing a supply, service or construction item fordelivery and the quantities or qualities of materials to be

furnished under the Contract. Specifications generally willstate the results or products to be obtained and may, onoccasion, describe the method and manner of doing thework to be performed. Specifications may be incorporatedby reference and/or may be attached to the Contract.

SUBCONTRACTOR, means a Person having a directcontract with the Contractor, or another Subcontractor, toperform one or more items of the Work.

SUBSTANTIAL COMPLETION, means the date when theOwner accepts in writing the construction, alteration or repairof the improvement to real property or any designatedportion thereof as having reached that state of completionwhen it may be used or occupied for its intended purpose.Substantial Completion of facilities with operating systemsoccurs only after thirty (30) continuous Days of successful,

trouble-free operation of the operating systems as providedin Section K.4.2.

SUBSTITUTIONS, means items that in function,performance, reliability, quality, and general configurationare the same or better than the product(s) specified.Approval of any substitute item shall be solely determined bythe Owner's Authorized Representative. The decision of theOwner's Authorized Representative is final.

SUPPLEMENTAL GENERAL CONDITIONS, means thoseconditions that remove from, add to, or modify these GeneralConditions. Supplemental General Conditions may beincluded in the Solicitation Document or may be a separateattachment to the Contract.

WORK, means the furnishing of all materials, equipment,labor, transportation, services and incidentals necessary tosuccessfully complete any individual item or the entireContract and the carrying out of duties and obligationsimposed by the Contract Documents.

A.2 SCOPE OF WORK

The Work contemplated under this Contract includes alllabor, materials, transportation, equipment andservices for, and incidental to, the completion of allconstruction work in connection with the project described inthe Contract Documents. The Contractor shall perform allWork necessary so that the project can be legally occupied

and fully used for the intended use as set forth in theContract Documents. 

A.3 INTERPRETATION OF CONTRACT DOCUMENTS

A.3.1 Unless otherwise specifically defined in the ContractDocuments, words which have well-known technicalmeanings or construction industry meanings areused in the Contract Documents in accordance withsuch recognized meanings. Contract Documents areintended to be complementary. Whatever is calledfor in one, is interpreted to be called for in all.However, in the event of conflicts or discrepanciesamong the Contract Documents, interpretations willbe based on the following descending order ofprecedence:

1. Contract amendments and Change Orders, withthose of later date having precedence overthose of an earlier date;

2. The Supplemental General Conditions;

3. The State of Oregon Public ImprovementAgreement Form;

4. The General Conditions

5. The Plans and Specifications

6. The Solicitation Document and any addendathereto;

7. The accepted Offer.

A.3.2 In the case of an inconsistency between Plans andSpecifications or within either document not clarifiedby addendum, the better quality or greater quantity ofWork shall be provided in accordance with theOwner or Owner's Authorized Representative'sinterpretation in writing.

A.3.3 If the Contractor finds discrepancies in, or omissionsfrom the Contract Documents, or if the Contractor isin doubt as to their meaning, the Contractor shall atonce notify the Owner or Owner's Authorized

Representative. Matters concerning performanceunder, and interpretation of requirements of, theContract Documents will be decided by the Owner'sAuthorized Representative, who may delegate thatduty in some instances to the Architect/Engineer.Responses to Contractor's requests for interpretationof Contract Documents will be made in writing byOwner's Authorized Representative (or theArchitect/Engineer) within any time limits agreedupon or otherwise with reasonable promptness.Interpretations and decisions of the Owner'sAuthorized Representative (or Architect/Engineer)will be consistent with the intent of and reasonablyinferable from the Contract Documents. Contractorshall not proceed without direction in writing from theOwner's Authorized Representative (or

Architect/Engineer).

A.3.4  References to standard specifications, manuals,codes of any technical society, organization orassociation, to the laws or regulations of anygovernmental authority, whether such reference bespecific or by implication, shall mean the lateststandard specification, manual, code, laws orregulations in effect in the jurisdiction where theproject is occurring on the first published date of theSolicitation Document, except as may be otherwisespecifically stated. 

A.4 EXAMINATION OF PLANS, SPECIFICATIONS, ANDSITE

Page 6: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 6/26

 

CM/GC Contract Form (4/09) (574022)

A.4.1 It is understood that the Contractor, beforesubmitting an Offer, has made a careful examinationof the Contract Documents; has become fullyinformed as to the quality and quantity of materialsand the character of the Work required; and hasmade a careful examination of the location andconditions of the Work and the sources of supply formaterials. The Owner will in no case be responsiblefor any loss or for any unanticipated costs that maybe suffered by the Contractor as a result of theContractor's failure to acquire full information inadvance in regard to all conditions pertaining to theWork. No oral agreement or conversation with anyofficer, agent, or personnel of the Owner, or with theArchitect/Engineer either before or after theexecution of this Contract, shall affect or modify anyof the terms or obligations herein contained.

A.4.2 Should the Plans or Specifications fail to particularlydescribe the materials, kind of goods, or details ofconstruction of any aspect of the Work, Contractorshall have the duty to make inquiry of the Owner andArchitect/Engineer as to what is required prior toperformance of the Work. Absent Specifications tothe contrary, the materials or processes that wouldnormally be used to produce first quality finishedWork shall be considered a part of the Contractrequirements.

A.4.3 Any design errors or omissions noted by theContractor shall be reported promptly to the Owner’sAuthorized Representative, including withoutlimitation, any nonconformity with applicable laws,statutes, ordinances, building codes, rules andregulations.

A.4.4 If the Contractor believes that additional cost orContract Time is involved because of clarifications orinstructions issued by the Owner's AuthorizedRepresentative (or Architect/Engineer) in response tothe Contractor’s notices or requests for information,the Contractor must submit a written request to theOwner’s Authorized Representative, setting forth thenature and specific extent of the request, including alltime and cost impacts against the Contract as soon

as possible, but no later than thirty (30) Days afterreceipt by Contractor of the clarifications orinstructions issued. If the Owner’s AuthorizedRepresentative denies Contractor’s request foradditional compensation, additional Contract Time,or other relief that Contractor believes results fromthe clarifications or instructions, the Contractor mayproceed to file a Claim under Section D.3, ClaimsReview Process. If the Contractor fails to performthe obligations of Sections A.4.1 to A.4.3, theContractor shall pay such costs and damages to theOwner as would have been avoided if the Contractorhad performed such obligations.

A.5 INDEPENDENT CONTRACTOR STATUS

The service or services to be performed under thisContract are those of an independent contractor as definedin ORS 670.600. Contractor represents and warrants that itis not an officer, employee or agent of the Owner.

A.6 RETIREMENT SYSTEM STATUS AND TAXES

Contractor represents and warrants that it is not acontributing member of the Public Employees' RetirementSystem and will be responsible for any federal or state taxesapplicable to payment received under this Contract.Contractor will not be eligible for any benefits from theseContract payments of federal Social Security, employment

insurance, workers' compensation or the Public Employees'Retirement System, except as a self-employed individual.Unless the Contractor is subject to backup withholding,Owner will not withhold from such payments any amount(s)to cover Contractor’s federal or state tax obligations.

A.7 GOVERNMENT EMPLOYMENT STATUS

A.7.1 If this payment is to be charged against federalfunds, Contractor represents and warrants that it isnot currently employed by the Federal Government.This does not preclude the Contractor from holdinganother contract with the Federal Government.

A.7.2 Contractor represents and warrants that Contractoris not an employee of the State of Oregon forpurposes of performing Work under this Contract.

SECTION BADMINISTRATION OF THE CONTRACT 

B.1 OWNER’S ADMINISTRATION OF THE CONTRACT 

B.1.1 The Owner’s Authorized Representative will provideadministration of the Contract as described in theContract Documents (1) during construction (2) untilfinal payment is due and (3) during the one-yearperiod for correction of Work. The Owner’s

Authorized Representative will act on behalf of theOwner to the extent provided in the ContractDocuments, unless modified in writing in accordancewith other provisions of the Contract. In performingthese tasks, the Owner’s Authorized Representativemay rely on the Architect/Engineer or otherconsultants to perform some or all of these tasks.

B.1.2 The Owner’s Authorized Representative will visit thesite at intervals appropriate to the stage of theContractor’s operations (1) to become generallyfamiliar with and to keep the Owner informed aboutthe progress and quality of the portion of the Workcompleted, (2) to endeavor to guard the Owneragainst defects and deficiencies in the Work, and (3)to determine in general if Work is being performed ina manner indicating that the Work, when fully

completed, will be in accordance with the ContractDocuments. The Owner’s AuthorizedRepresentative will not make exhaustive orcontinuous on-site inspections to check the quality orquantity of the Work. The Owner’s AuthorizedRepresentative will neither have control over orcharge of, nor be responsible for the constructionmeans, methods, techniques, sequences orprocedures, or for the safety precautions andprograms in connection with the Work.

B.1.3 Except as otherwise provided in the ContractDocuments or when direct communications havebeen specifically authorized, the Owner andContractor shall endeavor to communicate with eachother through the Owner’s Authorized

Representative or designee about matters arising outof or relating to the Contract. Communications byand with the Architect/Engineer’s consultants shallbe through the Architect/Engineer. Communicationsby and with Subcontractors and material suppliersshall be through the Contractor. Communications byand with separate contractors shall be through theOwner’s Authorized Representative.

B.1.4 Based upon the Architect/Engineer’s evaluations ofthe Contractor’s Application for Payment, or unlessotherwise stipulated by the Owner’s AuthorizedRepresentative, the Architect/Engineer will reviewand certify the amounts due the Contractor and willissue Certificates for Payment in such amounts.

Page 7: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 7/26

 

CM/GC Contract Form (4/09) (574022)

B.2 CONTRACTOR'S MEANS AND METHODS;MITIGATION OF IMPACTS

B.2.1 The Contractor shall supervise and direct the Work,using the Contractor’s best skill and attention. TheContractor shall be solely responsible for and havecontrol over construction means, methods,techniques, sequences and procedures and forcoordinating all portions of the Work under theContract, unless the Contract Documents give otherspecific instructions concerning these matters. If theContract Documents give specific instructionsconcerning construction means, methods,techniques, sequences or procedures, the Contractorshall evaluate the jobsite safety thereof and, exceptas stated below, shall be fully and solely responsiblefor the jobsite safety of such means, methods,techniques, sequences or procedures.

B.2.2 The Contractor is responsible to protect and maintainthe Work during the course of construction and tomitigate any adverse impacts to the project, includingthose caused by authorized changes, which mayaffect cost, schedule, or quality.

B.2.3 The Contractor is responsible for the actions of all itspersonnel, laborers, suppliers, and Subcontractorson the project. The Contractor shall enforce strict

discipline and good order among Contractor’semployees and other persons carrying out the Work.The Contractor shall not permit employment ofpersons who are unfit or unskilled for the tasksassigned to them.

B.3 MATERIALS AND WORKMANSHIP

B.3.1 The intent of the Contract Documents is to providefor the construction and completion in every detail ofthe Work described. All Work shall be performed ina professional manner and unless the means ormethods of performing a task are specifiedelsewhere in the Contract Documents, Contractorshall employ methods that are generally acceptedand used by the industry, in accordance with industrystandards.

B.3.2 The Contractor is responsible to perform the Work asrequired by the Contract Documents. DefectiveWork shall be corrected at the Contractor's expense.

B.3.3 Work done and materials furnished shall be subjectto inspection and/or observation and testing by theOwner's Authorized Representative to determine ifthey conform to the Contract Documents. Inspectionof the Work by the Owner's AuthorizedRepresentative does not relieve the Contractor ofresponsibility for the Work in accordance with theContract Documents.

B.3.4 Contractor shall furnish adequate facilities, asrequired, for the Owner's Authorized Representative

to have safe access to the Work including withoutlimitation walkways, railings, ladders, tunnels, andplatforms. Producers, suppliers, and fabricators shallalso provide proper facilities and access to theirfacilities.

B.3.5 The Contractor shall furnish Samples of materials fortesting by the Owner's Authorized Representativeand include the cost of the Samples in the ContractPrice. 

B.4 PERMITS

Contractor shall obtain and pay for all necessarypermits and licenses, except for those specifically excluded

in the Supplemental General Conditions, for the constructionof the Work, for temporary obstructions, enclosures, openingof streets for pipes, walls, utilities, environmental Work, etc.,as required for the project. Contractor shall be responsiblefor all violations of the law, in connection with theconstruction or caused by obstructing streets, sidewalks orotherwise. Contractor shall give all requisite notices topublic authorities. The Contractor shall pay all royalties andlicense fees. The Contractor shall defend all suits or claimsfor infringement of any patent or other proprietary rights andsave harmless and blameless from loss, on account thereof,the State of Oregon, and its departments, divisions,members and employees.

B.5 COMPLIANCE WITH GOVERNMENT LAWS ANDREGULATIONS

B.5.1 Contractor shall comply with all federal, state andlocal laws, codes, regulations and ordinancesapplicable to the Work and the Contract. Failure tocomply with such requirements shall constitute abreach of Contract and shall be grounds for Contracttermination. Without limiting the generality of theforegoing, Contractor expressly agrees to complywith the following as applicable: i) Title VI and VII ofCivil Rights Act of 1964, as amended; (ii) Section503 and 504 of the Rehabilitation Act of 1973, asamended; (iii) the Health Insurance Portability andAccountability Act of 1996; (iv) the Americans with

Disabilities Act of 1990, as amended; (v) ORSChapter 659A; as amended (vi) all regulations andadministrative rules established pursuant to theforegoing laws; and (vii) all other applicablerequirements of federal and state civil rights andrehabilitation statutes, rules and regulations.Owner’s performance under the Contract isconditioned upon Contractor's compliance with theprovisions of ORS 279C.505, 279C.510, 279C.515,279C.520, and 279C.530, which are incorporated byreference herein.

B.5.2 Contractor shall comply with all applicablerequirements of federal and state civil rights andrehabilitation statutes, rules and regulations; and

(a) Contractor shall not discriminate against

Disadvantaged, Minority, Women or EmergingSmall Business enterprises, as those terms aredefined in ORS 200.005, in the awarding ofsubcontracts (ORS 279A.110).

(b) Contractor shall maintain, in current and validform, all licenses and certificates required bylaw, regulation, or this Contract whenperforming the Work.

B.5.3 Unless contrary to federal law, Contractor shallcertify that it shall not accept a bid fromSubcontractors to perform Work as described in ORS701.005 under this Contract unless suchSubcontractors are registered with the ConstructionContractors Board in accordance with ORS 701.035

to 701.055 at the time they submit their bids to theContractor.

B.5.4 Unless contrary to federal law, Contractor shallcertify that each landscape contractor, as defined inORS 671.520(2), performing Work under thisContract holds a valid landscape contractor's licenseissued pursuant to ORS 671.560.

B.5.5 The following notice is applicable to Contractors whoperform excavation Work. ATTENTION: Oregon lawrequires you to follow rules adopted by the OregonUtility Notification Center. Those rules are set forthin OAR 952-001-0010 through OAR 952-001-0090.

Page 8: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 8/26

 

CM/GC Contract Form (4/09) (574022)

You may obtain copies of the rules by calling thecenter at (503)232-1987.

B.5.6 Failure to comply with any or all of the requirementsof B.5.1 through B.5.5 shall be a breach of Contractand constitute grounds for Contract termination.Damages or costs resulting from suchnoncompliance shall be the responsibility ofContractor.

B.6 SUPERINTENDENCE

Contractor shall keep on the site, during the progress ofthe Work, a competent superintendent and any necessaryassistants who shall be satisfactory to the Owner and whoshall represent the Contractor on the site. Directions givento the superintendent by the Owner's AuthorizedRepresentative shall be confirmed in writing to theContractor.

B.7 INSPECTION

B.7.1 Owner's Authorized Representative shall haveaccess to the Work at all times.

B.7.2 Inspection of the Work will be made by the Owner'sAuthorized Representative at its discretion. TheOwner’s Authorized Representative will haveauthority to reject Work that does not conform to the

Contract Documents. Any Work found to be not inconformance with the Contract Documents, in thediscretion of the Owner's Authorized Representative,shall be removed and replaced at the Contractor'sexpense.

B.7.3 Contractor shall make or obtain at the appropriatetime all tests, inspections and approvals of portionsof the Work required by the Contract Documents orby laws, ordinances, rules, regulations or orders ofpublic authorities having jurisdiction. Unlessotherwise provided, the Contractor shall makearrangements for such tests, inspections andapprovals with an independent testing laboratory orentity acceptable to the Owner, or with theappropriate public authority, and shall bear all relatedcosts of tests, inspections and approvals. Tests or

inspections conducted pursuant to the ContractDocuments shall be made promptly to avoidunreasonable delay in the Work. The Contractorshall give the Owner’s Authorized Representativetimely notice of when and where tests andinspections are to be made so that the Owner’sAuthorized Representative may be present for suchprocedures. Required certificates of testing,inspection or approval shall, unless otherwiserequired by the Contract Documents, be secured bythe Contractor and promptly delivered to the Owner’sAuthorized Representative.

B.7.4 As required by the Contract Documents, Work doneor material used without inspection or testing by theOwner's Authorized Representative may be ordered

removed at the Contractor's expense.

B.7.5 If directed to do so any time before the Work isaccepted, the Contractor shall uncover portions ofthe completed Work for inspection. After inspection,the Contractor shall restore such portions of Work tothe standard required by the Contract. If the Workuncovered is unacceptable or was done withoutsufficient notice to the Owner's AuthorizedRepresentative, the uncovering and restoration shallbe done at the Contractor's expense. If the Workuncovered is acceptable and was done with sufficientnotice to the Owner's Authorized Representative, theuncovering and restoration will be paid for as aChange Order.

B.7.6 If any testing or inspection reveals failure of theportions of the Work to comply with requirementsestablished by the Contract Documents, all costsmade necessary by such failure, including those ofrepeated procedures and compensation for theOwner’s Authorized Representative’s andArchitect/Engineer’s services and expenses, shall beat the Contractor’s expense.

B.7.7 When the United States government participates inthe cost of the Work, or the Owner has an agreementwith other public or private organizations, or if anyportion of the Work is being performed for a thirdparty or in close proximity to third party facilities,representatives of these organizations have the rightto inspect the Work affecting their interests orproperty. Their right to inspect shall not make thema party to the Contract and shall not interfere with therights of the parties of the Contract. Instructions ororders of such parties shall be transmitted to theContractor, through the Owner's AuthorizedRepresentative.

B.8 SEVERABILITY

If any provision of this Contract is declared by a court tobe illegal or in conflict with any law, the validity of theremaining terms and provisions shall not be affected and the

rights and obligations of the parties shall be construed andenforced as if the Contract did not contain the particularprovision held to be invalid.

B.9  ACCESS TO RECORDS 

B.9.1 Contractor shall keep, at all times on the Work site,one record copy of the complete ContractDocuments, including the Plans, Specifications,Change Orders and addenda, in good order andmarked currently to record field changes andselections made during construction, and one recordcopy of Shop Drawings, Product Data, Samples andsimilar submittals, and shall at all times give theOwner's Authorized Representative access thereto.

B.9.2 Contractor shall retain and the Owner and its duly

authorized representatives shall have access to, fora period not less than six (6) years, all RecordDocuments, financial and accounting records, andother books, documents, papers and records ofContractor which are pertinent to the Contractincluding records pertaining to Overhead and indirectcosts, for the purpose of making audit, examination,excerpts and transcripts. If for any reason, any partof the Contract is involved in litigation, Contractorshall retain all such records until all litigation isresolved. The Owner and/or its agents shall continueto be provided full access to the records duringlitigation.

B.10 WAIVER

Failure of the Owner to enforce any provision of thisContract shall not constitute a waiver or relinquishment bythe Owner of the right to such performance in the future norof the right to enforce any other provision of this Contract.

B.11 SUBCONTRACTS AND ASSIGNMENT

B.11.1 Contractor shall require each Subcontractor, tothe extent of the Work to be performed by theSubcontractor, to be bound by the terms and conditionsof these General Conditions, and to assume toward theContractor all of the obligations and responsibilities

Page 9: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 9/26

 

CM/GC Contract Form (4/09) (574022)

which the Contractor assumes toward the Ownerthereunder, unless (1) the same are clearly inapplicableto the subcontract at issue because of legalrequirements or industry practices, or (2) specificexceptions are requested by Contractor and approved inwriting by Owner. Where appropriate, Contractor shallrequire each Subcontractor to enter into similaragreements with sub-subcontractors at any level.

B.11.2 At Owner’s request, Contractor shall submit toOwner prior to their execution either Contractor’sform of subcontract, or the subcontract to beexecuted with any particular Subcontractor. If Ownerdisapproves such form, Contractor shall not executethe form until the matters disapproved are resolvedto Owner’s satisfaction. Owner’s review, commentupon or approval of any such form shall not relieveContractor of its obligations under this Agreement orbe deemed a waiver of such obligations ofContractor.

B.11.3 Contractor shall not assign, sell, or transfer its rights,or delegate its responsibilities under this Contract, inwhole or in part, without the prior written approval ofthe Owner. No such written approval shall relieveContractor of any obligations of this Contract, andany transferee shall be considered the agent of theContractor and bound to perform in accordance withthe Contract Documents. Contractor shall remain

liable as between the original parties to the Contractas if no assignment had occurred.

B.12 SUCCESSORS IN INTEREST

The provisions of this Contract shall be binding uponand shall accrue to the benefit of the parties to theContract and their respective permitted successors andassigns.

B.13 OWNER'S RIGHT TO DO WORK

Owner reserves the right to perform other or additionalwork at or near the project site with other forces than thoseof the Contractor. If such work takes place within or next tothe project site, Contractor will coordinate work with theother contractors or forces, cooperate with all other

contractors or forces, carry out the Work in a way that willminimize interference and delay for all forces involved, placeand dispose of materials being used so as not to interferewith the operations of another, and join the Work with thework of the others in an acceptable manner and perform it inproper sequence to that of the others. The Owner’sAuthorized Representative will resolve any disagreementsthat may arise between or among Contractor and the othercontractors over the method or order of doing all work(including the Work). In case of unavoidable interference,the Owner’s Authorized Representative will establish workpriority (including the Work) which generally will be in thesequence that the contracts were awarded.

B.14 OTHER CONTRACTS

In all cases and at any time, the Owner has the right toexecute other contracts related to or unrelated to the Work ofthis Contract. The Contractor of this Contract will fullycooperate with any and all other contractors withoutadditional cost to the Owner in the manner described insection B.13.

B.15 GOVERNING LAW

This Contract shall be governed by and construed inaccordance with the laws of the State of Oregon withoutregard to principles of conflict of laws.

B.16 LITIGATION

Any Claim between Owner and Contractor that arisesfrom or relates to this Contract and that is not resolvedthrough the Claims Review Process in Section D.3 shall bebrought and conducted solely and exclusively within theCircuit Court of Marion County for the State of Oregon;provided, however, if a Claim must be brought in a federalforum, then it shall be brought and conducted solely andexclusively within the United States District Court for theDistrict of Oregon. In no event shall this section beconstrued as a waiver by the State of Oregon on any form ofdefense or immunity, whether sovereign immunity,governmental immunity, immunity based on the EleventhAmendment to the Constitution of the United States orotherwise, from any claim or from the jurisdiction of anycourt. CONTRACTOR BY EXECUTION OF THISCONTRACT HEREBY CONSENTS TO THE INPERSONAM JURISDICTION OF THE COURTSREFERENCED IN THIS SECTION B.16.

B.17 ALLOWANCES

B.17.1 The Contractor shall include in the Contract Price allallowances stated in the Contract Documents. Itemscovered by allowances shall be supplied for suchamounts and by such persons or entities as theOwner may direct.

B.17.2 Unless otherwise provided in the ContractDocuments:

(a) when finally reconciled, allowances shall coverthe cost to the Contractor of materials andequipment delivered at the site and all requiredtaxes, less applicable trade discounts;

(b) Contractor’s costs for unloading and handling atthe site, labor, installation costs, Overhead,profit and other expenses contemplated forstated allowance amounts shall be included inthe Contract Price but not in the allowances;

(c) whenever costs are more than or less thanallowances, the Contract Price shall be adjustedaccordingly by Change Order. The amount of

the Change Order shall reflect (i) the differencebetween actual costs and the allowances underSection B.17.2(a) and (2) changes inContractor’s costs under Section B.17.2(b).

(d) Unless Owner requests otherwise, Contractorshall provide to Owner a proposed fixed pricefor any allowance work prior to its performance.

B.18 SUBMITTALS, SHOP DRAWINGS, PRODUCT DATAAND SAMPLES

B.18.1 The Contractor shall prepare and keep current, forthe Architect’s/Engineer’s approval (or for theapproval of Owner’s Authorized Representative if

approval authority has not been delegated to theArchitect/Engineer), a schedule and list of submittalswhich is coordinated with the Contractor'sconstruction schedule and allows theArchitect/Engineer reasonable time to reviewsubmittals. Owner reserves the right to finallyapprove the schedule and list of submittals.Submittals include, without limitation, ShopDrawings, Product Data, and Samples which aredescribed below:

(a) Shop Drawings are drawings, diagrams,schedules and other data specially prepared forthe Work by the Contractor or a Subcontractor(including any sub-subcontractor),

Page 10: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 10/26

 

CM/GC Contract Form (4/09) (574022)

manufacturer, supplier or distributor to i llustratesome portion of the Work.

(b) Product Data are illustrations, standardschedules, performance charts, instructions,brochures, diagrams and other informationfurnished by the Contractor to illustratematerials or equipment for some portion of theWork.

(c) Samples are physical examples which illustratematerials, equipment or workmanship andestablish standards by which the Work will be

 judged.

B.18.2 Shop Drawings, Product Data, Samples and similarsubmittals are not Contract Documents. Thepurpose of their submittal is to demonstrate for thoseportions of the Work for which submittals arerequired by the Contract Documents the way bywhich the Contractor proposes to conform to theinformation given and the design concept expressedin the Contract Documents. Review of submittals bythe Architect/Engineer is not conducted for thepurpose of determining the accuracy andcompleteness of other details such as dimensionsand quantities, or for substantiating instructions forinstallation or performance of equipment or systems,or for approval of safety precautions or, unless

otherwise specifically stated by theArchitect/Engineer, of any construction means,methods, techniques, sequences or procedures, allof which remain the responsibility of the Contractoras required by the Contract Documents. TheArchitect/Engineer’s review of the Contractor’ssubmittals shall not relieve the Contractor of itsobligations under the Contract Documents. TheArchitect/Engineer’s approval of a specific item shallnot indicate approval of an assembly of which theitem is a component. Informational submittals uponwhich the Architect/Engineer is not expected to takeresponsive action may be so identified in theContract Documents. Submittals which are notrequired by the Contract Documents may bereturned by the Architect/Engineer without action.

B.18.3 The Contractor shall review for compliance with theContract Documents, approve and submit to theArchitect/Engineer Shop Drawings, Product Data,Samples and similar submittals required by theContract Documents with reasonable promptnessand in such sequence as to cause no delay in theWork or in the activities of the Owner or of separatecontractors. Submittals which are not marked asreviewed for compliance with the ContractDocuments and approved by the Contractor may bereturned by the Architect/Engineer without action.

B.18.4 By approving and submitting Shop Drawings,Product Data, Samples and similar submittals, theContractor represents that the Contractor hasdetermined and verified materials, field

measurements and field construction criteria relatedthereto, or will do so, and has checked andcoordinated the information contained within suchsubmittals with the requirements of the Work and ofthe Contract Documents.

B.18.5 The Contractor shall perform no portion of the Workfor which the Contract Documents require submittaland review of Shop Drawings, Product Data,Samples or similar submittals until the respectivesubmittal has been approved by theArchitect/Engineer.

B.18.6 The Work shall be in accordance with approvedsubmittals except that the Contractor shall not be

relieved of responsibility for deviations fromrequirements of the Contract Documents by theArchitect/Engineer’s review or approval of ShopDrawings, Product Data, Samples or similarsubmittals unless the Contractor has specificallyinformed the Architect/Engineer in writing of suchdeviation at the time of submittal and (i) theArchitect/Engineer has given written approval to thespecific deviation as a minor change in the Work, or(ii) a Change Order has been executed by Ownerauthorizing the deviation. The Contractor shall notbe relieved of responsibility for errors or omissions inShop Drawings, Product Data, Samples or similarsubmittals by the Architect/Engineer’s review orapproval thereof.

B.18.7 In the event that Owner elects not to have theobligations and duties described under this SectionB.18 performed by the Architect/Engineer, or in theevent no Architect/Engineer is employed by Owneron the project, all obligations and duties assigned tothe Architect/Engineer hereunder shall be performedby the Owner's Authorized Representative.

B.19  SUBSTITUTIONS

The Contractor may make Substitutions only with theconsent of the Owner, after evaluation by the Owner’sAuthorized Representative and only in accordance with a

Change Order. Substitutions shall be subject to therequirements of the bid documents. By making requests forSubstitutions, the Contractor represents that the Contractorhas personally investigated the proposed substitute product;represents that the Contractor will provide the samewarranty for the Substitution that the Contractor would forthe product originally specified unless approved otherwise;certifies that the cost data presented is complete andincludes all related costs under this Contract includingredesign costs, and waives all claims for additional costsrelated to the Substitution which subsequently becomeapparent; and will coordinate the installation of the acceptedSubstitution, making such changes as may be required forthe Work to be completed in all respects.

B.20 USE OF PLANS AND SPECIFICATIONS

Plans, Specifications and related Contract Documentsfurnished to Contractor by Owner or Owner’sArchitect/Engineer shall be used solely for the performanceof the Work under this Contract. Contractor and itsSubcontractors and suppliers are authorized to use andreproduce applicable portions of such documentsappropriate to the execution of the Work, but shall not claimany ownership or other interest in them beyond the scope ofthis Contract, and no such interest shall attach. Unlessotherwise indicated, all common law, statutory and otherreserved rights, in addition to copyrights, are retained byOwner.

B.21 FUNDS AVAILABLE AND AUTHORIZED

Owner reasonably believes at the time of entering into

this Contract that sufficient funds are available andauthorized for expenditure to finance the cost of thisContract within the Owner's appropriation or limitation.Contractor understands and agrees that, to the extent thatsufficient funds are not available and authorized forexpenditure to finance the cost of this Contract, Owner’spayment of amounts under this Contract attributable toServices performed after the last day of the current bienniumis contingent on Owner receiving from the OregonLegislative Assembly appropriations, limitations or otherexpenditure authority sufficient to allow Owner, in theexercise of its reasonable administrative discretion, tocontinue to make payments under this Contract.

B.22 NO THIRD PARTY BENEFICIARIES

Page 11: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 11/26

 

CM/GC Contract Form (4/09) (574022)

Owner and Contractor are the only parties to thisContract and are the only parties entitled to enforce itsterms. Nothing in this Contract gives, is intended to give, orshall be construed to give or provide any benefit or right,whether directly, indirectly, or otherwise, to third personsunless such third persons are individually identified by nameherein and expressly described as intended beneficiaries ofthe terms of this Contract.

SECTION CWAGES AND LABOR 

C.1 MINIMUM WAGE RATES ON PUBLIC WORKS

Contractor shall comply fully with the provisions ofORS 279C.800 through 279C.870. Documents establishingthose conditions, as determined by the Commissioner of theBureau of Labor and Industries (BOLI), are included asattachments to or are incorporated by reference in theContract Documents. Contractor shall pay workers at notless than the specified minimum hourly rate of wage, andshall include that requirement in all subcontracts.

C.2 PAYROLL CERTIFICATION; ADDITIONALRETAINAGE; FEE REQUIREMENTS

C.2.1 In accordance with ORS 279C.845, the Contractor

and every Subcontractor shall submit written certifiedstatements to the Owner's AuthorizedRepresentative, on the form prescribed by theCommissioner of the Bureau of Labor and Industries,certifying the hourly rate of wage paid each workerwhich the Contractor or the Subcontractor hasemployed on the project and further certifying that noworker employed on the project has been paid lessthan the prevailing rate of wage or less than theminimum hourly rate of wage specified in theContract, which certificate and statement shall beverified by the oath of the Contractor or theSubcontractor that the Contractor or Subcontractorhas read such statement and certificate and knowsthe contents thereof and that the same is true to theContractor or Subcontractor's best knowledge andbelief. The certified statements shall set out

accurately and completely the payroll records for theprior week including the name and address of eachworker, the worker's correct classification, rate ofpay, daily and weekly number of hours worked,deductions made and actual wages paid. Certifiedstatements for each week during which theContractor or Subcontractor has employed a workeron the project shall be submitted once a month, bythe fifth business day of the following month.

The Contractor and Subcontractors shall preservethe certified statements for a period of six (6) yearsfrom the date of completion of the Contract.

C.2.2 Pursuant to ORS 279C.845(7),the Owner shall retain25 percent of any amount earned by the Contractor

on this public works project until the Contractor hasfiled the certified statements required by sectionC.2.1. The Owner shall pay to the Contractor theamount retained under this subsection within 14 daysafter the Contractor files the required certifiedstatements, regardless of whether a Subcontractorhas failed to file certified statements.

C.2.3 Pursuant to ORS 279C.845(8), the Contractor shallretain 25 percent of any amount earned by a first-tierSubcontractor on this public works project until thefirst-tier Subcontractor has filed with the Owner thecertified statements required by C.2.1. Before payingany amount retained under this subsection, theContractor shall verify that the first-tier Subcontractor

has filed the certified statement, Within 14 days afterthe first-tier Subcontractor files the required certifiedstatement the Contractor shall pay the first-tierSubcontractor any amount retained under thissubsection.

C.2.4 In accordance with statutory requirements, andadministrative rules promulgated by theCommissioner of the Bureau of Labor and Industries,the fee required by ORS 279C.825(1) will be paid byOwner to the Commissioner at the time Owner entersinto the Contract.

C.3 PROMPT PAYMENT AND CONTRACT CONDITIONS 

C.3.1 Pursuant to ORS 279C.505 and as a condition toOwner’s performance hereunder, the Contractorshall:

C.3.1.1 Make payment promptly, as due, to all personssupplying to Contractor labor or materials for theprosecution of the Work provided for in thisContract.

C.3.1.2 Pay all contributions or amounts due the StateIndustrial Accident Fund from such Contractor orSubcontractor incurred in the performance of theContract.

C.3.1.3 Not permit any lien or claim to be filed orprosecuted against the Owner on account of anylabor or material furnished. Contractor will notassign any claims that Contractor has againstOwner, or assign any sums due by Owner, toSubcontractors, suppliers, or manufacturers,and will not make any agreement or act in anyway to give Subcontractors a claim or standingto make a claim against the Owner.

C.3.1.4 Pay to the Department of Revenue all sumswithheld from employees pursuant toORS 316.167.

C.3.1.5 DEMONSTRATE THAT AN EMPLOYEEDRUG TESTING PROGRAM IS IN PLACE ASFOLLOWS:

(A) CONTRACTOR REPRESENTS ANDWARRANTS THAT CONTRACTOR HAS INPLACE AT THE TIME OF THE EXECUTIONOF THIS CONTRACT, AND SHALL MAINTAINDURING THE TERM OF THIS CONTRACT, AQUALIFYING EMPLOYEE DRUG TESTINGPROGRAM FOR ITS EMPLOYEES THATINCLUDES, AT A MINIMUM, THEFOLLOWING:

(1) A WRITTEN EMPLOYEE DRUG TESTINGPOLICY,

(2) REQUIRED DRUG TESTING FOR ALLNEW SUBJECT EMPLOYEES OR,ALTERNATIVELY, REQUIRED TESTINGOF ALL SUBJECT EMPLOYEES EVERY 12MONTHS ON A RANDOM SELECTIONBASIS, AND

(3) REQUIRED TESTING OF A SUBJECTEMPLOYEE WHEN THE CONTRACTORHAS REASONABLE CAUSE TO BELIEVETHE SUBJECT EMPLOYEE IS UNDERTHE INFLUENCE OF DRUGS.

A DRUG TESTING PROGRAM THAT MEETS THEABOVE REQUIREMENTS WILL BE DEEMED A“QUALIFYING EMPLOYEE DRUG TESTINGPROGRAM.” FOR THE PURPOSES OF THISSECTION, AN EMPLOYEE IS A “SUBJECT

Page 12: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 12/26

 

CM/GC Contract Form (4/09) (574022)

EMPLOYEE” ONLY IF THAT EMPLOYEE WILL BEWORKING ON THE PROJECT JOB SITE.

(B) CONTRACTOR SHALL REQUIRE EACHSUBCONTRACTOR PROVIDING LABOR FORTHE PROJECT TO:

(1) DEMONSTRATE TO THE CONTRACTORTHAT IT HAS A QUALIFYING EMPLOYEEDRUG TESTING PROGRAM FOR THESUBCONTRACTOR’S SUBJECTEMPLOYEES, AND REPRESENT ANDWARRANT TO THE CONTRACTOR THAT

THE QUALIFYING EMPLOYEE DRUGTESTING PROGRAM IS IN PLACE AT THETIME OF SUBCONTRACT EXECUTIONAND WILL CONTINUE IN FULL FORCEAND EFFECT FOR THE DURATION OFTHE SUBCONTRACT, OR

(2) REQUIRE THAT THESUBCONTRACTOR’S SUBJECTEMPLOYEES PARTICIPATE IN THECONTRACTOR’S QUALIFYINGEMPLOYEE DRUG TESTING PROGRAMFOR THE DURATION OF THESUBCONTRACT.

C.3.2 Pursuant to ORS 279C.515, and as a condition toOwner's performance hereunder, Contractor agrees: 

C.3.2.1 If Contractor fails, neglects or refuses to makeprompt payment of any claim for labor orservices furnished to the Contractor or aSubcontractor by any person in connection withthe project as such claim becomes due, theproper officer(s) representing the Owner maypay the claim and charge the amount of thepayment against funds due or to become dueContractor under this Contract. Payment ofclaims in this manner shall not relieve theContractor or the Contractor's surety fromobligation with respect to any unpaid claims.

C.3.2.2 If the Contractor or a first-tier Subcontractorfails, neglects or refuses to make payment to aperson furnishing labor or materials in

connection with the public contract for a publicimprovement within thirty (30) Days after receiptof payment from Owner or a contractor, thecontractor or first-tier Subcontractor shall owethe person the amount due plus interest chargescommencing at the end of the 10-Day periodthat payment is due under ORS 279C.580(3)and ending upon final payment, unless paymentis subject to a good faith dispute as defined inORS 279C.580. The rate of interest charged tothe Contractor or first-tier Subcontractor on theamount due shall equal three times the discountrate on 90-Day commercial paper in effect at theFederal Reserve Bank in the Federal Reservedistrict that includes Oregon on the date that isthirty (30) Days after the date when paymentwas received from Owner or from the

Contractor, but the rate of interest shall notexceed thirty (30) percent. The amount ofinterest may not be waived.

C.3.2.3 If the Contractor or a Subcontractor fails,neglects or refuses to make payment to aperson furnishing labor or materials inconnection with the Contract, the person mayfile a complaint with the ConstructionContractors Board, unless payment is subject toa good faith dispute as defined in ORS279C.580. Every contract related to thisContract shall contain a similar clause.

C.3.3 Pursuant to ORS 279C.580, Contractor shall include

in each subcontract for property or services enteredinto by the Contractor and a first-tier Subcontractor,including a material supplier, for the purpose ofperforming a construction contract:

(a) A payment clause that obligates the Contractorto pay the first-tier Subcontractor for satisfactoryperformance under its subcontract within ten(10) Days out of such amounts as are paid tothe Contractor by Owner under the Contract;

(b) An interest penalty clause that obligates theContractor if payment is not made within thirty(30) Days after receipt of payment from Owner,to pay to the first-tier Subcontractor an interestpenalty on amounts due in the case of eachpayment not made in accordance with thepayment clause included in the subcontractpursuant to paragraph (a) of this subsection.Contractor or first-tier Subcontractor shall notbe obligated to pay an interest penalty if theonly reason that the Contractor or first-tierSubcontractor did not make payment whenpayment was due is that the Contractor or first-tier Subcontractor did not receive payment fromOwner or Contractor when payment was due.The interest penalty shall be for the periodbeginning on the day after the required paymentdate and ending on the date on which payment

of the amount due is made; and shall becomputed at the rate specified inORS 279C.515(2).

(c) A clause which requires each of Contractor'sSubcontractor's to include, in each of theircontracts with lower-tier Subcontractors orsuppliers, provisions to the effect that the first-tier Subcontractor shall pay its lower-tierSubcontractors and suppliers in accordancewith the provisions of subsections (a) and (b),above and requiring each of theirSubcontractors and suppliers to include suchclauses in their subcontracts and supplycontracts.

C.3.4 All employers, including Contractor, that employ

subject workers who work under this contract in theState of Oregon shall comply with ORS 656.017 andprovide the required Workers’ Compensationcoverage, unless such employers are exempt underORS 656.126. Contractor shall ensure that each ofits Subcontractors complies with these requirements. 

C.4 PAYMENT FOR MEDICAL CARE

Pursuant to ORS 279C.530, and as a condition toOwner's performance hereunder, Contractor shall promptly,as due, make payment to any person, partnership,association or corporation furnishing medical, surgical, andhospital care or other needed care and attention, incident tosickness or injury, to the employees of such Contractor, allsums of which the Contractor agrees to pay for such

services and all moneys and sums which the Contractor hascollected or deducted from the wages of personnel pursuantto any law, contract or agreement for the purpose ofproviding or paying for such services.

C.5 HOURS OF LABOR

As a condition to Owner's performance hereunder,Contractor shall comply with ORS 279C.520, as amendedfrom time to time and incorporated herein by this reference:

Pursuant to ORS 279C.520 and as a condition to Owner'sperformance hereunder, no person shall be employed toperform Work under this Contract for more than ten (10)hours in any one day or forty (40) hours in any one week,

Page 13: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 13/26

 

CM/GC Contract Form (4/09) (574022)

except in cases of necessity, emergency or where publicpolicy absolutely requires it. In such instances, Contractorshall pay the employee at least time and a half pay:

(a) For all overtime in excess of eight (8) hours aday or forty (40) hours in any one week whenthe work week is five consecutive Days,Monday through Friday; or

(b) For all overtime in excess of ten (10) hours aday or forty (40) hours in any one week whenthe work week is four consecutive Days,Monday through Friday; and

(c) For all Work performed on Saturday and on anylegal holiday specified in ORS 279C.540.

This section C.5 will not apply to Contractor's Work underthis Contract if Contractor is currently a party to a collectivebargaining agreement with any labor organization.

This Section C.5 shall not excuse Contractor fromcompletion of the Work within the time required under thisContract.

SECTION DCHANGES IN THE WORK 

D.1 CHANGES IN WORK

D.1.1 The terms of this Contract shall not be waived,altered, modified, supplemented or amended in anymanner whatsoever without prior written approval ofthe Owner's Authorized Representative, and thenonly in a manner consistent with the Change Orderprovisions of this Section D.1 and after anynecessary approvals required by public contractinglaws have been obtained. Otherwise, a formalcontract amendment is required, which shall not beeffective until its execution by the parties to thisContract and all approvals required by publiccontracting laws have been obtained.

D.1.2 It is mutually agreed that changes in Plans,quantities, or details of construction are inherent in

the nature of construction and may be necessary ordesirable during the course of construction. Withinthe general scope of this Contract, the Owner'sAuthorized Representative may at any time, withoutnotice to the sureties and without impairing theContract, require changes consistent with thisSection D.1. All Change Order Work shall beexecuted under the conditions of the ContractDocuments. Such changes may include, but are notlimited to:

(a) Modification of specifications and design.

(b) Increases or decreases in quantities.

(c) Increases or decreases to the amount of

Work.

(d) Addition or elimination of any Work item.

(e) Change in the duration of the project.

(f) Acceleration or delay in performance ofWork.

(g) Deductive changes.

Deductive changes are those that reduce thescope of the Work, and shall be made by mutualagreement whenever feasible. In cases ofsuspension or partial termination under Section

J, Owner reserves the right to unilaterallyimpose a deductive change and to self performsuch Work, for which the provisions of B.13(Owner’s Right to Do Work) shall then apply.

Adjustments in compensation shall be madeunder the provisions of D.1.3, in which costs fordeductive changes shall be based upon a DirectCosts adjustment together with the relatedpercentage markup specified for profit,Overhead and other indirect costs, unlessotherwise agreed to by Owner.

D.1.3 The Owner and Contractor agree that Change OrderWork shall be administered and compensatedaccording to the following:

(a) Unit pricing may be utilized at the Owner’soption when unit prices or solicitation alternateswere provided that established the cost foradditional Work, and a binding obligation existsunder the Contract on the parties covering theterms and conditions of the additional Work.

(b) If the Owner elects not to utilize unit pricing, orin the event that unit pricing is not available orappropriate, fixed pricing may be used forChange Order Work. In fixed pricing the basisof payments or total price shall be agreed upon

in writing between the parties to the Contract,and shall be established before the Work isdone whenever feasible. The mark-ups setforth in D.1.3(c) shall be utilized by the partiesas a guide in establishing fixed pricing, and willnot be exceeded by Owner without adequate

 justification. Cost and price data relating toChange Orders shall be supplied by Contractorto Owner upon request, but Owner shall beunder no obligation to make such requests.

(c) In the event that unit pricing and fixed pricingare not utilized, then Change Order Work shallbe performed on a cost reimbursement basis forDirect Costs. Such Work shall be compensatedon the basis of the actual, reasonable andallowable cost of labor, equipment, and material

furnished on the Work performed. In addition,the following markups shall be added to theContractor's or Subcontractor's Direct Costs asfull compensation for profit, Overhead and otherindirect costs for Work directly performed withthe Contractor’s or Subcontractor’s own forces:

On Labor..................... 15%On Equipment.............. 10%On Materials................. 10%

When Change Order Work under D.1.3(c) is invoicedby an authorized Subcontractor at any level, eachascending tier Subcontractor or Contractor will beallowed a supplemental mark-up on each piece ofsubcontract Work covered by such Change Order as

follows:

$0.00 - $5,000.00 10%, and thenOver $5,000.00 5%

Payments made to the Contractor shall be completecompensation for Overhead, profit, and all costs thatwere incurred by the Contractor or by other forcesfurnished by the Contractor, includingSubcontractors, for Change Order Work. Ownermay establish a maximum cost for Change OrderWork under this Section D.1.3(c), which shall not beexceeded for reimbursement without additionalwritten authorization from Owner. Contractor shall

Page 14: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 14/26

 

CM/GC Contract Form (4/09) (574022)

not be required to complete such Change OrderWork without additional authorization.

D.1.4 Any necessary adjustment of Contract Time that maybe required as a result of a Change Order must beagreed upon by the parties before the start of theChange Order Work unless Owner’s AuthorizedRepresentative authorizes Contractor to start theWork before agreement on Contract Timeadjustment. Contractor shall submit any request foradditional compensation (and additional ContractTime if Contractor was authorized to start Workbefore an adjustment of Contract Time wasapproved) as soon as possible but no later than thirty(30) Days after receipt of the Change Order. IfContractor’s request for additional compensation oradjustment of Contract Time is not made within thethirty (30) day time limit, Contractor’s requestspertaining to that Change Order are barred. Thethirty (30) day time limit for making requests shall notbe extended for any reason, including withoutlimitation Contractor’s claimed inability to determinethe amount of additional compensation or adjustmentof Contract Time, unless an extension is granted inwriting by Owner. If the Owner’s AuthorizedRepresentative denies Contractor’s request foradditional compensation or adjustment of ContractTime, Contractor may proceed to file a Claim underSection D.3, Claims Review Process. No other

reimbursement, compensation, or payment will bemade, except as provided in Section D.1.5 for impactclaims.

D.1.5 If any Change Order Work under Section D.1.3causes an increase or decrease in the Contractor'scost of, or the Contract Time required for theperformance of, any other part of the Work under thisContract, the Contractor must submit a writtenrequest to the Owner’s Authorized Representative,setting forth the nature and specific extent of therequest, including all time and cost impacts againstthe Contract as soon as possible, but no later thanthirty (30) Days after receipt of the Change Order byContractor.

The thirty (30) day time limit applies to claims of

Subcontractors, suppliers, or manufacturers that maybe affected by the Change Order and that requestadditional compensation or an extension of ContractTime to perform; Contractor has responsibility forcontacting its Subcontractors, suppliers, ormanufacturers within the thirty (30) day time limit,and including their requests with Contractor’srequests. If the request involves Work to becompleted by Subcontractors, or materials to befurnished by suppliers or manufacturers, suchrequests shall be submitted to the Contractor inwriting with full analysis and justification for thecompensation and additional Contract Timerequested. The Contractor will analyze and evaluatethe merits of the requests submitted bySubcontractors, suppliers, and manufacturers to

Contractor prior to including those requests andContractor’s analysis and evaluation of thoserequests with Contractor’s requests for additionalcompensation or Contract Time that Contractorsubmits to the Owner’s Authorized Representative.Failure of Subcontractors, suppliers, manufacturersor others to submit their requests to Contractor forinclusion with Contractor’s requests submitted toOwner’s Authorized Representative within the timeperiod and by the means described in this sectionshall constitute a waiver of these Subcontractorclaims. The Owner’s Authorized Representative andthe Owner will not consider direct requests or claimsfrom Subcontractors, suppliers, manufacturers orothers not a party to this Contract. The consideration

of such requests and claims under this section doesnot give any person, not a party to the Contract theright to bring a claim against the State of Oregon,whether in this claims process, in litigation, or in anydispute resolution process.

If the Owner’s Authorized Representative denies theContractor’s request for additional compensation oran extension of Contract Time, the Contractor mayproceed to file a Claim under Section D.3, ClaimsReview Process.

D.1.6 No request or Claim by the Contractor for additionalcosts or an extension of Contract Time shall beallowed if made after receipt of final paymentapplication under this Contract. Contractor agrees tosubmit its final payment application within ninety (90)days after Substantial Completion, unless writtenextension is granted by Owner. Contractor shall notdelay final payment application for any reason,including without limitation nonpayment ofSubcontractors, suppliers, manufacturers or othersnot a party to this Contract, or lack of resolution of adispute with Owner or any other person of mattersarising out of or relating to the Contract. IfContractor fails to submit its final paymentapplication within ninety (90) days after SubstantialCompletion, and Contractor has not obtained writtenextension by Owner, all requests or Claims for

additional costs or an extension of Contract Timeshall be waived.

D.1.7 It is understood that changes in the Work areinherent in construction of this type. The number ofchanges, the scope of those changes, and the effectthey have on the progress of the original Workcannot be defined at this time. The Contractor isnotified that numerous changes may be required andthat there will be no compensation made to theContractor directly related to the number of changes.Each change will be evaluated for extension ofContract Time and increase or decrease incompensation based on its own merit.

D.2 DELAYS

D.2.1 Delays in construction include “Avoidable Delays”,which are defined in Section D.2.1.1, and“Unavoidable Delays”, which are defined in SectionD.2.1.2. The effect of Avoidable Delays is describedin Section D.2.2 and the effect of UnavoidableDelays is described in Section D.2.3.

D.2.1.1 Avoidable Delays include any delays other thanUnavoidable Delays, and include delays thatotherwise would be considered Unavoidable Delaysbut that:

(a) Could have been avoided by the exercise ofcare, prudence, foresight, and diligence on thepart of the Contractor or its Subcontractors.

(b) Affect only a portion of the Work and do notnecessarily prevent or delay the prosecution ofother parts of the Work nor the completion ofthe whole Work within the Contract Time.

(c) Do not impact activities on the accepted criticalpath schedule.

(d) Are associated with the reasonable interferenceof other contractors employed by the Ownerthat do not necessarily prevent the completionof the whole Work within the Contract Time.

D.2.1.2 Unavoidable Delays include delays other thanAvoidable Delays that are:

Page 15: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 15/26

 

CM/GC Contract Form (4/09) (574022)

(a) Caused by any actions of the Owner, Owner’sAuthorized Representative, or any otheremployee or agent of the Owner, or by separatecontractor employed by the Owner.

(b) Caused by any site conditions which differmaterially from what was represented in theContract Documents or from conditions thatwould normally be expected to exist and beinherent to the construction activities defined inthe Contract Documents. The Contractor shallnotify the Owner’s Authorized Representativeimmediately of differing site conditions beforethe area has been disturbed. The Owner’sAuthorized Representative will investigate thearea and make a determination as to whether ornot the conditions differ materially from eitherthe conditions stated in the Contract Documentsor those which could reasonably be expected inexecution of this particular Contract. IfContractor and the Owner’s AuthorizedRepresentative agree that a differing sitecondition exists, any additional compensation oradditional Contract Time will be determinedbased on the process set forth in Section D.1.5for Change Order Work. If the Owner’sAuthorized Representative disagrees that adiffering site condition exists and denies

Contractor’s request for additionalcompensation or Contract Time, Contractormay proceed to file a Claim under Section D.3,Claims Review Process.

(c) Caused by Force Majeure acts, events oroccurrences that could not have been avoidedby the exercise of care, prudence, foresight,and diligence on the part of the Contractor or itsSubcontractors.

(d) Caused by adverse weather conditions. Anyadverse weather conditions must besubstantiated by documentary evidence thatweather conditions were abnormal for thespecific time period claimed, could not havebeen anticipated by the Contractor, and

adversely impacted the project in a manner thatcould not be avoided by rescheduling the Workor by implementing measures to protect againstthe weather so that the Work could proceed. Arain, windstorm, high water, or other naturalphenomenon for the specific locality of theWork, which might reasonably have beenanticipated from the previous 10-year historicalrecords of the general locality of the Work, shallnot be construed as abnormal. The partiesagree that rainfall greater than the followinglevels cannot be reasonably anticipated:

(i) Daily rainfall equal to, or greater than,0.50 inch during a month when the monthlyrainfall exceeds the normal monthly average

by twenty-five percent (25 %) or more.

(ii) daily rainfall equal to, or greater than,0.75 inch at any time.

The Office of the Environmental Data Service of theNational Oceanic and Atmospheric Administration ofthe U.S. Department of Commerce nearest theproject site shall be considered the official agency ofrecord for weather information.

D.2.2 Except as otherwise provided in ORS 279C.315,Contractor shall not be entitled to additionalcompensation or additional Contract Time forAvoidable Delays.

D.2.3 In the event of Unavoidable Delays, based onprinciples of equitable adjustment, Contractor maybe entitled to the following:

(a) Contractor may be entitled to additionalcompensation or additional Contract Time, orboth, for Unavoidable Delays described inSection D.2.1.2 (a) and (b).

(b) Contractor may be entitled to additionalContract Time for Unavoidable Delaysdescribed in Section D.2.1.2(c) and (d).

In the event of any requests for additionalcompensation or additional Contract Time, or both,as applicable, arising under this Section D.2.3 forUnavoidable Delays, other than requests foradditional compensation or additional Contract Timefor differing site conditions for which a reviewprocess is established under Section D.2.1.2 (b),Contractor shall submit a written notification of thedelay to the Owner’s Authorized Representativewithin two (2) Days of the occurrence of the cause ofthe delay. This written notification shall state thecause of the potential delay, the project componentsimpacted by the delay, and the anticipated additionalContract Time or the additional compensation, orboth, as applicable, resulting from the delay. Within

seven (7) Days after the cause of the delay has beenmitigated, or in no case more than thirty (30) Daysafter the initial written notification, the Contractorshall submit to the Owner’s AuthorizedRepresentative, a complete and detailed request foradditional compensation or additional Contract Time,or both, as applicable, resulting from the delay.If the Owner’s Authorized Representative deniesContractor’s request for additional compensation oradjustment of Contract Time, the Contractor mayproceed to file a Claim under Section D.3, ClaimsReview Process.

If Contractor does not timely submit the noticesrequired under this Section D.2., then unlessotherwise prohibited by law, Contractor’s Claim shallbe barred.

D.3 CLAIMS REVIEW PROCESS 

D.3.1 All Contractor Claims shall be referred to theOwner’s Authorized Representative for review.Contractor’s Claims, including Claims for additionalcompensation or additional Contract Time, shall besubmitted in writing by Contractor to the Owner’sAuthorized Representative within five (5) Days aftera denial of Contractor’s initial request for anadjustment of Contract terms, payment of money,extension of Contract Time or other relief, providedthat such initial request has been submitted inaccordance with the requirements and within thetime limits established in these General Conditions.Within thirty (30) Days after the initial Claim,

Contractor shall submit to the Owner’s AuthorizedRepresentative, a complete and detailed descriptionof the Claim (the “Detailed Notice”) that includes allinformation required by Section D.3.2. Unless theClaim is made in accordance with these timerequirements, it shall be waived.

D.3.2 The Detailed Notice of the Claim shall be submittedin writing by Contractor and shall include a detailed,factual statement of the basis of the Claim, pertinentdates, Contract provisions which support or allow theClaim, reference to or copies of any documentswhich support the Claim, the dollar value of theClaim, and the Contract Time extension requestedfor the Claim. If the Claim involves Work to be

Page 16: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 16/26

 

CM/GC Contract Form (4/09) (574022)

completed by Subcontractors, the Contractor willanalyze and evaluate the merits of the Subcontractorclaim prior to forwarding it and that analysis andevaluation to the Owner’s AuthorizedRepresentative. The Owner’s AuthorizedRepresentative and the Owner will not considerdirect claims from Subcontractors, suppliers,manufacturers, or others not a party to this Contract.Contractor agrees that it will make no agreement,covenant, or assignment, nor will it commit any otheract that will permit or assist any Subcontractor,supplier, manufacturer, or other to directly orindirectly make a claim against Owner.

D.3.3 The Owner’s Authorized Representative will reviewall Claims and take one or more of the followingpreliminary actions within ten (10) Days of receipt ofthe Detailed Notice of a Claim: (1) request additionalsupporting information from the Contractor; (2)inform the Contractor and Owner in writing of thetime required for adequate review and response; (3)reject the Claim in whole or in part and identify thereasons for rejection; (4) based on principles ofequitable adjustment, recommend approval of all orpart of the Claim; or (5) propose an alternateresolution.

D.3.4 The Owner’s Authorized Representative’s decisionshall be final and binding on the Contractor unless

appealed by written notice to the Owner within fifteen(15) Days of receipt of the decision. The Contractormust present written documentation supporting theClaim within fifteen (15) Days of the notice of appeal.After receiving the appeal documentation, the Ownershall review the materials and render a decisionwithin thirty (30) Days after receiving the appealdocuments.

D.3.5 The decision of the Owner shall be final and bindingunless the Contractor delivers to the Owner itsrequests for mediation, which shall be a non-bindingprocess, within fifteen (15) Days of the date of theOwner's decision. The mediation process will beconsidered to have commenced as of the date theContractor delivers the request. Both partiesacknowledge and agree that participation in

mediation is a prerequisite to commencement oflitigation of any disputes relating to the Contract.Both parties further agree to exercise their bestefforts in good faith to resolve all disputes within sixty(60) Days of the commencement of the mediationthrough the mediation process set forth herein.

In the event that a lawsuit must be filed within thissixty (60) day period in order to preserve a cause ofaction, the parties agree that notwithstanding thefiling, they shall proceed diligently with the mediationto its conclusion prior to actively prosecuting thelawsuit, and shall seek from the Court in which thelawsuit is pending such stays or extensions,including the filing of an answer, as may benecessary to facilitate the mediation process.

Further, in the event settlements are reached on anyissues through mediation, the parties agree topromptly submit the appropriate motions and ordersdocumenting the settlement to the Court for itssignature and filing.

D.3.6 The mediator shall be an individual mutuallyacceptable to both parties, but in the absence ofagreement each party shall select a temporarymediator and the temporary mediators shall jointlyselect the permanent mediator. Each party shall payits own costs for the time and effort involved inmediation. The cost of the mediator shall be splitequally between the two parties. Both parties agreeto exercise their best effort in good faith to resolve all

disputes in mediation. Participation in mediation is amandatory requirement of both the Owner and theContractor. The schedule, time and place formediation will be mutually acceptable, or, failingmutual agreement, shall be as established by themediator. The parties agree to comply with Owner'sadministrative rules governing the confidentiality ofmediation, if any, and shall execute all necessarydocuments to give effect to such confidentiality rules.In any event, the parties shall not subpoena themediator or otherwise require the mediator toproduce records, notes or work product, or to testifyin any future proceedings as to information disclosedor representations made in the course of mediation,except to the extent disclosure is required by law.

D.3.7 Unless otherwise directed by Owner’s AuthorizedRepresentative, Contractor shall proceed with theWork while any Claim of Contractor is pending,including a Claim for additional compensation oradditional Contract Time resulting from ChangeOrder Work. Regardless of the review period or thefinal decision of the Owner's AuthorizedRepresentative, the Contractor shall continue todiligently pursue the Work as identified in theContract Documents. In no case is the Contractor

 justified or allowed to cease Work without a writtenstop work order from the Owner or Owner'sAuthorized Representative.

SECTION EPAYMENTS 

E.1 SCHEDULE OF VALUES 

The Contractor shall submit, at least ten (10) Days priorto submission of its first application for progress payment, aschedule of values ("Schedule of Values") for the contractedWork. This schedule will provide a breakdown of values forthe contracted Work and will be the basis for progresspayments. The breakdown will demonstrate reasonable,identifiable, and measurable components of the Work.Unless objected to by the Owner's AuthorizedRepresentative, this schedule shall be used as the basis forreviewing Contractor's applications for payment. If objected

to by Owner’s Authorized Representative, Contractor shallrevise the schedule of values and resubmit the same forapproval of Owner’s Authorized Representative.

E.2 APPLICATIONS FOR PAYMENT

E.2.1 Owner shall make progress payments on theContract monthly as Work progresses. Paymentsshall be based upon estimates of Work completedand the Schedule of Values. All payments shall beapproved by the Owner's Authorized Representative.A progress payment shall not be consideredacceptance or approval of any Work or waiver of anydefects therein. Owner shall pay to Contractorinterest on the progress payment, not includingretainage, due the Contractor. The interest shall

commence thirty (30) Days after the receipt ofinvoice (“application for payment”) from theContractor or fifteen (15) Days after the payment isapproved by the Owner's Authorized Representative,whichever is the earlier date. The rate of interestshall equal three times the discount rate on 90-daycommercial paper in effect at the Federal ReserveBank in the Federal Reserve district that includesOregon on the date that is thirty (30) Days afterreceipt of the application for payment from theContract or fifteen (15) Days after the payment isapproved by the Owner, whichever is the earlierdate, but the rate of interest shall not exceed thirty(30) percent. Notwithstanding the foregoing, ininstances when an application for payment is filled

Page 17: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 17/26

 

CM/GC Contract Form (4/09) (574022)

out incorrectly, or when there is any defect orimpropriety in any submitted application or whenthere is a good faith dispute, Owner shall so notifythe Contractor within fifteen (15) Days stating thereason or reasons the application for payment isdefective or improper or the reasons for the dispute.A defective or improper application for payment, ifcorrected by the Contractor within seven (7) Days ofbeing notified by the Owner, shall not cause apayment to be made later than specified in thissection unless interest is also paid. Accrual ofinterest will be postponed when payment on theprincipal is delayed because of disagreementbetween the Owner and the Contractor.

E.2.2 Contractor shall submit to the Owner's AuthorizedRepresentative, an application for each paymentand, if required, receipts or other vouchers showingpayments for materials and labor, includingpayments to Subcontractors. Contractor shallinclude, in its application for payment, a schedule ofthe percentages of the various parts of the Workcompleted, based on the Schedule of Values whichshall aggregate to the payment application total, andshall include, on the face of each copy thereof, acertificate in substantially the following form:

"I, the undersigned, hereby certify that the abovebill is true and correct, and the payment therefore,

has not been received.

Signed: _________________________________”

E.2.3 Generally, applications for payment will be acceptedonly for materials that have been installed. Underspecial conditions, applications for payment forstored materials will be accepted at Owner's solediscretion. Such a payment, if made, will be subjectto the following conditions:

(a) The request for stored material shall besubmitted at least thirty (30) Days in advance ofthe application for payment on which it appears.Applications for payment shall be entertainedfor major equipment, components or

expenditures only.

(b) The Contractor shall submit applications forpayment showing the quantity and cost of thematerial stored.

(c) The material shall be stored in a bondedwarehouse and Owner's AuthorizedRepresentative shall be granted the right toaccess the material for the purpose of removalor inspection at any time during the ContractPeriod.

(d) The Contractor shall name the Owner as co-insured on the insurance policy covering the fullvalue of the property while in the care and

custody of the Contractor until it is installed. Acertificate noting this coverage shall be issuedto the Owner.

(e) Payments shall be made for materials only.The submitted amount of the application forpayment shall be reduced by the cost oftransportation and for the cost of an inspector tocheck the delivery at out of town storage sites.The cost of said inspection shall be borne solelyby the Contractor.

(f) Within sixty (60) Days of the application forpayment, the Contractor shall submit evidenceof payment covering the material stored.

(g) Payment for stored materials shall in no wayindicate acceptance of the materials or waiveany rights under this Contract for the rejectionof the Work or materials not in conformancewith the Contract Documents.

(h) All required documentation must be submittedwith the respective application for payment.

E.2.4 The Owner reserves the right to withhold all or part ofa payment, or may nullify in whole or part anypayment previously made, to such extent as may benecessary in the Owner’s opinion to protect theOwner from loss because of:

(a) Work that is defective and not remedied, or thathas been demonstrated or identified as failing toconform with the Contract Documents,

(b) third party claims filed or evidence reasonablyindicating that such claims will likely be filedunless security acceptable to the Owner isprovided by the Contractor;

(c) failure of the Contractor to make paymentsproperly to Subcontractors or for labor,materials or equipment (in which case Ownermay issue checks made payable jointly to

Owner and such unpaid persons under thisprovision, or directly to Subcontractors andsuppliers at any level under Section C.3.2.1);

(d) reasonable evidence that the Work cannot becompleted for the unpaid balance of theContract Price;

(e) damage to the Owner or another contractor;

(f) reasonable evidence that the Work will not becompleted within the Contract Time required bythe Contract, and that the unpaid balance wouldnot be adequate to cover actual or liquidateddamages for the anticipated delay;

(g) failure to carry out the Work in accordance with

the Contract Documents; or

(h) assessment of liquidated damages, whenwithholding is made for offset purposes.

E.2.5 Subject to the provisions of the Contract Documents,the amount of each progress payment shall becomputed as follows:

(a) Take that portion of the Contract Price properlyallocable to completed Work as determined bymultiplying the percentage completion of eachportion of the Work by the share of the totalContract Price allocated to that portion of theWork in the Schedule of Values, less retainageas provided in Section E.5. Pending final

determination of cost to the Owner of changesin the Work, amounts not in the dispute may beincluded even though the Contract Price hasnot yet been adjusted by Change Order;

(b) Add that portion of the Contract Price properlyallocable to materials and equipment deliveredand suitably stored at the site for subsequentincorporation in the completed construction (or,if approved in advance by the Owner pursuantto Section E.2.3, suitably stored off the site at alocation agreed upon in writing), less retainageas provided in Section E.5;

Page 18: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 18/26

 

CM/GC Contract Form (4/09) (574022)

(c) Subtract the aggregate of previous paymentsmade by the Owner; and

(d) Subtract any amounts for which the Owner’sAuthorized Representative has withheld ornullified payment as provided in the ContractDocuments.

E.2.6 Contractor’s applications for payment may notinclude requests for payment for portions of the Workfor which the Contractor does not intend to pay to aSubcontractor or material supplier.

E.2.7 The Contractor warrants to Owner that title to allWork covered by an application for payment will passto the Owner no later than the time of payment. TheContractor further warrants that upon submittal of anapplication for payment all Work for which paymentsare received from the Owner shall be free and clearof liens, claims, security interests or encumbrancesin favor of the Contractor, Subcontractors, materialsuppliers, or other persons or entities making a claimby reason of having provided labor, materials andequipment relating to the Work.

E.2.8 If Contractor disputes any determination by Owner’sAuthorized Representative with regard to anyapplication for payment, Contractor neverthelessshall continue to prosecute expeditiously the Work.

No payment made hereunder shall be or beconstrued to be final acceptance or approval of thatportion of the Work to which such partial paymentrelates or shall relieve Contractor of any of itsobligations hereunder.

E.3 PAYROLL CERTIFICATION REQUIREMENT

Payroll certification is required before payments aremade on the Contract. Refer to Section C.2 for thisinformation.

E.4 DUAL PAYMENT SOURCES

Contractor shall not be compensated for Workperformed under this Contract from any state agency otherthan the agency that is a party to this Contract. 

E.5 RETAINAGE

E.5.1 Retainage shall be withheld and released inaccordance with ORS 279C.550 to 279C.580:

E.5.1.1 Owner may reserve as retainage from anyprogress payment an amount not to exceed fivepercent of the payment. As Work progresses,Owner may reduce the amount of the retainageand may eliminate retainage on any remainingmonthly Contract payments after 50 percent ofthe Work under the Contract is completed if, inthe Owner's opinion, such Work is progressingsatisfactorily. Elimination or reduction ofretainage shall be allowed only upon written

application by the Contractor, which applicationshall include written approval of Contractor'ssurety; except that when the Work is 97-1/2percent completed the Owner may, at itsdiscretion and without application by theContractor, reduce the retained amount to 100percent of the value of the Work remaining to bedone. Upon receipt of written application by theContractor, Owner shall respond in writing withina reasonable time.

E.5.1.2 In accordance with the provisions of ORS279C.560 and any applicable administrativerules, Contractor may request in writing:

(a) to be paid amounts which would otherwise havebeen retained from progress payments whereContractor has deposited acceptable bonds andsecurities of equal value with Owner or in acustodial account or other mutually-agreedaccount satisfactory to Owner, with anapproved bank or trust company to be held inlieu of the cash retainage for the benefit ofOwner;

(b) that retainage be deposited in an interestbearing account, established through the StateTreasurer for state agencies, in a bank, savingsbank, trust company or savings association forthe benefit of Owner, with earnings from suchaccount accruing to the Contractor; or

(c) that the Owner allow Contractor to deposit asurety bond for the benefit of Owner, in a formacceptable to Owner, in lieu of all or a portion offunds retained, or to be retained. Such bondand any proceeds therefrom shall be madesubject to all claims and liens in the manner andpriority as set forth for retainage under ORS279C.550 to ORS 279C.625.

Where the Owner has accepted the Contractor'selection of option (a) or (b), Owner may recover fromContractor any additional costs incurred through such

election by reducing Contractor's final payment. Wherethe Owner has agreed to Contractor's request for option(c), Contractor shall accept like bonds fromSubcontractors and suppliers on the project from whichContractor has required retainages.

E.5.1.3 The retainage held by Owner shall be includedin and paid to the Contractor as part of the finalpayment of the Contract Price. The Owner shallpay to Contractor interest at the rate of one andone-half percent per month on the final paymentdue Contractor, interest to commence thirty (30)Days after the Work under the Contract hasbeen completed and accepted and to run untilthe date Contractor shall notify Owner in writingwhen the Contractor considers the Workcomplete and Owner shall, within fifteen (15)

Days after receiving the written notice, eitheraccept the Work or notify the Contractor ofWork yet to be performed on the Contract. IfOwner does not within the time allowed notifythe Contractor of Work yet to be performed tofulfill contractual obligations, the interestprovided by this subsection shall commence torun thirty (30) Days after the end of the 15-Dayperiod.

E.5.1.4 In accordance with the provisions of ORS279C.560, Owner shall reduce the amount of theretainage if the Contractor notifies the controllerof the Owner that the Contractor has depositedin an escrow account with a bank or trustcompany, in a manner authorized by the

Owner's Authorized Representative, bonds andsecurities of equal value of a kind approved bythe Owner's Authorized Representative.

E.5.1.5 Contractor agrees that if Contractor elects toreserve a retainage from any progress paymentdue to any Subcontractor or supplier, suchretainage shall not exceed five percent of thepayment, and such retainage withheld fromSubcontractors and suppliers shall be subject tothe same terms and conditions stated inSubsection E.5 as apply to Owner’s retainagefrom any progress payment due to Contractor.

Page 19: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 19/26

 

CM/GC Contract Form (4/09) (574022)

E.5.2 As provided in subsections C.2.2 and C.2.3,additional retainage in the amount of 25% ofamounts earned shall be withheld and released inaccordance with ORS 279C.845(7) when theContractor fails to file certified statements asrequired by section C.2.1.

E.6 FINAL PAYMENT

E.6.1 Upon completion of all the Work under this Contract,the Contractor shall notify the Owner's AuthorizedRepresentative, in writing, that Contractor hascompleted Contractor's part of the Contract and shallrequest final payment. Upon receipt of such noticethe Owner's Authorized Representative will inspectthe Work, and if acceptable, submit to the Owner arecommendation as to acceptance of the completedWork and as to the final estimate of the amount duethe Contractor. If the Work is not acceptable, Ownerwill notify Contractor within fifteen (15) Days ofContractor's request for final payment. Uponapproval of this final estimate by the Owner andcompliance by the Contractor with provisions inSection K. 3 AFFIDAVIT/RELEASE OF LIENS ANDCLAIMS, and other provisions as may be applicable,the Owner shall pay to the Contractor all monies dueunder the provisions of these Contract Documents.

E.6.2 Neither final payment nor any remaining retained

percentage shall become due until the Contractorsubmits to the Owner’s Authorized Representative(1) a notarized affidavit/release of liens and claims ina form satisfactory to Owner that states that payrolls,bills for materials and equipment, and otherindebtedness connected with the Work for which theOwner or the Owner's property might be responsibleor encumbered (less amounts withheld by Owner)have been paid or otherwise satisfied, (2) acertificate evidencing that insurance required by theContract Documents to remain in force after finalpayment is currently in effect and will not becanceled or allowed to expire until at least thirty (30)Days' prior written notice has been given to theOwner, (3) a written statement that the Contractorknows of no substantial reason that the insurancewill not be renewable to cover the period required by

the Contract Documents, (4) consent of surety, ifany, to final payment and (5), if required by theOwner, other data establishing payment orsatisfaction of obligations, such as receipts, releasesand waivers of liens, claims, security interests orencumbrances arising out of the Contract, to theextent and in such form as may be designated by theOwner. If a Subcontractor refuses to furnish arelease or waiver required by the Owner, theContractor may furnish a bond satisfactory to theOwner to indemnify the Owner against such lien. Ifsuch lien remains unsatisfied after payments aremade, the Contractor shall refund to the Owner allmoney that the Owner may be compelled to pay indischarging such lien, including all costs andreasonable attorneys' fees.

E.6.3 Acceptance of final payment by the Contractor, aSubcontractor or material supplier shall constitute awaiver of claims by that payee except thosepreviously made in writing and identified by thatpayee as unsettled at the time of final application forpayment.

SECTION F JOB SITE CONDITIONS  

F.1 USE OF PREMISES

Contractor shall confine equipment, storage ofmaterials and operation of Work to the limits indicated byContract Documents, law, ordinances, permits or directionsof the Owner's Authorized Representative. Contractor shallfollow the Owner's Authorized Representative's instructionsregarding use of premises, if any.

F.2 PROTECTION OF WORKERS, PROPERTY, AND THEPUBLIC

F.2.1 Contractor shall maintain continuous and adequateprotection of all of the Work from damage, and shallprotect the Owner's Authorized Representative,Owner's workers and property from injury or lossarising in connection with this Contract. Contractorshall remedy acceptably to the Owner, any damage,injury, or loss, except such as may be directly due toerrors in the Contract Documents or caused byauthorized representatives or personnel of theOwner. Contractor shall adequately protect adjacentproperty as provided by law and the ContractDocuments.

F.2.2 Contractor shall take all necessary precautions forthe safety of all personnel on the job site, and shallcomply with the Contract Documents and allapplicable provisions of federal, state and municipalsafety laws and building codes to prevent accidentsor injury to persons on, about or adjacent to the

premises where the Work is being performed.Contractor shall erect and properly maintain at alltimes, as required by the conditions and progress ofthe Work, all necessary safeguards for protection ofworkers and the public against any hazards createdby construction. Contractor shall designate aresponsible employee or associate on the Work site,whose duty shall be the prevention of accidents. Thename and position of the person designated shall bereported to the Owner's Authorized Representative.The Owner's Authorized Representative has noresponsibility for Work site safety. Work site safety isthe responsibility of the Contractor.

F.2.3 Contractor shall not enter upon private propertywithout first obtaining permission from the propertyowner or its duly authorized representative.

Contractor shall be responsible for the preservationof all public and private property along and adjacentto the Work contemplated under the Contract andshall use every precaution necessary to preventdamage thereto. In the event the Contractordamages any property, the Contractor shall at oncenotify the property owner and make, or arrange tomake, full restitution. Contractor shall report,immediately in writing, to the Owner's AuthorizedRepresentative, all pertinent facts relating to suchproperty damage and the ultimate disposition of theclaim for damage.

F.2.4 Contractor is responsible for protection of adjacentwork areas including impacts brought about byactivities, equipment, labor, utilities, and materials on

the site.

F.2.5 Contractor shall at all times direct its activities insuch a manner as to minimize adverse effects on theenvironment. Handling of all materials will beconducted so no release will occur that may polluteor become hazardous.

F.2.6 In an emergency affecting the safety of life or of theWork or of adjoining property, the Contractor, withoutspecial instruction or authorization from the Owner'sAuthorized Representative, shall act reasonably toprevent threatened loss or injury, and shall so act,without appeal, if instructed by the Owner'sAuthorized Representative. Any compensation

Page 20: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 20/26

 

CM/GC Contract Form (4/09) (574022)

claimed by the Contractor on account of emergencywork shall be determined in accordance withSection D.

F.3 CUTTING AND PATCHING

F.3.1 Contractor shall be responsible for coordinating allcutting, fitting, or patching of the Work to make itsseveral parts come together properly and fit toreceive or be received by work of other contractorsor Subcontractors shown upon, or reasonablyimplied by, the Contract Documents.

F.3.2 Contractor shall be responsible for restoring all cut,fitted, or patched surfaces to an original condition;provided, however, that if a different condition isspecified in the Contract Documents, then Contractorshall be responsible for restoring such surfaces tothe condition specified in the Contract Documents.

F.4 CLEANING UP

From time to time as may be ordered by the Ownerthe Contractor shall, at its own expense, clean up andremove all refuse and unused materials of any kind resultingfrom the Work. If Contractor fails to do so within twenty-fourhours after notification by the Owner the work may be doneby others and the cost charged to the Contractor anddeducted from payment due the Contractor.

F.5 ENVIRONMENTAL CONTAMINATION

F.5.1 Contractor will be held responsible for and shallindemnify, defend (with counsel of Owner’s choice)and hold harmless Owner from and against anycosts, expenses, damages, claims, and causes ofaction, (including attorney fees), or any of them,resulting from all spills, releases, discharges, leaksand disposal of environmental pollution, includingstorage, transportation, and handling during theperformance of the Contract which occur as a resultof, or are contributed by, the negligence or actions ofContractor or its personnel, agents, orSubcontractors or any failure to perform inaccordance with the Contract Documents (except tothe extent otherwise void under ORS 30.140).

Nothing in this section F.5.1 shall limit Contractor'sresponsibility for obtaining insurance coveragesrequired under Section G.3 of these GeneralConditions, and Contractor shall take no action thatwould void or impair such coverages

F.5.1.1 Contractor agrees to promptly dispose of suchspills, releases, discharge or leaks to thesatisfaction of Owner and proper regulatoryagencies in a manner that complies withapplicable federal, state, and local laws andregulations. Cleanup shall be at no cost to theOwner and be performed by properly qualifiedpersonnel.

F.5.1.2 Contractor shall obtain the Owner's written

consent prior to bringing onto the Work site any(i) environmental pollutants or (ii) hazardoussubstances or materials, as the same orreasonably similar terms are used in anyapplicable federal, state, or local statutes, rulesor ordinances. Notwithstanding such writtenconsent from the Owner, the Contractor, at alltimes, shall:

(a) properly handle, use and dispose of allenvironmental pollutants and hazardoussubstances or materials brought onto the Worksite, in accordance with all applicable federal,state, or local statutes, rules, or ordinances;

(b) be responsible for any and all spills, releases,discharges, or leaks of (or from) environmentalpollutants or hazardous substances or materialswhich Contractor has brought onto the Worksite; and

(c) promptly clean up, without cost to the Owner,such spills, releases, discharges, or leaks to theOwner's satisfaction and in compliance with allapplicable federal, state, or local statutes, rulesor ordinances.

F.5.2 Contractor shall report all reportable quantityreleases to applicable federal, state, and localregulatory and emergency response agencies.Reportable quantities are found in 40 CFR Part 302,Table 302.4 for hazardous substances and in OARChapter 340 Division 108 for all products addressedtherein. Upon discovery, regardless of quantity,Contractor must telephonically report all releases tothe Owner. A written follow-up report shall besubmitted to Owner within 48 hours of the telephonicreport. Such written report shall contain, as aminimum:

(a) Description of items released (identity, quantity,manifest no., and all other documentationrequired by law.)

(b) Whether amount of items released is EPA/DEQreportable, and, if so, when it was reported.

(c) Exact time and location of release, including adescription of the area involved.

(d) Containment procedures initiated.

(e) Summary of communications about the releaseContractor has had with members of the pressor State officials other than Owner.

(f) Description of cleanup procedures employed orto be employed at the site, including disposallocation of spill residue.

(g) Personnel injuries, if any, resulting from, or

aggravated by, the release.

F.6 ENVIRONMENTAL CLEAN-UP

F.6.1 Unless disposition of environmental pollution isspecifically a part of this Contract, or was caused bythe Contractor (reference F.5 EnvironmentalContamination), Contractor shall immediately notifyOwner of any hazardous substance(s) whichContractor discovers or encounters duringperformance of the Work required by this Contract."Hazardous substance(s)" means any hazardous,toxic and radioactive materials and those substancesdefined as “hazardous substances,” “hazardousmaterials,” “hazardous wastes,” “toxic substances,”or other similar designations in any federal, state, or

local law, regulation, or ordinance, including withoutlimitation asbestos, polychlorinated biphenyl (PCB),or petroleum, and any substances, materials orwastes regulated in 40 CFR, Part 261 and defined ashazardous in 40 CFR S 261.3. In addition tonotifying Owner of any hazardous substance(s)discovered or encountered, Contractor shallimmediately cease working in any particular area ofthe project where a hazardous substance(s) hasbeen discovered or encountered if continued work insuch area would present a risk or danger to thehealth or well being of Contractor's or anySubcontractor's work force.

Page 21: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 21/26

 

CM/GC Contract Form (4/09) (574022)

F.6.2 Upon being notified by Contractor of the presence ofhazardous substance(s) on the project site, Ownershall arrange for the proper disposition of suchhazardous substance(s).

F.7 FORCE MAJEURE

A party to this Contract shall not be heldresponsible for delay or default due to Force Majeure acts,events or occurrences unless they could have been avoidedby the exercise of reasonable care, prudence, foresight, anddiligence by that party. The Owner may terminate thisContract upon written notice after determining that delay ordefault caused by Force Majeure acts, events oroccurrences will reasonably prevent successful performanceof the Contract.

SECTION GINDEMNITY, BONDING, AND INSURANCE 

G.1 RESPONSIBILITY FOR DAMAGES / INDEMNITY

G.1.1 Contractor shall be responsible for all damage toproperty, injury to persons, and loss, expense,inconvenience, and delay that may be caused by, orresult from, the carrying out of the Work to be doneunder this Contract, or from any act, omission or neglect of the Contractor, its Subcontractors,

personnel, or agents.

G.1.2 To the fullest extent permitted by law, Contractor shallindemnify, defend (with counsel approved by Owner)and hold harmless the Owner, Owner’s AuthorizedRepresentative, Architect/Engineer,Architect/Engineer’s consultants, and their respectiveofficers, directors, agents, employees, partners,members, stockholders and affiliated companies(collectively "Indemnitees") from and against allliabilities, damages, losses, claims, expenses(including reasonable attorney fees), demands andactions of any nature whatsoever which arise out of,result from or are related to, (a) any damage, injury,loss, expense, inconvenience or delay described inthis Section G.1.2, (b) any accident or occurrencewhich happens or is alleged to have happened in or

about the project site or any place where the Work isbeing performed, or in the vicinity of either, at any timeprior to the time the Work is fully completed in allrespects, (c) any failure of the Contractor to observe orperform any duty or obligation under the ContractDocuments which is to be observed or performed bythe Contractor, or any breach of any agreement,representation or warranty of the Contractor containedin the Contract Documents or in any subcontract,(d) the negligent acts or omissions of the Contractor, aSubcontractor or anyone directly or indirectlyemployed by them or any one of them or anyone forwhose acts they may be liable, regardless of whetheror not such claim, damage, loss or expense is causedin part by a party indemnified hereunder (except to theextent otherwise void under ORS 30.140), and (e) any

lien filed upon the project or bond claim in connectionwith the Work. Such obligation shall not be construedto negate, abridge, or reduce other rights orobligations of indemnity which would otherwise existas to a party or person described in this Section G.1.2.

G.1.3 In claims against any person or entity indemnifiedunder this Section G.1.2 by an employee of theContractor, a Subcontractor, anyone directly orindirectly employed by them or anyone for whose actsthey may be liable, the indemnification obligationunder Section G.1.2 shall not be limited by a limitationon amount or type of damages, compensation orbenefits payable by or for the Contractor or a

Subcontractor under workers' compensation acts,disability benefit acts or other employee benefit acts.

G.2 PERFORMANCE AND PAYMENT SECURITY;PUBLIC WORKS BOND

G.2.1 When the Contract Price is $100,000 or more (or$50,000 or more in the case of Contracts for highways,bridges and other transportation projects) theContractor shall furnish and maintain in effect at alltimes during the Contract Period, a performance bondin a sum equal to the Contract Price, and a separatepayment bond also in a sum equal to the ContractPrice. The bonds may be required if the ContractPrice is less than the above thresholds, if required bythe Contract Documents.

G.2.2 Bond forms furnished by the Owner and notarized byawarded Contractor's surety company authorized to dobusiness in Oregon are the only acceptable forms ofperformance and payment security, unless otherwisespecified in the Contract Documents.

G.2.3 Before starting Work the Contractor shall file with theConstruction Contractors Board, and maintain in fullforce and effect, the separate public works bondrequired by Oregon Laws 2005, Chapter 360, andOAR 839-025-0015, unless otherwise exempt underthose provisions. The Contractor shall also include in

every subcontract a provision requiring theSubcontractor to have a public works bond filed withthe Construction Contractors Board before startingWork, unless otherwise exempt, and shall verify thatthe Subcontractor has filed a public works bond beforepermitting the Subcontractor to start Work.

G.3 INSURANCE 

G.3.1 Primary Coverage: Insurance carried by Contractorunder this Contract shall be the primary coverage, andthe Owner's insurance is excess and solely fordamages or losses for which the Owner is responsible.The coverages indicated are minimums unlessotherwise specified in the Contract Documents.

G.3.2 Workers' Compensation: All employers, including

Contractor, that employ subject workers who workunder this contract in the State of Oregon shall complywith ORS 656.017 and provide the required Workers’Compensation coverage, unless such employers areexempt under ORS 656.126. This shall includeEmployer’s Liability Insurance with coverage limits ofnot less than $100,000 for each accident. Contractorswho perform the Work without the assistance or laborof any employee need not obtain such coverage if theContractor certifies so in writing. Contractor shallensure that each of its Subcontractors complies withthese requirements. The Contractor shall requireproof of such Workers’ Compensation by receiving andkeeping on file a certificate of insurance from eachSubcontractor or anyone else directly employed byeither the Contractor or its Subcontractors.

G.3.3 Builder's Risk Insurance:

G.3.3.1 Builder's Risk: During the term of this Contract, fornew construction the Contractor shall maintain inforce, at its own expense, Builder's Risk insuranceon an all risk form, including earthquake and flood,for an amount equal to the full amount of theContract. Any deductible shall not exceed $50,000for each loss, except the earthquake and flooddeductible shall not exceed 2 percent of each loss or$50,000, whichever is more. The policy will includeas loss payees the Owner, the Contractor and itsSubcontractors as their interests may appear.

Page 22: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 22/26

 

CM/GC Contract Form (4/09) (574022)

G.3.3.2 Builder's Risk Installation Floater: For other thannew construction the Contractor shall obtain, at theContractor's expense, and keep in effect during theterm of this Contract, a Builder's Risk InstallationFloater for coverage of the Contractor's labor,materials and equipment to be used for completion ofthe Work performed under this Contract. Theminimum amount of coverage to be carried shall beequal to the full amount of the Contract. Thisinsurance shall include as loss payees the State ofOregon, the Owner, the Contractor and itsSubcontractors as their interests may appear.

G.3.3.3 Such insurance shall be maintained until Owner hasoccupied the facility.

G.3.3.4 A loss insured under the Builder’s Risk insuranceshall be adjusted by the Owner and made payable tothe Owner for the insureds, as their interests mayappear. The Contractor shall pay Subcontractorstheir just shares of insurance proceeds received bythe Contractor, and by appropriate agreements,written where legally required for validity, shallrequire Subcontractors to make payments to theirSub-subcontractors in similar manner. The Ownershall have power to adjust and settle a loss withinsurers.

G.3.4  Liability Insurance: 

G.3.4.1 Commercial General Liability: Contractorshall obtain, at Contractor's expense, and keep ineffect during the term of this Contract, CommercialGeneral Liability Insurance covering bodily injury andproperty damage in a form and with coverages thatare satisfactory to the State. This insurance shallinclude personal injury liability, products andcompleted operations, and contractual liabilitycoverage for the indemnity provided under thisContract (to the extent contractual liability coveragefor the indemnity is available in the marketplace),and shall be issued on an occurrence basis.Combined single limit per occurrence shall not beless than $1,000,000 for each job site or location.Each annual aggregate limit shall not be less than$1,000,000.

G.3.4.2 Automobile Liability: Contractor shall obtain, atContractor's expense, and keep in effect during theterm of this Contract, Automobile Liability Insurancecovering owned, non-owned and/or hired vehicles,as applicable. The coverage may be written incombination with the Commercial General LiabilityInsurance. Combined single limit per occurrenceshall not be less than $1,000,000.00, or theequivalent.

G.3.4.3 "Tail" Coverage: If any of the required liabilityinsurance is arranged on a "claims made" basis,"tail" coverage will be required at the completion ofthis Contract for a duration of 24 months or themaximum time period available in the marketplace if

less than 24 months. Contractor will be responsiblefor furnishing certification of "tail" coverage asdescribed or continuous "claims made" liabilitycoverage for 24 months following Final Completion.Continuous "claims made" coverage will beacceptable in lieu of "tail" coverage, provided itsretroactive date is on or before the effective date ofthis Contract. This will be a condition of the finalacceptance of Work or services and related warranty(if any).

G.3.5 Additional Insured: The liability insurance coverage,except Professional Liability if included, required forperformance of this Contract shall include the Stateof Oregon, its departments, divisions, officers, and

employees, as Additional Insureds but only withrespect to the Contractor's activities to be performedunder this Contract. If Contractor cannot obtain aninsurer to name the State of Oregon, itsdepartments, divisions, officers and employees asAdditional Insureds, Contractor shall obtain atContractor's expense, and keep in effect during theterm of this Contract, Owners and ContractorsProtective Liability Insurance, naming the State ofOregon, its departments, divisions, officers andemployees as Named Insureds with not less than a$1,000,000.00 limit per occurrence. This policy mustbe kept in effect for 12 months following FinalCompletion. As evidence of coverage, Contractorshall furnish the actual policy to Owner prior to itsissuance of a Notice to Proceed.

G.3.6 Notice of Cancellation or Change: There shall be nocancellation, material change, potential exhaustioncoverages without thirty (30) Days' written noticefrom the Contractor or its insurer(s) to the Owner.Any failure to comply with the reporting provisions ofthis insurance, except for the potential exhaustion ofaggregate limits, shall not affect the coveragesprovided to the State of Oregon, its Owner and theirdivisions, officers, and employees.

G.3.7 Certificate(s) of Insurance: As evidence of theinsurance coverage required by this Contract, the

Contractor shall furnish certificate(s) of insurance tothe Owner prior to its issuance of a Notice toProceed. The certificate(s) will specify all of theparties who are Additional Insureds or Loss Payees.Insurance coverage required under this Contractshall be obtained from insurance companies orentities acceptable to the Owner that are allowed toprovide such insurance under Oregon law. Eligibleinsurers include admitted insurers that have beenissued a certificate of authority from the OregonDepartment of Consumer and Business Servicesauthorizing them to do an insurance business in thestate of Oregon, and certain nonadmitted surpluslines insurers that satisfy the requirements ofapplicable Oregon law and are approved by theOwner. The certificates will also specify that thereshall be no cancellation, material change, potential

exhaustion of aggregate limits or intent not to renewinsurance coverages without thirty (30) Days' writtennotice from the insurer(s) to the Owner. To theextent Certificates of Insurance contain words to theeffect that Contractor shall "endeavor to send noticeof cancellation" or similar language, Contractor shallrequire its insurer to send such notice by makingsure that the words “endeavor to” or similar wordsare removed from the Certificate. The Contractorshall be financially responsible for all deductibles,self-insured retentions and/or self-insurance includedhereunder. Any deductible, self-insured retentionand/or self-insurance in excess of $50,000 shall beapproved by the Owner in writing prior to issuance ofa Notice to Proceed and is subject to Owner'sapproval.

SECTION HSCHEDULE OF WORK 

H.1 CONTRACT PERIOD

H.1.1 Time is of the essence on this Contract. TheContractor shall at all times carry on the Workdiligently, without delay and punctually fulfill allrequirements herein. Contractor shall commenceWork on the site within fifteen (15) Days of Notice toProceed, unless directed otherwise.

Page 23: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 23/26

 

CM/GC Contract Form (4/09) (574022)

H.1.2 Unless specifically extended by Change Order, allWork shall be complete by the date contained in theContract Documents. The Owner shall have the rightto accelerate the completion date of the Work, whichmay require the use of overtime. Such acceleratedWork schedule shall be an acceleration inperformance of Work under Section D.1.2 (f) andshall be subject to the Change Order process ofSection D.1.

H.1.3 The Owner shall not waive any rights under theContract by permitting the Contractor to continue orcomplete the Work or any part of it after the datedescribed in Section H.1.2 above.

H.2 SCHEDULE

H.2.1 Contractor shall provide, by or before the pre-construction conference, a detailed schedule forreview and acceptance by the Owner. Thesubmitted schedule must illustrate Work bysignificant project components, significant labortrades, long lead items, broken down by buildingand/or floor where applicable. Each schedule itemshall account for no greater than 5 % of the monetaryvalue of the project or 5 % of the available ContractTime. Schedules with activities of less than one dayor valued at less than 1% of the Contract will beconsidered too detailed and will not be accepted.

Schedules lacking adequate detail, or unreasonablydetailed, will be rejected. Included within theschedule are the following: Notice to Proceed,Substantial Completion, and Final Completion.Schedules will be updated monthly and submittedwith the monthly payment application. Acceptance ofthe Schedule by the Owner does not constituteagreement by the Owner, as to the Contractor'ssequencing, means, methods, or allocated ContractTime. Any positive difference between theContractor's scheduled completion and the Contractcompletion date is float owned by the Owner. Ownerreserves the right to negotiate the float if it is deemedto be in Owner’s best interest to do so. In no caseshall the Contractor make a request for additionalcompensation for delays if the Work is completedwithin the Contract Time but after Contractor's

scheduled completion.

H.3 PARTIAL OCCUPANCY OR USE

H.3.1 The Owner may occupy or use any completed orpartially completed portion of the Work at any stage,provided such occupancy or use is consented to bypublic authorities having jurisdiction over the Work.Such partial occupancy or use may commencewhether or not the portion is substantially complete,provided the Owner and Contractor have reasonablyaccepted in writing the responsibilities assigned toeach of them for payments, retainage, if any,security, insurance or self-insurance, maintenance,heat, utilities, and damage to the Work, and haveagreed in writing concerning the period for correction

of the Work and commencement of warrantiesrequired by the Contract Documents with respect tosuch portion of the Work. Approval by the Contractorto partial occupancy or use shall not beunreasonably withheld. Immediately prior to suchpartial occupancy or use, the Owner and Contractorshall jointly inspect the area to be occupied or portionof the Work to be used in order to determine andrecord the condition of the Work. Partial occupancyor use of a portion or portions of the Work shall notconstitute acceptance of Work not complying with therequirements of the Contract Documents.

SECTION I

CORRECTION OF WORK 

I.1 CORRECTION OF WORK BEFORE FINAL PAYMENT

The Contractor warrants to the Owner that materialsand equipment furnished under the Contract will be of goodquality and new unless otherwise required or permitted bythe Contract Documents, that the Work will be free fromdefects, and that the Work will conform to the requirementsof the Contract Documents. Work failing to conform to theserequirements shall be deemed defective. Contractor shallpromptly remove from the premises and replace all defectivematerials and equipment as determined by the Owner'sAuthorized Representative, whether incorporated in theWork or not. Removal and replacement shall be without lossor expense to the Owner, and Contractor shall bear the costof repairing all Work destroyed or damaged by such removalor replacement. Contractor shall be allowed a period of nolonger than sixty (60) days for completion of defective(punch list) work, unless otherwise agreed. At the end ofthat period, or earlier if requested by the Contractor, Ownershall arrange for inspection of the Work by theArchitect/Engineer. Should the Work not be complete, andall corrections made, the costs for all subsequent re-inspections shall be borne by the Contractor. If Contractorfails to complete the punch list work within the above timeperiod, without affecting Contractor’s obligations Owner mayperform such work and Contractor shall reimburse Owner allcosts of the same within thirty (30) days after demand.

I.2 WARRANTY WORK

I.2.1 Neither the final certificate of payment nor anyprovision of the Contract Documents shall relieve theContractor from responsibility for defective Work and,unless a longer period is specified, Contractor shallcorrect all defects that appear in the Work within aperiod of one year from the date of issuance of thewritten notice of Substantial Completion by theOwner except for latent defects which will beremedied by the Contractor at any time they becomeapparent.

The Owner shall give Contractor notice of defectswith reasonable promptness. Contractor shallperform such warranty work within a reasonable time

after Owner’s demand. If Contractor fails tocomplete the warranty work within such period asOwner determines reasonable, or at any time in theevent of warranty work consisting of emergencyrepairs, without affecting Contractor’s obligations,Owner may perform such work and Contractor shallreimburse Owner all costs of the same within thirty(30) Days after demand.

I.2.2 This provision does not negate guarantees orwarranties for periods longer than one year includingwithout limitation such guarantees or warrantiesrequired by other sections of the ContractDocuments for specific installations, materials,processes, equipment or fixtures.

I.2.3 In addition to Contractor's warranty, manufacturer'swarranties shall pass to the Owner and shall not takeeffect until affected Work has been accepted inwriting by the Owner's Authorized Representative.

I.2.4 The one-year period for correction of Work shall beextended with respect to portions of Work performedafter Substantial Completion by the period of timebetween Substantial Completion and the actualperformance of the Work, and shall be extended bycorrective Work performed by the Contractorpursuant to this Section, as to the Work corrected.The Contractor shall remove from the site portions ofthe Work which are not in accordance with therequirements of the Contract Documents and are

Page 24: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 24/26

 

CM/GC Contract Form (4/09) (574022)

neither corrected by the Contractor nor accepted bythe Owner.

I.2.5 Nothing contained in this Section I.2 shall beconstrued to establish a period of l imitation withrespect to other obligations which the Contractormight have under the Contract Documents.Establishment of the period for correction of Work asdescribed in this Section I.2 relates only to thespecific obligation of the Contractor to correct theWork, and has no relationship to the time withinwhich the obligation to comply with the ContractDocuments may be sought to be enforced, nor to thetime within which proceedings may be commencedto establish the Contractor’s liability with respect tothe Contractor’s obligations other than specifically tocorrect the Work.

I.2.6 If the Owner prefers to accept Work which is not inaccordance with the requirements of the ContractDocuments, the Owner may do so instead ofrequiring its removal and correction, in which casethe Contract Price will be reduced as appropriate andequitable. Such adjustment shall be effectedwhether or not final payment has been made.

SECTION JSUSPENSION AND/OR TERMINATION OF THE WORK 

J.1 OWNER'S RIGHT TO SUSPEND THE WORK

J.1.1 The Owner and/or the Owner's AuthorizedRepresentative has the authority to suspend portionsor all of the Work due to the following causes:

(a) Failure of the Contractor to correct unsafeconditions;

(b) Failure of the Contractor to carry out anyprovision of the Contract;

(c) Failure of the Contractor to carry out orders;

(d) Conditions, in the opinion of the Owner'sAuthorized Representative, which are

unsuitable for performing the Work;

(e) Time required to investigate differing siteconditions;

(f) Any reason considered to be in the publicinterest.

J.1.2 The Owner shall notify Contractor and theContractor's Surety in writing of the effective dateand time of the suspension and shall notifyContractor and its surety in writing to resume Work.

J.2  CONTRACTOR'S RESPONSIBILITIES

J.2.1 During the period of the suspension, Contractor is

responsible to continue maintenance at the project just as if the Work were in progress. This includes,but is not limited to, protection of completed Work,maintenance of access, protection of storedmaterials, temporary facilities, and clean-up.

J.2.2 When the Work is recommenced after thesuspension, the Contractor shall replace or renewany Work damaged during the suspension, removeany materials or facilities used as part of temporarymaintenance, and complete the project in everyrespect as though its prosecution had beencontinuous and without suspension.

J.3  COMPENSATION FOR SUSPENSION 

J.3.1 Depending on the reason for suspension of theWork, the Contractor or the Owner may be duecompensation by the other party. If the suspensionwas required due to acts or omissions of Contractor,the Owner may assess the Contractor actual costs ofthe suspension in terms of administration, remedialwork by the Owner's forces or another contractor tocorrect the problem associated with the suspension,rent of temporary facilities, and other actual costsrelated to the suspension. If the suspension wascaused by acts or omissions of the Owner, theContractor shall be due compensation which shall be

defined using Section D, Changes in Work. If thesuspension was required through no fault of theContractor or the Owner, neither party owes theother for the impact.

J.4  OWNER'S RIGHT TO TERMINATE CONTRACT

J.4.1 The Owner may, without prejudice to any other rightor remedy, and after giving Contractor seven (7)Days’ written notice and an opportunity to cure,terminate the Contract in whole or in part under thefollowing conditions:

(a) If Contractor should voluntarily or involuntarily,seek protection under the United States

Bankruptcy Code and Contractor as debtor-in-possession or the Trustee for the estate fails toassume the Contract within a reasonable time;

(b) If Contractor should make a general assignmentfor the benefit of Contractor's creditors;

(c) If a receiver should be appointed on account ofContractor's insolvency;

(d) If Contractor should repeatedly refuse or fail tosupply an adequate number of skilled workersor proper materials to carry on the Work asrequired by the Contract Documents, orotherwise fail to perform the Work in a timelymanner;

(e) If Contractor should repeatedly fail to make

prompt payment to Subcontractors or formaterial or labor, or should disregard laws,ordinances or the instructions of the Owner orits Authorized Representative; or

(f) If Contractor is otherwise in material breach ofany part of the Contract.

J.4.2 At any time that any of the above occurs, Owner mayexercise all rights and remedies available to Ownerat law or in equity, and in addition, Owner may takepossession of the premises and of all materials andappliances and finish the Work by whatever methodit may deem expedient. In such case, the Contractorshall not be entitled to receive further payment untilthe Work is completed. If the Owner's cost offinishing the Work exceeds the unpaid balance of theContract Price, Contractor shall pay the difference tothe Owner.

J.5 TERMINATION FOR CONVENIENCE

J.5.1 Owner may terminate the Contract in whole or in partwhenever Owner determines that termination of theContract is in the best interest of the public.

J.5.2 The Owner will provide the Contractor with seven (7)Days’ prior written notice of a termination for publicconvenience. After such notice, the Contractor shallprovide the Owner with immediate and peacefulpossession of the premises and materials located on

Page 25: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 25/26

 

CM/GC Contract Form (4/09) (574022)

and off the premises for which the Contractorreceived progress payment under Section E.Compensation for Work terminated by the Ownerunder this provision will be according to Section E.In no circumstance shall Contractor be entitled to lostprofits for Work not performed due to termination.

J.6 ACTION UPON TERMINATION

J.6.1 Upon receiving a notice of termination, and except asdirected otherwise by the Owner, Contractor shallimmediately cease placing further subcontracts ororders for materials, services, or facilities. Inaddition, Contractor shall terminate all subcontractsor orders to the extent they relate to the Workterminated and, with the prior written approval of theOwner, settle all outstanding liabilities andtermination settlement proposals arising from thetermination of subcontracts and orders.

J.6.2 As directed by the Owner, Contractor shall upontermination transfer title and deliver to the Owner allRecord Documents, information, and other propertythat, if the Contract had been completed, would havebeen required to be furnished to the Owner. 

SECTION KCONTRACT CLOSE OUT  

K.1 RECORD DOCUMENTS

As a condition of final payment (refer also to sectionE.6), Contractor shall comply with the following: Contractorshall provide to Owner's Authorized Representative, RecordDocuments of the entire project. Record Documents shalldepict the project as constructed and shall reflect each andevery change, modification, and deletion made during theconstruction. Record Documents are part of the Work andshall be provided prior to the Owner's issuance of finalpayment. Record Documents include all modifications to theContract Documents unless otherwise directed.

K.2 OPERATION AND MAINTENANCE MANUALS 

As part of the Work, Contractor shall submit two

completed operation and maintenance manuals ("O & MManuals") for review by the Owner's AuthorizedRepresentative prior to submission of any pay request formore than 75% of the Work. No payments beyond 75% willbe made by the Owner until the 0 & M Manuals have beenreceived. The O & M Manuals shall contain a complete setof all submittals, all product data as required by thespecifications, training information, phone list of consultants,manufacturers, installer and suppliers, manufacturer'sprinted data, record and shop drawings, schematic diagramsof systems, appropriate equipment indices, warranties andbonds. The Owner's Authorized Representative shall reviewand return one O & M Manual for any modifications oradditions required. Prior to submission of its final payrequest, Contractor shall deliver three (3) complete andapproved sets of O & M Manuals to the Owner's Authorized

Representative.

K.3 AFFIDAVIT/RELEASE OF LIENS AND CLAIMS

As a condition of final payment, the Contractor shallsubmit to the Owner's Authorized Representative a notarizedaffidavit/release of liens and claims form, in a formsatisfactory to Owner, which states that all Subcontractorsand suppliers have been paid in full, all disputes withproperty owners have been resolved, all obligations on theproject have been satisfied, all monetary claims andindebtedness have been paid, and that, to the best of theContractor's knowledge, there are no claims of any kindoutstanding against the project. The Contractor shallindemnify, defend (with counsel of Owner's choice) and hold

harmless the Owner from all claims for labor and materialsfinished under this Contract. The Contractor shall furnishcomplete and valid releases or waivers, satisfactory to theOwner, of all liens arising out of or filed in connection withthe Work.

K.4 COMPLETION NOTICES

K.4.1 Contractor shall provide Owner notice of bothSubstantial and Final Completion. The certificate ofSubstantial Completion shall state the date ofSubstantial Completion, the responsibilities of theOwner and Contractor for security, maintenance,heat, utilities, damage to the Work and insurance,and the time within which the Contractor shall finishall items on the punchlist accompanying theCertificate. Both completion notices must be signedby the Contractor and the Owner to be valid. TheOwner shall provide the final signature on thenotices. The notices shall take effect on the datethey are signed by the Owner.

K.4.2 Substantial Completion of a facility with operatingsystems (e.g., mechanical, electrical, HVAC) shall bethat degree of completion that has provided aminimum of thirty (30) continuous Days ofsuccessful, trouble-free operation, which period shallbegin after all performance and acceptance testinghas been successfully demonstrated to the Owner's

Authorized Representative. All equipment containedin the Work, plus all other components necessary toenable the Owner to operate the facility in themanner that was intended, shall be complete on theSubstantial Completion date. The Contractor mayrequest that a punch list be prepared by the Owner'sAuthorized Representative with submission of therequest for the Substantial Completion notice.

K.5 TRAINING

As part of the Work, and prior to submission of therequest for final payment, the Contractor shall schedule withthe Owner's Authorized Representative, training sessions forall equipment and systems, as required in the individualspecifications sections. Contractor shall schedule trainingsessions at least two weeks in advance of the date of

training to allow Owner personnel adequate notice.The O & M Manual shall be used as a basis for training.Training shall be a formal session, held after the equipmentand/or system is completely installed and operational in itsnormal operating environment.

K.6 EXTRA MATERIALS

As part of the Work, Contractor shall provide spareparts, extra maintenance materials, and other materials orproducts in the quantities specified in the specifications, priorto final payment. Delivery point for extra materials shall bedesignated by the Owner's Authorized Representative.

K.7 ENVIRONMENTAL CLEAN-UP

As part of the Final Completion notice, or as a separatewritten notice submitted with or before the notice of FinalCompletion, the Contractor shall notify the Owner that allenvironmental pollution clean-up which was performed as apart of this Contract has been disposed of in accordancewith all applicable rules, regulations, laws, and statutes of allagencies having jurisdiction over such environmentalpollution. The notice shall reaffirm the indemnification givenunder Section F.5.1 above.

K.8 CERTIFICATE OF OCCUPANCY

The Contractor shall not be granted Final Completion orreceive final payment if the Owner has not received anunconditioned certificate of occupancy from the appropriate

Page 26: ODOT Building Contract: 28123 Exh A

8/4/2019 ODOT Building Contract: 28123 Exh A

http://slidepdf.com/reader/full/odot-building-contract-28123-exh-a 26/26

 state and/or local building officials, unless failure to obtain anunconditional certificate of occupancy is due to the fault orneglect of Owner.

K.9 OTHER CONTRACTOR RESPONSIBILITIES

The Contractor shall be responsible for returning to theOwner all items issued during construction such as keys,security passes, site admittance badges, and all otherpertinent items. The Contractor shall be responsible fornotifying the appropriate utility companies to transfer utilitycharges from the Contractor to the Owner. The utilitytransfer date shall not be before Substantial Completion andmay not be until Final Completion, if the Owner does nottake beneficial use of the facility and the Contractor's forcescontinue with the Work.

K.10 SURVIVAL 

All warranty and indemnification provisions of thisContract, and all of Contractor’s other obligations under thisContract that are not fully performed by the time of FinalCompletion or termination, shall survive Final Completion orany termination of the Contract

SECTION LLEGAL RELATIONS & RESPONSIBILITIES  

L.1 LAWS TO BE OBSERVED

In compliance with ORS 279C.525, Sections L.2through L.4 contain lists of federal, state and local agenciesof which the Owner has knowledge that have enactedordinances or regulations relating to environmental pollutionand the preservation of natural resources that may affect theperformance of the Contract:

L.2 FEDERAL AGENCIES

Agriculture, Department of

Forest Service

Soil Conservation Service

Coast Guard

Defense, Department of

Army Corps of Engineers

Energy, Department of

Federal Energy Regulatory Commission

Environmental Protection Agency

Health and Human Services, Department of

Housing and Urban Development, Department of

Solar Energy and Energy Conservation Bank

Interior, Department of

Bureau of Land Management

Bureau of Indian Affairs

Bureau of Mines

Bureau of Reclamation

Geological Survey

Minerals Management Service

U.S. Fish and Wildlife Service

Labor, Department of

Mine Safety and Health Administration

Occupation Safety and Health Administration

Transportation, Department of

Federal Highway Administration

Water Resources Council

L.3 STATE AGENCIES 

Administrative Services, Department of

Agriculture, Department of

Soil and Water Conservation Commission

Columbia River Gorge Commission

Energy, Department of

Environmental Quality, Department of

Fish and Wildlife, Department of

Forestry, Department of

Geology and Mineral Industries, Department of

Human Resources, Department of

Consumer and Business Services, Department of

Land Conservation and Development Commission

Parks and Recreation, Department of

State Lands, Division of

Water Resources Department of

L.4 LOCAL AGENCIES

City Councils

County Courts

County Commissioner, Board of

Design Commissions

Historical Preservation Commission

Planning Commissions