of prefab cat-ii & ews housing for delhi development...

56
DELHI DEVELOPMENT AUTHORITY FORM I & IA For Environmental Clearance Of Prefab CAT-II & EWS Housing For Delhi Development Authority At Pocket 1 B, Sector A1A4, Narela, New Delhi (July 17, 2014) SUBMITTED TO: State level expert Appraisal Committee, New Delhi Department of Environment, Govt. of NCT Delhi Sachivalaya IP Estate New Delhi SUBMITTED BY: DELHI DEVELOPMENT AUTHORITY VIKAS MINAR, ITO, NEW DELHI - 110002

Upload: others

Post on 01-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • DELHI DEVELOPMENT AUTHORITY

    FORM I & IA

    For

    Environmental Clearance Of

    Prefab CAT-II & EWS Housing For

    Delhi Development Authority

    At Pocket 1 B, Sector – A1A4, Narela, New Delhi

    (July 17, 2014)

    SUBMITTED TO: State level expert Appraisal Committee, New Delhi

    Department of Environment, Govt. of NCT Delhi

    Sachivalaya IP Estate

    New Delhi

    SUBMITTED BY:

    DELHI DEVELOPMENT AUTHORITY VIKAS MINAR, ITO, NEW DELHI - 110002

  • FORM- I

    Basic Information

    S. No. Item Details

    1. Name of the project/s Prefab CAT-II & EWS Housing For

    Delhi Development Authority At

    pocket-1 B ,Sector A1,A4 Narela New

    Delhi

    2. S. No. in the schedule 8‟A‟

    3. Proposed capacity/area/length/tonnage to be

    handled/command area/lease area/number of

    wells to be drilled

    Total Plot Area = 55100 SQM

    Net Site Area = 544771 SQM

    Total Built-up Area= 2,09,183.78

    SQM

    Total Nos. of Units = ( CAT-II 416+

    EWS 2860 ) =3276Nos.

    Green Area=10855 SQM

    Population 3276 x 5= 16,380

    4. New/Expansion/Modernization NEW

    5. Existing Capacity/Area etc. NA

    6. Category of Project. i.e.' A' or 'B' „A‟

    7. Does it attract the general condition? If yes,

    Please specify.

    No

    8. Does it attract the specific condition? If yes,

    Please specify.

    NA

    9. Location Narela

    Plot/Survey/Khasra No. Pocket I B, Sector A1A4

    Village

    Tehsil

    District North West Delhi

    State Delhi

    10.. Nearest railway station/airport along with Khera kalan Railway Station about 3

  • Distance in kms. km and Rithala metro station about 5 km.

    11. Nearest Town, city, District Headquarters

    Along with distance in kms.

    Delhi

    12. Village Panchayats, Zilla Parishad, Municipal

    Corporation, Local body (complete postal

    Addresses with telephone nos. to be given)

    Municipal Corporation,

    13. Name of the applicant Delhi Development Authority.

    14 Registered Address Vikas Minar, ITO, IP Estate

    New Delhi - 110002

    15. Address for correspondence Office of Executive Engineer

    Northern Division -4

    Delhi Development Authority

    Narela, New Delhi -110040

    Name Er. K G GUPTA

    Designation (Owner/Partner/CEO) Executive Engineer (ND - 4 ) DDA

    Address Office of Executive Engineer

    Northern Division - 4

    Delhi Development Authority

    Narela .

    Pin Code New Delhi -110040

    E-mail

    Telephone No. 011- 27282604

    Fax No.

    16. Details of Alternative Sites examined, if any.

    Location of these sites should be shown on a

    toposheet.

    Planned site

    17. Interlinked Projects No

    18. Whether separate application of interlinked

    Project has been submitted?

    No

    19. If yes, date of submission No

    20. If no, reason NA

    21. Whether the proposal involves approval/clearance No

  • under; if yes, details of the same and their status

    to be given.

    (a) The forest (Conservation) Act, 1980?

    (b) The wildlife (Protection) Act, 1972?

    (c) The C.R.Z. Notification, 1991?

    22. Whether there is any Government Order/Policy

    relevant/relating to the site?

    As per the master plan Residential

    project will be developed by DDA

    23. Forest land involved (hectares) No

    24. Whether there is any litigation pending against

    the project and for/or land in which the project is

    propose to be set up?

    (a)Name of the Court

    (b)Case No.

    (c) Orders/directions of the Court, if any and its

    relevance with the proposed project

    No

    (b) the following shall be inserted at the end, namely:-

    “I hereby given undertaking that the data and information given in in the application and

    enclosures are true to the best of my knowledge and belief and I am aware that if any part of

    data and information submitted found to false or misleading at any stage, that the project will

    be rejected and clearance give, if any to the project will be revoked at our risk and cost.

    Date: __________________

    Place: _________________ Signature of the applicant

    With Name and Full Address

    (Project proponent/ Authorized Signatory)

  • (II) Activity

    1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water

    bodies, etc.):

    S. No.

    Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities /rates, wherever possible)

    with source of information data

    1.1 Permanent or temporary change in

    land use, land cover or topography

    including increase in intensity of

    land use (with respect to local land

    use plan)

    No The project has been approved by the

    DDA; Hence no major land use change

    is envisaged.

    1.2 Clearance of existing land,

    vegetation and buildings?

    No Pocket IB, Sector A1A4, Narela, Prefab

    CAT-II & EWS Housing project

    developed by Delhi Development

    Authority,

    1.3 Creation of new land uses? No Land was earmarked for the

    development of Housing Complex land

    use purpose by Delhi Development

    Authority.

    1.4 Pre-construction investigations e.g.

    bore houses, soil testing

    Yes Soil Investigation has been done at site.

    Please refer to the 1.4 of Form1A

    1.5 Construction works? Yes Proposed construction of a prefab CAT-

    II & EWS Housing Complex

    1.6 Demolition works? No No site clearing is required

    1.7 Temporary sites used for

    construction works or housing of

    construction workers?

    No All the construction activity including

    stalking of raw materials will be

    confined within the project site only.

    Temporary labour hutments are

    proposed.260 Local labours from nearby

    area will be hired. Proper sanitation

    facilities for them will be developed at

    site.

    1.8 Above ground buildings, structures

    or earthworks including linear

    structures, cut and fill or excavations

    Yes It is estimated that approx 72000 m3 of

    soil has to be excavated for foundation

    and structures etc.

    1.9 Underground works including

    mining or tunneling?

    No No underground works including

    mining/ tunneling required

    1.10 Reclamation works? No No reclamation work required.

    1.11 Dredging? No No Dredging required.

    1.12 Offshore structures? No No offshore structures required.

    1.13 Production and Manufacturing

    processes?

    No No production/manufacturing process

    involved.

    1.14 Facilities for storage of goods or

    materials?

    Yes Separate raw material handling yard will

    be made. Cement will be separately

  • stored under cover in bales. Sand will be

    stacked neatly under tarpaulin cover.

    steel will be laid in open.

    The raw material handling yard will be

    located within the project site and

    separated by enclosures.

    1.15 Facilities for treatment or disposal of

    solid waste or liquid effluents?

    Yes Solid waste:

    Populati

    on/Area

    Per capita

    solid

    waste

    generation

    (kg/day)

    Total solid

    waste

    generation(

    kg/day)

    16,380 0.6 9828

    *(as per CPHEEO Manual of Solid

    Waste Management)

    Adequate number of collection bins

    separate for biodegradable and non-

    biodegradable waste shall be provided

    as per the MSW Rule, 2000. Final

    segregation of solid waste into

    biodegradable, non-biodegradable, and

    inert fraction will take place in

    centralized collection facility. The non-

    bio-degradable fraction will take place

    in centralized collection facility. The

    rest will be handed over to Municipal

    Corporation of Delhi.

    The process of disposal to be through

    sanitary landfill, composting and

    incineration depending upon the quality

    of the refuse. In future emphasis would

    be laid on solid waste disposal by more

    scientific method, where the land

    requirement gets reduced to minimum in

    consultation with the concerned

    agencies.

    A site of about 60 ha for solid waste

    has been earmarked near Narela –

    Bawana industrial area phase – II.

    Liquid Effluent: It has been estimated

    that approx. 1769 KLD of sewage will

    be generated from the project. The

    entire sewage will be treated in

    Common STP of Narela, sector- -A1A4

    of total capacity of 3.5 MLD. Approx.

  • 683 KLD of water requirement will be

    met through recycling of STP treated

    water‟

    The Developer will provide sewage

    treatment plant of following capacities

    base on FAB & MBBR process for

    treatment of sewage & sullage water

    The treated effluent shall be of a quality

    suitable for flushing & horticulture for

    external areas.

    1.16 Facilities for long term housing of

    operational workers?

    No No Facilities for long term housing of

    operational workers

    1.17 New road, rail or sea traffic during

    construction or operation?

    No Not applicable

    1.18 New road, rail, air water borne or

    other transport infrastructure

    including new or altered routes and

    stations, ports, airports etc.?

    No Not applicable

    1.19 Closure or diversion of existing

    transport routes or infrastructure

    leading to changes in traffic

    movements?

    No Not applicable

    1.20 New or diverted transmission lines

    or pipelines?

    No Not applicable

    1.21 Impoundment, damming, culver

    ting, realignment or other changes to

    the hydrology of watercourses or

    aquifers?

    No No Impoundment, damming, culverting,

    realignment or other changes to the

    hydrology of surface watercourses is

    proposed.

    Ground water exploration will be done

    at site(6 bore wells proposed)if

    permitted by DJB and also the water

    will be from DJB

    1.22 Stream crossing? No Not applicable

    1.23 Abstraction or transfers of water

    form ground or surface waters?

    Yes During construction phase water from

    tankers/Ground water (if DJB permits)

    will be used for Housing Complex.

    During the project operational stage,

    water will be supplied by DJB and

    partly Ground water only if DJB permits

    for the same

    1.24 Changes in water bodies or the land

    surface affecting drainage or run-

    off?

    No Surface drainage will not be affected.

    1.25 Transport of personnel or materials

    for construction, operation or

    decommissioning?

    yes Transports of personnel/material during

    the construction and operation phase are

    envisaged. During the operation phase

  • parking space for 648 ECS for EWS@

    0.5 ECS per 100 SQM AND 886 ECS

    @ 2 ECS per 100 SQM FOR CAT-II

    will be provided built-up area.

    In the construction phase, approx 25

    trucks per day over the entire

    construction phase are envisaged.

    1.26 Long term dismantling or

    decommissioning or restoration

    works?

    No Not applicable

    1.27 Ongoing activity during

    decommissioning which could have

    an impact on the environment?

    No Not applicable

    1.28 Influx of people to an area in either

    temporarily or permanently?

    No Approx. 260 nos. local labours from

    near by area will be hired in the

    construction phase per day. Thus, no

    influx of people is envisaged.

    1.29 Introduction of alien species? No Not applicable

    1.30 Loss of native species or genetic

    diversity?

    No Not applicable

    1.31 Any other actions? No None

    2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in

    short supply):

    S.

    No.

    Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities /rates, wherever possible)

    with source of information data

    2.1 Land especially undeveloped or

    agricultural land (ha)

    Yes Approx.32047 Sq. meter of land has

    been provided for development of

    CAT-II &EWS Housing project

    2.2 Water (expected source &

    competing users) unit: KLD

    Yes, The details of Water Requirement: During the operational phase water will

    be supplied by DJB and partly Ground

    water only if DJB permits for the same

    and through tankers during

    construction phase

    S.

    No.

    Name Water

    Demand

    (KLD)

    1 Flushing@45

    LPD

    765

    2 Domestic

    @90 LPD

    1474

  • Horticulture 28

    Total 2239

    2.3 Minerals (MT) None Not applicable

    2.4 Construction material – stone,

    aggregates, and soil (expected

    source – MT)

    Yes It will be prefab structure as per the

    design in the casting yard and shall be

    installed at the site as per the DDA

    specification. The prefab material will

    be basically sand, cement & aggregate

    & steel.

    2.5 Forests and Timber (source – MT) None Not applicable

    2.6 Energy including electricity and

    fuels (source, competing users)

    Unit: fuel (MT), energy (MW)

    Yes The total connected load as per NDPL

    is calculated to be around say,

    23100 KW and after@ 0.4 D.F. it will

    be around 9300 KW & after

    considering P.F. & 70% loading ,the

    reqd. transformer rating shall be 14200

    KVA for this Housing Complex.

    Power will be supplied by NDPL.

    HSD (low Sulphur variety) will be used

    for DG set,

    (4 x82.5+4x30+1x250) KVA

    HSD consumption will be around

    20 L/hour.

    2.7 Any other natural resources (use

    appropriate standard units)

    None Not applicable

    3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual

    or perceived risks to human health.:Paints and Varnish

    S. No. Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities /rates, wherever possible) with

    source of information data

    3.1 Use of substances or materials,

    which are hazardous (as per MSIHC

    rules) to human health or the

    environment (flora, fauna and water

    supplies)

    No This is a Housing Complex project based

    on Prefab Technology CAT-II & EWS

    Houses & no storage of hazardous

    chemicals (as per MSIHC Rules) will be

    done, apart from spent oil, Suitable

    management practice will be adopted for

    the same It will be stored in HDPE drums

    and kept in covered rooms, under lock

    and key and will be sold to authorized

    vendors only. Specialized care will be

    taken to prevent leaks and / or sips.

    HSD (low sulphur variety) will be used

  • for DG sets. However, the quantity stored

    will be below the threshold limit

    specified by the MSIHC Rules.

    3.2 Changes in occurrence of disease or

    effect disease vectors (e.g. insect or

    water borne diseases)

    No Suitable drainage and waste management

    measures will be adopted in both the

    construction and operational phase which

    will restrict stagnation of water or

    accumulation of waste. This will

    effectively restrict the reproduction and

    growth of disease vectors.

    3.3 Affect the welfare of people e.g. by

    changing living conditions/

    No No use, storage, transport, handling or

    production of any harmful product is

    envisaged from the proposed project.

    Thus no major adverse impacts on the

    human health/ environment are

    envisaged.

    Moreover this project will provide

    employment to approx. 260 local labours

    in the construction phase and approx. 40

    workers in the operational phase. Thus

    the proposed project is supposed to have

    major beneficial impacts & environment

    friendly.

    3.4 Vulnerable groups of people who

    could be affected by the project e.g.

    hospital patients, children, the

    elderly etc.,

    No Not applicable

    3.5 Any other cases None Not applicable

    4. Production of solid wastes during construction or operation or decommissioning (MT/month)

    S. No. Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities /rates, wherever possible) with

    source of information data

    4.1 Spoil, overburden or mine wastes No No such spoil, overburden or mine

    wastes will be generated.

    4.2 Municipal waste (domestic and or

    commercial wastes)

    Yes The details of municipal solid waste

    generated from the project is estimated as

    9828 Kg/day

    (as per CPHEEO Manual on Municipal

    Solid Waste Management)

    4.3 Hazardous wastes (as per Hazardous

    Waste Management Rules

    Yes Spent oil from DG sets (approx. 20-25

    L/year). This spent oil will be carefully

    stored in HDPE drums in isolated

    covered facility. This spent oil will be

  • sold to vendors authorized by DPCC for

    the treatment of same.

    Suitable care will be taken so that spills/

    leaks of spent oil from storage could be

    avoided.

    4.4 Other Industrial process wastes No Not applicable

    4.5 Surplus product No Not applicable

    4.6 Sewage sludge or other sludge from

    effluent treatment

    Yes STP is stalled at sector level .STP

    Sludge will be handed over to Municipal

    Authorities because as DDA will hand

    over the site after allotment to civic

    bodies

    4.7 Construction or demolition wastes No There is no construction or demolition

    wastes.

    4.8 Redundant machinery or equipment No Not applicable

    4.9 Contaminated soils or other

    materials

    No Not applicable

    4.10 Agricultural wastes No Not applicable

    4.11 Other solid wastes No Not applicable

    5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr): Nil

    S. No. Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities /rates, wherever possible) with

    source of information data

    5.1 Emissions from combustion of fossil

    fuels from stationery or mobile

    sources

    No Not applicable Not applicable

    5.2 Emissions from production

    processes

    No Not applicable

    5.3 Emissions from materials handling

    including storage or transport

    No Not applicable

    5.4 Emissions from construction

    activities including plant and

    equipment

    No Not applicable.

    5.5 Dust or odours from handling of

    materials, sewage and waste

    No Not applicable

    5.6 Emissions from incineration of

    waste

    No Not applicable

    5.7 Emissions from burning of waste in

    open air (e.g. slash materials,

    construction debris)

    No Not applicable

    5.8 Emissions from any other sources No Not applicable

    6. Generation of Noise and Vibration, and Emissions of CAT-IIht and Heat: From DG Set

  • S. No. Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities /rates, wherever possible) with

    source of information data

    6.1 From operation of equipment e.g.

    engines, ventilation plant, crushers

    No Source of noise in the operational phase

    will be DG sets only. The DG sets will be

    in operation during power failure only for

    water supply pumps and will acoustic

    enclosure.

    The excess sound pressure level will be

    perceivable at a distance of 6 m. Beyond

    this radius no excessive noise level is

    perceivable over the background noise

    level.

    6.2 From Industrial or similar processes No Not applicable

    6.3 From construction or demolition No Due to various construction activities,

    there will be short-term noise impacts in

    the immediate vicinity of the project site.

    The construction activities will include

    the following noise generating activities:

    Operation of DG sets, Excavation etc. activities Heavy vehicle movement.

    It has been estimated that during

    construction period the average noise

    level will be around 75-80 dB(A) during

    peak construction hours.

    6.4 From blasting or piling No No blasting or mechanized piling will be

    used in the construction phase.

    6.5 From construction or operational

    traffic

    Yes Some amount of noise will be generated

    from vehicular movement in the

    construction and operational phase.

    6.6 From CAT-IIhting or cooling

    systems

    No Not applicable.

    6.7 From any other sources No Not applicable

    6. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea.

    S. No. Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities /rates, wherever possible) with

    source of information data

    7.1 From handling storage, use or

    spilage of hazardous materials

    No Spent oil will be handed with utmost

    care, it will be stored in HDPE drums

    stationed over puckka platforms and will

    be directly transferred to vendors

    authorized to handle such hazardous

  • material. Hence no risk of contamination

    is envisaged.

    7.2 From Discharge of sewage or other

    effluents to water or the land

    (expected mode and place of

    discharge)

    No The liquid effluent of 1769 KLD will be

    treated in common STP of Narela sec -

    A1A4 of total capacity of approx 35

    MLD, located in Narela -Sector A1A4.

    7.3 By deposition of pollutants emitted

    to air into the land or into water

    No No major fresh water bodies are located

    in downward direction. The Sewage

    discharge will confirms to Surface

    disposal guidelines of MoEF.

    7.4 From any other sources No Not applicable

    7.5 Is there a risk of long term built up

    of pollutants in the environment

    from these sources

    No Not applicable

    7. Risk of accidents during construction or operation of the project, which could affect human health or the environment.

    S. No. Information/Checklist confirmation Yes/No Details there of (with approximate

    quantities /rates, wherever possible) with

    source of information data

    8.1 From explosions, spillages, fires etc

    from storage, handling, use or

    production of hazardous substances

    No This is basically a Housing Complex

    construction project and does not involve

    major hazardous construction activity.

    During construction all the labours will

    be provided with suitable personal

    protective equipment (PPE) as required

    under the health & safety norms.

    Training and awareness about the safety

    norms will be provided to all supervisors

    and labours involved in construction

    activity.

    An agreement will be signed with the

    contractor which will clearly deal with

    the safety aspects during construction.

    No major hazardous waste is being stored

    within the project site. No industrial or

    process activity is involved in this project

    hence chances of chemical hazards and

    accidents are minimal. However, suitable

    fire fighting measures will be provided.

    8.2 From any other causes No Not applicable

    8.3 Could the project be affected by

    natural disasters causing

    environmental damage (e.g. floods,

    earthquakes, landslides, cloudburst

    No The area under study falls in Zone-IV,

    according to the Indian Standard Seismic

    Zoning Map. Suitable seismic

    coefficients in horizontal and vertical

  • etc)? directions respectively, have to be

    adopted while designing the structures.

    There are no chances of floods and

    landslide

    8. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other

    existing or planned activities in the locality

    S. No. Information/Checklist confirmation Yes/No Details there of (with

    approximate quantities /rates,

    wherever possible) with source of

    information data

    9.1 Lead to development of supporting.

    Lities, ancillary development or

    development stimulated by the

    project which could have impact on

    the environment e.g.:

    Supporting infrastructure (roads, power supply, waste

    or waste water treatment,

    etc.)

    housing development

    extractive industries

    supply industries

    other

    Yes

    Yes

    Yes

    Appropriate infrastructure like,

    roads, power supply, waste

    management and waste water

    treatment will be developed

    within the site so that chances of

    occurrences of any adverse

    impacts are minimized.

    During construction, about 260

    skilled, unskilled and professional

    work force including temporary

    and permanent employees shall

    be required. This workforce shall

    be hired locally in order to

    generate the employment to the

    local people. While during the

    project operation stage for the

    purposes of day-to-day

    maintenance works about 40

    persons will be employed.

    Moreover, some more

    employment will be created as a

    result of positive induced

    developed in the immediate

    vicinity of project site.

    Not applicable

    Not applicable

    Not applicable

  • 9.2 Lead to after-use of the site, which

    could have an impact on the

    environment

    No Not applicable

    9.3 Set a precedent for later

    developments

    No Not applicable

    9.4 Have cumulative effects due to

    proximity to other existing or

    planned projects with similar effects

    No Not applicable

    (III) Environmental Sensitivity

    S.

    No.

    Areas Name/

    Identity

    Aerial distance (within 15 km.)

    Proposed project location

    boundary

    1 Areas protected under international

    conventions, national or local

    legislation for their ecological,

    landscape, cultural or other related

    value

    None Not applicable

    2 Areas which are important or

    sensitive for ecological reasons –

    Wetlands, watercourses or other

    water bodies, coastal zone,

    biospheres, mountains, forests

    Nangloi

    drain,

    Mamupur

    Reserve

    Forest

    Nangloi drain is located within

    10 km radius from the project

    site, Mamupur Reserve Forest is

    about 0.5 km

    3 Areas use by protected, important or

    sensitive species of flora or fauna for

    breeding, nesting, foraging, resting,

    over wintering, migration

    None Not applicable

    4 Inland, coastal, marine or

    underground waters

    No

    Coastal/

    Marine

    Area.

    Ground

    water is

    present

    There are no coastal or marine

    areas within 15 km radius of the

    site.

    The geology of the area is

    predominated by quaternary

    alluvium consisting of clays,

    occasional kankar, and sand of

    various grades in different depths

    form the main aquifer of ground

    water in the area.

    5 State, National boundaries Yes Haryana boundary is within 1

    KM radius.

    6 Routes or facilities used by the public

    for access to recreation or other

    tourist, pilgrim areas

    No Not applicable

    7 Defense installations No Not applicable

    8 Densely populated or built-up area Yes The project site is located at

    Pocket IB, Sector A1A4, Narela,

  • The site is surrounded by Shree

    atam Vallabh Smarak, Bhaisva

    Lake near Dr. Hedevar Marg,

    Water sports and recreational

    comlex near Dr. Hedevar Marg,

    Mughal Kos Pillar near in

    Shahpur Garhi, Splash water park

    in Alipur, Bawana Stadium in

    Bawana, Aditi Mahavidyalaya in

    Bawana, Bawana Industrial Area,

    Bawana, Delhi Public Schoo in

    Sec. 24, Ryan International in

    Sec. 25, Sanjay Gandhi Memorial

    in Mangolpuri, Kala Mandir in

    Mangolpuri, Surajmal Stadium

    near Nangloi, Delhi College of

    Engineering near Shahbad

    Daulatpur on Bawana Auchandi

    Road, Adventure Island in Sec.

    12, Mutiny Memorial in

    Jahangirpuri, Dilli Haat

    Pitampura etc.

    9 Areas occupied by sensitive man-

    made land uses (hospitals, schools,

    places or worship, community

    facilities)

    Yes Hospitals are available in city and

    Hospital is within 0.5 km from

    the site, such as rajiv Gandhi

    Cancer Hospital, ambedkar

    Hospital, Moris Stopes Hospital,

    sanjay Gandhi memorial

    Hospital, Mahira Hospital,

    Khosla Hospital, Ayurvedic

    Hospital. Small places of worship

    and community facilities within

    the influenced area are Shree

    Atam Smark, Bharti Vidyapeeth,

    Delhi Public School, Ryan

    International School, .

    10 Areas containing important, high

    quality or scarce resources

    (ground water resources, surface

    resources, forestry, agriculture,

    fisheries, tourism, minerals)

    None Not applicable

    11 Areas already subjected to pollution

    or environmental damage. (those

    where existing legal environmental

    standards are exceeded)

    No The ambient air quality results

    show that PM10, PM2.5, level is

    within limits standards

    prescribed by CPCB.

    12 Areas susceptible to natural hazard None The area under study falls in

  • which could cause the project to

    present environmental problems

    (earthquakes, subsidence, landslides,

    erosion, flooding or extreme or

    adverse climatic conditions)

    Zone-IV, according to the Indian

    Standard Seismic Zoning Map.

    Suitable seismic coefficient in

    horizontal and vertical directions

    respectively, has to be adopted

    while designing the structures.

    There are no possibilities of the

    proposed project site getting

    flooded as per records available.

    (IV) Proposed Terms of Reference for EIA studies

    Not applicable, as per the Stage (2) Scoping of Cause 7, S.O. 1533, All projects and activities

    listed as Category „A‟ in item 8 of the Schedule (Construction/Township/Commercial

    Complexes/Housing) shall not require Scoping and will be appraised on the basis of Form I/

    Form IA and the conceptual plan

  • FORM- IA

    Land use

    The proposed project site earmarked for development of CAT-II & EWS Housing is located

    at Pocket IB, Sector A1A4, Narela, New Delhi. Hence no land use change is anticipated as

    per MPD

    Project Site Location

    The proposed project site is located at Pocket IB, Sector A1A4, Narela,, New Delhi under

    the jurisdiction of Delhi Development Authority (DDA).

    Project Site

    The proposed development has been planned in an area of 55,100 SQM.

    1.2. List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs

    etc.

    Land area and Built-up area:

    The site is almost eve in topography and possesses in the area of 55100 SQM. The Housing

    Complex will be constructed as per the defined building by-laws of the Delhi Development

    Authority The proposed Housing Complex will have total built-up area of 2,09,183.78 SQ M

    having F.A.R. of 396.91 for EWS 199.65 for CAT-II and the area statement for the

    proposed EWS & CAT-II Housing Complex is as follows;

    Description Area in (SQM)

    Gross total Site Area 55100

    Net Site Area 54771

    EWS Part : 61.26% of the net area i.e 33551 sqm

    Max Permissible Ground Coverage No Restriction

    Proposed Ground [email protected]% 9099.58

    Max Permissible F.A.R. 134204 (400)

    Proposed F.A.R. 134120.39 (399.75)

    Permissible Built-up Area 134204

    Proposed Built-up Area 126299.47

    Built-up Area under Community 7820.92

    Total proposed Built-up Area 134120.39

    Nos. of Dwelling Units 2860

    Nos. of Block 19

    No of Floors 15-16

    CAT-II Part : 38.74% of the net area i.e 21220 sq m

    Max Permissible Ground Coverage@33% 7002.60

    Proposed Ground [email protected]% 3896.80

    Permissible F.A.R. 42440 (200%).

    Proposed F.A.R. 42403.92 (199.83%)

    Permissible Built-up Area 42440

    Proposed Built-up Area 42403.92

  • Proposed Built-up Area ,community needs 426.11

    Total proposed Built-up Area 42403.92

    Nos. of Dwelling Units 416 Nos

    Nos. of Blocks 04 Nos.

    N0.of Floors 13

    Stilt Area 3331.51

    No of Basements and area 2, 32659.47 SQM

    Total built-up Area (CAT-II+EWS +

    Basements )

    2,09,183.78

    Total Nos. of Dwelling Units (CAT-

    II+EWS)

    3276 Nos.

    Proposed Green Area@40,7 22338.58

    Proposed Vehicular Road Area 11620

    Proposed pedestrian pathways Area 5410

    Parking

    Parking [email protected] for 100 SQm for

    EWS

    646 ECS

    Parking Required@ 2 ECS for 100 SQm for

    CAT-II

    848 ECS

    Parking Proposed 648 ECS for EWS and 886

    ECS FOR CAT-II

    Water Consumption:

    During the construction stage, water will be sourced primarily through tankers arranged by

    the contractor and partly through bore wells only if D J B permits for the same. It is

    estimated that water demand during the construction phase may vary from 10 to 15 KLD for

    drinking purpose and toilets as the project is prefab based and prefab structure will be casted

    in the casting yard.

    During the project operational stage, water will be supplied by DJB and partly Ground

    water only if DJB permits for the same (estimated to be 1326 KLD). This would be supplied

    by DJB through command tanks. Each command tank has its own command area / ground

    water will be used if DJB permits for this. The water demand estimated for the proposed

    Housing Complex is shown in table below.

    Table2: Water Requirement Details

    S.No. Item Description Number of

    inhabitants/

    Population

    Per Capita

    water

    Requirement

    (L/D)

    Total water

    Requirement

    (KLD)

    A. Flushing Water 3276X5=16380 45 737

    B Domestic Water 16380 90 1474

    mailto:[email protected]:[email protected]

  • A+B Total Water Demand 135 2211

    C Horticulture for

    [email protected]/ SQM

    28

    Grand Total (A+B+C) 2239

    Quantity of Sewage disposal/day @80% of total

    domestic demand

    1769

    Treated water available

    @80% of sewage

    generation

    1415

    Requirement of Treated Waste Water From STP

    (Flushing and Horticulture)

    683

    Treated water Extra to be used for sector road side green areas & plantation, Sector greens & Other DDA projects etc

    732

    Wastewater:

    During the Construction stage, For construction work total anticipated labour to be

    employed will be 260 & labor camps will be made for site, Details of labor camp including all facilities.

    There will be temporary houses for the labors.

    There will be temporary canteen facilities for construction labors.

    All construction labors will be provided with Personal Protective Equipments like helmets, gum-boot, and hand gloves, etc.

    There will be separate first aid box in project site office as well as in contractor site office.

    There will be standby ambulance facility for whole construction schedule to deal with any emergency situations.

    There will be tie-up with local nursing home for health screening purposes of the construction labors.

    • Toilet with septic tank facilities will be provided for construction labours during the whole construction period.

    • Fuel for food cooking will be provided

    • For recreation Common Room with TV and indoor games will be provided

    During the operation stage, It has been estimated that approx. 1769 KLD of sewage will be

    generated from the project. The entire sewage will be treated in Common STP of Narela

  • A1A4 of total capacity of 35 MLD located in narela- A1A4. Aprox. 765 KLD of water

    requirement will be met through recycling of STP treated water

    The Developer will provide sewage treatment plant of following capacities base on FAB &

    MBBR process for treatment of sewage & sullage water The treated effluent shall be of a

    quality suitable for flushing & horticulture for external areas.

    SCHEMETIC DIAGRAM FOR PROPOSED STP

    Parameters Inlet Water Characteristics Outlet water Characteristics

    pH 7.5-8.5 6.0-8.0

    BOD 5 day, 21OC 200-250 mg/l Less than 10 mg/l

    Suspended Solids 200-400 mg/l Less than 5 mg/l

    COD 500-600 mg/l Less than 30 mg/l

    Oil & Grease 20 mg/l Less than 2 mg/l

    Temperature Ambient

    Power Requirement:

    The total connected load as per NDPL is calculated to be around say, 23100 KW and

    after@ 0.4 D.F. it will be around 9300 KW & after considering P.F. & 70% loading ,the

    reqd. transformer rating shall be 14200 KVA for this Housing Complex.

    Power will be supplied by NDPL.

    For Emergency purposes backup is proposed by using DG Sets

    (4 x 82.5+4x30+1x250) KVA

    For water supply pumps purposes backup is proposed by using DG Sets (2x45 KVA).

    The DG sets will be provided with AMF panels. Fuel consumption for DG sets has been

    calculated to be 20 ltrs/hr of HSD (Low sulphur variety). As per the latest CPCB norms, DG

    sets have to be installed in acoustic enclosures and silencer.

  • Connectivity:

    The Project site is located at Pocket IB, Sector A1A4, Narela having a Latitude 28O 34‟ 45”

    N and longitude 77O 07‟ 30” E., adjacent to NH- 1 Connecting Delhi with Faridabad .The

    site is within Narela, which is one of the best planned new township of Delhi and is located

    in the North West part of the State. Connected well with AIR, RAIL and ROAD to all major

    towns of India

    Community Facilities:

    In order to fulfill the daily basic needs of resident population as well as step in population,

    convenient shopping and community room-facility are planned for both categories.

    For CAT II the community needs specifies the Senior Citizen Rm, Recreation crèches &

    reading rm. is total of 426 .11 SQ M. which is free from FAR.

    For the EWS part the community needs specifies the Basti viakas Kendra, Health centre , the

    Religious Space, Police post, community hall etc provided for this category.

    Chowkidar Hut of 10 SQM, reqd. nos. of ESS of 10 X 8MT each, 2 no. Pump House has

    been planned, and also, provision for facilities such as water supply, power lines, better road

    & green belts etc has been proposed within the project premises.

    Parking needs:

    For the Housing Complex ample parking space will be provided as per norms. For the EWS

    category 648 ECS @ 0.5ECS/100 sqm. built-up area have been provided as open surface

    parking. For CAT-II 886 ECS @ 2 ECS/100 sqm. built-up area have been provided under the

    stilt area and basement.

    1.3. What are the likely impacts of the proposed activity on the existing facilities adjacent to

    the proposed site? (Such as open spaces, community facilities, details of the existing land

    use, disturbance to the local ecology).

    Impact on Land use pattern

    The project will be established on designated area. And there will be no displacement or

    resettlement of people from the acquired land. The land is not a forestland and no tree will be

    uprooted. Therefore, the predicted impacts on the land use pattern of site will be

    insignificant.

    Impact on ecological setting

    The impact due to construction activities on the ecology of the area will be confined to the

    construction site itself. There will be negligible impact on the ecology (flora & fauna) during

    the construction phase. As there is no forest in and around the proposed site, no impact is

    anticipated on the fauna. However, no adverse impact is anticipated on the ecology due to the

    proposed Housing complex.

  • No significant air pollutants air emissions will be discharged from the project. Therefore,

    there will be insignificant impacts on the flora and fauna due to the operation of the project.

    There will be very little SP M, SO2 and NOX emission from the proposed Housing activity.

    The entire project influenced area will be developed as per the Master Plan Delhi

    Development Authority, thus no induced development is foreseen due to the proposed

    project. Also the proposed development shall be carried out as per the defined building by-

    laws; hence no impacts are envisaged due to proposed development.

    Moreover, proposed project will be provide value addition to the existing infrastructure

    facilities such as improve public transportation system, telecommunications, power lines,

    better roads security etc.

    Further, during the construction as well as operation stage of the project, will generate direct

    and indirect employment opportunities for a large section of society. The employment will

    have positive impact thereby increasing the quality of life.

    1.4. Will there be any significant land disturbance resulting in erosion, subsidence &

    instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc

    may be given).

    Soil Type:

    In order to understand the existing scenario of soil quality in the study area of project site,

    Soil sample were collected from project site based on the collected Soil Map for the area,

    Existing Land use of the Area, sources of pollution etc. Samples were taken from one

    location based on the above said criteria. The baseline concentrations of important

    parameters like organic matter, nitrogen content and phosphate etc. indicate that soil in the

    study area has good productivity potential and sandy silt in texture. Table 3: Physio-Chemical Characteristics of Soil

    S. No. Parameter Project Site (Narela)

    1 pH 7.96

    2 Texture,%

    3 Sand 29.9

    4 Clay 5.4

    5 Silt 64.7

    6 Organic Matter,% 1.27

    7 Water Holding Capacity, % 16.5

    8 Conductivity (micro S/Cm) 336

    9 Nitrogen as N (mg/kg) 832

    10 Phosphate (as P2O5), (mg/kg) 263.5

    11 Potassium as K, (mg/kg) 71.2

    12 Sodium as Na (mg/kg) 387

    13 Magnesium as Mg (mg/kg) 632

    14 Calcium as Ca (mg/kg) 6.117

  • Slope Analysis: The project area possesses fairy plain terrain with drainage slope towards South-Eastern side

    of the project site.

    Total Station Survey was carried out not only for project site but also surrounding area.

    Erosion / Subsidence:

    Proper greening & paving of area will not cause any soil erosion problem and subsidence.

    Seismicity:

    The area under study falls in Zone-IV according to the Indian standard Seismic Zoning Map.

    Suitable seismic coefficients in horizontal and vertical directions respectively, have to be

    adopted while designing the structures.

    1.5. Will the proposal involve alteration of natural drainage systems? (Give details on a

    contour map showing the natural drainage near the proposed project site)

    The proposed project activities will not cause any alteration of natural drainage system.

    1.6. What are the quantities of earthwork involved in the construction activity-cutting, filling

    reclamation etc. (Give details of the quantities of earthwork involved, transport of fill

    materials from outside the site etc.)

    During construction phase, some excavation is envisaged in order to provide foundations and

    basement. This excavated soil (app. 5386 m3) will be properly stacked within the site under

    tarpaulin cover; and will be reused for backfilling purpose, road construction etc. The top-

    soil will be preserved separately and will be used for landscaping purpose only. Hence no

    immediate adverse impacts on the land environment are envisaged.

    1.7. Give details regarding water supply, waste handling etc during the construction period.

    Water Supply

    During the construction stage, water will be sourced primarily through tankers arranged by

    the contractor and partly through bore wells only if D J B permits for the same.

    Waste Generation / Handling

    Soil excavated will be reused for backfilling and the fertile top soil will be reused for

    horticultural purpose. Spillage of oil from the machinery or cement residual from concrete

    mixer plants will be properly collected and disposed off. For construction laborers, proper

    sanitary facilities & wash areas will be constructed and good hygienic conditions will be

    maintained.

    1.8. Will the low lying areas & wetlands get altered? (Provide details of how low lying and

  • Wet lands are getting modified from the proposed activity)

    No Low lying and wetlands areas are present in and around the project site.

    1.9. Whether construction debris & waste during construction cause health hazard? (Give

    quantities of various types of wastes generated during construction including the construction

    labour and the means of disposal)

    Construction and pre-operational cleaning of the proposed facility would generate limited

    amounts of some waste solvents and flushing materials. A licensed contractor would remove

    these materials for appropriate off-site disposal as discussed below The hazardous / non

    hazardous waste shall be subjected to proper segregation, reuse / recycle, disposal and proper

    documentation.

    Solid waste and debris that cannot be recycled, reused, or salvaged would be stored in on site

    dumpsters or similar containers for disposal. Potentially hazardous wastes would be

    separated from normal waste including segregation of storage. All waste from the project site

    would be removed in accordance with applicable regulatory requirements.

    During construction, all chemical materials would be evaluated during the material receiving

    process. Materials that are hazardous would be stored in identified storage areas that include

    containment measures. Personal would be rained on the proper use, handling, protective

    equipment, storage, and disposal of hazardous materials. A health and Safety Plan would be

    developed and implemented to insure that the potential for exposure of construction workers,

    workers on near by sites, and others in the area is minimized. The health and safety plan

    would define worker safety training, monitoring procedures, and personal protective

    measures. The construction phase would require use of various petroleum and chemical

    products, including medium- weight oil, thinners, solvents, paint, gasoline and diesel.

    The hazardous Waste is stored in leak proof container (s) and able to drain / remove liquids,

    and the containers are duly marked with “Hazardous Waste “in red colour an with date of

    beginning of storage on each containers. These Hazardous Waste containers are stored on

    pucca floor in an isolated covered area in the unit in such a manner that it does not in any

    way contaminate the environment or the ground water due to air/rain/ seepage/ leakage etc.

    That storage facility is having appropriate containment system. Care will be taken

    precautions to prevent any accidental ignition or reaction of ignitable or reactive waste.

    The construction debris generated from the construction project will be common place in

    nature and will not cause any health hazard to associate and nearby population. The

    construction debris will be used for land leveling / backfilling and landscaping according to

    its composition.. Waste concrete will be reused as aggregate in construction process. Total

    construction waste general is estimated as following: -

    Table 4: Details of Wastes Generated during Construction Phase

    Particular Approx. Qt.(in MT)

    Soil, Sand, Concrete & Gravel 15-20

    Metals 3-5

  • Bitumen 1-3

    Source: as per CPHEED manual of Municipal Solid Waste Management and TIFAC Report

    Abstract on Construction Industry.

    Approx. 260 labours will be used during the construction period. Proper sanitary facilities

    will be provided to construction laborers through moveable Sulabh Souchalaya and treatment

    will be done using septic tank. Wash areas will be constructed and good hygienic conditions

    will be maintained.

    2. WATER ENVIRONMENT

    2.1. Give the total quantity of water requirement for the proposed project with the breakup of

    requirements for various uses. How will the water requirement met? State the sources &

    quantities and furnish a water balance statement.

    Please refer to Clause no. 1.2 of Form IA for CAT-II & EWS Housing Complex project

    regarding details of water quantity, sources and wastewater generation. Kindly refer as given

    below for water balance diagram of proposed project.

    Water Storage:

    Storage will be provided for one day‟s requirement. In order to ascertain the quantity of

    water consumed, the supply will be through the water meter installed in the supply line. The

    water main will be fed into Fire Fighting storage tanks with total capacity and from these

    compartments the water will be allowed to overflow into Raw water Tanks, from the Raw

    Water Tank, water will fed through a Water Treatment Plant and will be pumped into Treated

    Domestic Water Tank. All the underground water tanks will be with adjacent pump room,

    which will be located about 600 mm below tanks in order to ensure a positive suction to all

    pumps. Half of the water storage will be done in overhead tanks in the proposed project.

    2 No. of underground tank of 370 KL each for proposed flushing water tanks and 2 No. of

    737 KL for proposed domestic water tanks will be provided. All the buildings shall have bulk

    overhead storage equivalent to half day consumption.

    The liquid effluent of 1793 KLD will be treated in common STP of Narela -A1A4 of total

    capacity 3.5 MLD, located in Narela -Sector A1A4.

    2.2. What is the capacity (dependable flow or yield) of the proposed source of water?

    Daily water demand for the Housing Complex has been calculated to be about 2239 KLD.

    Water demand will be met from DJB and partly through bore wells only if D J B permits for

    the same.

  • 2.3 What is the quality of water required, in case, the supply is not from a municipal source?

    (Provide physical, chemical, biological characteristics with class of water quality):

    Water will be supplied by DJB and partly Ground water only if DJB permits for the same.

    Status of water quality in project-influenced area has been shown below in Table 5:

    Table: Water Quality in Project Influenced Area

    S. No. Parameter Bore well at Project site (Narela)

    1 Colour (in hazen unit) 02

    2 Odour Unobjectionable

    3 pH 7.2

    4 Total. Hardness, mg/l 248

    5 Chlorides, mg/l 17

    6 Fluorides, mg/ 0.4

    7 TDS, mg/l 570

    8 Calcium, mg/l 51

    9 Magnesium, mg/l 26

    10 Sulphate mg/l 9.5

    11 Nitrate, mg/l 0.5

    12 Total. Alkalinity, mg/l 183

    13 Arsenic, mg/l

  • 2.5. Will there be diversion of water from other users? (Please assess the impacts of the

    project on other existing uses and quantities of consumption):

    There will not be any substantial effect on water demand of this region due to proposed

    project activity development will be as per the master plan and the peripheral services at the

    sector level are already approved by DJB / MCD

    2.6. What is the incremental pollution load from wastewater generated from the proposed

    activity? (Give details of the quantities and composition of wastewater generated from the

    proposed activity):

    The liquid effluent of 1793 KLD will be treated in common STP of Narela -A1A4 of total

    capacity 3.5 MLD, located in Narela -Sector A1A4.

    Table 6 below shows the expected characteristics of wastewater.

    Table 6: Characteristics of Domestic Wastewater

    Parameter Expected Wastewater

    Characteristics

    Treated Wastewater

    Characteristics

    pH 7.5-8.5 6.0-8.0

    BOD 5 day, 21OC 200-250 mg/l Less than 10 mg/l

    Suspended Solids 200-400 mg/l Less than 5 mg/l

    COD 500-600 mg/l Less than 30 mg/l

    Oil & Grease 20 mg/l Less than 2 mg/l

    Temperature Ambient

    2.7. Give details of the water requirements met from water harvesting? Furnish details of the

    facilities created.

    Water Harvesting will be done as per design enclosed for recharging the ground water level.

    The entire site is provided with planned underground drainage system with final disposal to a

    natural drainage system of the area providing protection of the site from flooding,

    water logging and preventing soil erosion.

    1. Rainwater from the entire complex is proposed to be harvested from Roof and from

    surface and landscape areas.

    a) Rainwater harvested from surface areas, roads and driveways and landscape will be first filtered in filter chambers having gravel and coarse sand as filter media .The RW

    will be connected to twelve recharge wells constructed as per the specifications of the

    central ground water board.

  • 2. Rainfall data (Refer Sheet 1 of 2)

    RAIN WATER HARVESTING CALCULATION FOR THE CAT-II & EWS

    HOUSING NARELA, NEW DELHI

    Total Terrace Surface Area - 14417 m²

    Total Green Area - 22338 m²

    Total Hard paved area - 18015m²

    Total yearly Rainfall - 660 mm

    No of rainy days per year - 30 days

    Total Rainfall per day - 23.8 mm

    SAY - 24 mm

    Average Hrs / Day of Rainfall - 2.5 Hrs.

    Peak - 0.035m//hr

    Run off coefficient for Green area - 0.25

    Run off coefficient for Hard paved area - 0.80

    Run off coefficient for Terrace - 0.85

    Peak Flow for Green area - 22338 x 0.25 x 0.035

    195 m³ / Hr

    Peak flow for Hard paved area - 18015 x 0.80 x 0.035

    504 m³ / Hr

    Peak flow for Terrace - 14417 x 0.85 x 0.035

    429 m³ / Hr

    Total Flow except peak - 1128 m³ / Hr

    Evaporation Loss 20% - 1128-226

  • - 902 m3/hr -

    Taking 15 mi as peak rain 902X0.25= 226 m3.hr

    Average throughout using 400mm diameter

    pipe with flow velocity of 0.15 m/Sec. - 71.1 m³ / Hr

    No of pits based on 18 m³ / Hr - 3.17Nos.

    Provided - 6 Nos.

    storm water from terraces and other open areas will be collected through rainwater down take

    pipes and connected to nearest deep drain with 100-200 mm dia pipes. The rain water will be

    collected by catch manholes with minimum depth of 600 mm and slope of 1:350 towards

    main drain with 300 mm dia PVC pipes and PCC cover. Open drains with perforated RCC

    cover will be places at every 3 m interval. The channels will lead to approx. 06 nos. rain

  • water harvesting pits, located at different locations around the premises. The size of rain

    water harvesting pits is 5x53m with desilting chamber 1.5x3m with 5 m effective depth. The

    pits will be laid with 500 mm thick layer of 1.5-2.0 mm average dia coarse sand, over 500

    mm thick layer of 5-10 mm dia gravels, which, in turn will be laid on 500 mm thick layer of

    10-30 mm dia loose boulders. A perforated PVC pipe, laid inside bore; will transfer the

    excess rain water to sandy layer. Casing will be provided with cleansed pea gravel of 3-6 mm

    average dia. The run-off from roads and parking area is provided with oil & grease trap

    system.

    For collecting storm water, storm water drainage network has been provided during the

    design stage as per the guidelines defined in Master Plan of Delhi City. In the project design,

    it shall be ensured that no mixing of the storm water with waste effluent takes place. All the

    storm water will be diverted to rain water – harvesting pits proposed in the complex. Roof

    rain water harvesting potential for the proposed project site is 1769.518 m3/hr. The excess

    rain water is disposed to the municipal storm water line as per the site condition. Diagram of

    typical rainy well is shown below:

    2.8. What would be the impact of the land use changes occurring due to the proposed project

    on the runoff characteristics (quantitative as well as qualitative) of the area in the post

    construction phase on a long term basis? Would it aggravate the problems of flooding or

    water logging in any way?

    No adverse impacts are envisaged due to proposed project on the runoff characteristics of the

    area as adequate arrangements will be made to trap & treat the rainwater and suitable storm

    water drainage system will be provided.

    During the post-construction phase, runoff from the project shall not be allowed to stand or

    enter into the roadside or nearby drain. Adequate measures (as discussed in Clause 2.7) shall

    be take to collect such runoff and either shall be reused or stored in recharging pits suitable

    garlanding drain as per the existing contours of the pot will be developed.

    2.9. What are the impacts of the proposal on the ground water? (Will there be tapping of

    ground water; give the details of ground water table, recharging capacity, and approvals

    obtained from competent authority, if any):

    As detailed out in Clauses 2.2, 2.3 and 2.5.

    2.10. What precautions/measures are taken to prevent the run-off from construction activities

    polluting land & aquifers? (Give details of quantities and the measures taken to avoid the

    adverse impacts)

    The best way of minimizing sediment loss from a construction site is to control the erosion in

    the first place. Sediment control measures that capture eroded soil (for example, hay bales

    and silt fences) are frequently limited in their effectiveness.

  • Erosion will be controlled by the following steps.

    Clean 'run-on' water will be diverted from upslope around the disturbed area. Care will be taken to ensure that such diversion of storm water above the disturbed area

    does not itself cause flooding, erosion or scour.

    Vehicle will be restricted to access to one stable entry and exit point.

    Preserving grassed areas and retains the maximum cover of natural vegetation by minimizing the amount of land disturbed by shaping. Mulch or revegetate disturbed

    areas as soon as possible.

    It will be ensured that stockpiles of sand, gravel, soil and similar materials are located so that material:

    - does not spill on to the road or pavement

    - is not placed in drainage lines, depressions or watercourses

    - cannot be washed into roadways, drainage lines, depressions or watercourses.

    Accidental spills of soil or other materials on the roadway or gutter will be removed daily.

    Excess materials and water from cleaning tools and equipment down storm water drains will be avoided.

    Minimize on-site vehicle activity during wet weather or when the site is muddy.

    Sediment control measures

    Sediment control structures aim to capture sediment or other pollutants washed from the land

    surface, thereby stopping them getting into receiving waters. As previously mentioned, it is

    far better to prevent erosion in the first place than to rely on sediment control.

    However, construction activities inevitably involve some land disturbance. Sediment control

    measures are therefore an essential part of construction site management.

    Sediment can be controlled by sediment basins, sediment traps or sediment filters.

    Sediment basins and/or the smaller sediment traps are excavations with a barrier or bank that

    may be constructed from a broad range of materials, including earth, gabions and rock, lined

    with geotextile material . Sediment basins and traps are generally used to treat channelised

    flow, generally by a combination of settling and filtration.

    It is imperative that sediment controls, whether basin, traps or filters ,be regularly ,inspected

    and maintained to ensure effective operation.

    During the construction phase, runoff from the construction site shall not be allowed to stand

    or enter into the roadside or nearby drain. Adequate measures shall be taken to collect such

    run off and either shall be reused (if possible) or disposed at the designed construction waste

  • disposal location. Suitable garlanding drain as per the existing contours of the plot will be

    developed.

    2.11. How is the storm water from within the site managed?(State the provisions made to

    avoid flooding of the area, details of the drainage facilities provided along with a site layout

    indication contour levels):

    As detailed out in Clause 2.7.

    2.12. Will the deployment of construction labourers particularly in the peak period lead to

    Unsanitary conditions around the project site (Justify with proper collection explanation):

    Proper sanitary facilities like common bath place, temporary toilets etc. will be provided to

    laborers and treatment will be done using septic tank.

    2.13. What on-site facilities are provided for the, treatment & safe disposal of sewage? (Give

    details of the quantities of wastewater generation, treatment capacities with technology &

    facilities for recycling and disposal)

    Domestic Wastewater Disposal:

    The liquid effluent of 1793 KLD will be treated in common STP of Narela -A1A4 of total

    capacity 3.5 MLD, located in Narela -Sector A1A4.

    2.14. Give details of dual plumbing system if treated waste used is used for flushing of toilets

    or any other use.

    Not Applicable

    3. VEGETATION

    3.1. Is there any threat of the project to the biodiversity? (Give a description of the local

    ecosystem with it‟s unique features, if any):

    There are no major wild life sanctuaries/parks within 10 km radius of the project site. Neither

    any rare or endangered species have been recorded in the project influence area. There is no

    notified natural forest area in the North West District. The Delhi NCR region falls under a

    transition zone between the North Western Thorn Scrub Forest(IM1303) ecoregion and

    Upper Gangetic Plains moist deciduous forests (IM0166) ecoregion, as delineated by World

    Wildlife Fund for Nature (WWF). This transition zone bears characteristics of both the

    ecoregions, and varies gradually from east to west. The study area represents the thorn scrub

    forests in north western region of the Indian subcontinent. Many ecologists consider this

    thorn scrub to represent a degraded state of tropical dry forests (Champion and Seth,1968;

    Puri et al. 1989).

    Babool (Acacia spp.), Eucalyptus (Eucalyptus hybrid), Shahtoot (Morus alba), Neem

    (Azadirachta indica), Seemal (Bombax Ceibs),Aswath (Ficus bengaensis), Bel (Aegle

  • marmelos) Amaltash (Cassia fistua), Sahjan (Moringa oleifera), Peepal (Ficus reCAT-IIiosa),

    Gulmohar (Delonix regia) are among the common dominant tree species found in the study

    area.

    Other than the large trees, some shrubs could also be located in the study area,dominated by

    Thevetia nerifolia, Langerostomia speciosa, Lantana camara etc. Lower no flowering plant

    forms and cryptogamous vegetation are absent during the time of study. Climbers and lionels

    were fewer in number.

    The ecology of the study area is not very rich in diversity or high in endemism which may be

    primarily accounted for the scattered distribution of poor quality and quantity of fodder. The

    major mammalian fauna of the project influenced area involve common languor, Rhesus

    macaques (macaqua mulata) mongoose (Herpestris edwardii) etc. Avifauna is primarily

    represented by Common crow (Corvus spendens), House sparrow (Passer domesticus), bue

    rock pigion(Columba livia), Rose ring paraqeet (Pitecula cramerii),spotted doves

    (Streptopelia chinensis) and finches. Common peacock (Pavo cristatus), are known to be

    present in the area. Small reptiles; primariy squamateslike izards,chameleons, poisionous &

    non-poisionous snakes are also found in the study area.

    Amphibians and fishes are primarily restricted to the water logged and marshy areas. This

    might account for their significant absence in the project influenced area. However the study

    area represents densely distributed human habitation. Lack of suitable habitat and proper

    food & fodder has lead away most of the faunal variety away from human habitations.

    No endangered or endemic species (as notified in IUCN Red Data Book) are located within

    the study area. No migratory birds breed in the study area. No Tiger reserve/ elephant reserve

    / turtle breeding place is located within 15 km radius of the study area.

    3.2. Will the construction involve extensive clearing or modification of vegetation? (Provide

    a detailed account of the trees & vegetation affected by the project):

    The proposed site is an open land which has been earmarked under Residential Landuse in

    Master Plan of Delhi.

    3.3. What are the measures proposed to be taken to minimize the likely impacts on important

    site features (Give details of proposal for tree plantation, landscaping, creation of water

    bodies etc along with a layout plan to an appropriate scale):

    There will not be any kind of impact of this project on site features. The Green Belt for the

    proposed project has been planned in an area of 43097 SQM(46.59%) to provide a clean,

    healthy and beautiful green environment for the people to live in and work in. Within the

    proposed project site green bet area has been designed to achieve a blend between modern

    building and various species of plants shrubs to create a clean, healthy and aesthetic

    environment that provides a visual retreat and relaxation to the occupants of these buildings.

    A combination of evergreen trees and deciduous species is used I these complexes. Some of

    the species are as follows: -

  • Table 7: Generally Used Pant Species for landscaping

    A) Evergreen Species

    Scientific Name Common name

    1) Alstonia scholaris Devil‟s tree

    2) Callistemon sp. Bottle brush

    3) Michelia champaca Sita Ashok

    4) Pumeria aba Champa

    5) Roystoea regia Royal Bottle plant

    6) Washngtonia filifera Petticoat palm

    B) Deciduous Species

    1) Bauchinia varegata Kachnar

    2) Cassia fistula Amaltas

    3) Cassia nodosa Pink cassia

    4) Erythrina blackii Tota

    5) Schleichera trijuga Kusum

    6) Tabebuia rosa Pink tabebuia

    The planting arrangement should be based on optimal use of available land and quantum of

    irrigation water and treated wastewater. It is recommended that tree plantation (large size

    species) should be undertaken at the time of preparation of the site so that they would grow

    to considerable size by the time of commissioning of the proposed project.

    Kindly refer for landscaping plan of proposed CAT-II & EWS Housing Complex.

    4. FAUNA

    4.1. Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of

    barriers for their movement? Provide the details.

    The proposed site is an open land and devoid of forestation, so in existing conditions, this

    pace is not the habitat for local fauna. There will not be any type of displacement or any

    other effect on the local fauna due to proposed project activities.

    4.2. Any direct or indirect impacts on the avifauna of the area? Provide details.

    Within the proposed project site, proper landscaping has been panned to provide a clean,

    healthy and beautiful green environment for the people to live in and work in. Common

    native variety of trees and ornamental flowering species will be planted in the green space.

    Landscaping can have direct positive impact on the local avifauna, as this will provide shelter

    to local birds.

    4.3. Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on

    fauna:

    These measures are applicable for this project.

  • 5. AIR ENVIRONMENT

    5.1. Will the project increase atmospheric concentration of gases & result in heat islands?

    (Give details of background air quality levels with predicted values based on dispersion

    models taking into account the increased traffic generation as a result of the proposed

    constructions):

    Increased traffic generation 435 no. of vehicles due to project is not going to cause

    significant increase in atmospheric concentration of gases and will not result in heat island

    formation.

    5.2. What are the impacts on generation of dust, smoke, odorous fumes or other hazardous

    gases? Give details in relation to all the meteorological parameters.

    Air Pollution Dispersion Relationship with Meteorology

    The measurements of wind speed and direction, temperature, humidity, rainfall and solar

    radiation are important parameters used in the study of air quality monitoring results and to

    further understand the chemical reactions that occur in the atmosphere. Meteorological

    monitoring is used to protect air pollution events such as inversions, high pollutant

    concentration days and to simulate and predict air quality using computer models.

    Wind Speed and Direction

    The region has a semi-arid climate with extreme seasons, hot summers, and heavy rainfall in

    the monsoon months and very cold winters. The mean monthly temperature ranges from

    14.3OC in January (minimum 3

    OC) to 34.5

    OC in June (Maximum 47

    OC). The annual mean

    temperature is 25.3OC (WMO 1971)

    Dust storms occur frequently during the summer months, leading to a build-up of particulate

    matter in the atmosphere.

    The monsoon period is favorable from the pollution point of view due to the frequent

    washout of pollutants along with rain. Mixing height is an important parameter that

    influences the dilution of pollutants. It varies diurnally as well as seasonally.

    During the construction and operation phase of proposed project, air pollution causing agents

    can be vehicular movement and occasional use of DG sets.

    Stacks for DG Sets will be provided with proper height as per CPCB Guidelines and

    emissions from DG sets will meet the stipulated norms as per NAAQM.

    5.3. Will the proposal create shortage of parking space for vehicles? Furnish details of the

    present level of transport infrastructure and measures proposed for improvement including

    the traffic management at the entry & exit to the project site.

  • For the Housing Complex ample parking space in the open area has been provided. With the

    consideration of surface parking, provision for parking will be provided for 648 ECS FOR

    EWS and 886 ECS for CAT-II in open area at ground surface 2 level basements.

    .

    5.4. Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian

    pathways, footpaths etc., with areas under each category.

    The total area is dedicated to roads, i.e. proposed vehicular road Area is 11620 SQM &

    proposed pedestrian pathway area is about 5410 SQM area will be under roads. In the project

    provision, wide service road is made for the smooth traffic movement. Internal roads with

    suitable width have also been provided. Adequate CAT-II arrangement has been provided

    covering al corners.

    5.5. Will there be significant increase in traffic noise & vibrations? Give details of the

    sources and the measures proposed for mitigation of the above.

    The prime sources of noise levels during the construction phase are the construction

    machinery and the vehicular noise. The effect of noise would be significant during day time,

    the residential area located in the near vicinity of the construction site may increase in the

    day time as well as night time ambient noise levels.

    Mitigation Measures

    The main stationary noise producing sources such as generators should be provided with

    noise shield around them.

    For protection of construction workers, earplugs should be provided to those working very

    close to the noise generating machinery.

    (a) Suitable damping the air compressor noise

    (b) Silencers/mufflers in the air compressor and DG sets should be provided

    (c) Regular preventive maintenance of pumps and other rotating equipments

    will reduce the noise levels.

    During the operation stage, there would be a minor increase in ambient noise levels in and

    around the site due to Housing activities there will be quiet large no of population.

    Mitigating Measures

    Development of Greenbelt around the CAT-II & EWS Residential complex can bring a

    considerable reduction in noise levels;

    During night & day time use of horns should be restricted

    The noise generation levels will be confined within the surrounding area of construction site

    and unlikely to affect the area 100 m away form the site. Construction period is only for

    about two years, hence there will be short term, localized and reversible impact on ambient

    noise levels during the construction activity.

  • Acoustic barriers should be placed near construction sites.

    The maximum noise levels near the construction site should be limited to 75dB (A) Leq (5

    min.) in industrial areas and to 65 dB (A) Leq (5 min.) in other areas.

    There should be fencing around the construction site to prevent people coming near the

    site.

    Materials need not be stockpiled and unused equipment to be placed between noisy

    operating equipments and other areas.

    Constructing temporary earth bund around the site using soil etc, this normally is hauled

    away from the construction site.

    It is envisaged that there shall be maximum movement of CAT-IIht motor vehicles and 2-

    wheelers inside the Residential Complex, hence this will have insignificant rise in noise

    level. Moreover, this will be further minimized by plantation on the sides of internal roads,

    on the open spaces inside and around the periphery of whole Residential Complex. Proper

    maintenance of the internal roads will be carried out and informatory signboards shall be

    provided to encourage vehicle owners to maintain their vehicle, not to bow horns and follow

    the emission standards fixed by Government Authorities.

    5.6. What will be the impact of DG sets & other equipment on noise levels & vibration in &

    ambient air quality around the project site? Provide details.

    Stacks for DG sets will be provided with proper height as per CPCB Guidelines and

    emissions from DG sets will meet the stipulated norms as per NAAQM. Noise emission from

    DG sets will meet the noise levels as per CPCB Guidelines.

    6. AESTHETICS

    6.1. Will the proposed constructions in any way result in the obstruction of a view, scenic

    amenity or landscapes? Are these considerations taken into account by the proponents?

    The land allocate for proposed project has been earmarked for the development of Housing

    Complex, hence no such adverse impacts are envisaged.

    6.2. Will there be any adverse impacts from new constructions on the existing structures?

    What are the considerations taken into account?

    The development in the entire project influenced area is as per the approved master plan of

    Delhi and will be as per the provisions of Delhi Development Authority. Hence no adverse

    impacts are anticipated from new constructions on the existing structures in this area.

    6.3. Whether there are any local considerations of urban form & urban design influencing the

    design criteria? They may be explicitly spelt out.

  • There are no local considerations of urban forms & urban design influencing the design

    criteria. The proposed site falls under the area of approved Master Plan of Delhi. The housing

    Complex project will be constructed within the designated as per the defined building by-

    laws of Delhi Development Authority.

    6.4. Are there any anthropological or archaeological sites or artifacts nearby? State if any

    other significant features in the vicinity of the proposed site have been considered.

    Within the project influence area, there are no significant archeological properties. Since all

    the activities whether during the construction or operation stage, will be carried out in the

    project premises, hence no impacts on any type of archeological monuments are envisaged.

    7. SOCIO-ECONOMIC ASPECTS

    7.1. Will the proposal result in any changes to the demographic structure of local population?

    Provide the details.

    Establishment of any residential project leads to socio-economic changes. Influx of

    population leads to change in economic status of the community. The peak labour force will

    be about 260 during the construction period.

    Employment potential

    For the proposed activity, the proposed activity is required to employ over 260 persons and

    number of manpower, is also required to increase indirectly in various other activities during

    the construction phases. Thus increasing the employment opportunities for local population.

    Other activities also help the local population in terms of employment.

    Significant number of permanent employees shall also be required during the operation phase

    of the mall. Some of the areas, which directly offer the job potential, are, parking attendants,

    sanitation workers, venders and hawkers.

    Economy of the region

    The increasing facilities in the transportation help to improve the economy of the area. Many

    people are involved in various unit related activities directly or indirectly and help to improve

    the general economic base of the region as a whole.

    The operation of the project shall provide value addition to the existing infrastructure, as due

    to development of the Housing Complex, facilities such as public transport, water supply,

    telecommunications, power lines, road maintenance etc. shall be upgraded in and around the

    project premises.

    The operation of project and other allied facilities, will improve the employment

    opportunities. During construction about 260 total skilled, unskilled and professional work

    force including temporary and permanent employees will be required per day. This work

    force will be hired locally in order to generate the employment to the local people. While

  • during the project operation stage for the purposes of day-to-day maintenance works about

    40 persons will be employed.

    Due to operation of proposed project, there will be enhancement in pubic health and safety.

    All fire and safety measures suggested by Government Authorities will be taken and regular

    mock drills will be conducted at the project site. Regular health check up will be carried for

    persons working near DG sets and security guards.

    Infrastructure Services in the Region:

    Schools

    The study area has adequate facility of education; there are several primary and secondary

    schools located in the area. The educational facilities are provided in stages i.e. junior basic

    school, senior basic school, higher secondary school, degree colleges, Polytechnic. Pre-

    primary and primary educations are mainly the responsibility of local bodies. Middle,

    secondary and senior secondary education is primarily looked after by Directorate of

    education, Government of Delhi. Delhi College of Engineering, Delhi public school, Ryan

    international School, Aditi mahividyalaya in Bawana, Kala Mandir, Keshav Mahidayala are

    within 10 km distance

    Tele-Communication

    Three Telephone exchange is provided at District level, Telecommunication facility in the

    study area is adequate; electronic telephone exchange is working in the study area, and

    mobile facility is also available. Delhi is connected with one of the best telecommunication

    networks in India.

    Roads and Transportation System

    The project area is having high road density. It is connected by a network of state level and

    internal roads to the entire region. There are more roads which link Punjab, HARYANA, UP,

    RAJASTHAN, i.e. GT Road, NH-1, Bawana Auchandi road, Khanjawala road, Bhagwan

    Mahavir Marg, guru Nanak dev Marg, Budh Vihar Marg, Mubarakpur main road, Road No.

    43, Outer Ring road, Ring Road etc within 10 km distance

    Post-Office

    Postal facility is available at town.

    Banks The study Area is having branches and ATMs of al major nationalized as well as privatized

    banks. In addition to leading international banks, almost all nationalized and private sector

    banks have branches in Delhi many with ATM centers. Financial Institutions are equally well

    represented, as is the insurance sector with every nationalized company operating a branch

    here.

  • Hospital The Health & Family Welfare Department of Govt. of Delhi. caters to health needs of this

    region and also has to share the burden of migratory as well as floating population from

    neighboring districts .

    Medical facilities abound with multi-speciality hospitals, nursing homes and other health-

    care centers all over Delhi . Catering to the citizens` health needs are: Rajiv Gandhi Cancer,

    Jaipur Golden, Ambedkar, Max Hospital, Moris Stopes, Khosla, sanjay Gandhi Memorial,

    Jaipur golden, Ayurvedic hospital are available within 10 km radius.

    Other features within 10 km boundary of the site.

    i) Shree atam Vallabh Smarak about 5 km

    ii) Bhaisva Lake near Dr. Hedevar Marg about 8 km.

    iii) Water sports and recreational comlex near Dr. Hedevar Marg about 8 km.

    iv) Mughal Kos Pillar near in Shahpur Garhi about 4.5 km.

    v) Splash water park in Alipur about 5 km.

    vi) Bawana Stadium in Bawana about 6.5 km.

    vii) Aditi Mahavidyalaya in Bawana about 4.5 km.

    viii) Bawana Industrial Area, Bawana about 3 km.

    ix) Delhi Public School in Sec. 24 about 4.5 km.

    x) Ryan International in Sec. 25 about 3.5 km.

    xi) Sanjay Gandhi Memorial in Mangolpuri about 7 km.

    xii) Kala Mandir in Mangolpuri about 6.5 km.

    xiii) Surajmal Stadium near Nangloi about 9 km.

    xiv) Delhi College of Engineering near Shahbad Daulatpur on Bawana Auchandi Road

    about 2.5 km.

    xv) Adventure Island in Sec. 12 about 5 km.

    xvi) Mutiny Memorial in Jahangirpuri about 10 km.

    xvii) Bharti Vidyapeeth in Pashchim Vihar about 10 km.

    xviii) Sultanpur Dabas Reserve Forest about 7 km.

    xix) Bawana Reserve Forest about 5 km.

    xx) Ghoga Reserve Forest about 6 km.

    xxi) Dilli Haat, Pitamura about 8 km. xxii) 13 Metro stations of Delhi Metro Rail Corporation of which 6 are of Red Line

    (Rithala about 4.5 km., Rohini West about 6 km, Rohine East about 7 km, Pitampura

    about 8 km, Kohat Enclave about 9 km and Netaji Subhash Place about 10 km) and 7

    are of Green Line about 8 km.( Madipur, Pashchim Vihar, Sachdev Park, Peera Garhi,

    Udyog Vihar, Surajmal Stadium and Nangloi).

    xxiii) Protected Forests in Mohammadpur about 10 km and Singhola Area about 8 km

    7.3. Will the project cause adverse effects on local communities, disturbance to sacred sites

    or other cultural values? What are the safeguards proposed?

  • The CAT-II & EWS Housing Complex project will be constructed within the designated site

    as per the defined building by-laws of Delhi Development Authority. There is no sacred site

    or cultural heritage site in nearby vicinity of proposed project; hence no adverse impacts are

    envisaged.

    8. BUILDING