offshore transmission giles stevens head of offshore electricity transmission
TRANSCRIPT
![Page 1: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/1.jpg)
Offshore Transmission
Giles StevensHead of offshore electricity transmission
![Page 2: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/2.jpg)
2 of 11
Contents
1. Regulatory approach
2. Attracting investment
3. User requirements & commitments
4. A potential scenario
![Page 3: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/3.jpg)
3 of 11
Regulatory approach
Approach must ensure that sound investment decisions provide the best value to consumers and offshore transmission users
Sound investment decisions require:– Co-ordination– Minimising risk of stranded assets and ‘gold plating’
To deliver best value to consumers and network users, the regulatory approach must:– Enable necessary investment to deliver economically efficient,
fit for purpose, transmission infrastructure– Provide certainty to investors in offshore transmission
![Page 4: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/4.jpg)
4 of 11
Attracting investment 1 Investors in offshore transmission will need certainty
What risks are private investors exposed to? Scope Timing Development Construction Financing Operation Returns
Price control can give certainty over: Regulated asset value Performance requirement Returns Incentive/penalty regime
![Page 5: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/5.jpg)
5 of 11
Attracting investment 2
The following are likely to be required:
Fair and transparent selection process Competitive pressure Independent ownership of offshore transmission assets No unfair advantage to incumbents Clear definition of scope of work i.e. technical standards User commitment from generators Enduring regulatory structure, including mechanisms for
change
![Page 6: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/6.jpg)
6 of 11
User requirements
Capacity
Location
Additional capacity
Performance
– Availability
– Time to repair
– Delivery date
![Page 7: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/7.jpg)
7 of 11
User commitment
TO ensure offshore transmission networks are not stranded investments, need:
Commitment from generators for transmission build
Commitment to be in place before transmission investment
Most efficient investment will take place once all generators
committed
Scope of transmission work dependent on firm signal from
generators
![Page 8: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/8.jpg)
8 of 11
Geographic areasThe following options were set out in the scoping document
1. Single zoneProsEasiest way to allocateEconomics of scale
2. Few ( 3 – 5)ProsReasonable investment scaleEconomics of scaleOpportunity for competition‘Spread the risk’
3. Many (17 zones)ProsPoint to point approachEasy to implement
Cons Scale (£1bn+) likely to deter all but largest players Less opportunity for competition ‘Eggs in one basket’ No comparison/benchmarking possible
Cons More complex regime Needs cooperation from generators
Cons Few opportunities for economies of sale More complex regime Investment may be too small to be attractive
![Page 9: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/9.jpg)
9 of 11
One potential scenario (1) Geographic areas
– 3 or 5 (as projects of £2-500m maybe most attractive to investors)
Security standards– Present standard, single fault etc
Connection requirements– Generator provides up front commitment– Offshore TO responsible for providing most economic
and timely connection
Scope– Requirements defined by generators to get least cost
solution
![Page 10: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/10.jpg)
10 of 11
One potential scenario (2) Selection of Offshore TO’s
– By competition
Price control– Provides long term RAV certainty– Regular efficiency reviews– Provides detailed arrangements for investment risks to
be managed:• Adoption• Changing scope• Offshore TO failure
![Page 11: Offshore Transmission Giles Stevens Head of offshore electricity transmission](https://reader036.vdocument.in/reader036/viewer/2022082917/551af6875503462e578b4c48/html5/thumbnails/11.jpg)
11 of 11
Promoting choice and value for all gas and electricity customers