ohio department of...

11
1 Ohio Department of Transportation www.transportation.ohio.gov John R. Kasich, Governor Jerry Wray, Director Best Value Design Build Owner’s Perspective Megan O’Callaghan, PE, Esq. Deputy Director Division of Construction Management 2 35 th in Size 7 th in Population 4 th largest interstate system with 6,700 lane miles 2 nd largest total number of bridges with 43,412 Single day’s drive from 60% of U.S. and Canada 2014 Construction Program 1,000 projects Estimated $2.2 Billion

Upload: phamnhu

Post on 30-May-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

1

Ohio Department of Transportation

w w w. t r a n s p o r t a t i o n . o h i o . g o v

John R. Kasich, Governor • Jerry Wray, Director

Best Value Design BuildOwner’s Perspective

Megan O’Callaghan, PE, Esq.Deputy Director

Division of Construction Management

2

35th in Size

7th in Population

4th largest interstate system with 6,700 lane miles

2nd largest total number of bridges with 43,412

Single day’s drive from 60% of U.S. and Canada

2014 Construction Program 1,000 projects Estimated $2.2 Billion

2

3

Design-Build Background

Authority to Pilot in 1995

Current Authority 2011 (ORC 5517.011)

Value-Based selection process (Quality + Price)

$1 Billion per year limit

Stipends – Max 2 per Project

DB Program Development

Industry Input

4

2 DB Methods

Least Cost (aka One-Step)

Contract is awarded to the lowest bidder.

8-12 Week Advertising

Value Based (aka Two-Step)

Combination of quality and cost.

SOQ = 8 weeks

RFP = 20-22 weeks

3

5

Why Value Based?

Owner’s PerspectiveTrue Best Value potential

More Qualified Builder

Innovation & “Betterments”

Speed

6

4

7

3 Phase Process

1. Statement of Qualifications & Shortlisting

2. Alternative Technical Concepts

3. Technical Proposal

Stipend Policy = ¼% - 1% of Estimate

8

Statement of Qualifications

Shortlisted to “approximately” 3

By law, allowed to pay 2 Stipends

50 page submittals

Evaluation per RFQ – comparison between teams

5

9

SOQ Evaluation Criteria

9

Topic Evaluation Criteria Maximum Points

Project

Understanding and

Approach

How well does the DBT’s SOQ demonstrate an in-

depth understanding of the design and construction

requirements of the project?

30

Design Build Project

Team

How well do the DBT’s qualifications, experience and

time availability relate to the requirements of the

project?

40

DBT Capabilities

How well does the DBT’s SOQ communicate their

design, construction and project management

experience for this project?

30

Total 100

10

Alternative Technical Concepts

Cost and Schedule not considered

“Equal or Better” consideration done in terms of life cycle

Confidential “1-on-1” meetings

Official Submittal in writing – Official response in writing

6

11

Technical Proposal

Direct Point Scoring

Weighted Scoring per Criteria

Minimum Score for Responsiveness

No more then 3 criteria under 70

No more then 1 under 60

70% Price - 30% Score

12

Technical Proposal

Criteria Score

MOT and Construction Access 20

Design Management 5

Proposed Design 20

Construction Management 5

Construction 20

Quality Management 15

Outreach to DBEs and OJT 5

TOTAL 100

7

13

Litigation

“The girder depth for the main span portion of the I-90 viaduct shall vary parabolically…”

Scope Requirement:

14

Scoping Example #3

Straight Line

8

15

Litigation

The 2nd DBT filed an injunction.

Claimed the winning DBT’s bridge beam shape is not a Parabola and did not comply with scope.

#1 was nonresponsive.

The winning DBT had a reasonable interpretation. When the bridge beam depth does vary, it varies in a parabolic shape.

16

Welcome

Ferzan AhmedDeputy Director, ODOT District 6

Before

9

17

Welcome

Ferzan AhmedDeputy Director, ODOT District 6

Future Rendering

18

Process Changes:

Cleveland to Columbus

Changed scoring to include Duration into award Formula

Removed the ATC meeting

Quality Management process requirements

10

19

Litigation

Technical Proposal deemed non-responsive

Modification to the approved Interchange Modification Study – Prohibited by Scope

Similar modifications requested in ATC from other proposers – denied in ATC process

Sued for Stipend Value – ultimately paid

20

Cleveland Innerbelt 2

Construction of “Sister” Bridge

Aesthetically resemble the first project

Initiated as a Design-Build-Finance

Being Finalized as Design-Build

11

21

Moving Forward

Alternative Project Delivery Task Force

Expand Shortlisting Process

$25 - $80 Million (Shortlisting – Least Cost)

More ATCs

Better Scopes!

Design Build Contract Administration Training

22