optix metro wdm series equipment commissioning and testing introduction issue1.0

Upload: seifeldinadel

Post on 02-Jun-2018

234 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    1/28

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    2/28

    Internal Use 2

    Objectives

    Upon completion of this course, you

    will be able to Understand preparation for

    commissioning and testing

    Understand Site commissioning

    Understand system commissioning

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    3/28

    Internal Use 3

    Chapter1 Preparation for commissioning and

    testing

    Chapter2 Site commissioning

    Chapter3 Networking commissioning

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    4/28

    Internal Use 4

    Commissioning Conditions Check

    Check the following items before commissioning: The equipment is well installed and has passed the hardware

    installation check.

    The OptiX iManager T2000 network management system

    (T2000 for short) is installed in both the central equipment room

    and the laptop, and it has been tested. The OptiX iManager T2000-local craft terminal (LCT for short) is

    installed in the laptop and has been tested.

    The equipment in each station is provided with two power

    supplies.

    The equipment is well connected with the external alarmequipment (if needed).

    The ODF in each station is installed and is ready for use.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    5/28

    Internal Use 5

    Site commissioning

    Item Sub-item

    Site commissioning

    Checking hardware

    Powering on the cabinet

    Testing subrack functions

    Checking software version

    Testing the visual and audible alarm

    Checking fiber connection

    Setting alarm and performance monitoring

    Testing embedded control channel (ECC)

    communication

    Backing up NE database

    Testing equipment restart

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    6/28

    Internal Use 6

    Networking Commissioning

    Item Sub-item

    Networking commissioning

    Checking network-wide fiber connections

    Testing the supervisory channel

    Adjusting optical power

    Testing system indices

    Testing protection switching

    Testing orderwire

    Testing bit errors

    Configuring servicesVerifying T2000 function

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    7/28Internal Use 7

    Chapter1 Preparation for commissioning and

    testing

    Chapter2 Site commissioning

    Chapter3 Networking commissioning

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    8/28Internal Use 8

    Checking Hardware

    Step Action

    1 Checking the Cabinet

    2 Checking the Subrack

    3 Checking Cable Distribution

    4 Checking the Board

    For details, refer to OptiX Metro 6100 WDM Multi-Service

    Transmission System Installation Manual.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    9/28Internal Use 9

    Powering on the Cabinet

    Step Action Index

    1 Checking the Fuse Capacity The maximum power consumption of asubrack : 600 W

    The fuse capacity of a subrack :20 A

    2 Checking the Output Voltage The output voltage of the power supply:38.4 V

    and57.6 V (48 V DC20%)

    3 Checking the Resistance

    (Turn all power switches on

    the front panel of the power

    distribution box to OFF)

    Measure the resistance between NEG1(-) or

    NEG2(-) and RTN1(+) or RTN2(+) . The valueshould be .

    Measure the resistance between NEG1(-) or

    NEG2(-) and protection grounding post. The value

    should be .

    4 Checking the Resistance

    (Turn all power switches on

    the front panel of the power

    distribution box to OFF)

    Measure the resistance between NEG1(-)or

    NEG2(-) and RTN1(+) or RTN2(+). . The value

    should be more than 20 k.

    Measure the resistance between NEG1(-) or

    NEG2(-) and protection grounding post (). The

    value should be more than 20 k

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    10/28Internal Use 10

    Testing Subrack Functions

    Step Action Index

    1 Powering on theSubrack Check whether the POWER ON indicator on

    the DPFU board in the interface area is on

    and whether the subrack is powered on.

    2 Checking the Fan Check the indicator on the front panel of the fan

    tray assembly.

    3 Checking Board Indicators Check whether only the green indicator of each

    board flashes once every other second.

    The yellow indicator on the SCC boards is

    constantly on.

    4 Testing the RST Button Press the RST button on the SCC board of an

    NE to restart it.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    11/28Internal Use 11

    Testing the Visual and Audible Alarm

    Step Action Details

    1 Testing the ALC Switch Remove the fiber connector from a receiving

    optical interface. The NE reports an alarm

    and buzzes. Turn the ALC switch down and check whether

    the alarm sound stops in three seconds.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    12/28Internal Use 12

    Checking Fiber Connection

    Step Action

    1 At the client ODF, connect the transmitting (Tx) and receiving (Rx)

    optical interfaces of an SDH analyzer with the Rx and Tx optical

    interfaces of an OTU board.

    2 At the line ODF, loopback the IN and OUT optical interfaces of theFIU board ensuring a 10 dB attenuator.

    3 Send optical signals to the OTU board through the Tx optical interface

    of the SDH analyzer. And then the Rx optical interface of the SDH

    analyzer should receive the signals after loopback. It indicates the fiber

    connection is correct.

    4 Check the fiber connection of other OTU boards in the same way.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    13/28Internal Use 13

    Continue

    Step Action Description

    1 Setting Alarm and Performance

    Monitoring

    Use the T2000 to set performance

    and alarm monitoring.

    Observe the performance event

    as long as possible, at least one

    hour.

    2 Testing ECC Communication in a

    Station

    All NEs should be accessed

    through NM. If any NE cannot be

    accessed, check the fiber

    connection or parameter

    configuration.

    3 Backing Up NE Database The NE database can ensure thatthe SCC unit restores to normal

    operation automatically upon data

    loss or power failure.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    14/28Internal Use 14

    Testing Equipment Restart

    Step Action

    1 Switch off the subrack.

    2 Switch on the subrack after ten minutes and check whether the boards runnormally.

    3 Check whether the services operate normally. Test some typical services and

    make sure there is no bit error or abnormal performance event.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    15/28Internal Use 15

    Inspection Items after Site Commissioning

    Item Description

    SCC The ALC switch is in the upper position.

    Orderwire phone The connector of the phone cable is inserted in the corresponding

    interface; the ring switch of the phone in ON, the dialing mode is T

    and the TALK button is not active.

    Board interface The fiber jumper for test purpose is removed and the normal

    connection is recovered.

    ODF The fiber jumper for test purpose is removed and the normal

    connection is recovered.

    T2000 NM All loopbacks of the boards are released and the services configured

    for test are deleted.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    16/28Internal Use 16

    Chapter1 Preparation for commissioning and

    testing

    Chapter2 Site commissioning

    Chapter3 Networking commissioning

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    17/28Internal Use 17

    Network Commissioning

    Network commissioning aims to: Connect all NEs in a network in line with the

    engineering design scheme.

    Test services of the network to verify the

    configuration.

    Test required functions for the network, such

    as orderwire and protection switching.

    Test long-term communication quality of the

    network through alarm and performance event.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    18/28Internal Use 18

    Checking Network-Wide Fiber Connections

    Step Action

    1 Measure the optical power . Make sure the FIU boards receive the optical

    signal from the opposite station.

    2 Measure the optical power from the OUT interface of the FIU.3 Check the fiber connection and the line attenuation between other adjacent

    stations in the same way.

    In this commissioning sub-item, check the following two items:

    Whether the transmitting and receiving optical interfaces of the

    line cables are connected correctly.Test required functions for the

    network, such as orderwire and protection switching.

    Whether the optical attenuation in the line is normal.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    19/28Internal Use 19

    Testing the Supervisory Channel

    Step Action

    1 Check the fiber connection of the OSC unit

    2 Use an optical power meter to measure the transmitting optical power of the

    OSC boards. It should range from3 dBm to6 dBm.

    3 Use the 10 dB optical attenuator to adjust the actual receiving optical power ofthe OSC boards to30 dBm.

    The OptiX Metro 6100 can offer two modes of supervisory:

    Whether the optical attenuation in the line is normal. Optical supervisory channel (OSC)

    Electric supervisory channel (ESC)

    Testing OSC

    Testing ESC

    When the OTU starts to work and the service is normal, the ESC route is set up.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    20/28Internal Use 20

    Adjusting optical power

    the main operation is to use optical attenuators to adjust thefollowing optical power values.:

    Input optical power of the optical amplifier at the transmit end.

    Input optical power of the optical amplifier at the receive end.

    Input optical power of OTU at the WDM side.

    Adj ti I t O ti l P f th O ti l

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    21/28Internal Use 21

    Adjusting Input Optical Power of the Optical

    Amplifier at Transmit End

    LWM1

    OBUM40

    SDH

    analyzer

    LWM2

    LWM3

    For stations equipped with optical amplifiers, adjust the optical power of any

    single-wavelength in the input signal of the optical amplifier at transmit end to

    the prescribed typical value.

    The type of

    optical

    amplifier

    Typical value of single-

    wavelength input optical

    power (dBm)

    Gain

    (dB)

    Input optical power

    range (dBm)

    Output optical

    power range

    (dBm)

    OAU-C01 21 to1520 to

    3332 to 0 12 to 20

    OAU-C02 24 to1820 to

    3332 to3 12 to 17

    OAU-C03 27 to2126 to

    3232 to6 6 to 20

    OBU-C01 21 23 32 to6 9 to 17

    OBU-C03 18 23 22 to3 1 to 20

    OPU-C01 21 20 32 to6 12 to 14

    OPU-C02 21 20 32 to6 12 to 14

    Adj sting Inp t Optical Po er of the Optical

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    22/28

    Internal Use 22

    Adjusting Input Optical Power of the Optical

    Amplifier at the Receive End

    For stations equipped with optical amplifiers, adjust the optical power of anysingle-wavelength in the input signal of the optical amplifier at transmit end to

    the prescribed typical value.

    At the receive end, adjust the optical power of the multiplexed signal

    coming from the line until the single wavelength optical power reaches the

    typical value.

    The optical power formula is: Pm=Ps + lgN

    Pm : Optical power of multiplexed signal

    Ps : Optical power of single wavelength signal

    N : Number of wavelengths in multiplexed signal

    LWM1

    OPUD40/

    MR2LWM2

    LWM3

    Adj i h I O i l P f OTU WDM Sid

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    23/28

    Internal Use 23

    Adjusting the Input Optical Power of OTU at WDM Side

    Adjust the input optical power of OTU at WDM side to the optimal

    range:

    Received signal rate Receiver laser typeOptimal range for input optical power

    (dBm)

    2.5 Gbit/s PIN 6 to12

    2.5 Gbit/s APD 16 to22

    10 Gbit/s PIN 6 to10

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    24/28

    Internal Use 24

    Testing System Indices

    Test item Description

    OTU

    Mean launched power Required

    Actual received optical power Required

    Receiver sensitivity OptionalReceiver overload Optional

    Central wavelength (frequency) anddeviation

    Optional

    Side mode suppression ratio Optional

    20dB spectral width Optional

    Optical multiplexer/demultiplexer unit Insertion loss Required

    OADM unit

    Insertion loss of drop channel Required

    Insertion loss of add channel Required

    Insertion loss of pass-through channel Required

    Optical amplifier

    Actual input optical power Required

    Actual output optical power Required

    Channel gain Required

    OSC unit

    Launched optical power Required

    Actual received optical power Required

    OSC operating wavelength Optional

    Receiver sensitivity Optional

    For indices requirement, refer to OptiX Metro 6100 WDM Mult i -Servic e Transm issio n

    System Technic al Manual.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    25/28

    Internal Use 25

    Testing Protection Switching

    The OptiX Metro 6100 supports the following protection modes:

    Intra-OTU 1+1 optical channel protection

    Inter-OTU 1+1 optical channel protection

    Client-side 1+1 optical channel protection

    Wavelength cross-connection protection

    Optical wavelength shared protection (OWSP)

    Optical line protection.

    For the working principle of each protection mode, refer to OptiX Metro

    6100 WDM Multi-Service Transmission System Technical Manual.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    26/28

    Internal Use 26

    Testing Bit Errors

    Testing the 15-Minute Bit Errors of each Optical Channel

    Testing the 24-Hour Network-Wide Bit Error

    Bit error test should cover all service channels in the network.

    There should be no bit error in consecutive 24 hours. To ensure

    the 24-hour network-wide bit errors test can be completed

    successfully, perform a 15-minute bit errors test to each channel

    in advance.

    Station A

    LWM1SDH

    analyzer LWM1

    IN

    OUT

    Tx

    Rx Tx

    Rx

    Station B

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    27/28

    Internal Use 27

    Other Items

    Configuring Services

    For details, refer to OptiX Metro 6100 WDM Multi-Service

    Transmission System Configuration Guideand T2000 online

    help.

    Verifying T2000 Function

    For verification items, refer to OptiX iManager T2000

    Transmission Network (Subnet Level) Management System

    Acceptance Manual.

  • 8/10/2019 OptiX Metro WDM Series Equipment Commissioning and Testing Introduction ISSUE1.0

    28/28

    Confidential Information of Huawei. No Spreading without Permission.