ouc administration building reliable plaza north fl aacei may 21, 2009

31
OUC Administration Building Reliable Plaza North FL AACEi May 21, 2009

Upload: isaak-barrell

Post on 11-Dec-2015

217 views

Category:

Documents


1 download

TRANSCRIPT

OUCAdministration Building

Reliable PlazaNorth FL AACEi

May 21, 2009

Background OUC parking garage demolished by FDOT due to

the I4/408 Expressway Interchange expansion Settlement compensation between OUC & FDOT

from the impact of this expansion Lost of parking garage Impact to operations, customers and employees Relocation of employees and departments to other OUC

facilities and leased a building in downtown

OUC needed to evaluate and select available real estate options and sites to accommodate OUC’s space program requirements

Evaluated Options

Refurbish existing Adm Bldg and build a new parking structure

Build new bldg and parking garage at existing OUC’s site (west of existing bldg)

Build new bldg and parking garage on other OUC’s property (Lake Highland site)

Build new bldg on purchased property Purchase an existing building 3rd party development (partial ownership of a

building/garage) Sell or lease existing building

Evaluated Options

Hard construction costs Site work Building structures MEP TI

Site acquisition (Owned or Purchased opportunity) Parking

Parking with garage (detached from building, under building, surface) Soft costs

Design/Permitting Misc. fees Temporary relocation

LEED certified building Other owner costs

IT Hook up Moving Owners Representative fees

Project Partners

Select PBS&J as Owner’s Representative As the “go to” consultant Assist in the writing of the Architect Statement of

Qualification (SOQ) Assist in the evaluation of all available options Assist in the execution of the selected option

Select Real Estate Research Consultants to perform financial model

Project Partners (Cont’d)

Baker Barrios Architects – Core & Shell Hunton Brady Architects– Interior TLC Engineering - MEP SKANSKA USA/JCB – GC GAI – Civil Engineers

Summary of Project CostsOption Project Cost

Refurbish Existing Bldg $31,059,440

New Building on Existing Site $32,819,000

New Building on Existing Site with Third Party Developer

Approximately

$29,000,000

OBT & 50 – McNamara Pontiac $30,172,000

500 E. Princeton $27,167,000

Lake Highland $29,515,000

Parramore $35,366,000

Developer Offer (Kuhn) $35,947,000

Construction Management at Risk

SKANSKA USA/JCB Delivered pre-construction services such as schedule,

budget and constructability reviews Centralize responsibility for construction under a single

contract Subcontracted the work and guaranteed the cost and completion

of project Contractor fee based as part of the building design Contractor provides a price with a maximum cap at the

90% design point At the completion of design, the contractor agrees to

construct at the agreed price or OUC can go back out to bid

Challenges

Boone Avenue Extension Parking Structure Efficiency Loss Two Additional Stair Tower Stops Four Additional Elevator Stops Additional Elevator Lobby Finish Additional Exterior Cladding Speed Ramp Access Program Growth 11,644SF Total Cost Impacts by City $1,376,183

Challenges (Cont’d)

Challenges (Cont’d)

Redesign of the 10th floor - $100,000 Redirect storms collection pipe - $80,000

Project Budget January 07 March 07

Original Project Budget $32,819,000 $32,819,000 Budget Correction 891,703 891,703 Construction/Material Escalation 2,018,068 2,018,068 Boone Blvd Extension 1,376,183 1,376,183 Renewable Energy Systems 1,246,902 1,431,842 Building Program Increase 1,663,336 1,663,336 Unique Building Features 2,426,969 3,380,589 Core/Shell – Design Mod/Hard Bid Inc 1,500,000 TI – Design Mod/Hard Bid Reconcile Inc 630,810 Direct Costs by owner Inc 1,538,469

Design, Asbestos, Furniture, Insurance OUC/Design Contingency Inc 650,000 Subtotal $42,442,161 $47,900,000 Tax Credit / VE Items ($ 1,000,000) ($ 1,100,000) Target Project Budget* $41,442,161 $46,800,000

* Approx. $10,000,000 will remain from the FDOT Taking of the Garage

General Information 128,000 square feet – 1st floor Customer Service, 1-

6 parking, 7-10 office Connected to OUCooling and use of OUConvenient

lighting Public Building 15,000 Customers though the building per month 3 Drive through payment service lanes 345 Employee work spaces at move in 355 Garage parking spots 45 surface customer and visitor parking spots Approximately 10,000 square foot available for

growth past 5 year plan

Why LEED Certification?

Energy efficiency and water conservation have always been a priority and OUC is setting an example for all future developments by being the greenest building downtown *LEED Gold Certification is approximately 6%

of building costs

Project Budget

Base Building (Core & Shell) $20,995,163 Design & Permitting 2,519,649 Site selection / feasibility 400,000 Parking 7,200,000 Renewable energy & water / conservation 1,431,842 Unique building features 3,380,589 Interior improvements 6,400,610 Furniture & loose walls 2,672,147 Information Systems equipment 600,000 Asbestos removal & demolition 1,200,000

of existing building Total $46,800,000

Renewable Energy & Water / Conservation

Leadership in Engineering and Environmental Design (LEED) Solar Electric Panels Solar Hot Water Panels OUCooling High Performance Glass Cistern for Roof Water Collection Raised Floor Design High Efficiency HVAC System Recycled & Low Volatile Organic Compound (VOC)

Emitting Materials

Designed for a LEED Gold Rating

Solar Electric Panels 30 KW of photovoltaic panels 2,000 square feet

Solar Hot Water

Reactive System designed to supply all building hot water needs.

OUCooling

Connected to OUCooling Saves up front capital Great environmental performance.

OUCooling operates 10% to 20% more efficient than a stand alone building chiller systems

No maintenance or annual contract worries

High Performance Glass

Clear Glass for Maximum Light Winter U value – 0.29 Shading Coefficient – 0.27 Solar Heat Gain Coefficient – 0.23 Allowed for daylight harvesting LEED point

Cistern for Storm Water Collection

30,000 gallon cistern to collect storm water from the buildings roof

System designed to meet 95% of irrigation needs (Landscape designed for low water needs)

Circulating filtration system to look like a fountain

Raised Floor Design

Tate Raised Floor 14 inches off of the floor Allowed for the floor to ceiling height to be reduced All electrical and HVAC is under the floor system Allows for cleaner air and more localized temperature control Allows for re-configuring work areas at a very low cost HVAC is Johnson Controls-York equipment installed by S.I. Goldman

High Efficiency HVAC

All major HVAC components are equipped with variable speed drives

Energy recovery is provided for Ventilation Air reducing impact on cooling load

Recycled & Low Volatile Organic Compound (VOC) Emitting Materials

Utilized these materials where possible.

Education Center

http://hq.ouc.greentouchscreen.com

Owner Needs and Goals

OUC needed and wanted to build a building that will be an example to others

Our goal was to build a Gold rated building that had carefully selected points for the right reasons

We were also willing to make the “right choices” even if it did not achieve a LEED point