outfall-pipeline design basis report final - … site#: r37893 document file loc: 4.15.01 report...

37
HONEYWELL SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge System Former Baron-Blakeslee, Inc., Solvent Recycling Facility Portland, Oregon Prepared for Honeywell International Inc. June 2011 Prepared by

Upload: phungtuong

Post on 12-Mar-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

HONEYWELL SITE#: R37893 DOCUMENT FILE LOC: 4.15.01

R e p o r t

Design Basis Report for Groundwater Conveyance and

Discharge System Former Baron-Blakeslee, Inc., Solvent

Recycling Facility Portland, Oregon

Prepared for

Honeywell International Inc.

June 2011

Prepared by

Page 2: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 ES032411184302PDX

Page 3: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 iii ES032411184302PDX

Contents

Section Page

Acronyms and Abbreviations .......................................................................................................... v 

1.0  Introduction ....................................................................................................................... 1-1 

2.0  Background ........................................................................................................................ 2-1 2.1  Extraction System Remedial Action Objectives ............................................... 2-1 2.2  Cleanup Levels ..................................................................................................... 2-1 2.3  Selected Remedy ................................................................................................... 2-1 2.4  Site Geology and Hydrogeology ........................................................................ 2-2 

3.0  Groundwater Conveyance and Discharge System ..................................................... 3-1 3.1  Design Objectives ................................................................................................. 3-1 3.2  Conveyance Piping from Wells EW-1 and EW-2 ............................................. 3-1 

3.2.1  Pipe Size .................................................................................................... 3-2 3.2.2  Pipe Material ............................................................................................ 3-2 3.2.3  Pipe Bedding ............................................................................................ 3-3 

3.3  Well Vaults ............................................................................................................ 3-3 3.4  Treated Water Discharge to Columbia Slough ................................................. 3-3 3.5  Utility Clearance ................................................................................................... 3-3 3.6  Management of Investigation-Derived Waste ................................................. 3-3 

4.0  Deliverables ....................................................................................................................... 4-1 

5.0  Permits and Access Agreements .................................................................................... 5-1 5.1  Site Development Permit ..................................................................................... 5-1 5.2  Construction Stormwater Permit ....................................................................... 5-1 5.3  Joint Permit Application ...................................................................................... 5-1 5.4  Federal Aviation Administration Permit .......................................................... 5-1 5.5  Access Agreements .............................................................................................. 5-1 5.6  Easements .............................................................................................................. 5-1 

6.0  Schedule ............................................................................................................................. 6-1 

7.0  Works Cited ....................................................................................................................... 7-1 

Appendix

A Design Drawings

Page 4: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …
Page 5: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 v ES032411184302PDX

Acronyms and Abbreviations

BBI former Baron-Blakeslee, Inc. Facility (the Site)

COC constituent of concern

CRSA Columbia River Sand Aquifer

CDAP Cleanup Discharge Authorization Permit

DEQ Oregon Department of Environmental Quality

DSL Oregon Department of State Lands

FAA Federal Aviation Administration

FRP fiberglass reinforced plastic

gpm gallon(s) per minute

HDPE high-density polyethylene

Honeywell Honeywell International Inc.

MCL maximum contaminant level

PCE tetrachloroethene

PVC polyvinyl chloride

PVDF polyvinylidene fluoride

RAO remedial action objective

ROD Record of Decision

Site BBI Solvent Recycling Facility

SST stainless steel

TCA trichloroethane

TCE trichloroethene

TGA Troutdale Gravel Aquifer

UGA Unconsolidated Gravel Aquifer

USACE U.S. Army Corps of Engineers

VOC volatile organic compound

Page 6: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …
Page 7: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 1-1 ES032411184302PDX

SECTION 1.0

Introduction

This report provides the design basis for the groundwater conveyance and discharge system being constructed for the groundwater remediation system at the former Baron-Blakeslee, Inc. (BBI) Solvent Recycling Facility (the Site) located in Portland, Oregon (Appendix A, Figure G-001). This remedial system is part of a groundwater remedial action being conducted by CH2M HILL on behalf of Honeywell International Inc. (Honeywell), which owns the BBI property. The location of the BBI property is shown in Figure 1. The property is a former solvent recycling facility, and constituents of concern (COCs) are volatile organic compounds (VOCs) of chlorinated solvents (1,1,1-trichloroethane [1,1,1-TCA], tetrachloroethene [PCE], and trichloroethene [TCE]) in soil and groundwater.

This remedial design has been completed to comply with a consent order entered into by the State of Oregon Department of Environmental Quality (DEQ) and Honeywell (DEQ Consent Order No. LQSR-NWR-08-09). The consent order requires Honeywell to design a groundwater remedy consistent with the Site’s Record of Decision (ROD) and in accordance with the Remedial Design/Remedial Action Scope of Work (SOW) in Attachment B of the consent order.

The selected groundwater remedy for the Site includes both a pump-and-treat system to remediate groundwater within the remedial action area, which is defined by maximum contaminant levels (MCLs), and groundwater circulation wells within the onsite source area. As outlined in the Remedial Design/Remedial Action Work Plan, Former Baron-Blakeslee, Inc., Solvent Recycling Facility Site, Portland, Oregon (CH2M HILL, 2009b), design and construction of the groundwater remedy will proceed in separate phases. This report covers the design and construction of the groundwater conveyance and discharge system for the pump-and-treat system.

This report is organized as follows:

• Section 1—Introduction describes the facility, purpose of the remedial action, and selected remedy.

• Section 2—Background presents background information, including the applicable remedial action objectives (RAOs), cleanup levels, the remedy selected in the ROD, and a summary of site geology and hydrogeology.

• Section 3—Groundwater Conveyance and Discharge System provides the design details for the water distribution systems.

• Section 4—Deliverables summarizes the deliverables associated with design of the groundwater conveyance and discharge system.

• Section 5—Permits and Access Agreements identifies the permits and access agreements required for the design work.

• Section 6—Schedule presents the schedule for completing each task.

Page 8: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

DESIGN BASIS REPORT FOR GROUNDWATER CONVEYANCE AND DISCHARGE SYSTEM, FORMER BARON-BLAKESLEE, INC., 1.0 INTRODUCTION SOLVENT RECYCLING FACILITY, PORTLAND, OREGON

1-2 PDX/111610001 ES032411184302PDX

• Section 7—Works Cited includes the references used in preparing this report.

• Appendix A—Design Drawings.

Page 9: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 2-1 ES032411184302PDX

SECTION 2.0

Background

This section presents the Site background information for the RAOs, a review of site-specific cleanup levels, a review of the selected remedy for the Site, and geology and hydrogeology.

2.1 Extraction System Remedial Action Objectives As described in the ROD, the groundwater RAOs for the Site are as follows:

• Prevent onsite occupational worker and offsite residential exposure to COCs in groundwater by direct contact, incidental ingestion, and inhalation that would result in an unacceptable excess lifetime cancer risk greater than 1 x 10-6 for individual chemicals, 1 x 10-5 cumulative risk for each pathway, and a hazard index greater than 1.

• Remediate the Unconsolidated Gravel Aquifer (UGA), Troutdale Gravel Aquifer (TGA), and Columbia River Sand Aquifer (CRSA) groundwater to levels protective of the potential future beneficial use as a domestic/municipal drinking water source.

• Control migration of contaminated groundwater containing COCs as necessary to protect the groundwater beneficial use.

2.2 Cleanup Levels According to the ROD, termination of the groundwater remediation system would be allowed by DEQ once the beneficial use of the aquifer is restored. This decision will be based on COCs meeting the United States Environmental Protection Agency MCLs in the UGA, TGA, and CRSA aquifers and complying with risk-based concentrations (RBCs) of drinking water at the nearest potential future supply well site C of the City of Portland Columbia South Shore Wellfield (DEQ, 2008).

2.3 Selected Remedy The selected groundwater remedy for the Site includes both a pump-and-treat system to remediate groundwater within the MCL remedial action area and groundwater circulation wells within the onsite source area. The locations of the extraction wells, MCL remedial action area, and modeled capture zone for the selected remedy are shown in Figure 2.

The pump-and-treat component of the remedy includes extracting groundwater from three offsite wells located along the approximate centerline of the groundwater plume. Groundwater removed from these extraction wells will be conveyed through a pipeline to a central treatment plant, where it will be treated by an air stripper to remove VOCs. The tentative location for the treatment plant is adjacent to TW-1, where Honeywell has an existing building on land leased from the Port of Portland. Treated water will then be discharged into the Columbia Slough. Depending on groundwater concentrations,

Page 10: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

DESIGN BASIS REPORT FOR GROUNDWATER CONVEYANCE AND DISCHARGE SYSTEM, FORMER BARON-BLAKESLEE, INC., 2.0 BACKGROUND SOLVENT RECYCLING FACILITY, PORTLAND, OREGON

2-2 PDX/111610001 ES032411184302PDX

additional treatment of water—to remove other inorganics before discharge—may also be required to meet the requirements of the site Cleanup Discharge Authorization Permit (CDAP). Offgas treatment may also be required, depending on groundwater influent concentrations. Preliminary data collected during aquifer testing of the extraction wells indicate that inorganics removal and offgas treatment will not be necessary to meet permit requirements. Technical memorandums will be prepared presenting data in support of these conclusions and will be provided to DEQ for concurrence in summer 2011.

2.4 Site Geology and Hydrogeology A detailed discussion of the site geology and hydrogeology, including the stratigraphy and COC concentrations along the plume axis, is included in the Design Basis Report for Well Installation and Aquifer Testing, Former Baron-Blakeslee, Inc., Solvent Recycling Facility Site, Portland, Oregon (CH2M HILL, 2009a) and the Feasibility Study Report for the Former Baron-Blakeslee, Inc., Solvent Recycling Facility Site, 5920 NE 87th Avenue, Portland, Oregon (CH2M HILL, 2008). The area for VOC containment and remediation is within the UGA and TGA upgradient of the transition to the CRSA.

Page 11: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 3-1 ES032411184302PDX

SECTION 3.0

Groundwater Conveyance and Discharge System

This section provides the design details for the groundwater conveyance and discharge system associated with the pump-and-treat system within the MCL remedial action area.

3.1 Design Objectives Design objectives for the well installation program are as follows:

• Outfall

− Minimize erosion along Columbia Slough bank − Minimize scouring in the slough channel − Minimize turbulence in the slough − Minimize impact to recreational users of the slough

• Conveyance piping

− Minimize leak potential

− Protect adjacent wetlands

− Size piping to accommodate various flow scenarios to allow for system adjustments to meet RAOs

− Allow independent monitoring of flow from each well

− Minimize potential vandalism

3.2 Conveyance Piping from Wells EW-1 and EW-2 Partially buried vaults will be installed over extraction wells EW-1 and EW-2, and the well heads will be modified as below grade completion according to Oregon Department of Water Resources guidance. The locations of the conveyance piping and associated electrical and instrumentation conduits from each well vault to the treatment building are shown in Appendix A, Figure C-100. Figure C-501 in Appendix A shows a cross section of the typical trench configuration.

Groundwater extracted from each well will be conveyed to the treatment building through separate buried double-wall piping. A sealed leak detection observation port will be installed at the low point of the pipeline alignment to allow periodic visual inspection for leakage from the carrier pipe. In addition, a small sump with float valve will be located within each well vault. Water accumulation within the sump will actuate the float valve,

Page 12: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

DESIGN BASIS REPORT FOR GROUNDWATER CONVEYANCE AND DISCHARGE SYSTEM, FORMER BARON-BLAKESLEE, INC., 3.0 GROUNDWATER CONVEYANCE AND DISCHARGE SYSTEM SOLVENT RECYCLING FACILITY, PORTLAND, OREGON

3-2 PDX/111610001 ES032411184302PDX

which will in turn send a signal to the programmable logic controller (PLC) located at the treatment building to shut down the pump.

3.2.1 Pipe Size The piping is sized to maintain a minimum flow rate of 3 feet per second to minimize settling of solids in the pipe and a maximum flow rate of 8 feet per second to minimize head loss and potential scouring of the internal pipe wall. For smooth wall pipe, these velocity criteria result in the following range of flows:

Nominal Pipe Size (inches)

Minimum Flow (gpm)

Maximum Flow(gpm)

3 65 175

4 110 300

6 260 700

On the basis of current data, the predicted long-term flows range from about 80 gallons per minute (gpm) to 100 gpm for wells EW-1 and well EW-2. From among the design options shown in the table above, a 4-inch nominal diameter pipe is recommended for conveying water from both EW-1 and EW-2. Results from groundwater pumping tests are being evaluated to finalize design flow rates and associated pipe diameters.

Double-wall containment pipe will be used to convey water from each well vault to the treatment building. As indicated above, the recommended carrier pipe is 4-inch nominal diameter. The associated containment pipe will be approximately 8-inch diameter, a size that is typical for 4-inch, pre-manufactured, double-wall containment pipe.

3.2.2 Pipe Material Because of the presence of COCs (solvents) in the groundwater, even at low concentrations, material that can be used for the carrier piping is limited. Various materials were reviewed for this application, including polyvinyl chloride (PVC), high-density polyethylene (HDPE), fiberglass reinforced plastic (FRP), polyvinylidene fluoride (PVDF), and stainless steel (SST). PVC, HDPE, and FRP were found to be potentially acceptable, given the likely ranges of VOC concentrations.

Manufacturers for both PVC and HDPE double-containment piping systems reviewed the predicted concentrations and have stated their products are acceptable for this application. FRP was not considered for use because of its higher cost and higher risk for failure in a buried application. PVDF is acceptable for all concentrations of the chemicals, but the material cost, which would be approximately 10 to 20 times higher than those for PVC and HDPE, is considered cost-prohibitive. SST is acceptable for all concentrations, and single-wall 304 SST piping is planned for use in the vaults and treatment building.

HDPE material will be used for the conveyance piping.

Page 13: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

DESIGN BASIS REPORT FOR GROUNDWATER CONVEYANCE AND DISCHARGE SYSTEM, FORMER BARON-BLAKESLEE, INC., SOLVENT RECYCLING FACILITY, PORTLAND, OREGON 3.0 GROUNDWATER CONVEYANCE AND DISCHARGE SYSTEM

PDX/111610001 3-3 ES032411184302PDX

3.2.3 Pipe Bedding Compacted sand or small rounded gravel (commonly referred to as pea gravel) will be placed as pipe bedding and pipe zone material under and around the pipe. Material from the trench excavation will be placed and compacted above the pipe zone to finish grade.

3.3 Well Vaults The design for the well vaults is shown in Figure C-502. A precast concrete vault will be installed at each extraction well location. The top of the vault will be approximately 1 foot above the adjacent ground surface. This design approach has been review and accepted by Oregon Department of Water Resources. The vault will be equipped with a watertight aluminum hatch with a bolt and gasket. The hatch will be design for H-20 wheel loading. Bollards will be installed around each vault for additional protection. Manifold piping and instrumentation within the vault will be included in the next phase of work.

3.4 Treated Water Discharge to Columbia Slough The design for the outfall is shown in Figure C-501. Treated water will be conveyed from the treatment building to the outfall diffuser in a buried HDPE pipe. The diffuser section will consist of a 32.5-foot-long section of perforated 12-inch-diameter HDPE pipe anchored on a narrow bench cut into the slough bank at elevation 18 (100-year flood elevation). Flow from the diffuser will travel downslope to the slough water surface over an anchored protective matting of concrete articulated block (Armorflex). Three rows of 0.75-inch-diameter pipe perforations will be oriented to direct flow downslope over the protective matting. Hydraulic calculations based on a total discharge flow of 400 gpm indicate discharge velocity through the diffuser ports on the order of 2 feet per second. This design approach has been reviewed and accepted by Multnomah County Drainage District.

3.5 Utility Clearance Before excavation, local utility companies will be contacted concerning the subsurface explorations. Utility checks will be performed by Utility Notification Center and by a private utility locator to ensure that the trench locations are at sufficient offset distances from utility locations. In addition, the upper 5 feet will be air-knifed and the cuttings will be inspected for evidence of utilities (uniform sand, caution tape, etc.) in the areas of identified underground utilities.

3.6 Management of Investigation-Derived Waste Upland soil at the Port of Portland property is uncontaminated based on samples collected during road construction activities in 2010. Soil that is not used for backfill in the pipeline trenches will be stockpiled, covered to prevent erosion, and used onsite for grading. Soils may be removed and disposed of offsite.

Soils excavated below the normal Slough water line will be stockpiled separately from upland soils. Characterization samples will be collected from the stockpiled soils at a

Page 14: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

DESIGN BASIS REPORT FOR GROUNDWATER CONVEYANCE AND DISCHARGE SYSTEM, FORMER BARON-BLAKESLEE, INC., 3.0 GROUNDWATER CONVEYANCE AND DISCHARGE SYSTEM SOLVENT RECYCLING FACILITY, PORTLAND, OREGON

3-4 PDX/111610001 ES032411184302PDX

frequency of one sample per 100 cubic yards. Samples will be analyzed at an offsite laboratory for polychlorinated biphenyls, metals, and total petroleum hydrocarbons. Analytical results will be compared to DEQ direct contact screening values (Risk-Based Decision Making for the Remediation of Petroleum-Contaminated Sites, updated September 15, 2009). The most conservative values for the occupational, excavation worker and construction worker scenarios for each parameter will be used. Soils with concentrations below the screening levels may be reused onsite for upland regrading or disposed of offsite.

Water generated through dewatering or equipment decontamination activities will be containerized and then discharged to surface water under the existing discharge authorization letter from DEQ (July 15, 2009).

Page 15: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 4-1 ES032411184302PDX

SECTION 4.0

Deliverables

After construction of the groundwater conveyance and discharge system is completed, a construction completion report that documents the work performed will be prepared and submitted to DEQ. The report will summarize the fieldwork and identify deviations from the approach presented in this Design Basis Report.

Page 16: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …
Page 17: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 5-1 ES032411184302PDX

SECTION 5.0

Permits and Access Agreements

This section summarizes the applicable permitting requirements and access agreements required for the groundwater conveyance and discharge system construction.

5.1 Site Development Permit A Site Development Permit will be obtained from the City of Portland before mobilization.

5.2 Construction Stormwater Permit A project-wide 1200-C Construction Stormwater Permit has been obtained (File No. 100676). The permit specifies best management practices for stormwater management and stockpiled materials to prevent erosion.

5.3 Joint Permit Application On March 5, 2010, the U.S. Army Corps of Engineers (USACE) responded to a joint permit application granting permission to install an outfall below ordinary high water in the Columbia Slough.

5.4 Federal Aviation Administration Permit Honeywell has received a Federal Aviation Administration (FAA) permit for activities within the Portland International Airport flight path. The FAA regulates structure height within the flight path as it relates to routine flight and emergency situations.

5.5 Access Agreements Honeywell has secured a lease with the Port of Portland for the site.

5.6 Easements Honeywell is applying for a long-term easement from the Oregon Department of State Lands (DSL) for the discharge outfall structure. DSL is aware of the project from the Joint Permit Application process. No issues are expected.

Page 18: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …
Page 19: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 6-1 ES032411184302PDX

SECTION 6.0

Schedule

Construction is planned for August and September 2011 so that outfall construction can be completed within the DSL/USACE summer work window of June 15 to September 15. Construction is expected to take approximately 6 weeks.

Page 20: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …
Page 21: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

PDX/111610001 7-1 ES032411184302PDX

SECTION 7.0

Works Cited

CH2M HILL. 2008. Feasibility Study Report for the Former Baron-Blakeslee, Inc., Solvent Recycling Facility Site, 5920 NE 87th Avenue, Portland, Oregon. March.

__________. 2009a. Design Basis Report for Well Installation and Aquifer Testing, Former Baron-Blakeslee, Inc., Solvent Recycling Facility Site, Portland, Oregon.

__________. 2009b. Remedial Design/Remedial Action Work Plan, Former Baron-Blakeslee, Inc., Solvent Recycling Facility Site, Portland, Oregon. May.

Oregon Department of Environmental Quality (DEQ). 2008. Record of Decision, Final Remedial Action for Former Blakeslee, Inc. Solvent Recycling Facility Site. September.

__________. 2009. Risk-Based Decision Making for the Remediation of Petroleum-Contaminated Sites. September 15.

Page 22: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …
Page 23: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

Appendix A Design Drawings

Page 24: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

N

FIGURE 1Site LocationFormer Baron-Blakeslee FacilityPortland, Oregon

Source: Parsons, 2004

ES062009008PDX 326958.P3.4T.46.03 6-22-09 ms

Page 25: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

'4'4

!!

!

!

!

!

!

!

!!!

!!

!

!!

!!

!!

!!

!!

!!!!

!

!!

!

!!!

!

!

!

Approximate Location of Transition

Between UGA-TGA and CRSA

EW-1

EW-2

!.

!.

FIGURE 2Particle Paths and CaptureZones for Selected Alternative

±0 500250 Feet

Downgradient System: - 2 extraction wells - 400 gpm total extraction rate - discharge of treated water to Columbia Slough

Source Area System: - 2 GCWs - 40 gpm circulation rate

Components of Alternative

Legend

Former Baron-Blakeslee FacilityPortland, Oregon

Capture Zone Extent

MCL Remedial Action Area

Particle Paths(Arrows Denote 1-Year Travel Times)

!. Downgradient GCW Well

'4 Source Area GCW Well! BBI Investigation Well

!. Extraction Well

Page 26: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

GE

NE

RA

L

MR

LIT

TL

E

G-001

PA

LO

NG

LO

CA

TIO

N M

AP

, V

ICIN

ITY

MA

P,

AN

D I

ND

EX

TO

DR

AW

ING

S

OREGON

PA

CIF

IC

OC

EA

N

N

NTS

LOCATION MAP

ST. HELENS

ASTORIA

TILLAMOOK

MCMINNVILLE

ALBANYNEWPORT

CORVALLIS

HOODRIVER

DALLESTHE

MADRAS

PRINEVILLE

COQUILLE

GRANTSPASS

Ashland

BURNS

KLAMATH

FALLS

CONDON

MORO

PENDLETON

LA GRANDE

ENTERPRISE

VALE Ontario

PORTLAND

SALEM

MEDFORD

EUGENE

ROSEBURG

Athena

N. Powder

UnityDayville

Sisters

Juntura

Frenchglen

Burns Jct.

McDermitt

Paisley

La Pine

Crescent

Biggs

Lexington

HermistonBoardman

Ukiah

Arlington

Malin

Brookings

Coos Bay

Drain

Canyonvil le

Reedsport

Oakridge

GoshenFlorence

Lincoln City

Waldport

HomeSweet

DetroitAntelope

Maupin

ForestGrove

Hebo

Cannon Beach

SeasideRainier

Milton-Freewater

30

26

101

20

99W

26 35 197

97

74

84

82

3

3951926

26

205

34

36

126

38

126

20

395

26

7

20

78

95

3953197

58

42

62

140

66

140

101

199

5

22

Bonanza

84

Junction City

BAKER CITY

HEPPNER

Copperfield

LakeSilver

JunctionCaveBEACH

GOLD

OrfordPort

82

LAKEVIEW

CANYONCITY

DayJohn

CITYOREGON

HILLSBORO

DALLAS

Redmond

Z

Z

Val leyJordan

205

BEND

INDEX TO DRAWINGS

SHEET

NO.

DRAWING

NO.

TITLE

GENERAL

CIVIL

NTS

VICINITY MAP

MAYWOODPARK

AV

E.

AV

E.

AV

E.

AV

E.

AV

E.

AV

E.

AV

E.

AV

E.

AV

E.

AV

E.

AV

E.

74T

H73R

D A

VE

.

79T

H

SKIDMORE

GOING GOING

GOING

WYGANT

ALBERTA ALBERTA

HUMBOLDT

ROSELAWNSUMNER

WEBSTER

HOLMAN

CAMPAIGN

SKIDMORE

PRESCOTT

96T

H

97T

H

WYGANT

AV

E.

ST.

ST.

ST.

ST.

ST.

ST.

ST.

ST.

ST.

WEBSTER

SUMNER

EMERSON

AV

E.

ST.

ST.

WYGANT

ST.

78T

HP

L.

PL.

83R

D

84T

H

85T

H

86T

H

87T

H

88T

H

89T

H

90T

H

92N

D

AV

E.

AV

E.

AV

E.

COLUMBIA

BLVD

.

ST.

ST.

WYGANTST.

SKIDMORE

SKIDMOREST.

CT.

88TH

AV

E.

90TH

AV

E.

AL

DE

RW

OO

D

COLUMBIA

RD

.

79TH

CT

.

92N

D

DR

.78T

H

CT

.

DR

.

MARX

80T

HA

VE

.

AV

E.

AV

E.

ST.

HO

LM

AN

ST.

RD.

AV

E.

82N

D

87T

H

BLVD.

MARX

ST.SIMPSON

SANDY

KILLINGSWORTH ST.

CLARK

RD.

ST.ST.

PRESCOTTST.

108T

H A

VE

.

101S

T

105T

H

91S

T

91S

T

AV

E.

AV

E.

AV

E.

1617

20 21

1516

21 22

M.P. 23.28

Columbia

Johnson

Lake

SACAJAWEA

PARK

SUMNERSCHOOL

FIRESTA.

GOLF

COURSE

PACIFIC

FR

EE

WA

Y

NO

. 64

HWY.

PORTLANDNORTHEAST30

BY.

30BUS.

80T

H

AV

E.

INTER

NA

TIO

NA

L

105T

HA

VE

.

FIRE

MT. HOOD

NO

RT

H

NO

. 68

82N

D

73R

D

102N

DA

VE

.

109T

H

LIBERTY

SARATOGAST.

ST.

AV

E.

Slough

106T

H A

VE

.

107T

H A

VE

.

GLASS PLANT

95T

H A

VE

.

98T

H A

VE

.

100T

H A

VE

.

103R

D A

VE

.

104T

H A

VE

.

75T

H

AV

E.

76T

HA

VE

.

AV

E.

AV

E.

77T

H

78T

H

AV

E.

PRESCOTTELEM.

COLUMBIAPIONEER

SCHOOL

Parkrose

Fir

WA

RD

ST.

AL

DE

RW

OO

DR

D.

COLFAX ST.

CEMETERY

STATION

COMM. COLLEGE

AL

DE

RW

OO

DRD

.

DEERING

RD

.

ALD

ERW

OO

D

GOLF

COURSE

NATIONAL

COLWOOD

UNION

75T

H A

VE

.

76T

H A

VE

.

ALBERTA

ST.

205

NHS

NHS

NHS

NHS

NHS

NHS

NHS

PROJECT

LOCATION

FO

RM

ER

BB

I S

OL

VE

NT

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L,

INC

G-001

G-002

1

2

HONEYWELL INTERNATIONAL, INC.FORMER BBI SOLVENTRECYCLING FACILITY

402431

1

N

V R

YB

EL

J T

RA

CY

NOT TO SCALE

ATTACHMENT

EROSION CONTROL PLAN AS PART OF THE 1200-C NPDES PERMIT #10676

PROJECT LOCATION:

PORTLAND

LOCATION MAP, VICINITY MAP, AND INDEX TO DRAWINGS

CIVIL AND ELECTRICAL LEGEND

3

4

5

6

7

8

9

10

11

12

C-100

C-101

C-102

C-103

C-201

C-501

C-502

C-503

C-504

C-505

OVERALL SITE PLAN

OUTFALL GRADING AND EROSION CONTROL PLAN

OUTFALL PLAN AND PROFILE

WELL PIPELINE AND CONDUIT PLAN

WELL PIPELINE SOUTH PROFILE

DETAILS

DETAILS AND SECTIONS

DETAILS

DETAILS AND SECTIONS

DETAILS

OFFSITE GROUNDWATER PUMP & TREAT SYSTEMOUTFALL AND PIPELINE CONSTRUCTION

100% DESIGN SUBMITTAL

MAY 2011

FILENAME: PLOT DATE: PLOT TIME:05-G-001_326958.dgn 5/5/2011 11:03:29 AM

CH

2M

HIL

L 2

00

9.

AL

L R

IGH

TS

RE

SE

RV

ED

.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D,

IN W

HO

LE

OR

IN

PA

RT

, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T,

AN

D T

HE

ID

EA

S A

ND

DE

SIG

NS

IN

CO

RP

OR

AT

ED

HE

RE

IN,

AS

AN

IN

ST

RU

ME

NT

OF

PR

OF

ES

SIO

NA

L S

ER

VIC

E,

IS T

HE

PR

OP

ER

TY

OF

RE

US

E O

F D

OC

UM

EN

TS

:c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A

Page 27: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

157.7

155 8" PE

H

E

//////XX GE

NE

RA

L

MR

LIT

TL

E

G-002

PA

LO

NG

NOT TO SCALE

GENERAL NOTE:

1.

CIVIL LEGEND

SPOT ELEVATION

CONTOUR LINE

DRAINAGEWAY OR DITCH

158.5

155

EMBANKMENT AND SLOPE3:1

SIGNOR

MANHOLE

POST OR GUARD POST

UTILITY POLE

SURVEY CONTROL POINT OR

POINT OF INTERSECTION

CENTER LINE, BUILDING, ROAD, ETC.

STRUCTURE, BUILDING OR FACILITY

LOCATION POINT - COORDINATES

N 1000.00

E 1000.00

LIGHT POLE

TREE

BRUSH/TREE LINE

FIRE HYDRANT

STRUCTURE, BUILDING OR FACILITYOR

ASPHALT CONCRETE PAVEMENT

GRAVEL SURFACING

OR

DEMOLITIONOROR

CULVERT

CATCH BASIN OR INLET

TRENCH DRAIN

ELECTRICAL MANHOLE

BENCH MARK

TEST PIT LOCATION AND NUMBER

PIEZOMETER LOCATION AND NUMBER

CONCRETE PAVEMENT

SINGLE SWING GATE

DOUBLE SWING GATE

ARCHITECTURAL FENCE

EXISTING THIS CONTRACT

INDICATOR POST VALVE

FLEXIBLE COUPLING

YARD PIPING LEGEND

PIPING < 30" DIAMETER

EXISTING PIPE TO BE ABANDONED

EXISTING PIPE TO BE REMOVED

NON-FREEZE HOSE VALVE (V-X)

X = NO. IN SPECIFICATIONS

NON-FREEZE HOSE VALVE WITH HOSE RACK (V-X)

X = NO. IN SPECIFICATIONS

GATE VALVE AND VALVE BOX

BUTTERFLY VALVE AND VALVE BOX

PLUG VALVE AND VALVE BOX

90° ELBOW UP

90° ELBOW DOWN

CONCENTRIC REDUCER

CAP OR PLUG

NOMINAL PIPE DIAMETER

8" PE

PIPE USE IDENTIFICATION

CLEANOUT

FIRE HYDRANT

TP-2

P-3

BEND < 90° UP

BEND < 90° DOWN

THIS CONTRACTEXISTING

OR

OR

GENERAL SITE NOTES:

BM

CB CB

T

D S

E

THIS IS A STANDARD LEGEND SHEET.

THEREFORE, NOT ALL OF THE INFORMATION

SHOWN MAY BE USED ON THIS PROJECT.

GW-24

1

C-501

3

C-501

FO

RM

ER

BB

I S

OL

VE

NT

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L,

INC

EW-24 EXTRACTION WELL LOCATION AND NUMBER

PILOT BORE HOLE LOCATION AND NUMBER

MONITORING WELL LOCATION AND NUMBER

ABBREVIATIONS

EW-24P2

//////XXWETLANDS LIMIT

100-YR FLOOD PLAIN (EL18.0’)

LIMIT OF ENVIRONMENTAL ZONE

EXCAVATION LIMIT

402431

2

2

C-501

SEDIMENT FENCE

HIGHLY VISIBLE PLASTIC FENCE

GRAVEL CONSTRUCTION ENTRANCE

EROSION CONTROL BLANKET

TURBIDITY CURTAINTC

V R

YB

EL

J T

RA

CY

CIV

IL A

ND

EL

EC

TR

ICA

L L

EG

EN

D

HHx-yz

GENERAL ELECTRICAL NOTES:

1.

2.

3.

4.

5.

ELECTRIC HANDHOLEx = 1, 2 SEE ELECTRICAL HANDHOLE SCHEDULEy = E (ELECTRICAL POWER), C (INSTRUMENTION & CONTROL)z = NUMERICAL LOCATION DESIGNATOREXAMPLE: HH1-E2, INDICATES TYPE HH1 HANDHOLE,FOR ELECTRICAL POWER, SECOND LOCATION

ELECTRICAL HANDHOLE SCHEDULE:

1.

2.

3.

HH1: HS20 TRAFFIC RATED CONCRETE PULL BOX WITH SOLID CONCRETE BOTTOM AND HINGED, SPRING-ASSIST

GALVANIZED DIAMOND PLATE DOOR WITH LATCH. PROVIDE CABLE RACK HARDWARE ON ALL SIDES FOR CABLE

SUPPORT. MINIMUM INTERIOR DIMENSIONS: 42"L x 42"W x 36"H.

HH2: SAME AS HH1 EXCEPT, MINIMUM INTERIOR DIMENSIONS: 24"L x 24"W x 24"H.

CONDUIT SCHEDULE:

TAG CONDUIT BANK TYPE CONDUITS

P1

P2

P3

C1

C2

C3

POWER

POWER

POWER

INSTRUMENTATION AND CONTROL

INSTRUMENTATION AND CONTROL

INSTRUMENTATION AND CONTROL

2 - 2"C & 2 - 1" C (MODIFIED)

1 - 2"C & 1 - 1" C (MODIFIED)

1 - 2"C & 1 - 1" C (MODIFIED)

1 - 1-1/4" C (ANALOG), 1 - 1-1/4"C, 1 - 1"C

1 - 1" C (ANALOG), 2 - 1"C

1 - 1" C (ANALOG), 2 - 1"C

1

C-5052

C-505

3

C-505

4

C-505

5

C-505

ALL CONDUITS SHALL CONTAIN A PULL STRING FOR FUTURE USE. STUB AND CAP ENDS OF CONDUIT RUNS.

ALL CONDUIT BENDS SHALL HAVE A MINIMUM RADIUS OF AT LEAST 12 TIMES THE NOMINAL CONDUIT TRADE SIZE

(IE 3" CONDUIT SHALL HAVE A MINIMUM 36" RADIUS BENDS AND SO ON).

ANALOG CONTROL CONDUITS SHALL NOT BE ROUTED CLOSER THAN 24-INCHES TO POWER CONDUITS.

FOR CONDUIT TRENCHES CONTAINING MORE THAN 2 CONDUITS, REFER TO . FOR CONDUIT TRENCHES

CONTAINING 1 OR 2 CONDUITS, SEE .

FOR ELECTRICAL AND CONTROL HANDHOLE PROVISIONS, SEE , , AND .

TOPOGRAPHIC SLOPE

C-502

2

SOURCE OF TOPOGRAPHY SHOWN ON THE CIVIL PLANS IS SURVEYED BY CH2M HILL, JAN 2009 AND JULY 2010.

EXISTING CONDITIONS MAY VARY FROM THOSE SHOWN ON THESE PLANS. VERIFY EXISTING CONDITIONS AND

ADJUST WORK PLAN ACCORDINGLY PRIOR TO BEGINNING CONSTRUCTION.

EXISTING TOPOGRAPHY, STRUCTURES, AND SITE FEATURES ARE SHOWN SCREENED AND/OR LIGHT-LINED.

NEW FINISH GRADE, STRUCTURES, AND SITE FEATURES ARE SHOWN HEAVY-LINED.

HORIZONTAL DATUM: NAD83(91) OREGON NORTH

VERTICAL DATUM: NAVD88

MAINTAIN, RELOCATE, OR REPLACE EXISTING SURVEY MONUMENTS, CONTROL POINTS, AND STAKES WHICH ARE

DISTURBED OR DESTROYED. PERFORM THE WORK TO PRODUCE THE SAME LEVEL OF ACCURACY AS THE ORIGINAL

MONUMENT(S) IN A TIMELY MANNER, AND AT THE CONTRACTOR’S EXPENSE.

COORDINATES AND DIMENSIONS SHOWN FOR ROADWAY IMPROVEMENTS ARE TO EDGE OF GRAVEL.

STAGING AREA SHALL BE FOR SUBCONTRACTOR’S EMPLOYEE PARKING, SUBCONTRACTOR’S TRAILERS AND

ON-SITE STORAGE OF MATERIALS.

PROVIDE TEMPORARY FENCING AS NECESSARY TO MAINTAIN SECURITY AT ALL TIMES.

ELEVATIONS GIVEN ARE TO FINISH GRADE UNLESS OTHERWISE SHOWN.

SLOPE UNIFORMLY BETWEEN CONTOURS AND SPOT ELEVATIONS SHOWN.

EROSION CONTROL DEVICES , AND ARE THE MINIMUM REQUIRED. INSTALL AS PER

THE LOCATIONS GIVEN IN THESE CONSTRUCTION DRAWINGS. INSTALL THE HIGHLY VISIBLE PLASTIC FENCING

AS PER THESE CONSTRUCTION DRAWINGS.

IN ADDITION TO THE ESC MEASURES NOTED ABOVE, FOLLOW THE EROSION CONTROL AND SEDIMENT CONTROL

PRACTICES OUTLINED AND COVERED IN THE EROSION CONTROL PLAN AS PART OF THE EXISTING 1200-C-NPDES

PERMIT (PERMIT #10676), WHICH IS INCLUDED AS AN ATTACHMENT TO THESE DRAWINGS. INSTALL THE ESC

MEASURES, FROM SAID PLAN, THAT APPLY TO THE AREAS THAT WILL BE IMPACTED BY THIS PROJECT,WHICH

INCLUDE AS A MINIMUM THE ACCESS ROAD, THE WETLANDS PROTECTION, THE STAGING AREAS, AND THE

ENVIRONMENTAL ZONE.

FIELD VERIFY LOCATION AND DEPTH OF ALL EXST UTILITIES PRIOR TO BEGINNING EXCAVATION.

MAINTAIN GOOD HOUSEKEEPING PRACTICES IN ACCORDANCE WITH THE EROSION CONTROL PLAN.

MAINTAIN EXISTING SEDIMENT FENCING, GRAVEL CONSTRUCTION ENTRANCE, STOCKPILES AND HIGHLY

VISIBLE PLASTIC FENCE ACCORDING TO THE MAINTENANCE REQUIREMENTS LISTED IN THE EROSION

CONTROL PLAN (PERMIT #10676).

TAKE ALL OTHER MEASURES TO POSITIVELY PRECLUDE EROSION MATERIALS FROM LEAVING THE SITE.

MINIMUM ALLOWABLE CLEARANCE BETWEEN PIPES AT CROSSINGS WILL BE 3�. PROVIDE CLSM SUPPORT AT

CROSSINGS AS PER

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.LEASE AREA BOUNDARY

ACB

BTWN

C-C

C

CL

CLSM

CONC

DIA

DWCP

EL

ECB

ESC

EXST

GALV STL

GW

HDPE

HH

IE

MAX

MIN

NTS

OD

P

POB

POE

REQD

SCHED

SDR

TC

TOC

TYP

ARTICULATED CONCRETE BLOCK

BETWEEN

CENTER TO CENTER

CONDUIT OR CONTROL

CENTERLINE

CONTROLLED LOW STRENGTH MATERIAL

CONCRETE

DIAMETER

DOUBLE WALL CONTAINMENT PIPE

ELEVATION

EROSION CONTROL BLANKET

EROSION AND SEDIMENT CONTROL

EXISTING

GALVANIZED STEEL

GROUNDWATER

HIGH DENSITY POLYETHYLENE

HANDHOLE

INVERT ELEVATION

MAXIMUM

MINIMUM

NOT TO SCALE

OUTSIDE DIAMETER

POWER

POINT OF BEGINNING

POINT OF ENDING

REQUIRED

SCHEDULE

STANDARD DIMENSION RATIO

TURBIDITY CURTAIN

TOP OF CONCRETE

TYPICAL

MAY 2011

FILENAME: PLOT DATE: PLOT TIME:05-G-002_326958.dgn 5/5/2011 11:03:35 AM

CH

2M

HIL

L 2

00

9.

AL

L R

IGH

TS

RE

SE

RV

ED

.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D,

IN W

HO

LE

OR

IN

PA

RT

, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T,

AN

D T

HE

ID

EA

S A

ND

DE

SIG

NS

IN

CO

RP

OR

AT

ED

HE

RE

IN,

AS

AN

IN

ST

RU

ME

NT

OF

PR

OF

ES

SIO

NA

L S

ER

VIC

E,

IS T

HE

PR

OP

ER

TY

OF

RE

US

E O

F D

OC

UM

EN

TS

:c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A

Page 28: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

GATE

GATE

CMP

INV

CMP

INV

CMP

INV

ECONC

INV

SQUARE

W

SS

GATE

GATE

GATE

GATE

CMP

INV

CMP

INV

SQUARE

E

MW

SQUARE

SQUARE

E

W

W

W

W

W

CMP

INV

CMP

INV

MW

MW

SQUARE

CMP

INV

MW

SS

W

MWMW

MWMW

W

GATE

MW #23

MR

LIT

TL

E

N

1" = 60’

C-100

PA

LO

NG

NOTES:

CIV

ILF

OR

ME

R B

BI

SO

LV

EN

T

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L,

INC

.

DESCRIPTIONPOINT

I.D.

SURVEY MONUMENT TABLE

NORTHING EASTING ELEV

OV

ER

AL

L S

ITE

PL

AN

0 60 120 180

Scale In Feet

ENVIRONMENTAL

ZONE

WITTAKER SLOUGH

COLUMBIA SLOUGH

NE

82N

D A

VE

WETLANDS

WETLANDS

COMMENT

CONTRACTOR ACCESS

PATH, SEE NOTES 2 AND 3

2

C-501

1.

2.

3.

4.

LEASE AREA

EXST GRAVEL

ROAD

402431

10" DIFFUSER,

SEE C-102

10" OUTFALL,

SEE C-102

EXST TREATMENT

BUILDING

MAINTAIN EXST GRAVEL

CONSTRUCTION ENTRANCE

MAINTAIN EXST SEDIMENT

FENCING AND HIGHLY VISIBLE

PLASTIC FENCING, TYP

3

PORT OF PORTLAND BUILDING

305

351

352

700499.20

700482.11

700613.12

7670128.45

7670380.31

7670133.87

28.88

22.73

28.63

MAG NAIL WITH WASHER

MAG NAIL WITH WASHER

MAG NAIL WITH WASHER

APPROX 115’ SOUTH OF SURVEY POINT 352

APPROX 252’ EAST OF SURVEY POINT 305, SOUTH OF BLDG WALL

SE CORNER OF 82ND AVE AND CONTRACTOR ACCESS

STOCKPILE AREA,

SEE NOTE 4

V R

YB

EL

J T

RA

CY

STAGING AREA,

SEE NOTE 1

EW-1

EW-2

NEW PIPELINE AND

CONDUIT, SEE C-103

STAGING AREAS SHALL BE SIZED AND LOCATED

PER THE DIRECTION OF THE PRIME CONTRACTOR

AS REQUIRED IN THE 1200-C NPDES PERMIT

(PERMIT #10676)

LIMIT THE MOVEMENT AND TRANSPORT OF

CONSTRUCTION EQUIPMENT, SUPPLIES, AND

PERSONNEL TO THE ROUTES DESIGNATED HEREIN.

ALLOW AND MAINTAIN ACCESS DURING CONSTRUCTION.

CONSTRUCT STOCKPILES AS PER . DO NOT

ALLOW SEDIMENT OR OTHER STOCKPILED MATERIAL

TO ENTER THE WETLANDS OR ENVIRONMENTAL ZONE.

NORTH VAULT

SOUTH VAULT

MAY 2011

FILENAME: PLOT DATE: PLOT TIME:05-C-SPn-00_326958.dgn 5/5/2011 11:02:37 AM

CH

2M

HIL

L 2

00

9.

AL

L R

IGH

TS

RE

SE

RV

ED

.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D,

IN W

HO

LE

OR

IN

PA

RT

, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T,

AN

D T

HE

ID

EA

S A

ND

DE

SIG

NS

IN

CO

RP

OR

AT

ED

HE

RE

IN,

AS

AN

IN

ST

RU

ME

NT

OF

PR

OF

ES

SIO

NA

L S

ER

VIC

E,

IS T

HE

PR

OP

ER

TY

OF

RE

US

E O

F D

OC

UM

EN

TS

:c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A

305

351

352

Page 29: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

MR

LIT

TL

E

N

1" = 20’

C-101

PA

LO

NG

CIV

ILF

OR

ME

R B

BI

SO

LV

EN

T

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L,

INC

.

402431

4

0 5 10 15

Scale In Feet

LIMIT OF ENVIRONMENTAL

ZONE

ER

OS

ION

CO

NT

RO

L P

LA

N

20’

20’

HIGHLY VISIBLE

PLASTIC FENCE

1

C-501

30’

30’

2:1

2:1

2:1

2:1

EXCAVATION

LIMITS

18.0

18.0

3’3.3

3%

1.5:1 SLOPE

1.5:1 SLOPE

20’

20’

ANCHOR POINT, TYP

1.5:1

1.5:1

15’-

0"

3’

MIN

70’–

NOTES:

1. REFER TO C-102 FOR ACB MATTING AND DIFFUSER

PIPING.

MATCH EXST GRADE,

EL 12.50–

1:1

1:1

1:1

V R

YB

EL

J T

RA

CY

INSTALL SEDIMENT FENCE

ALONG WATER EDGE

EROSION CONTROL

BLANKET3

C-501

1

C-503

OU

TF

AL

L G

RA

DIN

G A

ND

SEDIMENT FENCE,

SEE C-103 FOR

CONTINUATION

HIGHLY VISIBLE

PLASTIC FENCE

ACB MATTING,

SEE NOTE 1

INSTALL TEMPORARY TURBIDITY

CURTAIN OUTSIDE WORK

MAY 2011

FILENAME: PLOT DATE: PLOT TIME:05-C-SPn-02_326958.dgn 5/5/2011 11:02:59 AM

CH

2M

HIL

L 2

00

9.

AL

L R

IGH

TS

RE

SE

RV

ED

.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D,

IN W

HO

LE

OR

IN

PA

RT

, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T,

AN

D T

HE

ID

EA

S A

ND

DE

SIG

NS

IN

CO

RP

OR

AT

ED

HE

RE

IN,

AS

AN

IN

ST

RU

ME

NT

OF

PR

OF

ES

SIO

NA

L S

ER

VIC

E,

IS T

HE

PR

OP

ER

TY

OF

RE

US

E O

F D

OC

UM

EN

TS

:c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A

N 700430.49

E 7671082.81

N 700364.05

E 7671063.12

N 700374.22

E 7670993.14

N 700445.06

E 7671014.14

N 700429.55

N 700418.39

E 7671063.46EL 17.9

E 7671025.35EL 17.9’

N 700439.62

E 7671015.66

N 700426.31

E 7671078.45

TC

TC

TC

TC

TC

Page 30: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

CMP

INV

CMP

INV

CMP

INV

CMP

INV

MW

MW

N

SITE PLAN1"= 20’

ORDINARY HIGH WATER

EL. 16.0

1

A1"=10’

NORMAL W.S EL. 12.5

1

2

1

2

MONITORING

WELLS

EXST 6" CMP

LIMITS OF EXST

GRAVEL ROAD AND

TURNAROUND AREA

ENVIRONMENTAL

ZONE BOUNDARY

BASE FLOOD EL 18.0

(100-YEAR FLOOD)

ORDINARY HIGH

WATER EL 16.0

402431

EXCAVATION

LIMITS

1

1

EXST

ELEC

E 7671043.70

IE 18.0

10" DIFFUSER

EXST

GROUND

1/2"= 1’-0"

GEOTEXTILE,

AS SPECIFIED

5

C-501

EXISTING

TREATMENT

BUILDING

10" OUTFALL

EL 12.5

ARTICULATED

CONCRETE

BLOCK

MATTING

EL 18.0

INSTALL EROSION CONTROL

BLANKET AND SEED WITH

GRASS AS SPECIFIED

FILL CELLS WITH EARTHFILL

AND SEED WITH GRASS AS

SPECIFIED

10"x10" TEE

STA 1+02.18

N 700421.68

S8 PLATIPUS STEALTH ANCHOR

60-INCH MIN EMBEDMENT. INSTALL

PER MANUFACTURER SPECS AND

REQUIREMENTS

OUTFALL SECTION

BANK EARTHWORK DETAIL

Scale In Feet

0 20 40 60

BUTT-FUSE JOINTS AS SPEC’D

INSTALL EROSION CONTROL

BLANKET AND SEED WITH

GRASS AS SPECIFIED

10" DR11 HDPE

DIFFUSER

FILL CELLS

WITH GROUTCMU BLOCK

MAY 2011

ARTICULATED CONCRETE BLOCK (ACB)

MATTING, OVERALL LENGTH = 22’

3.3%

3

C-503

FILL VOID SPACE BTWN SLOPE AND

ARMORFLEX WITH GROUT. SLOPE

GROUT AWAY FROM 1:1 EARTH SLOPE

CONNECT GROUND ANCHOR

TO STEEL REBAR, SEE

FILENAME: PLOT DATE: PLOT TIME:05-C-SPn-01_326958.dgn 5/5/2011 2:04:29 PM

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

PROJ

DATE

SHEET

DWG

A

E 7671015.95

BEGIN PIPELINEN 700327.76

NORMAL W.S. EL. 12.5

DISTANCE (FT)

ORDINARY HIGH WATER EL. 16.0

COLUMBIA

SLOUGH

EXST

GROUND

1

0

10

20

30

40

-10

0

10

20

30

40

-10

-0+10 0+00 1+00 1+80

-

FINISH

GRADE

4

C-501

DEEPEST DREDGE ELEV. 5.5 NAVD = EL. +2.0 NGVD

EXST

TREATMENT

BUILDINGCONNECTION TO BLDGBY OTHERS

BANK

EARTHWORKTYPICAL TRENCH

FLOOR EL. 25.6–

Page 31: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

CMP

INV

CMP

INV

CMP

INV

CMP

INV

CMP

INV

CMP

INV

MW

MW

AP

VR

ND

AT

ED

ES

CR

IPT

ION

NO

N N N N

AP

RV

AP

VR

AP

VR

AP

VR

DA

TE

DA

TE

DA

TE

DA

TE

DE

SC

RIP

TIO

N

DE

SC

RIP

TIO

N

DE

SC

RIP

TIO

N

DE

SC

RIP

TIO

N

NO

NO

NO

NO

MR

LIT

TL

E

0 20 40 60

Scale In Feet

N

1" = 20’

C-103

PA

LO

NG

LIMIT OF

ENVIRONMENTAL

ZONE

NOTES: CIV

IL

EXISTING

TREATMENT

BUILDING

FO

RM

ER

BB

I S

OL

VE

NT

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L, IN

C.

WETLANDS

LIMITS, TYP

SEE NOTE 1

WETLANDS

LIMITS, TYP

SEE NOTE 1

LIMIT OF

ENVIRONMENTAL

ZONE

402431

JT T

RA

CY

6

MAINTAIN HIGHLY VISIBLE

PLASTIC FENCE AROUND

THE WETLANDS

2

C-503

MAINTAIN EXST

SEDIMENT FENCE

SEE NOTE 2

10" OUTFALL,

SEE DWG C-102

SEE NOTE 2

PI, 90° BENDN 700283.94

E 7671014.42

B

C-504

EXST

GRAVEL

ROAD

PROTECT EXST

MONITORING WELL,

TYP

1

C-502

EXST ELEC,

SEE NOTE 3

1

C-502

6

C-505

EXST

GRAVEL ROAD

[P1]

3"/6" GW (DWCP)

5

C-503

5

C-503

MAINTAIN EXST

SEDIMENT FENCE

100-YR FLOOD

PLAIN, EL 18.0

SOUTH

WELL VAULT

GUARD POST,

TYP OF 4

LEAK DETECTION

STATION, SEE

AND C-201

CONNECT TO EXST

SEDIMENT FENCE

WE

LL

PIP

EL

INE

AN

D C

ON

DU

IT P

LA

N

SEDIMENT FENCE,

SEE

C-501

1

SEDIMENT FENCE,

SEE1

C-501

[C1]

TERMINATE AT HIGHLY

VISIBLE PLASTIC FENCE,

SEE C-101

CONNECT 3"/6" GW TO

VAULT AT CL EL 20.75

SEDIMENT FENCE

INSTALL AT EDGE

OF STOCKPILE AREA,

SEE C-100

C-501

1

DJ

MIL

LE

R

DA

TE

NO

NA

PV

RD

ES

CR

IPT

ION

CAP PIPES WITH BLIND

FLANGE 5’ FROM BUILDING

[P2]

[P1]

PROTECT EXST

ELEC, SEE NOTE 3

HH2-C1

HH1-E1

[C1]

C

C-5

04

HH2-C2

[P3]

[C3]

HH1-E2

40°

3"/6" GW (DWCP) FOR

PROFILE, SEE DWG C-201

40%%d

40%%d

HH2-C3

HH1-E3

45%%d

[C2]

[C3]

[P3]

45%%d HH1-E4

HH2-C4

CONNECT 3"/6" GW

TO VAULT

NORTH WELL

VAULT

GUARD POST,

TYP OF 4SEE NOTE 4

2’CONC ENCASE

3"/6" GW, SEE 1

C-504

2’

MAY 2011

GUARD POST,

TYP OF 4

GUARD POST,

TYP OF 4

DO NO ENTER OR DISTURB EXST WETLAND.

MAINTAIN SEDIMENT FENCE AND HIGHLY VISIBLE

PLASTIC FENCE AROUND WETLAND AS SHOWN

PRIOR TO BEGINNING CONSTRUCTION. PROTECT

WETLANDS PER THE EROSION CONTROL PLAN

(PERMIT #10676).

SEED AND MULCH THE BACKFILLED TRENCH AS

PER THE REQUIREMENTS OF THE EROSION

CONTROL PLAN (PERMIT #10676) AND SPEC

SECTION 31 32 00, SOIL STABILIZATION.

FIELD VERIFY LOCATION AND DEPTH OF EXST ELEC

CONDUITS PRIOR TO COMMENCING EXCAVATION

ACTIVITIES IN AREA. A 3" PVC CONDUIT WITH 24"

COVER IS ANTICIPATED. PROTECT IN PLACE.

RESTORE GRAVEL ROAD AS PER

1.

2.

3.

4.

FILENAME: PLOT DATE: PLOT TIME:05-C-SPn-03_326958.dgn 5/5/2011 2:05:23 PM

CH

2M

HIL

L 2

009. A

LL

RIG

HT

S R

ES

ER

VE

D.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D, IN

WH

OL

E O

R I

N P

AR

T, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T, A

ND

TH

E I

DE

AS

AN

D D

ES

IGN

S I

NC

OR

PO

RA

TE

D H

ER

EIN

, A

S A

N I

NS

TR

UM

EN

T O

F P

RO

FE

SS

ION

AL

SE

RV

ICE

, IS

TH

E P

RO

PE

RT

Y O

FR

EU

SE

OF

DO

CU

ME

NT

S:

c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A

N 700261.19

E 7671028.81

N 700440.80

E 7670675.77

N 700415.83

E 7670668.53

N 700392.01

E 7670843.84

N 700354.79

E 7670762.87

N 700334.66

E 7670718.81

N 700264.15

E 7670685.27

N 700208.54

E 7670699.71

N 700135.95

E 7670823.24

LEAK DETECTIONSTATIONN 700353.37

EW-2 (BY OTHERS)

N 700120.97–

E 7670832.96–

APPROX,

FIELD VERIFY

EW-1 (BY OTHERS)

N 700391.95–

E 7670787.72–

APPROX,

FIELD VERIFY

E 7670775.30CL EL 18.25

EW-2P(BY OTHERS)

GW-24(BY OTHERS)

EW-1P2(BY OTHERS)

GW-25(BY OTHERS)

TC

Page 32: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

AP

VR

ND

AT

ED

ES

CR

IPT

ION

NO

N N N N

AP

RV

AP

VR

AP

VR

AP

VR

DA

TE

DA

TE

DA

TE

DA

TE

DE

SC

RIP

TIO

N

DE

SC

RIP

TIO

N

DE

SC

RIP

TIO

N

DE

SC

RIP

TIO

N

NO

NO

NO

NO

MR

LIT

TL

E

1" = 20’

C-201

PA

LO

NG

CIV

ILF

OR

ME

R B

BI

SO

LV

EN

T

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L,

INC

.

402431

JT T

RA

CY

7

MA

TC

HL

INE

, S

EE

BE

LO

W

MA

TC

HL

INE

, S

EE

AB

OV

E

1

C-502

5’

3"/6" GW PROFILE

EL

EV

AT

ION

(F

T)

EL

EV

AT

ION

(F

T)

DJ

MIL

LE

R

DE

SC

RIP

TIO

ND

AT

EN

ON

AP

VR

WE

LL

PIP

EL

INE

SO

UT

H P

RO

FIL

E

HORIZ 1"=20’VERT 1"=2’

STATION (FT)

SOUTH WELL VAULT

FOR EW-2, SEE

EXST GROUND

STATION (FT)

EXST TREATMENT

BUILDING WALL

MAY 2011

FILENAME: PLOT DATE: PLOT TIME:05-C-SPn-04_326958.dgn 5/5/2011 11:03:23 AM

CH

2M

HIL

L 2

00

9.

AL

L R

IGH

TS

RE

SE

RV

ED

.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D,

IN W

HO

LE

OR

IN

PA

RT

, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T,

AN

D T

HE

ID

EA

S A

ND

DE

SIG

NS

IN

CO

RP

OR

AT

ED

HE

RE

IN,

AS

AN

IN

ST

RU

ME

NT

OF

PR

OF

ES

SIO

NA

L S

ER

VIC

E,

IS T

HE

PR

OP

ER

TY

OF

RE

US

E O

F D

OC

UM

EN

TS

:c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A

10

12

16

20

24

28

0+00 1+00 2+00 3+00 4+00

3" CARRIER PIPE HDPE DR 17, 6" CONTAINMENT PIPE HDPE DR26

10

12

16

20

24

28

5+00 6+00 7+00 8+00

GW PIPELINE FROM NORTH VAULT

LOCATED IN SAME TRENCH AS

SOUTH PIPELINE FROM THIS LOCATION

TO THE TREATMENT BUILDING

3" CARRIER PIPE HDPE DR 17, 6" CONTAINMENT PIPE HDPE DR26

Page 33: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

1NTS

G-002

C-101

SEDIMENT FENCE

NOTES:ELEVATION

SECTION

PLAN

USE STITCHED LOOPS

OVER 2"x4" POSTS

NEWLY GRADED

OR DISTURBED

SLOPE

PROVIDE BASE COURSE

BACKFILL IN TRENCH

FILTER FABRIC MATERIAL,

36" WIDE ROLLS

INTERLOCKED 2"x4"

POSTS AND ATTACH

FILTER FABRIC

MATERIAL

1.

2.

3.

4.

ANGLE BOTH ENDS OF FILTER FABRIC

FENCE TO ASSURE SOIL IS TRAPPED

6"

6’ MAXIMUM SPACING

2NTS

G-002

C-100

3

G-002

C-101

BURY BOTTOM OF FILTER FABRIC 6" VERTICALLY BELOW FINISHED GRADE.

2"x4" DOUGLAS FIR OR STEEL FENCE POSTS.

STITCHED LOOPS TO BE INSTALLED UPHILL SIDE OF SLOPE.

COMPACT ALL AREAS OF FILTER FABRIC TRENCH.

4NTS

G-002

C-102

STOCKPILE DETAIL

402431

*

1

NOTES:

3’, TYP EXISTING GROUND

SAND BAGS,

TYP

1

C-501

SEDIMENT FENCE

ALL AROUND

MAXIMUM SLOPE,SEE NOTE 6

COVERING, SEE

NOTE 7

REINFORCED PLASTIC COVERING

LAID BELOW STOCKPILED MATERIAL

ALL SEAMS SHALL BE TAPED OR WEIGHTED DOWN FULL LENGTH. ALL SEAMS SHALL HAVE A

MINIMUM 12" OVERLAP.

SEAMS PARALLEL TO THE SLOPE CONTOUR SHALL HAVE THE UPHILL SHEET OVERLAP THE

DOWN HILL SHEET.

NO SURFACE RUN-OFF SHALL BE ALLOWED TO RUN UNDER THE PLASTIC COVERING.

DRAINAGE FROM AREAS COVERED BY REINFORCED PLASTIC SHEETING SHALL BE CONTROLLED

SUCH THAT NO DISCHARGE OCCURS DIRECTLY ONTO UNCONTROLLED DISTURBED AREAS OF THE

CONSTRUCTION SITE.

ALL SAND BAGS SHALL BE MAINTAINED IN PLACE WITH ROPE.

2:1 MAX SLOPE FOR STOCKPILES.

COVER STOCKPILES WITH REINFORCED PLASTIC COVERING.

1.

2.

3.

4.

5.

6.

7.

STOCKPILED MATERIAL

NTS

TYPICAL TRENCH

MIN WIDTH

PIPE ZONE

PIPE OD+1’-6"

DEPTH OF

COVER

TRENCH

BACKFILL

ABOVE

PIPE ZONE

12" MIN

PIPE OUTSIDE

DIAMETER

PIPE BEDDING

MATERIAL

TRENCH

STABILIZATION

WHERE REQD

MARKING

TAPE AS

SPECIFIED

1.

2.

3.

4.

5.

NOTES:

ANCHOR IN 6"x6" MIN TRENCH

AND STAPLE AT 12" INTERVALS

MIN 2" OVERLAP

STAPLE OVERLAPS,

MAX 5’ SPACING

MIN 6"

OVERLAP

BRING MATERIAL DOWN

TO A LEVEL AREA, TURN

THE END UNDER 4" AND

STAPLE AT 12" INTERVALS

5DIFFUSER DETAIL

C-102

3/4"=1’-0"

PLAN

A

3"10"x10" TEE

0.75" HOLE, TYP

SECTION A

3"4" TYP

4" C-C SPACING,

TYP10" HDPE SDR11

DIFFUSER PIPE

ESC BLANKET

3/8" GALV STL CABLE, PROVIDE

1/2" NEOPRENE PAD BTWN

CABLE AND PIPE

EROSION CONTROL BLANKET ON SLOPE

IF THERE IS A BERM AT THE TOP OF SLOPE, ANCHOR UPSLOPE OF THE BERM.

SLOPE SURFACE SHALL BE SMOOTH BEFORE PLACEMENT FOR PROPER SOIL CONTACT.

DO NOT STRETCH BLANKETS/MATTINGS TIGHT, ALLOW THE ROLLS TO MOLD TO ANY

IRREGULARITIES.

STAPLING PATTERN AS PER MANUFACTURER’S RECOMMENDATIONS.

FERTILIZE AND SEED BEFORE INSTALLATION.

DR 17

8" 8"

2’ 2’

HDPE PIPE, SEE

SPEC 33 05 01.10

10" DIFFUSER PIPE

8"x8"x16" CMU BLOCK,

FILL WITH GROUT

GEOTEXTILE

SEAT CMU BLOCK

IN GROUT

3/8" GALV STL

CABLE

MAY 2011

16.25’ 16.25’

3" 3"

PROVIDE ONE CABLE ADJACENT

TO AND 3" OUTSIDE EACH CMU

BLOCK, TYP BOTH SIDES

3"

FUSION WELDED JOINT

2" MIN FROM

JOINT, TYP

3"

DR 11

3" 3"

12", TYP BOTH SIDES2.5’ TO 3’, TYP

FLANGED ADAPTER WITH EPOXY

COATED DUCTILE IRON BACKING RING

AND BLIND FLANGE AND 304 STAINLESS

STEEL BOLTS, TYP BOTH ENDS

CMU BLOCK

(BELOW), TYP

FLANGED ADAPTER WITH EPOXY

COATED DUCTILE IRON BACKING RING

AND BLIND FLANGE AND 304 STAINLESS

STEEL BOLTS

DRILLED 0.75" DIA

HOLE, TYP

FILL OPENING

WITH GROUT

ACB CONC UNIT

GALVANIZED EYE-EYE TURNBUCKLE

RATED FOR MIN 500LBS AND INSTALLED

ON DRY SIDE OF DIFFUSER6" GRANULAR FILL WITHIN

3’ BENCH AREA

PREPARED SUBGRADE

FILENAME: PLOT DATE: PLOT TIME:05-C-501_326958.dgn 5/5/2011 2:07:16 PM

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

PROJ

DATE

SHEET

DWG

A

Page 34: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

P

P

MR

LIT

TL

E

AS NOTED

C-502

PA

LO

NG

CIV

ILF

OR

ME

R B

BI

SO

LV

EN

T

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L,

INC

.

402431

9

J T

RA

CY

12" TYP 12" TYP

MINIMUM ALLOWABLE

CLEARANCE IS 3"

PLAN SECTION

1.

2.

3.

4.

CLSM SUPPORT IS REQUIRED:

NOTES:

2TRENCH PIPE CROSSINGNTS

G-002

1

C-103

4’-

6"

PLAN

1’-

0"

WELL VAULT

1’-

6"

2’-0"

6"

MIN

CONTROLLED

LOW-STRENGTH

MATERIAL (CLSM)

CLSM

WHEN BOTH PIPELINES ARE NEW AND CLEARANCE BETWEEN THEM IS LESS THAN 12".

WHEN A NEW PIPELINE IS CROSSING OVER AN EXISTING PIPELINE AND THE

CLEARANCE BETWEEN THEM IS LESS THAN 12".

AT ALL PIPE CROSSINGS WHERE A NEW PIPELINE IS CROSSING UNDER AN

EXISTING PIPELINE.

REFER TO SPECIFICATION SECTION 02320 FOR CLSM REQUIREMENTS.

4

C-503

NTS

DJ

MIL

LE

R

FLOAT SWITCH

(BY OTHERS)

12"

NOTES:

STEEL

DISCHARGE

PIPE (BY

OTHERS)

EXST WELL

CASING

2%

4"

WELL CASING

PENETRATION PREPARED

SUBGRADE

6"

BALL VALVE(BY OTHERS)

VAULT FLOOR

2% MIN

WATER LEVEL

TRANSMITTER

CABLE (BY

OTHERS)

DRAIN CHANNEL AROUND

EDGE OF HATCH AND

THROUGH CENTER

ALUMINUM

ACCESS HATCH

GROUND

SURFACE

8"

BALL VALVE(BY OTHERS)

FLANGE FITTINGS, TYP

WATER LEVEL

TRANSMITTER

CABLE (BY OTHERS)ELECTRICAL

CABLE (BY

OTHERS)

ADJUSTABLE

PIPE SUPPORT

(BY OTHERS)

1-1/2" PVC DRAIN PIPE

CONNECT TO DRAIN

CHANNEL THEN SLOPE

AT S=1% TO DAYLIGHT

BLINDFLANGE

BLIND FLANGE

TO TREATMENT

BUILDING

6" 6"

4" 8" 13" 13" 4" 4"4"

1" P

2" P

1" C

1" C

3"/6

" G

W

1" C

6"

PRECAST

CONC VAULT

PREPARED

SUBGRADE

15" T

YP

HOLE SHALL BE PRECAST,

TYP. COORDINATE HOLE

SIZE WITH PIPE DIAMETERS

SECTION A

SECTION B

DE

TA

ILS

AN

D S

EC

TIO

NS

GRANULAR FILL, COMPACT

TO 95% RELATIVE COMPACTION

IN ACCORDANCE WITH ASTM

D1557

GRANULAR FILL, COMPACT

TO 95% RELATIVE COMPACTION

IN ACCORDANCE WITH ASTM

D1557

SEAL END OF ELEC

AND COMM CONDUITS

WITH SILICONE, TYP

BLIND FLANGE

PRESSURE GAUGE(BY OTHERS)

2

C-504

A

6"

4’-

2"

6"

48"x72" ALUMINUM, HINGED, H-20 RATED DOUBLE-LEAF,

ACCESS HATCH. HATCH SHALL BE LOCKABLE AND

EQUIPPED WITH STEEL LIFT ASSISTS. MFG BY

SYRACUSE CASTINGS. HATCH SHALL BE GASKETED

FOR A WATERTIGHT AND GAS TIGHT APPLICATION.

PROVIDE MODEL LDTD-GSKTS-B

STEEL

DISCHARGE PIPE

(BY OTHERS)

WELL CASING

NON-SHRINK

GROUT

6" 6’-6" 6"

3’-0"

8"

TO TREATMENT

BUILDING

B

PRECAST CONCRETE VAULT

OLDCASTLE PRECAST MODEL

575-LA, SIM

VAULT FLOOR

2% MIN

ELECTRICAL

CABLE (BY OTHERS)

B

3

C-504

6"

NON-SHRINK

GROUT, TYP 2

C-504

LIMITS OF FLEX

RESTRAINT

COLLAR

PRECAST VAULT BASE SHALL BE

CAST AS A SINGLE MONOLITHIC

POUR WITH NO JOINTS

3

C-504

FO

R P

&C

NON-SHRINK

GROUT, TYP

CL SEE PROFILE

ON DWGS C-201

AND C-103

LIMITS OF FLEX

RESTRAINT COLLAR

DO NOT INSTALL

SILICONE SEAL IN

END OF DWCP

DOUBLE WALLCONTAINMENT PIPE(DWCP)

PVC CONDUIT

MAY 2011

TO TREATMENT

BUILDING

DOUBLE WALL PIPE

WALL

PENETRATION

OF DWCP

FLEX RESTRAINT

COLLAR

2" T

YP

STEEL WALL

MOUNTED

LADDER, SEE

NOTE 2

12" DIA SUMP

PIPE PENETRATION, TYPFOR PVC CONDUITS

PVC CONDUIT

1.

2.

3.

4.

2%

EXST WELL

CASING TO

BE REMOVED

EXST WELL

CASING TO

REMAIN

GROUT TO

PROVIDE

SLOPE TO

FLOOR

FLOAT SWITCH

(BY OTHERS)

VAULT SHALL BE

DESIGNED TO RESIST

3500LB POINT LOAD

DUE TO THERMAL

EXPANSION OF DWCP

ELECTRICAL AND I&C CONDUITS SHOWN SCHEMATICALLY. INSTALL NUMBER AND SPACING PER G-002 AND .

ATTACH LADDER TO WALL AND TO FLOOR USING 1/2" DIA ANCHORS AND AS PER THE MANUFACTURER’S

RECOMMENDATIONS.

VAULT SIZE AND DESIGN BASED ON OLD CASTLE PERCAST MODEL 575-LA.

INSTALL A 10"x14" SELF-ADHESIVE WARNING SIGN ONTO THE ALUMINUM ACCESS HATCH. SIGN SHALL READ

"DANGER - CONFINED SPACE, ENTER BY PERMIT ONLY".

FILENAME: PLOT DATE: PLOT TIME:05-C-502_326958.dgn 5/5/2011 2:10:29 PM

CH

2M

HIL

L 2

00

9.

AL

L R

IGH

TS

RE

SE

RV

ED

.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D,

IN W

HO

LE

OR

IN

PA

RT

, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T,

AN

D T

HE

ID

EA

S A

ND

DE

SIG

NS

IN

CO

RP

OR

AT

ED

HE

RE

IN,

AS

AN

IN

ST

RU

ME

NT

OF

PR

OF

ES

SIO

NA

L S

ER

VIC

E,

IS T

HE

PR

OP

ER

TY

OF

RE

US

E O

F D

OC

UM

EN

TS

:c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A

Page 35: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

MR

LIT

TL

E

AS NOTED

C-503

PA

LO

NG

CIV

ILF

OR

ME

R B

BI

SO

LV

EN

T

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L,

INC

.

1NTS

C-101

402431

J T

RA

CY

TURBIDITY CURTAIN

TURBIDITY CURTAIN

PLAN

SECTION

WATER SURFACE

EXST

GROUND

BOTTOM OF

CURTAIN

ANCHOR

1’

2SURFACE RESTORATIONNTS

C-103

3"

12"

EXST GRAVEL

ROAD

EXST

GEOTEXTILETRENCH BACKFILL

ABOVE PIPE ZONE

12’ MIN TRENCH WIDTH 12" MIN

1"-0 DENSE GRADED

AGGREGATE SURFACE

COURSE

2 -1/2"-0 DENSE GRADED

AGGREGATE BASE

COURSE COMPACTED IN

(2) EQUAL LIFTS

3NTS

C-102

ARMORFLEX ANCHOR CONNECTION

DE

TA

ILS

10

TOE OF SLOPE,

SEE1

C-102

ARMORFLEX CLASS 40

REVETMENT

FLOATATION

MEMBER

UPPER TENSION

MEMBER

TURBIDITY CURTAIN

LOWER ANCHOR MEMBER

CONNECTING ANCHOR TO

FLOATATION MEMBER

DIRECTION OF FLOW

6"6"

OPENING

DIAMETER

FILL W/

NON-SHRINK

GROUT

COMPACTED

GRANULAR FILL#4 HOOP PIPE OD+4"

TYP T&B

PRECAST

VAULT

BASE

WELL SEAL

12"

4NTS

C-502

S8 PLATIPUS STEALTH

ANCHORS, SEE NOTE 1

C-103

NTS5

EXST WELL

CASING

3" CARRIER

PIPE

DJ

MIL

LE

R

LEAK DETECTION STATION

WELD SEEPAGE RING

TO EXST CASING

10.75"

WELL CASING PENETRATION

ANCHOR

BOTTOM OF

CURTAIN

FLOTATION AND

UPPER TENSION

MEMBER

0 20 40 60

Scale In Feet

N

GEOTEXTILE

2’ 2’

CL ARMORFLEX

PANEL

SLOPE GROUT AT

2:1 AWAY FROM

CASING

HYDROPHILIC

WATERSTOP

TRIM EXISTING

REINF 2" CLEAR

OF PIPE, TYP

2" MIN

6"

6" INSPECTION PIPE

COMPACTED

GRANULAR FILL

CL

#5@12" EW

6" TEE IN CONTAINMENT

PIPE AT LOW POINT

6" TEE TO PROVIDE

LOW POINT FOR

INSPECTION AND

CLEANOUT

8" SQ

MAY 2011

2’ 2’

EDGE OF 8’ WIDE

ARMORFLEX PANEL

TERMINATE PLATIPUS

ANCHOR WITH HARD-EYE

TOP FITTING, TYP

EDGE OF 8’ WIDE

ARMORFLEX PANEL

8’ LONG, HOT-DIPPED

GALVANIZED #8 STEEL REBAR

REVETMENT CABLE LOOPS

3’x’3’ CONCRETE SLAB

MORRISON BROTHERS ABOVE

GROUND WELL PROTECTOR,

MODEL 680XA OR EQUAL. CUT

TO LENGTH AS REQUIRED.

SHOP COAT WITH TWO PART

EPOXY MATERIAL IN ACCORDANCE

WITH AWWA C550. DRY FILM

THICKNESS SHALL BE 10 MILS. MIN

3’

L 2x2x1/4x0’-4"

TYP 4 SIDES

1/8"

3/8" DIA ADHESIVE

ANCHOR W/ 3" MIN

EMBED, TYP

HDPE CAP. PROVIDE 3" CLEARANCE

BETWEEN TOP OF CAP AND WELL

PROTECTOR COVER

6"

4"

FILENAME: PLOT DATE: PLOT TIME:05-C-503_326958.dgn 5/5/2011 2:12:39 PM

CH

2M

HIL

L 2

00

9.

AL

L R

IGH

TS

RE

SE

RV

ED

.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D,

IN W

HO

LE

OR

IN

PA

RT

, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T,

AN

D T

HE

ID

EA

S A

ND

DE

SIG

NS

IN

CO

RP

OR

AT

ED

HE

RE

IN,

AS

AN

IN

ST

RU

ME

NT

OF

PR

OF

ES

SIO

NA

L S

ER

VIC

E,

IS T

HE

PR

OP

ER

TY

OF

RE

US

E O

F D

OC

UM

EN

TS

:c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A

Page 36: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

MR

LIT

TL

E

AS NOTED

C-504

PA

LO

NG

CIV

ILF

OR

ME

R B

BI

SO

LV

EN

T

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L,

INC

.

402431

J T

RA

CY

11

DJ

MIL

LE

R

DE

TA

ILS

AN

D S

EC

TIO

NS

C-103

NTS

SECTIONB

2’

MIN

PROTECT EXST SEDIMENT

FENCE AND HIGHLY

VISIBLE PLASTIC FENCE

DO NOT DISTURB

WETLANDS

EXST

GEOTEXTILE

RESTORE GRAVEL

SURFACING PER 2

C-503

12"

VARIES, SEE PLANS

PO

WE

R C

ON

DU

IT

I&C

CO

ND

UIT

NEW GEOTEXTILE

12" MIN

RESTORE GRAVEL THAT

SETTLES OR SLUFFS OFF

DURING CONSTRUCTION

EXST

GRAVEL ROAD

2’

MIN

SE

E P

RO

FIL

E

3"/6

" G

W

SCHEMATIC TRENCH EXCAVATION LIMITS.

CONTRACTOR TO VERIFY TRENCH WALL

STABILITY AND CONSTRUCT TO AVOID

IMPACTING THE EXST ADJACENT EROSION

CONTROL FENCING

EXST

GROUND

CSECTIONNTS

C-103

SCHEMATIC TRENCH EXCAVATION LIMITS.

CONTRACTOR TO VERIFY TRENCH WALL

STABILITY AND CONSTRUCT TO AVOID

IMPACTING THE EXST ADJACENT EROSION

CONTROL FENCING

2’

MIN

SE

E P

RO

FIL

E

2’

MIN

PO

WE

R C

ON

DU

IT

I&C

CO

ND

UIT

EXST GRAVEL

ROAD

1NTS

C-103

PIPE ENCASEMENT

7- #5

CONTINUOUS

LAP LENGTH, 12"

#5 TIES @ 12"

3" CLR,

TYP

8" MIN ALL

AROUND

C-502

NTS2

PIPE PENETRATION DETAIL

HYDROPHILIC

WATERSTOP

NON-SHRINK

GROUT

SECTION

PLAN

PRECAST HOLE

IN VAULT WALL

PIPE

PRECAST HOLE COORD

DIA WITH PIPE DIA

NON-SHRINK GROUT

2" MIN,

TYP

2

1

A

EXST ELEC, FIELD VERIFY

LOCATION AND DEPTH

PRIOR TO EXCAVATION

3"/6

" G

W F

RO

M

NO

RT

H W

EL

L V

AU

LT

3"/6

" G

W F

RO

M

SO

UT

H W

EL

L V

AU

LT

HYDROPHILIC

WATERSTOP

3NTS

C-502

FLEX RESTRAINT COLLAR

1’-0"

14", TYP

2", TYP

12"

#5 HOOP x

PIPE OD + 4"

SECTION

#5@12" EW

W/ 2 - #5@3"

T&B & EA

SIDE OF PIPE

18"

18"

6" 6"

BACKFILLED

SIDE OF WALL

6"

4000 PSI CONC

CLOSURE COLLAR,

SEE NOTE 2

2" , TYP

NOTES:

1.

2.

HYDROPHILIC WATERSTOP

BONDED TO PRECAST

SURFACE OF WALL CONT

ALL AROUND

ROUGHEN

SURFACE

FORM 1/2"x3/4"x1"

DEEP RECESS FOR

NON-SHRINK GROUT

ALL AROUND

4000 PSI CONC

IN HOLE

MAY 2011

1’-4" 2’ 1’-4"

MARKING TAPE,

AS SPECIFIED

MARKING TAPE,

AS SPECIFIED

1’-4" 1’-4"

SECTION - A

4000 PSI CONC

ELECTRO FUSE 2 FLEX RESTRAINTS TO THE PIPE. FLEX RESTRAINTS SHALL BE EQUALLY SPACED ABOUT

THE CIRCUMFERENCE OF THE PIPE. FLEX RESTRAINTS SHALL BE RATED FOR MIN 9000LB AXIAL FORCE.

MFG BY CENTRAL PLASTICS COMPANY OR APPROVED EQUAL. INSTALL AS PER THE MANUFACTURER

RECOMMENDATIONS.

SOAK CONCRETE SURFACES AND WITHIN 15-MINUTES CAST CONCRETE CLOSURE. (CONCRETE CLOSURE

MUST BE CAST BEFORE HYDROPHILIC WATERSTOP EXPANDS).

B

A

#5 DOWELS @

6" MAX SPG ALL

AROUND PERIMETER

OF CLOSURE COLLAR,

DRILL & EPOXY GROUT

4" INTO EXST WALLFLEX RESTRAINT,

SEE NOTE 1

SECTION - B

CIR

CU

LA

R O

PE

NIN

G

PIP

E O

D +

4"

#5 HOOP X PIPE

OD + 3" CNTRD

IN WALL

PRECAST HOLE

EXISTING WALL

REINF, BEND 1"

CLR OF PIPE

FILENAME: PLOT DATE: PLOT TIME:05-C-504_326958.dgn 5/5/2011 2:15:15 PM

CH

2M

HIL

L 2

00

9.

AL

L R

IGH

TS

RE

SE

RV

ED

.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D,

IN W

HO

LE

OR

IN

PA

RT

, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T,

AN

D T

HE

ID

EA

S A

ND

DE

SIG

NS

IN

CO

RP

OR

AT

ED

HE

RE

IN,

AS

AN

IN

ST

RU

ME

NT

OF

PR

OF

ES

SIO

NA

L S

ER

VIC

E,

IS T

HE

PR

OP

ER

TY

OF

RE

US

E O

F D

OC

UM

EN

TS

:c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A

///X

Page 37: Outfall-pipeline Design Basis Report FINAL - … SITE#: R37893 DOCUMENT FILE LOC: 4.15.01 Report Design Basis Report for Groundwater Conveyance and Discharge …

MR

LIT

TL

E

AS NOTED

C-505

PA

LO

NG

CIV

ILF

OR

ME

R B

BI

SO

LV

EN

T

RE

CY

CL

ING

FA

CIL

ITY

HO

NE

YW

EL

L I

NT

ER

NA

TIO

NA

L,

INC

.

402431

J T

RA

CY

DE

TA

ILS

FINISH GRADE

SPACERS

D

D

INSTALLATION OF DIRECT BURIAL DUCT BANKS WHICH

INCLUDE THREE OR MORE CONDUITS OR DUCTS SHALL

BE MADE IN ACCORDANCE WITH THIS DETAIL.

D = 3"MIN FOR 2"-6" CONDUIT

D = 2"MIN FOR <2 INCH CONDUIT

COMPACTED

EARTH

BACKFILL

#12 GALV IRON

TIE DOWN WIRE,

MAX 4’-0" APART

BACKFILL WITH

BEDDING AND

PIPE ZONE

MATERIAL 3"

ABOVE AND

3" BELOW

CONDUITS,

HAND TAMP

2’-0" MIN

(< 600 VOLTS)

3’-0 MIN

(> 600 VOLTS)

NOTES:

1.

"D"

CONDUIT

1’-2" MIN

(2-DUCTS)

8" MIN

(1-DUCT)

2"

MIN

2"

MIN

3"

MIN

3"

MIN

D = 3" MIN FOR 2" AND

LARGER CONDUIT

D = 2" MIN FOR 1 1/2" AND

SMALLER CONDUIT

24

" M

IN (

< 6

00

VO

LT

S)

36

" M

IN (

> 6

00

VO

LT

S)

FINISH

GRADE

SEE TRENCH AC

TOPPING DETAIL

(IF APPLICABLE)

COMPACTED

BEDDING AND

PIPE ZONE

MATERIAL

2"

SECTION

LIFT BRACKETS

HINGED COVER

2’-

0"

MIN

4" TYP

LENGTH VARIES,

SEE SCHEDULE

DE

PT

H V

AR

IES

,

SE

E S

CH

ED

UL

E

1’-

0"

MIN

12

"

MIN

GRADING RINGS

AS REQUIRED

INSCRIBE

"ELECTRICAL"

COVER LOCKING

SCREWS,

(TYP FOR 4)

HOT-DIPPED GALVANIZED

STEEL TRAFFIC DUTY COVER

AND FRAME HS-20 LOADING

FINISH

GRADE

GROUT TO FULL

WALL THICKNESS

AROUND PIPES AT

KNOCKOUTS, TYP

PLAN

4 LIFTING INSERTS

PVC CONDUIT

PVC END BELL

GROUT TO FULL

WALL THICKNESS

AROUND PIPES AT

KNOCKOUTS, TYP

3’-

6"

3’-

6"

3"

4"

CL

RM

IN

1’-6"

MIN DIA

1"

GROUT PLUG

FINISH GRADE

1NTS

G-002

3

G-002

NTS

2NTS

G-002

4

G-002

5NTS

G-002

UNDERGROUND CONDUIT IN NON-PAVED AREAS

TRENCH AND CONDUIT PLACEMENT

HANDHOLE

VA

RIE

S

SE

E S

CH

ED

UL

E

CONDUIT

CONDUIT HANDHOLE/MANHOLE ENTRANCENTS

CABLE RACK

INSIDE FACE

OF HANDHOLE

WALL

OUTSIDE FACE

OF HANDHOLE

WALL

CABLE RACK, HOOKS AND INSULATORS.

PROVIDE A MINIMUM OF 3 ON EACH RACK

MEMBER EACH CAPABLE OF SUPPORTING

3-CONDUCTOR SHELDED POWER CABLE

UP TO #2 ANG

6NTS

C-103

GUARD POST

8" DIA SCHED 40 STEEL

PIPE, GRIND SMOOTH,

FILL WITH CONC AND

PAINT SAFETY YELLOW

CONCRETE ENCASEMENT

MIN 4000 PSI STRENGTH

CONCRETE

12

FOR CONDUIT

ENTRANCE,

SEE4

CABLE RACKS OR SUPPORT

BRACKET ALL SIDES. MAY BE

EMBEDDED OR BOLTED, SEE

5

COMPACTED GRAVEL, 12"

DEEP, MIN 3/4" MINUS

6" MIN DRAIN

WITH GRATE

10 CF 1" TO 1 1/2"

GRAVEL, ALL

AROUND SUMP

DJ

MIL

LE

R

COMPACTED

EARTH BACKFILL

MARKING TAPE,

AS SPECIFIED

MARKING TAPE,

AS SPECIFIED

MAY 2011

FILENAME: PLOT DATE: PLOT TIME:05-C-505_326958.dgn 5/5/2011 11:02:28 AM

CH

2M

HIL

L 2

00

9.

AL

L R

IGH

TS

RE

SE

RV

ED

.

1 2 3 4 5 6

B

C

D

VERIFY SCALE

BAR IS ONE INCH ON

ORIGINAL DRAWING.

1"0

CH

2M

HIL

L A

ND

IS

NO

T T

O B

E U

SE

D,

IN W

HO

LE

OR

IN

PA

RT

, F

OR

AN

Y O

TH

ER

PR

OJE

CT

WIT

HO

UT

TH

E W

RIT

TE

N A

UT

HO

RIZ

AT

ION

OF

CH

2M

HIL

L.

TH

IS D

OC

UM

EN

T,

AN

D T

HE

ID

EA

S A

ND

DE

SIG

NS

IN

CO

RP

OR

AT

ED

HE

RE

IN,

AS

AN

IN

ST

RU

ME

NT

OF

PR

OF

ES

SIO

NA

L S

ER

VIC

E,

IS T

HE

PR

OP

ER

TY

OF

RE

US

E O

F D

OC

UM

EN

TS

:c

PROJ

DATE

DS

GN

DR

RE

VIS

ION

CH

K

AP

VD

BY

AP

VD

SHEET

DWG

A