pa14-006-3w-0003 tr for navigation aid
TRANSCRIPT
-
Doc. Code : Revision No : B1 Date : 17 / 04 / 2014 Page : 1 of 27
BADAMYAR DEVELOPMENT PROJECT
TECHNICAL REQUISITION FOR NAVIGATION AID SYSTEM
DOC. NO. : BDP-WHP-TR-E-0005
Prepared by Reviewed by Approved by
Full name
Signature
Date
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 2 of 27
RECORD OF REVISION
No Date Page Contents Remark
1 14/04/2014 All Approved for Bid B1
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 3 of 27
TABLE OF CONTENTS
1.0 PROJECT DESCRIPTION ........................................................................................ 4 2.0 SCOPE OF WORK / SUPPLY ................................................................................... 6 3.0 TECHNICAL REQUIREMENTS / SPECIFIC INSTRUCTIONS .......................... 8 4.0 DEVIATIONS, ALTERNATIVES AND CLARIFICATIONS................................. 9 5.0 LIST OF APPLICABLE DOCUMENTS ................................................................. 10
5.2 DATA SHEET(S) ............................................................................................................. 10 5.3 PROJECT DRAWING(S) ................................................................................................ 10 5.4 PROJECT SPECIFICATION(S) ..................................................................................... 10 5.5 OTHERS ......................................................................................................................... 11
6.0 VENDOR DATA REQUIREMENT LIST VDRL ................................................ 12 7.0 TYPICAL INSPECTION AND TEST PLAN .......................................................... 22 ATTACHMENT 1: TEST AND INSPECTION GENERAL REQUIREMENTS ............ 26 ATTACHMENT 2: DEVIATION / ALTERNATIVE / CLARIFICATION LIST ........... 27 ATTACHMENT 3: SPARE PARTS LIST AND INTERCHANGEABILITY RECORD 28
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 4 of 27
1.0 PROJECT DESCRIPTION
COMPANY has developed PM-3 CAA Northern Fields with a Central Processing Platform BO-A located at the Bunga Orkid Field with a series of Well Head Riser Platforms namely BO-B, BO-C & BO-D delivering hydrocarbons from the various field areas to the CPP with Bunga Pakma A as future.
The project will consider the design, build, installation and commissioning of the BP-A minimum facilities platform for the drilling of 7 initial gas wells with potential of up to 11 future wells. Production evacuation will be through a new export pipeline to BO-D/BO-A.
Bunga Pakma facilities will have 15 years design life. The current plan date for first gas is 1st Q 2016. The project will also incorporate the required brownfield modifications on BO-D/BO-A required to transport Bunga Pakma production to PM3 CAA Bunga Raya field and onward to the gas export pipelines.
This project will follow TML Project Delivery System (PDS) guideline. One technically and commercially viable business case will be developed followed by alternative selection process and assurance reviews to select best alternative concept.
Bunga Pakma presently comprises North Bunga Pakma and Bunga Pakma fields, which are located approximately 10 km from BO-A CPP. The FDP Rev 4 Addendum Update 5 was approved by PETRONAS in March 2005. In the FDP, there is a provision for a future remote wellhead platform in the Bunga Pakma area (BP-A WHRP). BP-A WHRP will act as a gathering point for production from North Bunga Pakma and Bunga Pakma fields.
The current plan is to have BP-A facility operational by January 2016. This is imperative as it is forecasted that TML gas production from Bunga Orkid field will decline. The Unit Gas Sales Agreement (UGSA) commitment is 270 MMSCF/D net hydrocarbons.
Bunga Pakma will provide Proven plus Probable (2P) reserves of 35.9 MMBOE (including 180.7 Bscf sales gas) gross over life of field while proven undeveloped reserves of 20.0 MMBOE (including 102.8 Bscf sales gas) gross are expected as of December 31st, 2011. Bunga Pakma will help ensure TML meets its contractual gas sales commitment as per UGSA and 2013 Business Plan.
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 5 of 27
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 6 of 27
2.0 SCOPE OF WORK / SUPPLY
VENDORs scope of work and supply shall include but not be limited to design, engi-neering, material procurement, manufacture, inspection, testing, surface preparation & painting, packaging for shipment and delivery of the equipment (as per the required de-livery terms and conditions) in accordance with the table below. The VENDOR shall be responsible for the supply of item(s) in all respects for the safe and reliable operation of the package.
No. Item/
Tag No. Qty Description
A EQUIPMENT I Navigation Aid system for LCP Platform shall be detailed in MM-YAD-35-
TTBE-130006, consist of:
1 NOBAT 31-2-1 1 lot NiCd Battery and ExeBattery Box, temperature Sensor with accessories
NOBCB 31-2-1 1 lot Navigation aids battery breaker 2 NOCP-31-2-1 1 EA Central Navigation Aids Control Panel 3 LCP-MNL-W1 1 EA Main Navigation Aids lantern
4 LCP-MNL-R1 LCP-MNL-R2 2 EA Subsidiary Navigation Aids lantern
5 LCP-AOL-R1 1 EA Aeronautical Obstruction Light 6 - 1 EA Photocell 7 - 1 lot Control interfacing with PDCS and ICSS system II Navigation Aid system for WP4 Platform shall be detailed in MM-YAD-90-
TTBE-130006, consist of:
1 NOBAT-41-2-1 1 lot Battery and Battery Box, temperature Sensor with accessories NOCBC-41-2-1 1 lot Navigation aids battery breaker
2 NOCP-41-2-1 1 EA Central Navigation Aids Control Panel
3
WP4-MNL-W1 WP4-MNL-W2 WP4-MNL-W3 WP4-MNL-W4
4EA Main Navigation Aids lantern
4 1EA Helideck Status 5 WP4-FH-1 1 EA Fog horn c/w Fog horn Controller.
6 WP4-AOL-R1 WP4-AOL-R2 2 EA Aeronautical Obstruction Light c/w accessories
7 1 EA Photocell 8 1 lot Control interfacing with PDCS and ICSS system B SCOPE OF WORK (applicable for each Navigation Aid System)
1 - All interconnection cabling between NCCP, marine lanterns, foghorns, photocell, etc, to complete system
2 - Control, indication, monitoring and communication facilities
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 7 of 27
3 - Complete system protection and metering facilities
4 - Any other service as may agree at time of other placement - Factory Acceptance testing I Spare parts and Special Tools 1 1 Lot Spare part for Startup/Commissioning
2 1 Lot Price list of recommended spare parts for 2 years op-eration
3 - 1 Lot Special tools for installation , operation and mainte-nance( where required)
4 - 1 Lot Spreader bars, slings and shackles for installation of the equipment using single point lift c/w with certifi-cate (If applicable)
II Guarantee and Warranty
1 - 1 Lot Guarantee and warranty complete for the package and supplied items III Painting, Inspection, Testing and Certification
1 - Surface preparation and painting(external) as per specifi-cation requirements
2 - - Inspection, Testing and Certification as per project re-quirements and attachment 1 IV Delivery 1 - - Packing, marking, forwarding and preservation
2 - - Transportation from the fabrication / assembly location to the point of delivery. 3 - - Shipping/transportation supports (if required). V Documentation
1 - 1 Lot Documentation as per VDRL and applicable Specifica-tions
2 - 1 Lot Final documentation e.g. Installation & Operating Manual (IOM), Manufacturers Data Report (MDR) VI Vendor supervision
1 Vendor supporting for installation, onshore commission-ing, offshore start up and commissioning. (Quote separate-ly, per diem rates)
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 8 of 27
3.0 TECHNICAL REQUIREMENTS / SPECIFIC INSTRUCTIONS
3.1 Technical requirements shall be as per the list of documents attached with this requisi-tion.
3.2 The VENDOR shall submit all the required drawings and documents as per Vendor Da-ta Requirement List (VDRL) available in Section 6.0 of this requisition. The VDRL shall be agreed between the VENDOR and PURCHASER / COMPANY before place-ment of order.
3.3 Vendor Document Schedule (VDS) Immediately after the award of contract, the VENDOR shall provide Vendor Document Schedule to the PURCHASER as per agreed VDRL. The register shall be in Microsoft excel format and contain the follow-ing data:
x Company/Purchaser Document / Drawing Number x VDRL Code x Vendor Document / Drawing Number (if applicable) x Document / Drawing title x Latest revision x Planned submission date x Actual 1st submission date of transmittal x Actual Return Date x Drawing/document approval status x Remarks if any x Columns shall be added for subsequent submissions
3.4 The VENDOR shall provide the list of commissioning and start-up spare parts. Spare
parts shall be part of main offer.
3.5 The VENDOR shall also provide the list of recommended spare parts for 2 years opera-tion along with pricing.
3.6 VENDOR shall provide a firm commitment for the continuous availability with the best terms, prices and conditions for all related special tools, spare parts and maintenance ser-vices necessary for duration of twenty (20) years after the ex-works delivery.
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 9 of 27
4.0 DEVIATIONS, ALTERNATIVES AND CLARIFICATIONS
VENDOR shall notify PURCHASERs of any proposed deviations and alternatives from the requirement specified in this requisition and Applicable Documents specified in section 5.0. VENDOR shall submit the deviations and alternatives list together with VENDOR proposal using ATTACHMENT 2.
VENDOR shall agree that the only deviations, exceptions and alternatives to be consid-ered by PURCHASER shall be limited to those separately specified in a proposed De-viation / Alternative / Clarification Sheet accompanying VENDOR proposal. PURCHASER has no responsibility to discover any deviations, exceptions or alterna-tives entered in other parts of VENDOR proposal than the said Deviation / Alternative / Clarification List.
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 10 of 27
5.0 LIST OF APPLICABLE DOCUMENTS
5.2 DATA SHEET(S)
No. Document Number Document Title Rev
1 MM-YAD-90-TTBE-130006 Datasheet for Navigation Aids System (WP4 Platform) 00
2 MM-YAD-35-TTBE-130006 Datasheet for Navigation Aids System (LCP Platform) 00
5.3 PROJECT DRAWING(S)
No. Document Number Document Title Rev 1 MM-YAD-90-TTBE-140001 WP4-General Single line Diagram 00
2 MM-YAD-90-TTBE-140002 WP4- Single line Diagram LV Switchgear 00
3 MM-YAD-35-TTBE-140001 LCP Platform-General Single line Diagram 01
4 MM-YAD-35-TTBE-140002 LCP Platform- Single line Diagram-LV nor-mal Switchgear 00
5 MM-YAD-35-TTBE-140010 LCP Platform- Single line Diagram-LV essen-tial Switchboard 00
6 MM-YAD-90-TTBE-140005 WP4-Single line diagram for Navigation Aids system 00
7 MM-YAD-35-TTBE-140005 LCP- Single line diagram for Navigation Aids system 00
8 MM-YAD-35-TTBE-140008 LCP Platform- Electrical Equipment Layout 00
5.4 PROJECT SPECIFICATION(S)
No. Document Number Document Title Rev 1 Exhibit H Quality Management 0 2 Exhibit H - Attachment H1 Scope of Work Certification 0
3 Exhibit H - Attachment H2 Specification for Equipment and Material Certi-fication 0
4 Exhibit H - Attachment H3 Minimum Inspection Requirements 0 5 Exhibit J List of Subcontractors and Vendors 0 6 Exhibit J Appendix J1 Approved Vendors List 0 7 GS EP ELE 001 Electrical Design Criteria 08
8 GS EP ELE 079 Electrical Apparatus for HV & LV Cable Siz-ing 06
9 GS EP ELE 161 Electrical Cable 05 10 GS EP ELE 221 Electrical Control system 05
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 11 of 27
11 GS EP ELE 321 Specification for Navigation Aids System 04 12 GS EP ELE 374 Construction site electrical installation 02
13 GS EP ELE 451 Third party inspection independent verifica-tion of electrical Facilities 03
14 GS EP ELE 460 Engineering Studies 04 15 GS EP LSO 115 Helideck Specification 01 16 GS EP STR 002 Crane for fixed offshore installation 08 17 GS EP TEL410 Installation Rules 05
18 MM-YAD-00-TTBE-110001 Electrical Design basic and Operating Phi-losophy 00
19 MM-YAD-00-TTBE-120008 Specification for Navigation Aid System 01
20 MM-YAD-00-TTBE-120009 Specification for Earthing and Bonding sys-tem 02
21 MM-YAD-00-TTBE-120011 Specification for Electrical requirement package 02
22 MM-YAD-00-TTBE-120013 Specification for Electrical Installation 01
23 MM-YAD-00-TTBE-130001 Datasheet for Electric Cable 02
24 MM-YAD-00-TTBE-170001 Electrical Equipment List 01
5.5 OTHERS
No. Document Number Document Title Rev 1 2
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 12 of 27
6.0 VENDOR DATA REQUIREMENT LIST VDRL
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10)
1 Commercial/Contractual
C01 Vendor Document Index & Schedule IFR +2W -- --
C02 Engineering, Procurement, Manufacturing and Test Schedule
IFR +4W -- --
C03 Sub Contract Work Proposal
C04 Delivery, Handling and Packing Proposals
C05 Exception and Non-Conformity Form IFR +4W MDR
C06 Vendors Sub-Orders (Un-Priced copy) -- IFR +4W -- MDR
C07 Warranty/Guarantee Confirmation IFR +4W MDR
C08 Vendor/Sub-Vendor List IFR +4W MDR
C09 Project Management Organisation
C10 Progress Reports (Weekly and Monthly) -- IFR Bi-
Monthly -- --
C11 Proven Design and Manufacturing Experi-ence List
IFR +4W -- --
C12 Schedule of Nozzle Pricing
2 Process / Mechanical / Piping / Structural
M01 Foundation Load and Anchor Bolt Loca-tion
M02 Drive Assembly Details
M03 Equipment Design Calculations including Transportation
M04 Structural Design Calculations
M05 Pipe Stress Calculations
M06 Process Flow Diagrams including Heat and Mass Balance
M07 Piping and Instrument Diagrams
M08 Process Sizing Calculations
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 13 of 27
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10)
M09 Exchanger Thermal Rating Calculations
M10 Hydraulic Calculations
M11 Thermal Growth Calculations
M12 Utility Calculations
M13 Flare/Relief System Calculations
M14 Flare Dispersion Calculations
M15 Reliability/Availability Data and Calcula-tions
-- IFR +6W MDR
M16 Lube and Seal Oil System Sizing Calcula-tions
M17 Anti Surge Valve Sizing Calculations
M18 Line List
M19 Equipment Data Sheet including speciality items
IFR +4W MDR/ IOM
M20 Prime Mover Data Sheets (Motor/ Diesel engine/ Gas Engine/ Turbine)
M21 Weight Data Sheet
M22 Noise Level Data Sheets -- IFR +6W MDR
M23 General Arrangement Drawings IFR +4W MDR/ IOM
M24 Detail / Assembly / Fabrication Drawings
M25 Cross Section Drawing / Exploded View Drawings
-- IFR +4W IOM/MDR
M26 Internals Drawings / Miscellaneous Draw-ings
-- IFR +4W IOM/MDR
M27 Mechanical Seal Drawings
M28 Shaft Alignment Drawings
M29 Bill of Material IFR +8W MDR/ IOM
M30 Centre of Gravity Sketch
M31 Installation & Dismantling Drawings / Procedures (As Applicable)
-- IFR +8W MDR/IOM
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 14 of 27
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10)
M32 Lifting / transportation Drawings
M33 Name Plate Drawings -- IFR +8W MDR/ IOM
M34 HVAC Schematic and Flow Diagrams
M35 Skid/Module GA and Detail Drawings
M36 Lifting Lug Details / Calculations
M37 Allowable Nozzle Load Calculations
M38 Weight and Centre of Gravity Calculations -- IFR +4W IOM/MDR
M39 Lifting Equipment Calculations
M40 Lateral Critical Speed Calculations
M41 Torsional Critical Speed Calculations
M42 Bearing Life Calculations
M43 Thrust Bearing sizing Calculations
M44 Pulsation Dampener Design Calculations
M45 Rotor/Shaft system Unbalanced Response Analysis
M46 Coupling Selection Calculations
M47 Dynamic Characteristics: Lateral & Tor-sional Analysis
M48 Foundation Load Calculations
M49 HVAC Calculations
M50 Vibration Calculations
M51 Miscellaneous Calculations
M52 Skid Piping GA Drawings
M53 Pipe Work Support Details
M54 Valve List
M55 Piping Isometrics
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 15 of 27
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10)
M56 Non-Actuated Valve Torque Calculations
M57 Tie-in Schedule
M58 Pulsation Analysis
M59 Relief Valves Calculations and Sizing
M60 Lifting Lug / Trunnion Calculations
M61 Structural Skid / Support Calculations
M62 Tank Tress Calculation
3 Instrument/Electrical
J01 Package Electrical Termination Drawings -- IFR +6W MDR
J02 Panel Layout and Details -- IFR +6W IOM/MDR
J03 Panel Wiring Diagrams
J04 Instrument / Fire and Gas Location Plans / Cable Layouts
J05 Instrument / Fire and Gas Installation De-tails / Hook-ups
J06 Loop Diagrams
J07 Cause & Effect Charts
J08 Alarm / Trip Set Point List
J09 Electrical Wiring Diagrams -- IFR +6W MDR
J10 Electrical Schematic Diagrams -- IFR +6W MDR
J11 Electrical Single Line Diagrams -- IFR +6W IOM/MDR
J12 Sequence and Logic Diagrams, Cause and Effect Diagrams
-- IFR +8W MDR
J13 Instrument/Electrical [ISA] Data Sheets IFR +6W MDR/ IOM
J14 Instrument schematics and control diagram -- IFR +8W MDR
J15 Functional Design Specifications -- IFR +8W MDR
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 16 of 27
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10)
J16 Cable block diagram, SR Data link Ad-dress & Screen Graphics
-- IFR +6W MDR
J17 Instrument Calculations including Safety Valves, Control Valves, FE's, RO's, etc.
J18 Instrument Index
J19 I/O Schedules -- IFR +6W MDR
J20 VDU Screen Display Graphics
J21 Control and Shutdown Philosophy
J22 Cable Schedule -- IFR +6W MDR
J23 Junction Box - Specification and Drawings
J24 Electronic Cable detail
J25 Panel Test Procedure -- IFR +6W MDR
J26 Type Test Procedure -- IFR +6W MDR
J27 Tie-in Schedule
J28 Protection relay coordination & setting study report
-- IFR +6W MDR
4 General
G01 Descriptive Literature and Catalogue In-formation
Info +4W MDR
G02 Sub Vendor Data Sheets / Manuals Info +6W MDR
G03 Recommended Spare Parts For 2 Year Operation, Priced
Info +4W IOM
G04 Recommended Spare parts for Start-up & Commissioning, Priced
IFR +4W IOM
G05 List of Special Tools, where applicable Info +4W IOM
G06 Utility Requirements Power / Air / Water / Other
G07 Consumables list including lubrication
G08 Loading, Transport and Unloading Details
G09 Preservation and Storage Procedure -- IFR -2W BD MDR/ IOM
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 17 of 27
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10)
G10 Hazardous Area Dossier
G11 Hardware Standard Software Documenta-tion
G12 Material Safety Data Sheet
G13 Packing List -- IFR -1W BD MDR/ IOM
G14 All Approved "As-Built" - Drawings and Data Sheets
-- Info -3W BD MDR/ IOM
G15 Preparation for Shipment Procedure
5 Performance
P01 Performance and Test Procedure -- IFR +8W IOM
P02 Performance Curves and Data (Pump, Compressor, Gas Turbine, Motor, Engine, Fan, Vessel Internals, etc)
P03 Trial Assembly Report
P04 Performance Test Reports
P05 Noise Reports -- Info +2W AT IOM
P06 FAT Reports -- Info +2W AT IOM
P07 Commissioning and Site Acceptance Test Results
-- Info +2W AT IOM
P08 Vibration Reports -- Info +2W AT IOM
P09 Acoustic Analysis
P10 Crane Failure Mode Analysis
P11 Heat Emission Calculations
P12 Battery Charge/Discharge Curves -- IFR +6W MDR
P13 Electrical Relay Characteristics
P14 Pulsation Study -- IFR +6W MDR / IOM
6 QA/Certification/Reports
Q01 QA Accreditation Certification -- -- -- -- --
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 18 of 27
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10)
Q02 Contract Quality Plan -- -- -- -- --
Q03 Welding Procedures & Qualification Test Reports
-- Info +8W MDR
Q04 Inspection and Test Plan IFR +6W MDR
Q05 Inspection and Test Reports -- IFR +2W AT MDR
Q06 Calibration Procedures & Results
Q07 Hydro Test / Pneumatic Test Procedures
Q08 Hydro Test/ Pneumatic Test Reports
Q09 Material Mill Test Certification -- Info As
Reqd MDR
Q10 Electrical Type Test Certificates -- Info As
Reqd MDR
Q11 Approval of Relevant Authorities
Q12 Statement of Code Compliance
Q13 Hazardous Area Certification -- IFR +8W MDR/ IOM
Q14 Heat Treatment Records, where applicable
Q15 Charpy Impact Tests, where applicable
Q16 Vendor Concession Request
Q17 Surface Preparation for Painting and Inter-nal Coating Procedure
-- IFR +6W MDR
Q18 NDE Procedure & NDE Location Plan
Q19 Manufacturing Procedures including Heat Treatment
Q20 Pre-Commissioning / Commissioning / Site Acceptance Test Procedure
-- IFR +8W MDR/ IOM
Q21 Factory Acceptance Test Procedure -- IFR +8W MDR
Q22 Weighing Procedure
Q23 Post Weld Heat Treatment Procedures
Q24 Non-Conformance Report (NCR) Procedure
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 19 of 27
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10)
Q25 Erection & Installation Procedure
Q26 Weld Location Plans
Q27 Repair Procedures -- IFR +8W MDR
Q28 Weight Certificate (equipment > 50 kg) -- IFR +8W MDR
Q29 Lifting Equipment Certification
Q30 Dimensional Control Report -- IFR +8W MDR
Q31 Welder Performance Qualification Rec-ords/Certificates
Q32 NDE Operator Qualifications & Certifi-cates
Q33 Production Test Results (Including weld-ing)
Q34 NDE Reports
Q35 Material Traceability Records (Location Drawing)
Q36 Certificate of Compliance -- Info -2W BD MDR
Q37 Painting/Insulation Inspection Reports -- IFR +8W MDR
Q38 Inspection Release Certificate
Q39 Photographs/Videos (i.e. Boroscope)
Q40 Weld Overlay/Cladding Procedures, where applicable
Q41 Cleaning and Flushing Procedures
Q42 PMI Procedures and PMI Location Plan
Q43 Pickling and Passivation Procedures
Q44 Tube to Tube sheet Joint Mock-Up Test Procedure
Q45 Tube to Tube sheet Mock-Up Test Results
Q46 Pitting and Crevice Corrosion Resistance Test Procedure (ASTM G48)
Q47 Intergranular Corrosion Test Procedure
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 20 of 27
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10) (ASTM 262)
Q48 Coupon Test Procedure
Q49 Continuity Test Procedure and Results required for all internal Coatings
Q50 Weld Repair Report(if applicable)
Q51 P.M.I Test Certificate for WO Cladding
Q52 Hardness Test Procedure
Q53 Hardness Test Certificate
Q54 Impact Test Record Q55 NPSH / Acceleration head Test Procedure
Q56 NPSH / Acceleration head Test Report
Q57 Ingress protection rating certificates -- IFR +8W MDR Q58 Electrical short circuit test record -- IFR +8W MDR Q59 Electrical equipment heat run test record -- IFR +8W MDR Q60 Inpulse voltage test record -- IFR +8W MDR
7 Manuals & Indices
R01 Installation Operation and Maintenance Manual (IOM)
-- -- -- -- IOM
R02 Manufacturers Data Report (MDR) -- -- -- -- MDR
R03 Training Manuals (Operation and Mainte-nance)
-- -- -- -- IOM
R04 Installation Operation and Maintenance Manual (IOM) Index
-- IFR +8W IOM
R05 Manufacturers Data Report (MDR) Index -- IFR +8W MDR
8 Miscellaneous
TBA TBA -- -- -- -- -- --
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 21 of 27
VDRL Code
(1) Data/Document Description
With Bid After Purchase Order
Final Issue
(9) (11)
Tick (1P+E)
(5)
Tick (3P+E)
(6)
Purpose (IFR / Info) (7)
Issue date (8)
IFR Tick
(1P+E) (6)
IOM/
MDR (1P+1CD)
(10)
NOTES: (1) * = Priority documents subject to penalization in term of payment. (2) All documents shall be in English language. (3) All documents returned to Vendor with comments shall be re-issued after implementing
comments. (4) Vendor Quality Assurance: The Vendor shall submit (a) ISO 9001-2000 Official Certifi-
cation (b) Quality Manual (c) Project Quality Plan. (5) 3 prints of documents along with electronic file shall be submitted where tick marked
With Bid. (6) P = Print, E = Electronic file, CD = CD ROM. After Purchase Order, 1 prints of docu-
ments shall be submitted where tick marked. Other than prints, documents shall also be delivered electronically.
(7) Purpose; IFR = Issue for review and comments, Info = Issue for information. (8) Issue Date; number of D = Days / W = Weeks / M = Months after purchase order effec-
tive date (unless otherwise specified) (9) Final Issue; Document without comments (10) P = Print, CD = CD ROM. 1prints + 1CDs of IOM/MDR shall be submitted. (11) Native files of all calculations and drawings shall also be submitted. (12) MDR: Data/Documents due 2 weeks after delivery. (13) IOM: Data/Documents due 4 weeks before delivery. (14) Definitions:
IOM - Installation and Operation Manual MDR - Manufacturers Data Report NDE Non Destructive Examination VDS Vendor Data Schedule BD Before Delivery BT Before Test AT After Test
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 22 of 27
7.0 TYPICAL INSPECTION AND TEST PLAN
SI. No. Activities
Gov-erning
QA/QC Proce-dure
Ac-ceptance/ Rejection Criteria
Inspecting Parties
Ven-dor
Company / Purchaser
Third Party
1 Pre-Inspection Meeting 2 Documents:
Specifications / Data
Sheets
Drawings (comment-
ed copies and status of follow-up actions)
Technical Queries /
Concession Requests (approved)
QC System Manual
Inspection and Test
Plan (ITP)
Welding Procedure Specifications (WPS) & Procedure Qualifi-cation Record (PQR)
Welder Qualification
record
Welding repair pro-
cedures
NDE procedures
NDE personnel quali-
fication records
Cladding procedure
(where applicable).
Material test reports/
certificates
3 Material verification
4 Positive Material Identifi-cation
5 Components /Parts In-spection (Visual, Dimen-sions)
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 23 of 27
SI. No. Activities
Gov-erning
QA/QC Proce-dure
Ac-ceptance/ Rejection Criteria
Inspecting Parties
Ven-dor
Company / Purchaser
Third Party
Pumps Instrumentation Electrical Panel Supports External attachments
6 Fabrication/ Assembly Inspection
7 Preliminary dimensional & orientation check
8 Welding Inspection
Welding material ver-
ification
Fit-Up/Joint prepara-
tion
Visual & Dimension-
al element
Cladding (where ap-
plicable)
Production Test
Piece & Testing
NDE & Other exami-
nation (prior to heat treatment)
NDE activities
(RT/UT/MPI/DPI)
Hardness test Impact test
NDE & Other exami-
nation (after heat treatment)
Post Weld Heat
Treatment (PWHT) (where applicable)
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 24 of 27
SI. No. Activities
Gov-erning
QA/QC Proce-dure
Ac-ceptance/ Rejection Criteria
Inspecting Parties
Ven-dor
Company / Purchaser
Third Party
PWHT procedure PWHT
9 Final Dimensions & Ori-entation Check
10 Testing: Test procedures Hydrostatic test Pneumatic test
High pressure N2/
Helium tests (where applicable)
Performance test Control panel test
Test Reports /Test
Certificates
11 Cleaning/Pickling Inspec-tion
12 Cleaning Internal (etc)
13 Surface Preparation & Painting
Coating Procedure
Surface Prepara-tion/Primer Coat (thickness) visual, etc)
Intermediate Coats
(thickness, visual, etc)
Topcoat (thickness, visual, adhesion, hol-iday detection, finish colour)
14 Nameplate / Code Stamp-ing
15 Final Inspection 16 Certificate of Compliance
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 25 of 27
SI. No. Activities
Gov-erning
QA/QC Proce-dure
Ac-ceptance/ Rejection Criteria
Inspecting Parties
Ven-dor
Company / Purchaser
Third Party
17 Spare parts 18 Data skid
19 Preparation for shipment
Preservation Shipped loose items
Two year operation
spares
Commissioning and
start-up spares
20 Release for shipment
21 Site welding repair (where applicable)
W - Witness: Witnessing is mandatory. Intimation should be sent to all relevant party at least 2 weeks before due date. O - Observe: relevant inspector will be informed of time and location of testing at least 15 days advance. However work may proceed without the presence of inspector at the inspector's discretion. R - Check of certificates and/or documents with approved procedures, specifications and ac-ceptance criteria. C - Check has been performed and certificate issued O - Documentation only.
-
TECHNICAL REQUISITION FOR NAVIGATION AID BDP-WHP-TR-E-0005 Effective Date: 10/03 /2014
Revision : D1 Page 26 of 27
ATTACHMENT 1: TEST AND INSPECTION GENERAL REQUIREMENTS
1 VENDOR shall refer to Appendix H3 to Exhibit H to comply the Inspection Mini-
mum Requirements. The inspection and test shall be performed in accordance with the Applicable Documents listed in this Requisition
2 The VENDOR shall submit inspection procedures and Inspection and Test Plan show-ing the details, timing and acceptance criteria of inspection and test to PURCHASER for approval prior to any testing or inspection.
3 PURCHASER, COMPANY and/or third party reserve the right to witness or audit the
VENDORs quality control at VENDORs facilities when necessary.
4 At each witness inspection and test, the VENDOR shall submit to the PURCHASER and/or third partys inspector the inspection and test record/certificate for both wit-nessed and non-witnessed at his visit.
5 The VENDOR shall provide all test equipment and facilities required for the witness in-
spection and test at his cost.
6 The VENDOR shall furnish the suitable number of assistants to execute the inspection and/or test at his cost.
7 VENDOR shall submit the final Test Report confirming that the Equipment/Materials
are inspected and tested in accordance with and meet the relevant Requisition and Ap-plicable Documents.
8 PURCHASERs witnessed inspections and document reviews do not relieve the
VENDOR of his responsibility for the final quality.
9 Shop witness shall be carried out in accordance with the documents approved by PURCHASER.
10 The attached table summarizes the planned inspection and test items to be conducted by
PURCHASER, OWNER and/or Third Party.
-
TECHNICAL REQUISITION FOR LOW VOLTAGE SWITCHGEAR Effective Date:10 /03 /2014
Revision : D1 Page 27 of 27
ATTACHMENT 2: DEVIATION / ALTERNATIVE / CLARIFICATION LIST
DEVIATION / ALTERNATIVE / CLARIFICATION LIST
Requisition No. : Equipment No. : VENDOR Name:
Referenced Specification No. Project Requirement Mark* Deviation / Alternate / Clarification PURCHASER's Disposition Mark * A = Alternative, D = Deviation, C = Clarification
-
TECHNICAL REQUISITION FOR LOW VOLTAGE SWITCHGEAR Effective Date:10 /03 /2014
Revision : D1 Page 28 of 27
ATTACHMENT 3: SPARE PARTS LIST AND INTERCHANGEABILITY RECORD