pak: punjab irrigation agriculture investment project new ......acquisition act 1894 for additional...

28
Social Monitoring Report November 2016 PAK: Punjab Irrigation Agriculture Investment Project New Khanki Barrage Project Loan 2841 Internal Resettlement Monitoring Report Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department, Punjab for the Asian Development Bank (ADB). The social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Upload: others

Post on 27-Mar-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Social Monitoring Report

November 2016

PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841

Internal Resettlement Monitoring Report

Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department,

Punjab for the Asian Development Bank (ADB).

The social monitoring report is a document of the borrower. The views expressed herein do not

necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Page 2: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

GOVERNMENT OF THE PUNJAB

IRRIGATION DEPARTMENT

New Khanki Barrage Project (NKBP)

ADB Loan No. 2841-PAK

Internal Resettlement Monitoring Report

For

Quarter July-September 2016

PROJECT MANAGEMENT OFFICE (PMO) FOR PUNJAB BARRAGES

IRRIGATION DEPARTMENT CANAL BANK MUSTAFABAD,

LAHORE

Page 3: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

New Khanki Barrage Project (NKBP)

Internal Resettlement Monitoring Report for the Quarter July - September 2016

1. LAND ACQUISITION AND RESETTLEMENT PLAN (LARP)

The project is category B for i volu tary resettle e t a d category C for i dige ous people. Draft Land Acquisition and Resettlement Plan (LARP) for New Khanki Barrage was

prepared and submitted to ADB for approval. ADB cleared the draft LARP on July 07, 2012. LARP

was revised/ updated and cleared by ADB in Feb 2014. Land Acquisition is in progress according

to requirement of Land Acquisition Act 1894. A total of 8.6 acres of land was required for

construction of Head Regulator and Head Reach of the new LCC. Section 4 and section 5 of Land

Acquisition Act for 8.6 acres of land were notified and published in the Punjab Gazette on

August 07, 2012 and January 21, 2013 respectively. Land price was assessed, and the EA

released the total amount Rs. 9.925 million to the Revenue Department, Government of the

Punjab.

However, due to change in engineering design it was found that only 4.58 acres out of 8.6 acres

of land was required along with a new piece of land 1 acre, 6 kanal, 3 marlas, and 4.5 Sarsai.

Due to this change, process of land acquisition was re-initiated. The section 4 & 5 of land

Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on

July 11, 2014 and July 29, 2015 respectively.

Again due to change in engineering design of LCC Lead Channel, the procedure for acquiring 5

kanal, 10 Marla of private land from one landowner (Mr. Farooq Akbar Cheema) is still in

process. Compensation rates have been re-calculated to reflect current values and procedures.

The landowner has received full payment for crop losses, trees and structures.

The five affected families which were residing at the Dera of land owner, now they have been

shifted in their new accommodation built by the landowner on his remaining land. Their

livelihoods remain unaffected. These households have received their relocation allowance (Pak

Rupees 5,000/household) and cash assistance for vulnerable households (Pak Rupees72, 000/-

household). Alternative accommodation for the 15 no. of the affected families of Irrigation staff

is also being constructed and all AFs have been shifted in new buildings. Compensation

payment for 6.625 acres land will be paid by October 2016.

Page 4: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

LARP implementation activities for Tranche-2 relates to LCC Lead Channel (component) of New

Khanki Barrage Project. Internal Resettlement Monitoring of all relevant activities is the

responsibility of PMO (Environment and Social Unit (ESU). Internal Monitoring Reports in the

shape of QPR are being regularly submitted to the Bank.

ESU / PMO for Punjab Barrages in busy in Implementation of LARP since 2012.

The Implementation Schedule of LARP is given below:

Sr.

No. Action Time Line Responsibility To date Status

1 Establishment of PMO - PID PMO is already in place at

Lahore.

2 Setting-up the ESU. In place PMO ESU is already in place.

3 Setting-up the LIU at Khanki 30 June, 2012 PMO Notified

4 Establish Grievance Redress Cell. 30 Sep, 2012 PMO Notified.

5 Submission of draft LARP to ADB 30 June, 2012 PMO Submitted

6 Approval of LARP 15 June, 2012 ADB Cleared

7 Urdu translation and disclosure of

LARP 05 July, 2012 PD/ ESU

Also paste at website

8 Formation of DPs Consultation

Committees (2 Nos.) 30 Jun 2012 LIU Formed and notified.

9 Deployment of Supervisory

Consultants 30 Sep. 2012 PMO Deployed

10 Deployment of Social & Environment 31 Dec 2012 PMO Deployed

11 Employment to DPs/ locals (age of

economic group)

June 2013 to

March 2017

Contractor/

Consultants/PMO

A list of willing and

potential DPs/ locals is

included in LARP. Also

given to DESCON

(Contractor) for action.

12 IMR submission before handing over

Barrage site for construction 31 Oct, 2012 PMO Done

13 NTP for Barrage - ADB Done

Page 5: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

14 Construction of Link LCC 30 Jun. 2016 Contractor/ PMO To be completed up to

October, 2016.

Land Acquisition

15 Section-4 Notification Dec. 2015 LAC

Due to new / revised

drawing of LCC the

Section-4 of additional

land was published in

Punjab Gazette on

February 03, 2016.

16 Section-5 Notification January-2016 LAC

Due to new / revised

drawing of LCC the

Section-5 of additional

land was published in

Punjab Gazette on April

15, 2016.

17 De-notification of excessive land

under Section-4 & 5 LAC

As per requirement

under LAC De-notification

of excessive land (35

Kanal, 13 Marla and 3.5

Sarsai) under Section-4

has been published in

Punjab Gazette on June

20,2016 and De-

notification under

Section-5 has been

published in Punjab

Gazette on August 10,

2016.

18 Land Acquisition Process through

Private Negotiation -- -- Not Applicable

19 LARP Updation Oct. 2015 Consultant

Discussed with ADB

representatives on

October 07, 201 and

approved on November

2015..

20 Payment to DPs July 2015 Land owner/ PMO

100% payment has

released to land owner,

laborers are shifted in

alternate location at

nearby place.

Page 6: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

21 Relocation of Farming labourers Dec., 2015 Land owner/Agri.

Labourers PMO

Relocated in their newly

build houses by the

landowner.

22

Final payment to land owner after

confirmation by IM that labourers

have been relocated and paid as in

LARP.

May 2016 PMO -

23 Possession/ Transfer of Land October 2016 LAC/ PMO Section 5-A and Section-6

is in progress.

24 Relocation/ Construction of Staff

Colony Dec. 2015 PMO Completed

25 Relocation/ shifting of PID staff Dec. 2015 Residents/ PMO

All PID staff has been

shifted in their new

houses.

26 Construction of Community Lined

Watercourses 30 Jun 2016 Contractor/ PMO NA

27 Construction of Lined Public

Watercourse 30 Jun 2016 Contractor/ PMO -

28 Construction of High Level Channel 30 June 2016 Contractor/ PMO -

29 Date of contract award (expected) 30 Sept.,

2012 PMO -

30 Full Implementation of LARP Dec. 2016 PMO -

31 IMR confirming LARP implementation Dec. 2016 IM Specialist/

PMO -

32 Commencement of civil works

Subject to

ADB approval

for NTP.

ADB

Subject to ADB approval

on the satisfactory

implementation of LARP.

32 Redress of Community Complaints Continuous

activity GRC/ PMO

Ongoing activity till

project completion.

Total amount under LARP is Rs. 18.05 Million. Out of which, Rs. 9.925 Million has already been

paid to the Revenue Department for land Acquisition. Rupees 4.175 million have been paid to

the 21 no. of affected families as compensation amount for their structures, crop

Page 7: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

compensation, Tubewell, hand pumps and trees. The vulnerability allowance & shifting

allowance has also been paid to the PAPs. The detail is given in Annex-A.

2. ADJUSTMENT MADE IN THE COMPENSATION RATE DURING UPDATING OF LARP

The LARP of New Khanki Barrage was approved in 2012. Again, it was updated and approved in 2014.

The adjustment was made in compensation rates of the land after certification by the Revenue

Department, Government of Punjab.

The rates are still applicable up till now. The adjustment made in the compensation is given in

Annex-B.

3. EMPLOYMENT FOR THE AFFECTED HOUSEHOLDS IN PROJECT RELATED JOBS

Two types of affected families are residing at LCC Lead Channel. First are Irrigation Department

Employees and they are already serving in Irrigation Department. Second are the land owner and his

agriculture laborers, those are cultivating crops. They have been shifted in newly built houses. The

Contractor is ready to accommodate the affected families for jobs as and when they demand. ESU, PMO

Punjab Barrages requested to the Consultants to ask the Contractor to provide jobs under the project.

As per recommendation of the Engineer, the Contractor trace each of the person included in the list, the

list of the potential persons of affected families requiring jobs under the project. The Contractor offered

them an appropriate employment. Out of 16 affected persons, only 3 residents of Irrigation Colony were

willing for jobs with the Contractor and the Contractor hired their services. The contractor also offered

jobs to the family members of the employees of Irrigation Department of Khanki Division. Out of 26

applications, 20 family members of Irrigation staff were offered jobs and the contractor hired their

services under the project. Regarding employment to the unskilled labor of the local area, the status of

skilled and un-skilled labor employment for the month of April-June 2016 is given in Annex C. The

percentage of skilled and un-skilled labor remained 60%, 60% and 58% respectively.

4. RELOCATION OF AFFECTED HOUSEHOLDS AND THEIR CURRENT LIVING CONDITION

Total Twenty One (21) affected families (AFs) were to be dislocated from LCC Lead Channel component

of New Khanki Barrage Project. In first phase, land owner and his five (05) Agri-laborers are relocated

and an amount of Pak Rupees 3.927 million has been paid to the six (06) no. of affected families as the

Page 8: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

compensation amount for their structure and other assets Shifting allowance to all PID affected staff has

been paid. All affected families of Irrigation Department Employees families have been shifted to the

newly constructed residences.

The owner of the land has built the new dera along with the residences for the laborers. 05 No.

of Agri. Laborers have been shifted in their new residences. The pictorial view of before and

after comparison of residences is available in this report.

5. PID OWNED PUBLIC INFRASTRUCTURE

Punjab Irrigation Department owned a non-perennial irrigation channel named High Level

Channel has to be relocated in this project that was supplying canal water to the village Khanki,

Kot Imam Bukhsh and Faqiranwali. Pr.

ior to give supply in the channel a temporary bridge and outlet was arranged to the cultivators

for their smooth agricultural practices. The snaps of bridge, outlet and water course are as

under:

A view of temporary bridge and outlet at RD: 2066-R of High Level Channel.

Page 9: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

A view of lined community watercourse at RD: 2066-R.

Community watercourse was dismantled during the construction work of new High Level

Channel, due to this issue the concerned farmer were facing a lot of difficulty. On the request of

the affected farmers the unlined water course was restored in the above mentioned quarter.

A view of restored community unlined water course.

Page 10: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No.1

Mr. Farooq Akbar Cheema is the only land owner fall in category of affected household. His land, trees

and residential structures were affected due to NKBP. A compensation payment of amounting Pak Rs.

1,570,362 was given for crops, tube well, hand pump and structures. Current status of land and

structure can be viewed as under:

Mr. Farooq Akbar Cheema (Land owner) is standing on his land and structures in the back ground.

Case No.2

Mr. Muhammad Anwar the farm laborer of Mr. Farooq Akbar Cheema. He was shifted to the new

constructed house by the land owner. He has collected an amount of Rs. 77,000/- as compensation

/poverty allowance and relocation allowance.

Page 11: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No.3

Mr. Amanat Ali is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted in newly

constructed house by the land owner. He has collected an amount of Rs. 77,000/- as compensation

/poverty allowance and relocation allowance.

Case No.4

Mr. Manzoor Hussain is the farm laborer of the Mr. Farooq Akbar Cheema. He built the residential

structure in the land of land owner. He has been shifted in newly constructed house and paid an amount

of Rs. 986,100/- as compensation for structure, 1 no. hand pump, poverty allowance and relocation

allowance.

Page 12: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No.5

Mr. Anayat Muhammad is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted in the

newly constructed house by the land owner. He has collected an amount of Rs. 77,000/- as

compensation /poverty allowance and relocation allowance.

Case No.6

Mr. Muhammad Ramzan is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted to the

newly constructed house by the land owner. He has collected an amount of Rs. 77,000/- as

compensation /poverty allowance and relocation allowance.

Page 13: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

SHIFTING OF IRRIGATION STAFF

The 14 No. of Irrigation Department employees have been shifted to their new residences constructed

under New Khanki Barrage Project. The remaining 1 No. of Irrigation employee shall be shifted to his

new residences in the month of August 2016.

COMPARISON OF RESIDENCES OF IRRIGATION STAFF CAN BE VIEWED AS UNDER:

Case No. 7. Mr. Abdul Hameed (Guage Reader) with his family at current residence.

Case No.8. Mr. Muhammad Mansha (Beldar) with his family at his current residence.

Page 14: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No. 9. Mr. Ghulam Abbas (Chowkidar) with family at his current residence.

Case No. 10. Mr. Faisal Mehmood (Naib Qasid) at his current residence.

Page 15: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No. 11. Mr. Muhammad Akram (Regulation Beldar) with family at his current residence.

Case No. 12. Mr. Muhammad Riaz (Boatman) with family at his current residence.

Page 16: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No.13. Mr. Liaqat Ali (Regulation Beldar) with family at his current residence.

Case No. 14. Mr. Walayat Hussain (Head Boatman) with family at his current residence.

Page 17: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No. 15. Mr. Muhammad Shabbir (Beldar) standing in front of his current residence

Case No.16

Mr. Muhammad Mushtaq (Beldar) is living in Government residence that needs to be relocated at the

earliest. Under NKBP new residence is near completion. He will be relocated to new allocated building

and get relocation allowance of Rs. 5,000/-

Case No. 16. Mr. Muhammad Mushtaq(Beldar) standing in front of his current residence

Page 18: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No. 17. Mr. Ashraf Masih(Sweeper), standing in front of his current residence.

Case No. 18. Amanat Ali (Painter) standing in front of his current residence.

Page 19: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No. 19. Sibt Ul Hassan (Sub Engineer) standing in front of his current residence.

Case No. 20. Rana Ayub (Sub Engineer) standing in front of his current residence

Page 20: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Case No. 21. Muhammad Shabir (Sub Engineer) standing in front of his current residence

5. GRIEVENCE REDRESSAL MECHANISM

Tranche-2 also has an operational Grievance Redressal Mechanism that covers all types of

grievances of NKBP, including resettlement. Complaint register is also being maintained by the

Consultants to record community concerns and their solutions. Out of 38 complaints, 30

complaints have been resolved while 8 complaints are yet to be resolved. The detail of

complaints is given in Annex D.

Page 21: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Annex –A

Implementation of LARP for New Khanki Barrage as of September 2016

Contract No. 2841-PAK

Sr.

No

Contract

No.

Status of

Preparatio

n, vetting

and

approval of

RP

No.

of

AFs

Payment

Due (PKR

in

million)

Total

AFs

paid

Amount

Paid (PKR

in million

%

Implement

ation

%

Amount

Paid Remarks

1 2841-PAK

LARP for

LCC Lead

Channel

Component

(under

NKBP)

Draft LARP

of LCC Lead

Channel

was

prepared

and

approved

in 2012.

Later on

LARP was

revised,

updated

and cleared

by ADB in

Feb, 2014

21 13.446 21 4.175 95% 31.05 Cost of 6.625

@ 1,200,000

is amounting

to Rs.

7,950,000

while PMO

has

deposited Rs.

9.925

(million) to

the Revenue

Department

for payment

to the land

owner. The

payment will

be paid in

October

2016.

Page 22: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Adjustment made in Compensation Rates in LARP July, 2014 Annex - B

Sr. No.

Description Unit Unit Rate of LARP 2012

Unit Rate of updated LARP 2014

Remarks

A) Mouza -Wise Acquisition of Private Land

I) Khanki Acres 0.474(Rs.Million) 1.2( Rs. Million)

The rates of

2012 were not applicable in

2014 so, after Consultation with

Revenue and Agriculture

Department, rate for land and crop

compensation were updated, while rates for structures and,

other i.e. Tree

compensation and livelihood assistance are

still applicable in 2015-16.

Therefore, there is no much changes

recognized for D, E, F and G up till

now.

B) Land Acquisition Compulsory Surcharge (15%)

- - -

C) Crop Compensation

Rabi Acres 32,236 42,000

Kharif Acres 54,373 82,000

D) Residential Structures (Houses)

Sq. ft. Rs.675/sqft Rs.675/sqft

- i) Pacca structure Sq. ft. - - - ii) Semi-Pacca structures - Sq. ft. - - - iii) Katcha/ thatched shed - Sq. ft. - -

E) Others - - - i) Cattle Yard Sq. ft. Rs.675/sqft Rs.675/sqft

ii) Borehole of a tube well / drilling

No 148000/ bore 148000/ bore

iii) Hand pump No 0.01 0.01

Cost of W/C 1 community ,Private

Meters 1445/m 1445/m

F) Tree Compensation

Fruit Trees

No 4208.33 4208.33

Timber wood trees

No 1663.16 1663.16

G) Livelihood Assistance - -

- Livelihood assistance to vulnerable families

- - -

a) impassion cash assistance /allowance equivalent to 6 months OPL adjustment amount , i.e.(Rs. 12000)

DFs 0.072 0.072

b) Relocation assistance Rs. 5000/- to be paid all the DPs requiring to move out of the ROW or Land acquired for the Project

DFs 0.005 0.005

Page 23: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

UP-DATED STATUS OF SKILLED & UNSKILLED LABOUR AT NKBP ANNEX-C

DESCON Engineering Limited

New Khanki Barrage Project (NKBP)

District Wise Skilled / Unskilled Labour for the Month of JULY-2016

Sr #

Districts

DESCON

Total

Sub Contractor TOTAL

TOTAL Skilled

Un-skilled

Skilled Un-

skilled Skilled

Un-skilled

1 GUJRANWALA 52 31 83 24 14 76 45 121

2 HAFIZABAD 32 4 36 18 6 50 10 60

3 CHINIOT 8 16 24 8 16 24

4 SHEIKHUPURA 10 6 16 10 6 16

5 NANKANA 14 2 16 14 2 16

6 FAISALABAD 47 6 53 47 6 53

7 JHANG 25 15 40 25 15 40

8 TOBA TEK SINGH

12 4 16 12 4 16

9 Gujrat (Barrage adjoining villages)

112 32 144 24 2 136 34 170

Total 312 116 428 66 22 378

138 516

%age 61.66% 58.59%

60.80%

72.53% 64.71% 63% 59% 62%

10 Other Districts 194 82 276 25 12 219 94 313

Total Districts 506 198 704 91 34 597 232 829

59% Unskilled labour was used during the month of JULY-2016

Page 24: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

UP-DATED STATUS OF SKILLED & UNSKILLED LABOUR AT NKBP ANNEX-C

DESCON Engineering Limited

New Khanki Barrage Project (NKBP)

District Wise Skilled / Unskilled Labour for the Month of August-2016

Sr # Districts

DESCON

Total

Sub Contractor TOTAL

TOTA

L Skilled

Un-skille

d

Skilled

Un-skille

d Skilled

Un-skille

d

1 GUJRANWALA 52 36 88 24 14 76 50 126

2 HAFIZABAD 33 4 37 18 6 51 10 61

3 CHINIOT 8 16 24 8 16 24

4 SHEIKHUPURA 10 6 16 10 6 16

5 NANKANA 12 2 14 12 2 14

6 FAISALABAD 58 6 64 58 6 64

7 JHANG 26 13 39 26 13 39

8 TOBA TEK SINGH

16 3 19 16 3 19

9 Gujrat (Barrage adjoining villages)

98 26 124 34 2 132 28 160

Total 313 112 425 76 22

389

134 523

%age

68.94%

56.57%

65.18%

67.86%

64.71%

69% 58% 66%

10 Other Districts 141 86 227 36 12 177 98 275

Total Districts 454 198 652 112 34 566 232 798

58% Unskilled labour was used during the month of August-2016

Page 25: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

UPDATED STATUS OF SKILLED & UNSKILLED LABOUR AT NKBP ANNEX-C DESCON Engineering Limited

New Khanki Barrage Project (NKBP)

District Wise Skilled / Unskilled Labour for the Month of September-2016

Sr # Districts

DESCON

Total

Sub Contractor TOTAL

TOTAL Skilled

Un-skilled

Skilled Un-

skilled Skilled

Un-skille

d

1 GUJRANWALA 52 36 88 24 14 76 50 126

2 HAFIZABAD 33 14 47 18 6 51 20 71

3 CHINIOT 19 16 35 19 16 35

4 SHEIKHUPURA 10 14 24 10 14 24

5 NANKANA 16 7 23 16 7 23

6 FAISALABAD 58 12 70 58 12 70

7 JHANG 29 13 42 29 13 42

8 TOBA TEK SINGH

18 7 25 18 7 25

9 Gujrat (Barrage adjoining villages)

98 26 124 38 2 136 28 164

Total 333 145 478 80 22

413

167 580

%age 70.25% 62.77%

67.80%

65.57% 64.71% 69% 63% 67%

10 Other Districts 141 86 227 42 12 183 98 281

Total Districts 474 231 705 122 34 596 265 861

63% Unskilled labour was used during the month of September-2016

Page 26: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

Complaint Register of New Khanki Barrage Project Annex-D

Sr# Name of complainant

Date Contact Number

Issue /Location Status of

Complaint Date of

Completion Remarks

1 Imtiaz Ahmed 10/2/2014 3237476606 Demand for Culverts at Chanawan Road

Solved 17/2/2015

2 Zubair Ahmad

1/1/2015 3026262531 Demand for Culverts/186+36 and 192+32 /Chanawan Road

Solved 5/1/2015

3 Mansoor Warraich

10/1/2015 3009806351 Demand for Culverts134+71/Chanawan Road

Solved 17/1/2015

4 Khizar Hayat 5/1/2014 3046205578 Demand for Culverts/115+70Chanawan Road

Solved 11/1/2015

5 Naseem Hussain

10/12/2014 3015564233 Demand for Culverts/84+93/Chanawan Road

Solved 16/12/2014

6 Master Shafqat Ali

15/12/2014 3456498530 Demand for Culverts/56+37/Chanawana Road

Solved 22/12/2014

7 Farooq Akbar Cheema

14/10/2014 3216273305 Increase the rate of land /LCC

DCO Office in Process GRW

Section

Vl in

process

8 Dr. Azhar Iqbal Cheema

26/12/2014 3338402054 Small Bridge /Gunayanwala to KotJaffar Road

Completed

9 Rana Muhammad Khan

1/12/2014

Demand for Culverts/19+200/ Chanawan Road 21+150

Completed

10 Dr. Azhar Iqbal Cheema

Repeated App

3338402054 No 8 Applicaton Repeated.

In Process

11 Ghulam Sarwar Cheema

12/4/2015 3036786566 Demand for Culverts/Chanawan Road

Solved 19/04/2015

12 Head Mistress Girls School

21/05/2015

Play Ground/ Khanki In Process

Irrigation

matter

13 Ghulam Rasool

16/5/2015 3456596818 Cemented Ramp & Soling /LMB Road

In Process

Drawing

awaited

14 Farooq Akbar Cheema

21/5/2015 3216273305 Drainage of flood water/Chanawan Road

In Process

In

Process

at RE

Preparat

ory Desk

15 Umer Hayat 14/5/2015 3216273305 Demand for Culverts/Chanawan Road

Completed

16 Hafiz SaifUllah Chatta

8/6/2015 3022786127 Speed Breaker/ Footpath /Chanawan Road

Completed

17 Muhammad Aslam Randhawa

9/6/2015 3066282001 Outlet /Chanawan Road Completed

Page 27: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

18 Haji AmjadPervaiz Randhawa

8/6/2015 3022786127 Repair the old bridge /Chanawan Road

Completed

19 Pervaiz Iqbal Bhatti

7/6/2015 3212332348 Repair the old bridge/Chanawan Road

Completed

20 XEN Irrigation

9/6/2015 3455810002 Boundary wall / Play Ground/Irrigation Colony

Completed

21 Master Nasir Mahmood

6/4/2015 3002786400 Change the location of culvert/Chanawan Road

Solved 13/04/2015

22 Waqas Chatta Advocate

11/4/2015

Court Case /Chanawan Road

Solved 17/04/2015

Withdra

wn by

applicant

23 SDO Headworks

9/7/2015

Breakage of High Level Channel

Solved 11/7/2015

24 Umer Hayat 7/7/2015 3086464171 Hurdle on Chanawan Road

Completed

25 Farooq Akbar Cheema

14/7/2015 3216273305 Drainage of Rain water from crops

Solved 17/7/2015

26 Amanat Ali 22/7/2015

Standing Rain Water in Colony

Solved 23/7/2015

27 SDO Headworks

28/7/2015

Breakage of High Level Channel

Solved 29/7/2015

28 Sibt-E-Hassan

19/11/2015 3006273305 Boundary wall of New Irrigatoin Colony

Completed

29 Hafiz SaifUllah Chatta

10/9/2015 0302-

2786127 Irrigation Water issue Completed

30 Farooq Akbar Cheema

27/11/2015 3216273305 Earthfilling of the Pond Completed

31 Farooq Akbar Cheema

28/11/2015 3216273305 Water level issue of Khanki village

In Process

In

Process

32 Ghulam Rasool

25/1/2016

Demand of paved path In Process

33 Johar Sarwar 1/2/2016 0302-

8488888 Demand of Play Ground In Process

Irrigation

matter

34 Safdar Mumtaz Sandhu

2/2/2016 3009622355 Demand of Mosque & Park

In Process

35 Farooq Akbar Cheema

31/03/2016 3216273305 Demand of culvert In Process

In

process

in PMO

36 Muhammd Hanif

7/4/2016

demand of path from LMB road

Completed

Page 28: PAK: Punjab Irrigation Agriculture Investment Project New ......Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

37 Muhammad Nazim

20/05/2016

Demand of paved path In Process

38 Muhammad Hanif Saleemi

3/6/2016 3216273305 road level and culverts In Process

39 Ch. Akram 19/08/2016 Spur at right side Completed

40 Kram Rasool Culvert at Kot Imam

Buksh Completed

41 Ghulam Rasool

25/08/2016 09/09/2016

0345 6596818

Ramp at Rattowali In Process

drawing awaited

42 Farooq Akbar Cheema

24/09/2016 0321627330

5 Sub base at road Completed

43 Farooq Akbar Cheema

1/10/2016 0321627330

5 Culvert on high level channel

In process

44 Abdul malik 03/10/2016 Kot Imam Buksh Completed

45 XEN GEPCO Wazirabad

06/10/2016 Complaint Office In process

Total Application =45

Action Completed=31

In process 14

Average=69%