pak: punjab irrigation agriculture investment project new ......acquisition act 1894 for additional...
TRANSCRIPT
Social Monitoring Report
November 2016
PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841
Internal Resettlement Monitoring Report
Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department,
Punjab for the Asian Development Bank (ADB).
The social monitoring report is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
GOVERNMENT OF THE PUNJAB
IRRIGATION DEPARTMENT
New Khanki Barrage Project (NKBP)
ADB Loan No. 2841-PAK
Internal Resettlement Monitoring Report
For
Quarter July-September 2016
PROJECT MANAGEMENT OFFICE (PMO) FOR PUNJAB BARRAGES
IRRIGATION DEPARTMENT CANAL BANK MUSTAFABAD,
LAHORE
New Khanki Barrage Project (NKBP)
Internal Resettlement Monitoring Report for the Quarter July - September 2016
1. LAND ACQUISITION AND RESETTLEMENT PLAN (LARP)
The project is category B for i volu tary resettle e t a d category C for i dige ous people. Draft Land Acquisition and Resettlement Plan (LARP) for New Khanki Barrage was
prepared and submitted to ADB for approval. ADB cleared the draft LARP on July 07, 2012. LARP
was revised/ updated and cleared by ADB in Feb 2014. Land Acquisition is in progress according
to requirement of Land Acquisition Act 1894. A total of 8.6 acres of land was required for
construction of Head Regulator and Head Reach of the new LCC. Section 4 and section 5 of Land
Acquisition Act for 8.6 acres of land were notified and published in the Punjab Gazette on
August 07, 2012 and January 21, 2013 respectively. Land price was assessed, and the EA
released the total amount Rs. 9.925 million to the Revenue Department, Government of the
Punjab.
However, due to change in engineering design it was found that only 4.58 acres out of 8.6 acres
of land was required along with a new piece of land 1 acre, 6 kanal, 3 marlas, and 4.5 Sarsai.
Due to this change, process of land acquisition was re-initiated. The section 4 & 5 of land
Acquisition Act 1894 for additional land was notified and published in the Punjab Gazette on
July 11, 2014 and July 29, 2015 respectively.
Again due to change in engineering design of LCC Lead Channel, the procedure for acquiring 5
kanal, 10 Marla of private land from one landowner (Mr. Farooq Akbar Cheema) is still in
process. Compensation rates have been re-calculated to reflect current values and procedures.
The landowner has received full payment for crop losses, trees and structures.
The five affected families which were residing at the Dera of land owner, now they have been
shifted in their new accommodation built by the landowner on his remaining land. Their
livelihoods remain unaffected. These households have received their relocation allowance (Pak
Rupees 5,000/household) and cash assistance for vulnerable households (Pak Rupees72, 000/-
household). Alternative accommodation for the 15 no. of the affected families of Irrigation staff
is also being constructed and all AFs have been shifted in new buildings. Compensation
payment for 6.625 acres land will be paid by October 2016.
LARP implementation activities for Tranche-2 relates to LCC Lead Channel (component) of New
Khanki Barrage Project. Internal Resettlement Monitoring of all relevant activities is the
responsibility of PMO (Environment and Social Unit (ESU). Internal Monitoring Reports in the
shape of QPR are being regularly submitted to the Bank.
ESU / PMO for Punjab Barrages in busy in Implementation of LARP since 2012.
The Implementation Schedule of LARP is given below:
Sr.
No. Action Time Line Responsibility To date Status
1 Establishment of PMO - PID PMO is already in place at
Lahore.
2 Setting-up the ESU. In place PMO ESU is already in place.
3 Setting-up the LIU at Khanki 30 June, 2012 PMO Notified
4 Establish Grievance Redress Cell. 30 Sep, 2012 PMO Notified.
5 Submission of draft LARP to ADB 30 June, 2012 PMO Submitted
6 Approval of LARP 15 June, 2012 ADB Cleared
7 Urdu translation and disclosure of
LARP 05 July, 2012 PD/ ESU
Also paste at website
8 Formation of DPs Consultation
Committees (2 Nos.) 30 Jun 2012 LIU Formed and notified.
9 Deployment of Supervisory
Consultants 30 Sep. 2012 PMO Deployed
10 Deployment of Social & Environment 31 Dec 2012 PMO Deployed
11 Employment to DPs/ locals (age of
economic group)
June 2013 to
March 2017
Contractor/
Consultants/PMO
A list of willing and
potential DPs/ locals is
included in LARP. Also
given to DESCON
(Contractor) for action.
12 IMR submission before handing over
Barrage site for construction 31 Oct, 2012 PMO Done
13 NTP for Barrage - ADB Done
14 Construction of Link LCC 30 Jun. 2016 Contractor/ PMO To be completed up to
October, 2016.
Land Acquisition
15 Section-4 Notification Dec. 2015 LAC
Due to new / revised
drawing of LCC the
Section-4 of additional
land was published in
Punjab Gazette on
February 03, 2016.
16 Section-5 Notification January-2016 LAC
Due to new / revised
drawing of LCC the
Section-5 of additional
land was published in
Punjab Gazette on April
15, 2016.
17 De-notification of excessive land
under Section-4 & 5 LAC
As per requirement
under LAC De-notification
of excessive land (35
Kanal, 13 Marla and 3.5
Sarsai) under Section-4
has been published in
Punjab Gazette on June
20,2016 and De-
notification under
Section-5 has been
published in Punjab
Gazette on August 10,
2016.
18 Land Acquisition Process through
Private Negotiation -- -- Not Applicable
19 LARP Updation Oct. 2015 Consultant
Discussed with ADB
representatives on
October 07, 201 and
approved on November
2015..
20 Payment to DPs July 2015 Land owner/ PMO
100% payment has
released to land owner,
laborers are shifted in
alternate location at
nearby place.
21 Relocation of Farming labourers Dec., 2015 Land owner/Agri.
Labourers PMO
Relocated in their newly
build houses by the
landowner.
22
Final payment to land owner after
confirmation by IM that labourers
have been relocated and paid as in
LARP.
May 2016 PMO -
23 Possession/ Transfer of Land October 2016 LAC/ PMO Section 5-A and Section-6
is in progress.
24 Relocation/ Construction of Staff
Colony Dec. 2015 PMO Completed
25 Relocation/ shifting of PID staff Dec. 2015 Residents/ PMO
All PID staff has been
shifted in their new
houses.
26 Construction of Community Lined
Watercourses 30 Jun 2016 Contractor/ PMO NA
27 Construction of Lined Public
Watercourse 30 Jun 2016 Contractor/ PMO -
28 Construction of High Level Channel 30 June 2016 Contractor/ PMO -
29 Date of contract award (expected) 30 Sept.,
2012 PMO -
30 Full Implementation of LARP Dec. 2016 PMO -
31 IMR confirming LARP implementation Dec. 2016 IM Specialist/
PMO -
32 Commencement of civil works
Subject to
ADB approval
for NTP.
ADB
Subject to ADB approval
on the satisfactory
implementation of LARP.
32 Redress of Community Complaints Continuous
activity GRC/ PMO
Ongoing activity till
project completion.
Total amount under LARP is Rs. 18.05 Million. Out of which, Rs. 9.925 Million has already been
paid to the Revenue Department for land Acquisition. Rupees 4.175 million have been paid to
the 21 no. of affected families as compensation amount for their structures, crop
compensation, Tubewell, hand pumps and trees. The vulnerability allowance & shifting
allowance has also been paid to the PAPs. The detail is given in Annex-A.
2. ADJUSTMENT MADE IN THE COMPENSATION RATE DURING UPDATING OF LARP
The LARP of New Khanki Barrage was approved in 2012. Again, it was updated and approved in 2014.
The adjustment was made in compensation rates of the land after certification by the Revenue
Department, Government of Punjab.
The rates are still applicable up till now. The adjustment made in the compensation is given in
Annex-B.
3. EMPLOYMENT FOR THE AFFECTED HOUSEHOLDS IN PROJECT RELATED JOBS
Two types of affected families are residing at LCC Lead Channel. First are Irrigation Department
Employees and they are already serving in Irrigation Department. Second are the land owner and his
agriculture laborers, those are cultivating crops. They have been shifted in newly built houses. The
Contractor is ready to accommodate the affected families for jobs as and when they demand. ESU, PMO
Punjab Barrages requested to the Consultants to ask the Contractor to provide jobs under the project.
As per recommendation of the Engineer, the Contractor trace each of the person included in the list, the
list of the potential persons of affected families requiring jobs under the project. The Contractor offered
them an appropriate employment. Out of 16 affected persons, only 3 residents of Irrigation Colony were
willing for jobs with the Contractor and the Contractor hired their services. The contractor also offered
jobs to the family members of the employees of Irrigation Department of Khanki Division. Out of 26
applications, 20 family members of Irrigation staff were offered jobs and the contractor hired their
services under the project. Regarding employment to the unskilled labor of the local area, the status of
skilled and un-skilled labor employment for the month of April-June 2016 is given in Annex C. The
percentage of skilled and un-skilled labor remained 60%, 60% and 58% respectively.
4. RELOCATION OF AFFECTED HOUSEHOLDS AND THEIR CURRENT LIVING CONDITION
Total Twenty One (21) affected families (AFs) were to be dislocated from LCC Lead Channel component
of New Khanki Barrage Project. In first phase, land owner and his five (05) Agri-laborers are relocated
and an amount of Pak Rupees 3.927 million has been paid to the six (06) no. of affected families as the
compensation amount for their structure and other assets Shifting allowance to all PID affected staff has
been paid. All affected families of Irrigation Department Employees families have been shifted to the
newly constructed residences.
The owner of the land has built the new dera along with the residences for the laborers. 05 No.
of Agri. Laborers have been shifted in their new residences. The pictorial view of before and
after comparison of residences is available in this report.
5. PID OWNED PUBLIC INFRASTRUCTURE
Punjab Irrigation Department owned a non-perennial irrigation channel named High Level
Channel has to be relocated in this project that was supplying canal water to the village Khanki,
Kot Imam Bukhsh and Faqiranwali. Pr.
ior to give supply in the channel a temporary bridge and outlet was arranged to the cultivators
for their smooth agricultural practices. The snaps of bridge, outlet and water course are as
under:
A view of temporary bridge and outlet at RD: 2066-R of High Level Channel.
A view of lined community watercourse at RD: 2066-R.
Community watercourse was dismantled during the construction work of new High Level
Channel, due to this issue the concerned farmer were facing a lot of difficulty. On the request of
the affected farmers the unlined water course was restored in the above mentioned quarter.
A view of restored community unlined water course.
Case No.1
Mr. Farooq Akbar Cheema is the only land owner fall in category of affected household. His land, trees
and residential structures were affected due to NKBP. A compensation payment of amounting Pak Rs.
1,570,362 was given for crops, tube well, hand pump and structures. Current status of land and
structure can be viewed as under:
Mr. Farooq Akbar Cheema (Land owner) is standing on his land and structures in the back ground.
Case No.2
Mr. Muhammad Anwar the farm laborer of Mr. Farooq Akbar Cheema. He was shifted to the new
constructed house by the land owner. He has collected an amount of Rs. 77,000/- as compensation
/poverty allowance and relocation allowance.
Case No.3
Mr. Amanat Ali is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted in newly
constructed house by the land owner. He has collected an amount of Rs. 77,000/- as compensation
/poverty allowance and relocation allowance.
Case No.4
Mr. Manzoor Hussain is the farm laborer of the Mr. Farooq Akbar Cheema. He built the residential
structure in the land of land owner. He has been shifted in newly constructed house and paid an amount
of Rs. 986,100/- as compensation for structure, 1 no. hand pump, poverty allowance and relocation
allowance.
Case No.5
Mr. Anayat Muhammad is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted in the
newly constructed house by the land owner. He has collected an amount of Rs. 77,000/- as
compensation /poverty allowance and relocation allowance.
Case No.6
Mr. Muhammad Ramzan is the farm laborer of Mr. Farooq Akbar Cheema. He has been shifted to the
newly constructed house by the land owner. He has collected an amount of Rs. 77,000/- as
compensation /poverty allowance and relocation allowance.
SHIFTING OF IRRIGATION STAFF
The 14 No. of Irrigation Department employees have been shifted to their new residences constructed
under New Khanki Barrage Project. The remaining 1 No. of Irrigation employee shall be shifted to his
new residences in the month of August 2016.
COMPARISON OF RESIDENCES OF IRRIGATION STAFF CAN BE VIEWED AS UNDER:
Case No. 7. Mr. Abdul Hameed (Guage Reader) with his family at current residence.
Case No.8. Mr. Muhammad Mansha (Beldar) with his family at his current residence.
Case No. 9. Mr. Ghulam Abbas (Chowkidar) with family at his current residence.
Case No. 10. Mr. Faisal Mehmood (Naib Qasid) at his current residence.
Case No. 11. Mr. Muhammad Akram (Regulation Beldar) with family at his current residence.
Case No. 12. Mr. Muhammad Riaz (Boatman) with family at his current residence.
Case No.13. Mr. Liaqat Ali (Regulation Beldar) with family at his current residence.
Case No. 14. Mr. Walayat Hussain (Head Boatman) with family at his current residence.
Case No. 15. Mr. Muhammad Shabbir (Beldar) standing in front of his current residence
Case No.16
Mr. Muhammad Mushtaq (Beldar) is living in Government residence that needs to be relocated at the
earliest. Under NKBP new residence is near completion. He will be relocated to new allocated building
and get relocation allowance of Rs. 5,000/-
Case No. 16. Mr. Muhammad Mushtaq(Beldar) standing in front of his current residence
Case No. 17. Mr. Ashraf Masih(Sweeper), standing in front of his current residence.
Case No. 18. Amanat Ali (Painter) standing in front of his current residence.
Case No. 19. Sibt Ul Hassan (Sub Engineer) standing in front of his current residence.
Case No. 20. Rana Ayub (Sub Engineer) standing in front of his current residence
Case No. 21. Muhammad Shabir (Sub Engineer) standing in front of his current residence
5. GRIEVENCE REDRESSAL MECHANISM
Tranche-2 also has an operational Grievance Redressal Mechanism that covers all types of
grievances of NKBP, including resettlement. Complaint register is also being maintained by the
Consultants to record community concerns and their solutions. Out of 38 complaints, 30
complaints have been resolved while 8 complaints are yet to be resolved. The detail of
complaints is given in Annex D.
Annex –A
Implementation of LARP for New Khanki Barrage as of September 2016
Contract No. 2841-PAK
Sr.
No
Contract
No.
Status of
Preparatio
n, vetting
and
approval of
RP
No.
of
AFs
Payment
Due (PKR
in
million)
Total
AFs
paid
Amount
Paid (PKR
in million
%
Implement
ation
%
Amount
Paid Remarks
1 2841-PAK
LARP for
LCC Lead
Channel
Component
(under
NKBP)
Draft LARP
of LCC Lead
Channel
was
prepared
and
approved
in 2012.
Later on
LARP was
revised,
updated
and cleared
by ADB in
Feb, 2014
21 13.446 21 4.175 95% 31.05 Cost of 6.625
@ 1,200,000
is amounting
to Rs.
7,950,000
while PMO
has
deposited Rs.
9.925
(million) to
the Revenue
Department
for payment
to the land
owner. The
payment will
be paid in
October
2016.
Adjustment made in Compensation Rates in LARP July, 2014 Annex - B
Sr. No.
Description Unit Unit Rate of LARP 2012
Unit Rate of updated LARP 2014
Remarks
A) Mouza -Wise Acquisition of Private Land
I) Khanki Acres 0.474(Rs.Million) 1.2( Rs. Million)
The rates of
2012 were not applicable in
2014 so, after Consultation with
Revenue and Agriculture
Department, rate for land and crop
compensation were updated, while rates for structures and,
other i.e. Tree
compensation and livelihood assistance are
still applicable in 2015-16.
Therefore, there is no much changes
recognized for D, E, F and G up till
now.
B) Land Acquisition Compulsory Surcharge (15%)
- - -
C) Crop Compensation
Rabi Acres 32,236 42,000
Kharif Acres 54,373 82,000
D) Residential Structures (Houses)
Sq. ft. Rs.675/sqft Rs.675/sqft
- i) Pacca structure Sq. ft. - - - ii) Semi-Pacca structures - Sq. ft. - - - iii) Katcha/ thatched shed - Sq. ft. - -
E) Others - - - i) Cattle Yard Sq. ft. Rs.675/sqft Rs.675/sqft
ii) Borehole of a tube well / drilling
No 148000/ bore 148000/ bore
iii) Hand pump No 0.01 0.01
Cost of W/C 1 community ,Private
Meters 1445/m 1445/m
F) Tree Compensation
Fruit Trees
No 4208.33 4208.33
Timber wood trees
No 1663.16 1663.16
G) Livelihood Assistance - -
- Livelihood assistance to vulnerable families
- - -
a) impassion cash assistance /allowance equivalent to 6 months OPL adjustment amount , i.e.(Rs. 12000)
DFs 0.072 0.072
b) Relocation assistance Rs. 5000/- to be paid all the DPs requiring to move out of the ROW or Land acquired for the Project
DFs 0.005 0.005
UP-DATED STATUS OF SKILLED & UNSKILLED LABOUR AT NKBP ANNEX-C
DESCON Engineering Limited
New Khanki Barrage Project (NKBP)
District Wise Skilled / Unskilled Labour for the Month of JULY-2016
Sr #
Districts
DESCON
Total
Sub Contractor TOTAL
TOTAL Skilled
Un-skilled
Skilled Un-
skilled Skilled
Un-skilled
1 GUJRANWALA 52 31 83 24 14 76 45 121
2 HAFIZABAD 32 4 36 18 6 50 10 60
3 CHINIOT 8 16 24 8 16 24
4 SHEIKHUPURA 10 6 16 10 6 16
5 NANKANA 14 2 16 14 2 16
6 FAISALABAD 47 6 53 47 6 53
7 JHANG 25 15 40 25 15 40
8 TOBA TEK SINGH
12 4 16 12 4 16
9 Gujrat (Barrage adjoining villages)
112 32 144 24 2 136 34 170
Total 312 116 428 66 22 378
138 516
%age 61.66% 58.59%
60.80%
72.53% 64.71% 63% 59% 62%
10 Other Districts 194 82 276 25 12 219 94 313
Total Districts 506 198 704 91 34 597 232 829
59% Unskilled labour was used during the month of JULY-2016
UP-DATED STATUS OF SKILLED & UNSKILLED LABOUR AT NKBP ANNEX-C
DESCON Engineering Limited
New Khanki Barrage Project (NKBP)
District Wise Skilled / Unskilled Labour for the Month of August-2016
Sr # Districts
DESCON
Total
Sub Contractor TOTAL
TOTA
L Skilled
Un-skille
d
Skilled
Un-skille
d Skilled
Un-skille
d
1 GUJRANWALA 52 36 88 24 14 76 50 126
2 HAFIZABAD 33 4 37 18 6 51 10 61
3 CHINIOT 8 16 24 8 16 24
4 SHEIKHUPURA 10 6 16 10 6 16
5 NANKANA 12 2 14 12 2 14
6 FAISALABAD 58 6 64 58 6 64
7 JHANG 26 13 39 26 13 39
8 TOBA TEK SINGH
16 3 19 16 3 19
9 Gujrat (Barrage adjoining villages)
98 26 124 34 2 132 28 160
Total 313 112 425 76 22
389
134 523
%age
68.94%
56.57%
65.18%
67.86%
64.71%
69% 58% 66%
10 Other Districts 141 86 227 36 12 177 98 275
Total Districts 454 198 652 112 34 566 232 798
58% Unskilled labour was used during the month of August-2016
UPDATED STATUS OF SKILLED & UNSKILLED LABOUR AT NKBP ANNEX-C DESCON Engineering Limited
New Khanki Barrage Project (NKBP)
District Wise Skilled / Unskilled Labour for the Month of September-2016
Sr # Districts
DESCON
Total
Sub Contractor TOTAL
TOTAL Skilled
Un-skilled
Skilled Un-
skilled Skilled
Un-skille
d
1 GUJRANWALA 52 36 88 24 14 76 50 126
2 HAFIZABAD 33 14 47 18 6 51 20 71
3 CHINIOT 19 16 35 19 16 35
4 SHEIKHUPURA 10 14 24 10 14 24
5 NANKANA 16 7 23 16 7 23
6 FAISALABAD 58 12 70 58 12 70
7 JHANG 29 13 42 29 13 42
8 TOBA TEK SINGH
18 7 25 18 7 25
9 Gujrat (Barrage adjoining villages)
98 26 124 38 2 136 28 164
Total 333 145 478 80 22
413
167 580
%age 70.25% 62.77%
67.80%
65.57% 64.71% 69% 63% 67%
10 Other Districts 141 86 227 42 12 183 98 281
Total Districts 474 231 705 122 34 596 265 861
63% Unskilled labour was used during the month of September-2016
Complaint Register of New Khanki Barrage Project Annex-D
Sr# Name of complainant
Date Contact Number
Issue /Location Status of
Complaint Date of
Completion Remarks
1 Imtiaz Ahmed 10/2/2014 3237476606 Demand for Culverts at Chanawan Road
Solved 17/2/2015
2 Zubair Ahmad
1/1/2015 3026262531 Demand for Culverts/186+36 and 192+32 /Chanawan Road
Solved 5/1/2015
3 Mansoor Warraich
10/1/2015 3009806351 Demand for Culverts134+71/Chanawan Road
Solved 17/1/2015
4 Khizar Hayat 5/1/2014 3046205578 Demand for Culverts/115+70Chanawan Road
Solved 11/1/2015
5 Naseem Hussain
10/12/2014 3015564233 Demand for Culverts/84+93/Chanawan Road
Solved 16/12/2014
6 Master Shafqat Ali
15/12/2014 3456498530 Demand for Culverts/56+37/Chanawana Road
Solved 22/12/2014
7 Farooq Akbar Cheema
14/10/2014 3216273305 Increase the rate of land /LCC
DCO Office in Process GRW
Section
Vl in
process
8 Dr. Azhar Iqbal Cheema
26/12/2014 3338402054 Small Bridge /Gunayanwala to KotJaffar Road
Completed
9 Rana Muhammad Khan
1/12/2014
Demand for Culverts/19+200/ Chanawan Road 21+150
Completed
10 Dr. Azhar Iqbal Cheema
Repeated App
3338402054 No 8 Applicaton Repeated.
In Process
11 Ghulam Sarwar Cheema
12/4/2015 3036786566 Demand for Culverts/Chanawan Road
Solved 19/04/2015
12 Head Mistress Girls School
21/05/2015
Play Ground/ Khanki In Process
Irrigation
matter
13 Ghulam Rasool
16/5/2015 3456596818 Cemented Ramp & Soling /LMB Road
In Process
Drawing
awaited
14 Farooq Akbar Cheema
21/5/2015 3216273305 Drainage of flood water/Chanawan Road
In Process
In
Process
at RE
Preparat
ory Desk
15 Umer Hayat 14/5/2015 3216273305 Demand for Culverts/Chanawan Road
Completed
16 Hafiz SaifUllah Chatta
8/6/2015 3022786127 Speed Breaker/ Footpath /Chanawan Road
Completed
17 Muhammad Aslam Randhawa
9/6/2015 3066282001 Outlet /Chanawan Road Completed
18 Haji AmjadPervaiz Randhawa
8/6/2015 3022786127 Repair the old bridge /Chanawan Road
Completed
19 Pervaiz Iqbal Bhatti
7/6/2015 3212332348 Repair the old bridge/Chanawan Road
Completed
20 XEN Irrigation
9/6/2015 3455810002 Boundary wall / Play Ground/Irrigation Colony
Completed
21 Master Nasir Mahmood
6/4/2015 3002786400 Change the location of culvert/Chanawan Road
Solved 13/04/2015
22 Waqas Chatta Advocate
11/4/2015
Court Case /Chanawan Road
Solved 17/04/2015
Withdra
wn by
applicant
23 SDO Headworks
9/7/2015
Breakage of High Level Channel
Solved 11/7/2015
24 Umer Hayat 7/7/2015 3086464171 Hurdle on Chanawan Road
Completed
25 Farooq Akbar Cheema
14/7/2015 3216273305 Drainage of Rain water from crops
Solved 17/7/2015
26 Amanat Ali 22/7/2015
Standing Rain Water in Colony
Solved 23/7/2015
27 SDO Headworks
28/7/2015
Breakage of High Level Channel
Solved 29/7/2015
28 Sibt-E-Hassan
19/11/2015 3006273305 Boundary wall of New Irrigatoin Colony
Completed
29 Hafiz SaifUllah Chatta
10/9/2015 0302-
2786127 Irrigation Water issue Completed
30 Farooq Akbar Cheema
27/11/2015 3216273305 Earthfilling of the Pond Completed
31 Farooq Akbar Cheema
28/11/2015 3216273305 Water level issue of Khanki village
In Process
In
Process
32 Ghulam Rasool
25/1/2016
Demand of paved path In Process
33 Johar Sarwar 1/2/2016 0302-
8488888 Demand of Play Ground In Process
Irrigation
matter
34 Safdar Mumtaz Sandhu
2/2/2016 3009622355 Demand of Mosque & Park
In Process
35 Farooq Akbar Cheema
31/03/2016 3216273305 Demand of culvert In Process
In
process
in PMO
36 Muhammd Hanif
7/4/2016
demand of path from LMB road
Completed
37 Muhammad Nazim
20/05/2016
Demand of paved path In Process
38 Muhammad Hanif Saleemi
3/6/2016 3216273305 road level and culverts In Process
39 Ch. Akram 19/08/2016 Spur at right side Completed
40 Kram Rasool Culvert at Kot Imam
Buksh Completed
41 Ghulam Rasool
25/08/2016 09/09/2016
0345 6596818
Ramp at Rattowali In Process
drawing awaited
42 Farooq Akbar Cheema
24/09/2016 0321627330
5 Sub base at road Completed
43 Farooq Akbar Cheema
1/10/2016 0321627330
5 Culvert on high level channel
In process
44 Abdul malik 03/10/2016 Kot Imam Buksh Completed
45 XEN GEPCO Wazirabad
06/10/2016 Complaint Office In process
Total Application =45
Action Completed=31
In process 14
Average=69%