part 1.2 hardware system · 2009. 7. 1. · conceptual process development project sanction design,...

66
PART 1.2 HARDWARE SYSTEM Dr. AA, Process Control & Safety 1

Upload: others

Post on 04-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

PART 1.2 HARDWARE

SYSTEM

Dr. AA, Process Control & Safety

1

Page 2: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

How to Ensure that Process Plant is Safe

1. Preliminary Decision

– Process Selection, site

selection etc

2. Process Design

– Inherent safety

3. Process Safety Management

2

Page 3: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

PROCESS SYSTEM

Many different scenarios

• Fully Automated vs manual plant

• Fully integrated continuous plant vs batch

plant

• Onshore vs offshore

3

Page 4: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

PART 1.2 HARDWARE

SYSTEM

Topic 1 Inherently Safe Design

4

Page 5: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Inherent Safety

• To make the concept more understandable, the

following four words have been recommended

to describe inherent safety

– Minimise (intensification)

– Substitute (substitution)

– Moderate (attenuation and limitation of

effects)

– Simplify (simplification and error tolerance)

Page 6: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Minimise (example)

• Change from larger batch reactor to smaller

continuous reactor

• Reduce storage inventory of raw materials

• Improve control to reduce inventory of

hazardous intermediate chemicals

• Reduce process hold-up

Page 7: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Substitute (example)

• Use mechanical pump seals vs packing

• Use welded pipe vs flanged

• Use solvent that are less toxic

• Use mechanical gauges vs mercury

• Use chemicals with higher flash point, boiling

points, and other less hazardous properties

• Use water as heat transfer fluid instead of hot

oil

Page 8: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Moderate (example)

• Use vacuum to reduce boiling point

• Reduce process temperature and pressure

• Refrigerate storage vessel

• Dissolve hazardous materials in safe solvent

• Place control rooms away from operation

• Operate at conditions where runaway reactions

are not possible

• Separate pump rooms from other rooms

• Barricade control rooms and tanks

Page 9: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Simplify (example)

• Keep piping systems neat and visually easy to follow

• Design control panels that are easy to comprehend

• Design plants for easy and safe maintenance

• Pick equipment with low failure rates

• Separate systems and controls into blocks that are

easy to comprehend and understand

• Label pipes for easy „walking the line”

• Label vessels and controls to enhance understanding

• Add fire and explosion resistant barricades

Page 10: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

10

Inherent Safety Concept

• Reduce the risk at early stage of design

Page 11: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

11

PROJECT PHASE

Conceptual Process

development

Project

sanctionDesign, engineering,

construction

Hand

over

operation

Stage 1

Concept

Stage 2

Process

design

Stage 3

Detailed

Engineering

Stage 6

Post-

commis

sioning

Stage 5

Pre-

Commis

sioning

Stage 4

Construction

Relationship of six-stage process study system to project life-cycle

Safety issues must be embedded within all project life-cycle

Page 12: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

12

Many hazard identification technique can be used at

appropriate cycle

Method Used

Checklist

RR

What-if

FTAETA

FMEA

LOPAHAZOP

PHR

Page 13: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

13

Hazard identification technique and project phase

Method

used

Project life cycle stage

0 1 2 3 4 5 6 7

Checklist X X X X X X X X

RR X X (X) (X)

What-If X X X X

FTA X X X (X) X

ETA X X X (X) X

FMEA (X) X X (X)

LOPA X X X

HAZOP (X) X X

PHR X (X)

Page 14: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

PART 1.2 HARDWARE

SYSTEM

Topic 2 Plant Operation System

14

Page 15: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Typical Objectives of Plant Operation

1. Protect people

2. Protect Environment

3. Protect Equipment

4. Maintain Smooth operation

5. Achieve Product rates and quality

6. Profit = optimising first five

7. Monitoring & diagnosis

These are Achieved Through Process Control…

15

Page 16: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

DCS Architecture

Process Transmitters and Actuators

Data Highway

(Shared Communication Facilities)

......

Data

Storage Unit

Host

Computer

System

ConsolesPLC

4-20 mA

Local

Console

Local

Control

Unit

4-20 mA

Local

Control

Unit

Local

Console

16

Page 17: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Fieldbus Technology

• Introduced 1988 but underwent

many development

• Standard IEC61158 introduced

in 1999

• Based upon smart valves, smart

sensors and controllers

installed in the field.

• Uses data highway to replace

wires from sensor to DCS and to

the control valves.

• Less expensive installations

and better reliability.

• Can mix different sources

(vendors) of sensors,

transmitters, and control valves.

• Now commercially available and

should begin to replace DCSs.

CEAG

I/O

P5001 0

... 150 bar

•Foundation Fieldbus (FF)

•Profibus (Process Field Bus)

•Others: ControlNet, P-Net, SwiftNet ,

WorldFIP, Interbus, EtherCAT,

SERCODS etc 17

Page 18: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Fieldbus Architecture

Plant Optimization

.................

Smart

Sensors

Smart Control

Valves and

Controllers

Local

Area

Network

Smart

Sensors

Smart Control

Valves and

Controllers

Local

Area

Network

H1 Fieldbus Network H1 Fieldbus Network

H1 Fieldbus H1 Fieldbus

Data Storage

PLCs

High Speed Ethernet

18

Page 19: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

PLC Architecture

ProcessorPower

Supply

Data Highway

PLC Cabinet

Programming

Interface

I/O Modules

Input

Devices

Output

Devices

19

Page 20: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

We desire independent protection layers, without

common-cause failures - Separate systems

sensors

SIS system

i/o i/o………….

sensors

Digital control system

i/o i/o………….

DCS handles controls

and alarms functions.

PLC handles SIS and Alarms

associated with SIS

Redundancy

20

Page 21: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Layer of Protection

DR. AA

Process Control & Safety Group

Page 22: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

ALARMS

SIS

RELIEF

CONTAINMENT

EMERGENCY RESPONSE

BPCS

Strength in Reserve

• BPCS - Basic process

control

• Alarms - draw attention

• SIS - Safety interlock

system to stop/start

equipment

• Relief - Prevent

excessive pressure

• Containment - Prevent

materials from reaching,

workers, community or

environment

• Emergency Response -

evacuation, fire fighting,

health care, etc.

A

U

T

O

M

A

T

I

O

N

Layers of Protection for High Reliability

22

Page 23: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• Four Layers in the Safety Hierarchy

• Methods and equipment required at all

four layers

• Process examples for every layer

• Workshop

Safety Through Automation

23

Page 24: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

All Processes must have Safety Through

Automation

• Safety must account for failures of equipment

(including controller) and personnel

• Multiple failure must be covered

• Responses should be limited, try to maintain

production if possible

• Automation systems contribute to safe

operation24

Page 25: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

SAFETY STRENGTH IN DEPTH !

PROCESS

RELIEF SYSTEM

SAFETY INTERLOCK SYSTEM

ALARM SYSTEM

BASIC PROCESSCONTROL SYSTEM

Closed-loop control to maintain processwithin acceptable operating region

Bring unusual situation to attentionof a person in the plant

Stop the operation of part of process

Divert material safely

Seriousness

of event

Four

independent

protection

layers (IPL)

Redundancy – Key Concept in Process Safety

25

Page 26: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

1. Safety

2. Environmental Protection

3. Equipment Protection

4. Smooth Operation &

Production Rate

5. Product Quality

6. Profit

7. Monitoring & Diagnosis

We are now emphasizing

these topics

Control systems are designed to achieve well-

defined objectives, grouped into seven categories.

Objective of process Control

26

Page 27: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• Technology - Multiple PIDs, cascade, feedforward, etc.

• Always control unstable variables (Examples in flash?)

• Always control “quick” safety related variables

- Stable variables that tend to change quickly (Examples?)

• Monitor variables that change very slowly

- Corrosion, erosion, build up of materials

• Provide safe response to critical instrumentation failures

- But, we use instrumentation in the BPCS?

1. Basic process Control System (BPCS)

27

Page 28: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Control Strategy

• Feedback Control

– Single-loop feedback

• Overcoming disturbances

– Cascade

– Feed forward

– Ratio

• Constraints

– Split-range, override/select control

• Multivariable

– multi-loop

– Decoupling

– Multivariable control 28

Page 29: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Level Control on a Tank

Fin

LT

Fout

Lsp

LC

Without a cascade level

controller, changes in

downstream pressure disturb

the tank level.

Ordinary Feedback Control

Fin

FC

LT

RSP

FT

Fout

Lsp

LC

With cascade level controller, changes

in downstream pressure will be

absorbed by the flow controller before

they can significantly affect tank level

because the flow controller responds

faster to this disturbance than the tank

level process.

Cascade Control

29

Page 30: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Multiple Cascade Example

FT

AC

AT

TCTT

FC

RSP

RSP

This approach works because the flow control loop is much

faster than the temperature control loop which is much faster

than the composition control loop.

Page 31: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Level Control: Feedback vs feedforward

Make-upWater

To SteamUsers

LT

LC

Feedback-only must

absorb the variations in

steam usage by feedback

action only.

Make-up Water

To Steam Users

LT

FT

FF

Feedforward-only handle

variation in steam usage but

small errors in metering will

eventually empty or fill the

tank.

FeedforwardFeedback

31

Page 32: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Level Control: Feedforward-Feedback

To Steam Users

LT

FT FF

LC +

Make-up Water

Combined feedforward and feedback has

best features of both controllers.

32

Page 33: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Split Range Control: Another Example

FT

FT

FC

FC

Sometimes a single flow control loop cannot provide accurate flow

metering over the full range of operation.

Split range flow control uses two flow controllers

One with a small control valve and one with a large control valve

At low flow rates, the large valve is closed and the small valve provides

accurate flow control.

At large flow rates, both valve are open.

Larger Valve

Sig

nal to

Co

ntr

ol

Valv

e (

%)

Smaller Valve

Total Flowrate

33

Page 34: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Titration Curve for a Strong Acid-Strong Base

System

0

2

4

6

8

10

12

14

0 0.002 0.004 0.006 0.008 0.01

Base to Acid Ratio

pH

Therefore, for accurate pH control for a wide range of flow

rates for acid wastewater, a split range flow controller for

the NaOH is required.

34

Page 35: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Override/Select Control

• Override/Select control uses LS and HS action to

change which controller is applied to the

manipulated variable.

• Override/Select control uses select action to switch

between manipulated variables using the same

control objective.

35

Page 36: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Furnace Tube Temperature Constraint Control

FT

FC

TT TT

LS TCTC

RSP

FlueGas

ProcessFluidFuel

36

Page 37: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Column Flooding Constraint Control

FT

AC

AT

LSDPC

FC

RSP

Lower value of flowrate is selected to avoid

column flooding

37

Page 38: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

How would we protect against an error in the

temperature sensor (reading too low) causing a

dangerously high reactor temperature?

TC

Cold

feed

Highly exothermic reaction.

We better be sure that

temperature stays within

allowed range!

BPCS- measurement redundancy

38

Page 39: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

How would we protect against an error in the temperature sensor

(reading too low) causing a dangerously high reactor temperature?

T1

Cold

feed

T2

TYTC

Measured value

to PID controller

Controller

output

>

TY

>

Selects the

largest of all

inputs

Use multiple sensors and select most

conservative!

39

Page 40: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Summary of Control Strategies

• Feedback Control

• Enhancement of single-loop Feedback control

– Cascade, split-range, override control

• Feedforward and Ratio Control

• Computed Control (e.g. reboiler duty, internal reflux

etc)

• Advanced Control

– Inferential control

– Predictive control

– Adaptive control

– Multivariable control

40

Page 41: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• Alarm has an anunciator and visual

indication

- No action is automated!

- A plant operator must decide.

• Digital computer stores a record of recent

alarms

• Alarms should catch sensor failures

- But, sensors are used to measure variables

for alarm checking?

2. Alarms that require actions by a Person

41

Page 42: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• Common error is to design too many alarms

- Easy to include; simple (perhaps, incorrect) fix to prevent repeat

of safety incident

- example: One plant had 17 alarms/h - operator acted on only 8%

• Establish and observe clear priority ranking

2. Alarms that require actions by a Person

- HIGH = Hazard to people or equip., action required

- MEDIUM = Loss of RM, close monitoring required

- LOW = investigate when time available

42

Page 43: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• Automatic action usually stops part of plant

operation to achieve safe conditions

- Can divert flow to containment or disposal

- Can stop potentially hazardous process, e.g., combustion

• Capacity of the alternative process must be for

“worst case”

• SIS prevents “unusual” situations

- We must be able to start up and shut down

- Very fast “blips” might not be significant

3. Safety Interlock System (SIS)

43

Page 44: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• Also called emergency shutdown system (ESS) or

safety instrumented system (SIS)

• SIS should respond properly to instrumentation

failures

- But, instrumentation is required for SIS?

• Extreme corrective action is required and

automated

- More aggressive than process control (BPCS)

• Alarm to operator when an SIS takes action

3. Safety Interlock System

44

Page 45: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

The automation strategy is usually simple,

for example,

If L123 < L123min; then, reduce fuel to zero

steam

water

LC

PC

fuel

How do we

automate this SIS

when PC is adjusting

the valve?

Example

45

Page 46: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

If L123 < L123min; then, reduce fuel to zero

steam

water

LC

PC

fuel

LS s s

fc fc

15 psig

LS = level switch, note that separate sensor is used

s = solenoid valve (open/closed) fc = fail closed

Extra valve with tight shutoff

3. Safety Interlock System

46

Page 47: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• The automation strategy may involve several variables, any

one of which could activate the SIS

If L123 < L123min; or

If T105 > T105max

…….

then, reduce fuel to zero

SIS

100

L123

T105

…..

s

Shown as “box”

in drawing with

details elsewhere

SIS: Another Example

47

Page 48: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• The SIF saves us from hazards, but can shutdown the plant

for false reasons, e.g., instrument failure.

1 out of 1

must indicate

failure

T100s

2 out of 3

must indicate

failure

T100

T101

T102

Same variable,

multiple sensors!

s

False

shutdown

Failure

on

demand

5 x 10-35 x 10-3

2.5 x 10-6 2.5 x 10-6

Better

performance,

more expensive

SIS: measurement redundancy

48

Page 49: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• We desire independent protection layers, without

common-cause failures - Separate systems

sensors

SIS system

i/o i/o………….

sensors

Digital control system

i/o i/o………….

BPCS and Alarms SIS and Alarms

associated with SIS

SIS & DCS

49

Page 50: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

4. Safety Relief System

• Overpressure

– Increase in pressure can lead to rupture of vessel

or pipe and release of toxic or flammable material

• Underpressure

– Also, we must protect against unexpected vacuum!

• Relief systems provide an exit path for fluid

– Benefits: safety, environmental protection,

equipment protection, reduced insurance,

compliance with governmental code

50

Page 51: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• Entirely self-contained, no external power required

• The action is automatic - does not require a person

• Usually, goal is to achieve reasonable pressure

- Prevent high (over-) pressure

- Prevent low (under-) pressure

• The capacity should be for the “worst case” scenario

4. Safety Relief System

51

Page 52: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• No external power required -

• self actuating - pressure of

process provides needed

force!

• Valve close when pressure

returns to acceptable value

• Relief Valve - liquid systems

• Safety Valve - gas and vapor

systems including steam

• Safety Relief Valve - liquid

and/or vapor systems

• Pressure of protected

system can exceed the set

pressure.

4. Safety Relief System

52

Page 53: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Rupture Disk

• No external power

required

• self acting

• Rupture disk / burst

diaphragm must be

replaced after opening.

4. Safety Relief System

53

Page 54: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

• Spring-loaded safety relief valve

Process

To effluent handling

• Rupture disc

Process To effluent handling

4. Safety Relief System

54

Page 55: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

IN SOME CASES, RELIEF VALVE AND

DIAPHRAGM ARE USED IN SERIES - WHY?

Why is the pressure

indicator provided?

Is it local or

remotely displayed?

Why?

• What is the advantage of two in series?

• Why not have two relief valves (diaphragms) in series?

4. Safety Relief System

55

Page 56: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

IN SOME CASES, RELIEF VALVE AND DIAPHRAGM ARE USED IN

SERIES - WHY?

Why is the pressure

indicator provided?

If the pressure

increases, the disk

has a leak and should

be replaced.

Is it local or remotely

displayed? Why?

The display is local to

reduce cost, because

we do not have to

respond immediately

to a failed disk - the

situation is not

hazardous.

• What is the

advantage of two in

series?

The disc protects the

valve from corrosive

or sticky material.

The valve closes

when the pressure

returns below the

set value.

4. Safety Relief System

56

Page 57: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

WE SHOULD ALSO PROTECT AGAINST EXCESSIVE VACUUM

• The following example uses buckling pins

overpressure

underpressure

4. Safety Relief System

57

Page 58: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Location of Relief System

• Identify potential for damage due to high (or low)

pressure (HAZOP Study)

• In general, closed volume with ANY potential for

pressure increase

– may have exit path that should not be closed but could be

– hand valve, control valve (even fail open), blockage of line

• Remember, this is the last resort, when all other

safety systems have not been adequate and a fast

response is required!

58

Page 59: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Flash Drum Example

Page 60: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

LET‟S CONSIDER A FLASH DRUM

Is this process safe and ready to operate?

Is the design completed?

F1

60

Page 61: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

Where could we use BPCS in the flash process?

F1

Basic Process Control System

61

Page 62: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

The level is

unstable; it must

be controlled.

The pressure will

change quickly and

affect safety; it must

be controlled.

F1

62

Page 63: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

F1

Where could

we use alarms

in the flash process?

Alarms

63

Page 64: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

A low level could

damage the pump;

a high level could

allow liquid in the

vapor line.

The pressure affects

safety, add a high alarm

F1

PAH

LAH

LAL

Too much light key

could result in a large

economic lossAAH

64

Page 65: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

F1

Safety Relief System

Add relief to the following system

65

Page 66: PART 1.2 HARDWARE SYSTEM · 2009. 7. 1. · Conceptual Process development Project sanction Design, engineering, construction Hand over operation Stage 1 Concept Stage 2 Process design

F1

The drum can be isolated

with the control valves;

pressure relief is

required.

We would like to recover

without shutdown; we

select a relief valve.

66