pavement & material design,tanzania
TRANSCRIPT
-
7/24/2019 Pavement & Material Design,Tanzania
1/185
-
7/24/2019 Pavement & Material Design,Tanzania
2/185
-
7/24/2019 Pavement & Material Design,Tanzania
3/185
-
7/24/2019 Pavement & Material Design,Tanzania
4/185
-
7/24/2019 Pavement & Material Design,Tanzania
5/185
-
7/24/2019 Pavement & Material Design,Tanzania
6/185
-
7/24/2019 Pavement & Material Design,Tanzania
7/185
-
7/24/2019 Pavement & Material Design,Tanzania
8/185
Cut back slope
Shoulder breakpoint
Shoulder Shoulder
Embankment side slope
Carriageway
Roadway
Open side drain
Centre
line
Lane Lane
Original ground level
Finished road level
Pavement layers
Improvedsubgrade layers
Cutting
In-situ subgrade Fill
Formation level
Subgrade
Roadbed
Asphalt concrete surfacing Surface treated pavementsWearing course
Binder course (if required)
SurfacingSurfacing
SubgradeSubgrade
Surfacing
Gravel roads
Gravel wearing course
Structural layer (improved subgrade, if required)
Subgrade
-
7/24/2019 Pavement & Material Design,Tanzania
9/185
-
7/24/2019 Pavement & Material Design,Tanzania
10/185
-
7/24/2019 Pavement & Material Design,Tanzania
11/185
-
7/24/2019 Pavement & Material Design,Tanzania
12/185
-
7/24/2019 Pavement & Material Design,Tanzania
13/185
-
7/24/2019 Pavement & Material Design,Tanzania
14/185
-
7/24/2019 Pavement & Material Design,Tanzania
15/185
-
7/24/2019 Pavement & Material Design,Tanzania
16/185
-
7/24/2019 Pavement & Material Design,Tanzania
17/185
-
7/24/2019 Pavement & Material Design,Tanzania
18/185
Project appraisal
Environment
Pavement Design-
New Roads
Cross Section,Shoulders and Drainage
Traffic
Subgrade
Problem Soils
Pavement Materials
DESIGNELEMENTS
PavementRehabilitation
BituminousSurfacings
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
19/185
-
7/24/2019 Pavement & Material Design,Tanzania
20/185
-
7/24/2019 Pavement & Material Design,Tanzania
21/185
-
7/24/2019 Pavement & Material Design,Tanzania
22/185
-
7/24/2019 Pavement & Material Design,Tanzania
23/185
-
7/24/2019 Pavement & Material Design,Tanzania
24/185
-
7/24/2019 Pavement & Material Design,Tanzania
25/185
-
7/24/2019 Pavement & Material Design,Tanzania
26/185
Project appraisal
Pavement Design-
New Roads
Cross Section,Shoulders and Drainage
Traffic
Subgrade
Problem Soils
Pavement Materials
DE
SIGN
ELEMENTS
PavementRehabilitation
BituminousSurfacings
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
27/185
-
7/24/2019 Pavement & Material Design,Tanzania
28/185
-
7/24/2019 Pavement & Material Design,Tanzania
29/185
-
7/24/2019 Pavement & Material Design,Tanzania
30/185
-
7/24/2019 Pavement & Material Design,Tanzania
31/185
-
7/24/2019 Pavement & Material Design,Tanzania
32/185
-
7/24/2019 Pavement & Material Design,Tanzania
33/185
-
7/24/2019 Pavement & Material Design,Tanzania
34/185
-
7/24/2019 Pavement & Material Design,Tanzania
35/185
Project appraisal
Environment
Pavement Design-
New Roads
Traffic
Subgrade
Problem Soils
Pavement Materials
DESIGNELEMENTS
PavementRehabilitation
BituminousSurfacings
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
36/185
-
7/24/2019 Pavement & Material Design,Tanzania
37/185
-
7/24/2019 Pavement & Material Design,Tanzania
38/185
75 mm
Water Pervious materialBase
course
Subbase
Granularbase course
Subbase
Water
-
7/24/2019 Pavement & Material Design,Tanzania
39/185
General requirementmin 0,5 m
Cuttings - general requirementmin 1,0 m
Cuttings - lime modified subgrademin 0,5 m
Pavement
Formationlevel
Pavement
Formationlevel
Pavement
Formationlevel
-
7/24/2019 Pavement & Material Design,Tanzania
40/185
-
7/24/2019 Pavement & Material Design,Tanzania
41/185
Project appraisal
Environment
Pavement Design-New Roads
Cross Section,Shoulders and Drainage
Subgrade
Problem Soils
Pavement Materials
DESIGNELEMENTS
PavementRehabilitation
BituminousSurfacings
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
42/185
tonnes load
kPa
load per area
contact pressure
loads t1 t2 t3 t4.......tn
-
7/24/2019 Pavement & Material Design,Tanzania
43/185
Pavement serviceability
Project construction, the
pavement beingcompleted in parts.
Completed
pavementon
theentire
project
Terminal valueof serviceability
(nore
seal)
Res
eal
Reseal
Pavement
rehablitation
Design Period
Traffic count
for each
direction
Chapter 4.2.1
Axle load survey
for each
direction
Chapter 4.2.2
Proportion of
E80 made up
from axles
heavier than 13t
Chapter 4.2.4
Vehicle
equivalency
factor
Chapter 4.2.3
Proportion of
E80 made up
from axles
heavier than13tChapter 4.2.4
Vehicle
equivalency
factorChapter 4.2.3
Classify
as'heavy' or not
Chapter 4.2.4
Apply
traffic growth
Chapter 4.2.5
and lane
distribution
Chapter 4.2.6
Include
construction
traffic
Chapter 4.2.7
Classify into
Traffic Load Class
Chapter 4.3Socio -economicstudies
Design trafficloading
-
7/24/2019 Pavement & Material Design,Tanzania
44/185
-
7/24/2019 Pavement & Material Design,Tanzania
45/185
-
7/24/2019 Pavement & Material Design,Tanzania
46/185
-
7/24/2019 Pavement & Material Design,Tanzania
47/185
-
7/24/2019 Pavement & Material Design,Tanzania
48/185
-
7/24/2019 Pavement & Material Design,Tanzania
49/185
Project appraisal
Environment
Pavement Design-
New Roads
Traffic
Subgrade
Problem Soils
Pavement Materials
DESIGNELEMENTS
PavementRehabilitation
BituminousSurfacing
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
50/185
Original ground level
Finished road level
Pavement layers
Design depth
Other roads
Paved trunk roads
-
7/24/2019 Pavement & Material Design,Tanzania
51/185
-
7/24/2019 Pavement & Material Design,Tanzania
52/185
Sitereconnaissance
Compilation
of input data
Demarcation ofhomogenoussections
Min 3 CBRtests per uniform
section
Cut ?Use lowestCBR value
:CBRdesignClassify
S3, S7, S15
Design improved
subgrade as
required
Min 5 CBRtests per uniform
section
Specialassessmentof thesection
Plot valuesin ascendingorder
Determine 90%-ile valueat the 0.1 X (n-1) pointon the curve
Yes
Yes
YesNo
No
-
7/24/2019 Pavement & Material Design,Tanzania
53/185
0
2
4
6
8
10
12
14
16
1 2 3 4 5 6 7 8 9Test
CBR(%)
n = 9 tests
d = 0.1 x (n-1)
= 0.8
d=0.8
Example
CBR data68999
11121214
90% -ile7.6
CBRdesign8%
CBR values plottedin ascending order
1
10
100
88
90
92
94
96
98
100
102
104
% of MDD
CBR4dayssoaked
(%)
-
7/24/2019 Pavement & Material Design,Tanzania
54/185
Subgrade Density for
class Wet or moderate determinationclimatic zones of CBRdesign
4 days soaked value Tested at OMC 4 days soaked value [% of MDD]
S15 Min 15 Min 15 Min 7 95 BS-HeavyS7 7 - 14 7 - 14 3 - 14 93 BS-HeavyS3 3 - 6 3 - 6 2 - 6 100 BS-Light
Soaked and OMC refer to standard 4 days soaking and the optimum moisture content determined inaccordance with tests CML1.9 and CML 1.11. Climatic zones are shown in/Figure 2.1/.
BS-Light compaction effort is used on poor in-situ soils and deep in-situ soils rather than BS-Heavy due to itsbetter correspondence with the actual effect from compaction equipment under conditions with poor support
for compaction. The referred laboratory test methods are CML 1.9 and 1.11.
Problem soils: Special treatment is required./Chapter 6/
CBRdesign [%]
Dry climatic zones(both requirements shall be met)
-
7/24/2019 Pavement & Material Design,Tanzania
55/185
sub grad e l ayers C ompa cted l ayer
Formation level (150 +150 mm) thickness (max 1m)
Roadbed or previous fill layer
Dump rock - cross section
Max 2/3 of compactedlayer thickness
dMAX
*) Material requirements for improved subgrade layers, including limits for maximum compacted layerthickness are given inTable 5.5.
G15G15
300mm
150mm
G15
150mm
150mm
150mm
G15
G7
requirement or dry climate Moderate Wet
General General requirements
S3S7Heavy traffic classes (-H)
WetModerate climateor dry
G15
S15
Subgrade classes
G7
300mm 300mm
150mmG7
G7
300mm 300mm
Heavy traffic
classes (-H)
none
none
none none
G15
Improvedsubgrade
layertobeconstructed
Lowerlayer*)
Upperlayer*)
CBR [%], wet or moderate
climatic zones 1)
CBR [%], dry climatic zones 1) Min 15 at OMC Min 7 at OMC 1.9 and
(both requirements shall be met) Min 7 after 4 days soaking Min 3 after 4 days soaking 1.7
CBR-swell [%] 2) Max 1.5 Max 2.0
PI [%] Max 25 Max 30 1.2 and 1.3
Max particle size, dMAX 2/3 of layer thickness 2/3 of layer thickness 1,7
Compacted layer thickness [mm] Max 250 Max 250
1) Climatic zones are shown in /Figure 2.1/. CBR values shall be assesed at density as given in Table 5.3.
Soaked and OMC refer to standard 4 days soaking and the optimum moisture content determined in
accordance with tests CML test methods 1.9 and 1.11
2) CBR-Swell is measured at 100% BS-Heavy compaction effort.
Min 15 after 4 days soaking Min 7 after 4 days soaking
-
7/24/2019 Pavement & Material Design,Tanzania
56/185
Depth
150mm
Scarify & compact
Future formation level
-
7/24/2019 Pavement & Material Design,Tanzania
57/185
-
7/24/2019 Pavement & Material Design,Tanzania
58/185
-
7/24/2019 Pavement & Material Design,Tanzania
59/185
Project appraisal
Environment
Pavement Design-
New Roads
Cross Section,Shoulders and Drainage
Traffic
Subgrade
Pavement Materials
DESIGNELEMENTS
PavementRehabilitation
BituminousSurfacings
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
60/185
-
7/24/2019 Pavement & Material Design,Tanzania
61/185
Routine investigations
Expansive
Extended investigations
Expansive?
In-depth studyDesign and constructionmeasures for expansive soils
Normaldesign
Severe consequencesto the construction
economy?
No
No
No
Yes
Yes
Perhaps
Cross section
Outer zones having large seasonalvariations in moisture content
Expansive soils
Seasonal
movement
Seasonal
movement
-
7/24/2019 Pavement & Material Design,Tanzania
62/185
-
7/24/2019 Pavement & Material Design,Tanzania
63/185
min. 6 m (4 m)
side drainembankment
-
7/24/2019 Pavement & Material Design,Tanzania
64/185
-
7/24/2019 Pavement & Material Design,Tanzania
65/185
Freely draining material
Pavement layers
Fill and improved subgrade Side-fill
Expansive soil
1:6 or flatter
1:2
Freely draining materialPavement layers
Fill and improved subgrade
Side-fill
Expansive soil excavated 0.6 m
deep and replaced with fill
Freely draining materialPavement layers
Fill and improved subgrade Side-fill
Temporary stockpile of
Embankments 2 m or higher
Embankments less than 2 m in hight
excavated expansive soilto be used for side-fill
>2 m
Max. the width of the surfacing
excavated expansive soilto be used for side-fill
Temporary stockpile of
< 2 m
1:4 or flatter
1:2
1:6 or flatter
1:2
Expansive soil excavated 0.6 m deep and replaced with fill
-
7/24/2019 Pavement & Material Design,Tanzania
66/185
cross section
A thin bituminous sealgets pushed up by thecrystallisation forcesand blistering occurs,having a diametre of5 to 10 cm initially, Crystallisation of
subsequently developing soluble salts under
into a pothole. the bituminous seal.
Soluble salts migrate towards thesurface within granular layers
See detail
-
7/24/2019 Pavement & Material Design,Tanzania
67/185
-
7/24/2019 Pavement & Material Design,Tanzania
68/185
-
7/24/2019 Pavement & Material Design,Tanzania
69/185
Project appraisal
Environment
Pavement Design-New Roads
Cross Section,Shoulders and Drainage
Traffic
Subgrade
Problem SoilsDESIGNELEMENTS
PavementRehabilitation
BituminousSurfacings
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
70/185
-
7/24/2019 Pavement & Material Design,Tanzania
71/185
-
7/24/2019 Pavement & Material Design,Tanzania
72/185
Material CML test properties method
Wet or moderate climatic zones: min 80after 4 days soak Wet or moderate climatic zones: min 60after 4 days soakCBR [%] Dry climatic zones (both requirements shall be met): Dry climatic zones (both requirements shall be met):
at 98% MDD of min 80at OMC of BS-Heavy min 60at OMC of BS-Heavy 1.7 and
BS-Heavy min 60after 4 days soaking min 45after 4 days soaking 1.11
General Coral rock, calcrete or General Coral rock, calcrete or
Atterberg requirements other calcified materials requirements other calcified materials
limits 1) Wet or Dry Wet Dry or Wet Dry or Wet Dry or
moderate climate climate moderate climate moderate climate moderate
maxLL [%] 30 40 35 45 35 45 40 45 1.2
maxPI [%] 8 14 10 16 10 16 12 18 1.3maxLS [%] 4 7 5 8 5 8 6 9 1.4
Grading, sieve
sizes [mm]
63
37.5 Grading requirements:
20 - dMAXshall be maximum 2/3 of the compacted layer thickness
5 - Grading Modulus (GM*)
): min2.0 2 *) 0.425 GM = [ 300 - (% passing 2mm) - (% passing 0.425mm) - (% passing 0.075mm) ] / 100
0.075
Particle TFVdry : min80 kN TFVdry : min50 kN
strength TFVsoaked : min60% of TFVdry TFVsoaked : min60% of TFVdry
Soluble salts Where the gravel is used under a surface treatment, soluble salt content is assessed in accordance with /7-11/.
Field density
CBR - swell [%]max 0.5 max 1.0
measured at BS-Heavy compaction measured at BS-Heavy compaction
30 - 65
1) It is emphasised that the Atterberg limits shall be measured according to CML test methods 1.2, 1.3 and 1.4. These methods follow BS procuders and
Nominal value: min 98% of MDD, BS-Heavy
utilise BS equipment. Other laboratory test procedures are likely to give results that are not comparable with the given material requirements.
1.7
2.7
10 - 30
20 - 50
Material class
5 - 15
100
80 - 100
60 - 95
Grading envelope, G80
[% passing]
G80 G60
(no envelope for G60, coral rock, calcrete or other calcified materials)
-
7/24/2019 Pavement & Material Design,Tanzania
73/185
Material CML test
propertiesmethod
Wet or moderate climatic zones: min 45after 4 days soak Wet or moderate climatic zones: min 25after 4 days soak
CBR [%] Dry climatic zones (both requirements shall be met): Dry climatic zones (both requirements shall be met):
at 95% MDD of min 45at OMC of BS-Heavy min 25at OMC of BS-Heavy 1.7 andBS-Heavy min 25after 4 days soaking min 15after 4 days soaking 1.11
General Coral rock, calcrete or General Coral rock, calcrete or
Atterberg requirements other calcified materials requirements other calcified materials
limits 1) Wet or Dry Wet Dry or Wet or Dry Wet Dry ormoderate climate climate moderate moderate climate climate moderate
maxLL [%] 40 45 45 50 45 50 45 55 1.2
maxPI [%] 14 18 16 20 16 20 18 24 1.3 maxLS [%] 7 9 8 10 8 10 9 12 1.4
Grading *)
Modulus (GM) *) GM = [ 300 - (% passing 2mm) - (% passing 0.425mm) - (% passing 0.075mm) ] / 100
Particle size dMAXshall be maximum 2/3 of the compacted layer thickness
Soluble salts Where the gravel is used under a surface treatment, soluble salt content is assessed in accordance with /7-11/.
Field density
BS equipment. Other laboratory test procedures are likely to give results that are not comparable with the given material requirements.
Nominal value: min 95% of MDD, BS-Heavy
G45 G25
1) It is emphasised that Atterberg limits shall be measured according to CML test methods 1.2, 1.3 and 1.4. These methods follow BS procuders and utilise
1.7
Material class
min1.5 min1.2
CBR - swell [%]max 0.5 max 1.0
measured at BS-Heavy compactionmeasured at BS-Heavy compaction
-
7/24/2019 Pavement & Material Design,Tanzania
74/185
Material CML test properties method
Material source
maxLL [%]1) 1.2
maxLS [%]1) 1.4
Grading, sieve
sizes [mm] Coarse Type Fine Type Coarse Type Fine Type
50 100
37.5 100 90 - 100 100
28 87 - 97 100 75 - 95 90 - 100
20 75 - 90 87 - 97 60 - 90 65 - 95
10 52 - 68 62 - 77 40 - 75 40 - 70
5 38 - 55 44 - 62 29 - 60 29 - 52
2 23 - 40 27 - 45 20 - 45 20 - 40
1,18 18 - 33 22 - 38 17 - 40 15 - 33
0,425 11 - 24 13 - 27 12 - 31 10 - 24
0,075 4 - 12 5 - 12 5 - 15 4 - 12 Aggregate strength
Soluble salt content For aggregate used under a surface treatment, soluble salt content is assessed in accordance with /7-11/.
Field density requirements
4
of MDD BS-Heavy
Nominal value: min 100%
Material class
CRR
[% passing][% passing]
CRS
335
Nominal value: min 88%
30
1) It is emphasised that Atterberg limits shall be measured according to CML test methods 1.2, 1.3 and 1.4. These methods follow BS procuders and utilise
BS equipment. Other laboratory test procedures are likely to give results that are not comparable with the given material requirements.
2.7
1.7
TFVdry: min110 kN
TFVsoaked : min75% of TFVdry TFVsoaked : min60% of TFVdry
of Aggregate Density
Crushed rock. Shall be made by crushing and
screening of fresh quarried rock or clean, un-weathered
boulders of minimum 0.3 m diameter. All particles shall
be crushed, no soil fines allowed.
Crushed stone. Made by crushing and screening of
blasted rock, stones, boulders and oversize from natural
gravel. Min 50% by mass of particles larger than 5 mm
shall have at least one crushed face. Max 30% of
material passing 5 mm can be soil fines.
-
7/24/2019 Pavement & Material Design,Tanzania
75/185
Material CML test properties C2 C1 CM method
Earthworks quality soils/gravel
minUCS [MPa] 2,0 1,0 0,5 1.21
ICL - test 1.22
max PI after stabilisation [%]1)
8 8 8 1.2 and 1.3
Before stabilisation:
min CBRsoaked [%] at 95% MDD of BS-Heavy
max PI [%]1) 20 25 35 1.2 and 1.3
min 1.5 min 1.2 -
Particle size, dMAX
Aggregate strength TFVdry : min 50 kN - - 2.7
Field density Nominal value: min 97% of MDD BS-Heavy
Grading modulus*)
Nominal quality of source material - with requirements as given here
1)
It is emphasised that Atterberg limits shall be measured according to CML test methods 1.2, 1.3 and 1.4. These methods follow BS procuders and utilise BS equipment. Other laboratory test procedures are likely to give results that are not comparable with the given material requirements.
1.11
1.7
The content of organic matter should not exceed 0.5% - 1% - 2% for C2 - C1 - CM materials respectively.
Source material
Material class
d MAXto be max 2/3 of compacted layer thickness
Stabiliser content [ % design ] shall be minimum the initial consumption of lime (ICL) value
*) GM = [ 300 - (% passing 2mm) - (% passing 0.425mm) - (% passing 0.075mm) ] / 100
30 -20
Subbase quality soils/gravel
-
7/24/2019 Pavement & Material Design,Tanzania
76/185
curing membrane
cemented base course
Loose - 50 mm -granular layer tobe kept wet.
cemented subbase
-
7/24/2019 Pavement & Material Design,Tanzania
77/185
-
7/24/2019 Pavement & Material Design,Tanzania
78/185
Material properties DBM 40 DBM 30
CMLtestmethod
Dense bitumen macadam Dense bitumen macadam
Max nominal size 40 mm 30 mm
Grading, sievesizes [mm] % passing % passing
50 100 -
37.5 95 - 100 100 28 70 - 95 90 - 100
20 - 70 - 95
14 56 - 76 58 - 82
10 53 - 70 52 - 73
5 39 - 56 40 - 56 1.7
2 24 - 40 24 - 40
1,18 19 - 35 19 - 35
0,425 9 - 25 9 - 25
0,300 7 - 21 7 - 21
0,075 2 - 9 2 - 9
3.22
Type of bitumen
Aggregate strength
Layer thickness 80 - 200 mm 60 - 150 mm
Bitumen content nominally 4.0% nominally 4.5%
60/70 or 40/50 penetration grade
Material class
TFV soaked : min 75% of TFV dry TFV dry : min 110 kN
2.7
-
7/24/2019 Pavement & Material Design,Tanzania
79/185
Material LAMBS CML test properties Large aggregate mix for base course method
Aggregates shall be made by crushing of fresh rockor clean, large boulders with a diametre >0.3 m.
min 37.5
max 50
Shape of the grading min 0.4 *)
curve, n-value max 0.7
Aggregate TFVsoaked 24hrs: min 75% of TFVdry
strength TFVdry : min 110 kN
Aggregate LS [%] max 2 1.4
Filler content, pass. 0.075 mm [%] 5 - 8 1.7
Traffic TLC 20 and TLC 50: 40/50 pen. grade
Traffic TLC 1 to TLC 10: 60/70 pen. grade
Bitumen content [%] 3.5 to 4.5 to be determined in the mix design 3.22
Mix design Shall be carried out in accordance with Ref/7- 4/
min 1.5 x ( dMAX), preferably 2 x ( dMAX)80 - 200 mm compacted thickness
3.5
Aggregate type
Bitumen grade
Layer thickness
2.7
Max particle size, dMAX [mm]
1.7
Water absorption [%] max 3 3.13
-
7/24/2019 Pavement & Material Design,Tanzania
80/185
Material CMLtestmethod properties PM 80 PM 60 PM 30
Max nominal size [mm] 80 60 30
125 100 50
The layer thickness of the penetration macadam should correspond with theaggregate fraction in order to obtain stability of the layer.
Bitumen spray rate [l/m2]
*)3 - 4 3 - 4 2 - 3
3.5 Bitumen type 80/100 or 60/70 penetration grade
Aggregate strength TFVsoaked : min 75% of TFVdry TFV dry : min 110 kN 2.7
Grading, sieve Main fraction sizes [mm] % passing % passing % passing
100 100 - -
75 75 - 100 100 -63 - 80 - 100 -
50 0 - 50 0 - 50 -37,5 0 - 25 0 - 25 100 2.3
28 0 - 5 0 - 5 80 - 10020 - - 0 - 50
14 - - 0 - 2510 0 - 5
Flakiness Index - - 35
Grading, sieve Key stone *)
sizes [mm] % passing % passing % passing
50 100 - -37,5 85 - 100 100 -
28 0 - 50 85 - 100 -20 0 - 25 0 - 50 100
14 0 - 5 0 - 25 85 - 100 2.3
10 - 0 - 5 0 - 55
6.3 - - 0 - 25 5 - - 0 - 10
Flakiness Index - 35 35
Material class
Layer thickness [mm]
*) Requirements for alternative use of a bituminous mix instead of key stone are set out in the text.
2.4
2.4
-
7/24/2019 Pavement & Material Design,Tanzania
81/185
-
7/24/2019 Pavement & Material Design,Tanzania
82/185
Material Material class
propertiesFBMIX
CML test
Foamed bitumen mix method
Aggregate source Natural gravel or crushed material, free from lumps of clay or other deleterious matter.
PI [%]1) max 14 before admixture of bitumen 1.2 and 1.3
CBRsoaked [%] min 30 before admixture of bitumen, tested at 95 % MDD of BS-heavy 1.11
Aggregate TFVsoaked: min 75% of TFVdry
strength Traffic TLC 3 and TLC 10: TFVdry : min 110 kN
Traffic TLC 1 and lower: TFVdry: min 80 kN
Grading, sievesizes [mm] % passing
37,5 10028 80 - 10020 60 - 9510 42 - 785 30 - 652 20 - 50
0,425 10 - 300,075 5 - 15
E-Modulus [MPa] min 1600, measured by indirect tensile strength, tested at 29oC 3.21
Marshall stability [N] min 6000 tested at 40oC
Marshall flow [mm] 2 - 4
Moisture content at min: mix design moisture less 1.5% points
the time of laying [%] max: mix design moisture plus 0.5% points
Type of bitumen 80/100 or 150/200 penetration grade 3.5
Adhesion agents Approved adhesion agents shall be admixed at min 0.5% by weight of bitumen
Bitumen content Consumption, residual bitumen: 80 to 100 litres per m3of compacted material 3.22
Field density min 96% of Marshall dry density
1) It is emphasised that Atterberg limits shall be measured according to CML test methods 1.2, 1.3 and 1.4. These methods follow
BS procuders and utilise BS equipment. Other laboratory test procedures are likely to give results that are not comparable with the given material requirements.
1.1
2.7
1.7
3.18
-
7/24/2019 Pavement & Material Design,Tanzania
83/185
MaterialMaterial class
CML test
properties BEMIXmethod
Bitumen emulsion mix
Aggregate source Natural gravel or crushed material, free from lumps of clay or other deleterious matter.
PI [%]1) max 8 before admixture of bitumen 1.2 and 1.3
CBRsoaked [%] min 30 before admixture of bitumen, tested at 95 % MDD of BS-heavy 1.11
Aggregate TFVsoaked : min 75% of TFVdry
strength Traffic TLC 3: TFV dry : min 110 kN
Traffic TLC 1 and lower: TFVdry : min 80 kN
Grading, sievesizes [mm] % passing
37,5 10028 80 - 10020 60 - 9510 35 - 705 25 - 502 18 - 35
0,425 10 - 250,075 5 - 8
E-Modulus [MPa] min 1200, measured by indirect tensile strength, tested at 29oC 3.21
Marshall stability [N] min 4500 tested at 40oC
Marshall flow [mm] 2 - 4
Moisture content at min: mix design moisture less 1.5% points
the time of laying [%] max: mix design moisture plus 0.5% points
Type of base bitumen 80/100 or 150/200 penetration grade 3.5
Bitumen content Consumption, residual bitumen: 80 to 100 litres per m3of compacted material 3.22
Field density min 96% of Marshall dry density
1)It is emphasised that Atterberg limits shall be measured according to CML test methods 1.2, 1.3 and 1.4. These methods follow
BS procuders and utilise BS equipment. Other laboratory test procedures are likely to give results that are not comparable with the given material requirements.
1.1
2.7
1.7
3.18
-
7/24/2019 Pavement & Material Design,Tanzania
84/185
-
7/24/2019 Pavement & Material Design,Tanzania
85/185
-
7/24/2019 Pavement & Material Design,Tanzania
86/185
-
7/24/2019 Pavement & Material Design,Tanzania
87/185
-
7/24/2019 Pavement & Material Design,Tanzania
88/185
Project appraisal
Environment
Cross Section,Shoulders and Drainage
Traffic
Subgrade
Problem Soils
Pavement Materials
DESIGNELEMENTS
PavementRehabilitation
BituminousSurfacings
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
89/185
granular
granular
time and traffic
riding quality
rut depth
cracking
granular
cemented
traffic
deformation
deflection
curvature
post-cracked phasepre-cracked influenceof waterphase
-
7/24/2019 Pavement & Material Design,Tanzania
90/185
bituminous mix
granular or cemented
time and traffic
riding quality
rut depth
cracking
cemented
cemented (preferred)
time and traffic
riding quality
rut depth
cracking
penetration macadam
granular or cemented
time and traffic
riding quality
deformation
cracking
-
7/24/2019 Pavement & Material Design,Tanzania
91/185
-
7/24/2019 Pavement & Material Design,Tanzania
92/185
-
7/24/2019 Pavement & Material Design,Tanzania
93/185
-
7/24/2019 Pavement & Material Design,Tanzania
94/185
< 0.2 0.2 - 0.5 0.5 - 1.0 1 - 3 3 - 10 10 - 20 20 - 50
G45
150mm
Basecourse
150mm
G80
150mm
G25
150mm
Subgrade
C1G45
CBR >15%
G45
150mm
Subbase
1)
C1
200mm
ST
AC
ST
TLC 20 TLC 50
GranularBase course type:
AC50mm
applicable)
TLC 10TLC 02 TLC 05
2)
CRR
200mm
G60 G80
150mm
(not applicable)
150mm
AC50mm
100mm
CRRCRR
asbelow
CRS
150mm
150mm
150mm
asbelow
200mm
+150mm
150mm
C2200mm
CM
For the heavy Traffic Load
For the heavy Traffic Load
General requirements
below
as
as
below
General requirements
asbelow
asbelow
asbelow
General requirements
Classes (TLC 05-Hto TLC 20-H) (notCRS
(not
applicable)
below
ST
CRS
125mm
ST ST
asbelow
as
Heavy Traffic Load Classes (-H) apply for
For the heavy Traffic Load
loaded to above13 tonnes.
Surfacing
Classes (TLC 05-Hto TLC 20-H)
Traffic Load Classes (million E80) E80 >0.2 million under conditions where
TLC 3
Material requirements:
Climatic zones: layers or base course:/Chapter 7/ Dry / Moderate
Bituminous surfacings:/Chapter 10/-
more than 50% of E80 comes from axles
-
- Granular or cemented materials for subbase
TLC 1
- Surface treatments, carriageway:
- Shoulders: /Chapter 10.7/
Traffic:- Traffic Load Classes, including the heavy ( -H)
classes: /Chapter 4/ Subgrade design:
- Design for CBR less than 15%: /Chapter 5/
Classes (TLC 05-Hto TLC 20-H)
/Chapter 10.2 to 10.4/
Asphalt concrete: /Chapter 10.8/
- Material standards of improved subgrade layers: /Chapter 5/
Surfacing design:
/Figure 2.1/
-
7/24/2019 Pavement & Material Design,Tanzania
95/185
< 0.2 0.2 - 0.5 0.5 - 1.0 1 - 3 3 - 10 10 - 20 20 - 50
200mm
- Surface treatments, carriageway:
For the heavy Traffic Load
Heavy Traffic Load Classes (-H) apply for
Surfacing
Basecourse
E80 >0.2 million under conditions where
150mm
G45
150mm
G80
200mm
150mm
CRS
below
loaded to above13 tonnes.
below below
For the heavy Traffic Load
Classes (TLC 05-Hto TLC 20-H)
ST
G80
Subgrade
AC
AC
AC50mm
100mm
150mm
CRS
150mm
G45
asbelow
150mm
Subbase
1)
C2
G25
CBR >15%
200mm
CM
200mm
asbelow
C1
CRR
150mm
150mm
as
below
+150mm
as
CM C1
as
asbelow
125mm
CRR
150mm
CRS
STST
TLC 50
50mm
100mm
AC
AC
TLC 20
50mm
CRR
below
General requirements
Classes (TLC 05-Hto TLC 20-H)
as150mm
CRR
ST
150mm
General requirements
General requirements
For the heavy Traffic Load
Classes (TLC 05-Hto TLC 20-H)
(not
applicable)
(not
applicable)
(not
applicable)as
Base course type:
layers:/Chapter 5/
Surfacing design:
TLC 02 TLC 05 TLC 1 TLC 3
Traffic Load Classes (million E80) more than 50% of E80 comes from axles
TLC 10
Bituminous surfacings:/Chapter 10/ Wet-
/Chapter 10.2 to 10.4/- Shoulders: /Chapter 10.7/- Asphalt concrete: /Chapter 10.8/
Material requirements:- Granular or cemented materials for subbase Climatic zones:
layers or base course:/Chapter 7/
GranularSubgrade design:
- Design for CBR less than 15%: /Chapter 5/- Material standards of improved subgrade
Traffic:
- Traffic Load Classes, including the heavy (-H)lasses: /Chapter 4/
/Figure 2.1/
-
7/24/2019 Pavement & Material Design,Tanzania
96/185
< 0.2 0.2 - 0.5 0.5 - 1.0 1 - 3 3 - 10 10 - 20 20 - 50
150mm150mm
Subgrade
Subbase
1)
General requirements
(not
applicable)
CM
CBR >15%
G45G45
G45 C1
C1150mm
200mmC1
General requirements
For the heavy Traffic Load
G25
For the heavy Traffic Load
Basecourse
Surfacing
Classes (TLC 05-Hto TLC 20-H)
+150mm
CM
150mm150mm
CM
150mm
+125mm
AC100mm
ST STST
50mmAC
below AC
C1 C2C1
50mm
asbelow
as
as
150mm 150mmGeneral requirements
below belowClasses (TLC 05-Hto TLC 20-H)
ST
150mm 150mm 150mm 150mm
CM
ST
(not
applicable)
as
below
as
200mm
C1
125mm
as
below
For the heavy Traffic LoadClasses (TLC 05-Hto TLC 20-H)
asbelow(not
applicable)
below
as
below
as
below
C2 C2
as
Traffic:
- Traffic Load Classes, including the heavy ( -H) classes: /Chapter 4/
TLC 50
Subgrade design:- Design for CBR less than 15%: /Chapter 5/- Material standards of improved subgrade
layers: /Chapter 5/
Surfacing design:
Cemented
TLC 10 TLC 20
- Surface treatments, carriageway:/Chapter 10.2 to 10.4/
E80 >0.2 million under conditions where more than 50% of E80 comes from axles loaded to above13 tonnes.
Heavy Traffic Load Classes (-H) apply for
- Asphalt concrete: /Chapter 10.8/
- Bituminous surfacings:/Chapter 10/
- Granular or cemented materials for subbase Material requirements:
layers or base course:/Chapter 7/
- Shoulders: /Chapter 10.7/
Base course type:
TLC 02 TLC 05 TLC 1 TLC 3
Traffic Load Classes (million E80)
AllClimatic zones:
/Figure 2.1/
-
7/24/2019 Pavement & Material Design,Tanzania
97/185
< 0.2 0.2 - 0.5 0.5 - 1.0 1 - 3 3 - 10 10 - 20 20 - 50
150mm
FBMIX
DBM 30
DBM 40
DBM 30
FBMIX FBMIX
CM
CM
CM
150mm
200mm200mm
G45G45G45
60mm
DBM 40
DBM 30
BEMIX BEMIX BEMIX BEMIX
DBM 30
FBMIX
ST ST
125mm+
125mm
LAMBS LAMBS LAMBS
80mm
ACAC50mm
200mm175mm
LAMBS
DBM 40
50mm
STST
TLC 20 TLC 50TLC 10
100mm125mm
Subbase1)
200mm
150mm
Subgrade
G45G45
CBR > 15%
150mm
this pavement type.
DBM 30
ST
Alternative material types: FBMIX
Basecourse
S
urfacing
LAMBS
DBM 40 DBM 40
TLC 02 TLC 05 TLC 1 TLC 3
Traffic Load Classes(million E80)No special pavement design alternatives are required for the heavy Traffic LoadClasses (TLC 05-Hto TLC 50-H )for
All
Base course type:
layers: /Chapter 5/
Surfacing design:-
Climatic zones:
- Bituminous base course: /Chapter 7/
Bituminous
mix- Asphalt concrete: /Chapter 10.8/
Surface treatments, carriageway: /Chapter 10.2 to 10.4/-
- Design for CBR less than 15%: /Chapter 5/- Material standards of improved subgrade
Traffic:- Traffic Load Classes:/Chapter 4/
Subgrade design:
Shoulders: /Chapter 10.7/
Material requirements:
- Granular or cemented materials for subbase layers:/Chapter 7/
- Bituminous surfacings: /Chapter 10/ /Figure 2.1/
-
7/24/2019 Pavement & Material Design,Tanzania
98/185
< 0.2 0.2 - 0.5 0.5 - 1.0 1 - 3 3 - 10 10 - 20 20 - 50
TLC 02 TLC 05 TLC 1 TLC 3 TLC 10 TLC 20
150mm125mm
+
150mm
+
125mm
50mm
PM60
50mm
100mm125mm
PM80
CMCM CMCM
C1150mm200mm
150mm
50mm
PM30Basecourse
PM80
AC50mm
STST
100mm
AC
PM30 PM60
G45
150mm
G45
150mm
ST
CBR > 15%
C1
Subgrade
Subbase
1)
CM
125mm 125mm
Surfacing
Traffic Load Classes(million E80)
TLC 50
are required for the heavy Traffic LoadClasses (TLC 05-Hto TLC 50-H)forthis pavement type.
No special pavement design alternatives
PM80
AC100mm100mm
AC
Penetration
Traffic:
Subgrade design:
layers: /Chapter 5/
- Traffic Load Classes:/Chapter 4/
Shoulders:/Chapter 10.7/- Asphalt concrete:/Chapter 10.8/-
- Design for CBR less than 15%: /Chapter 5/- Material standards of improved subgrade
Macadam
Base course type:
AllClimatic zones:- Bituminous surfacings: /Chapter 10/
- Penetration Macadam: /Chapter 7/
Surfacing design:- Surface treatments, carriageway: /Chapter 10.2 to 10.4/
Material requirements:
- Granular or cemented materials for subbase layers:/Chapter 7/
/Figure 2.1/
-
7/24/2019 Pavement & Material Design,Tanzania
99/185
-
7/24/2019 Pavement & Material Design,Tanzania
100/185
Project appraisal
Environment
Pavement Design-
New Roads
Cross Section,Shoulders and Drainage
Traffic
Subgrade
Problem Soils
Pavement Materials
DESIGNELEMENTS
BituminousSurfacings
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
101/185
-
7/24/2019 Pavement & Material Design,Tanzania
102/185
Carry out desk study
Start Carry out initial assessment ofpavement condition
Establish homogenous sections
based on initial assessment ofpavement condition
Carry out structural surveys asrequired based on the detailedcondition survey
Carry out detailed condition surveyif required in accordance with/Fig. 9.2/
Assess each homogenous sectionaccording to/Fig 9.2/
Re-assess demarcation intohomogenous sections based on allavailable data
Carry out pavement rehabilitationdesign for each homogenoussection
Combine sections with similarrehabilitation measures intopractical lengths for construction
-
7/24/2019 Pavement & Material Design,Tanzania
103/185
YES NO
NO YES
NO
YES
NO
YES
Any possibilitiesof salvaging the
pavement ?
Determine
subgrade CBR/Chapter 5/
Design full pavement
reconstruction without anyfurther investigation of the
section./Chapter 9.3.3/
Carry out detailed condition
surveys: - rutting
- roughness - surface defects
/Chapter 9.1.4/
Start
Determine the need forstructural surveys:
- DCP
- deflection - sampling (lab. testing)
/Chapter 9.1.4/
Traffic
projection/Chapter 9.1.2/
Recommend correctivemeasures. Further
investigation of the section isnormally not necessary.
Section withno distress ?
Section with
only localiseddistress ?
Section withonly surface
defects ?
Establish the cause of thelocalised distress, if necessarycarry out additional fieldtesting.
Traffic
projection/Chapter
9.1.2/
-
7/24/2019 Pavement & Material Design,Tanzania
104/185
-
7/24/2019 Pavement & Material Design,Tanzania
105/185
-
7/24/2019 Pavement & Material Design,Tanzania
106/185
-
7/24/2019 Pavement & Material Design,Tanzania
107/185
RUTTING: SOUND WARNING or SEVERE WARNING or SEVERE
CRACKING: WARNING or SEVERE SEVERE SOUND or WARNING
If rutting is due to shoving in the asphalt:carry out special investigations.
Cons ider whether full reconstruc tion Cons ider whether full reconstruc tionapplies/Chapter 9.3.3/ applies/Chapter 9.3.3/
NO
YES
NO
YES
Structural number method/Chapter 9.2.2/, or (for confirmation) Maximum deflection method /Chapter 9.2.1/
Mechanistic method /Chapter 9.2.3/
Select appropriate rehabilitation option /Chapter 9.3/ and consider options to prevent reflective cracking if applicable /Chapter 9.4/
Major mode of distress
Rehabilitation design method
Design traffic loading is less than
10 million E80?
Good correlation rutting / deflection, orroughness / deflection?
-
7/24/2019 Pavement & Material Design,Tanzania
108/185
-
7/24/2019 Pavement & Material Design,Tanzania
109/185
YES
NO
YES
NO
Establish homogenous
sections. (The CUSUM
method in /Appendix A8.3/may be used).
Measure and calculate design
deflection for each
homogenous section.
Determine expected pavement
life (total E80)
/Fig. 9.5/
Maximum deflection methoddoes not apply.
Past E80 larger
than expected
pavement life?
Calculate residual capacity:= expected capacity - past E80
Residual life
larger than
design traffic
loading?
No strengthening is required
based on the maximum
deflection method.
Determine target deflection.
/Fig. 9.5 or /Fig. 9.6/
Determine requiredstrengthening, SNdiff
/Fig. 9.7/
Select overlay alternative as
appropriate.
/Table 9.9/
Determine traffic loading:
- past E80
- future E80 (design traffic loading)
-
7/24/2019 Pavement & Material Design,Tanzania
110/185
-
7/24/2019 Pavement & Material Design,Tanzania
111/185
-
7/24/2019 Pavement & Material Design,Tanzania
112/185
TLC 05 TLC 1 TLC 3 TLC 10 TLC 20
Critical condition. 90%confidence in achieving life
167
154
142
129
116
103
90
77
64
51
39
2613
0.2 0.3 0.5 1.0 1.5 2.0 3.0 5.0 10 15 20 30
Equivalent standard axles, E80 [ x 106 ]
De
flection
[mm
x10
2]
0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6
0.8
0.6
0.4
0.2
0.50
0.80
1.60
2.20
Targetdeflection[mm]
Design deflection, measured [ mm ]
Structuralnumber,SNdiff
1.20
-
7/24/2019 Pavement & Material Design,Tanzania
113/185
-
7/24/2019 Pavement & Material Design,Tanzania
114/185
-
7/24/2019 Pavement & Material Design,Tanzania
115/185
-
7/24/2019 Pavement & Material Design,Tanzania
116/185
-
7/24/2019 Pavement & Material Design,Tanzania
117/185
*) Asphalt concrete Bituminous mix Penetration Granular baseoverlay for base course 1) macadam 2) course 3)
< 0.50
Only TLC 10 or lower
Only TLC 10 or lower
Only TLC 10 or lower
Only TLC 10 or lower
CRR 200 mm
Bit. 100 mm
ACPM 60 100 mm
100 mmPM 60
80 mm
ST
PM 80
80 mm
125 mm
ST
50 mm
ST
2,25
2,00
Bit.
ST
AC Bit.
50 mm50 mmPM 30
Apply a surface treatment or do nothing depending on site conditions.
CRR
ST
150 mm
ST
PM 30 50 mm
100 mmBit. 80 mm
ST
AC 60 mm
AC
PM 60
alternatively:
alternatively:
alternatively:
alternatively:
alternatively:
alternatively:
alternatively:
PM 80
ST
AC 100 mm
PM 60
50 mm
100 mm
125 mmPM 80
ST
140 mmBit.
AC
50 mm
50 mm
ST
100 mm
Bit.
AC60 mm
50 mm
AC 50 mm
PM 80 125 mm
ST
AC
200 mm
AC 50 mm
AC 50 mm
125 mm
50 mm
CRR 150 mm
CRR
ST
200 mm
AC
0,50
CRR
ST
PM 30 50 mm
1,00
1,25
1,50
120 mm
ST
*) Select the nearest of the given values for SN diffSN diff
0,75
Overlay alternatives
AC 40 mm
AC
PM 30 50 mm
1,75
AC 50 mm
PM 60 100 mmBit.
PM 60 100 mmAC 120 mm2 mm
100 mm
PM 60Bit. 100 mm
AC
130 mm
50 mm
ST
PM 60
-
7/24/2019 Pavement & Material Design,Tanzania
118/185
-
7/24/2019 Pavement & Material Design,Tanzania
119/185
-
7/24/2019 Pavement & Material Design,Tanzania
120/185
-
7/24/2019 Pavement & Material Design,Tanzania
121/185
Project appraisal
Environment
Pavement Design-
New Roads
Cross Section,Shoulders and Drainage
Traffic
Subgrade
Problem Soils
Pavement Materials
DESIGNELEMENTS
PavementRehabilitation
Gravel RoadsSTRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
122/185
Asphalt Concrete *)
Double Surface Dressing
Double Otta Seal
Single Otta Seal with a Sand Cover Seal
Single Surface Dressing with a Sand Cover Seal
Double Sand Seal
32 11 125 640 1
Years
Type of surfacing 13 147 8 9 10
-
7/24/2019 Pavement & Material Design,Tanzania
123/185
-
7/24/2019 Pavement & Material Design,Tanzania
124/185
-
7/24/2019 Pavement & Material Design,Tanzania
125/185
-
7/24/2019 Pavement & Material Design,Tanzania
126/185
-
7/24/2019 Pavement & Material Design,Tanzania
127/185
-
7/24/2019 Pavement & Material Design,Tanzania
128/185
-
7/24/2019 Pavement & Material Design,Tanzania
129/185
-
7/24/2019 Pavement & Material Design,Tanzania
130/185
MaterialCML test
properties method AADT>100: TFVsoaked: min. 75% of TFVdry For AADT100: TFVdry: min. 110 kN For AADT
-
7/24/2019 Pavement & Material Design,Tanzania
131/185
Sieve sizes Coarse grading1)
Medium grading1)
CML test
[mm] [% passing] [% passing] method
20 100 100
14 60 - 82 68 - 94
10 36 - 58 44 - 73
5 10 - 30 19 - 42 1.7
2 0 - 8 3 - 18
1,18 0 - 5 1 - 14
0,425 0 - 2 0 - 6
0,075 0 - 1 0 - 2
1)These grading envelopes are given for the the purpose of proper design of the seal and are not material requirements for aggregate.
AADT at the time Type of bitumen of construction
The grading should be
altered for this application
150/200 normally
MC3000 in cold weather
80/100 penetration grade bitumen shall not be used in Otta Seal unless softened or cut back to meet the above requirements.
Softening to make 150/200: 3% - 5% softener is mixed with 95% - 97% 80/100 pen. grade bitumen. Softener can be apurpose-made petroleum destillate, alternatively engine oil, old or new.
The cutback bitumen grades can be made by blending 150/200 pen. grade bitumen on site using the following proportions:
MC3000: 5% - 8% kerosine mixed with 92% - 95% 150/200 pen. grade bitumen
MC800: 15% - 18% kerosine mixed with 82% - 85% 150/200 pen. grade bitumen
If the cutback grades are made directly from 80/100 pen. grade bitumen, then an additional 3% - points kerosine shall be used.
Diesel shall not be used for cutting back to MC grades. Circulation in the tank shall be carried out at least 1 hour after mixing.
Proper safety procedures shall be adhered to in the case cutting back on site is being done.
Type of Otta Seal
2nd layer 1,5 1,6 1,7 AADT
-
7/24/2019 Pavement & Material Design,Tanzania
132/185
-
7/24/2019 Pavement & Material Design,Tanzania
133/185
-
7/24/2019 Pavement & Material Design,Tanzania
134/185
-
7/24/2019 Pavement & Material Design,Tanzania
135/185
-
7/24/2019 Pavement & Material Design,Tanzania
136/185
-
7/24/2019 Pavement & Material Design,Tanzania
137/185
-
7/24/2019 Pavement & Material Design,Tanzania
138/185
Material CML test properties AC 20 AC 14 AC 10 method
Primarily b inder course. Wearing course in areas with Wearing course, but only under
Notes - use of the different Wearing course in severely normal traffic loading. conditions with moderate
mix types loaded areas Chapter 10.8.2. traffic loading.
Preferably to be surface dressed
when used as wearing course.
Layer thickness [mm] Compacted 50 - 80 Compacted 40 - 60 Compacted 30 - 40
Aggregate properties
3.13
Aggregate strength TFVsoaked : min 75% of TFVdryTFVdry : min 110 kN
2.7
The filler shall be hydrated lime, Portland cement, limestone dust or other suitable types proven to
1.7
% passing 0.075 mm: 70 - 100 %, all material shall pass the 0.600 mm sieve size
Grading, sieve sizes
[mm]
28 100
20 80 - 100 100
14 60 - 80 85 - 100 100
10 50 - 70 72 - 94 85 - 100
5 36 - 56 52 - 72 55 - 72
2,36 28 - 44 37 - 55 38 - 57 1.7
1,18 20 - 34 26 - 41 27 - 42
0,600 15 - 27 16 - 28 18 - 32
0,300 10 - 20 12 - 20 13 - 23
0,150 5 - 13 8 - 15 9 - 16
0,075 2 - 6 4 - 10 4 - 10
Bitumen type
Normal loading conditions: 60/70 or 40/50 penetration grade Severely loaded areas: Chapter 10.8.2 40/50 penetration grade, or modified binders
3.5
Marshall (2x75 blow)
mix requirements
Severely loaded areas: min 9000 Chapter 10.8.2
Traf fic TLC 20 and TLC 50: min 8000 max 18000
Traffic TLC 10 and TLC 3: min 7000 max 15000
Traffic TLC 1 and lower: min 4000 max 10000
Flow [mm] min 2 max 4 3.18
Air voids [%] min 3 max 6
Voids in Mineral Aggregate [%] min 14 for AC 20 min 15 for AC 14 min 16 for AC 10
Refusal lab. compaction Air voids shall be min. 3% after refusal lab. compaction for severely loaded areas Chapter 10.8.2.
Indirect tensile strength [kPa] min 800 tested at 25oC
3.20
3.21 Imersion index [%] min 75
Water absorption [%]
provided materials are carefully selected. Addition of a separate type of fines is normally needed.
[ % passing ]
give acceptable results in AC mixes under the prevailing conditions.
max 2
Stability [N]
Requirements for the filler
Mix type
Coarse aggregates shall be made of crushed fresh rock or stones. Fine aggregate, passing the
and free from soft or unsound particles, clay or other deleterious matter. Coral rock can be used
5 mm sieve, can be a material such as sand, gravel or crushed stone. All aggregate shall be durable Types of aggregate
-
7/24/2019 Pavement & Material Design,Tanzania
139/185
Nominal mix CML testmethod proportions
AC 20 AC 14 AC 10 Aggregate [%] 95 94,5 94 Bitumen [%] 5 5,5 6
3.18
Normal loading conditions: 60/70 or 40/50 penetration grade
Severely loaded areas: 40/50 penetration grade or modified binders3.5
Asphalt Concrete
Type of bitumen
-
7/24/2019 Pavement & Material Design,Tanzania
140/185
-
7/24/2019 Pavement & Material Design,Tanzania
141/185
Project appraisal
Environment
Pavement Design-
New Roads
Cross Section,Shoulders and Drainage
Traffic
Subgrade
Problem Soils
Pavement Materials
DESIGNELEMENTS
PavementRehabilitation
BituminousSurfacings
STRUCTURAL
DESIGN
Comparison of alternatives andselection of design
Refinement of design, if required
Ch
Ch
-
7/24/2019 Pavement & Material Design,Tanzania
142/185
-
7/24/2019 Pavement & Material Design,Tanzania
143/185
-
7/24/2019 Pavement & Material Design,Tanzania
144/185
Erodible materials
0 10
200
100
0
20
Good
Ravels and corrugates
30
Ravels
Slippery
270
40
Good, but may be dusty
ShrinkageProduct,SP
Grading Coefficient, GC
500
400
300
400
120
16 34
-
7/24/2019 Pavement & Material Design,Tanzania
145/185
Moderate or dry Wet climatic zones climatic zones
1) Classification S15, S7 and S3 and requirements for G7 materials are given:/Chapter 5 Subgrade/.
Subgrade classes1)
GW
100mm
150mm200mm
S3S15 orS7
100mm
GW
( none )G7
subgrade
layer
Gravelwearingcourse
Improved
100mm
GW
G7
1) Classificationsubgrade classes S3, S7 and G15 and requirements for G7 and G15 materials are given:/Chapter 5 Subgrade/.2) Maximum 50% heavy vehicles is assumed. Heavy vehicles are those having an un-laden weight of more than
3 tonnes, or buses with a seating capacity of 40 or more: /Chapter 4 Traffic/.
S7 1)
G71)150 G7 1)G7 1)
150 GW
G15 1)
300150 G71)
150 G151)
GW
100 mmGWGW
G15 1)
Dry / Moderate Dry / Moderate Dry / ModerateWet
G151)100
GWGW150
Wet
GW 150
G71) 200
GW 150
G151) 200G151) 200
AADT 2)
S15 1) GW GW
< 20 20 - 100 100 - 300
150 mm
150 mm 150 mm 150 mm
150 mm
150 mm150 mm
S3 1)
climatic zones
150
GW
300
Wetclimatic zones climatic zones climatic zones climatic zones climatic zones
G7 1)
150150
GW
mm
mm mm
mm
mm
mm
-
7/24/2019 Pavement & Material Design,Tanzania
146/185
-
7/24/2019 Pavement & Material Design,Tanzania
147/185
-
7/24/2019 Pavement & Material Design,Tanzania
148/185
-
7/24/2019 Pavement & Material Design,Tanzania
149/185
-
7/24/2019 Pavement & Material Design,Tanzania
150/185
-
7/24/2019 Pavement & Material Design,Tanzania
151/185
-
7/24/2019 Pavement & Material Design,Tanzania
152/185
-
7/24/2019 Pavement & Material Design,Tanzania
153/185
CML test method,reference number
Tests on Soils and Gravels1.1 Moisture Content BS1377:Part 2:19901.2 Liquid Limit (Cone Penetrometer) BS1377:Part 2:19901.3 Plastic Limit & Plasticity Index BS1377:Part 2:1990
1.4 Linear Shrinkage BS1377:Part 2:1990
1.5 Particle Density Determination - Pyknometer BS1377:Part 2:19901.6 Bulk Density for undisturbed samples BS1377:Part 2:19901.7 Particle Size Distribution - Wet sieving BS1377:Part 2:19901.8 Particle Size Distribution - Hydrometer Method BS1377:Part 2:19901.9 Compaction Test - BS Light and BS Heavy BS1377:Part 4:19901.10 CBR Test - One point method BS1377:Part 4:1990
BS1377:Part 4:1990 andTMH1:method A8:1986
1.12 Consolidation Test - Oedometer BS1377:Part 5:19901.13 Triaxial Test BS1377:Part 7:19901.14 Shear Box Test BS1377:Part 7:19901.15 Permeability Test - Constant Head BS1377:Part 5:1990
BS1377:Part 3:1990 and
NPRA 014 test 14.445
1.17 Crumb Test BS1377:Part 5:19901.18 pH Value (pH meter) BS1377:Part 3:1990
TMH1:method A14:1986 and
BS1924:Part 2:1990
TMH1:method A14:1986 and
BS1924:Part 2:19901.21 UCS of Stabilised Materials TMH1:method A14:1986
1.22 Initial Consumption of Lime - ICL BS1924:Part 2:1990
Tests on Aggregates and Concrete
2.1 Moisture Content of Aggregates BS812:Part 109:19902.2 Relative Density and Water Absorption BS812:Part 2:1975
2.3 Sieve Tests on Aggregates BS812:Part 103.1:19852.4 Flakiness Index (FI) and Average Least Dimension (ALD) BS812:Section 105.1:19892.5 Elongation Index BS812:Section 105.2:19902.6 Aggregate Crushing Value (ACV) BS812:Part 110:19902.7 Ten Percent Fines Value (TFV) BS812:Part 111:19902.8 Aggregate Impact Value (AIV) BS812:Part 112:19902.9 Los Angeles Abrasion Test (LAA) ASTM C535-89
2.10 Sodium Soundness Test (SSS) ASTM C88-902.11 Slump Test BS1881:Part 102:19832.12 Making of Concrete Test Cubes BS1881:Part 108:19832.13 Concrete Cube Strength BS1881:Part 116:1983
Tests on Asphalt and Bituminous Materials3.1 Pre-conditioning of Bitumen Samples Prior to Mixing or Tes ting NPRA 014 test 14.5113.2 Density of Bituminous Binders ASTM D70-973.3 Flash and Fire Point by Cleveland Open Cup ASTM D92-90
3.4 Thin-Film Oven Test (TFOT) ASTM D1754-873.5 Penetration of Bituminous Materials ASTM D5-86
3.6 Softening Point Test ASTM D36-70
3.7 Ductility ASTM D113-863.8 Viscosi ty Determination using the Brookfield Thermosel Apparatus ASTM D4402-913.9 Density and Water Absorption of Aggregates Retrieved on a 4.75 mm Sieve ASTM C127-883.10 Density and Water Absorption of Aggregates Passing the 4.75 mm Sieve ASTM C128-883.11 Calibration of Glass Pycnometers (0.5-1 litre) NPRA 014 test 14.59223.12 Mixing of Test Specimens; Hot Bituminous Mixes NPRA 014 test 14.5532
Determination of Maximum Theoretical Density of Asphalt Mixes
and Absorption of Binder into Aggregates3.14 Bulk Density of Saturated Surface Dry Asphalt Mix Samples ASTM D2726-963.15 Bulk Density of Paraffin-Coated Asphalt Mix Samples ASTM D1188-893.16 Bulk Density of Asphalt Mix Samples, Calliper Measurements NPRA 014 test 14.56223.17 Calculation of Void Content in Bituminous Mixes ASTM D3203 and AASHTO pp19-933.18 Marshall Test ASTM D1559-893.19 Marshall Mix Design ASTM D1559-89
3.20 Refusal Density Mix Design TRL Overseas Road Note 31, app. D:19903.21 Indirect Tensile Strength Test ASTM D3967 and NPRA 014 test 14.5543.22 Determination of Binder Content and Aggregate Grading by Extraction ASTM D2172-88, method B3.23 Effect of Water on Bituminous Coated Aggregates, Boiling Test ASTM D3625-96
ASTM D2041-95 and D4469-85
Reference to test methods
CBR Test - Three point method1.11
Preparation of Stabilised Samples for UCS1.19
Compaction Test - Stabilised Materials1.20
Organic Content - Ignition Loss Method1.16
Name of test
3.13
-
7/24/2019 Pavement & Material Design,Tanzania
154/185
-
7/24/2019 Pavement & Material Design,Tanzania
155/185
-
7/24/2019 Pavement & Material Design,Tanzania
156/185
-
7/24/2019 Pavement & Material Design,Tanzania
157/185
-
7/24/2019 Pavement & Material Design,Tanzania
158/185
-
7/24/2019 Pavement & Material Design,Tanzania
159/185
-
7/24/2019 Pavement & Material Design,Tanzania
160/185
-
7/24/2019 Pavement & Material Design,Tanzania
161/185
-
7/24/2019 Pavement & Material Design,Tanzania
162/185
-
7/24/2019 Pavement & Material Design,Tanzania
163/185
-
7/24/2019 Pavement & Material Design,Tanzania
164/185
-
7/24/2019 Pavement & Material Design,Tanzania
165/185
-
7/24/2019 Pavement & Material Design,Tanzania
166/185
-
7/24/2019 Pavement & Material Design,Tanzania
167/185
-
7/24/2019 Pavement & Material Design,Tanzania
168/185
-
7/24/2019 Pavement & Material Design,Tanzania
169/185
-
7/24/2019 Pavement & Material Design,Tanzania
170/185
-
7/24/2019 Pavement & Material Design,Tanzania
171/185
-
7/24/2019 Pavement & Material Design,Tanzania
172/185
CBR data
3
4 90%-ile
5 3,4
5 CBR DESIGN6 3 %
0
1
2
3
4
5
6
7
1 2 3 4 5
Test
CBR(%)
d=0.4
n = 5 testsd = 0.1 x (n-1)
= 0.4
CBR values plottedin ascending order
1 2 3
Subgrade class
G15
150mm
G15
150mm
G15Upper layer
Lower layer
Section
S3 S7 S7
not required
150mm
G7
150mm
CBR values plottedin ascending order
CBR data
68
9
9
9
11 90%-ile12 7,6
12 CBR DESIGN14 8 % 0
2
4
6
8
10
12
14
16
1 2 3 4 5 6 7 8 9
Test
CBR(%)
d=0.8
n = 9 testsd = 0.1 x (n-1)
= 0.8
-
7/24/2019 Pavement & Material Design,Tanzania
173/185
B C
Chainage Rutting Difference CUSUM
measured from average (Accumulated[Km] [mm] (A- B) values of C )
1 14 -1,2 -1,2
2 13 -0,2 -1,4
3 15 -2,2 -3,6
4 14 -1,2 -4,85 13 -0,2 -5,0
6 14 -1,2 -6,2
7 7 5,8 -0,4
8 9 3,8 3,4
9 8 4,8 8,2
10 13 -0,2 8,0
11 15 -2,2 5,8
12 18 -5,2 0,6
13 14 -1,2 -0,6
14 16 -3,2 -3,8
15 14 -1,2 -5,0
16 14 -1,2 -6,2
17 15 -2,2 -8,4
18 18 -5,2 -13,6
19 14 -1,2 -14,8
20 15 -2,2 -17,0
21 9 3,8 -13,222 10 2,8 -10,4
23 9 3,8 -6,6
24 12 0,8 -5,8
25 9 3,8 -2,0
26 11 1,8 -0,2
Average: A = 12,8
Homogenous sections
-20
-15
-10
-5
0
5
10
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Chainage
CUSUM
Plotting of CUSUM against Chainage
Interpretation of data:
A change of slope indicates change of conditions along
the data. Four distinct homogenous sections can be seenin the above chart.
-
7/24/2019 Pavement & Material Design,Tanzania
174/185
-
7/24/2019 Pavement & Material Design,Tanzania
175/185
Existing pavement: Material coefficients:/Table 9.4/
t1= 60 mm Asphalt concrete, severely cracked a1= 0.18
t2= 180 mm Natural gravel, PI = 10, CBR = 40% a = 0.10
t2= 150 mm Natural gravel, PI = 15, CBR = 15% a = 0.08
CBR = 8%
Calculations: /Chapter 9.2.2/
SNexist = (a1xt1) / 25.4 = (0.18 x60) / 25.4 = 0.43
Old AC a1= 0.18 t1=60mm
SNrequired = 2.35 /Table 9.5/ for TLC 10 and CBR=40
CBR = 40% a2 = 0.10 t2= 180mm
SNexist = [(a1xt1)+(a2xt2) ] / 25.4 = [(0.18 x60)+(0.10 x180)] / 25.4 = 1.33
SNdiff = SNrequired - SNexist = 2.75 - 1.33 = 1.42
SNrequired= 2.75 /Table 9.5/ for TLC 10 and CBR=15
CBR = 15% a3 = 0.08 t3 = 150mm
SNexist= [(a1xt1)+(a2 xt2)+(a3 xt3)] / 25.4 = [(0.18 x60)+(0.10 x180)+(0.08 x150)] / 25.4 = 1.61
SNdiff = SNrequired - SNexist = 3.30 - 1.61 = 1.69SNrequired = 3.30 /Table 9.5/for TLC 10 and CBR=8
CBR = 8%
SNdiff = SNrequired - SNexist = 2.35 - 043 =1.92 (highest, i.e. critical)
-
7/24/2019 Pavement & Material Design,Tanzania
176/185
AC 50 mm
PM 80 125 mm
Asphalt concrete Bituminous mix Penetration Granular baseoverlay for base course macadam course
3 )1 ) 2 )
Overlay alternatives
SNdiff The nearest value for SNdiff has been selected.
2,00
AC 50 mm
PM 80 125 mm
Alternatively:ST
AC 50 mm
Bit. 100 mm PM 60
AC 50 mm
PM 60 100 mmCRR 00 mm
100 mm
-
7/24/2019 Pavement & Material Design,Tanzania
177/185
New base course and surfacing to be selected in compliance with
Exitsing AC reprocessed, or removed, depending on chosen method.
Existing base course (and subbase) reprocessed to subbasein the new pavement.
/Chapter 8.3.2/depending on achieved quality of the new subbase.
Existing base course (and subbase)
Reprocessed AC
New base course
New surfacing
-
7/24/2019 Pavement & Material Design,Tanzania
178/185
-
7/24/2019 Pavement & Material Design,Tanzania
179/185
-
7/24/2019 Pavement & Material Design,Tanzania
180/185
-
7/24/2019 Pavement & Material Design,Tanzania
181/185
-
7/24/2019 Pavement & Material Design,Tanzania
182/185
-
7/24/2019 Pavement & Material Design,Tanzania
183/185
-
7/24/2019 Pavement & Material Design,Tanzania
184/185
-
7/24/2019 Pavement & Material Design,Tanzania
185/185