8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
1/23
PE08 - ReducingDeployment Time for
Substation IED Integration
and Control
Ken Roslan
Marketing Manager
661-716-5260
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
2/23
ProSoft Technology Company Overview
Privately Held Company Founded by Doug Sharratt
First products in 1988
HQ in Bakersfield, CA
Global Organization Over 110 employees worldwide
Strong application experience
Industrial communication
DNP-Org.
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
3/23
Our Solutions
Dec 12, 2006
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
4/23
Serial Protocols Modbus DF1, ASCII, DH485 DNP3.0
IEC 60870-5-101 & 103
Siemens 3964R Emerson FC
Foxboro Systronic
Ethernet Protocols EtherNet/IP Modbus TCP/IP IEC 60870-5-104
DNP3 Ethernet
ASCII Ethernet CC-Link
GE Global Data
Over +60 Protocols
o nson on ro e asys York Chiller
Specialty Modules C Programmable Gas Flow Computing InChassis PC
SCANport modules Profibus Modbus, Modbus Plus
Metasys N2
- e Open Ethernet Port C
Fieldbus Protocols HART Multidrop HART Analog Honeywell DE
Profibus DPV1
Modbus Plus Interbus
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
5/23
Agenda
Brief on IEC 61850IEDs
Data formats
Applications
Wind PowerHydro Electric Power
Future solutions
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
6/23
ModbusDNP
60870-5-101/104
60870-5-103
Profibus
Protocols used in power delivery today
LON
MVB
Proprietary
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
7/23
IEC 61850 vs...
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
8/23
IEC 61850 in other domains
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
9/23
What is IEC 61850 ?
As an international standard for substation automationsystems
IEC 61850 defines the communication between devicesin the substation and related system requirements it usesa publisher-subscriber concept
It describes a structure for addressing interoperability of
Common configuration language
Standardized object models and naming conventions
Self-describing devices
Standardized meaning of data
Standardized services and device behavior models Profiles for Control/SCADA, Protection messaging, Transducers
and I/O
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
10/23
Parts of IEC 61850
SCL Substation
Configuration
DefinedProtocols
Data Model
Language
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
11/23
IEC 61850 Protocol Suite
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
12/23
Intelligent Electric Device (IED)
Reference USA and 61850 For Dummies - Siemens Power Transmission &
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
13/23
Object-Oriented
IEC 61850 uses an object-oriented approach with Logical Nodes (LN)Describes the physical IED
Multiple logical Devices per IED
Multiple objects logical Nodes per Device
Data oint er lo ical NodeMultiple Attributes per Data point
Examples are all data of a circuit breaker contained in the Logical Node XCBR. Therefore, thesubstation or protection engineer identifies those objects. Logical Nodes have data, and all thedata have attributes
Attributes are related to the data called Pos, one attribute for diagnostic stVal, which indicatesthe position of a valve (off, on, intermediate-state, bad-state) and another attribute ctlVal for theopening and closing command (values: off, on).
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
14/23
Accessing Data
The Pos folder is of type Controllable Double Point (CDP) data
class. The CDP data class consists of 14 data fields (some aremandatory and must always be present, others are optional). TheStVal field contains the value of the CB
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
15/23
Where will IEC 61850 be used?
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
16/23
How will 61850 be used?
IEC 61850 will not replace ALL protocols in use now
As in industrial automation different applications require different types ofnetworks
IEC61850 was developed to create an open communicationenvironment in substations on the station and process level
Not to solve EVERY communication problem in the energy distributionindustry
More IEDs support the network protocol
Many utilities are in the process of migrating from proprietaryprotocols to the serial IEC-101/IEC-103 or the IEC-104.
The application of the new IEC61850 highly depends on customerspresent situation, and the suppliers migration strategy
What equipment is installed (network support??)Obsolescence issues to consider
Time/Cost involvement for upgrades
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
17/23
Substation Data
In a typical substation, all data attributes
(approximately 100) from each of the 50 IEDs aredesired at the PLC
Data is desired at the Station PLC (for decisionmaking) and at the SCADA system
Examples of data needs:Data gathered for Condition Based Monitoring purposes, todetect point of degradation of an aging mechanism
Checking SF6 gas insulation temperature
Alarm data with high precision of accuracy needed, todetermine which IED alarmed (GOOSEd) first
Control of bay-level switchgear -- interlocking &maintenance purposes
17
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
18/23
IEC 61400-25: Wind Power
61400-25 data objects are 61850 compatible
61400-25 services are nearly the same
- .than being based upon a DATA-SET, with 61400-25you have to subscribe to data for reporting.
61850 being used for some Wind Power installationsrather than 61400-25
18
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
19/23
IEC 61850-7-410: Hydro-electric Power
Extension of 61850 Part 7-4
63 additional Logical Nodes
3 additional Common Data Classes definedspecifically for Hydro
19
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
20/23
EtherNet/IP to IEC 61850 Gateway
IEC 61850 Pass-
throughconfiguration
Station or Bay Controller w/distributedgateway integrated controller
IEC 61850 NetworkConfiguration
IEC 61850 MMS/GOOSE
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
21/23
ProSoft 61850 Gateway Service Conformance
ProSofts 61850 Clientgateway supports theyellow-highlightedservices.
Blue rows are future
61850-7-2 ACSI Class desc.
Clause 6 Server Model
Clause 7 Association Model
Clause 8 Logical Device Model
Clause 9 Logical Node Model
Clause 10 Data Model
Clause 11 Data-Set Model
21
tems.
See ProSofts PICSstatement for details.
Clause 12 Substitution Model
Clause 13 Setting-Group-Control-Block
Clause 14 BRCB, URCB, Log
Clause 14 Log
Clause 15 GSE
Clause 16 Sampled ValuesClause 17 Control Model
Clause 18 Time & Time Synch
Clause 19 Naming Conventions
Clause 20 File Transfer Model
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
22/23
ProSofts 61850 Client gateway
61850 Client Gateway will connect to 60IEDs
Easy to configure
Information gathered from IEDconfiguration files (CID file), so userdoes not have to re-type information
. . ,Drag & Drop selection of IEDs dataattributes
Tag names automatically generated foryou
ODVA-compliant hardware with specificEtherNet/IP LEDs
22
-
8/6/2019 PE08 - Reducing Deployment Time for Substation IED Integration and Control
23/23
Questions