PEACE RIVER MANASOTA REGIONAL WATER SUPPLY AUTHORITY BOARD OF DIRECTORS MEETING August 5, 2020 ROUTINE STATUS REPORTS ITEM 6 Maintenance Facility & Warehouse Construction

Upload: others

Post on 08-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

PEACE RIVER MANASOTA REGIONAL WATER SUPPLY AUTHORITY BOARD OF DIRECTORS MEETING

August 5, 2020

ROUTINE STATUS REPORTS ITEM 6

Maintenance Facility & Warehouse Construction

Page 2: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

1

Maintenance and Warehouse Facility Construction - August 5, 2020

Project Status Report

Project: Maintenance Facility and Warehouse Construction

Date: August 5, 2020

Prepared by: Ford Ritz, PE, Project Manager

Project Description

The Maintenance Facility & Warehouse construction project was awarded to L. Cobb Construction Inc. of Wauchula, FL at the July 25, 2018 Authority Board Meeting for an amount not-to-exceed $2,544,280.24. This project will result in the construction of two buildings: a 4,225-sf office building and a 7,530-sf warehouse adjacent to the office (see below).

7,530-sf Maintenance Warehouse 4,225- sf Maintenance Office

Current status

Desoto County issued the Certificate of Occupancy on July 7, 2020. L. Cobb Construction, Inc. completed project Work, with the exception of several punch list items. The Engineer of Record determined that Substantial Completion had been obtained on July 14, 2020. The Office furniture and Warehouse shelving have been installed. Currently the Contractor is completing punch-list items and continuing to submit project close-out documentation. The Maintenance staff is looking forward to moving into the facility in the near future.

Page 3: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

2

Maintenance and Warehouse Facility Construction - August 5, 2020

May 2020

April 2020

Page 4: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

3

Maintenance and Warehouse Facility Construction - August 5, 2020

March 2020

January 2020

Page 5: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

4

Maintenance and Warehouse Facility Construction - August 5, 2020

November 2019

September 2019

Page 6: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

5

Maintenance and Warehouse Facility Construction - August 5, 2020

July 2019

May 2019

Page 7: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

6

Maintenance and Warehouse Facility Construction - August 5, 2020

February 2019

Page 8: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

7

Maintenance and Warehouse Facility Construction - August 5, 2020

Project History Briefing

Project: Maintenance Facility and Warehouse Construction

Date: August 5, 2020

Prepared by: Ford Ritz, PE, Project Manager

General

The following information summarizes the historical milestones and events of the Maintenance Facility and Warehouse Construction Project.

October 4, 2017 Authority Board of Directors authorizes Design and Permitting

Services to AECOM, Inc. for the Maintenance Facility and Warehouse.

May 9, 2018 Invitation to Bid is advertised

June 20, 2018 Bid Opening

June 29, 2018 Engineer/Architect of Record Bid Evaluation and Recommendation of Award

June 29, 2018 Authority staff publishes Notice of Intended Decision

July 25, 2018 Authority Board of Directors awards contract to L. Cobb

Construction, Inc. of Wauchula, FL.

January 22, 2019 Authority issues Notice-to-Proceed to L. Cobb Construction, Inc.

October 2, 2019 Change Order 1 for 33-calendar days Board Approved

April - May 2019 This period regularly scheduled Project Progress Meetings have been held every two weeks. The meetings have been attended by Authority, L. Cobb and AECOM staff. The Maintenance Office footings, stem walls, slab and block have been completed. The Warehouse footings and slab preparation have been completed. MEPF (utilities under slabs) installation has been completed. Civil site work is ongoing. Materials have been tested per specifications. The Contract is on schedule and within budget.

June - July 2019 This period regularly scheduled Project Progress Meetings have

been held every two weeks. The meetings have been attended by the Authority, L. Cobb and AECOM staff. The Maintenance

Page 9: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

8

Maintenance and Warehouse Facility Construction - August 5, 2020

Office masonry walls have been completed and grout filled, roof trusses have been assembled and installed, and roof decking installation is near complete. The Warehouse concrete slab has been completed and installation of columns for the warehouse is underway. This period the Contractor completed installation of the storm drainage piping, continued electrical duct bank installation and cut down the parking area for subbase and base installation. The Contract is on schedule and within budget. The project is about 30% complete.

Aug. – Sep. 2019 This period regularly scheduled Project Progress Meetings have

been held every two weeks. The meetings have been attended by the Authority, L. Cobb and AECOM staff. The Maintenance Office masonry walls have been completed and grout filled, roof trusses have been installed, and roof decking is complete. Interior plumbing and electrical is underway. The Warehouse frame has been erected and the siding is being installed. This period the Contractor completed installed the electrical duct bank to the lift station and placed and compacted the parking area base aggregate. There was above normal rainfall recorded on site during July and August. The Contract is within budget and about 45% complete.

Change Order 1 Due to above normal rainfall in July and August (11-inches above normal average) and based upon negotiations with L. Cobb, 30- calandar days for unforeseen weather was agreed upon for July and August. An additional 3-calendar days for work was also recommended by AECOM (Engineer of Record). If Board approved, Change Order 1 will add a total of 33-calendar days to the Contract. Revised Substantial Completion and Final Completion dates will be February 23, 2020 and April 23, 2020 respectively.

Oct. – Nov. 2019 This period regularly scheduled Project Progress Meetings have

been held every two weeks. The meetings have been attended by the Authority, L. Cobb and AECOM staff. Maintenance Office; This period the roof installation (dry in) is 95% complete. When the office is “dried in” the Contractor will complete interior electrical, drywall, HVAC and install exterior store front windows and doors. Warehouse; Roof insulation was completed and the standing metal roof is 95% complete. Exterior block work is 95% complete.

Site Work; Contractor completed berm/sod along the eastern side of the site. Preparations were made for installation of the lift station and force-main alignment. The Contractor performed hot

Page 10: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

9

Maintenance and Warehouse Facility Construction - August 5, 2020

taps for the future water and sewer connections, respectively.

The Contract is within budget and about 55% complete.

Change Order 1 Board Approved October 2, 2019. Change Order 1 added a total of 33-calendar days to the Contract. Revised Substantial Completion and Final Completion dates will be February 23, 2020 and April 23, 2020 respectively.

Dec. 19 – Jan. 2020 This period regularly scheduled Project Progress Meetings have

been held every two weeks. The meetings have been attended by the Authority, L. Cobb and AECOM staff. On December 18, 2019 AECOM specialty engineers conducted a site walk through. Maintenance Office; The Contractor continued exterior masonry, installed window and door frames and began installation of sidewalks. Electrical, plumbing, and drywall installation was continued. Additionally, HVAC ductwork and ceiling fans and were installed and insulated, and air handling units were placed into the mechanical room for future connection.

Warehouse; Electrical, installation of interior wall and ceiling liners, as well as, work on the air-conditioned space/room, was continued. Exterior wall panels around the air-conditioned space were completed. Exterior wall panels were cut to fit for sill block installation.

Site Work; The lift station (electrical and mechanical not completed) and force-main were installed. The force main was connected to the County sanitary sewer system. The water service for the Maintenance Facility was installed and connected to the existing water main. Installation of the backflow preventer is underway.

The Maintenance Facility project is on budget, about 65% complete, and scheduled to be finished in the spring of 2020.

Feb. – March 2020 This period regularly scheduled Project Progress Meetings have been held every two weeks. The meetings have been attended by the Authority, L. Cobb and AECOM staff

Maintenance Office; The Contractor, completed the metal roof and gutter, installed window glass and continued installation of sidewalks and curbing and began installation of exterior wall panels. Interior - electrical, and plumbing, work was continued and drywall installation was completed.

Page 11: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

10

Maintenance and Warehouse Facility Construction - August 5, 2020

Interior painting and tile work in the bathrooms is underway.

Warehouse; Electrical panels were installed. The air-conditioned space/room, walls were insulated. Exterior trim was started.

Site Work; The lift station electrical, mechanical work, and civil work was continued. The force-main was pressure tested. The water service and backflow preventer, were also pressure tested and disinfected. Bollard were installed around the Warehouse.

The Maintenance Facility project is on budget, about 70% complete, with projected completion date in late spring 2020.

April – May 2020 This period includes the timeframe impacted by the Covid-19

virus quarantine. Construction was largely unaffected with the construction crews observing safe distancing, wearing PPE and voluntary self-isolating if they fell ill out of an abundance of caution. Delivery of some materials (indoor carpeting) has suffered minor delays due to the widespread virus impacts but substantial completion of the structure is scheduled for late May. The parking areas were paved in the first week of May and that brought an end to major construction work. Work ongoing at this time includes finishing activities such as final electrical/lighting work, ceiling panels and installing plumbing fixtures in restrooms. In the warehouse structure, outside canopies, skylights and ventilation fans remain to be installed. As we approach late May, the project is estimated to be 95% complete.

June – July 2020 This period regularly scheduled Project Progress Meetings have

been held every week to discuss project close out with L. Cobb. During the week of July 6th, daily close out meetings were held. The meetings have been attended by the Authority, L. Cobb and AECOM, staff., many were held via Teams.

At the request of the Contractor, on May 22nd, the AECOM design team and Authority staff performed a formal walkthrough of the Maintenance Facility and provided feedback and guidance on unsatisfactory items, corrective actions needed and documentation required to reach Substantial Completion. Again, at the request of the Contractor, on June 22nd, the AECOM Project Architect performed the formal Substantial Completion walk through and generated a close-out punch list. In early July, the Desoto County Fire and Building Departments conducted their inspections. On July 7th the Contractor was awarded the Certificate of Occupancy by DeSoto County and continued work on punch list items as well as submittal of documentation needed for Substantial Completion such as: warranties, O&M Manuals and As-Built drawings.

Page 12: PEACE RIVER MANASOTA REGIONAL WATER SUPPLY … · 8/5/2020  · AECOM, staff., many were held via Teams. At the request of the Contractor, on May 22nd, the AECOM design team and Authority

11

Maintenance and Warehouse Facility Construction - August 5, 2020

On July 14th, AECOM determined the Project to be Substantially Complete which commences a contractual 60-day count down to Final Completion. At this time, AECOM is working with Authority staff and the Contractor to insure punch list items are completed and proper close out documentation is submitted.