peaking plant bayonne (nj/usa) - siemens energy sector · pdf file9/25/2016 ·...
TRANSCRIPT
Peaking plant Bayonne (NJ/USA) A flexible solution to support a volatile grid based on aero-derivative turbines
Tom Scarinci & Tobias Aschoff
siemens.com/gasturbines Unrestricted © Siemens AG 2017
June 2017 Page 2 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Case study – Bayonne Energy Center – Key facts
Owner (NYSE:MIC) Macquarie Infrastructure Corporation
Operator EthosEnergy Group
• Eight aero-derivative Siemens SGT-A65 TR* with 512 MW generating capacity, in operations since 2012
• Currently building additional 132 MW (two more SGT-A65 TR) on adjacent land owned by IMTT
• Also constructing additional gas lateral to Spectra TETLP M3 pipeline (already connected to Transco Z6)
• Dual fuel capable with liquid fuel connection from Buckeye Terminal
• Provides peak power to New York City via a 6.5-mile submarine cable
* formally know as Industrial Trent 60
June 2017 Page 3 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Bayonne Energy Center – Necessity
BEC is needed to ensure competitive peaking power and grid stability for NYC
Why …
3.000
4.000
5.000
6.000
7.000
8.000
9.000
Time Stamp 09/21/2016 09/22/2016 09/23/2016 09/24/2016 09/25/2016
3,500 MW spread
How … BEC is the New York City peaking facility providing the most flexible operating range and the only one offering 10min non-spinning-reserve with automatic dispatch
500 MW in 10 min
N.Y.C. load forecast
NYC load is predominantly driven by the ambient temperature and the weather forecast (A/C demand depending on temperature)
The NYC grid has a load spread of 3,500 MW and more per day
Most of the other NYC power plant facilities are more than 40 years old
June 2017 Page 4 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Bayonne Energy Center – Purchasing Criteria
BEC Requirements SGT-A65 TR
Multiple starts and stops per day Unlimited cycles per day, no lock-out
Low cost per start Low parasitic loads, fast acceleration
10 minute start (non-spinning reserve) 500 MW in <10 minutes (cold to full load)
High full and part load efficiency Best in class efficiency levels
High availability and starting reliability Very low eFORd, very high starting reliability
High power density Highest MW output on BEC’s footprint
Black start capable Low starting power requirement (<350 kW)
Automatic generation control Automatically starts & achieves MW set point
Low operation and maintenance costs Two operators on shift for eight turbines
State of the art (SOTA) emission levels Best achievable emission performance
June 2017 Page 5 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
BEC supports the volatile demand of the NY grid using high cycle capable units
Bayonne Energy Center – High cycling capability
March 7, 2016: 33 total start (six starts on unit 2)
Total plant Output (~500 MW peak)
Unit No. 2 Output (64 MW max)
Total plant Output (~500 MW peak)
Unit No. 2 Output (64 MW max)
No EOH counter
June 2017 Page 6 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Bayonne Energy Center – 10 minutes start up capability & low cost per start
Cost per start: $40-60
Based on ≈20 MMBTU gas required to accelerate to base load and $2-3 per MMBTU
0
2000
4000
6000
8000
10000
12000
0 50 100 150 200 250 300 350 400 450 500 550 600
High
Spe
ed S
pool
Spee
d (NH
) (rp
m)
Time (Seconds)
Start permissivesare met, then start
Ventilation system @ 5s
Base
load A
chiev
ed
Light-off to Sub-Sync Idle (20s)
Start InitiationStart LO & Hydr.
Systems &Enclosure Ventilation
(70s)
GT Rotation to Purge Speed(60s)
Ramp RateIncrease - 0.35 MWe/sDecrease - 0.17 MWe/s
Droop Control – 0.65 MW/s (Max)
Sub Sync Idle (SSI)
Dwell(90s)
Accel from SSI
to SI(40s)
Auto Sync check & in Progress
and breaker close(30s)
Acceleration to 66MW (194s)
Begin
G.T.
Rot
ation
to P
urge
G.T.
Purg
e Spe
ed A
chiev
ed
Sub-
Sync
Idle
Achie
ved
GT W
arm-up
Com
plete
Sync
Idle
Achie
ved
Comp
lete P
urge
Brea
ker C
losed
Cold Purge
(21s) RR Std Pkg,
Site Specific)ISO 21789
Total air volume purged by gas turbine only is 124.14 m3. Code requirements define volume and time requried
SGT-A65 TR WLE (Gas Fuel) – 10 min start sequence
Fast start enables 10 min non-spinning-reserve and low start up costs due to less time at lower efficiency
June 2017 Page 7 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Bayonne Energy Center – High full and part load efficiency
Multiple unit concept enables flexibility and optimized efficiency at all operating points
Advantages of multiple unit power plants
Plant Efficiency Curve*
0 50 100 150 200 250 300 350 400 450 500 550
42 40
34
38 36
32 30 28 26
0
Efficiency (%)
Power (MW)
High simple cycle full load efficiency
Better efficiency at most part load operating points
Fast start and steep ramp rates
Low station power loss during gas turbine maintenance outage (up to 448 MW available)
Turndown to <5% plant output
Emission compliance over entire curve
* Schematic
BEC efficiency higher than most other NYC peaking facilities
June 2017 Page 8 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Bayonne Energy Center – High availability and starting reliability
IEEE Standard – eFORd
A measure of the probability that a generating unit will not be available due to forced outages or forced derating when there is a demand on the unit to generate
Average simple cycle eFORd ≈ 5.30%
BEC 2016 YTD eFORd = 0.86 %
Only 13 failed starts out of 2653 attempts.
Average failed start ≈ 15 minutes
Report Summary
Month (2016) Att. Act. Rel. eFORd EAF
January 207 206 99.5% 0.40 96.82
February 263 261 99.2% 0.73 99.90
March 512 511 99.8% 1.76 98.50
April 423 422 99.8% 0.29 88.07
May 328 325 99.1% 0.03 81.06
June 275 273 99.3% 0.14 99.89
July 311 311 100.0% 0.59 97.63
August 334 331 99.1% 1.30 97.90
Report Totals 2653 2640 99.5% 0.86 94.94
Att. = Attempted Starts | Act. = Actual Starts | Rel. = Starting Reliability | eFORd = Equivalent Demand Forced Outage Rate EAF = Equivalent Availability Factor
June 2017 Page 9 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Bayonne Energy Center – Highest power density
Optimal land utilization in the high price NYC area
Bayonne Energy Center (“BEC”): 6.8 acres (≈27,500 m²) +132 MW BEC Expansion Site
The applied solution enables about 20% more power on the give ground
SGT-A65 TR Other solutions
512 MW ~400 MW
19 kW/m² 14.5 kW/m²
June 2017 Page 10 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Siemens SGT-A65 TR Heritage from Rolls-Royce Aero Trent
Trent 800 SGT-A65 TR
SGT-A65 TR
~30 Million – Aero Trent 800 hours
1.2 Million – SGT-A65 TR fleet hours
104 – Total engines sold
June 2017 Page 11 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Siemens SGT-A65 TR Combustion Systems
Wet Low Emission (WLE)
Dry Low Emission (DLE)
Dual fuel with water injection burner No EOH on liquid operation.
June 2017 Page 12 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Siemens SGT-A65 TR Package
Weights GT Skid 75,000 kg GT Package Roof 18,000 kg GT Engine 14,000 kg Filter 21,300 kg Generator Skid 107,000 kg
Designed for Maintainability and Quick Installation
Engine weighs less than 11 tonnes and is air freight transportable
Small footprint (~220 m²)
Installation possible <75 days
Engine change-out within <48 hours
June 2017 Page 13 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
SGT-A45 TR Mobile Unit – Fast Power. Superior Performance. Trusted technology.
Key benefits 44 MWe (ISO) – highest power density
2-weeks installation
Delivered by road, air or sea
Performance optimized for hot climates
50 Hz or 60 Hz
Liquid and gas fuel
Emissions as low as 25 vppm NOx
Proven turbomachinery
Minimal site interfaces and preparation
June 2017 Page 14 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Conclusion & Outlook
Conclusion Outlook
BEC is a successful plant for grid support in a weather driven, highly volatile grid due to • Fast start and operational flexibility • High full and part load efficiency • High reliability and availability
Flexible Combine Cycle Plants with up to 53.6% efficiency
Bayonne recently extends the plant by two more units due to good experience and great performance
The concept can be applied to other volatile grids – e.g. with high share of renewables
Hybrid plants • SGT-A65 TR with heavy duty large gas turbine
(using the same boiler) • SGT-A65 TR combined with battery storage for
back start and quick response • SGT-A65 TR with CSP plant
(using the same boiler)
Mobile Power SGT-A45 TR Mobile Unit with 44MW launched
June 2017 Page 15 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Thank you for your attention
Tobias Aschoff Power and Gas Division Distributed Generation PG DG SPM
Mobile: +49 173 5133163 E-mail: [email protected]
Tom Scarinci Power and Gas Division Distributed Generation PG DG GCS
Mobile: +1 514 4636283 E-mail: [email protected]
siemens.com
June 2017 Page 16 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Package sliding doors
Combustion air inlet filter (incl. ducting for Inlet Fogging or Chilling coil)
LP BOV ductwork
Package ventilation ductwork
Exhaust stack
OAC AC Gen
Package base plate
SGT-A65 TR
Siemens SGT-A65 TR Package Layout
BACK-UP
June 2017 Page 17 Tom Scarinci & Tobias Aschoff / Siemens AG Unrestricted © Siemens AG 2017
AL: N ECCN: N
Disclaimer
This document contains statements related to our future business and financial performance and future events or developments involving Siemens that may constitute forward-looking statements. These statements may be identified by words such as “expect,” “look forward to,” “anticipate” “intend,” “plan,” “believe,” “seek,” “estimate,” “will,” “project” or words of similar meaning. We may also make forward-looking statements in other reports, in presentations, in material delivered to shareholders and in press releases. In addition, our representatives may from time to time make oral forward-looking statements. Such statements are based on the current expectations and certain assumptions of Siemens’ management, of which many are beyond Siemens’ control. These are subject to a number of risks, uncertainties and factors, including, but not limited to those described in disclosures, in particular in the chapter Risks in Siemens’ Annual Report. Should one or more of these risks or uncertainties materialize, or should underlying expectations not occur or assumptions prove incorrect, actual results, performance or achievements of Siemens may (negatively or positively) vary materially from those described explicitly or implicitly in the relevant forward-looking statement. Siemens neither intends, nor assumes any obligation, to update or revise these forward-looking statements in light of developments which differ from those anticipated.
Trademarks mentioned in this document are the property of Siemens AG, its affiliates or their respective owners.
TRENT® and RB211® are registered trade marks of and used under license from Rolls-Royce plc. Trent, RB211, 501 and Avon are trade marks of and used under license of Rolls-Royce plc.