Intelsat Proprietary And Confidential Information 1

Satellite Transition Methodology

Pegaso IS1R – StarOne C2 Project Plan

Jason Calhoun

Program Management

November, 18 2008

Rev: 1.1

Confidential

Page 2: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 2

Project Plan – Table of Content

• Revision History / Sign-Off Concurrence

• Pegaso IS1R Project Transition Objective, Scope & Approach

• Project Assumptions, Constraints & External Dependencies

• Pegaso System Architecture Diagrams

• Pegaso Hub Migration / Antenna Repoint Timeline

• Pegaso IS1R Transition Milestone Schedule

• Pegaso Hub / Antenna Migration Schedule

• Pegaso IS1R Transition Key Deliverables / Acceptance Criteria

• Pegaso IS1R Transition Key Project Requirements / Success Factors

• Pegaso IS1R Transition Project Major Procurements

• Pegaso IS1R Transition Risks & Issues

• Pegaso IS1R Transition Project Budget Forecast

• Pegaso IS1R Transition Project Budget Codes

• Pegaso IS1R Transition Team Structure / Roles & Responsibilities

Page 3: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 3

Pegaso IS1R Project Transition Objective, Scope & Approach

• Project Transition Objective

- Intelsat IS14 will replace Intelsat IS1R at 315E orbital location (IS1R has an anomaly with solar cell degradation and requires turning transponders off over time). In particular, IS14 has no replacement for the IS1R North America extended Ku-band beam covering Mexico. The Ku-band beam on IS14 also does not cover Brazil whereas IS1R Latin America beam does. In lieu of this fact, all Pegaso services will be transitioned from IS1R to StarOne C2 at 70W. IS1R will drift to 310E where it will replace IS705 that is approaching the end of its station-kept life.

• Project Transition Scope

- Intelsat will acquire and install a new SurfBeam Hub at the Ellenwood teleport operations for the purpose of migrating the Pegaso network from IS1R to StarOne C2. Implementation will encompass the migration of the uplink/downlink from IS1R to StarOne C2 and the repointing of 16753 VSAT remote antennas throughout Mexico to the C2 satellite.

• Project Transition Approach

- Pegaso will migrate their services off of their existing SMTS hub and onto the new Intelsat purchased SMTS hub. Once all services have been migrated over to the new hub, Pegaso will begin the transition of the original SMTS hub uplinks to Star One C2, and will then transition the services off of the new Intelsat purchased SMTS hub back onto the original SMTS hub.

- The migration of Pegaso services from IS1R to StarOne C2 will require the upgrade of the 7.2m ATL-K02 antenna system located at the Ellenwood teleport (to be used to facilitate a temporary dual illumination period) and upgrade to the 13m ATL-K23 antenna system which is currently used by Pegaso on IS1R (also located at the Ellenwood teleport).

- ATL-K02 will be the future TT&C antenna for IS1R at it’s new location of 310E. A new 9m Ku-band antenna system ATL-K15 will be built for IS14 comms when it replaces IS1R at 315E. ATL-K23 will remain on IS1R during the dual illumination period until the new 9m ATL-K15 is completed and IS1R carriers are transferred to IS14 (scheduled for completion by 31-July-2009). ATL-K23 will then be repointed to StarOne C2 for exclusive Pegaso use once IS14 is in place and all other traffic have been moved.

Page 4: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 4

Project Assumptions, Constraints & External Dependencies

• Assumptions

– Reduced availability and UPC margins during transition period on the ATL-K02 7.2m antenna are acceptable

– HPA and antenna sizing are based on Link budgets provided for StarOne C2 spot beam that do not show spot beam coverage for the Atlanta region

– Web access remote monitoring system for carrier access

– ViaSat will provide installation, configuration and support

– ½ rate FEC will be used for inbound carriers

– Intelsat will procure LNB's to accommodate the StarOne C2 frequency plan

• Constraints

– ATL-K02 antenna needs a complete uplink chain built before the Pegaso carriers can be dual illuminated on StarOne C2

– Transition of all Pegaso and other traffic off of IS1R

• External Dependencies

– Contractual agreement with Pegaso must be in place to support hub implementation and system migration

– ViaSat SurfBeam Hub equipment delivery to Intelsat

– StarOne C2 segment negotiations/agreement

Page 5: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 5

Pegaso Existing Service On IS1R / 13m Antenna (ATL-K23)

Page 6: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 6

Pegaso StarOne C2 Temporary Service / 7m Antenna (ATL-K02)

Page 7: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 7

Pegaso Temporary Infrastructure Solution

Page 8: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 8

Pegaso Permanent Infrastructure Solution

Page 9: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 9

Pegaso IS1R Hub Migration / Antenna Repoint Timeline

Aug 09• Termination ofservices on IS1R.

01-Nov-08- 31-Jan-09 01-Feb-09 31-Jul-09

01-Aug-09 -Pegaso Repoint Complete

1-Feb-09 - 31-Jul-09 6 mos. Antenna Repoint Campaign

01-Feb-09 Pegaso DualIS1R

- Illumination Start StarOne C2

31-Jan-09 Intelsat 7.2m Antenna (ATL-K02)

Ready for Temporary Dual Illumination Period

1-Nov-08>Intelsat SMTS Hub Implementation/Antenna Upgrade<• 7.2m ATL-K02 antenna system upgrade located at the Ellenwood teleport to be used to facilitate temporary dual illumination period.

1-Nov-08 - 31-Jan-09 3 mos. SMTS Hub Implementation/

7.2m Antenna Upgrade

Page 10: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 10

Pegaso IS1R Transition Milestone Schedule

Facilitate temporary dual illumination period for IS1R – StarOne C2 transitionFuture31 Jan 20097.2m Antenna Upgrade (ATL-K02)

ViaSat will ship SurfBeam hub equipment to Ellenwood lab site, integrate into existing vacant SMTS rack and test / ViaSat will provide system support for system migration

Future01 Jan 2009SurfBeam Hub Implementation

Transition of services from IS1R – StarOne C2 / Remote antenna repoints Future01 Feb 2009Dual Illumination Start

ApprovedCompleted13 Nov 2008Purchase Requests for ViaSat SurfBeam Hub / LNBs

Transition complete from IS1R / Move from temporary 7.2m ATL-K02 / Repoint ATL-K23 to StarOne C2 for exclusive Pegaso use

Future19 Jun 200913m Antenna Upgrade (ATL-K23)

Submitted to ViaSat for equipment order / Anticipated delivery by mid December

Completed18 Nov 2008Purchase Orders for ViaSat SurfBeam Hub/LNBs Approved

Built for IS14 Comms when it replaces IS1R at 315EFuture01 Jun 20099m Ku-band Antenna Build/Install for IS14 Comms (ATL-K15)

VSAT repoints for 16753 antennas throughout MexicoFuture31 Jul 2009Antenna Repoint Campaign

Shipped in four phases for a total of 17053 (includes 300 units for spares)Future30 Mar 2009LNBs Shipment/Delivery Complete

Pending Intelsat/Pegaso legal negotiationsFuture30 Dec 2008Intelsat/Pegaso Contract Agreement Signed

Discussed (1.) Implementation of new SurfBeam hub in Ellenwood teleport lab; (2.)Migration of services from IS1R to StarOne C2; (3.)Repoints of 16753 VSAT remote terminals throughout Mexico; (4)VSAT remote LNB shipment logistics

Completed13 Nov 2008Hub Implementation/Antenna Repoint-Migration Review Meeting with Pegaso/ViaSat

ApprovedCompleted13 Nov 2008SOW for ViaSat SurfBeam Hub Implementation/Migration Support

Project scope, objective and approach discussed. Team structure, roles and responsibilities identified

Completed12 Nov 2008Project Transition Kick-Off Meeting

CommentProject StatusTarget Date

Milestone

Page 11: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 11

Pegaso Hub / Antenna Migration Schedule

Page 12: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 12

Pegaso Hub / Antenna Migration Schedule

Page 13: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 13

Pegaso IS1R Transition Key Deliverables / Acceptance Criteria

Network Engineering / RF Teleport Management

Successful transition of carriers from IS1R to IS14, cutover of ATL-K23 from IS1R to StarOne C2 and commissioning of ATL-K15 to IS14Completion of 9m ATL-K15 Antenna

Procurement / Logistics & Asset Management LNBs shipped/delivered to primary distribution sites in MexicoDeployment of LNBs

Network Engineering (Data Platforms/RF-TT&C)

Completion of ATL-K02 uplink chain and SMTS hub migration/network services transitionStart Dual Illumination

Network Engineering (RF, TT&C Systems)Successful migration of Ellenwood uplink/downlink from IS1R to StarOne C2 ATL-K02 RF Uplink Chain Built

Network Engineering (Data Platforms Systems)

Install/Test SMTS in lab rack. Successful system migration of outroute/inroute links and transition of services from IS1R to StarOne C2SurfBeam SMTS Hub Integration

Sign-OffAcceptance CriteriaKey Deliverables

Page 14: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 14

Pegaso IS1R Transition Key Project Requirements / Success Factors

• SurfBeam SMTS Hub Integration/Migration

• 7.2m ATL-K02 Antenna Upgrade/Uplink Chain Built

• 13m ATL-K23 Antenna Upgrade for Exclusive Pegaso Use

• 9m ATL-K15 Ku-band Antenna Build/Install for IS14

• VSAT Remote Antenna LNB Deployment Into Mexico

• VSAT Remote Antenna Repoints throughout Mexico

Page 15: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 15

Pegaso IS1R Transition Project Major Procurements

• Major Procurements

– SurfBeam SMTS Hub

– Gen4 KPA System for 7.2m ATL-K02 Antenna Upgrade

– Gen4 KPA System for 13m ATL-K23 Antenna Upgrade

– 9m ATL-K15 Antenna System for IS14

– LNBs for remote antennas (16753)

• Long Lead Items

– 9m Antenna System >6 - 7 months<

• Procurement Items Requiring SOW

– SurfBeam SMTS Hub >ViaSat Integration/Migration Support<

Page 16: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 16

Pegaso IS1R Transition Risks & Issues

• Project Risks

– Dual Illumination Start

– >Need to start by 01-Feb-2009 (Contingent on SMTS hub migration and 7.2m antenna ATL-K02 upgrade readiness)<

– Manufacture Equipment Delivery

– >SMTS hub delivery by end of December 2008<

– >Transmitters delivery for antenna upgrades by mid January 2009 (ATL-K02/ATL-K23)<

– >LNBs shipment/delivery into Mexico for remote antennas by end of January 2009<

– VSAT Remote Antenna Repoint Completion

– >Need to be completed by end of July 2009 (Services terminated on IS1R)<

– 9m Antenna ATL-K15 Build/Install

– >Projected completion date of 1st of June 2009 (Contingent on construction conditions, i.e. weather, materials, personnel, etc.)<

• Project Issues

– ViaSat committed to provide support services to Intelsat network engineering and Pegaso in order to maintain projected schedule for dual illumination start. Also committed to on time equipment delivery.

– Pegaso integrators/installers responsible for VSAT remote antenna repoints throughout Mexico

Page 17: Pegaso Is1 R S1 C2 Transition Project Plan Link

2008-09-09 Intelsat Proprietary And Confidential Information 17

Pegaso IS1R Transition Project Budget Forecast