PEP-II B-Factory AIP. John Seeman SLAC Operations Review June 16, 2004. Past AIP funding. Accelerator Improvement Project (AIP) funding as proposed by the PEP-II staff over the years in order to increase the luminosity to remain competitive was about 7000 k$ per year. - PowerPoint PPT PresentationTRANSCRIPT
SLAC Accelerator Department
PEP-II B-Factory AIP
John Seeman
SLAC Operations Review
June 16, 2004
SLAC Accelerator Department
Past AIP funding
• Accelerator Improvement Project (AIP) funding as proposed by the PEP-II staff over the years in order to increase the luminosity to remain competitive was about 7000 k$ per year.
• Actual AIP funding for past years:– FY99 = 3715 k$– FY00 = 5800 k$– FY01 = 6188 k$– FY02 = 7100 k$– FY03 = 3300 k$
SLAC Accelerator Department
Peak PEP-II Luminosity (x1E33) per Month
0
1
2
3
4
5
6
7
8
9
10
Jun
-99
Dec
-99
Jun
-00
Dec
-00
Jun
-01
Dec
-01
Jun
-02
Dec
-02
Jun
-03
Dec
-03
AIP funding has driven PEP-II luminosity increases!
SLAC Accelerator Department
SLAC AIP Changes between Funding Plans
• The SLAC Field Task Proposal (April 2004) used the following funding profile for AIP: FY05-FY09: 8M$, 8M$, 7M$, 6M$, 6M$.
• The Lehman review proposed AIP funding profile for the “Base 2%” case (June 2004) : FY05-FY09: 6M$, 6M$, 6M$, 6M$, 6M$.
• The Lehman review proposed AIP funding profile for the “Flat-Flat” case (June 2004): FY05-FY09: 6M$, 6M$, 5M$, 4 M$, 3 M$.
• The details of these three cases are shown below.
SLAC Accelerator Department
Changes in AIP Work Scope
• To get from the Field Task Proposal to the Lehman “Base 2%” case:– One PEP-II RF station was delayed from 2005
to 2006 installation.– The bunch shortening cavities in the HER were
eliminated. (Reduces the PEP-II overall peak luminosity from 2.4E34 to about 2.2E34.)
– Some PEP-II vacuum work was delayed which delays achievement of the ultimate peak luminosity.
– Some non-PEP-II work was delayed.
SLAC Accelerator Department
Further changes in AIP Scope
• To get from the Lehman “Base 2%” case to the Lehman “Flat-Flat” case:– Some PEP-II vacuum work was delayed by a
year from 2007 to 2008.– Some PEP-II magnet, feedback, and diagnostic
work was delayed from 2007 to 2008.– Many non-PEP-II items were delayed.
• It is assumed that the early year PEP-II upgrades and people are “protected” except for the above.
SLAC Accelerator Department
AIP Upgrades from SLAC Field Task Proposal April 2004
Fiscal Year PEP-II Radio-Frequency RF System
PEP-II Vacuum System
PEP-II Magnet, PS, Instruments, Feedback
Linac, DR, Gun, BSY, FFTB, PPS
Total
(k$)
2003 2234 300 766 0 3300
2004 2948 1396 2356 100 6800
2005 4900 2230 670 200 8000
2006 3465 2850 1585 100 8000
2007 1900 1800 2065 1235 7000
2008 1000 500 600 3900 6000
2009 0 0 0 6000 6000
SLAC Accelerator Department
AIP Upgrades for SLAC Lehman “Base 2%” June 2004
Fiscal Year PEP-II Radio-Frequency RF System
PEP-II Vacuum System
PEP-II Magnet, PS, Instruments, Feedback
Linac, DR, Gun, BSY, FFTB, PPS
Total
(k$)
2003 2234 300 766 0 3300
2004 2948 1396 2356 100 6800
2005 3248 1980 772 0 6000
2006 3332 1413 1255 0 6000
2007 1813 2537 1365 285 6000
2008 1087 500 500 3913 6000
2009 0 0 0 6000 6000
SLAC Accelerator Department
AIP Upgrades for SLAC Lehman “Flat-Flat” June 2004
Fiscal Year PEP-II Radio-Frequency RF System
PEP-II Vacuum System
PEP-II Magnet, PS, Instruments, Feedback
Linac, DR, Gun, BSY, FFTB, PPS
Total
(k$)
2003 2234 300 766 0 3300
2004 2948 1396 2356 100 6800
2005 3248 1980 772 0 6000
2006 3332 1413 1255 0 6000
2007 1813 1837 1065 285 5000
2008 1087 1200 800 913 4000
2009 0 0 0 3000 3000
SLAC Accelerator Department
Integrated PEP-II Luminosity• The PEP-II integrated luminosity for each of the three AIP
funding profiles was calculated month by month including the expected down times, turn-on schedules, and anticipated peak luminosities.
• The peak luminosity for each year was determined by the available installed hardware.
• A listing of the integrated luminosity by year is shown in the table below.
• These projections assume that the PEP-II staff for operation, maintenance, engineering, and construction remain at current levels.
• In summary: The “Base 2%” case reduces the overall integrated luminosity by about 8% compared to the Field Task Proposal and the “Flat-Flat” case an additional 2%.
SLAC Accelerator Department
PEP-II Delivered Integrated Luminosity under Various Plans
Delivered as of end of fiscal year
SLAC Field Task Proposal
SLAC Lehman “Base”
SLAC Lehman “Flat”
FY2004 253 /fb 253 /fb 253 /fb
FY2005 392 392 392
FY2006 545 534 534
FY2007 855 802 802
FY2008 1216 1130 1106
FY2009 1577 1462 1432
FY2010 1939 1795 1764
SLAC Accelerator Department
Conclusions
• AIP projects have provided the hardware opportunities to successfully increase the luminosity in PEP-II over the past years.
• Future AIP project money is important for continued luminosity improvement of PEP-II.
• With potential future reductions in the AIP funding, accelerator projects (and the associated luminosity gains) will likely be delayed to later years.