performance characteristics of-main
TRANSCRIPT
CHAPTER ONE
LITERATURE SURVEY
1.1 CLASSIFICATION OF SUBSTATIONS AND SUBSTATION
LAYOUTS
Substations maybe classified according to service,
mounting, function and type of apparatus.
1.1.1 DISTRIBUTION SUBSTATION: These are transforming
stations where voltages are transformed to low values for use by
household and other small power consumers. This system is
generally a four wire 3 - phase system with the Phase - Phase
Voltage at 415V and the Phase - Neutral Voltage at 230V.
1.1.2 INDUSTRIAL SUBSTATION: These substations serve the
needs of consumers who need bulk power, as it is advisable that
they install an individual substation.
1.1.3 POWER FACTOR CORRECTION SUBSTATION: This variation of
substation is used in the control of the transmission line receiving
end voltage and power factor. They have synchronous condensers
and reactors as their major components. These take care of the
large variations in voltage and power factor, which occur because
of the line inductance and capacitance.
1.1.4 FREQUENCY CHANGER SUBSTATION: These substations
convert any frequency to the type that can be utilized. This
substation is found where there are two or more power systems
1
operating at two different frequencies. A typical example is in the
United Kingdom where independent power producers generate
different frequencies from each other and the public utilities. A
frequency changer substation is used when it is required to
connect the systems together.
This kind of substation is not in the country right now but
with the recent government policy on the deregulation of electric
power industry, independent power producers are expected in the
country and this shall give rise to this kind of substation.
1.1.5 OUTDOOR/INDOOR SUBSTATION: Substations can also be
classified according to whether it is outdoor or indoor. The type
chosen depends on choice after a careful consideration of their
respective advantages and disadvantages.
1.2 ADVANTAGES OF OUTDOOR SUBSTATIONS OVER
INDOOR SUBSTATIONS
1. Outdoor substations require less constructional work than the
indoor substation.
2. Less quantity of building materials is needed.
3. The cost of switchgear installation is less.
4. Adequate spacing between two adjoining equipment can be
provided which will reduce the possibility of faults.
5. Erection of switchgear can be completed in a much lesser time.
2
6. The whole equipment can be viewed and this makes fault
location easier.
7. The scheme is easier to extend when needed.
1.3 DISADVANTAGES OF OUTDOOR SUBSTATIONS
1. A much more space is needed for arranging the equipment.
2. Dirt and dust deposits accumulate over the contacts of switches
etc. and thus, the maintenance cost increases.
3. The switching operations become difficult during rainy season
as the chances of current leakages increase.
1.4 TRANSMISSION SUBSTATION: This serves the purpose of
connecting generating stations to the national grid. They serve the
purpose of stepping up the voltage obtained from the generating
stations to higher values so that power can be sent over long
distances across the country.
1.5 11/0.415KV LOCAL SUBSTATION
An 11/0.415KV distribution substation is a local substation
used to feed the L.T lines within the L.T network. The substation
usually consists of a distribution transformer, a feeder pillar and an
3
RMU for supplying voltage. The substation may be fed through an
RMU or through a set of three J&P fuses on the H.T overhead lines.
RMU are used either as sources of supply or as open points or as
the junction points in the H.T network. They may be installed in the
substation or anywhere along the street, but properly earthed
fence shall be made to enclose the substation RMU which is raised
above the ground by the use of plinths.
The local substation is usually a rectangular enclosed area of
3.8m x 2.74m properly fenced and earthed by wire - gauze
reinforced by concrete pillars. An outlet in the form of a door is
provided in the fence. It is normally sited at junctions of two or
more streets and shall be always locked and only authorized
persons are allowed to enter the fenced area. The ground is
covered with gravel to avoid water - logging or accumulation of oil.
This permits any dripping oil from the transformer to sink into the
soil so as not to cause slippery hazard for the personnel working in
the area. Both the transformer and RMU are raised above the
ground by the use of solid concrete plinths of standard dimensions
specified by the authority for the contractors.
The 11KV supply from either a fused RMU or from H.T.
overhead lines through the three J&P fuses goes into the 11KV
primary - side of the distribution transformer (The size of cables
used depends on the capacity of the transformer but usually,
4
35mm2 XLPE cables or 70mm2, 1 - core cables are used as the
droppers for up to 300KVA transformers). At the L.T secondary
side of the transformer, four single - core cables of sizes
depending on the capacity of the transformers are connected by
the use of Raychem.
1.6 POWER ROUTING AND TRANSFORMER LOADING
PRACTICE
A substation supplies a given area and should be located at
or near the load centre of that area. Thismakes the copper losses
in the outgoing feeders or distributors a minimum and will reduce
difficulties due to voltage drop. In practice however, it is usually
impossible to obtain a suitable substation site at precisely the
point required and hence compromise must be struck.
1.7 ESTIMATION OR PREDICTION OF LOAD
Load prediction for an area depends upon the following factors
among others.
a. Nature of the area
b. Population and population density of area
c. Living standards of people in the locality
d. Industrial, commercial and agricultural development of the
area
5
e. Whether the load forecast is for a new town or
reinforcements of existing supply.
Terms that are important in forecasting load are:
(1) Consumer Demand factor (Df) = Maximum Demand Connected Load
Thus a consumer of maximum demand of 400w, but with connected load of 500w has a Df= 400 = 80% 500
(2) Load Factor = Average load Maximum load
Load Factor = Energy consumed during time t hrs Maximum demand in time t hrs
The needs of consumers differ and accordingly they do not
simultaneously impose their respective maximum demands at the
same time on the supply systems. Accordingly, there is diversity in
the occurrence of load. Thus,
Diversity Factor = Sum of individual Maximum Demands Simultaneous maximum demand
Diversity factor can easily be determined from a study of load
curves of consumers or even the load curve of an area or town.
From this, load current and load duration curve can be deduced
6
which becomes very useful for deciding power generation
requirements for the region.
1.8 TYPES OF LOAD
The main types of load are:
(1) Residential or domestic load which consists of, fans, heaters,
kettles, refrigerators, electric cookers, air conditioners, electric
water heaters and various other small appliances.
(2) Commercial loads which include shop lightings, fans, refrigerators,
light and various types of electric appliances used in commerce.
(3)Industrial load: This may include items in (1) and (2) above in
addition to heavy machineries driven by electric motors,
welding plants, electric furnaces.
Industrial loads may further be classified as
(i) Cottage industries 5kw load
(ii) Small scale industries 25kw load
(iii) Medium scale industries 500kw load
(iv) Heavy industries > 500kw load
In 24 hours, industries demand factors remain at about 85%
to 90% whilst load factor is 70% to 80%.
(4) Government load: This includes various kinds of office
equipment.
(5) Municipal load: This includes street lighting, their offices,
water supply, sewage system and drainage pumps.
(6) Irrigation loads for farms
(7) Mining Load (Heavy machinery)
7
(8) Traction load for trains (not available yet in Nigeria except in
moving devices which carry and generate their power
(requirements).
(9) Bulk supply to distribution centers.
(10) Specialised power requirement such as chemical plants,
steel plants, textile mills, paper mills, refineries and
extraction plants may need specific power supply
arrangement.
It is obvious that different types of load at different time may
be supplied by a power system leading to improvement of
individual load factors.
1.9 TRANSFORMER LOADING PRACTICES
Because of the varying load cycle of most transformers, it is
customary to permit loading considerably in excess of the
transformer nameplate rating. There may be limitations on the
transformer imposed by bushings, leads, tap changers, cables,
disconnecting switches, circuit breakers, etc. Good engineering
design however will permit operation without these limitations.
Increase in transformer loading is limited by the effect of
temperature on insulation life. High temperature decreases the
mechanical strength, increases the brittleness of fibrous insulation,
and makes transformer failure increasingly likely even though
dielectric strength of the insulation may not be seriously
decreased. Overloading should be limited then by considering the
effect on insulation life and transformer life. For recurring loads
8
such as the daily load cycles, the transformer would be operated
for normal life expectancy. For emergencies, either planned or
accidental, loading would be based on some percentage cost of
life.
In a typical case for a failure of part of the electrical system,
a 2.5% loss of life per day for a transformer may be acceptable.The following temperatures and load limitations are
generally applied to transformers. The temperature of the top oil
should never exceed 100oC. The maximum hot-spot winding
temperature should not exceed 150oC for 55oC rise transformers or
180oC for 65oC rise transformers. Short-time peak loading for 1/2hr
or more should not exceed 200% rating. At abnormally high
temperatures, it may be necessary to remove some oil in order to
avoid overflow or excessive pressure.
A substation must be designed to be efficient from the
technological point of view.
That is:
(1) It must be able to carry the load imposed upon it without
causing excessive heating in the conductors, the
consequence of which is damage to insulation.
(2) The voltage drop throughout the network must be kept to a
minimum to hold the voltage at the consumers' terminals
within specified limits, whatever the load condition. An
allowable drop of 10% is used.
9
(3) The substation must be designed to provide for continuity of
supply and should a fault occur on the system, power
interruption to individual consumers must be within the
shortest possible time. The system should be as simple to
operate and maintain as possible and losses must be kept at
a minimum. It is also required that routine maintenance
should be carried out without interruption of supply.
This condition involves a certain amount of circuit
duplication. This highlight the features of a perfect system but
the cost will be prohibitive
1.10 COMMON FAULTS IN DISTRIBUTION SYSTEM
Common faults in distribution system can be categorized as listed
below:
1.) Insulation breakdown in cables, transformer windings,
transformer oil, bushings and insulators.
2.) Over - current, earth - fault, short - circuit faults on lines, underground cables,
breakers and associated equipment.
3.) Over voltage, overload and under voltage.
1.11 NECESSITY OF PROTECTIONS IN DISTRIBUTION
SYSTEMSProtection of electrical distribution supply system is highly
necessary and important to:
10
(a) Prevent damages on the equipment within the network and
safety of personnel.
(b) Limit Load losses and prevent instability of the system .
(c) Maintain the continuityof the system for better revenue
generation .
Protection is achieved by means of Protection devices and
Protective relays.
1.12 PROTECTIVE DEVICES
These devices protect electrical equipment physically
against atmospheric and mechanical fault occurrences. They are:
(a)Lightning Arresters or surge diverters-: used to guard the
outdoor equipment against direct and indirect
lightning - strokes by transferring the accumulated
charges directly to the general earth. Lightning
strokes usually result in over voltages in the network.
(b)Arcing - horns-: Used on transformers and H.T. lines to divert
lightning strikes to earth.
(c)Shield - wire-: Used to protect and shield the entire switchyard
equipment against lightning. It is normally installed above
the switchyard or the H.T lines at angles of 30o to the
shielded equipment.
(d) Lightning - Spikes-: Used to absorb lightning charges down to
the general earth instantaneously.
11
(e) Breathers (Silica gel)-: Used on transformers to prevent ingrain
of moisture.
(f) Pressure - relief device-: Used to release excessive gas -
pressure, generated within transformers during faults,
to the atmosphere.
(g) Oil - level indicators-: Used to monitor the level of oil inside
transformer tanks and oil switch - gears for
satisfactory performances.
(h) Bare - conductor fuses-: Used to protect electrical equipment
against excessive fault currents.
(I) HRC fuses-: Used to protect electrical equipment against
excessive fault currents within shorter - time of fault.
(j) CT and VT-: Used to monitor excess current in a feeder or
transformer and converts it to a value for the
operation of the protective relays.
CHAPTER 2
DATA COLLECTED
2.1.0: SUBSTATIONS IN BENIN ENVIRONMENT
2.1.1: UGBOWO 33/11KV INJECTION SUBSTATION
2.1.1.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY
CAPACITY: 2 X 15MVA
12
SUBSTATION TYPE: OUTDOOR/INDOOR
EARTHING SYSTEM: EFFECTIVELY EARTHED
D C SYSTEM: 110V DC WITH NEGATIVE GROUND
NUMBER OF RADIATING FEEDERS:4
2.1.1.2 LINE PARAMETERS:
LINE LENGTH: 8KM section one, 6KM section two.
Total line length = 14KM
CONDUCTOR TYPE: AAC (ALL ALUMINIUM CONDUCTORS)
CONDUCTOR AREA: 150mm2
LINE IMPEDANCE: (0.0022 +j0.2) Ω/KM
NOMINAL VOLTAGE: 33KV
CONDUCTOR SPACING: 0.7m
RATED LINE CAPACITY: 30MW
2.1.1.2.1 UGBOWO 11KV FEEDER
LINE PARAMETERS
LINE LENGTH: 20.5KM
MAXIMUM LOAD: 350A
TYPE OF LOAD: RESIDENTIAL, SMALL SCALE INDUSTRIES AND
OFFICES.
NOMINAL SENDING END VOLTAGE: 11KV
13
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
LINE IMPEDANCE = (O.0024 + j0.395) Ω/KM TABLE 2.1: OUTAGES RECORDED IN MAY 2007
DATE DURATION REASONS FOR FAILURE LOAD
INTERRUPTED
06-05-
07
1608 –
2110HRS
(302MINS)
FEEDER OFF SEVICE DUE TO POOR
SYSTEM FREQUENCY 296A
07-05-
07
1005 –
1106HRS
(61MINS)
FEEDER OFF SERVICE ON OVER
CURRENT .RAINSTORM WAS
REPORTED DURING TRIPPING.
260A
16- 05-
07
0430 -
0630HRS
(120MINS)
FEEDER OFF SEVICE DUE TO POOR
SYSTEM FREQUENCY. 300A
19-05-
07
1000 –
1430HRS
(270MINS)
FEEDER OFF SERVICE BECAUSE of
A BROKEN CROSS ARMS 316A
26-05-
07
1111 –
1508HRS
FEEDER OFF SEVICE DUE TO POOR
SYSTEM FREQUENCY. 296A
14
(242MINS)
30-05-
07
1210 –
1808HRS
(352MINS)
FEEDER OFF SERVICE ON
EMERGENCY FOR THE REPAIR OF
THE LINE CIRCUIT BREAKER.
300A
2.1.1.2.2 FEDERAL GOVERNMENT COLLEGE 11KV FEEDER
LINE PARAMETERS
LINE LENGTH: 7KM
MAXIMUM LOAD: 110A
TYPE OF LOAD: RESIDENTIAL AND OFFICES
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
LINE IMPEDANCE = (0.0024 + j0.395) Ω/KM
TABLE 2.2: OUTAGES RECORDED IN MAY 2007
DATE DURATION FAILURE
LOAD
INTERRUPTED
1016– FEEDER WAS OFF ON LOAD
SHEDDING DUE TO POOR
15
01- 05-
07
1109HRS
(53MINS)
SYSTEM FREQUENCY. 100A
04-05-
07
2030–
2116HRS
(46MINS)
FEEDER WAS OFF ON LOAD
SHEDDING DUE TO POOR
SYSTEM FREQUENCY.
110A
16-05-
07
1515-
1816HRS
( 181MINS)
FEEDER OFF SERVICE DUE TO
A CUT DOWN WIRE.
106A
19-05-
07
2020-
2310HRS
(170MINS)
FEEDER WAS OFF ON LOAD
SHEDDING DUE TO POOR
SYSTEM FREQUENCY.
99A
26-05-
07
1516 -
1610HRS
(54MINS)
FEEDER WAS OFF SERVICE AS
A RESULT OF A SHATTERED
LIGHTENING ARRESTER.
108A
2.1.1.2.3 EGUADIAEKEN 11KV FEEDER
LINE PARAMETERS
LINE LENGTH: 9.0KM
MAXIMUM LOAD: 180A
TYPE OF LOAD: MIXED
NOMINAL SENDING END VOLTAGE: 11KV
16
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
LINE IMPEDANCE = (0.0024 + j0.395) Ω/KM
TABLE 2.3: OUTAGES RECORDED IN MAY 2007
DATE DURATION FAILURE LOAD INTERRUPTED
02-05-07
0600 – 0715HRS(75MINS)
LOAD SHEDDING DUE TO POOR SYSTEM FREQUENCY.
172A
09-05-07
0600-0730HRS(90MINS)
LOAD SHEDDING DUE TO POOR SYSTEM FREQUENCY.
170A
0600 –
17
13-05-07
0730HRS (90MINS)
LOAD SHEDDING DUE TO POOR SYSTEM FREQUENCY.
166A
16-05-07
1400 – 1442HRS(42MINS)
LOAD SHEDDING DUE TO POOR SYSTEM FREQUENCY
150A
19-05-07
2015-2206HRS(111MINS)
LOAD SHEDDING DUE TO POOR SYSTEM FREQUENCY.
180A
20-05-07
0918-1030(72MINS) LOAD SHEDDING DUE TO POOR
SYSTEM FREQUENCY.170A
26-05-07
0948-1030HRS(72MINS)
LOAD SHEDDING DUE TO POOR SYSTEM FREQUENCY.
180A
31-05-07
1950-2130HRS(130MINS)
LOAD SHEDDING DUE TO POOR SYSTEM FREQUENCY.
180A
2.1.1.2.4 USELU 11KV FEEDER
LINE PARAMETERS
LINE LENGTH: 10KM
MAXIMUM LOAD: 350A
TYPE OF LOAD: MIXED
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
18
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY = 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
LINE IMPEDANCE = (0.0024 + j0.395) Ω/KM
TABLE 2.4: OUTAGES RECORDED IN MAY 2000
DATE DURATION FAILURE LOAD INTERRUPTED
01-05-07
0530-0830HRS
(180MINS)
LOADSHEDDING DUE TO POOR SYSTEM FREQUENCY. 300A
08-05-07
1950-2200HRS
(190MINS)
LOADSHEDDING DUE TO POOR SYSTEM FREQUENCY. 296A
16- 05-07
1952-2210HRS
LOADSHEDDING DUE TO POOR SYSTEM FREQUENCY. 200A
19
(132MINS)22-05-
071206-
1515HRS(189MINS)
LOADSHEDDING DUE TO POOR SYSTEM FREQUENCY. 216A
24-05-07
1414-1906HRS
(308MINS)
FEEDER OFF SERVICE AS A RESULT OF A BROKEN CROSS ARM
219A
28-05-07
0600 – 0815HRS
(135MINS)
LOADSHEDDING DUE TO POOR SYSTEM FREQUENCY. 300A
2.1.1.3 INCOMING 33KV LINE PARAMETERS
LINE LENGTH: 8KM section one, 6KM section 2.
Total line length = 12KM
CONDUCTOR TYPE: AAC (ALL ALUMINIUM CONDUCTORS)
CONDUCTOR AREA: 150mm2
LINE IMPEDANCE: (0.0022 +j0.2) Ω/KM
NOMINAL VOLTAGE: 33KV
CONDUCTOR SPACING: 0.7m
RATED LINE CAPACITY: 30MW
2.1.1.4 SWITCHGEAR ARRANGEMENT
20
Figure 2.1 SINGLE LINE DIAGRAM OF UGBOWO INJECTION SUBSTAT MAY 2007
The substation is fed on 33KV via the same line that supplies power to
Guinness injection substation, from where it tees off to Ugbowo.The
33KV line is 12km long and the substation consists of two 15MVA
transformers. It is interesting to note that until the year 2004, the
substation used to be a 33/6.6KV type. The problem of low voltage and
the associated overload led to its upgrade. The incoming 33KV line ends
at Ugbowo substation. The original arrangement is such that the 33KV
line terminates at Okada injection substation. Siluko Injection Substation
is feeding the Army barracks/Okada axes of the network. This is due to the
operational difficulties being encountered by the Authority of PHCN.This
study is based on the present arrangement
21
FIG.2.2: SINGLE LINE DIAGRAM OF POWER FLOW FROM THE 33KV
SOURCE TO UGBOWO INJECTION SUBSTATION AS AT MAY 2007
22
2.1.2 SILUKO 33/11KV INJECTION SUBSTATION
2.1.2.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY
CAPACITY: 2x15MVA
SUBSTATION TYPE: OUTDOOR/INDOOR
EARTHING SYSTEM: EFFECTIVELY GROUNDED
DC VOLTAGE: 110Vdc
YEAR OF COMMISSIONING: 1976
NUMBER OF RADIATING FEEDERS: FOUR
2.1.2.2 LINE PARAMETERS
2.1.2.2.1 OLIHA 11KV FEEDER
LINE LENTH: 6KM
MAXUMUM LOAD RECORDED: 360A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
23
TABLE 2.5: OUTAGES RECORDED IN MAY
DATE DURATION REASONS FOR FAILURE LOAD LOST
01-05-071830-2030HRS(120MINS) Feeder was off service on load shedding due to poor
system frequency320A
02-05-071006-1209HRS(123mins) Feeder tripped on earth fault. A cut down cable was
amended before restoration308A
02-05-071830-2030HRS(120mins) Feeder off service on load shedding due to
transformer load limitation330A
05-05-071230-1436HRS(126mins) Feeder off service on emergency load shedding due to
transformer load limitation312A
07-05-070630-1016HRS(226mins) Feeder tripped on over current blue phase. A broken
cross arm was replaced before restoration320A
09-05-071045-1845HRS(480mins)
Feeder was off service on over current. Rainstorm was reported during tripping. Broken poles were replaced before restoration
212A
10-05-071010-2010HRS(600mins)
Feeder tripped on overcurrent.Rainstorm was reported during the tripping and broken poles were re-planted before restoration of service.
300A
15-05-071000-1408HRS(248mins) Feeder was off service for the maintenance of circuit
the line SF6 circuit breaker at the substation.200A
19-05-071408-1610HRS(122mins) Loss of the 33KV incomer. This was to enable them
carry out maintenance at the transmission substation.300A
21-05-071616-2010HRS(236mins) Feeder off service on over current. Rainstorm was
reported during tripping.312A
22-05-071930-2030HRS(60mins) 33KV incomer was opened on load shedding at
Transmission end.338A
25-05-071318-1710HRS(232mins) Feeder was opened on load shedding due to poor
generated power.318A
31-05-071414-1508HRS(54mins) Feeder was opened on load shedding due to poor
generated power320A
24
2.1.2.2.2 UPPER SILUKO 11KV FEEDER
LINE LENTH: 8KM
MAXIMUM LOAD: 240A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE: 2.6 OUTAGES RECORDED ON UPPER SILUKO FEEDER IN MAY 2007
25
DATE DURATION FAILURE LOAD
LOST
01-05-07 1828-2032HRS
(124mins)
Feeder off service due to poor system frequency.
220A
02-05-07 1606-2210HRS
(364mins)
Feeder off service due to poor system frequency 218A
07-05-07 1206hrs(7/5/7)-
1206hrs(10/5/7)
Broken poles. Rainstorm reported during tripping. 200A
19-05-07 1616-2000HRS
(214mns)
Feeder tripped on over current. Rainstorm was
reported during tripping.
218A
22-05-07 1930-2032HRS
(58mins)
Load shedding because of poor generation. 200A
31-05-07 1444-1500HRS
(16mins)
Load shedding because of poor generation. 212A
2.1.2.2.3 EDO TEXTILE MILL 11KV FEEDER
LINE LENTH: 6.1KM
MAXIMUM LOAD: 290A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
26
TABLE 2.7: OUTAGES RECORDED IN MAY 2007
DATE DURATION FAILURE
LOAD
LOST
06- 05-
07
1016-
1515HRS
(299MINS)
Feeder off service on overcurrent.Lightening was
Reported during tripping.
215A
07-05-
07
0906-
1112HRS
(186mins)
Emergency load shedding on poor system
frequency.
200A
7-5-07 1030-
2230HRS
(180mins)
Load shedding on transformer load limitation 268A
10-5-07 1410-
1432HRS
(22mins)
Feeder off service on over current. Rainstorm
reported during tripping.
116A
13-5-07 2020-
2356HRS
(226mins)
Transformer tripped on over current. 210A
15-05-
07
1618-
2015HRS
(237mins)
Feeder off service for the amendment of a broken
cross arm on the 11kv circuit.
200A
18-05-
07
10120-
1418HRS
(248mins)
Load shedding due to transformer load limitation. 219A
19-05-
07
1730-
2230HRS
(300mins)
Load shedding on poor system frequency. 268A
21-05-
07
1616-
2210HRS
(8mins)
Load shedding on poor system frequency. 210A
27
DATE DURATION FAILURE
LOAD
LOST
22-05-
07
0815-
1015HRS
(120mins)
Load shedding on poor system frequency. 219A
25-05-
07
1930-
2210HRS
(200mins)
Load shedding on poor system frequency. 200A
26-05-
07
2010-
2018HRS
(8mins)
Feeder off service on over current 196A
30-05-
07
1616-
1840HRS
(134mins)
Feeder off service on over current. Broken cross
arms were replaced before restoration.
200A
31-05-
07
0010-
1008HRS
(542mins)
Feeder tripped on earth fault. Broken cross arms
were replaced before restoration.
218A
2.1.2.2.4 UWELU 11KV FEEDER
LINE LENTH: 8KM
MAXIMUM LOAD: 320A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
28
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.8: OUTAGES RECORDED IN MAY 2007
DATE DURATION FAILURE LOAD LOST
08-05-07 1030-1530HRS
(300MINS)
Load shedding due to low system
frequency.
299A
10-05-07 1410-1440HRS
(30mins)
Feeder tripped on over current.
Rainstorm was reported during trip.
308A
13-05-07 2010-2350HRS
(190mins)
Transformer tripped o overcurrent.The
transformer is suspected to have been
loaded beyond the set point of its
300A
18-05-07 1000-1510HRS
(310mins)
Feeder was opened on load shedding
due to poor system frequency.
312A
22-05-07 1030-1415HRS
(225mins)
Feeder was opened on load shedding
due to poor system frequency
300A
25-05-07 1440-1928HRS
(288mins)
Feeder was opened on load shedding
due to poor system frequency
333A
26-05-07 2010-2216HRS
(6mins)
Feeder was opened on load shedding
due to poor system frequency
316A
29
2.1.2.3 SWITCHGEAR ARRANGEMENT
The substation is fed by a 33KV line that is approximately 32KM in lenth.The
switchgear are arranged such that the 33KV circuit is outdoor while the 11KV is
indoor. Four 11KV feeders radiate from the substation with two on each
transformer. The areas being fed by these feeders consists of residential,
commercial and industrial loads.
Figure 2.3: SINGLE LINE DIAGRAM OF SILUKO SUBSTATION
2.1.3 WELFARE 33/11KV INJECTION SUBSTATION
2.6.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY
CAPACITY: 1 X 15MVA, 33/11KV
SUBSTATION TYPE: OUTDOOR/INDOOR
EARTHING SYSTEM: EFFECTIVELY EARTHED
DC VOLTAGE: 110V dc
30
YEAR OF COMMISSIONING
NUMBER OF RADIATING FEEDERS: TWO
2.1.3.2 LINE PARAMETERS
2.1.3.2.1 UPPER SAKPONBA FEEDER
LINE LENGTH: 7KM
MAXIMUM LOAD: 440A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2. 9: OUTAGES RECORDED IN MAY 2007
31
DATE DURATION REASONS FOR FAILURE FAILURE
LOAD
INTERRUPTED
01-05-07 1828-
2932HRS
(124MINS)
LOAD SHEDDING DUE TO POOR
SYSTEM FREQUENCY
400A
02-05-07 1606-
2210HRS
(364MINS)
LOAD SHEDDING DUE TO POOR
SYSTEM FREQUENCY 389A
19-05-07 1616-
2000HRS
(214MINS)
LOAD SHEDDING DUE TO POOR
SYSTEM FREQUENCY 355A
22-05-07 1930-
2032HRS
(58MINS)
LOAD SHEDDING DUE TO POOR
SYSTEM FREQUENCY 400A
23-05-07 1320-
1700HRS
(220MINS)
LOAD SHEDDING DUE TO POOR
SYSTEM FREQUENCY
328A
25-05-07 1440-
1500HRS
(16MINS)
LOAD SHEDDING DUE TO POOR SYSTE
LOAD SHEDDING DUE TO POOR
SYSTEM FREQUENCY M FREQUENCY
330A
31-05-07 1830-
2030HRS
(120MINS)
BROKEN CROSS ARM ON THE 33KV
LINE.
414A
2.1.3.2.2 ST. SAVIOUR 11KV FEEDER
LINE LENGTH: 3KM
MAXIMUM LOAD: 70A
NOMINAL SENDING END VOLTAGE: 11KV
32
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.10: RECORDED IN MAY 2007
DATE DURATION FAILURE LOAD LOST
08-05-07 1030-1530HRS
(300MINS)
Load shedding due to low system frequency.299A
10-05-07 1410-1440HRS(30mins)
Feeder tripped on over current. Rainstorm was reported during trip. 308A
13-05-07 2010-2350HRS(190mins)
Transformer tripped on overcurrent.The transformer is suspected to have been loaded beyond the set point of its protective relays.
300A
18-05-07 1000-1510HRS(310mins)
Feeder was opened on load shedding due to poor system frequency. 312A
22-05-07 1030-1415HRS(225mins)
Feeder was opened on load shedding due to poor system frequency 300A
25-05-07 1440-1928HRS(288mins)
Feeder was opened on load shedding due to poor system frequency 333A
26-05-07 2010-2216HRS(6mins)
Feeder was opened on load shedding due to poor system frequency 316A
33
2.1.3.3 SWITCHGEAR ARRANGEMENT
Two 11KV feeders radiate from this substation namely: UPPER SAKPONBA and
ST. SAVIOUR FEEDERS.
Figure 2.4: SINGLE LINE DIAGRAM 0F WELFARE SUBSTATIO
2.1.4 GUINESS 33/11/6.6KV INJECTION SUBSTATION
2.1.4.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY
CAPACITY: 1 X 15 MVA 33/11KV, 1 X 7.5 MVA 33/6.6KV
SUBSTATION TYPE: OUTDOOR/INDOOR
EARTHING TYPE: EFFECTIVELY EARTHED
D C VOLTAGE: 110V DC WITH NEGATIVE GROUND
2.1.4.2 LINE PARAMETERS
34
2.1.4.2.1 NEW BENIN 11 KV FEEDER
LINE LEGTH: 8 KM
MAXIMUM LOAD: 270A
LINE TYPE: OVERHEAD
TYPE OF LOAD: RESIDENTIAL, COMMERCIAL AND COTTAGE
INDUSTRY
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.11: OUTAGES RECORDED IN MAY 2007DATE DURATION FAILURE LOAD
INTERRUPTED10-05-07 0530-0700HRS
(90MINS)FEEDER OFF SERVICE ON POOR SYSTEM FREQUENCY.
120A
16-05-07 1630-1710HRS(40MINS)
FEEDER OFF SERVICE AS ARESULT OF A CUT DOWN 11KV CONDUCTOR.
220A
21-05-07 1515- 1810HRS(175MINS)
FEEDER OFF SERVICE AS A RESULT OF POOR SYSTEM FREQUENCY.
211A
24-05-07 2030-2115HRS(75MINS)
FEEDER OFF SERVICE AS ARESULT OF TRANSFORMER LOAD LIMITATION.
210A
30-05-07 2110-2115HRS (5MINS)
FEEDER TRIPPED ON OVERCURRENT. THUNDERSTORM WAS REPORTED DURING TRIPPING.
215A
2.1.4.2.2 BDPA 11KV FEEDER
35
LINE LENGTH: 4KM
MAXIMUM LOAD: 230A
TYPE OF LOAD: RESIDENTIAL
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.12: OUTAGES RECORDED IN MAY
DATE DURATION FAILURE LOAD INTERRUPTED
01-05-07 0530-0630HRS
(60MINS)
FEEDER OFF SERVICE DUE
TO POOR SYSTEM
FREQUENCY
200A
04-05-07
1016 – 1508HRS
(308MINS)
FEEDER OFF SERVICE AS A
RESULT OF A SHATTERED
LIGTHENING ARRESTER.
216A
10-05-07
1020-1410HRS
(230MINS)
FEEDER OFF SERVICE DUE
TO BROKEN CROSSARM. 216A
14-05-07
1020-1410HRS
(230MINS)
FEEDER OFF SERVICE DUE
TO POOR SYSTEM
FREQUENCY.
200A
36
DATE DURATION FAILURE LOAD INTERRUPTED
15-05-07
1810-1910HRS
(60MINS)
FEEDER OFF SERVICE FOR
THE EMERGENCY REPAIR
OF A BREAKER
200A
16-05-07
1440-1810HRS
(210MINS)
FEEDER OFF SERVICE DUE
TO A SHATTERED
LIGHTENING
180A
27-05-07
1106-1206HRS
(60MINS)
FEEDER OFF SERVICE ON
LOAD SHEDDING DUE TO
POOR SYSTEM
FREQUENCY.
200A
2.1.4.2.3 ASABA 6.6 KV FEEDER
LINE LENGTH: 7KM
MAXIMUM LOAD: 400A
TYPE OF LOAD: RESIDENTIAL/COTTAGE INDUSTRIES
NOMINAL SENDING END VOLTAGE: 6.6KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 670A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
LINE IMPEDANCE (0.0024 + j0.395)/KM
37
TABLE 2.2.13: OUTAGES RECORDED IN MAY
DATE DURATION FAILURELOAD INTERRUPTED
01-05-07 0545-0745HRS
(120MINS)
FEEDER TRIPED ON
OVERCURRENT.THE FEEDER WAS
LOADED BEYOUND THE SET
VALUES FOR THE PROTECTIVE
RELAYS.
400A
02-05-07 1016-1208HRS
(112MINS)
FEEDER TRIPED ON
OVERCURRENT.THE FEEDER WAS
LOADED BEYOUND THE SET
VALUES FOR THE PROTECTIVE
RELAYS.
392A
04-05-07 2020-2115HRS
(65MINS)
LOAD SHEDDING DUE TO POOR
SYSTEM FREQUENCY
318A
06-05-07 0630-0715HRS
(45MINS)
FEEDER TRIPPED ON OVERCURRENT.
RAINSTORM WAS REPORTED
DURING THE FAILURE 200A
08-05-07 1616-1830HRS
(134MINS)
LOAD SHEDDING DUE TO POOR
SYSTEM FREQUENCY.
180A
10-05-07 2008-2116HRS
(68MINS)
FEEDER TRIPPED ON OVERCURRENT.
FEEDER IS SUSPECTED TO HAVE
BEEN OVERLOADED.
399A
18-05-07 1306-1408HRS
(62MINS)
LOADSHEDDING DUE TO POOR
SYSTEM FREQUENCY.
206A
21-05-07 1108-1208HRS
(60MINS)
FEEDER WAS OFF SERVICE FOR THE
REFIL OF LINE CIRCUIT BREAKER
WITH SF6 GAS. 200A
22-05-07 0630-1118HRS
(288MINS)
FEEDER OFF SERVICE DUE TO POOR
SYSTEM FREQUENCY. 188A
38
24-05-07 1010-1810HRS
(480MINS)
FEEDER TRIPPED ON EARTH FAULT.
A CUT DOWN CONDUCTOR WAS
REPAIRED BEFORE RESTORATION. 200A
26-05-07 1515-1615HRS
(60MINS)
FEEDER WAS OFF SERVICE ON LOAD
SHEDDING DUE TO POOR SYSTEM
FREQUENCY.
119A
28-05-07 2008-2016HRS
(120MINS)
FEEDER TRIPPED ON OVERCURRENT.
OVERLOAD BEYOUND PROTECTION
SETTING. 399A
31-05-07 0530-0730HRS
(120MINS)
FEEDER TRIPPED ON OVERCURRENT.
OVERLOAD BEYOUND PROTECTION
SETTING. 390A
2.1.4.3 INCOMING 33KV FEEDER
LINE LENGTH: 8KM
LINE TYPE: OVERHEAD
CONDUCTOR TYPE: AAC
LINE IMPEDANCE :( 0.0022+j0.22)Ω/KM
NOMINAL VOLTAGE: 33KV
CONDUCTOR SPACING: 0.7m
39
2.1.4.4 SWITCHGEAR ARRANGEMENT
Figure2.5: SINGLE LINE DIAGRAM OF GUINESS SUBSTATION
The substation is fed by a 20KM –long 33KV line from the transmission substation. The
injection substation, which is the indoor/outdoor type, has two power transformers with
different power and voltage ratings.
2.1.5 NEKPENEKPEN 33/11KV INJECTION SUBSTATION
2.1.5.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY
CAPACITY: 2x15MVA
SUBSTATION TYPE: OUTDOOR/INDOOR
EARTHING SYSTEM: EFFECTIVELY EARTHED
SYSTEM DC VOLTAGE: 110V DC
40
2.1.5.2 LINE PARAMETERS
2.1.5.2.1 FEEDER 1
LENTH OF LINE: 7KM
LINE TYPE: OVERHEAD
MAXIMUM LOAD RECORDED: 350A
TYPE OF LOAD: MIXED
TABLE 2.14: OUTAGES RECORDED IN THE MONTH OF MAY
DATE DURATION FAILURE LOAD LOST
02-05-07
1015-1315HRS(180MINS)
Feeder was off service on load shedding due to poor system frequency 300A
06-05-07
1530-2010HRS(280MINS)
Feeder tripped on over current. Rainstorm was reported during tripping. 295A
09-05-07
0630-1030HRS(280MINS)
Feeder was off service as a result of a broken cross arm. 318A
10-5-7 1620-1830HRS(130MINS)
Feeder was off service for the emergency repair of a hot spot at the 11kv busbar. 326A
16-05-07
1440-1640HRS(120MINS)
Feeder was off service as a result of high transformer winding temperature. 318A
20-05-07
2310-2354HRS(44MINS)
Feeder was off service due to system frequency correction. 341A
41
2.1.5.2.2 FEEDER 2
LENTH OF LINE: 6KM
LINE TYPE: OVERHEAD
MAXIMUM LOAD: 400A
TYPE OF LOAD: RESIDENTIAL, COMMERCIAL AND COTTAGE INDUSTRY
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.15: OUTAGES RECORDED IN MAY
DATE DURATION FAILURE LOAD
LOST
5-05-
07
1015-
1035HRS
(20MINS)
Feeder tripped on over current 210A
5-5-07
1902-
2115HRS
(133mins)
Feeder off service due to transformer load
limitation
350A
6-05-
07
0630-
1108HRS
(66mins)
Feeder off service for replacement of broken pin
insulator 320A
12-5-
07
2210-
2315hrs
Feeder tripped on earth fault. Cut down wire was
amended before restoration 316A
42
(65mins)
14-05-
07
1010-
1806HRS
(474mins)
Feeder off service due to broken pole
310A
14-05-
07
1515-
1610hrs
(53mins)
Feeder off service on poor system frequency
312A
16_05-
07
1018-
1316hrs
(178mins)
Feeder off service on over current. A cut down
jumper was replaced before restoration 296A
22-05-
07
1832-
1942hrs
(50mins)
Feeder off service to correct poor system
frequency. 310A
30-05-
07
1916-
2110hrs
(114mins)
Feeder off service on transformer load limitation 382A
31-05-
07
0630-
0710hrs
(40mins)
Feeder tripped on over current 375A
2.1.5.2.3 FEEDER 3
LINE LENTH: 6KM
LINE TYPE: OVERHEAD
MAXIMUM LOAD: 410A
TYPE OF LOAD: MIXED
43
DATE DURATION FAILURE LOAD INTERRUPTED
01-05-07 0530-0630HRS
(60MINS)
FEEDER OFF SERVICE DUE
TO POOR SYSTEM
FREQUENCY
200A
04-05-07
1016 – 1508HRS
(308MINS)
FEEDER OFF SERVICE
BECAUSE of A SHATTERED
LIGTHENING ARRESTER.
216A
10-05-07
1020-1410HRS
(230MINS)
FEEDER OFF SERVICE DUE
TO BROKEN CROSSARM. 216A
14-05-07
1020-1410HRS
(230MINS)
FEEDER OFF SERVICE DUE
TO POOR SYSTEM
FREQUENCY.
400A
15-05-07
1810-1910HRS
(60MINS)
FEEDER OFF SERVICE FOR
THE EMERGENCY REPAIR
OF A BREAKER
430A
16-05-07
1440-1810HRS
(210MINS)
FEEDER OFF SERVICE DUE
TO A SHATTERED
LIGHTENING
380A
27-05-07
1106-1206HRS
(60MINS)
FEEDER OFF SERVICE ON
LOAD SHEDDING DUE TO
POOR SYSTEM
FREQUENCY.
200A
TABLE 2.16: OUTAGES RECORDED IN MAY 2007
44
2.1.5.2.4 FEEDER 4
LINE LENGTH: 7.1KM
LINE TYPE: OVERHEAD
MAXIMUM LOAD RECORDED: 220A
TYPE OF LOAD: RESIDENTIAL
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
DATE DURATION FAILURE LOAD
LOST
01-05-07 1816-2000HRS
(104MINS)
Load shedding on poor system
frequency 200A
06-05-07 0016-
0230HRS(134MIN
S)
Feeder off service on over
current.Rainstorm was reported
during tripping.
212A
09-05-07 0630-1030HRS
(240MINS)
Feeder off service on over current. A
broken crosarm was replaced before
restoration.
200A
16-05-07 1500-1606HRS
(126MINS)
Load shedding due to transformer
load limitation. 96A
19-05-07 0816-1016HRS
(120MINS)
Feeder tripped on earth fault. A cut
down conductor was replaced before
restoration.
168A
20-05-07 1616-1630HRS Feeder tripped on over current.
45
(14MINS) Lightening storm was reported
during tripping.
210A
29-05-07 1008-1216HRS
(128MINS)
Feeder off service on over current.
Rainstorm reported during tripping. 200A
TABLE 2.17: OUTAGES RECORDED IN THE MONTH OF MAY 2007
2.1.5.3 SWITCHGEAR ARRANGEMENT
The injection substation fed via Nekpenekpen 33KV feeder from the transmission
substation at Sapele road Benin City. The 33KV switchgear arrangement is outdoor while
the 11KV ones are the indoor type. The substation supplies power to Sakponba,
Evbuoriaria, Oka, Ugbekun, Idogbo and Muritala Mohammed settlements of Benin City.
These are densely populated settlements that consist of mixed loads, as activities ranging
from commercial to private and governmental take place here. Four 11KV feeders radiate
from the substation, two being fed by each of the transformers.
46
Figure 2.6: SINGLE LINE DIAGRAM OF NEKPENEKPEN SUBSTATIO
2.1.6 ETETE 33/11KV INJECTION SUBSTATION
2.1.6.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY
CAPACITY: 2x15MVA
SUBSTATION TYPE: OUTDOOR/INDOOR
EARTHING SYSTEM: EFFECTIVELY GROUNDED
D C VOLTAGE: 110Vdc WITH NEGATIVE GROUND
YEAR OF COMMISIONING: 1997
2.1.6.2 LINE PARAMETERS
47
2.1.6.2.1 IHAMA 11KV FEEDER
LINE LENGTH: 5KM
MAXIMUM LOAD: 432A
TYPE OF LOAD: RESIDENTIAL/GOVERNMENT
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.18: OUTAGES RECORDED IN THE MONTH OF MAY 2007
DATE DURATION FAILURE LOAD LOST
02-05-07
1015-1315HRS(180MINS)
Feeder was off service on load shedding due to poor system frequency 400A
06-05-07
1530-2010HRS(280MINS)
Feeder tripped on over current. Rainstorm was reported during tripping. 295A
09-05-07
0630-1030HRS(280MINS)
Feeder was off service because of a broken cross arm. 318A
10-5-7 1620-1830HRS(130MINS)
Feeder was off service for the emergency repair of a hot spot at the 11kv busbar. 366A
16-05-07
1440-1640HRS
Feeder was off service because of high transformer winding temperature. 388A
48
(120MINS)20-05-07
2310-2354HRS(44MINS)
Feeder was off service due to system frequency correction. 349A
2.1.6.2.2 DUMEZ 11KV FEEDER
LINE LENGTH: 6KM
MAXIMUM LOAD: 264A
TYPE OF LOAD: RESIDENTIAL/OFFOCIAL
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
DATE DURATION FAILURE LOAD LOST
02-05-07
1015-1315HRS(180MINS)
Feeder was off service on load shedding due to poor system frequency 200A
06-05-07
1530-2010HRS(280MINS)
Feeder tripped on over current. Rainstorm was reported during tripping. 195A
09-05-07
0630-1030HRS(280MINS)
Feeder was off service because of a broken cross arm. 118A
10-5-7 1620-1830HRS(130MINS)
Feeder was off service for the emergency repair of a hot spot at the 11kv busbar. 166A
16-05-07
1440-1640HRS(120MINS)
Feeder was off service because of high transformer winding temperature. 188A
20-05- 2310- Feeder was off service due to system frequency
49
07 2354HRS(44MINS)
correction. 229A
TABLE 2.9 : OUTAGES RECORDED
2.1.6.2.3 UGBOR 11 KV FEEDER
LINE LENGTH: 6KM
MAXIMUM LOAD: 440A
TYPE OF LOAD: RESIDENTIAL/OFFICES
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.20: OUTAGES RECORDED IN MAYDATE DURATION FAILURE LOAD
LOST
01-05-07 1816-2000HRS
(104MINS)
Load shedding on poor system
frequency 300A
06-05-07 0016-
0230HRS(134MIN
S)
Feeder off service on over
current.Rainstorm was reported
during tripping.
312A
09-05-07 0630-1030HRS
(240MINS)
Feeder off service on over current. A
broken crosarm was replaced before
restoration.
300A
16-05-07 1500-1606HRS
(126MINS)
Load shedding due to transformer
load limitation. 296A
50
19-05-07 0816-1016HRS
(120MINS)
Feeder tripped on earth fault. A cut
down conductor was replaced before
restoration.
168A
20-05-07 1616-1630HRS
(14MINS)
Feeder tripped on over current.
Lightening storm was reported
during tripping.
310A
29-05-07 1008-1216HRS
(128MINS)
Feeder off service on over current.
Rainstorm reported during tripping. 230A
2.1.6.2.4 UPPER SAPELE 11KV FEEDER
LINE LENGTH: 7KM
MAXIMUM LOAD: 316A
TYPE OF LOAD: RESIDENTIAL AND OFFICIAL
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
51
TABLE 2.21: OUTAGES RECORDED IN MAY 2007
DATE DURATION REASONS FOR FAILURE FAILURE LOAD LOST
02-05-07 0530-0730hrs
(120MINS)
Load shedding due to poor system
frequency 300A
04-05-07 1018-1416HRS
(238MINS)
Broken cross arm .Rainstorm as
reported during tripping 309A
06-05-07 2010-2210HRS
(120MINS)
Load shedding due to poor system
frequency 300A
08-05-07 1944-2210HRS
(86MINS)
Load shedding due to transformer load
limitation. 296A
18-05-07 1614-2018HRS
(244MINS)
Feeder tripped on earth fault. Broken
poles were replaced before restoration. 290A
21-05-07 2014 -2030 HRS
(16MINS)
Feeder tripped on over current. Broken
poles were replaced before restoration. 211
24-05-07 1015-
1206HRS(111MINS)
Load shedding due to poor system
frequency. 290A
26-05-07 1515-1608HRS
(53MINS)
Load shedding due to poor system
frequency 310A
27-05-07 0810-0916HRS
(66MINS)
Load shedding due to poor system
frequency 306A
29-05-07 1018-1416HRS
(238MINS)
Load shedding due to poor system
frequency 289A
29-05-07 1018-1416HRS
(238MINS)
Load shedding due to poor system
frequency 289A
31-05-07 1106-1119HRS
(13MINS)
Load shedding due to poor system
frequency 211A
52
2.1.6.3 SWITCHGEAR ARRANGEMENT
This substation is fed via ETETE 33KV feeder from the transmission substation,
which is just 2.8km away. Four 11KV feeders radiate from the substation with
two tied to each transformer. These feeders are IHAMA, DUMEZ, UGBOR and
UPPER SAPELE 11KVfeeders.
Figure 2.7: SINGLE DIAGRAM OF ETETE INJECTION SUBSTATION
2.1.7 GRA 33/11KV INJECTION SUBSTATION
2.1.7.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY, EDO STATE.
CAPACITY: 2x15MVA
SUBSTATION TYPE: OUTDOOR/INDOOR
YEAR OF COMMISSIONING: 1995
EARTHING SYSTEM: EFFECTIVELY EARTHED
DC SYSTEM: 110V DC WITH NEGATIVE GROUND
2.1.7.2 LINE PARAMETERS
2.1.7.2.1 OBA PALACE 11KV FEEDER
53
MAXIMUM LOAD RECORDED: 285A
LINE TYPE: OVERHEAD
LINE LENTH: 7KM
TYPE OF LOAD: OFFICES, COTTAGE INDUTRIES AND RESIDENTIAL.
TABLE 2.22 OUTAGES RECORDED IN MAY 2007
DATE DURATION FAILURE LOAD
LOST
12-15-
07
1006-
1200HRS
(114MINS)
The line was interrupted for replanting of a
broken pole.
280A
22-05-
07
1600-
1200HRS
(55MINS)
The feeder tripped on over current. Rainstorm
was reported during tripping.
252A
54
2.1.7.2.2 GRA 11KV FEEDER
MAXIMUM LOAD RECORDED: 279A
LINE TYPE: OVERHEAD
LINE LENTH: 6KM
TABLE 2.23 OUTAGES RECORDED IN MAY 2007
DATE DURATION
FAILURE
LOAD LOST
09-05-
07
1616 -1635HRS
(19MINS)
The feeder tripped on earth fault. A cut-down
conductor was amended before restoration.
230A
16-05-
07
0205-0630HRS
(265MINS)
The feeder tripped on over current red and blue
phases. Rainstorm was reported during the trip. 200A
24-05-
07
1935-2000HRS
(25MINS)
The line was of service as the 33KV feeder was
opened on emergency load shedding for system
frequency control.
250A
30-05-
07
1000-1245HRS
(165MINS)
The feeder was opened for the emergency
maintenance of its line breaker, which lost SF6
gas.
270A
30-05-
07
1608-1702HRS
(66MINS)
The feeder tripped on over current blue phase. It
was patrolled and no fault was found .It was
then restored back to service.
258A
55
2.1.7.2.3 RESERVATION 11KV FEEDER
MAXIMUM LOAD: 430A
LINE LENTH: 6KM
TYPE OF LOAD: RESIDENTIAL/GOVERNMENT OFFICES
CONDUCTOR TYPE: AAC
CURRENT RATING: 401.9A
MW RATING: 7.5MW
TABLE 2.24 OUTAGES RECORDED IN MAY
DATE DURATION FAILURE
LOAD
LOST
12-5-
07
1440-
1540HRS
(60MINS)
The feeder was opened on emergency to replant
a weak electric pole 398A
2.1.7.3 SWITCHGEAR ARRANGEMENT
56
Figure 2.8: SINGLE LINE DIAGRAM OF GRA SUBSTATION
GRA 33KV feeder feeds the substation from Benin transmission substation at
sapele road in Benin City. The 33KV switchgear arrangement is outdoor and
consists of isolators, circuit breakers, insulation support and surge arresters which
are so arranged that the 33KV line feeds into 33KV busbar to which two
transformers are connected via isolators and circuit breaker.
The 11KV circuit is indoor. The circuit breaker CB4 is provided to facilitate both
parallel operation of the two transformers and to allow for transfer of load from
one transformer to the other. At the time of this research however, the
transformers were running individually and not in parallel.Transfomer one feeds
Oba palace and GRA feeders while transformer 2 feeds Reservation feeder.
57
2.1.8 EVBUOTUBU 33/11KV INJECTION SUBSTATION
2.1.8.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY
CAPACITY: 1 X 15MVA, 33/11KV
EARTHING SYSTEM: EFFECTIVELY EARTHED
DC SYSTEM: 110Vdc WITH NEGATIVE GROUND
YEAR OF COMMISSIONING: 2002
2.1.8.2 LINE PARAMETERS
2.1.8.2.1 EVBUOTUBU 11KV FEEDER
58
LINE LENGTH: 8KM
MAXIMUM LOAD: 288A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.25 OUTAGES RECORDED IN MAY 2007
DATE DURATION FAILURE LOAD INTERRUPTED
06-05-07 1005-1206HRS
(120MINS)
LOAD SHEDDING DUE TO POOR FREQUENCY 200A
16-05-07 1216- 1416HRS
(120MINS)
LOAD SHEDDING DUE TO POOR FREQUENCY 236A
22-05-07 0630-1006HRS
(116MINS)
LOAD SHEDDING DUE TO POOR FREQUENCY 250A
24-05-07 1944-2210HRS
(146MINS)
LOAD SHEDDING DUE TO POOR FREQUENCY 275A
26-05-07 1515-2010HRS
(295MINS)
LOAD SHEDDING DUE TO POOR FREQUENCY 200A
30-05-07 0201-0415HRS
(134MINS)
LOAD SHEDDING DUE TO POOR FREQUENCY 200A
59
2.1.8.2.2 ASORO 11KV FEEDER
LINE LENGTH: 8KM
MAXIMUM LOAD: 255A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.26 OUTAGES RECORDED IN MAY
DATE DURATION FAILURE LOAD
09-05-
07
1930-
2230HRS
(180MINS)
LOAD SHEDDING DUE TO POOR SYSTEM
FREQUENCY
250A
19-05-
07
1930-
2230HRS
(180MINS
LOAD SHEDDING DUE TO POOR SYSTEM
FREQUENCY
250A
26-05-
07
0530-
0730HRS
(120MINS)
LOAD SHEDDING DUE TO POOR SYSTEM
FREQUENCY 250A
28-05-
07
1414-
1814HRS LOAD SHEDDING DUE TO POOR SYSTEM
FREQUENCY
200A
60
(240MINS)
31-05-
07
0530-
0700HRS
(90MINS)
LOAD SHEDDING DUE TO POOR SYSTEM
FREQUENCY
250A
2.1.8.3 SWITCHGEAR ARRANGEMENT
Figure 2.9: SINGLE LINE DIAGRAM OF EVBUOTUBU SUBSTATION
The substation is one of the newest in the zone and it supplies power to the Evbuotubu, Ekenwan and Asoro communities. The load is largely residential with pockets of cottage industries. The substation is supplied on 33KV from the transmission substation. Two 11KV feeders are available and they are EVBUOTUBU and ASORO 11KV feeders.
2.1.9 FEDERAL SECRETERIAT 33/11KV INJECTION SUBSTATION
2.1.9.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY
CAPACITY: 1X 15MVA, 33/11KV
SUBSTATION TYPE: OUTDOOR/INDOOR
EARTHING SYSTEM: EFECTIVELY EARTHED
DC SYSTEM: 110V DC WITH NEGATIVE GROUND
61
2.1.9.2 LINE PARAMETERS
2.1.9.2.1 NEW AUCHI 11KV FEEDER
LINE LENGTH: 6KM
MAXIMUM LOAD: 440A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.27 OUTAGES RECORDED IN MAY 2007
DATE DURATION FAILURE LOAD
LNTERRUPTED
01-05-07 0630-
0800HRS
(90MINS)
LOAD SHEDDING DUE TO
POOR SYSTEM
FREQUENCY
399A
06-05-07 1616-
2016HRS
(240MINS)
LOAD SHEDDING DUE TO
POOR SYSTEM
FREQUENCY
409A
16-05-07 1010-
1510HRS
(300MINS)
LOAD SHEDDING DUE TO
POOR SYSTEM
FREQUENCY
410A
23-05-07 1606-
1620HRS
LOAD SHEDDING DUE TO
POOR SYSTEM 430A
62
(14MINS) FREQUENCY
29-05-07 1930-
2030HRS
(60MINS)
LOAD SHEDDING DUE TO
POOR SYSTEM
FREQUENCY
300A
2.1.9.2.2 FEDERAL HOUSING 11KV FEEDER
LINE LENGTH: 4KM
MAXIMUM LOAD: 180A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.28 OUTAGES RECORDED IN MAY 2007
DATE DURATION FAILURE LOAD
INTERRUPTED
06-05-
07
0530-
0730HRS
(120MINS)
LOADSHEDDING DUE TO POOR
SYSTEM FREQUENCY 170A
10-05-
07
0545-
0730HRS
(105MINS)
LOADSHEDDING DUE TO POOR
SYSTEM FREQUENCY
170A
16-05-
07
1930-
2030HRS
(60MINS)
LOADSHEDDING DUE TO POOR
SYSTEM FREQUENCY 180A
63
2.1.9.3 SWITCHGEAR ARRANGEMENT
Figure 2.10: SINGLE LINE DIAGRAM OF FEDERAL SECRETERIAT SUBSTATION
2.1.10 IKPOBA DAM 33/11KV INJECTION SUBSTATION
2.1.10.1 SUBSTATION PARAMETERS
LOCATION: BENIN CITY
CAPACITY: 1X7.5MVA &1X15MVA, 33/11KV
SUBSTATION TYPE: OUTDOOR/INDOOR
EARTHING SYSTEM: EFFECTIVELY EARTHED
DC VOLTAGE: 110VDC WITH NEGATIVE GROUND.
2.1.10.2 LINE PARAMETERS
2.1.10.2.1 DAM 11KV FEEDER
LINE LENGTH: 0.1KM
64
MAXIMUM LOAD: 200A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.29 OUTAGES RECORDED IN MAY
DATE DURATION FAILURE LOAD INTERRUPTED
06-05-07
1440-1630HRS
(110MINS)
FEEDER WAS OFF SERVICE FOR THE MAINTENANCE OF ITS TERMINAL EQUIPMENT
186A
2.1.10.2.2 UPPER LAWANI 11KV FEEDER
LINE LENGTH: 4KM
MAXIMUM LOAD: 110A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.30: OUTEGES RECORDED IN MAY 2007
DATE DURATION FAILURE LOAD
65
INTERRUPTED06-05-
071440-
1635HRS(115MINS)
GENERAL MAINTENANCE 100A
16-05-07
0650-1005HRS
(255MINS)
POOR SYSTEM FREQUENCY 105A
20-05-07
1005-1210HRS
(125MINS)
POOR SYSTEM FREQUENCY 103A
22-05-07
1616-1916HRS
(180MINS)
POOR SYSTEM FREQUENCY 96A
26-05-07
0530-0730HRS
(120MINS)
POOR SYSTEM FREQUENCY 108A
2.1.10.2.3 OKHORO 11KV FEEDER
LINE LENGTH: 4.5KM
MAXIMUM LOAD: 190A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.30: OUTAGES RECORDED IN MAY 2007
DATE DURATION FAILURE LOAD INTERRUPTED
66
6-05-07 1440-1640HRS
(120MINS)
GENERAL MAINTENANCE 180A
07-05-07 0630-0700HRS
(30MINS)
POOR SYSTEM FREQUENCY 190A
10-05-07 1630-1930HRS
(180MINS)
POOR SYSTEM FREQUENCY 120A
13-05-07 1900-2200HRS
(180MINS
POOR SYSTEM FREQUENCY 180A
23-05-07 2210-2220HRS
(10MINS)
POOR SYSTEM FREQUENCY 152A
29-05-07 0630-0659HRS
(29MINS)
POOR SYSTEM FREQUENCY 166A
2.1.10.3 SWITCHGEAR ARRANGEMENT
Figure 2.11: SINGLE LINE DIAGRAM OF IKPOBA DAM SUBSTATION
67
This substation supplies power to Ikpoba River dam which is the only water works in
Benin City and to two other feeders on 11KV .The feeders are: OKHORO &
LAWANI 11KV FEEDERS.
2.2.0 SUBSTATIONS IN DELTA STATE ENVIRONMENT
2.2.1 OGHAREKI 33/11KV INJECTION SUBSTATION
2.2.1.1 SUBSTATION PARAMETERS
LOCATION: Oghara town Delta state
CAPACITY: 1x15MVA
SUBSTATION TYPE: outdoor/indoor
YEAR OF COMMISSIONING: 2001
2.2.1.2 LINE PARAMETERS
LINE LENGTH: 10KM
68
LINE TYPE: OVERHEAD
MAXIMUM LOAD RECORDED ON THE FEEDER: 450A
MINIMUM LOAD RECORDED ON THE FEEDER: 215A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.32: OUTAGES RECORDED IN THE MONTH OF MAY 2007
DATE DURATION FAILURE LOAD
16-05-07
1000-
1015HRS
(15MINS)
LOSS OF SOURCE 300A
22-05 -07
2105-2145HR
(40MINS)
FEEDER TRIPPED ON OVERCURRENT
A BLOWN HRC FUSE WAS REPLACED
BEFORE RESTORATRION
408A
30-05-07
2130-
2155HRS
(25MINS)
FEEDER TRIPPED ON OVERCURRENT
A BLOWN HRC FUSE WAS REPLACED
BEFORE RESTORATRION
430A
2.2.1.2 SWITCHGEAR ARRANGEMENT
69
The substation receives supply from Amukpe 330/33KV transmission substation
via Mosogar 33KV feeder. The 33KV switchgear is outdoor and 11KV
switchgear arranged indoor. One 11KV feeder, Oghareki 11KV feeder originates
from the station. This feeder feeds the Oghareki community, which has mixed
loads (residential, small cottage industries, offices and schools).
2.2.2 OGHAREFE 33/11KV INJECTION SUBSTATION
70
2.2.2.1 SUBSTATION PARAMETERS
CAPACITY: 1x15MVA
SUBSTATION TYPE: OUTDOOR/INDOOR
YEAR OF COMMISSIONING: 2001
2.2.2.2 LINE PARAMETERS
2.2.2.2.1 GOVERNOR 11KV FEEDER
LINE LENTH: 6KM
TYPE OF LINE: OVERHEAD
TYPE OF LOAD: OFFICES, RESIDENTIAL AND COTTAGE INDUSTRIES.
MAXIMUM LOAD RECORDED: 220A
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR:100mm2
OUTAGES RECORDED IN THE MONTH OF MAY 2007: NIL
2.2.2.2.2 OTEFE 11KV FEEDER
LINE LENTH: 10KM
TYPE OF LINE: OVERHEAD
TYPE OF LOAD: COTTAGE INDUSTRIES, OFFICES AND RESIDENTIAL.
MAXIMUM LOAD RECORDED: 300A
NOMINAL SENDING END VOLTAGE: 11KV
71
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.33 OUTAGES RECORDED IN THE MONTH OF MAY
DATE DURATION REASONS FOR FAILURE LOAD LOST
6-05-07
0245-1045HRS
(480mins)
Broken pin insulators at Otefe town
caused the trip. 200A
18-5-07
0924-1010HRS
(46mins)
Feeder opened to enable maintenance
crew replace blown HRC fuses. 272A
2.2.3 BETA GLASS 33/11KV INJECTION SUBSTATION
2.2.3.1 SUBSTATION PARAMETERS
LOCATION: UGHELLI, DELTA STATE
CAPACITY: 1x7.5MVA
SUBSTATION TYPE: OUTDOOR/INDOOR
YEAR OF FIRST COMMISSIONING: 1978
2.2.3.2 LINE PARAMETERS
2.2.3.2.1 UGHELLI 11KV FEEDER
LENTH OF LINE: 12KM
TYPE OF LINE: Overhead
72
MAXIMUM LOAD RECORDED: 200A
TYPE OF LOAD: RESIDENTIAL
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW
CROSS SECTIONAL AREA OF CONDUCTOR: 100mm2
TABLE 2.34: OUTAGES RECORDED ON THE FEEDER IN MAY2007
DATE DURATION FAILURE LOAD LOST
03-05-07 0600-1035HRS.
(275mins.)
The feeder tripped on earth fault. A tree branch was removed from the line before restoration.
180A
16-05-07 1436-1458HRS.
(22mins.)
There was loss of supply from the source 33kv feeder. This was for the purpose of maintenance of their 33kv line breaker.
200A
26-05-07 2006-2027HRS.The feeder tripped on over current red phase.
200A
73
(21mins.)
2.2.3.2.2 BETA GLASS 11KV FEEDER
LENTH OF LINE=3KM
TYPE OF LINE: OVERHEAD
MAXIMUM LOAD: 150A
TYPE OF LOAD: INDUTRIAL (GLASS FACTORY)
NOMINAL SENDING END VOLTAGE: 11KV
CONDUCTOR TYPE: AAC (All aluminum conductors)
CONDUCTOR CODE: SPARROW
CURRENT CAPACITY: 401.9A
MW CAPACITY: 7.5MW CROSS SECTIONAL AREA OF CONDUCTOR:100mm2
TABLE 2.35: OUTAGES RECORDED IN THE MONTH OF MAY 2007
DATE DURATION REASONS FOR FAILURE LOAD LOST
16-05-07
1436-1458(22MINS)
THERE WAS LOSS OF POWER FROM SOURCE 33KV SUBSTATION.
120A
2.2.3.3 SWITCHGEAR ARRANGEMENT
74
Figure2.14: SINGLE LINE DIAGRAM OF BETA GLASS SUBSTATION
The substation, which is both the indoor and outdoor type, is fed via a 2km-long
33kv feeder which comes from Delta power station also in ughelli. The 33kv
switchgear is outdoor while the 11kv switchgear is indoor. The 33kv arrangement
consists of a line isolator, an SF6 gas circuit breaker and a transformer isolator.
The 11kv output of the transformer goes straight to the indoor switchgear
arrangement for distribution to consumers via two 11kv overhead lines.
CHAPTER 3
ANALYSIS OF DATA
3.1.0 SUBSTATIONS IN BENIN ENVIRONMENT
3.1.1 UGBOWO 33/11KV INJECTION SUBSTATION
CALCULATIONS
Current in section 1 = Current due to Ugbowo substation + Current due to
Guinness substation
75
CURRENT DUE TO UGBOWO SUBSTATION
MAXIMUM LOAD DUE TO TRANSFORMER 1= 460A
MAXIMUM LOAD DUE TO TRANSFORMER 2=530A
TOTAL LOAD = 990A AT 11KV
TOTAL LOAD =330A AT 33KV
CURRENT DUE TO GUINESS SUBSTATION
MAXIMUM LOAD DUE TO TRANSFORMER 1 = 500A AT 11KV (166.7A
AT 33KV)
MAXIMUM LOAD DUE TO TRANSFORMER 2 = 400A AT 6.6KV (80A AT
33KV)
TOTAL LOAD DUE TO GUINESS SUBSTATION = 246.7A AT 33KV
TOTAL LOAD DUE TO GUINESS SUBSTATION = 13.8MW
CURRENT IN SECTION 1 = 576.7A
IMPEDANCE OF SECTION 1 = (0.0022 +j0.2) x 8 = ( 0.0176 + j1.6)Ω
AT FULL LOAD VOLTAGE DROP OF SECTION 1 = I x Z = 576.7X
(0.0176+j1.6) = (10.14 +j921.6) V
CURRENT IN SECTION 2 AT FULL LOAD = 330A
IMPEDANCE OF SECTION 2 = (0.002+j0.2) x 6 = (0.012+j1.2) Ω
VOLTAGE DROP IN SECTION 2 AT FULL LOAD = 330 x (0.012+j1.2)Ω =
(3.96 + j396)V
TOTAL VOLTAGE DROP = VOLTAGE DROP IN SECTION 1 + VOLTAGE
DROP IN SECTION 2 = (14.1 + j1317.6) V
|V| =1.32KV
76
VOLTAGE AT THE RECEIVING END = 33-1.32= 31.68KV
VOLTAGE REGULATION = RECEIVING END VOLTAGE x 100 SENDING END VOLTAGE
= 31.68 x 100 = 96 % 33.0
3.1.1.2 CALCULATIONS FOR 11KV FEEDERS
3.1.1.2.1 UGBOWO 11KV FEEDER
RATED CURRENT CAPACITY = 401.9A
% LOADING = 350 X 100 = 87.1% 401.9
TOTAL LINE RESISTANCE = (0.0024 +j0.395) x 20.5 = (0.0492 + j8.096)Ω
VOLTAGE DROP = I x Z = 350 x ( 0.0492 + j8.096) = (17.22 + j2833.6)V |V| =2.83KV
VOLTAGE AT THE MOST REMOTE END OF FEEDER= 8.17KV
TOTAL OUTAGE PERIOD = 302+ 61 + 120 + 270 + 242 + 352 = 134MINUTES
TOTAL SERVICE PERIOD = 44640MINUTES
AVAILABILITY = 44640 -1347 = 0.97 44640
3.1.1.2.2 FEDERAL GOVERNMENT COLLEGE 11KV FEEDER
RATED CURRENT CAPACITY OF LINE = 401.9A
% LOADING OF LINE = 110 X 100 = 27.3% 401.9
TOTAL LINE IMPEDANCE = (0.0024 +j0.395) x 7 = (0.0168 +j2.765)Ω
VOLTAGE DROP = I X Z = 110 X(0.0168 + j2.765) = (1.848 +j304.15)V
|V| = 0.3KV
77
VOLTAGE AT THE MOST REMOTE END =11-0.3=10.7KV
TOTAL OUTAGE PERIOD = 53 + 46 + 181 +170 +54 =504MINS
TOTAL SERVICE PERIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 504 = 0.99 44640
3.1.1.2.3 EGUADIEKEN 11KV FEEDER
RATED CURRENT CAPACITY = 401.9A
%LOADING OF LINE = 180 x 100 = 44.8% 401.9
TOTAL LINE IMPEDANCE = (0.0024 + j0.395) x 9 = (0.022 + j3.56)
VOLTAGE DROP = I X Z = 180 X (0.022 + j3.56) = (3.96 +j640.8) V
|V| =0.64KV
VOLTAGE AT THE MOST REMOTE END = 11.0 – 0.64 = 10.38KV
TOTAL OUTAGE PERIOD = 692MINS
TOTAL SERVICE PERIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 692 = 0.99 44640
3.1.1.2.4 USELU 11KV FEEDER
78
% LOADING OF LINE = 350 X 100 = 87.1% 401.9TOTAL LINE IMPEDANCE = (0.0024 + j0.395) x 10 = (0.024 +j3.95) Ω
VOLTAGE DROP = I X Z = 350 X (0.024 +j3.95) V
|V| = 1.4KV
VOLTAGE AT THE MOST REMOTE SUBSTATION = 11.0 – 1.4 =9.6KV
TOTAL OUTAGE PERIOD: 180 + 190 + 132 + 189 + 30C 8 + 135 = 1134MINS.
TOTAL SERVICE PERIOD = 44640 MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABITY = 44640 – 1134 = 0.98
44640
3.1.1.3 TRANSFORMER LOADING Transformer 1
RATING: 15MVA, 33/11KV
COOLING TYPE: ONAN
WINDING TYPE: DY1
CALCULATIONS
MAXIMUM LOAD ON TRANSFORMER = 350 + 110 = 460A
P =√3xIxVxCosø
79
TRANSFORMER RATED CURRENT = 15 X 10 6 = 803.36A √3X11X103X0.98
%LOADING = 460 X 100 = 57.3% 803.36
MAXIMUM H.V VOLTAGE = 34.0KV (RECORDE BY OPERATORS)
MINIMUM H.V VOLTAGE = 31.04KV (FROM CALCULATIONS)
MAXIMUM L.V VOLTAGE = 11.3KV (RECORDE BY OPERATORS)
MINIMUM L.V VOLTAGE = 10.4KV (FROM CALCULATIONS)
3.1.1.3.2 TRANSFORMER 2
RATING: 15MVA, 33/11KV
COOLING TYPE: ONAN
WINDING TYPE: DY1
CALCULATIONS
MAXIMUM LOAD ON TRANSFORMER = 180 + 350 = 530A
P =√3xIxVxCosø RATED FULL LOAD CURRENT = 15 X 10 6 = 803.36 √3X11X103X0.98
% LOADING = 530 X 100 = 66% 803.36 MAXIMUM H.V VOLTAGE =34.0KV
MINIMUM H.V VOLTAGE = 31.04KV
MAXIMUM L.V VOLTAGE = 11.3 KV
MINIMUM L.V VOLTAGE = 10.4KV
80
PROTECTION AVAILABLE FOR THE TRANSFORMERS
Differential protection
Over current protection
Restricted earth fault protection
Buchholz (gas) protection
Winding temperature protection
Surge protection
LINE PROTECTION
2-Phase over current relay
1-Sensitive earth fault relay
3.1.2 SILUKO 33/11KV INJECTION SUBSTATION
3.1.2.1 CALCULATIONS FOR 11KV FEEDERS
3.1.2.1.1 OLIHA 11KV FEEDER
% LOADING OF LINE: 360 X100 =89.57% 401.9
CALCULATIONS
TOTAL LINE IMPEDANCE= (0.0024 + j0.395) x 6 = (0.012 +j2.4)Ω
VOLTAGE DROP= IxZ= 360X(0.012 + j2.4)=(4.32 + j864)V
|V| =0.9KV
VOLTAGE AT THE MOST REMOTE END = 11-0.9=10.1KV
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIODTOTAL SERVICE PERIOD: 44640 MINUTES
81
AVAILABILITY= 44640-2147 = 0.9544640
3.1.2.1.2 UPPER SILUKO 11KV FEEDER
% Loading of line = 240 x 100 =59.72% 401.9
TOTAL LINE IMPEDANCE =(0.0024 + j0.395) X 8 =(0.0192 + j3.16)Ω
VOLTAGE DROP = I x Z = 240 x(0.0192 + j3.16) =(4.608 + j758.4) 1.7 KV
|V| = 0.76KV
VOLTAGE AT THE MOST REMOTE END OF THE LINE =11-0.76=10.4KV
TOTAL OUTAGE PERIOD = 996 MINS
TOTAL SERVICE PERIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AILABILITY = 44640 – 996 =0.98 44640
3.1.2.1.3 EDO TEXTILE MILL 11KV FEEDER
% LOADING OF LINE: 290 X 100 =72.2% 401.9TOTAL LINE IMPEDANCE = (0.0024 + j0.395) x 6.1 = (0.015 + j2.41)
VOLTAGE DROP = I X = 290 X (0.015 + j2.4) = (4.35 + j696)
|V| = 0.7KV
VOLTAGE AT THE REMOTE END OF FEEDER = 11-0.7=10.3KV
TOTAL OUTAGE PERIOD: 3056 MINUTES
82
SERVICE PERIOD: 44640MINUTES
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY =44640– 3056 =0.93 44640
3.1.2.1.4 UWELU 11KV FEEDER
% LOADING OF LINE: 320 X 100 =77.9% 401.9 TOTAL LINE IMPEDANCE :( 0.0024 + j 0.395) X 8 = (0.019 + j3.16)Ω
VOLTAGE DROP : I X Z = 320 X(0.019 + j3.16) = (6.08 + j1011.2)Ω
|V| = 1.0KV
TOTAL OUTAGE PERIOD: 1349MINUTES
SERVICE PERIOD: 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY= 44640 – 1349 = 0.97 44640
3.1.2.2 TRANSFORMER LOADING
Transformer 1
RATING: 15 MVA, 33/11KV
COOLING TYPE: ONAN
WINDING TYPE: DY11
CALCULATIONS
COMBINED LOAD ON TRANSFORMER: 600A
83
P =√3xIxVxCosø
RATED FULL LOAD CURRENT: 803.6A
% LOADING 600 X 100 =74.7% 803.6
3.1.2.2.2 TRANSFORMER 2
RATING: 15MVA,33/11KV
COOLING TYPE: ONAN
WINDING TYPE:DY11
CALCULATIONS
COMBINED LOAD: 610A
P =√3xIxVxCosø
TRANSFORMER RATED CURRENT= 803.36A
% LOADING OF TRANSFORMER = 610 X 100 = 76% 803.36
PROTECTION AVAILABLE FOR THE TRANSFORMERS
Differential protection
Over current protection
Restricted earth fault protection
Buchholz (gas) protection
Winding temperature protection
84
Surge protection
LINE PROTECTION
2-Phase over current relay
1-Sensitive earth fault relay
3.1.3 WELFARE 33/11KV INJECTION SUBSTATION 3.1.3.1 CALCULATIONS FOR 11KV FEEDERS
UPPER SAKPONBA FEEDER
% LOADING OF LINE = 440 X 100 =109.5% 401.9TOTAL LINE IMPEDANCE = (0.0024 + j0.395) X7 =(0.016 +j2.765)Ω
VOLTAGE DROP = I X Z = 440 X(0.016 + j2.765) =(7.04 + j1216.6)V
|V| =1.2KV
VOLTAGE AT REMOTE END = 11-1.2 = 10.8KV
TOTAL OUTAGE PERIOD = 1116MINS
TOTAL SERVICE PERIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 1116 = 0.98 44640
3.1.3.1.2 ST. SAVIOUR 11KV FEEDER
% LOADING OF LINE = 70 X 100 = 17.4% 401.9
TOTAL LINE IMPEDANCE = (0.0024 + j0.395) X 3 = (0.0072 + j1.185) Ω
85
VOLTAGE DROP = I X Z = 70 X (0.0072 + j1.185)V
|V| = 0.1KV
VOLTAGE AT REMOTE END = 11-0.1=10.9KV
TOTAL OUTAGE PERIOD: 1349MINUTES
SERVICE PERIOD: 44640
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY= 44640 – 1349 = 0.97 44640
3.1.3.2 TRANSFORMER LOADING
RATING: 15MVA, 33/11KV
COOLING TYPE: ONAN
WINDING TYPE : DY11
CALCULATIONS
MAXIMUM LOAD = 440+70 = 510A
P =√3xIxVxCosø
RATED CURRENT = 803.36A
% LOADING = 510 X 100 =63.5% 803.36
PROTECTION AVAILABLE FOR THE TRANSFORMERS
Differential protection
86
Over current protection
Restricted earth fault protection
Buchholz (gas) protection
Winding temperature protection
Surge protection
LINE PROTECTION
2-Phase over current relay
1-Sensitive earth fault relay
3.1.4 GUINESS 33/11/6.6KV INJECTION SUBSTATION
3.1.4.1 INCOMING 33KV FEEDER
CALCULATIONS
TOTAL LINE IMPEDANCE = (0.0022 + j0.22) x 8 =(0.0176 +j1.76)Ω
MAXIMUM LOAD DUE TO 11KV FEEDERS = 270 + 230 = 500A
87
EQUIVALENT LOAD AT 33KV = 500 X 11 = 166.7A 33MAXIMUM LOAD DUE TO 6.6KV FEEDER = 400A
EQUIVALENT LOAD AT 33KV = 400 X 6.6 = 80A 33
LOAD DUE TO GUINESS SUBSTATION AT 33KV =66.7+ 80=246.7A
LOAD DUE TO UGBOWO SUBSTATION AT 33KV = 330A
TOTAL LOAD FLOWING THROUGH THE 8KM SECTION AT PEAK
PERIOD =330 +246.7 =576.7A
VOLTAGE DROP = I X Z = 576.7 x (0.0176+ j1.6) =(10.14 + j921.6)V
|V| = 0.92KV
3.1.4.2 CALCULATIONS FOR 11KV FEEDERS
3.1.4.2.1 NEW BENIN 11 KV FEEDER
CALCULATIONS
% LOADING OF LINE = 270 X 100 = 67.2% 401.9TOTAL LINE IMPEDANCE= (0.0024 + j0.395) x 7=(0.0168 + j2.765)Ω
VOLTAGE DROP = 270 X (0.0168 + j2.765) =(4.54 + j746.6)V
|V| =0.8KV TOTAL SERVICE PERIOD = 44640MINUTES
TOTAL OUTAGE PERIOD = 385 MINUTES
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 385 = 0.99 44640
88
3.1.4.2.2 BDPA 11KV FEEDER
CALCULATIONS
% LOADING = 230 X 100 = 70.3% 401.9
TOTAL LINE IMPEDANCE = (0.0024+ j 0.395) x 4 = (0.0096 + j1.58) Ω
VOLTAGE DROP = I X Z = 230 X(0.0096 + j1.58) = (2.208 + j363.4)V
|V| =0.36KV
3.1.4.2.3 ASABA 6.6 KV FEEDER
CALCULATIONS
% LOADING OF LINE = 400 X 100 = 59.7% 670
TOTAL LINE IMPEDANCE = (0.0024 + j0.395) x 7 = (0.0168 + j2.77) Ω
VOLTAGE DROP = I XZ = 400 X(0.0168 + j2.77) = (6.72 + j1108)V
|V| = 1.1KV
TOTAL OUTAGE PERIOD = 1563MINUTES
TOTAL SERVICE PERIOD = 44640MINUTES
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 1563 = 0.97 44640
3.1.4 .3 TRANSFORMER LOADING
89
3.1.4.3.1 Transformer 1
CALCULATIONS
COMBINED LOAD = 270 + 230 = 500A
P =√3xIxVxCosø
RATED CURRENT CAPACITY = 15 X 10 6 = 803.365 √3 X 11 X 103 X 0.98
% LOADING = 500 X 100 = 62.2% 803.36
3.1.4.3.2 Transformer 2
CALCULATIONS
MAXIMUM LOAD ON TRANSFORMER = 400A
P =√3xIxVxCosø TRANSFORMER RATED CURRENT= 7.5 X 106 = 669.5A √3 X 6.6 X 103 X0.98
% LOADING OF TRANFORMER = 400 X 100 = 59.8% 669.5
PROTECTION AVAILABLE FOR THE TRANSFORMERS
Differential protection
Over current protection
Restricted earth fault protection
Buchholz (gas) protection
Winding temperature protection
90
Surge protection
LINE PROTECTION
2-Phase over current relay
1-Sensitive earth fault relay
3.1.5 NEKPENEKPEN 33/11KV INJECTION SUBSTATION
3.1.5.1 CALCULATIONS FOR 11KV FEEDERS
3.1.5.1.1 FEEDER 1
CALCULATIONS
TOTAL OUTAGE PERIOD:
135+71+175+76+124+66+25+51+199+3810+210+20+180+165+63=5370MINS
TOTAL SERVICE PERIOD: 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY= 44640-5370 =0.88 44640
3.1.5.1.2 FEEDER 2
CALCULATIONS
TOTAL OUTAGE
PERIOD:15+116+126+70+195+64+375+24+49+75+200+45=1354MINUTES
TOTAL SERVICE PERIOD= 44640
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
91
AVAILABILITY= 44640-1354 =0.97 44640
3.1.5.1.3 FEEDER 3
CALCULATIONS
TOTAL OUTAGE PERIOD: 1517 MINUTES
TOTAL SERVICE PERIOD: 44640
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY= 0.97
3.1.5.1.4 FEEDER 4
TOTAL OUTAGE PERIOD=688MINUTES
TOTAL SERVICE PERIOD=44640MINUTES
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIODAVAILABILITY=0.98
3.1.5.2 TRANSFOMER LOADING
3.1.5.2.1 TRANSFORMER 1
TRANSFORMER RATED FULL LOAD CURRENT= 803.36A
%LOADING= 800 X 100 = 99.96% 803.36
3.1.5.2.2 TRANSFORMER 2
92
RATED CURRENT = 803.36A% LOADING = 630 X 100 =78.4% 803.36
PROTECTION AVAILABLE FOR THE TRANSFORMERS
Differential protection
Over current protection
Restricted earth fault protection
Buchholz (gas) protection
Winding temperature protection
Surge protection
LINE PROTECTION
2-Phase over current relay
1-Sensitive earth fault relay
3.1.6 ETETE 33/11KV INJECTION SUBSTATION
3.1.6.1 INCOMING 33KV FEEDER
CALCULATIONS
MAXIMUM LOAD AT 11KV= 432 + 264+ 440+316 = 1452A
TRANSFORMER RATIO: 33/11 = 3:1
MAXIMUM LOAD AT 33KV = 1452 = 484A 3VOLTAGE DROP = I X Z = 484 X (00616 + j0.56)V
93
|V| = 0.3KV 3.1.6.2 CALCULATIONS FOR 11KV FEEDERS 3.1.6.2.1 IHAMA 11KV FEEDER
% LOADING OF LINE = 432 X 100 = 107.5% 401.9TOTAL LINE IMPEDANCE = (0.0024 + j 0.395) X 5 = (0.0120 + j 1.975)Ω
VOLTAGE DROP = I X Z = 432 X(0.0120 = j 1.975)V
|V| = 0.9KV
TOTAL OUTAGE PERIOD: 2120 MINUTES
TOTAL SERVICE PERIOD: 44640MINUTES
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 2120 = 0.95 44640
3.1.6.2.2 DUMEZ 11KV FEEDER
% LOADING OF LINE = 264 X 100 = 65.7% 401.9
TOTAL LINE IMPEDANCE = (0.0024 + j0.395) x 6 = (0.0144 + j2.4)Ω
VOLTAGE DROP = 264 X (0.0144 + j2.4) = (3.80 + j625.7)V | V| = 0.63KV
3.1.6.2.3 UGBOR 11 KV FEEDER
% LOADING OF LINE: 440 X 100 = 109.5% 401.9
TOTAL LINE IMPEDANCE :( 0.0024 +j 0.395) X 6 = (0.0144 + j2.37) Ω
VOLTAGE DROP = I X Z = 440 X(0.0144 + j2.37)V
|V| =1.04KV
TOTAL OUTAGE PERIOD = 866MINUTES
TOTAL SERVICE PERIOD= 44640MINUTES
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE
94
TOTAL SERVICE PERI AVAILABILITY = 44640 – 866 = 0.98
44640
3.1.6.2.4 UPPER SAPELE 11KV FEEDER
% LOADING OF LINE = 316 X 100 = 78.6% 401.9
TOTAL LINE IMPEDANCE = (0.0024 + j0.395) X 7 = (0.0168 + j2.765)Ω
VOLTAGE DROP = I X Z = 316 X (0.0168 + j2.765)V
|V| = 0.9KV
TOTAL OUTAGE PERIOD: 1305MINUTES
TOTAL SERVICE PERIOD: 44640MINUTES
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 1305 = 0.97 44640
3.1.6.3 TRANSFORMER LOADING
3.1.6.3.1 Transformer 1
COMBINED LOAD: 696A
P =√3xIxVxCosø
I = 803.36A
% LOADING = 696 X 100 = 86.7% 803.36
3.1.6.3.2 Transformer 2
95
COMBINED LOAD = 756A
P =√3xIxVxCosø
I = 15 X 10 6 = 803.36 √3x11x103x0.98
% LOADING OF TRANSFORMER = 756 x 100 = 94.1% 803.36
3.1.7 GRA 33/11KV INJECTION SUBSTATION
3.1.7.1 CALCULATIONS FOR 11KV
3.1.7.1.1 OBA PALACE 11KV FEEDER
CALCULATIONS
TOTAL OUTAGE PERIOD: 114+55=169MINUTES
TOTAL SERVICE PERIOD: 44640MINUTES
AVAILABILITY=44640-169 44640
AVAILABILITY=0.99
3.1.7.1.2 GRA 11KV FEEDER
CALCULATIONS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
TOTAL OUTAGE PERIOD= 19+265+25+165+66= 540MINS
TOTAL SERVICE PERIOD=44640MINS
AVAILABILITY= 44640-540 = 0.98 44640
96
3.1.7.1.3 RESERVATION 11KV FEEDER
TOTAL OUTAGE PERIOD: 60MINS
TOTAL SERVICE PERIOD: 44640MINS
AVAILABILITY= 44640-60 44640
3.1.7.2 TRANSFORMER LOADING
3.1.7.2.1 Transformer 1
I= 15x10 6 √3x11x103x0.98
I= 803.36A
The full load current rating of the transformer=803.6A
MAXIMUM LOAD RECORDED ON THE TRANSFORMER=564A
% LOADING= 564 x 100 = 70.2% 803.36
3.1.7.2.2 Transformer 2
Transformer rated maximum load= 803.36A
% LOADING= 430 X 100 =53.5% 803.36
3.1.8 EVBUOTUBU 33/11KV INJECTION SUBSTATION
3.1.8.1 CALCULATIONS FOR 11KV FEDERS
97
3.1.8.1.1 EVBUOTUBU 11KV FEEDER
CALCULATIONS
%LOADING OF LINE = 288 X 100 = 71.7% 401.9
TOTAL LINE IMPEDANCE= (0.0024 + j 0.395) X 7 = (0.0168 + j2.8)Ω
VOLTAGE DROP = I X Z =288 X(0.0168 + j2.8) = (4.8 + j2.8)V
|V| = 0.8KV
TOTAL OUTAGE PERIOD = 931MINS
TOTAL SERVICE PERIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 -931 = 0.98 44640
3.1.8.1.2 ASORO 11KV FEEDER
CALCULATIONS
%LOADING OF LINE =255 X 100 = 63.5% 401.9
TOTAL LINE IMPEDANCE = (0.0024 + j0.395) X 8 = (0.019 + j 3.16)Ω
VOLTAGE DROP = I XZ = 255 X (0.019 + j 3.16) = (4.9 + j805)V
|V| =0.8KV
98
CALCULATIONS
TOTAL OUTAGE PERIOD = 810MINS
TOTAL SERVICE PERIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 810 = 0.98 44640
3.1.8.2 TRANSFORMER LOADING MAXIMUM LOADING = 543A
P =√3xIxVxCosø
RATED MAXIMUM CURRENT = 803.36A
% LOADING = 543 X 100 = 67.6% 803.36
3.1.9 FEDERAL SECRETERIAT 33/11KV INJECTION
SUBSTATION
3.1.9.1 CALCULATIONS FOR 11KV FEEDERS 3.1.9.1.1 NEW AUCHI 11KV FEEDER
CALCULATIONS
% LOADING OF LINE = 440 X 100 =109.5% 401.9
99
TOTAL LINE IMPEDANCE = (0.0024 + j0.395) X 6 = (0.0144 + j2.37) Ω
VOLTAGE DROP = I X Z = 440 X(0.0144 + j2.37) = (6.34 + j1042.8)V
|V| = 1.04KV
TOTAL OUTAGE PERIOD = 90+240+300+60+4=694MINS
TOTAL SERVICE PRIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE
TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 694 = 0.99 44640
3.1.9.1.2 FEDERAL HOUSING 11KV FEEDER
CALCULATIONS
% LOADING OF LINE = 180 X 100 = 44.8% 401.9
TOTAL LINE IMPEDANCE = (0.0024 + j 0.395) X 4 =(0.0096 + j1.58)Ω
VOLTAGE DROP = 180 x (0.0096 + j1.587) = (1.728 + j284.4)V
|V| =0.3KV TOTAL OUTAGE PERIOD = 120+105+60+185 = 470 MINS
TOTAL SERVICE PERIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 470 = 0.99 44640 3.1.9.2 TRANSFORMER LOADING
TRANSFORMER1 RATED CURRENT = 803.36A
% LOADING = 620 X 100 = 77.2% 803.36
100
TRANSFORMER 2
MAXIMUM LOAD = 190 + 110 = 300A
P =√3xIxVxCosø
RATED CURRENT = 803.36A
% LOADING = 300 X 100 = 37.3% 803.36
3.1.10 IKPOBA DAM 33/11KV INJECTION SUBSTATION 3.1.10.1 CALCULATIONS ON 11KV FEEDERS
3.1.10.1.1 DAM 11KV FEEDER
CALCULATIONS
% LOADING OF LINE = 200 X 100 = 49.8% 401.9
TOTAL LINE IMPEDANCE = (0.0024 + j0.395) X0.1 = (0.00024 + j 0.0395)Ω
VOLTAGE DROP = 200 X (0.00024 + j 0.0395) = (0.048 + j79)V
| V| =0.08KV
TOTAL OUTAGE PERIOD = 110MINS
TOTAL SERVICE PERIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640 – 110 = 0.98 44640
101
3.1.10.1.2 UPPER LAWANI 11KV FEEDER
CALCULATIONS
% LOADING OF LINE = 110 X 100 = 27.4% 401.9
TOTAL LINE IMPEDANCE = (0.0024 + j0.395) x 4 = (0.0096 + j1.58)Ω
VOLTAGE DROP = I X Z = 110 x (0.0096 + j1.58) = (1.056 + j173.8)V
|V| = 0.2KV
TOTAL OUTAGE PERIOD = 795MINS
TOTAL SERVICE PERIOD = 44640MINS
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 44640- 795 = 0.98 44640
3.1.10.1.3 OKHORO 11KV FEEDER
% LOADING = 190 X 100 = 47.3% 401.9
TOTAL LINE IMPEDANCE =(0.0024 +j 0.395) X 4.5 = (0.0108 + j1.8)Ω
VOLTAGE DROP = I x Z =190 x (0.0108 + j1.8)= (2.052 + j337.7)V
|V| =0.34KV TOTAL OUTAGE PERIOD = 549MINS
TOTAL SERVICE PERIOD = 44640
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
AVAILABILITY = 4640 4-549 = 0.99
102
44640
3.1.10.2 TRANSFORMER LOADING
3.1.10.2.1 TRANSFORMER 1
MAXIMUM LOAD = 200A
P =√3xIxVxCosø
RATED CURRENT = 401.7A
% LOADING = 200 X 100 = 49.1% 401.7
3.1.10.2.2 TRANSFORMER 2
MAXIMUM LOAD = 190 + 110 = 300A
P =√3xIxVxCosø
RATED CURRENT = 803.36A
% LOADING = 300 X 100 = 37.3% 803.36
3.2.0 SUBSTATIONS IN DELTA ENVIRONMENTS
3.2.1 OGHAREKI 33/11KV INJECTION SUBSTATION
3.2.1.1 CALCULATIONS ON 11KV FEEDERS
3.2.1.1.1 OGHAREKI 11KV FEEDER
CALCULATIONS
RATED CURRENT CAPACITY =401.9A
103
% LOADING OF LINE = 400 X 100 = 68.8% 401.9
TOTAL LINE IMPEDANCE=(0.0024+j0.395) x 10 = (0.024 + j3.95)Ω
VOLTAGE DROP = I X Z = 450 X(0.024 +j3.95)V = (10.8 +j1777.5)V
|V|=1.8KV
VOLTAGE AT THE MOST REMOTE SUBSTATION =11 – 1.8 = 9.2KV
CALCULATIONS:
TOTAL OUTAGE PERIOD: 15+40+25=80mins.
TOTAL SERVICE PERIOD: 31x24x60=44640mins
Availability of feeder= (44640-80)/44640 =0.99
3.2.1.2 TRANSFORMER LOADING
I=P/ √ 3xVx COSø = (15x106)/√3x11x103x0.98
Full load current = 803.36A
Maximum load recorded on the transformer =450A
3.2.2 OGHAREFE 33/11KV INJECTION SUBSTATION
3.2.2.1 CALCULATIONS ON 11KV FEEDERS 3.2.2.1.1 GOVERNOR 11KV FEEDER
CALCULATIONS
RATED CURRENT CAPACITY =401.9A
% LOADING OF LINE = 220 X 100 = 54.7% 401.9
104
TOTAL LINE IMPEDANCE =(0.0024 +j 0.395) X 6 =(0.0144 +j2.37)Ω
VOLTAGE DROP = I XZ = 220 X(0.0144 +j2.37) = (3.16 +j521.4)
|V| = 0.52KV
VOLTAGE AT THE MOST REMOTE SUBSTATION = 11 – 0.52 =10.48KV
No outage was recorded on the feeder in the month of May 2007. The availability
of the feeder is unity.
3.2.2.1.2 OTEFE 11KV FEEDER
CALCULATIONS
RATED CURRENT CAPACITY =401.9A
% LOADING OF LINE = 300 X 100 = 74.7% 401.9
TOTAL LINE IMPEDANCE=(0.0024 + j0.395) x 10 =(0.024+j3.95)Ω
VOLTAGE DROP = I X Z = 300 X(0.024 + j3.95) =(7.2 +j1185)
|V| = 1.2KV Total outage period = 526mins
Total period in the month = 44640mins
Availability = (44640-526)/44640 =0.98
3.2.2.2 TRANSFORMER LOADING
P = √3xIxVxCosø
Full load current = (15x106)/ (√3x11x103x0.98) = 803.36A
% Loading of transformer = 520/803.36 x100 =64.7%
105
PROTECTION AVAILABLE IN THE SUBSTATION
TRANSFORMER PROTECTION
1. Differential protection
2. Over current protection
3. Restricted earth fault protection
4. Buchholz (gas) protection
5. Winding temperature protection
6. Surge protection
LINE PROTECTION
1.Over current relays
2.Earthfault relays
3.2.3 BETA GLASS 33/11KV INJECTION SUBSTATION
3.2.3.1 CALCULATIONS FOR 11KV FEEDERS
3.2.3.1.1 UGHELLI 11KV FEEDER
CALCULATIONS
106
RATED CURRENT CAPACITY =401.9A
% LOADING = 200 X 100 = 48.7% 401.9 AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
No. of days in May=31
No. of hours in a day=24
No. of minutes in one hour=60
Total period of time in one month=31x24x60=44640
Period feeder was off service=275+22+21=318minutes
AVAILABILITY= (44640-318)/44640 =0.99
3.2.3.1.2 BETA GLASS 11KV FEEDER
RATED CURRENT CAPACITY = 401.9A
% LOADING = 150 X 100 = 36.5 % 401.9
TOTAL LINE IMPEDANCE = (0.0024 + j 0.395) X 3 = (0.0072 + j1.185)Ω
VOLTAGE DROP = I X Z = 150 X (0.0072 + j1.185) = (1.05 +j177.8)V
|V| = 0.2KV
AVAILABILITY = ACTUAL PERIOD FEEDER WAS IN SERVICE TOTAL SERVICE PERIOD
Availability = (44640-22) /44640 =0.99
Ughelli 11kv feeder: 200A
Beta glass 11kv feeder: 150A
Total: 350A
107
Rating of transformer: 7.5MVA
Cooling type: ONAF
Winding type: Yd11
CALCULATIONS
P = √3xIxVxcos
P=Power=7.5MVA
I=current
V=Voltage=11kv
Cosø=power factor=0.98
I= p/ (√3V cosø) = (7.5x106) / (√3x11x103x0.98) =401.68A
The substation is capable of supplying 401.68A
There is therefore, a reserve capacity of 401.68-350=51.68A
Percentage loading of the transformer = (350/401.68) x100 =87.13%
CHAPTER FOURSUMMARY AND DISCUSSION
TABLE 4.1 TABULATED SUMMARY OF 11KV FEEDERS
SUBSTATION FEEDER
LENGTH (KM)
CAPACITY (A)
MAX.LOAD(A)
%LOADING
NOMINALVOLTAGE (KV)
VOLTAGE DROP
(KV)%VOLTAGE REGULATION
AVAILABILITY
REMARKS
WELFARE
ST.SAVIOUR 3.0 401.9 70 17.4 11 0.10 0.9 0.97 SATISFACTORY
“ UPPER SAKPONBA
7.0 401.9 440 109.5 11 1.2 0.9 0.98 LINE IS OVER LOADED
GUINESS
NEW BENIN 8.0 401.9 270 67.2 11 0.8 7.2 0.99 SATISFACTORY
“ BDPA 4.0 401.9 230 70.3 11 0.36 3.3 0.97 SATISFACTORY“ ASABA 7.0 670.0 400 59.7 6.6 1.10 10.0 0.97 HIGN LOSSES
108
NEKPENEKPEN
FEEDER 1 7.0 401.9 350 87.1 11 0.17 1.6 0.88 SATISFACTORY
“ FEEDER 2 6.0 401.9 400 99.5 11 0.95 0.64 0.97 SATISFACTORY“ FEEDER 3 6.0 401.9 410 102.0 11 0.98 8.9 0.97 LINE IS OVER
LOADED“ FEEDER 4 7.1 401.9 220 54.7 11 0.62 5.6 0.98 SATISFACTORY
ETETE
IHAMA 5.0 401.9 432 107.5 11 0.90 8.2 0.95 LINE IS OVER LOADED
“ DUMEZ 6.0 401.9 264 65.7 11 0.63 5.7 N/A SATISFACTORY“ UGBOR 6.0 401.9 440 109.5 11 1.04 9.5 0.98 LINE IS OVER
LOADED“ UPPER SAPELE 7.0 401.9 316 78.6 11 0.90 8.2 0.97 SATISFACTORY
GRA OBA PALACE 7.0 401.9 285 70.9 11 0.78 7.1 0.99 SATISFACTORY“ GRA 6.0 401.9 279 69.4 11 0.67 6.1 0.98 SATISFACTORY“ RESERVATION 6.0 803.6 330 53.5 11 1.0 9.1 0.99 SATISFACTORY
EVBUOTUBU
EVBUOTUBU 8.0 401.9 288 71.7 11 0.8 7.3 0.98 SATISFACTORY
“ ASORO 8.0 401.9 255 63.5 11 0.8 7.3 0.98 SATISFACTORYFEDERA
L SECRETERIAT
NEW AUCHI 6.0 401.9 440 109.5 11 1.04 9.5 0.99 LINE IS OVER LOADED
“ FEDERAL HOUSING
4.0 401.9 180 44.8 11 0.3 2.7 0.99 SATISFACTORY
IKPOBA DAM
DAM 0.1 401.9 200 49.8 11 0.08 0.7 0.98 SAT SATISFACTORY ISFACTORY
“ UPPER LAWANI
4.0 401.9 110 27.4 11 0.2 1.8 0.98 SATISFACTORY
“ OKHORO 4.5 401.9 190 47.3 11 0.34 3.1 0.99 SATISFACTORYUGBOW
OUGBOWO 20.5 401.9 350 87.1 11 2.83 2.83 0.97 SATISFACTORY
“ FEDERAL GOVERNMENT
COLLEGE
7.0 401.9 110 27.3 11 1.9 1.9 0.99 SATISFACTORY
“ EGUADIAEKEN 9.0 401.9 180 44.8 11 0.64 0.64 0.99 SATISFACTORY“ USELU 10.0 401.9 350 87.1 11 1.4 1.4 0.98 SATISFACTORY
OGHAREKI
OGHAREKI 10.0 401.9 400 99.8 11 1.8 1.8 0.99 SATISFACTORY
OGHAREFE
GOVERNOR 6.0 401.9 220 54.7 11 0.52 0.52 1.0 SATISFACTORY
“ OTEFE 10.0 401.9 300 74.7 11 1.2 1.2 0.98 SATISFACTORYBETA
GLASSUGHELLI 12.0 401.9 200 48.7 11 0.95 0.95 0.99 SATISFACTORY
“ BETA GLASS 3.0 401.9 150 36.5 11 0.2 0.2 0.99 SATISFACTORYSILUKO OLIHA 6.0 401.9 360 89.57 11 0.9 0.9 0.95 SATISFACTORY
“ UPPER SILUKO 8.0 401.9 240 59.72 11 0.76 0.76 0.98 SATISFACTORY“ EDO TEXTILE
MILL6.1 401.9 290 72.2 11 0.7 0.7 0.93 SATISFACTORY
“ UWELU 8.0 401.9 320 77.9 11 1.0 1.0 0.97 SATISFACTORY
TABLE 4.2: TABULATED SUMMARY OF TRANSFORMERSSUBSTATION INSTALLED
CAPACITY(MVA)
MAX.LOAD
T1(A)
MAX.LOAD
T2(A)
%LOADING
T1
%LOADING
T2
%VOLTAGE
REGULATIONT1
%VOLTAGE
REGULATIONT2
REMARKS
UGBOWO 2X15 460 530 57.3 66.O 7.96 7.96 SATISFACTORYSILUKO 2X15 600 610 74.7 76.0 5.3 5.3 SATISFACTORYWELFARE 1X15 510 N/A 63.5 N/A 5.3 N/A SATISFACTORYGUINESS 1X15
1X7.5500 400 62.2 59.8 5.3 5.9 SATISFACTORY
NEKPENEKPEN 2X15 800 630 99.6 78.4 8.9 8.9 SATISFACTORYETETE 2X15 696 756 86.7 94.1 2.6 2.6 SATISFACTORYGRA 2X15 564 430 70.2 53.5 8.7 8.7 SATISFACTORYEVBUOTUBU 1X15 543 N/A 67.6 N/A 1.8 N/A SATISFACTORYFEDERAL SECRETERIAT
1X15 620 N/A 77.2 N/A 2.7 N/A SATISFACTORY
109
IKPOBA DAM 1X7.51X15
200 300 49.1 37.3 8.7 8.7 SATISFACTORY
OGHAREKI 1X15 450 N/A 56.1 N/A 2.7 N/A SATISFACTORYOGHAREFE 1X15 220 N/A 27.4 N/A 2.7 N/A SATISFACTORYBETA GLASS 1X7.5 350 N/A 87.1 N/A 2.7 N/A SATISFACTORY
DISCUSSION
The availability of the 11KV feeders and the injection substations was observed
to be quite low in some cases. This can be attributed to overloaded transformers
and poor distribution network.
It was also observed that feeders were taken off service due to poor generated
power.
The common denominators to all the substations in this study are:
All the substations have outdoor 33KV switchgear and indoor 11KV
switchgear.
All the transformers belong to the ONAN cooling system. It is highly
recommended that for the transformers to carry higher load especially in
overloaded substations, assisted cooling in the form of fans should be
provided.
In some substations with two transformers, it was observed that their
vector groups are dissimilar making it impossible to run them in parallel.
No frequency meter was found in any of the control rooms. This leads to
slow response to system disturbances and eventually lead to system
collapse.
110
It was observed that a 33/6.6KV transformer is in circuit at GUINNES
substation in Benin City. This should be upgraded to take care of the
overload and voltage drop problem being encountered by consumers on
that transformer.
Transformers were observed to have tripped on high winding temperature
on many occasions. This can be prevented if the temperature warning
alarms are made effective.
REFERENCES
Brown R.E (2002) “Electric Power Distribution Reliability” “Marcel Dekker, Inc. New York.
Billinton, R and Allan, R.N (1996) “Reliability Evaluation of Power Systems”. Platinum Press, New York, USA.
GEC –ALSTHOM (2004) ‘‘Network Protection and Automation Guide’’ ‘‘GEC- ALSTHOM, United Kingdom’’
111
Power Holding Company of Nigeria Hourly Reading Sheets and operational records.
112