Business Planning B1131 Module 1 : Business Planning & GAP Analysis Session 2
Abid Hussiny & Aneeqa Azeem
Strategies for Improvement Performance Improvement Plan
Water Supply
![Page 2: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/2.jpg)
What is a Strategy ?
• a plan of action designed to achieve a long-term or overall aim.
• A method or plan chosen to bring about a desired future, such as achievement of a goal or solution to a problem.
What is our strategy based on the gap analysis to achieve our kPI of Water supply or improve water supply operations and service delivery
![Page 3: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/3.jpg)
Group Work
![Page 4: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/4.jpg)
Strategies
1. Pressurised system is introduced –OHR 2. 24/7 is introduced – selection of area 3. Removal of all illegal connections and suction
pumps that people install on the water mains.
4. Effective billing and collection system 5. Effective O&M System & Monitoring system
![Page 5: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/5.jpg)
Strategies
1. Water Quality Monitoring system 2. Effective complain management system 3. Leakage detection program 4. Asset Replacement Plan of Poor or non
performing asset 5. Efficiency of tube wells is improved
![Page 6: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/6.jpg)
Group work
• Select any 5 strategies' • Add any strategy you wish to use • Match strategies to your SWOT • Check with mission and statement • On the Map of zone or sub division select
area and mark the strategy to be implemented
![Page 7: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/7.jpg)
Step
• Map or select Sub Division /Area • Location of OHR and pressurised system • Location of 24/7 zone • Location of leakage detection program • Selection of replacement area lines, TWs etc • Area of water quality samples • Illegal connections • After completing the exercise – Check the work of
same sub division in the IDAMP
![Page 8: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/8.jpg)
Prepare Performance improvement Plan
• Discuss the Framework • Start working on the Framework of PIP based
on selected area and strategies
![Page 9: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/9.jpg)
Example- demonstration
• O&M system for WASAs• AMIS System for WASAs• Consumer Survey for WASAs• GIS system for WASAs
![Page 10: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/10.jpg)
Service Improvement by Replacement & Extension of Water Supply Network
Steps:
1. Marking of lines to be replaced on GIS base map2. Marking of New lines on GIS base map for improving %
of water supply coverage3. Tube well Rehabilitation 4. Operationalization of OHRs5. Making Project in phased manners6. Costing of Projects based on pipe length
2
Business Planning B1131 Module 1 : Business Planning & GAP Analysis Session 1
![Page 11: Performance Improvement Plan Water Utilities](https://reader036.vdocument.in/reader036/viewer/2022091121/58abc8091a28ab68068b52cb/html5/thumbnails/11.jpg)
Costing
Project CostWater Supply Pipe replacement or New Installation
Diameter Length Unit Cost (Per meter) Pipe Cost
(A)Construction Cost
(B)Total Cost
(A+B)3" 4" 6"
3
Business Planning B1131 Module 1 : Business Planning & GAP Analysis Session 1