performance of sheet pile wall in peat - semantic …...sheet piles and sheet pile design state of...

14
Performance of Sheet Pile Wall in Peat Yong Tan 1 and Samuel G. Paikowsky 2 Abstract: To study the performance of sheet pile wall in peat during roadway construction, a long-term instrumentation program was conducted over a period of two years, measuring total lateral earth pressures, sheet pile deflections, soil movements, and water table level variances during construction. The analysis of field data indicated: 1 The earth pressure distribution in peat matched well with the classic Rankine earth pressure; 2 the expected long-term postconstruction sheet pile movement due to the creep behavior of peat was not observed; 3 fully passive earth pressure in peat was mobilized once the maximum measured sheet pile deflection exceeded 0.8% of sheet pile length; and 4 arching effect due to the protruding cross section of sheet pile caused pressure differences of 3–10 kPa between the inside web and outside web of the sheeting. Then, all the construction stages were continuously modeled by finite-element method and the calculated results were compared with the field measurements. The comparisons showed that the calculated results were consistent with the field data and provided reasonable explanations and helpful insights to understand soil–structure interaction mechanism. Finally, some conclusions and suggestions for sheet pile design and construction in peat were reached. DOI: 10.1061/ASCE1090-02412008134:4445 CE Database subject headings: Earth pressure; Sheet pile; Instrumentation; Finite element method; Retaining walls; Waterfront structures. Introduction Sheet pile wall is a common type of flexible earth retaining sys- tem used as waterfront structure. One of its advantages to other types of retaining walls is that the construction of sheet pile wall usually does not require dewatering the site. Sheet piling is ide- ally applicable to sites with high groundwater tables or soils with low bearing capacity. Calculations of earth pressures in sheet pile design are usually based on classical soil mechanics; however, the actual earth pressure distributions along sheet pile wall have not been very well understood. Experimental and field-measured data will be helpful to verify and when needed, to modify current design criteria. Substantial experimental research and field measurements Terzaghi 1934; Coyle and Bartoskewitz 1976; Sherif et al. 1982; Fang and Ishibashi 1986; Bentler and Labuz 2006 have been carried out regarding the lateral earth pressures developing against rigid retaining walls. By contrast, only a limited number of studies have been conducted to examine current sheet pile design procedures via experimental or field-measured data Peck 1943; DiBiagio 1977; Stille 1979; Finno 1989; Endley et al. 2000. Further, most of these studies were related to anchored or strutted sheet piles in excavation, or only measured strut or an- chor loads instead of measuring earth pressures directly. Even fewer studies are known to investigate passive earth pressures against the supporting face of a sheet pile. So far, no study is known to directly measure passive earth pressures against canti- lever sheet pile walls, especially in peat deposits. Peat is a material consisting largely of organic residues, which originates under aerobic and anaerobic conditions through incom- plete decomposition of plant and animal matters. Because it ex- hibits low bearing capacity, extremely high compressibility, and long-term creep behavior, peat is characterized as one of the worst foundation soils. Different from clays, majority of the de- formation in peat is not caused by dissipation of pore pressure primary consolidation, but by volume changes resulting from continuous rearrangement of soil particles under a constant verti- cal effective stress after pore pressure dissipates secondary com- pression. The significant creep behavior of peat is one of the great concerns for construction in peatlands. Extensive studies of peat creep behavior have been performed in recent years, result- ing in important advancements in understanding its mechanism Buisman 1936; Harahan 1954; Adams 1963; MacFarlane and Allen 1964; Barden 1969; Berry and Poskitt 1972; Mesri 1973; Berry and Vickers 1975; Dhowian 1978; Mesri and Godlewski 1979; Dhowian and Edil 1980; Fox 1992; Fox et al. 1992; Mesri et al. 1994; Ernst et al. 1996; Mesri et al. 1997; Colleselli and Cortellazo 1998; Elsayed 2003. Fox 1992 pointed out: 1 Compression of peat requires a long term to be completed; 2 primary consolidation of peat occurs rapidly; and 3 the magni- tude and rate of secondary compression are high for peat and may account for as much as half of the total settlements. Mesri et al. 1997 attributed the reason why the secondary compression in peat is often more significant than in other geotechnical materials to three factors: 1 Peat deposits exist at high natural water con- tents and void ratios; 2 among geotechnical materials, peat has the highest ratio of C / C C , where C secondary compression index and C C compression index; and 3 the time for primary consolidation of peat deposits is relatively short; hence, secondary 1 Geotechnical Engineer, WPC, Inc., 2201 Rowland Avenue, Savan- nah, GA 31404 corresponding author. E-mail: tanyong21th@ hotmail.com 2 Professor, Dept. of Civil and Environmental Engineering, Univ. of Massachusetts Lowell, One University Ave. Lowell, MA 01854. Note. Discussion open until September 1, 2008. Separate discussions must be submitted for individual papers. To extend the closing date by one month, a written request must be filed with the ASCE Managing Editor. The manuscript for this paper was submitted for review and pos- sible publication on January 18, 2007; approved on September 6, 2007. This paper is part of the Journal of Geotechnical and Geoenvironmental Engineering, Vol. 134, No. 4, April 1, 2008. ©ASCE, ISSN 1090-0241/ 2008/4-445–458/$25.00. JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / APRIL 2008 / 445

Upload: others

Post on 24-Mar-2020

20 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

Performance of Sheet Pile Wall in PeatYong Tan1 and Samuel G. Paikowsky2

Abstract: To study the performance of sheet pile wall in peat during roadway construction, a long-term instrumentation program wasconducted over a period of two years, measuring total lateral earth pressures, sheet pile deflections, soil movements, and water table levelvariances during construction. The analysis of field data indicated: �1� The earth pressure distribution in peat matched well with the classicRankine earth pressure; �2� the expected long-term postconstruction sheet pile movement due to the creep behavior of peat was notobserved; �3� fully passive earth pressure in peat was mobilized once the maximum measured sheet pile deflection exceeded 0.8% of sheetpile length; and �4� arching effect due to the protruding cross section of sheet pile caused pressure differences of 3–10 kPa between theinside web and outside web of the sheeting. Then, all the construction stages were continuously modeled by finite-element method and thecalculated results were compared with the field measurements. The comparisons showed that the calculated results were consistent withthe field data and provided reasonable explanations and helpful insights to understand soil–structure interaction mechanism. Finally, someconclusions and suggestions for sheet pile design and construction in peat were reached.

DOI: 10.1061/�ASCE�1090-0241�2008�134:4�445�

CE Database subject headings: Earth pressure; Sheet pile; Instrumentation; Finite element method; Retaining walls; Waterfrontstructures.

Introduction

Sheet pile wall is a common type of flexible earth retaining sys-tem used as waterfront structure. One of its advantages to othertypes of retaining walls is that the construction of sheet pile wallusually does not require dewatering the site. Sheet piling is ide-ally applicable to sites with high groundwater tables or soils withlow bearing capacity. Calculations of earth pressures in sheet piledesign are usually based on classical soil mechanics; however, theactual earth pressure distributions along sheet pile wall have notbeen very well understood. Experimental and field-measured datawill be helpful to verify and when needed, to modify currentdesign criteria.

Substantial experimental research and field measurements�Terzaghi 1934; Coyle and Bartoskewitz 1976; Sherif et al. 1982;Fang and Ishibashi 1986; Bentler and Labuz 2006� have beencarried out regarding the lateral earth pressures developingagainst rigid retaining walls. By contrast, only a limited numberof studies have been conducted to examine current sheet piledesign procedures via experimental or field-measured data �Peck1943; DiBiagio 1977; Stille 1979; Finno 1989; Endley et al.2000�. Further, most of these studies were related to anchored orstrutted sheet piles in excavation, or only measured strut or an-

1Geotechnical Engineer, WPC, Inc., 2201 Rowland Avenue, Savan-nah, GA 31404 �corresponding author�. E-mail: [email protected]

2Professor, Dept. of Civil and Environmental Engineering, Univ. ofMassachusetts Lowell, One University Ave. Lowell, MA 01854.

Note. Discussion open until September 1, 2008. Separate discussionsmust be submitted for individual papers. To extend the closing date byone month, a written request must be filed with the ASCE ManagingEditor. The manuscript for this paper was submitted for review and pos-sible publication on January 18, 2007; approved on September 6, 2007.This paper is part of the Journal of Geotechnical and GeoenvironmentalEngineering, Vol. 134, No. 4, April 1, 2008. ©ASCE, ISSN 1090-0241/

2008/4-445–458/$25.00.

JOURNAL OF GEOTECHNICAL AND

chor loads instead of measuring earth pressures directly. Evenfewer studies are known to investigate passive earth pressuresagainst the supporting face of a sheet pile. So far, no study isknown to directly measure passive earth pressures against canti-lever sheet pile walls, especially in peat deposits.

Peat is a material consisting largely of organic residues, whichoriginates under aerobic and anaerobic conditions through incom-plete decomposition of plant and animal matters. Because it ex-hibits low bearing capacity, extremely high compressibility, andlong-term creep behavior, peat is characterized as one of theworst foundation soils. Different from clays, majority of the de-formation in peat is not caused by dissipation of pore pressure�primary consolidation�, but by volume changes resulting fromcontinuous rearrangement of soil particles under a constant verti-cal effective stress after pore pressure dissipates �secondary com-pression�. The significant creep behavior of peat is one of thegreat concerns for construction in peatlands. Extensive studies ofpeat creep behavior have been performed in recent years, result-ing in important advancements in understanding its mechanism�Buisman 1936; Harahan 1954; Adams 1963; MacFarlane andAllen 1964; Barden 1969; Berry and Poskitt 1972; Mesri 1973;Berry and Vickers 1975; Dhowian 1978; Mesri and Godlewski1979; Dhowian and Edil 1980; Fox 1992; Fox et al. 1992; Mesriet al. 1994; Ernst et al. 1996; Mesri et al. 1997; Colleselli andCortellazo 1998; Elsayed 2003�. Fox �1992� pointed out: �1�Compression of peat requires a long term to be completed; �2�primary consolidation of peat occurs rapidly; and �3� the magni-tude and rate of secondary compression are high for peat and mayaccount for as much as half of the total settlements. Mesri et al.�1997� attributed the reason why the secondary compression inpeat is often more significant than in other geotechnical materialsto three factors: �1� Peat deposits exist at high natural water con-tents and void ratios; �2� among geotechnical materials, peat hasthe highest ratio of C� /CC, where C��secondary compressionindex and CC�compression index; and �3� the time for primary

consolidation of peat deposits is relatively short; hence, secondary

GEOENVIRONMENTAL ENGINEERING © ASCE / APRIL 2008 / 445

Page 2: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

compression will appear as long as construction loading is com-pleted. Weber �1969� reported a case that the embankments con-structed over peat deposits in the San Francisco Bay experiencedlinear secondary settlements over 25 years. Currently, the ex-tremely poor engineering properties of peat, especially its signifi-cant creep behavior, do limit and challenge construction in peatdeposits. Considering the fact that peatlands cover a total ofaround 5–8% of global land mass �Lappalaine 1996�, constructionin peat will be more and more inevitable, especially in thosecountries or areas with large distributions of peatlands.

At the site of highway US Route 44 relocation project inCarver, Mass., long steel sheet pile walls were installed in wet-land areas with peat deposits to mitigate environmental impacts.More than 60% of the deformation in Carver peat was predictedto take place in the secondary compression phase �Ernst et al.1996�. Therefore, significant long-term postconstruction sheet pilemovements were expected. The existence of peat deposits pre-sented major obstacles to construction at this site. It also chal-lenged current understanding of earth pressures acting againstsheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations locatedin deep peat deposits were selected for instrumentation, measur-ing total lateral earth pressures, sheet pile deflections, soil move-ments induced by embankment construction, and water table levelvariances during roadway construction.

In order to understand soil–structure interaction mechanismduring construction, finite-element method �FEM� analysis wasconducted to model the entire roadway construction in peat. AsClough and Duncan �1971� introduced FEM into soil–structureinteraction analysis, many researchers had performed FEM mod-eling for different types of retaining structures under differentconstruction conditions �Clough 1977; Clough and Hansen 1981;Clark and Wroth 1984; Borja and Lee 1990; Finno and Harahap1991; Ng and Lings 1995; Ou et al. 1996�. However, most knownstudies focused on modeling soil–structure interaction under onespecific construction condition, and hence the accumulated effectsof continuous construction activities were not considered. Further,few studies are known to model performance of a retaining struc-ture during deep dynamic compaction �DDC�. In this study, all ofthe roadway construction activities �including peat removal, back-filling, consolidation, DDC, and construction of mechanically sta-bilized earth �MSE� wall and embankment� were continuouslymodeled for a period of 3.5 years based on the constructionrecords. Then, the FEM-calculated results were compared withthe field measurements to study sheet pile performance duringroadway construction in peat deposits.

Route 44 Relocation Project and Site Conditions

Section I of Route 44 relocation project started from the town ofCarver, Mass., in the vicinity of Route 58 and extended approxi-mately 9.5 km �5.9 mi� eastward to meet Section II in Kingstonnear the Plymouth and Kingston town line, Massachusetts. Theproposed highway was a four-lane divided roadway with a typicalmedian width of 18.3 m �60 ft�. The project included constructionof eight on/off ramps and reconstruction or realignment of por-tions of four secondary roadways that intersected the proposedhighway.

Many areas of this project required embankment fills to ac-commodate the proposed highway. Unfortunately, a large portionof the proposed embankments was to be constructed in cranberry

bog and pond areas. A series of field exploration programs includ-

446 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINE

ing standard penetration testing �SPT� and peat probing had beenconducted along the proposed roadway to investigate site condi-tions. Fig. 1 presents the typical soil profiles of stations 98+00 Rto 110+00 R in cranberry bogs. Organic soils were found imme-diately below the ground surface in bog and pond areas, whichconsisted primarily of peat. The investigated thickness of peatdeposits ranged from 0 to 10.5 m �35 ft�. In cranberry bog areas,long-term groundwater was observed to be near the existingground surface. Directly below peat deposits were natural me-dium dense to dense sands, interbedded with gravels and inor-ganic silts.

If embankments were built directly over peat deposits, as peatareas varied in thickness, long-term settlements would not be uni-form beneath the embankments and would differ sharply betweenareas overlying peat and areas overlying sands. The consequentdifferential settlements would cause local depressions in roadwayand continue to be a maintenance problem. Leaving peat in placewould also cause uncertainties to global embankment stability.The above-mentioned effects were considered to negatively out-weigh the factors involved in removing peat entirely. Therefore, itwas determined to replace the peat at the locations of proposedembankment with suitable granular soils. In order to mitigate con-struction impacts on wetlands, long steel sheet pile walls with acumulative length of approximately 2.4 km �1.5 mi� were in-stalled on both sides of the proposed roadway in wetland areas asretaining structures.

Soil Properties

The peat in the wetland areas at Carver, Mass., was the result oforganic deposit accumulation over a lengthy period of time inkettle holes created by glaciers �Ernst et al. 1996�. A series oflaboratory testing programs including one-dimensional consolida-tion tests and triaxial tests had been carried out by Elsayed �2003�to investigate its engineering properties. Carver peat contains60–77% porous fiber. It exhibits extremely high compressibility,low strength, and significant “creep” behavior. Table 1 summa-rizes its index properties and engineering parameters. The stiff-ness �elastic modulus� and strength parameters �friction angle andcohesion in terms of effective stress concept� of Carver peat weredetermined from consolidated undrained �CU� triaxial tests onundisturbed peat samples. The CU testing results suggested fol-lowing strength parameters for Carver peat: effective angle offriction, ��, of 12° and effective cohesion, c�, of 2.0 kPa.

To quantify the engineering properties of the backfill and thein situ sands below the peat deposits at the project site, laboratorytests, including triaxial tests, had been conducted on representa-tive soil samples collected from the field. The backfill mainlyconsisted of loose to medium dense sands, with traces of gravelsand inorganic silts. Its unit weight was around 18 kN /m3 andeffective friction angle of around 32°. For the natural mediumdense to dense sand underneath the peat deposits, it had a unitweight of around 19.5 kN /m3 and effective friction angle ofaround 36°.

Construction

Construction work in the wetland areas started in winter, 2001and was almost completed in spring, 2005. Fig. 2 illustrates themain construction stages in the wetlands at the relocated US

Route 44 in Carver, Mass.

ERING © ASCE / APRIL 2008

Page 3: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

Stage I—Replacement of Peat with Backfill

Prior to peat removal, sheet pile walls were installed along bothsides of the proposed roadway in the wetlands since November,2001. Then, the peat between the sheet pile walls was completely

Fig. 1. Soil profiles of s

Table 1. Index Properties and Engineering Parameters of Carver Peat �B

Parameter name Symbol

Total unit weight � �kLiquid limit L.L.

Plastic limit P.L.

Water content w

Organic content Oc

Permeability in horizontal direction Kx

Permeability in vertical direction Ky

Effective cohesion c�Effective friction angle ��Initial elastic modulus Eo

Elastic modulus at failure Ef

Compression index CC

Swelling index CS

Secondary compression index C�

Initial void ratio eo

JOURNAL OF GEOTECHNICAL AND

removed and backfilled with granular materials. Peat excavationwas accomplished using a crane outfitted with a dragline bucketwithout dewatering. After removing the peat, granular soils wereplaced between the sheet pile walls and were pushed forward bya dozer.

98+00 R to 110+00 R

n Elsayed 2003�

Magnitude Note

10.43 ASTM D 4531

590 Atterberg test

390 Atterberg test

759–950 ASTM D 2974

60–77 ASTM D 2974

3.05�10−7 Permeability test �constant head�

3.48�10−8 Permeability test �constant head�

2.0 Triaxial test �CU�

12 Triaxial test �CU�

1,100 Triaxial test �CU�

160 Triaxial test �CU�

3.4 Consolidation test

0.47 Consolidation test

0.15 Consolidation test

8.0 Consolidation test

tations

ased o

Unit

N /m3��%�

�%�

�%�

�%�

�m/s�

�m/s�

�kPa�

�°��kPa�

�kPa�

GEOENVIRONMENTAL ENGINEERING © ASCE / APRIL 2008 / 447

Page 4: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

Stage II—Consolidation

Following the completion of Stage I in January, 2002, the site wasleft for consolidation for about 1 1 /2 years. During this period,there were no recorded construction activities beyond installationof the instrumented sheet piles in January, 2003, which will beintroduced in a later section entitled “Instrumentation.”

Stage III—Deep Dynamic Compaction

Because the site was not dewatered during the process of peatreplacement, it was suspected that the backfill was in a loose,saturated state, susceptible to liquefaction during earthquakes. Inthe summer of 2003, the backfill was densified by two passes ofDDC. The time interval between the two passes of DDC was 6days. A 14.4 t tamper, 1.5 m in diameter, was dropped from aheight of 18.3 m �60 ft�. Each tamping point was repeatedly im-pacted by nine blows. The distance between two adjacent tamping

Fig. 2. Construction in the wetland areas

points in each pass was 4.6 m. The second pass was conducted at

448 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINE

the center spacing of the first pass. To avoid unexpected largesheet pile deflection, the minimum distance between the tampingpoints and the sheet pile wall was designed to be 4.6 m. Conepenetration testing �CPT� was carried out before and after eachpass of DDC to investigate compaction effects. The site-characterization results indicated that DDC greatly densified thebackfill, but showed very limited effects on the natural mediumdense to dense sands below �Tan et al. 2007�.

Stage IV–Consolidation

After Stage III, the site was left for consolidation for about 1 /2–1year without construction activities recorded.

Stage V–MSE Wall and Embankment Construction

Construction of MSE walls and embankments started in 2004.The MSE walls and embankments were designed to be 7.6 m�25 f� away from the sheet pile wall, and the embankments wereaveragely 4.3 m �14 ft� above the backfill ground surface. TheMSE walls consisted of six soil layers reinforced by steel stripswith a dimension of 4 mm �thick� �50 mm �wide� �3.7 m�long�, which were installed at a spacing of 0.6 m �2 ft� in bothvertical and horizontal directions. One end of the steel strips wasfixed to the facade panels of the MSE walls, which were basicallyconcrete panels with a dimension of 1.5 m �5 ft��1.8 m �6 ft� inplane and 14 cm �5.5 in.� in thickness. The MSE walls served asretaining structures to ensure the stability of the embankments.

Stage VI–Completion

Pavements were finally laid over the embankments, and the top ofthe sheet pile walls was cast with concrete caps in Spring 2005.Sheet pile walls were left in the wetlands permanently, function-ing as supporting structures of the roadway. Fig. 3 presents atypical view of the completed roadway in the cranberry bogaround stations 99+00 R to 103+00 R.

Major construction activities, together with the dates whenparticular activities were conducted at five instrumented stations,are summarized in Table 2. Major construction activities refer tothose which induced significant earth pressure variations or sheet

Fig. 3. Typical completed roadway in cranberry bog

pile deflections.

ERING © ASCE / APRIL 2008

Page 5: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

Instrumentation

In order to measure sheet pile wall deflections, total lateral earthpressures developing in peat against the supporting face of thesheet pile wall, soil movements induced by embankment con-struction, and water table level variances in peat, five stationslocated in the cranberry bogs and ponds with deep peat depositswere chosen for instrumentation. The instruments at each stationconsisted of two clusters of pressure cells, two inclinometer cas-ings, and one piezometer. Figs. 4 and 5 show detailed locations ofvarious instruments at station 101+00 R. The top of the instru-mented sheet pile was 0.9 m �3 ft� above the ground surface.Three vibrating wire total pressure cells �TPC� �designated as A,B, and C� along with four tactile single load cells �designated asGup, Gdown, Hup, and Hdown� composing one cluster were installed

Fig. 4. Typical road cross section at the instrumented station

Table 2. Major Construction Activities at Five Instrumented Stations

JOURNAL OF GEOTECHNICAL AND

on the inside web of the sheeting, whereas the remaining threeTPC cells �designated as D, E, and F� along with two tactilesingle load cells �designated as Jup, and Jdown� composing anothercluster were installed on the outside web. The purpose of instru-menting pressure cells on both inside and outside webs was tostudy potential arching effect induced by the protruding cross-

Fig. 5. Schematic view of sheet pile instrumentation layout

GEOENVIRONMENTAL ENGINEERING © ASCE / APRIL 2008 / 449

Page 6: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

section shape of sheet pile. In order to obtain appropriate calibra-tion factors for field measurements, all the TPC cells were cali-brated in laboratory, and on average the accuracy was around 5%�5 kPa� and resolution 0.007 kPa. Detailed information about thevibrating wire TPC cells, the tactile single load cells, and theircalibration can be found in Tan �2005�. Two 10 cm �4 in.��10 cm �4 in.��0.6 cm �0.25 in.�steel notched angles, whichled the reading cables of the instruments to the ground surface,were welded on the instrumented sheet pile along depth.

To monitor sheet pile deflections, an inclinometer casing,which was secured by an iron pipe, was affixed to the corner ofthe sheet pile. The length of the inclinometer casing was equal tothat of the instrumented sheet pile. In March 2004, prior to em-bankment construction, another 13.7 m �45 ft� long inclinometercasing was grouted into a predrilled hole in the backfill �accessroad� at each instrumented station to monitor the soil movementscaused by embankment construction. This inclinometer casingwas located 4.6 m �15 ft� away from the proposed embankment,and 3.0 m �10 ft� away from the sheet pile wall. A standpipe pi-ezometer for water table levels was installed inside a borehole inpeat at each instrumented station, 0.9 m �3 ft� away from the in-strumented sheet pile and embedded at a depth of 1.8 m �6 ft�below the ground surface. During DDC and the followingmonths, pore pressure variations were monitored by a vibratingwire piezometer located at a depth of 1.8 m below the groundsurface. Detailed descriptions of sheet pile instrumentation designand instrumentation preparation in both laboratory and machineshop can be found in Tan �2005�.

Prior to installation of the instrumented sheet piles, zero read-ings were taken for all the pressure cells. The instrumented sheetpiles were not installed in situ until January 2003, about 1 yearafter peat removal. The process of field installation was basicallyreplacing the existing sheet pile at the selected station with theinstrumented sheet pile, and was composed of the following mainsteps: �1� Installing a temporary protective sheet pile into thebackfill within few inches from the existing sheet pile; �2� pullingout the existing sheet pile; �3� installing the instrumented sheetpile; and �4� pulling out the temporary protective sheet pile.

Generally, the readings of the TPC cells and the tactile singleload cells were taken by a portable readout box and an ohmmeter,respectively. Inclinometer readings were taken by an inclinometerprobe along with a portable readout box. During DDC, data read-ings of both pressure cells and vibrating wire piezometers wererecorded, stored and processed using a multiple-channel data log-ger system, which was programmed to take readings at a 2 mininterval.

Field Measurements

Although no field measurements were available before in-situ in-stallation of the instrumented sheet piles, it could be expected thatpeat excavation �unloading� and backfilling �loading� should havesome effects on the overall response of the peat on the supportingside. However, the extent of such influence should be limited.Considering the facts that the unit weight of peat �10.43 kN /m3�is only slightly greater than that of water �9.8 kN /m3� and the sitewas not dewatered during peat excavation, the pressure differ-ences on both sides of the sheet pile wall should be very smalland the sheet pile deflections induced by excavation would bevery limited. As a result, large strains should not be expected tooccur in the supporting peat during unloading. Backfilling process

would have relatively more significant effects on the stress–strain

450 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINE

behavior of peat due to much greater unit weight and strength ofthe backfill. These effects will be discussed in a later sectionentitled “Comparison between Measurements and CalculatedResults.”

Field measurements including total lateral earth pressures andwater table levels were taken immediately after the instrumentedsheet piles were installed in-situ. Only 3 out of 30 TPC weredamaged during this field installation process, which were cells Eat stations 101+00 R and 156+25 R and cell B at station 141+00 R. Unfortunately, only two tactile single load cells located atpositions Gup and Gdown at station 101+00 R functioned well afterfield installation of the instrumented sheet piles. Due to its flex-ible thin-film structure, tactile single load cell was susceptible tothe force induced by driving the instrumented sheet pile into soils.No pressure cell readings were available after November 8, 2004,as the cables of all the pressure cells were accidentally cut offduring construction Stage VI in early Spring 2005. The last incli-nometer readings were taken on April 8, 2005.

During the entire monitoring period, the instrumented sheetpiles at five stations behaved similarly. In addition, only pressurereadings at stations 101+00 R and 117+50 R were recorded dur-ing DDC. Based on the previous considerations and paper lengthlimit, this study only presents and discusses the measured resultsat station 101+00 R. As only two tactile single load cells func-tioned, their measurements are not presented here either but canbe found in Tan �2005�.

At station 101+00 R, the length of the instrumented sheet pilewas 14.6 m �48 ft�. Peat deposit was 4.6 m �15 ft� deep. Long-term water table level was near the existing ground surface. Allthe pressure cells were located in the peat deposits at this station.Detailed locations of the instruments at station 101+00 R refer toFigs. 4 and 5.

Total Lateral Earth Pressures and Pore Pressures

Fig. 6 shows the development of measured total lateral earth pres-sures and pore pressure at station 101�00 R from January 17,2003 to November 8, 2004. The left, central, and right graphsdescribe measured pressures before, during, and after DDC, re-spectively. The first readings were taken immediately upon thecompletion of field installation of the instrumented sheet pile onJanuary 17, 2003. The TPC cell at position E did not functionafter installation. Within the following week, three additionalreadings were taken for each pressure cell, showing no significantchanges except the immediate reduction after the first reading.This immediate reduction was possibly due to the consolidationof peat, which was caused by the decay of excess pore pressuresdeveloping around the cell pad during the driving process of theinstrumented sheet pile. Similar observations had been reportedby Tedd and Charles �1981, 1983� and Carder and Symons�1989�, who used “push-in” spade cells in London clay. This re-duction was around 2 kPa on the inside web �positions A, B, C�,and was 3.5 and 6.9 kPa at positions D and F on the outside web,respectively. Then, except for position B, the earth pressures didnot show significant variations over time until the application ofDDC. The small variations in pore pressure �piezometer readings�were mainly caused by seasonal water level fluctuations. At po-sition B, about two weeks after installation, the earth pressurejumped abruptly from 34.5 to 43.5 kPa due to some unknownreasons. It continued to go up till 58.6 kPa in the following onemonth, and then came down gradually to its initial value. Suchabnormal measurement was not observed at other stations. It was

also noticed that at the completion of field installation of the

ERING © ASCE / APRIL 2008

Page 7: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

instrumented sheet pile, the pressures measured on the inside webwere equal to those measured on the outside web at the samedepth. However, a pressure difference developed shortly after andalmost kept constant with time. At positions A and D, this pres-sure difference was around 3.4–4.8 kPa, and was around 6.9 kPaat positions C and F. Similar observation had been reported byDiBiagio �1977�, who attributed such pressure difference to sheetpile movement or soil consolidation. In this study, one possiblereason might be the arching effect across the flange and the out-side web �recessed back� of the sheeting, which resulted in dif-ferent values measured on the inside and outside webs.

During each pass of DDC, the measured total lateral earthpressures jumped rapidly to peaks and then went down quickly asDDC stopped. At each position, the measured pressure incrementinduced by the first pass of DDC was greater than that induced bythe second pass. This can be explained by the fact that the mini-mum distance from the tamping points to the sheet pile wall in thefirst-pass DDC was 2.3 m less than the minimum distance in thesecond pass. During dynamic compaction, it would be expectedthat most of the stress increments, ��, induced by DDC would becarried by pore pressures, �u, and very few carried by soil skel-eton, as water could not escape out of the undrained peat withinsuch short time. This assumption was verified by FEM simula-tion, which will be introduced in a later section. However, themeasured pore pressure increment during DDC was much smallercompared with the measured earth pressure increments. This phe-nomenon implies that the vibrating wire piezometer used in thisstudy has a very limited ability to correctly measure pore pressuredevelopment in short-duration case such as dynamic compaction.Both the residual total lateral earth pressures and pore pressureafter DDC continuously went down at reduced rates and almostrecovered to their original values in the following one to two

Fig. 6. Field measured total lateral earth p

months. Then, the measured pressures stabilized until embank-

JOURNAL OF GEOTECHNICAL AND

ment construction. The pressure difference after DDC betweenthe inside web and outside web increased to around 4.8–6.9 kPaat positions A and D, and to 6.9–10.4 kPa at positions C and F.The measured pressures tended to decrease gradually followingthe completion of embankment construction, and the reductionrates at the upper positions A and D were greater than those at thelower positions C and F.

Fig. 7 shows the comparison between the measured and thetheoretical total lateral earth pressures at station 101+00 R. Thetheoretical at-rest, active and passive earth pressure distributionswere calculated using the at-rest earth pressure theory �Jaky 1944�and classic active and passive Rankine earth pressure theories.These calculations used ��=12°, c�=2 kPa for peat with assumedground water level at the ground surface. The measured earthpressure distributions along depth were almost linear. Except forthose measured during and shortly after DDC, the measured earthpressures at positions A, B, and F were close to the passive Rank-ine earth pressures, whereas at positions D and C, they were about3.5–6.9 kPa greater. This comparison indicated that fully passiveearth pressures had already been mobilized in the supporting peatat the time of field installation of the instrumented sheet pile.

Sheet Pile Wall Deflections

Due to heavy snow and extremely cold weather, the first sheetpile deflection readings were not taken until February 28, 2003,almost 40 days after field installation of the instrumented sheetpiles. Although sheet pile deflections were not measured duringthe process of peat excavation and backfilling, the first measuredsheet pile deflections actually had included the deflections in-duced by replacing peat with backfill. Fig. 8 summarizes the mea-sured sheet pile deflection toward the supporting peat at station

es and pore pressure at station 101+00 R

ressur

101+00 R. The first reading indicated that at the time of field

GEOENVIRONMENTAL ENGINEERING © ASCE / APRIL 2008 / 451

Page 8: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

installation of the instrumented sheet pile, the sheet pile had al-ready developed deflection toward the supporting peat, which wasaround 20 cm relative to the verticality at its top. In the followingthree and a half months, the sheet pile developed additional de-

Fig. 8. Measured sheet pile lateral movement at station 101+00 R

Fig. 7. Comparison between measu

452 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINE

flection of around 2.5 cm till June 12, 2003. Then, deflectionstopped developing until DDC. During the two passes of DDC�September 10–16, 2003�, the sheet pile developed large unrecov-erable deflection toward peat, which was around 10 cm. Lateralearth pressures also experienced large increments within the sameperiod. After compaction was completed on September 16, 2003,no postconstruction sheet pile movement was observed in thefollowing six months. During the embankment construction �fromMarch 25 to July 20, 2004�, the sheet pile developed further de-flection toward peat which was around 6.5 cm. On the contrary,the measured lateral earth pressures did not show any significantchanges. The measurements in the following eight months afterthe completion of embankment indicated that the sheet pile move-ment had completely stopped and the sheet pile wall had beenstabilized.

In summary, the total measured sheet pile deflection at station101+0 R was 39 cm, of which, 58% �22.5 cm� occurred prior toground improvement �DDC�, 26% �10 cm� occurred during DDC,and only 16% �6.5 cm� occurred during embankment construc-tion. Contrary to expectations, no postconstruction sheet piledeflection was observed after the completion of embankmentconstruction.

The change of earth pressure against retaining wall from at-rest state to active or passive state is a function of wall movement�Terzaghi 1936�. In this study, fully passive earth pressures hadalready been initialized in the supporting peat at all of the fiveinstrumented stations when the instrumented sheet piles were in-stalled in situ. In order to check the sheet pile deflection requiredto mobilize fully passive earth pressure in peat, Fig. 9 summarizesthe initial normalized maximum sheet pile deflections at five in-strumented stations, which were measured on February 28, 2003.It indicates that when the maximum sheet pile deflection towardpeat was 0.8% of sheet pile length, passive earth pressures hadalready been mobilized in peat.

Soil Movements within the Access Road

Fig. 10 presents the cumulative lateral soil movements, which

rth pressures and theoretical values

red ea

were caused by embankment construction, within the access road

ERING © ASCE / APRIL 2008

Page 9: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

between the embankment and the sheet pile wall at station 101+00 R. The initial inclinometer reading taken on March 25, 2004,beginning date of embankment construction, was set to zero.Therefore, the data shown in Fig. 10 represent the lateral soilmovements that developed since the beginning of embankmentconstruction. During the embankment construction �March 25–July 20, 2004�, the inclinometer recorded cantilever type of soil

Fig. 9. Initial normalized maximum sheet pile deflection at five in-strumented stations

Fig. 10. Measured lateral soil movements at station 101+00 R

JOURNAL OF GEOTECHNICAL AND

movements, with a maximum value of around 1.6 cm at theground surface. Following the completion of embankment con-struction, the upper portion of soil mass developed additionalmovement of 0.8 cm toward the sheet pile wall till November 8,2004. This additional soil movement may be due to redistributionof shear stress in soil mass. Since then, no soil movement wasobserved.

It was noticed that as construction proceeded, both sheet pileand soil mass developed significant movements toward the sup-porting peat. However, after embankment construction, no move-ment or only limited additional movement was developed in bothsheet pile and soils. The movements came to a complete stop aftera certain period of time. The expected long-term postconstructionmovements due to the creep peat were not observed. One possibleexplanation is that the peat on the supporting side had not beenstressed extensively, except those in the vicinity of the sheet pilewall. This assumption will be discussed and verified in the latersection entitled “Comparison between Measurements and Calcu-lated Results.”

Finite-Element Method Analysis

To model sheet pile performance in peat, two-dimensional finite-element code PLAXIS 8.2 �Brinkgreve et al. 2002� was adopted.The purpose of this FEM simulation was to investigate soil–structure interaction mechanism by comparing the calculated re-sults with the field measurements, and hence to obtain helpfulinsight for future sheet pile design and construction in peat. Thestaged construction feature of PLAXIS makes it possible to simu-late construction process continuously by first setting up a com-plete, final layout of the project, and then executing analyses in aseries of phases. During each phase, various portions of the sys-tem were deactivated and activated. Table 3 describes the proce-dures of continuous FEM modeling of the entire constructionprocess at station 101+00 R. The potential arching effect due tothe corrugated cross section of the sheet pile could not be simu-lated by this two-dimensional code. One of the challenges in thissimulation was how to model DDC. This problem was satisfacto-rily solved by using a block load acting on a fictitious steel plate.In PLAXIS 8.2, block load is defined as the dynamic loadingapplied within a single duration time �Brinkgreve et al. 2002�.Fig. 11 presents a typical finite-element mesh made up of 15-nodetriangular elements along with model parameters at station 101+00 R. In order to simplify modeling, a plane-strain model withhalf geometry was adopted. Peat was simulated by an undrainedsoft-soil-creep �SSC� model, which can account for creep effects.Backfill and in situ sands below peat deposits were modeled by aMohr–Coulomb model. In order to account for DDC effects,backfill parameters before and after DDC were assigned withthose obtained by laboratory and field exploration tests. Both thesheet pile wall and the façade panels of MSE wall were simulatedby plate elements, and the steel reinforcement strips were mod-eled by geotextile elements. Because of paper length limit, detailsof how to continuously simulate construction in peat usingPLAXIS 8.2 �see Tan 2005� will not be described here.

Comparison between Measurements and CalculatedResults

Fig. 12 shows the comparison between the measured and calcu-lated total lateral earth pressures and pore pressures at station

101+00 R. In Fig. 12, the thick lines represent the calculated

GEOENVIRONMENTAL ENGINEERING © ASCE / APRIL 2008 / 453

Page 10: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

values and the thin lines represent the field measurements. As nofield measurements were available, the comparison prior to in-situinstallation of the instrumented sheet pile could not be done. Thecalculated total lateral earth pressures against the supporting faceof the sheet pile had very small reduction �less than 2.5 kPa� withthe progress of peat excavation. During backfilling, the earth pres-sures increased rapidly and then stabilized quickly following thecompletion of backfilling. During the time between the comple-tion of field installation of the instrumented sheet pile and DDC,the calculated earth pressures and pore pressure were consistentwith the field measurements. Compared with the field measure-ments which fluctuated slightly over time, the calculated earthpressures and pore pressure were more stable. This is attributed to

Table 3. Procedures of Continuous FEM Modeling of Entire Constructio

FE element

Stage I

Sheet pileinstallation Excavation

Peat Excavation side 3 �

Supporting side 3 3

Underlying sands 3 3

Backfill � �

Sheet pile 3 3

Block loads �DDC� � �

MSE wall and embankmenta � �

Pavement � �

Note: 3�activated and ��deactivated.aIncluding facade panels, steel reinforcement strips, fill layers.

Fig. 11. Typical FE mesh used

454 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINE

that in FEM modeling, the water table level was assumed to be atthe existing ground surface all the time, whereas the actual watertable level fluctuated seasonally.

In order to present the comparison in greater details, both cal-culated and measured peak earth pressures and pore pressuresduring DDC were plotted against depth in Fig. 13. As shown inFigs. 12 and 13, the calculated earth pressures during DDCshowed a similar tendency as the field measurements, but weregreater than the measured values. Different from the measuredpore pressure, the calculated pore pressure during DDC had sig-nificant increment almost the same as the earth pressures. Follow-ing DDC, both calculated residual earth pressures and pore pres-sure recovered to their initial states at similar rates. This verifies

ess

Construction stage

StageII

StageIII

StageIV

StageV

StageVIackfilling

� � � � � �

3 3 3 3 3 3

3 3 3 3 3 3

3 3 3 3 3 3

3 3 3 3 3 3

� � 3 � � �

� � � � 3 3

� � � � � 3

simulation at station 101+00 R

n Proc

B

in the

ERING © ASCE / APRIL 2008

Page 11: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

the former assumption that during DDC, most of the stress incre-ments, ��, induced by DDC were carried by pore pressures, �u.The reason why the calculated earth pressures were greater thanthe field measurements can be attributed to the fact: In order tobalance the water table levels on both sides of the sheet pile wall,some holes had been cut on the sheet piles prior to installation.These cut-holes could function as drainage paths, and hence, the

Fig. 12. Comparison between the ca

Fig. 13. Comparison between the measured and the ca

JOURNAL OF GEOTECHNICAL AND

actual excess pore pressures generated in DDC could dissipatefaster than those predicted by FEM modeling, in which the sheetpile was treated as an impermeable material and functioned as anundrained boundary. Both field measurements and calculatedresults indicated that embankment construction did not imposesignificant effects on the earth pressures developing in the sup-porting peat and in the long term the earth pressures showed a

ed and the measured earth pressures

d peak earth pressures and pore pressure during DDC

lculat

lculate

GEOENVIRONMENTAL ENGINEERING © ASCE / APRIL 2008 / 455

Page 12: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

tendency of decreasing gradually with time. It can be predictedthat the mobilized passive earth pressures in peat would eventu-ally recover to the at-rest state, if enough time was guaranteed.

Fig. 14 presents the comparison between the measured andcalculated sheet pile deflections at station 101+00 R. The FEMmodeling results indicated that at the completion of excavation,the sheet pile only developed 0.5 cm deflection to the excavationside. This small sheet pile deflection can be attributed to twofactors: �1� The site was not dewatered during excavation and thewater tables on both side of the sheet pile wall were still at thesame level and �2� the total unit weight of peat �10.43 kN /m3� isonly slightly greater than unit weight of water �9.8 kN /m3�. Fol-lowing backfilling, the sheet pile deflected oppositely toward thesupporting peat side. At the completion of backfilling, the calcu-lated sheet pile deflection toward peat was 3 cm. In the followingone year, the sheet pile developed additional 5 cm deflection to-ward the peat side. Prior to DDC, the measured sheet pile deflec-tion was greater than the calculated. This can be attributed to theFact that in FEM modeling the sheet pile was assumed to bevertical at the completion of installation, whereas, in reality thesheet pile wall could have deflected from the vertical line afterbeing driven into soils. Also, in FEM modeling, the possible ef-

Fig. 14. Comparison between measured and calculated sheet piledeflections

fects on sheet pile deflection due to the operation of construction

456 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINE

equipments were not considered. During DDC, the sheet pile de-veloped greater calculated deflection than measured deflection,which can be interpreted by the greater calculated earth pressuresdescribed in the previous paragraphs. Both the calculated andmeasured sheet pile deflections stopped developing following thecompletion of DDC, which verifies that the relief of residual earthpressures after DDC in this study was attributed to the dissipationof excess pore pressures, not the retaining wall movements asusual. During the embankment construction, both the calculatedand measured sheet pile deflections developed further towardpeat. Following the completion of embankment, sheet pile move-ment almost stopped.

In general, both the measured and calculated results showedthat the sheet pile developed unrecoverable deflection toward thesupporting peat during the entire construction process. However,as long as the construction stopped, no long-term postconstructionsheet pile movement was developed. Fig. 15 shows the calculatedshear strain configurations in the soil mass at the end of embank-ment construction at station 101+00 R. It was observed that inthe supporting peat, shear strains mainly occurred in the areasclose to the sheet pile. For those areas away from the sheet pile,only very limited or no shear strains took place. This modelingresult verifies the former assumption: except those in the vicinityof the sheet pile wall, the peat on the supporting side had not beenstressed extensively, which explains why the expected long-termpostconstruction sheet pile movement was not observed.

Summaries and Conclusions

Monitored results of two years regarding sheet pile wall perfor-mance in peat during U.S. Route 44 relocation project in Massa-chusetts have been reported, analyzed, and compared with thecalculated results by FEM simulation. Based on the interpretedresults, the following conclusions can be drawn:1. Considering that both the field-measured and FEM-

calculated earth pressures matched well with the classic pas-sive Rankine earth pressures in this study, it seems that thefriction force between the peat and the sheet pile wall �inter-facial friction� was not mobilized. This can be explained bythe fact that the saturated peat behaves more like liquid than

Fig. 15. Shear strain configurations in soil mass at end of embank-ment construction

solid. In passive earth pressure calculation, the inclusion of

ERING © ASCE / APRIL 2008

Page 13: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

interfacial friction may cause overestimation of the passiveresistance provided by peat.

2. As the passive resistance recorded by the instrumentationwas only slightly larger than the static pressure developedagainst the sheet pile wall from water, at-rest earth pressures,instead of passive earth pressures, are recommended for cal-culation of resistance provided by peat in design.

3. An appropriate factor of safety �FS� should be adopted insheet pile design in peat. Commonly, FS=1 is sufficient forsheet pile design unless deformations of sheet pile wall arerestricted �USACE 1994�. However, as peat exhibits verypoor engineering properties, FS1 is essential to assure de-sign safety.

4. Arching will result in pressure difference on the inside weband outside web of sheeting. Whereas, compared with theabsolute pressure values, this difference can be disregardedin sheet pile design.

5. As the measured earth pressures did not change with thesheet pile movements toward the supporting peat as fieldinstallation of the instrumented sheet piles, it indicated thatfully passive earth pressures had already been mobilized inpeat with a measured maximum sheet pile deflection around0.8% of sheet pile length.

6. During each pass of DDC, both the total lateral earth pres-sures and pore pressure in peat increased rapidly to peaksand thereafter went down as compaction stopped. Both ofthem finally recovered to their initial values without addi-tional sheet pile deflection. It proves in this study that it wasthe dissipation of excess pore pressures that relieved the re-sidual total lateral earth pressures, not the movements of theretaining wall as usual.

7. Although the sheet piles developed large unrecoverable de-flections toward peat during DDC, no damaged sheeting wasobserved. The expected long-term postconstruction sheet piledeflections and soil movements were not observed, as onlythe creep peat in the vicinity of the sheet pile wall was ex-tensively stressed. The results from this study demonstratethat flexible steel sheet pile wall is a kind of effective retain-ing structure for construction in peat or other soft soils withlow strength, high compressibility, and significant creepbehavior.

8. Under conditions of high water table level, cut-holes onsheeting will help accelerate dissipation of excess pore pres-sures generated in dynamic compaction. In return, dissipationof excess pore pressures will relieve residual total earth pres-sures against sheet pile wall.

9. If appropriate soil parameters and construction conditions areused and assumed, continuous FEM modeling can accuratelypredict sheet pile performance during roadway constructionin peat. Therefore, such analysis can serve as a reference fordesign or prediction on performance of retaining structures.In addition, continuous FEM analysis is a powerful tool tounderstand soil–structure interaction mechanism under com-plex construction conditions.

Acknowledgments

The work presented in this paper is further research based on thefirst writer’s doctoral thesis. The writers appreciate the supportfrom the following people and organizations: Dr. N. Hourani andMr. P. Connors from Massachusetts Highway Department

�MHD�; P. A. Landers, Inc. of Hanover, Massachusetts; TerraSys-

JOURNAL OF GEOTECHNICAL AND

tems of Lovettsvill, Va.; Geosciences Testing and Research, Inc.�GTR� at North Chelmsford, Mass.; Mr. J. C. Adams, Mr. L. Hart,and Mr. L. R. Chernauskas of GTR, and Dr. A. A. Elsayed forfield assistance; and Mr. G. Howe of University of MassachusettsLowell �UML� for laboratory assistance. Finally, the writerswould like to thank the editor and two peer reviewers for theirvaluable comments and recommendations, which have enhancedthe paper presentation.

References

Adams, J. I. �1963�. “A comparison of field and laboratory measurementsin peat.” Proc., Ninth Muskeg Research Conf. and Ontario Hydro-Research, Q. 15, 1–7.

Barden, L. �1969�. “Time dependant deformation of normally consoli-dated clays and peats.” J. Soil Mech. and Found. Div., 95�SM1�,1–31.

Bentler, J. G., and Labuz, J. F. �2006�. “Performance of a cantileverretaining wall.” J. Geotech. Geoenviron. Eng., 132�8�, 1062–1070.

Berry, P. L., and Poskitt, T. J. �1972�. “The consolidation of peat.” Geo-technique, 22�1�, 25–52.

Berry, P. L., and Vickers, B. �1975�. “Consolidation of fibrous peat.” J.Geotech. Engrg. Div., 101�GT8�, 741–753.

Borja, R. I., and Lee, S. R. �1990�. “Cam-clay plasticity. 1: Implicitintegration of elasto-plastic constitutive relations.” Comput. MethodsAppl. Mech. Eng., 78�1�, 48–72.

Brinkgreve, R. B. J., Al-Khoury, R., Bakker, K. J., Bonnier, P. G., Brand,P. J. W., Broere, W., Burd, H. J., Soltys, G., Vermeer, P. A., and Haag,D. D. �2002�. PLAXIS finite-element code for soil and rock analyses,Balkema, Rotterdam, The Netherlands.

Buisman, A. S. K. �1936�. “Results of long duration settlement tests.”Proc., 1st Int. Conf. on Soil Mechanics and Foundation Engineering,Vol. 1, 103–106.

Carder, D. R., and Symons, I. F. �1989�. “Long-term performance of anembedded cantilever retaining wall in stiff clay.” Geotechnique,39�1�, 55–75.

Clark, B. G., and Wroth, C. P. �1984�. “Analysis of dunton green retain-ing wall based on results of pressuremeter tests.” Geotechnique,34�40�, 549–561.

Clough, G. W. �1977�. “Stabilizing berm design for temporary walls inclay.” J. Geotech. Engrg. Div., 103�2�, 75–90.

Clough, G. W., and Duncan, J. M. �1971�. “Finite-element analyses ofretaining wall behavior.” J. Soil Mech. and Found. Div., 97�SM12�,1657–1672.

Clough, G. W., and Hansen, L. A. �1981�. “Clay anisotropy and bracedwall behavior.” J. Geotech. Engrg. Div., 107�7�, 893–913.

Colleselli, F., and Cortellazo, G., �1998�. “Laboratory testing of an Italianpeaty soil.” Int. Symp. on Problematic Soils—IS-TOHOKU 98.

Coyle, H. M., and Bartoskewitz, R. E. �1976�. “Earth pressure on precastpanel retaining wall.” J. Geotech. Engrg. Div., 102�GT5�, 441–456.

Dhowian, A. W. �1978�. “Consolidation effects on properties of highlycompressible-soils-peats.” Ph.D. thesis, Univ. of Wisconsin-Madison,Madison, Wis.

Dhowian, A. W., and Edil, T. B. �1980�. “Consolidation behavior ofpeats.” Geotech. Test. J., 3�3�, 105–114.

DiBiagio, E. �1977�. “Filed instrumentation, a geotechnical tool.” Publi-cation No. 115, Norwegian Geotechnical Institute, Oslo, Norway, 29–40.

Elsayed, A. A. �2003�. “The characteristics and engineering properties ofpeat in bogs.” Master’s thesis, Univ. of Massachusetts-Lowell, Low-ell, Mass.

Endley, S. N., Dunlap, W. A., Knuckey, D. M., and Sreerama, K. �2000�.“Performance of an anchored sheet-pile wall.” Geotechnical specialpublication, No. GSP106, ASCE, Reston, Va., 179–197.

Ernst, H., Connors, P., and Pettis, J. �1996�. “Geotechnical report for

relocated Route 44, section I Carver, Plympton and Kingston.” Rep.,

GEOENVIRONMENTAL ENGINEERING © ASCE / APRIL 2008 / 457

Page 14: Performance of Sheet Pile Wall in Peat - Semantic …...sheet piles and sheet pile design state of art. To study the long-term performance of sheet pile wall in peat, five stations

Massachusetts Highway Department �MHD�, Geotechnical Section,Boston.

Fang, Y. S., and Ishibashi, I. �1986�. “Static earth pressure with variouswall movements.” J. Geotech. Engrg., 112�3�, 317–333.

Finno, R. J. �1989�. “Subsurface conditions and pile installation data.”Proc., Symp. on Predicted and Observed Behavior of Piles, Evanston,Geotechnical Special Publication No. GSP 23, ASCE, Reston, Va.,1–74.

Finno, R. J., and Harahap, I. S. �1991�. “Finite-element analysis ofHDR-4 excavation.” J. Geotech. Engrg., 117�10�, 1590–1609.

Fox, P. J. �1992�. “An analysis of one-dimensional creep behavior ofpeat.” Ph.D. thesis, Univ. of Wisconsin-Madison, Madison, Wis.

Fox, P. J., Edil, T. B., and Lan, L. T. �1992�. “C� /CC concept applied tocompression of peat.” J. Geotech. Engrg., 118�8�, 1256–1263.

Harahan, E. T. �1954�. “An investigation of some physical properties ofpeat.” Geotechnique, 4�3�, 108–123.

Jaky, J. �1944�. “The coefficient of earth pressure at-rest.” J. Soc. Hung.Archit. Eng., 78�22�, 355–358.

Lappalaine, E. �1996�. Global peat resource, International Peat Society,Finland Couch, G.R.

MacFarlane, I. C., and Allen, C. M. �1964�. “An examination of someindex procedures for peat.” Proc., 9th Muskeg Research Conf., NRC,ACSSM Technical Memo. No. 81, 171–183.

Mesri, G. �1973�. “Coefficient of secondary compression.” J. Soil Mech.and Found. Div., 99�1�, 123–137.

Mesri, G., and Godlewski, P. M. �1979�. “Closure to ‘time- and stress-compressibility interrelationship.” J. Geotech. Engrg. Div., 105�1�,106–113.

Mesri, G., Lo, D. O. K., and Feng, T. W. �1994�. “Settlement of embank-ments on soft clays.” Geotechnical special publication, No. GSP 40,ASCE, Reston, Va., 8–56.

Mesri, G., Stark, T. D., Ajlouni, M. A., and Chen, C. S. �1997�. “Second-

ary compression of peat with or without surcharging.” J. Geotech.

458 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINE

Geoenviron. Eng., 123�5�, 411–421.Ng, C. W. W., and Lings, M. L. �1995�. “Effects of modeling soil non-

linearity and wall installation on back-analysis of deep excavation instiff clay.” J. Geotech. Engrg., 121�10�, 687–695.

Ou, C. Y., Chiou, D. C., and Wu, T. S. �1996�. “Three-dimensional finite-element analysis of deep excavations.” J. Geotech. Engrg., 122�5�,337–345.

Peck, R. B. �1943�. “Earth pressure measurements in open cuts, Chicago�ILL.� subway.” Trans. Am. Soc. Civ. Eng., 1943�108�, 1008–1036.

Sherif, M. A., Ishibashi, I., and Lee, C. D. �1982�. “Pressure against rigidretaining walls.” J. Geotech. Engrg. Div., 108�GT5�, 679–694.

Stille, H. �1979�. “Behavior of anchored sheet pile walls.” Doctoral the-sis, Royal Institute of Technology, Stockholm, Sweden.

Tan, Y. �2005�. “Sheet pile wall design and performance in peat.” Doc-toral thesis, Univ. of Massachusetts-Lowell, Lowell, Mass.

Tan, Y., Lin, G., Paikowsky, S. G., and Fang, J. �2007�. “Evaluation ofcompaction effects on granular backfill using CPT.” Geotechnicalspecial publication No. GSP172, ASCE, Reston, Va., 1–10.

Tedd, P., and Charles, J. A. �1981�. “In-situ measurement of horizontalstress in over-consolidated clay using push-in spade-shaped pressurecells.” Geotechnique, 31�4�, 554–558.

Tedd, P., and Charles, J. A. �1983�. “Evaluation of push-in pressure cellresults in stiff clay.” Proc., Int. Symp. on Soil and Rock Investigationby in-situ Testing, Vol. 2, 579–584.

Terzaghi, K. �1934�. “Large retaining wall tests-I.” Eng. News-Rec., 85�February 1–April 19�, 136–140.

Terzaghi, K. �1936�. “A fundamental fallacy in earth pressure computa-tion.” J. Boston Soc. Civ. Eng., XXIII�April�, 71–88.

U.S. Army Corps of Engineers �USACE�. �1994�. Engineering anddesign—Design for sheet pile walls, engineering manual EM 1110-2-2504, Vicksburg, Miss.

Weber, G. W. �1969�. “Performance of embankments constructed over

peat.” J. Soil Mech. and Found. Div., 95�1�, 53–76.

ERING © ASCE / APRIL 2008