phase 3 stakeholders meeting may 14th, 2018 · 5/14/2019 · 4 replacing/repairing 6.4 miles of...
TRANSCRIPT
Phase 3 – Stakeholders Meeting
May 14th, 2018
Louisville Water CompanyMike Meyer, Project Engineer
Kelley Dearing Smith – Vice President, Communications & MarketingMarySusan Abell – Manager, Communications & Marketing
Vince Guenthner – Consultant Communications
Cleary Construction, IncPaul Harbron, Project Manager
Joey Still, Project Superintendent
HDR Consulting Engineers Kevin Brian, Project Manager
Aaron Thompson, Project Engineer
Meet The Team
Phase 3 – Stakeholders Meeting
May 14, 2019
• Opening Comments – Kelley Dearing Smith
• LWC 48” Main Rehab Update
• Project Overview – Mike Meyer
• Project Design, Schedule, Construction
Sequence and MOTs – Kevin Brian
• Communications Plan – Vince Guenthner
• Questions, Viewing Exhibits
Phase 3 - Meeting Overview
Phase 3 – Stakeholders Meeting
May 14, 2019
4
Replacing/repairing 6.4 miles of main
PHASE 3 (1.7 MI)JUNE 2019 TO MAY 2020
PHASE 2B (0.9 MI)COMPLETED MAY 2019
PHASE 2A (1.7 MI)COMPLETED APRIL 2018
PHASE 1 (2.1 MI)COMPLETED APRIL 2017
Phase 3 – Existing 48” Cast Iron Main
5
History/Issues• 48-Inch cast iron main• Unlined, heavily turberculated• Numerous leaks• Taken out of service in 2007 (12 years)
• Total length – 8,650 lf of 42” steel/DI pipe
• Push Pits/Point Excavations – 20
• 3 tie-ins requiring closure of Lexington• 42” construction in intersection of Stilz and
Lexington
• 24” tie-in at Top Hill Rd
• 24” tie-in at West of Garden Dr
• Six (6) Maintenance of Traffic Phases
Phase 3 Design Elements
Typical Slip Lining & Push Pull Pits
• Slip a new 42-inch diameter steel
pipeline inside the existing 48-inch cast
iron main
• Typical Work hours Mon – Fri 7:00 am – 7:00 pm
(Special circumstances – Require night work)
• Light towers at job sites
• Traffic control signs
• Use of arrow boards and message boards
• Typical construction site noise
• Hard fencing and concrete barriers around open
construction pits
What to Expect
Contractor staging areas
▪ Crescent Hill Filtration Plant
▪ Closed lanes along Lexington Rd and Stilz Ave
▪ Willow Lake parking lot
Pavement restoration
▪ Backfill to surface with concrete slab
▪ Temporary crushed stone base for sidewalks
▪ Repave disturbed areas
▪ New sidewalk Historic mix concrete
Ground restoration
▪ Straw blanket with seed and fertilizer
What to Expect
Objectives:
• Provide Safe Working Environment for
Contractor and Public
• Provide Clear and Delineated Traffic Controls for
Vehicle Travel
• Utilize Lane/Road Closures to Expedite Work
Along Project
Maintenance of Traffic Phases
▪ Six MOT phases
▪ Use Barrels and Traffic Cones
▪ Message Boards will be employed for
communication
Work Sequence/Maintenance
of Traffic Phases
Phase 3 Pipe Installation Sequence
12
How will we inform those who live and
travel along the route?
• Project specific web page LouisvilleWater.com/EasternPkwyProject
• Web page will include real-time traffic detours
• Key Stakeholder communication
• Frequent updates to council members
• Updates to neighborhoods, business
associations and education institutions
How are we informing those who live
and travel along the route?
• Frequent updates to traffic reporters
• Traffic and construction updates via NextDoor neighborhood app
• Consistent updates on Louisville Water’s Twitter and Facebook pages
• Opportunity for home and business owners to subscribe to weekly email
blast
• Reminder postcard mailed to affected home
and business owners at start of each new
traffic phase