phase 4 report - university of delaware department … the overall dimensions have changed slightly....
TRANSCRIPT
![Page 1: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/1.jpg)
DELAWARE DIAMOND KNIVES
PHASE 4 REPORT
December 10, 2010
By Jeff LeBlanc, Nnamdi Ibeka, David Kim, and Matthew Lindemer
![Page 2: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/2.jpg)
Table of Contents Updated Project Scope ................................................................................................................................. 3
New Project Information .............................................................................................................................. 3
Prototype Fabrication ................................................................................................................................... 6
Subsystem A: Shaft Collar ......................................................................................................................... 6
Subsystem B: Lead Screws ........................................................................................................................ 6
Subsystem C: Guide Rails .......................................................................................................................... 7
Subsystem D: Digital Indicator and Laser Mount ...................................................................................... 7
Subsystem E: Leg Supports ....................................................................................................................... 8
Testing Results & Analysis ............................................................................................................................. 8
Broad Measurement Range (Area) ........................................................................................................... 8
Broad Measurement Range (Thickness) ................................................................................................. 10
Measurement Accuracy .......................................................................................................................... 12
Assembly Time ........................................................................................................................................ 13
Mobility ................................................................................................................................................... 15
Finite Element Analysis ............................................................................................................................ 16
Future Process Design Changes .................................................................................................................. 20
Chemical Mechanical Grinding ................................................................................................................... 20
Path Forward ............................................................................................................................................... 21
Appendix A: Cost Analysis ........................................................................................................................... 22
Appendix B: Design Specification ................................................................................................................ 23
Appendix C: Gantt Chart ............................................................................................................................. 24
Appendix D: Design Package ....................................................................................................................... 24
![Page 3: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/3.jpg)
Updated Project Scope The purpose of this project is to design and manufacture a measuring device that is sensitive enough to precisely measure the thickness of diamond slabs manufactured by Delaware Diamond Knives within an accuracy of 1 micron. The current measurement tools used by Delaware Diamond Knives require the diamond specimens to be removed from their apparatuses which consequently results in measurement inaccuracy due to bow, glue-line thickness, and taper. To combat this issue the new measuring device will be designed to measure the diamond wafers while they remain in their respective positions on the grinding apparatus.
New Project Information Since the end of Phase 3, there have been design changes to the grinding arm. The assembled grinding
head has been changed from a stationary head to a head that swivels in place. This design has added
some difficulty and variables into our Final Concept Design. Since the head of the grinding arm now has
the ability to swivel, our Final Concept Design had to attach to the shaft of the head, because the
surrounding parts have become moving parts. Also there were new clearance heights around the shaft
and the overall dimensions have changed slightly.
Updated Design Changes
Figure 1: New Rail System Design
90° Joining Plate
After our Phase 3 presentation with our sponsor, we found a design flaw in our rail system. The
Phase 3 Design Package had assembled our rails using pin connections (connection locations
circled in Figure 1). These pin connections would cause our rail system to become a
parallelogram over time, because the pin would allow for two degrees of freedom. Our new
design uses 90° Joining Plates, which we modeled from any common bridge or truss connection
that sustains loading over time. This new connection will provide a more rigid structure and
perform better over time than pins would have.
![Page 4: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/4.jpg)
Figure 2: Additional Design to Acme Screw
Another design change that was made since Phase 3 is the addition of knobs [Figure 2] to the end of our
Acme Screws. It is difficult to turn the Acme Screws by hand in the prototype, because of the small
diameter rod, the grease added to provide extra lubrication to the flange, and the fine thread. The
knobs have a knurled radius that provide extra grip when working with the prototype. Another reason
why the knobs were knurled is because the employee’s at DDK are constantly working with machinery
and mechanical devices, so they often have grease on their hands. The knob’s will improve our ease of
use metric and provide better ability to make fine adjustments.
Figure 3: Battery Pack Assembly
One of our original metrics from Phase 2 was to use a battery operated laser. However, the
manufacturer did not specify if the Voltage to our Laser Level was DC or AC, so we waited till we
received the laser before we made our battery pack. The battery back includes 3AA battery in series,
which are wired to an operating switch, which allows the operator to turn the laser on and off [Figure 3].
This battery pack improves the mobility metric and the ease of use metric. It improves the mobility
metric, because the prototype is no longer limited to operational use near an electrical power source.
Also, the ease of use metric is improved, because a switch operated laser will be easier to operate than
plugging and unplugging the laser for operational use.
Knurled Knob
![Page 5: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/5.jpg)
During our sponsor discussion after Phase 3, we re-examined any ways to simplify the fabrication
process of the reference plane. In inspection of the copper face plates [Figure 4] we found that they
were purposely notched to prevent the face plate from rotating in place. The design change we decided
to make was to use this notched piece of the copper faceplate and extended our reference plane from
this point [Figure 5]. In Phase 3, our design package included a drawing to lathe down the head of the
Grinding Arm then insert a plane that would extended in the radial direction beyond the copper
faceplate. The new reference plane required less machining, taking advantage of an existing feature,
and a smaller amount of material added to the Grinding Head. The smaller amount of material will
reduce the risk of changing the performance of the Grinding Head and also improve the metric of ease
of use. The shaft collar will be assembled easier with the new reference plane, because it does not
restrict some on the clearance problems that occurred with the Phase 3 design.
In Phase 3, our design to mount the Digital Indicator to the L-Bracket was done by using the provided
hole pattern that was on the back of the Indicator. This design did not allow for any fine adjustments
Figure 5: Notched Copper Face Plate Figure 4: New Reference Plane
Figure 7: New Digital Indicator Mount Figure 6: Rack and Pinion Provides Track Movement
Pinion
Rack Set Screw
Reference Plane
![Page 6: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/6.jpg)
because in order to bring the Indicator closer or further away from the diamond film, all the lead screws
would have to be adjusted. The new design uses a Rack and Pinion Gear System [Figure 6], where the
black knob turns the pinion and translates the motion of the rack, the Indicator, along the distance of
the rack. This mounting plate also has set screws, seen in [Figure 7] which provides a locking mechanism
to ensure that the Indicator does not freely move.
Prototype Fabrication The main components, including guide rails, acme screws, ball joints, flanges, leveling feet, digital
indicator, and laser, were purchased. Our design team fabricated the remaining parts. The design was
modified in order to simplify machining. All of fabrication and assembly was performed in the Delaware
Diamond Knives’ machine shop. Aluminum sheets were the main fabrication material. The total cost of
aluminum stock was $105.33.
Subsystem A: Shaft Collar The Shaft Collar components were milled by a CNC
Router, including the hole pattern seen in [Figure 8]. The
center arcs in the collar were milled to a radius of 1.35
inches. The three larger holes were milled by the router
to a diameter of 0.5 inches, which is the clearance hole
size for the flange nuts of the acme screws. The hole
pattern around the three holes match the flange hole
pattern for the acme screws. These holes were tapped
using ¼-20 taper tap then the bottom piece was tapped
using 5-40 taps and then deburred.
Subsystem B: Lead Screws Most of parts of this subsystem were purchased, but
some modification was required. The acme screw was
cut using a hack saw to acquire the needed length. Also,
since the ball joint thread angle is different from the
thread angle of the acme screw, the ball joint threads
were bored out with a lathe machine and the acme
screws were connected to them using an epoxy.
[Figure 9].
Figure 8: Shaft Collar
Figure9: Lead Screw
![Page 7: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/7.jpg)
Subsystem C: Guide Rails Three kinds of brackets used in this assembly, two of
the bracket connecting carts and the crossing guide
rail, four joining plates, and three brackets connecting
the guide rails and ball joints. Two alignment rods were
machined on the milling machine for the supporting
frame of the rail system. The lip was also fabricated to
attach to one of alignment rod. The main caution on
this subsystem was keeping the side guide rails parallel
to each other. In order to keep the side guide rail
parallel, a slip hole feature was machined on the
alignment rods so that the rails could be adjusted on the
assembly to make them parallel. After attaching the 90⁰
joining plates with the alignment rods, guide rails were placed on to the opposite side of the joining
plates as seen in [Figure 10] using the holes on the guide rails as a clearance hole, punched on the
joining plates and tapped using #5-40 taper tap. The cart bracket was tapped with M3 size tap to attach
on the carts following the dimensions provided by THK, the guide rail manufacturer. Finally, to mount
the crossing guide rail on top of it, the holes were tapped using #5-40 taps.
Subsystem D: Digital Indicator and Laser Mount
The L-bracket was fabricated to mount digital indicator and laser on opposite sides of each other as seen
in [Figure 11]. This bracket was also machined on the milling machine with .125 inch thick aluminum
sheet. The battery casing was also modified on the milling machine to allow for the appropriate cavities
for both the wires and switch, which increased the overall mobility of the prototype instead of using a
power cord. [Figure 12]
Figure 10: Guide Rail System
Figure 11: L-bracket with Micrometer and Laser Figure 12: Battery Pack
![Page 8: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/8.jpg)
Subsystem E: Leg Supports Bases of the legs and blocks, which sit on at the end of the rods, were
fabricated on the milling machine with aluminum stock, which came
from the sponsor’s general inventory. The angle at one of corner was
cut at 45⁰ to meet the shaft alignment rod lip at its flat surface. The
length of all four threaded rods were modified using a hack saw, as
shown in [Figure 13].
Figure 13: Leg Supports
Testing Results & Analysis
Broad Measurement Range (Area) Purpose of This Test: The purpose of this test is to prove our measurement area metric. The metric
states that the prototype must have the ability to measure a circular area with the diameter of 50mm or
2 inches.
Method: Center the Digital Indicator in the center of the Linear Guide Rail System. Then move the
Digital Indicator to the furthest position in the X and Y direction. The Laser Leveling System was not
attached beneath the Indicator for this test, but the height and size of the laser was taken into account
when taking measurement. All measurements were taken using high accuracy calipers. The
measurement was completed by measuring from the outer most radius of the shaft collar to the tip on
the Digital Indicator. Since we know that the radius of the Shaft Collar was fabricated with a radius of
1.35inches. So the radius of the Shaft Collar was subtracted from each measurement, which would
ensure that we would be taking our measurement from the center of the collar.
Figure 14.1: Centering the Digital Indicator within the Rail System
![Page 9: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/9.jpg)
Figure 14.2: Indicator to the bottom Y position Figure 4.3: Indicator to the right X position
Figure14.5: Indicator to the top Y position Figure 14.4: Indicator to the left X position
![Page 10: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/10.jpg)
Test Results:
Data Analysis:
Every data point measured must be beyond the radius of 25mm or 1 inch, which shows that the
Indicator can measure on a diameter of 50 mm or 2 inches. The top Y position, right X position, left X
position show that the Indicator satisfies the 50mm requirement and has enough freedom of movement
to go farther than the diamond and reach the reference plane. However, the bottom Y position can only
reach a radius of 1.05 inches or 27mm, this satisfies the 25mm radius requirement, but does not allow
the Indicator to reach the reference plane in the lower Y region of the measuring area.
In conclusion, the prototype satisfies the measurement area requirement. In addition to the
measurement area requirement, the data taken shows that the reference plane can only be found in the
upper Y region of the measuring area because the laser mount below the Indicator allows for less
clearance at the bottom position than the top position.
Broad Measurement Range (Thickness) Purpose of Test: The purpose of this test is to prove the metric for thickness measurement range of the
prototype. The metric states that the prototype must measure a range of 5µm to 2mm.
Method: The way this tested was using known thickness values of materials then testing them by first
leveling the Indicator. Then providing a measuring surface, aluminum plate, and zeroing the Indicator in
this position. Then measuring two materials with known thickness and analyze the results.
1.35” Radius (Shaft Collar)
2.35” (Right X Position)
2.45” (Top Y Position)
2.55” (Left X Position)
1.05” (Bottom Y Position)
X
Y
![Page 11: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/11.jpg)
Test Results:
The first item used for testing was a sheet of paper with a known thickness of 50µm or 0.050mm, this
paper was then replaced with a paper of known thickness of 49µm or 0.049mm. This shows that the
prototype is able to measure a thickness change of 1µm. Our next item that we measured was a gold
diamond film backed by a silicon wafer with the thickness of 3.944mm or 3944µm. This item matches
our metric requirement because the film thickness of this silicon wafer is 1.944mm thick and the silicon
wafer backing it has a thickness of 2mm. So this wafer represents the maximum testing range for the
prototype.
Figure 15.1: Zeroing Indicator on Aluminum Figure 5.2: Measuring Thin Piece of Paper
Figure 16: Gold Colored Diamond Film Figure 17: Measuring Diamond Film
![Page 12: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/12.jpg)
Data Analysis:
This test shows that the prototype satisfies the thickness range requirement of 5µm to 2mm diamond
film. This accuracy can be due to the high tolerance Digital Indicator and also the fine tip that was
special ordered from Mahr. This special tip has a diameter of .040 inches or 40 thousands of an inch.
However, this small tip also showed how sensitive the Indicator was to small amounts of movement. The
combination of the high accuracy Indicator and needle point tip show that operational use of the
Indicator will have to be very precise because of the sensitivity.
Measurement Accuracy Purpose of Test: The purpose of this test is to prove the metric accuracy of the prototype. The metric
states that the prototype must have an accuracy of 1µm.
Method:
The measurement accuracy and repeatability were tested by taking a displacement measurement from
the set reference plane to the top surface of the diamond film wafer each time the prototype was
attached to the grinding arm, a total of 12 times. Before taking the measurements specific steps were
taken to ensure the measurement readings would be as accurate as possible. Using the three lead
screws and the alignment laser, the plane of the prototype was finely adjusted until a parallel was
achieved between the plane of prototype and the face of the diamond film. Observing when the center
point of the cross-hair laser beam shined directly back into its orifice served as an indicator for when
parallel planes were achieved. The results from the measurements are shown in [Table 1]
Figure 18: Measuring Data Point Figure 6: Reference Plane with Diamond Film
![Page 13: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/13.jpg)
Test Results:
Trial # Wafer Displacement (mm)
1 1.895
2 1.892
3 1.894
4 1.896
5 1.888
6 1.895
7 1.899
8 1.889
9 1.901
10 1.891
11 1.903
12 1.893
MEAN 1.895
MODE 1.895
ST. DEV 0.005
Data Analysis:
Based on the data obtained from the measurement trials the measurement prototype was accurate
within +/- 5 microns. According to the metric set in the project scope of +/- 1 micron for measurement
accuracy, the accuracy of the measurement prototype missed the set metric by 4 microns. Due to this
shortcoming an analysis of sources of error were done. After some timely observation the project team
identified a few sources of error that could generate such a small discrepancy. Imperfections in part
fabrication could be a viable source of error and also vigorous vibrations generated from surrounding
machinery also would cause a variance in the accuracy of the prototype. It is also possible that the
parallel positioning set during the measurement processes are not always 100% perfect and in that case
the accuracy of the device would be offset. Vibrations were considered to be the most underlining cause
of in accuracy. Based on these observations the accuracy achieved was deemed acceptable given that it
still improves upon the current accuracy of DDK’s measuring process.
Assembly Time Purpose of Test: The purpose of this test is to test the prototypes assembly time metric. This metric has
been adjusted since Phase 2, because of new information gathered about the current process. Currently
it takes 15 minutes to remove the wafer, dissolve the adhesive backing, then measure and reapply the
Table 1: Displacement Data
![Page 14: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/14.jpg)
wafer to the grinding arm. The target metric is to have the prototype assemble for 12 minutes to
outperform the current solution
Method: The processing time was tested by measuring time durations during two stages of the diamond
film measuring process. The stages observed during the test were the time it takes to attach the
measurement device to the grinding arm and the time it takes to disassemble and remove the device
from the grinding arm. The test was done in a total 12 trials, each member of the project team
completed three trials each. Several people completed multiple time trials in order to generate realistic
variances in assembly times, being that many employees at DDK will use the prototype and the assembly
and disassembly time will vary from person to person. The data in [Table 2] depicts the recorded times
for each of the 12 trials.
Test Results:
Trial # Mount Time (sec) Dismount Time (sec)
1 234 227
2 295 231
3 236 242
4 241 213
5 266 216
6 238 221
7 257 239
8 255 235
9 225 219
10 261 246
11 224 212
12 227 235
Average Time 246.5833333 228
Approx. 4 minutes 7 seconds Approx. 3 minutes 48 seconds
Figure 20: Assembly the Prototype Figure 7: Prototype Fully Assembled
Table2: Assembly Data
![Page 15: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/15.jpg)
Data Analysis:
Based upon the information obtained from DDK machinist, Bill Tabeling, the original preparation time
needed to get the diamond wafer to be measured was approximately 15 minutes. This process included
removing the wafer from the grinding apparatus, soaking it in a solution to soften and dissolve the
adhesive, and cleaning the adhesive from the surface completely. Based on the time it originally took to
prepare the wafer for measurement, an acceptable goal for set up and breakdown time for assembly
time was set at simply achieving a time shorter than the original time it took to prepare the wafer for
measurement. As shown in the data table the average set-up and breakdown time for the measurement
prototype was approximately 8 minutes, which nearly cuts the time in half from the original preparation
time. Based on the given data the assembly time for the prototype is considered acceptable.
Mobility Purpose of Test: The purpose of this test is to analyze the mobility metric of the prototype. The metric
states that the prototype must weigh less than 5lbs.
Method: This test was conducted by weighing the subsystems of the prototype on a packaging scale
provided by the sponsor. After all the subsystems have been weighed, the combined weight will be
added together.
Test Results: The weight of the prototype in full assembly was measured to be 4.5 pounds.
Data Analysis: The components that comprise what is considered to be the full assembly are as follows:
shaft collar, acme screws (with nuts and flanges), guide rail assembly with carts, digital indictor with an
adjustable mount, alignment laser, a series of brackets used throughout out the assembly, as well as a
variety of screws used to assemble the prototype. The leg supports were not include in the weighing
process during the mobility testing due to the fact they are handled separately when installing the main
measurement device to the grinding arm. As shown by the previously stated results, the weight of the
prototype is within the set weight constraints and therefore meets the mobility requirements.
Figure 22: Weighing Indicator Figure 8: Weighting Guide Rails with Acme Screws
![Page 16: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/16.jpg)
Finite Element Analysis Purpose of Test: The purpose of this test is to analyze the durability and the amount of deflection that
occurs when the acme screws are loaded differently in potential situations
Method: Using SolidWorks and SimulationXpress, a model of the Acme Screw, with the material
property of Stainless Steel, was loaded in compression and in a bending moment.
Bending Moment on Acme Screw
Figure 24: SolidWorks Model of Acme Screw, ¼ inch Diameter, 5 inches Long
Figure 25: Fixing Bottom of Screw to Create Screw in Shaft Collar
![Page 17: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/17.jpg)
Load (lbf) Maximum Deflection (mm)
1.00 8.88E-05
1.50 1.33E-04
2.00 1.78E-04
2.50 2.22E-04
3.00 2.66E-04
3.50 3.11E-04
4.00 3.55E-04
4.50 3.99E-04
5.00 4.44E-04
5.50 4.88E-04
6.00 5.33E-04
6.50 5.77E-04
7.00 6.21E-04
7.50 6.66E-04
8.00 7.10E-04
8.50 7.54E-04
9.00 7.99E-04
9.50 8.43E-04
10.00 8.88E-04
0.00E+00
1.00E-04
2.00E-04
3.00E-04
4.00E-04
5.00E-04
6.00E-04
7.00E-04
8.00E-04
9.00E-04
1.00E-03
0.00 2.00 4.00 6.00 8.00 10.00 12.00
De
fle
ctio
n (
mm
)
Load (lbf)
Acme Screws in Compression Loading
Data Analysis: This testing shows that the screw can be loaded in compression up to 10 lbf, which would
be over the realistic loading limit, and still show no significant deflection. The maximum deflections
occur in the top of the screw, 8.88x10^-4 mm, where the acme screw would be loaded in compression
by the ball joint on the rail system.
Figure 26: Compression Force on top of Screw Simulating Loading from Rails
Figure 27: Compression Loading Results from SimulationXpress
Chart 1: Acme Screw in Compression Table3 Load vs. Max Deflection
![Page 18: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/18.jpg)
0.00E+00
5.00E-01
1.00E+00
1.50E+00
2.00E+00
2.50E+00
0.00 2.00 4.00 6.00 8.00 10.00 12.00
De
fle
ctio
n (
mm
)
Bending Moment (lbf)
Bending Moment on Acme Screw
Data Analysis: The deflection in the screw is the largest at the
location of the bending moment. The maximum deflection that was
seen is 2.12 mm. This is more than expected, but the prototype
should never experience a bending moment of 10 lbf. This also
shows that the rod is still in the elastic region and has some
flexibility. This flexibility will help keep the screw from translating
more force into the shaft collar. It is a concern if the acme screw is
too flexible because it possibly become permanently deformed.
Load (lbf)
Maximum Deflection (mm)
1.00 2.12E-01
1.50 3.18E-01
2.00 4.24E-01
2.50 5.24E-01
3.00 6.35E-01
3.50 7.41E-01
4.00 8.47E-01
4.50 9.53E-01
5.00 1.06E+00
5.50 1.17E+00
6.00 1.27E+00
6.50 1.38E+00
7.00 1.48E+00
7.50 1.59E+00
8.00 1.69E+00
8.50 1.80E+00
9.00 1.91E+00
9.50 2.01E+00
10.00 2.12E+00
Figure 28: Force Location to Create Bending Moment Figure 29: Resulting Bending Moment of 1 lbf
Table 4: Load vs. Deflection Chart 2: Bending Moment on Acme Screw
![Page 19: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/19.jpg)
0.00E+00
5.00E-04
1.00E-03
1.50E-03
2.00E-03
2.50E-03
3.00E-03
0.00 2.00 4.00 6.00 8.00 10.00 12.00
Max
imu
m D
efl
ect
ion
(m
m)
Load (lbf)
Bending Moment on Shaft Collar
Bending Moment on Shaft Collar
Table 5: Load vs. Deflection
Load (lbf) Maximum Deflection (mm)
1.00 2.78E-04
1.50 4.17E-04
2.00 5.56E-04
2.50 6.95E-04
3.00 8.33E-04
3.50 9.72E-04
4.00 1.11E-03
4.50 1.25E-03
5.00 1.39E-03
5.50 1.53E-03
6.00 1.67E-03
6.50 1.81E-03
7.00 1.95E-03
7.50 2.08E-03
8.00 2.22E-03
8.50 2.36E-03
9.00 2.50E-03
9.50 2.65E-03
10.00 2.78E-03
Figure 30: Resultant Deformation Diagram Figure 31: Fixed Shaft Collar Center with Bending Moment
Chart 3: Bending Moment on Shaft Collar
![Page 20: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/20.jpg)
Data Analysis: This data shows the possible deformation of the Shaft Collar design. The reason why we
would want to reduce the deformation in the Shaft Collar is because it could possible move the hole
locations. The largest amount of deflection is 2.78E-03 mm, which is not a significant amount of
deflection. Therefore, we are convinced under the loading conditions of the prototype there will be no
significant deformation causing the prototype to lose any performance metrics.
Further Design Development After analyzing the overall design of the measurement prototype there are a few changes that could be
made in the future to improve the quality, versatility, and ease of use of the device. In the future DDK
will look to upgrade the mounting collar’s latching mechanism from screws to toggle clamps. This
change will make it easier to fasten the collar to the grinding shaft and will therefore cut down the time
it takes to mount and dismount the device to and from the grinding arm substantially. Further feasible
design developments also include implementing set screws in the shaft collar which would be used to
adjust the diameter of the collar. Such development would make it possible for the measurement device
to be adaptable to new grinding mechanisms that DDK will design and fabricate in the future as well as
other grinding stations that were not included in the scope of this project. Using set screws would
undoubtedly increase the overall adaptability of the prototype.
Future Process Design Changes Though fabricating a device that allows one to measure the thickness of diamond wafers while they
remain on the grinding arm improves the accuracy and efficiency of the grinding process, it is imperative
to recognize that the accuracy in measurement also depends greatly on the efficiency of the grinding
process itself. With the implication of that notion, it has been determined that there are more efficient
ways to grind CVD diamond films in opposition to the process chosen by Delaware Diamond Knives, such
as, Chemical-Mechanical Planarization.
Chemical Mechanical Grinding Chemical Mechanical Planarization (CMP) defined as a process of
smoothing surfaces by means of both chemical and mechanical forces.
This method of surface grinding/finishing can be used to remove
topography from silicon oxide, metals, and polysilicon surfaces. The
mechanical process currently used by DDK has a much higher surface
damage rate when compared to CMP. The process of grinding by
method of CMP uses abrasive and corrosive chemical slurry, most likely
a colloid, combined with a polishing pad and a retaining ring as shown
in [Figure 32]. Also notable, CMP is capable of grinding surface down to
Angstrom levels.
Figure 32: CMP Diagram: http://en.wikipedia.org/wiki/Chemical-mechanical_planarization
![Page 21: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/21.jpg)
By implementing this grinding process in place of their current fully mechanical grinding process DDK
would greatly improve the quality of the diamond films they polish. The faces of the diamond films
would definitely be more even and the rate at which films are cracked and damaged during the actual
grinding process would decrease greatly. Being that reducing the risk of damage to the diamond film
was an essential aspect of the project scope, it would be feasible to propose that DDK look into
optimizing their grinding process in the future.
Path Forward In order to move our design into a fully working item for all grinding devices a few steps to need be
taken. The final design is completed, but to fully implement our design to all of DDK’s grinding machines
new shaft collars and alignment rods would need to be fabricated to fit grinding machines of different
configurations. The manufacturing process is similar to the one used previous. The only differences are
the center arc radius of the shaft collar and the distance between the holes that the acme screws come
out of. The additional design development as noted previously also includes, toggle clamps and
implementing set screws into shaft collar. Finally, the measurement process requires training workers to
calculate exact thicknesses from the measured displacement as well as the mounting and dismounting
process.
![Page 22: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/22.jpg)
QTY Part Brand Order/ Item #
Price Quote
(each)
1 Micrometer Mahr XLI - 20002 $454.75
1 Mounting Bracket Mahr AT - 116
1 Tip Mahr PT - 2265
4 Linear Guide Rail (Cross Section) THK RSR12ZM $86.00
1 Material Stock McMaster-Carr 9246K13 $19.00
1 Material Stock McMaster-Carr 8973K43 $51.14
3 Threaded Rod (Acme) Roton Industries 60760 $18.63
6 Lead Screw Nut Roton Industries 91734 $22.10
6 Lead Screw Flange Roton Industries 89837 $27.07
3 Ball Joint Mid-West Control FMIL250C $3.19
1 Laser Level Cole-Parmer EW-42935-22 $289
1 Laser Battery Sears UPG 5.00v Lithium-Ion Battery$16.99
2 Leveling Foot 80/20 Inc 2194
1 Rod Ends McMaster-Carr 95475A576 $6.74
1 Material Stock McMaster-Carr 9135K261 $31.51
1 Inch Standard Screws McMaster-Carr 91251A080 $3.82
1 Inch Standard Screws McMaster-Carr 91251A126 $8.25
1 Inch Standard Screws McMaster-Carr 90128A245 $11.12
1 Metric Standard Screws McMaster-Carr 91290A113 $4.32
1 Inch Standard Screws McMaster-Carr 91251A125 $8.44
TOTAL: $1,601.31
Appendix A: Cost Analysis
After looking at the materials and parts costs it is determined that a budget of $2000 would be sufficient
to complete the prototype. The table below is the complete list of all of parts that were purchased. The
two most cost intensive of part were Micrometer and Laser Level. Other purchased products were
comparatively small. Some aluminum materials, acme screw handle, and battery pack were provided by
Sponsor DDK. The final design cost was about $1,600 which is significantly less than the initial target
value of $9,000. Delaware Diamond Knives costs $3,000-$10,000 to grow diamond film on the wafer and
have 5% chance of breaking the diamond film while taking on and off from the grinding arm. The use of
our design will save at least $1,400 on first month and save same amount money as loss by breaking the
diamond film from next month. Over a year, the benefit will be $31,400 at least and $184,000 at most.
Purchased Parts:
Table6: Purchase Sheet
![Page 23: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/23.jpg)
Future Cost
The prototype which was built is only for one type of the grinding machine. The shaft collar and guide
rail system including the alignment rod and the corner bracket will be machined for another grinding
machine. Also, changes of the laser will increase accuracy of the leveling the system.
Part Price
Material Stock $200
Laser $300
Total $500
Appendix B: Design Specification
Final Design Details How the Design Works
The mathematical theory behind the design is very simple. Our idea for the design was to use a Digital Indicator to measure the “change in thickness” of the diamond films. Our sponsor gave us a list of assumptions to base our design around. These assumptions include:
1. While the Diamond Film is grown onto the Silicon Wafer during the Chemical Vapor Deposition process in the High Pressure Microwave Plasma Reactor, the Silicon Wafer will not have any thickness etched away and will remain at 1/8” thickness.
2. The current Micrometer at DDK’s facility has the ability to map the thickness profile of the Diamond Film after the Diamond is grown onto the Silicon and before the Silicon and Diamond Wafer is placed onto the Grinding Arm. Thus the sponsors current solution with give us an initial thickness profile for the Diamond.
3. The Diamond Film backed with the Silicon Wafer is placed onto the Grinding Arm using a light adhesive. This adhesive is a paste material that is applied by hand, and does not have a uniform thickness profile. Also the lightweight strength of this adhesive cause the diamond to spin in place while it is being grinded because the wheel with physically spin the Diamond and the adhesive does not stop the diamond from rotating.
The first things to be done to begin is put the shaft collar over the shaft, and secure the bottom of the collar using ¼-20 screws to pull the collar tight to the shaft. Then level a diamond film measurement is to ensure that the frame of our design and the Digital Indicator is square with the Diamond Film. To do this we will use our laser leveling system, which is backed by the Digital Indicator to ensure we are parallel with the Indicator. Then we will use the three lead screws to make fine adjustments in the angle of the frame. The theory behind this leveling system is that you need three points to create a plane; therefore we need three adjustments to ensure that the digital indicator is on a square plane with the diamond.
The purpose of the Digital Indicator is to use the New Surface (which will be added using the lathe), as a reference point that will be permanent. If we directly attach a surface to the shaft of the Grinding Head, we know that it will be an unchanging reference point and square to the diamond.
Table6: Estimated Future Cost
![Page 24: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/24.jpg)
The Digital Indicator will measure the distance to the New Surface, and Zero that position. This will be done every time before a measurement is taken. The Digital Indicator will map the height of the diamond film, using the same mapping technique the sponsor uses, and this will be a measurement of the initial height.
So after the initial height around the diamond is mapped. The structure will be reattached, leveled, and zeroed. Then the Diamond Film with be mapped again, and the change in height around the Diamond Film will be the resulting thickness change in the Film. Since the initial thickness of the Film is known, we can calculate what the current thickness of the diamond.
Appendix C: Gantt Chart The project schedule will be uploaded onto Sakai
File Name: “Updated Gantt Chart Phase 4_Appendix C”
Appendix D: Design Package
Bill of Materials
Table 7: Bill of Materials
DWG NO. PART NAME PART NUMBER DESCRIPTION QTY.
1 Lead Screw 60760 ¼”-20 Diameter 3
2 Lead Nut 91734 Bronze Nut 3
3 Ball Joint FMIL250C ¼” - 20 3
4 Flange 89837 3
5 Cart 1 RSR12ZM 3
6 Rail 220mm RSR12ZM 1
7 Alignment Rod 1
8 Alignment Rod with Lip 1
9 Rail 160mm RSR12ZM 2
10 Cart Bracket 2
11 Bracket for Block 2
12 Shaft Collar 1 1
13 Shaft Collar 2 1
14 Leveling feet 2515T15 2
15 Leg to Collar Shaft 2
16 Leg to Guide Rail 2
17 Base of the Leg 2
18 L-Bracket 1
19 Laser LTM2HKD 1
![Page 25: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/25.jpg)
20 Standard Screw 90128A242 ¼”-20 1/2" length 1
21 Standard Screw 91251A173 #5- 40 1 - 1/4" length
1
22 Bracket to Cart 92196A459 ,
92196A459 #1 – 64 1/4" Length
1
23 Standard Screw, 91251A096
91251A096 #3-48 1/2" Length
1
24 Set Screw 91375A124 91375A124 #5-401/4" Length
1
25 Micrometer XLI-20002 Digital-1” Stroke
1
Part List
Figure 1: Fully Assembled Prototype with Numbers Referencing Bill of Materials in previous page
![Page 26: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/26.jpg)
Full Assembly Drawing
Figure 2: Assembly Drawing with instructions
![Page 27: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/27.jpg)
Sub Assembly Drawings
Sub Assembly Drawing #1: Lead Screw
Figure 3: Sub Assembly Drawing #1: Lead Screw
![Page 28: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/28.jpg)
Sub Assembly Drawing #2: Guide Rail System
Figure 4: Sub Assembly Drawing #2 for Guide Rail System
![Page 29: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/29.jpg)
Sub Assembly Drawing #3: Collar Shaft
![Page 30: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/30.jpg)
Sub Assembly Drawings #4: Support Legs
![Page 31: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/31.jpg)
Part Drawings
Parts in Sub Assembly #1
![Page 32: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/32.jpg)
![Page 33: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/33.jpg)
![Page 34: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/34.jpg)
![Page 35: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/35.jpg)
Parts in Sub Assembly #2
![Page 36: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/36.jpg)
![Page 37: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/37.jpg)
![Page 38: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/38.jpg)
![Page 39: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/39.jpg)
![Page 40: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/40.jpg)
![Page 41: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/41.jpg)
![Page 42: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/42.jpg)
Parts in Sub Assembly #3
![Page 43: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/43.jpg)
![Page 44: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/44.jpg)
Parts in Sub Assembly #4
![Page 45: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/45.jpg)
![Page 46: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/46.jpg)
![Page 47: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/47.jpg)
![Page 48: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/48.jpg)
Remaining Parts
![Page 49: PHASE 4 REPORT - University of Delaware Department … the overall dimensions have changed slightly. ... thread angle of the acme screw, ... for both the wires and switch,](https://reader034.vdocument.in/reader034/viewer/2022051722/5aaa15aa7f8b9a8b188dac06/html5/thumbnails/49.jpg)