phase iii: execution phase iv: monitoring and control earned value analysis burns: chapter 8: pages...

51
Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe: Chapter 7

Upload: evan-lynch

Post on 23-Dec-2015

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Phase III: Execution Phase IV: Monitoring and

ControlEarned Value Analysis

Burns: Chapter 8: pages 10-13

Burns: Chapter 12: the entire chapter

Schwalbe: Chapter 7

Page 2: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Recitation

What does RAM stand for in the context of HR Management?

What was the name of the guy who categorized all job satisfaction factors into two categories?

What were those two categories?

Page 3: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

13–3

The Project Control ProcessControl

The process of comparing actual performance against plan to identify deviations, evaluate courses of action, and take appropriate corrective action.

Project Control Steps1. Setting a baseline plan.

2. Measuring progress and performance.

3. Comparing plan against actual.

4. Taking action.

Tools Tracking and baseline Gantt charts Control charts

Page 4: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

What is a baseline?

It makes the plan difficult to change It is rather like writing the plan (schedule and cost)

on the backside of Moses’ tablets Its an anchor point for measuring performance

against planPlanned costPlanned schedulePlanned scope

Page 5: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

13–5

Baseline and Tracking Gantt Charts

FIGURE 13.1

Page 6: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

13–6

Project Schedule Control Chart

FIGURE 13.2

Page 7: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Important Concepts during Execution

Leadership Communication Focus Tracking

Page 8: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Questions Would you use a Cost Reimbursement contract in a

situation where the requirements are well known and nonvolatile?

Would you use a Fixed Price contract in a situation where the user does not know exactly what he wants?

If the material requirements are certain, but the time and effort entailed and requirements are uncertain, what type of contract would you use?

Page 9: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Freeze Requirements???

What are the PROS?

What are the CONS?

Page 10: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Freeze those requirements!!Late-project creeping requirements are the most

common source of cost and schedule overrunsLate-project creeping requirements are a major factor in

project cancellations

Page 11: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Rather than freezing, use some kind of change control system

Allows for some changes to happen, depending upon contractual considerations

Allows for the system to reject some proposed changes

Use of a CCB is considered a modern BEST PRACTICE

Page 12: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Forces pushing for late-project requirements change

Competition intros new version of competitive product with unanticipated KILLER features

New work is undiscovered late in the project A “Wouldn’t It be Great if…” scenario happens End-users want changes because they now know more

about their requirements than they did 18 months ago Developers want changes because they have a great

emotional and intellectual investment in all of the system’s details

Page 13: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Processes utilized in Phase IIIof the lifecycle Integration management:

Monitor and Control Project WorkPerform Integrated Change Control

Scope management: Control Scope

Time management: Control Schedule

Cost management: Control cost

Quality management: Perform Quality Control

Page 14: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Processes utilized in Phase III, Continued

Communication management: Distribute Information Report Performance

Risk management: Monitor and Control Risks

Procurement management: Administer Procurements

Page 15: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Controlling Changes to the Project Schedule

Perform reality checks on schedules Allow for contingencies?? Don’t plan for everyone to work at 100%

capacity all the time Hold progress meetings with stakeholders and

be clear and honest in communicating schedule issues

Page 16: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Execution

Focus and leadership are keys to success in execution

Poor execution leads to losses in the business world just as it does in sports

Page 17: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Factors leading to poor Execution

Multitasking—doing several things at once

Procrastination (student syndrome)—putting things off until the last minute

Others we will discuss later

Page 18: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Multitasking

A finishes

A finishes

B finishes

Page 19: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Cost Control

Project cost control includesmonitoring cost performanceensuring that only appropriate project changes are

included in a revised cost baseline informing project stakeholders of authorized changes to

the project that will affect costs Earned value analysis is an important tool for cost

control

Page 20: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Earned Value Analysis (EVA)

EVA is a project performance measurement technique that integrates scope, time, and cost data

Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals with EVA

You must enter actual information periodically to use EVA. Figure 6-1 shows a sample form for collecting information

Page 21: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

13–23

Glossary of Terms

TABLE 13.1

EV Earned value for a task is simply the percent complete times its original budget. Stated differently, EV is the percent of the original budget that has been earned by actual work completed.

PV The planned time-phased baseline of the value of the work scheduled. An approved cost estimate of the resources scheduled in a time-phased cumulative baseline [BCWS—budgeted cost of the work scheduled].

AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work. [ACWP—actual cost of the work performed].

CV Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV – AC.

SV Schedule variance is the difference between the earned value and the baseline line to date where SV = EV – PV.

BAC Budgeted cost at completion. Total budgeted cost of the baseline or project cost accounts.

EAC Estimated cost at completion.

ETC Estimated cost to complete remaining work.

VAC Cost variance at completion. VAC indicates expected actual over- or under-run cost at completion.

Page 22: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

13–24

Developing an Integrated Cost/Schedule System

1. Define the work using a WBS.

a. Scope

b. Work packages

c. Deliverables

d. Organization units

e. Resources

f. Budgets

2. Develop work and resource schedules.

a. Schedule resources to activities

b. Time-phase work packages into a network

3. Develop a time-phased budget using work packages included in an activity. Accumulate budgets (PV).

4. At the work package level, collect the actual costs for the work performed (AC). Multiply percent complete times original budget (EV).`

5. Compute the schedule variance (EV-PV) and the cost variance (EV-AC).

Page 23: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Earned Value Analysis Terms

Budgeted cost of work performed (BCWP), also called earned value, is the percentage of work actually completed multiplied by the budget for the activity

Budgeted cost of work scheduled (BCWS),Budgeted cost of work scheduled (BCWS), also called planned value, is that portion of the approved total cost estimate planned to be spent on an activity during a given period

Actual cost of work performed (ACWP), also called actual cost, are the total direct and indirect costs incurred in accomplishing work on an activity during a given period

Page 24: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Earned Value analysis--EVA Earned value = Budgeted Cost of Work Performed

(BCWP) Planned value = Budgeted Cost of Work

Scheduled (BCWS), and Actual Cost = Actual Cost of Work Performed

(ACWP) When you complete an activity, you earn the

budgeted value of that activity

Page 25: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Schedule Variance (SV) Defined as the difference between the budgeted

cost of work performed and the budgeted cost of work scheduled

= BCWP – BCWS = EV - PV Indicates the deviation between the work content

performed and the work content scheduled for the control period

Page 26: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Cost Variance (CV) Defined as the difference between the budgeted

cost of work performed and the actual cost of work performed

= BCWP – ACWP = EV - AC A positive CV indicates a lower actual cost than

budgeted for the control period, while a negative CV indicates a cost overrun

Page 27: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Schedule Performance Index (SPI) Defined as the ratio BCWP/BCWS = EV/PV A value close to 1 indicates an activity that is on

schedule Values greater than 1 suggest the activity is

ahead of schedule Values less than 1 indicate a schedule overrun

Page 28: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Cost Performance Index (CPI) Defined as the ratio BCWP/ACWP = EV/AC A value close to 1 indicates an activity that is on

budget Values greater than 1 suggest the activity is

below budget Values less than 1 indicate a budget overrun

Page 29: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Rules of Thumb for EVA Numbers Negative numbers for cost and schedule

variance indicate problems in those areas. The project is costing more than planned or taking longer than planned

CPI and SPI less than 100% indicate problems

Page 30: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Figure 6-2. Earned Value Calculations for a One-Year Project After Five Months

Page 31: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

In the Figure above Budget at Completion = BAC = original budget at the

planned completion date Time at Completion = TAC = original completion time In the figure above, $100,000 in month 12 Estimate at completion = EAC = BAC/CPI Estimate at completion = $100,000/.83 = $120,455 Estimated time to complete = ETAC = TAC/SPI Estimated time to complete = 12/.96 = 12.55 mos.

Page 32: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Why Earned Value Analysis?? You can’t tell what your true cost variance is

because you don’t know where you are relative to scheduleSuppose you are behind schedule but also you have

spent less than what the schedule has called for. Are you really under budget?

Page 33: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Updating cost estimates BAC = Budget at completion = total budget of the

project activities based on the original project plan Assuming the original budget (the BAC) was

$200,000 and the CPI is 1.12, what is EAC? EAC = BAC / CPI = $200,000 / 1.12 $178,571

Page 34: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Updating schedule estimates TAC = Time at completion = total time required to

complete the schedule, as determined by the CP ETAC = Estimated (revised) time to complete Assuming the TAC was 12 months and the SPI

= .77, what is the ETAC? ETAC = TAC / SPI = 12 / .77 15.6 months Project will be delayed almost 4 months

Page 35: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Updating, Cont’d WR = Work Remaining = budgeted cost of the

work not yet accomplished by the end of the reporting period

WR = BAC - BCWP EAC = updated estimate of the total project cost =

BAC/CPI = BAC/CI ETAC = updated estimate of the total project

duration = TAC/SPI = TAC/SI

Page 36: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Figure 6-3. Earned Value Chart for Project After Five Months

-

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

1 2 3 4 5 6 7 8 9 10 11 12

Month

$

BCWS or Cumulative Plan ACWP or Cumulative Actual BCWP or Cumulative EV

BCWS

ACWP

BWCP

BAC

EAC

Page 37: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

13–42

Cost/Schedule Graph

FIGURE 13.4

Page 38: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

13–43

Earned-Value Review Exercise

FIGURE 13.5

Page 39: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Using Software to Assist in Cost Management

Spreadsheets are a common tool for resource planning, cost estimating, cost budgeting, and cost control

Many companies use more sophisticated and centralized financial applications software for cost information

Project management software has many cost-related features

Page 40: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Using MS Project for Execution & Control

First, make certain your project plan is complete and final

Second, save it as a baseline Begin entering actual information

Actual costsPercentage complete

Page 41: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Tracking: MS Project will track—

Task start dates Task finish dates Task duration Task cost work Percentage of task that is complete

Page 42: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Getting Earned Value Data Visible You can go to view and replace the entry table

with the Earned Value table Or, you can enter the earned value columns into

your existing table through the Insert Column facility.The columns are BCWP, BCWS, ACWP, CV, SC, SPI,

CPI, etc.You can also request the Tracking Gantt Chart off the

LHS side of MS Project

Page 43: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Entering actual start & Finish dates for a task

On the view bar, click Gantt chart In the task name field select the task to update On the Tools menu, point to tracking and click

Update Tasks Under Actual, type the dates in the Start and

Finish boxes

Page 44: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Indicating progress on a task as a percentage

In the task name field of the Gantt Chart Double click—this brings up the task information

sheet Select the general tab In the percentage complete box type a whole

number between 0 and 100

Page 45: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Entering actual costs for a resource assignment

On the Tools menu, click options, then click the calculation tab

Clear the Actual costs are always calculated by MS Project check box

Click OK On the view bar, click Task usage On the view menu, point to the Table, and click Tracking Drag the divider bar to the right to view the Activity Cost field In the activity cost field, type the actual cost for the assignment

for which you want to update costs

Page 46: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

The End…..

Page 47: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

James R. Burns, Texas Tech Univeresity

Earned Value analysis--EV

= Budgeted Cost of WorkPerformed (BCWP)

Also uses Budgeted Cost of WorkScheduled (BCWS), and

Actual Cost of Work Performed(ACWP)

When you complete a milestone,you earn the budgeted value of thatmilestone

James R. Burns, Texas Tech Univeresity

An Example

TIME

Budget

Budget

Actual

Overrun???

James R. Burns, Texas Tech Univeresity

Budgeted Cost of WorkPerformed (BCWP)

Defined as the monetary value ofthe work actually accomplishedwithin the control period.

ACTIVITY BCWP

1 $12,0002 $30,0003 $16,000

$58,.000CUMULATIVE

James R. Burns, Texas Tech Univeresity

Cost Variance (CV)

Defined as the difference betweenthe budgeted cost of workperformed and the actual cost ofwork performed

= BCWP - ACWP A positive CV indicates a lower

actual cost than budgeted for thecontrol period, while a negative CVindicates a cost overrun

Page 48: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:
Page 49: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:
Page 50: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe:

Recitation What are two of the four Myers/Briggs

dimensions? What are the other two? To what Myers/Briggs category do most IT

professionals belong? Who is the motivation guru? What are his five levels? Who gave us Theory X and Theory Y??

Page 51: Phase III: Execution Phase IV: Monitoring and Control Earned Value Analysis Burns: Chapter 8: pages 10-13 Burns: Chapter 12: the entire chapter Schwalbe: