phase shifting transformers -...

38
Page 1 Siemens Energy, Inc. Phase Shifter Application Workshop Phase Shifter Application Workshop James McIver SIEMENS Energy, Inc. SIEMENS Transformers Austria, Weiz Phase Shifting Transformers – Principles, Design Aspects and Operation

Upload: phamkiet

Post on 06-Feb-2018

252 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 1 Siemens Energy, Inc.Phase Shifter Application Workshop

Phase Shifter Application Workshop

James McIver

SIEMENS Energy, Inc.SIEMENS Transformers Austria, Weiz

Phase Shifting Transformers –Principles, Design Aspects

and Operation

Page 2: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 2 Siemens Energy, Inc.Phase Shifter Application Workshop

Purpose and function of PSTs

Basic function of a PST§ In principle, a phase shifting transformer creates a phase

shift between primary (source) & secondary (load) side

§Usually, this phase shift can be varied under load

§Sometimes, it can be made advance and retard

A Phase Angle Regulator >Controls power flow through specific linesCreates a driving force onto power transmission networks

Page 3: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 3 Siemens Energy, Inc.Phase Shifter Application Workshop

Purpose and function of PSTs

How does phase shift influence power flow?

The „natural“ current distribution is dependent on theimpedance of the lines

i1

i2

X1

X2

itotal

VS VL

DV

Page 4: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 4 Siemens Energy, Inc.Phase Shifter Application Workshop

Purpose and function of PSTs

i1

i2VS VL

DV

DV

The „natural“ distribution may be rather inefficient, if X1 andX2 are extremely different.For example if X1 = 2*X2:

Page 5: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 5 Siemens Energy, Inc.Phase Shifter Application Workshop

Purpose and function of PSTs

Equalization of currents:

An additional voltage source must be introduced

i1 +Di

i2- Di

X1

X2

itotal

VS VL

~

VS´

VPST DV1

DV2

Page 6: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 6 Siemens Energy, Inc.Phase Shifter Application Workshop

Purpose and function of PSTs

This additional voltage source, perpendicular to the phasevoltage, generates a „circulating“ current, increasing i1 anddecreasing i2:

DV1

i1+Di i2- Di

VPST

DV2

DV2

DV1

VLVS´VS

VPST

Page 7: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 7 Siemens Energy, Inc.Phase Shifter Application Workshop

Purpose and function of PSTs

Another control need –

Power transfer between nodeswith fixed voltage

Node 1Voltage V1

Node 2Voltage V2

desired power flow

Power System

Page 8: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 8 Siemens Energy, Inc.Phase Shifter Application Workshop

Categories and types

Phase shifting transformers can be classifiedfor different parameters:

§ symmetrical – non symmetrical§ quadrature - non quadrature§ single core - two core§ single tank - two tank

Page 9: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 9 Siemens Energy, Inc.Phase Shifter Application Workshop

Categories and types

Non-symmetrical singlecore solution:

Advantageous for small phase angleand rating

Reversing switch operation is critical

§ Delta-connected excitingwinding,

§ One tap winding§ One LTC§ One reversing change-over

switch

Phasor Diagram:

j

L1 S1

L2

S3

S2L3

Winding Connection with Reversing Switch:S3 L2 S1 L3 S2L1

Page 10: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 10 Siemens Energy, Inc.Phase Shifter Application Workshop

Categories and types

Symmetrical single coresolution:

Load tap changers exposed to systemdisturbances

Rating strongly limited by LTC

§ Delta-connectedexciting winding

§ Two tap windings§ Two tap changers§ Two advance retard

switches j

L1 S1

L2S3

S2L3

Phasor Diagram:

L1 S1 L2 S2 L3 S3

Winding Connection with two ARS Switches:

Page 11: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 11 Siemens Energy, Inc.Phase Shifter Application Workshop

Categories and types

Alternative symmetricaloption:

Often used for lower voltage level

Delta- hexagonal design

§ Hexagonal connection ofexciting winding and tapwinding

§ One LTC§ Two ARS

Winding Scheme with Advance-Retard Switch:S1 L2 S2 L3 S3L1

RW

EW

AdditionalImpedance

j

L1 S1

L2S3

S2L3

Phasor Diagram:

Page 12: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 12 Siemens Energy, Inc.Phase Shifter Application Workshop

Categories and types

Classic solution:

Widely used in USA

Phase Shifting Transformer (PAR)

Winding Arrangement and Connections:

S1 L1 S2 L2 S3 L3

a b c

Phasor Diagram:

a

bc

Secondary (regulating) circuit

j

S1

L2S3

S2L3

L1

Primary circuit

§ Symmetrical two coredesign

§ Series unit and excitingunit

§ One LTC

Page 13: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 13 Siemens Energy, Inc.Phase Shifter Application Workshop

Operational considerations

Phase shifting transformers in Operation:

Variation of load voltage due to load current,ohmic components neglected

iLXPST

VS VL

~

VPST

VL0

jXPST*iL

a

iL

VL

VSVL0

Da

jXPST*iL VPST

j

Page 14: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 14 Siemens Energy, Inc.Phase Shifter Application Workshop

Operational considerations

Effect of load on effective phase angle

Page 15: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 15 Siemens Energy, Inc.Phase Shifter Application Workshop

Operational considerations

§ Impedance as low as possible, minimum value determinedby short circuit requirements

§ With lower impedance, no load phase angle can be reduced

§ Lower no load phase angle means lower design rating, lowerweight, lower cost.

For a given phase shift under load, designoptimization is necessary:

Page 16: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 16 Siemens Energy, Inc.Phase Shifter Application Workshop

Page 17: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 17 Siemens Energy, Inc.Phase Shifter Application Workshop

Tap changer limitations @Max MVA andregulating angle

§ PST’s can be designed with fixed or variable phase angle.For a variable phase angle design, a load tap changer(LTC) and a regulating winding is required.

§ In general, the regulating winding and therefore the LTCmust be designed for the maximum design rating of thePST

§ The maximum regulating capacity (switching capacity perstep times the number of steps) is limited by the capacityof available tap changers.

Tap changer application

Page 18: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 18 Siemens Energy, Inc.Phase Shifter Application Workshop

Tap changer application

Maximum throughput rating Pmaxversus maximum regulating capacity R

0

2

4

6

8

10

0 10 20 30 40 50 60Maximum phase angle (deg)

Pmax/R

Single core, with two tap changers

Single core, with hexagonal winding connection

Dual core, with series and exciting unit

Page 19: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 19 Siemens Energy, Inc.Phase Shifter Application Workshop

Page 20: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 20 Siemens Energy, Inc.Phase Shifter Application Workshop

F1

FS

F2

F1FS

2 1

F2

Power transformerFlux distribution at rated load, cos j ~ 1

Operational considerations

Page 21: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 21 Siemens Energy, Inc.Phase Shifter Application Workshop

Testing

Testing phase shifting transformers :

Heat run§ PST fully assembled§ minimized deviation of loss distribution during short circuit

condition§ access to all windings for resistance measurement

Specific requirements:

Induced voltage test§ PST fully assembled§ tests at zero and maximum phase shift

Page 22: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 22 Siemens Energy, Inc.Phase Shifter Application Workshop

Testing

Heat run test:

For resistance measurement, all these connections can be opened

Temporary bushings inserted at all connections between series and exciting unit

~

Series Transformer

Exciting Transformer

AuxiliaryBushings

Short circuit connection

Page 23: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 23 Siemens Energy, Inc.Phase Shifter Application Workshop

No Load Losses (kW) a = 0 a =maximum

Series UnitExciting Unit

0100

10070

Load Losses (kW) a = 0 a =maximum

Series UnitExciting Unit

4000

400400

Total Losses (kW) a = 0 a =maximum

Series UnitExciting Unit

400100

500470

Note difference in loss distribution for nominaloperation vs. condition for heat run test

Design consideration - Heat run test settings

Page 24: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 24 Siemens Energy, Inc.Phase Shifter Application Workshop

Testing

Induced voltage test:

Application of an additional step-up transformer is avoided by proper tap selection

Temporary bushings are connected to the regulating winding

S2 L2 S3 L3S1 L1

Series Transformer

Exciting Transformer

~ Auxiliary bushings

Page 25: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 25 Siemens Energy, Inc.Phase Shifter Application Workshop

Operational considerations

Bypass breaker considerations

§ Due to the PST’s impedance, inserting the PST withphase angle zero normally reduces the load flow

§ A minimum advance phase angle is necessary to restorethe original load flow condition

§ Therefore, by-passing the PST might be advantageous incertain conditions

§ On the other hand, lightning strikes can also appear withthe PST by-passed

§ Internal stresses have to be investigated carefully for thiscondition

Page 26: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 26 Siemens Energy, Inc.Phase Shifter Application Workshop

Testing

Lightning impulse test:

Recommended test if by-pass breaker is provided - at least for tap position zero (0°)

Only the primary windings of one phase are shown

L2S2 S2 L2

Standard LI test:

Source- andload- terminalconnected

Special LI test:

Page 27: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 27 Siemens Energy, Inc.Phase Shifter Application Workshop

Testing

-50

0

50

100

150

0 40 80 120T(ms)

V(%)

Applied voltage and typical wave shape of voltage at crossover during lightningimpulse test with source and load side terminals connected

Lightning impulse stresses in the series winding

Page 28: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 28 Siemens Energy, Inc.Phase Shifter Application Workshop

Phase shifting transformer protection

In PST, difference between source & load current @ normaloperating condition becomes too large for conventionaldifferential protection.

Therefore, specific differential schemes for PST’s are required,different for single core and dual core designs.

CTs required for protection often located inside tank of the PST.

NOTE > protection scheme must be finalized @ design stage.

In general, PST protection is similar to power transformers.There is one exception > differential relaying

Page 29: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 29 Siemens Energy, Inc.Phase Shifter Application Workshop

Differential protection scheme for dual core design (example)

87-1

87-2

S1

L1

S2

L2

S3

L3

primary

secondary

Page 30: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 30 Siemens Energy, Inc.Phase Shifter Application Workshop

Recent PST units

Phase Shifting Transformer

Two-tank designTwo-core design

Classical design PST

n 700MVA, 230kV, 60Hzn ±32° no load (± 24Taps); 22.2°..-41.8° loadn uk: 11.1% Tap 0; 17.4% Tap 24n Noise Level < 74 dB(A) with fans

Page 31: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 31 Siemens Energy, Inc.Phase Shifter Application Workshop

Recent PST units

Phase Shifting Transformer

Two-tank designTwo-core design

Classical design PST

n 800MVA, 230kV, 60Hzn ±35° no load (± 32Taps); load 25.3°..-44.9°n uk: 11.4% Tap 0 ; 17.6% Tap 32n Noise Level < 77dB(A)

Page 32: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 32 Siemens Energy, Inc.Phase Shifter Application Workshop

650 MVA, 525 kV, ±24°, Largest PSTs in world,(2) for SRP, Arizona and (2) for NPC, Nevada

Page 33: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 33 Siemens Energy, Inc.Phase Shifter Application Workshop

Lake ElsionrePumpPowerHouse

To SCE ValleySub 30

miles

To SCE SerranoSub32

miles

500 kV230 kV115 kV

13.8 to 20 kVExisting

New AdditionsFurtherAdditions

16.5miles

12.7miles

To SDG&E TalegaSub10

miles

To SG&E EscondidoSub37

miles

Lee LakeSubstation

Camp PendletonSubstation

LEAPSTransmission One-

Line

Page 34: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 34 Siemens Energy, Inc.Phase Shifter Application Workshop

Recent PST units

Phase Shifting Transformer

Classical design PST

n 300 MVA, 138 kV, 60 Hz

n ±25.0° at no load (± 16 taps);n 14.4° at rated load - extreme advancen -5.4° at rated load - mid tapn -35.6° at rated load - extreme retardn uk: 9.5% Tap 0; 18.6% Tap 16n Noise level < 70 dB(A)

Single-tank designTwo-core design

Page 35: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 35 Siemens Energy, Inc.Phase Shifter Application Workshop

Recent PST units

Phase Shifting Transformer

Classical design PST

Two-tank designTwo-core design

n 1200MVA, 400kV, 50Hzn ± 24° no load (±16 taps);n 16.6° at rated load - extreme advancen -5.3° at rated load - mid tap (0)n -31.4° at rated load - extreme retardn uk: 9.25% Tap 0; 13.0% Tap 32n Noise power level < 80 dB(A) - sound house

Page 36: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 36 Siemens Energy, Inc.Phase Shifter Application Workshop

Phase shifting transformers >

•Look like normal power transformers

•Manufactured using the same technology

However, several special aspects only in PST’s

PST issues appear in both design and testing.

Therefore special expertise required.

Conclusion

Page 37: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 37 Siemens Energy, Inc.Phase Shifter Application Workshop

Conclusion

§The classical two-tank two-core solution:Offers greatest operational security @higher voltageThis because LTC not directly exposed to systemdisturbances.

§The single-core solution offers economic advantagesat lower system voltage levels (and lower MVA).

Page 38: Phase Shifting Transformers - Siemensw3.usa.siemens.com/smartgrid/us/en/events/Documents/Transformer... · Page 1 Phase Shifter Application Workshop Siemens Energy, Inc. Phase Shifter

Page 38 Siemens Energy, Inc.Phase Shifter Application Workshop

Thank you!

Questions?