phasor measurements in the wecc - about naspi | … · phasor measurements in the wecc ken martin...
TRANSCRIPT
![Page 1: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/1.jpg)
Phasor Measurements in the WECC
Ken Martin – Quanta TechnologyDave Hawkins – California ISOBharat Bhargava – Southern California Edison
WECC Disturbance Monitor Working Group & Wide
Area Measurement Task Force
WECC -- DMWG & WIPP
![Page 2: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/2.jpg)
Early history
• 1986 Phasor Project at BPA – 1st PMU from Virginia Tech– Tested on BPA system 1989-92– Lab tests 1991-2
• EPRI – WSCC phasor controls project– 21 PMUs – APS, BPA, LADWP, PG&E, SCE– Real-time damping controls to DC intertie– Industry restructuring prevented completion
![Page 3: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/3.jpg)
The first Virginia Tech PMU
External signal conditioning unit&GPS receiver
![Page 4: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/4.jpg)
August 10, 1996
• System loses dynamic stability– System breaks into islands when it separates
at Malin– 25, 578 MW of generation lost– 30, 489 MW of load lost– System restoration takes several hours
• WAMS recordings document the breakup with high accuracy
![Page 5: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/5.jpg)
Phasor measurement dataMW Power Transfer
-500
0
500
1000
1500
2000
2500
3000
3500
15:48:40.00 15:48:44.00 15:48:48.00 15:48:52.00 15:48:56.00 15:49:00.00Time
MW
Malin - Round Mountain
Colstrip - Broadview
Voltage Phase Angles
-30
0
30
60
90
120
150
15:48:40.00 15:48:44.00 15:48:48.00 15:48:52.00 15:48:56.00 15:49:00.00
Time
Degr
ees
Grand Coulee - Malin
Colstrip - Grand Coulee
Phasor measurements take on a new life
![Page 6: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/6.jpg)
WAMS Development in WECC• 1997 real time to PDC
– BPA – 4 PMUs– SCE – 4 PMUs
• 1998– BPA – SCE direct link
• 2000 – 2002– Local recording systems at
AESO & Pacific Power– Real-time systems at
APS/SRP, BC Hydro, PG&E, PNM, & WAPA
– BPA—CAISO direct link• 2004
– Direct link PG&E—CAISO & BPA
– Direct link SCE—CAISO
BPA
WAPA
SCE
PG&ECAISO
![Page 7: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/7.jpg)
Current WECC Phasors
BPA PDC
SEL PDC
Macrodyne PDC (Not in Service)
Network connection
Possible Future Network Connection
SCE-LDWP-BPA Microwave Circuit
CONVENTIONS
(aa/bb) # PMUs / # Phasors
States/Provences with PMU Installations
WECC TOTALS132 PMUs877 PhasorsCAISO TOTALS54 PMUs369 Phasors
PG&E (6/42)
LADWP (1/5)
(PMU connected to BPA PDC)
SCE (19/143)
BPA(24/157)
WAPA (5/32)
APS (8/63)
CAISO
BC Hydro (11/63)
CAISO ECN/WECC WON
CERTS/EPG/JRC 10-29-08
PNM(4/24)
SDG&E (5/40)
AESO(26/160)(Local
recording)
NPC (6,48)
IPC
(5/40)Pacific Power(2/20)
(Local recording)
SRP (10/40)
![Page 8: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/8.jpg)
WECC – WAMS real-time net• Real-time phasor data exchange net
– Disturbance Monitor WG & WAMS TF• Builds on current development
– BPA – CAISO link 2002, additions in 2004-6– Use utility PDC units, standard router/firewalls– T1 communication links, utility or leased
• If approved, deployment can start in 2009– 3 year deployment, start with central links & RCs– Expand out to all participating utilities
![Page 9: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/9.jpg)
Current WECC Phasor Net
BPA PDC
SEL PDC
Macrodyne PDC (Not in Service)
Network connection
Possible Future Network Connection
SCE-LDWP-BPA Microwave Circuit
CONVENTIONS
(aa/bb) # PMUs / # Phasors
States/Provences with PMU Installations
WECC TOTALS132 PMUs877 PhasorsCAISO TOTALS54 PMUs369 Phasors
PG&E (6/42)
LADWP (1/5)
(PMU connected to BPA PDC)
SCE (19/143)
BPA(24/157)
WAPA (5/32)
APS (8/63)
CAISO
BC Hydro (11/63)
CERTS/EPG/JRC 10-29-08
PNM(4/24)
SDG&E (5/40)
AESO(26/160)(Local
recording)
NPC (6,48)
IPC
(5/40)Pacific Power(2/20)
(Local recording)
SRP (10/40)
![Page 10: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/10.jpg)
Proposed WECC Synchronized Phasor Network
PDCs
T1 links
CONVENTIONS
XXX Utility host or RC
PG&E
LADWPSCE
BPA
WAPA
APS
CAISO
BCTC
PNM
IPCO
AESO
SDGESRP
Functional diagramPoint-to-point links connected at signal access points.Actual paths and connection points may differ – will be determined by optimal design.
VRCC
LRCC
![Page 11: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/11.jpg)
WECC phasor network (WAMS)BCTCPDCIn
put
syst
em
PMU 1
PMU N
Rou
ter/
Fire
wal
l
Multiple stream data (input)Single stream data (output)
BPAPDCIn
put
syst
em
CISOPDC
Inpu
tsy
stem
PG&EPDCIn
put
syst
em
SCEPDCInpu
tsy
stem
APSPDCIn
put
syst
em
WAPAPDC
WAN network backbone (T1)
PMU 1
PMU 1
PMU 1
PMU 1PMU 1
PMU N
PMU N
PMU N
PMU N
PMU N
Other utilities as needed
LRCCPDC
VRCCPDC
Rou
ter/
Fire
wal
lR
oute
r/Fi
rew
all
Rou
ter/
Fire
wal
lR
oute
r/Fi
rew
all
Rou
ter/
Fire
wal
lR
oute
r/Fi
rew
all
Rou
ter/
Fire
wal
lR
oute
r/Fi
rew
all
![Page 12: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/12.jpg)
Real-time Data Sharing Agreement• Terms of (new) data sharing agreement have
been completed and signing of the document expected in February.
• Scope is limited to data sharing between Transmission Operators and Reliability Coordinators (SCE, BPA, PG&E, WAPA, CAISO, and RC’s).
• Includes an amendment page for other TO’s to sign that are interested in sharing their PMU data.
• Elements of system can be used in NASPInet when it is available
![Page 13: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/13.jpg)
News from around WECC
• PG&E adding PMUs on Pacific intertie• SCE update
– Added 2 new PMUs– Rate case financing– Situation awareness center– Controls projects
• Interesting incidents
![Page 14: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/14.jpg)
Visualization Tiers – Dashboard, Interconnection, Reliability Coordinator, Local AreaReal Time Alarms within ALLRTDMS Client Applications
Visualization – In Use at CAISO
![Page 15: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/15.jpg)
Phasor Workstation in CAISO Control Room
![Page 16: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/16.jpg)
Small Signal Stability is an Emerging Focus –Mode Identification and Characterization
0.7Hz Colstrip Mode
0.4Hz Alberta Mode
0.25 Hz PACI Mode
0.5 Hz Southwest Mode
Higher Damping ⇔Greater Stability
Goal: Real-time identification of oscillatory modes from ambient phasor data
![Page 17: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/17.jpg)
![Page 18: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/18.jpg)
2008-1-26 Pacific DC Line event• PDCI – Path 65 operating at 1700 MW - South to North
flow• Short circuit at Big Eddy substation resulted in loss of
transformers between 500Kv and 230kV (Ice storm)• The loss of the Big Eddy 500/230 kV ties affected the PDCI
controls and an oscillation occurred with the DC current fluctuating approximately +/- 150 amps.
• The SCE operator noticed the oscillations on the analog recorder but the oscillations were not visible on SCADA
• Oscillations continued for an extended period of time and were finally observed by the CMRC on the phasor monitoring system.
• PDCI link was then shut down.
![Page 19: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/19.jpg)
2008-1-26 PDCI event – Sylmar voltage oscillation
![Page 20: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/20.jpg)
EMS 4 second data
![Page 21: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/21.jpg)
2008-5-20 PDCI multiple events-BPA gen. trip
![Page 22: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/22.jpg)
June 1 – Pacific DC Interconnection Oscillation
![Page 23: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/23.jpg)
Southwest Power Link outage• 500 kV transmission line trip• Major angle separation between San Diego area
and Arizona made it very difficult to close the breaker to reconnect the two areas– Load drop required to bring angles into line– Real-time PMU measurements could simplify
process, perhaps minimize load drop • PMU coverage insufficient to due show angle of
separation but do show some of the resulting transients on the SCE system
![Page 24: Phasor Measurements in the WECC - About NASPI | … · Phasor Measurements in the WECC Ken Martin ... XXX Utility host or RC. PG&E. ... CAISO. BCTC. PNM. IPCO. AESO. SDGE. SRP. …](https://reader030.vdocument.in/reader030/viewer/2022021712/5b991f1809d3f22f0a8d3b5b/html5/thumbnails/24.jpg)
The Direction Forward• System analysis
– Incident analysis & problem solving– Operation verification– Model validation
• Real time monitoring– System awareness– Instability & islanding alarms– State estimation
• Measurement based controls