picture report for maersk jabal - eureka control · 2017. 6. 20. · page 6 of 16 b16, e/r 2nd...
TRANSCRIPT
Page 1 of 16
Picture Report for Maersk Jabal
Vessel Name: Maersk Jabal
Customer: Maersk line Ship Mgnt.
Location: Keppel shipyard &
Anchorage
Date: 26 Mar 2016 to 06 April 2016
Jobs Description: To check and service on the following systems
-15ppm monitor calibration
-Fire alarm system condition check
-Cargo Hold Bilge Alarm System
- Fuel Oil Flowmeters to service calibrate
- To install new Fuel oil Leakage Alarm System
REPORTS:
We attended the vessel at Keppel shipyard, discussed with the attending supt
and started the paperworks with the shipyard. Since there was only few days
left before the vessel sail. We had to start work the following day itself.
Page 2 of 16
AA) 15 ppm Calibration
Make: Georim Engineering co. ltd
Model: GBA-155
Serial no: GBA-155-215
Herewith below is the picture of the 15ppm unit installed on board the vessel.
The unit had been
15ppm monitor Analysing unit
The unit has been successfully tested the 000ppm with clean water and tested
the 15ppm alarm using the test tube provided from the maker itself.
Page 3 of 16
When testing the 15 ppm alarm to
second engineer and also ch engineer,
we also tested the 3 way valve and
found satisfactory. The system is now
calibrated and tested to satisfactory
and now ready for operation.
BB) Fire Alarm System
Make: Autronica Auto- Safe
Model: 3.68.0
Version: 3.7.0
As requested by supt. for us to check the complete fire alarm system and
submit condition and recommendation report. Therefore, our guys start to
check and test the complete system.
Herewith below the type of fire alarm panel installed on board. The system
consist of total 4 loops and 124 sensors and call points.
Page 4 of 16
Picture above indicating the main fire alarm control panel.
Picture beside indicating manual call
point type.
Page 5 of 16
Picture indicating the type of smoke
sensor used for the system
We tested and simulated all 4 loops, fire alarm, disable/enable function and
found all working properly.
Loop 1 – we tested total 52 no’s sensors and call point. Found all sensors and
some call points working good except for the following manual call points
A62, poop deck corridor (manual call point)
A63, poop deck emergency d/g room (manual call point)
A70, poop deck corridor (manual call point)
A81, main deck CO2 room (manual call point)
A82, main deck changing room (manual call point)
Loop 2 – we tested total 50 no’s sensor and call point, found the following
below faulty and need replacement.
B03, casing –deck (manual call point)
B06, poop deck E/R entrance (manual call point)
B09, E/R 2nd deck, M/E stairway (manual call point)
Page 6 of 16
B16, E/R 2nd deck, S/G room entrance (manual call point)
B24, E/R 2nd deck, spare M/E cylinder (smoke detector)
B43, E/R 3rd deck floor, M/E stairway stbd (manual call point)
B63, E/R floor, stairway stbd (manual call point)
B67, E/R floor, emergency exit (manual call point)
Loop 3 – we tested total 09 sensors and call points. The following found faulty
and require replacement.
C11, B/S bow thruster room (manual call point)
Loop 4 – we tested total 13 no’s sensors and call points and found all working
in good condition.
In order to get the system complete operational, we will require to renew all
the faulty items and must be addressed by maker before delivering to the
vessel.
Remark: We were unable to test the following 09 no’s sensors due to time
constrain and also located very high. There was no access. Had inform supt
regarding this.
B04, B05, D05, D06 and D07 – Located above M/E
D08, D09, D10 and D11 – Located above no 1, 2 and 3 generator
CC) Cargo Bilge Alarm System
Attended the vessel and check and test the cargo hold bilge level alarm system
as requested by supt. Total there are 6 cargo hold. Cargo hold 2 to 6 consist of
2 no’s bilge sensor each and cargo hold no 1 only consist of 1 bilge sensor.
There is also 2 no’s bilge sensor located at bow thruster room. So total there
are 13 no’s bilge level sensor in the system. Picture below indicating the
monitor of the system.
Page 7 of 16
All bilge sensor alarm is indicated on the computer monitor in engine control
room as in picture above.
We tested all the 13 no’s bilge sensor and found as follows
-In bow thruster room, tested both the fwd and aft bilge sensor and found
satisfactory.
-Cargo hold no.1 to no.6, total 11 no’s all found in very bad condition. Now
working.
Informed the supt. and requested all the following 11 no’s bilge sensor must
be renewed in order to get the system up and running.
NOTE: The system was then tested and simulated from the IS barrier to
confirm that the loop was working satisfactory and only sensor require
renewal.
Page 8 of 16
Picture above indication the condition of most of the cargo hold bilge level
sensors.
ADDITIONAL JOB TO RENEW ALL BILGE LEVEL SENSORS AFTER CONFIRMATION
BY SUPT.
As requested and confirmed by attending supt. To renew all the faulty cargo
hold bilge alarm sensors. We proceed with the order and upon receiving the
new bilge alarm sensors, we carried out the renewal job accordingly at
anchorage.
Page 9 of 16
Since the bilge level sensors was in very bad condition, we had to knock out all
the bolt, drill and re-tap the bolt thread. Renew the bolts and also gaskets.
Finally we manage to renew all the faulty cargo hold bilge level sensor
accordingly and connect and secure the cables properly.
Supt had ordered total of 13 no’s bilge level sensors. Total 11 no’s had been
renewed for cargo hold and 2 no’s to supply as ship spare.
As picture beside indicating all the faulty
sensors was replaced and brought on top the
deck. All was found in poor condition.
Page 10 of 16
Finally the cargo hold bilge level alarm system was tested after renewal and
found in satisfactory condition. Ch engineer and second engineer was satisfied
with the system.
DD) Fuel Oil Flow Meters
As requested by supt to remove and bring out the fuel oil flow meters for
shore calibration on URGENT basis. Therefore the following flow meters were
remove and brought back to shore. The removed pipes was blanked with
flanges as requested and for safety reason.
- M/E Fuel Oil Flow Meter 01 unit
Make: NITTO
Serial no: 0166978
- G/E Fuel Oil Flow Meter 01 unit
Make: NITTO
Serial no: 0166979
- CONTOIL Flow Meter 01 unit
Serial no: 4668294
Picture below indicating the removal of flow meters locate inside purifier room
Page 11 of 16
The 3 no’s flow meters was calibrated and obtained meter factor accordingly.
Finally the flow meters was delivered on board and installed. After running for
1 day during vessel shifting to anchorage, second engineer complained that the
G/E fuel oil flow meter was not working. Therefore, when we attended the
vessel at anchorage, we opened up dismantled the counter assembly to
investigate the fault.
The counter assembly was removed from
the flow meter to investigate on the fault
complained.
We then dismantle the magnetic
gear shaft and found it was jammed
due to some small particle found
stuck inside. So we dismantle the
complete piece, serviced and
assemble back to original. Then installed back and tested to satisfactory. Ch
engineer and 2nd engineer was satisfied.
Finally all the flow meters was tested and found in satisfactory and ready for
operation.
Page 12 of 16
EE) Installation of New Fuel Oil Leakage Alarm system
As discuss with supt. on board the vessel, we are requested to design, supply
and install a new fuel oil leakage alarm system on the existing fuel oil leakage
line located in the engine room platform. So we discussed, sketch a drawing
and agreed by supt that we will design according to drawing.
Upon confirmation, we start the fabrication of new oil tank with one inlet on
top, one outlet return line, one testing oil inlet on top of the tank and a
horizontal float installed to the tank. Picture below indicating the newly
fabricated oil tank.
Testing with oil inlet Oil leakage inlet
Outlet return line
We also installed a valve on the inlet line to oil tank and outlet return line as
requested by ch engineer.
So as requested by supt. we start to remove the main fuel oil leakage pipe
which was about 350mm diameter, and transport to the engine room
workshop where the hot works can take place. See picture below
Page 13 of 16
After dismantling the big pipe and lifting it down, we transported the pipe to
the engine room workshop. There, the ship crew assisted us in the hot works.
We cut the socket out and welded a 2 inch
pipe elbow pipe with a flange connection.
Page 14 of 16
After hot works completed, we transport back the big pipe to its original
location and fit in place so that we can start to fabricate the 2 inch pipe from
the flange connection to the new oil tank.
Newly fabricated 2 inch pipe new oil tank
After all pipe fabrication, we installed the
magnetic float switch and connected the
cable which we had run from engine
control room console to the engine room
bottom platform at the newly oil tank.
Magnetic float switch
Page 15 of 16
We also fabricated a new alarm panel with two alarm points (one as spare).
The alarm panel was installed on top of the engine room console as agreed by
ch engineer and supt. See picture below.
Newly fabricated alarm panel with two alarm points
We also run cable from the new alarm panel in engine control room to the
outside of engine control room where we had installed an external
audio/visual upon request. See picture below
Page 16 of 16
Finally upon completion, we tested the complete system with the presence of
ch engineer and second engineer by actually filling the new oil tank with oil.
The alarm activated accordingly and they also checked on the audio/visual
alarm locate outside engine control room. The sound was loud enough and can
be heard clearly in engine room. The system is found satisfactory and accepted
by ch engineer.
REMARK: ALL MATERIALS USED ARE REFLECTED IN SERVICE REPORT
ACCORDINGLY
End of Report