pip-ii*: overview, goals , status , and strategy

48
PIP-II*: Overview, Goals, Status, and Strategy Stuart Henderson Fermilab CERN Visit February 11, 2014 *Proton Improvement Plan-II

Upload: kamil

Post on 22-Feb-2016

47 views

Category:

Documents


0 download

DESCRIPTION

Stuart Henderson Fermilab CERN Visit February 11 , 2014. PIP-II*: Overview, Goals , Status , and Strategy. *Proton Improvement Plan-II. Recent Developments. See XMAC website. New Fermilab Director Established LBNE as laboratory flagship - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PIP-II*:  Overview, Goals , Status , and Strategy

PIP-II*: Overview, Goals,Status, and Strategy

Stuart HendersonFermilab

CERN VisitFebruary 11, 2014

*Proton Improvement Plan-II

Page 2: PIP-II*:  Overview, Goals , Status , and Strategy

Recent Developments

• New Fermilab Director Established LBNE as laboratory flagship Requested rework of Project X concept to provide significant

enhancement to LBNE, at an affordable cost to DOE Requested a new name

• P5 formed to provide advice to DOE Plan for the next ten years, within context of next twenty

• PIP-II concept developed Whitepaper published Presentation to P5 at BNL meeting Funding requirements to P5

• Fermilab assumes major role in srf cryomodule production for LCLS-II

S. Henderson, CERN Visit2

See XMAC website

Page 3: PIP-II*:  Overview, Goals , Status , and Strategy

Motivation/Goals

Our goal is to construct & operate the foremost facility in the world for particle physics utilizing intense beams.• Neutrinos

MINOS+, NOvA @700 kW (now) LBNE @ >1 MW (2025) LBNE @ >2 MW (>2030) Short baseline neutrinos

• Muons Muon g-2 @ 17 kW (2017) Mu2e @ 8 kW (2020) Mu2e @ 100 kW (>2023)

• Longer term opportunities Þ This will require more protons!

S. Henderson, CERN Visit 3

Page 4: PIP-II*:  Overview, Goals , Status , and Strategy

Design Criteria

Support long term physics research goals by providing increased beam power to LBNE while providing a platform for the future Design Criteria

Deliver 1.2 MW of proton beam power from the Main Injector to the LBNE target at 120 GeV, with power approaching 1 MW at energies down to 60 GeV, at the start of LBNE operations

Continue support for the current 8 GeV program, including Mu2e, g-2, and the suite of short-baseline neutrino experiments; provide upgrade path for Mu2e

Provide a platform for eventual extension of beam power to LBNE to >2 MW

Provide a platform for extension of capability to high duty factor/higher beam power operations

At an affordable cost to DOE

S. Henderson, CERN Visit4

Page 5: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit

Strategy

• Increase Booster/Recycler/Main Injector per pulse intensity by ~50%. Requires increasing the Booster injection energy

• Select 800 MeV as preferred Booster injection energy 30% reduction in space-charge tune shift w/ 50% increase in beam intensity Provides margin for lower beam loss at higher intensities

• Modest modifications to Booster/Recycler/Main Injector To accommodate higher intensities and higher Booster injection energy

Þ Cost effective solution: 800 MeV superconducting pulsed linac, extendible to support >2 MW operations to LBNE and upgradable to continuous wave (CW) operations Building on significant existing infrastructure Capitalizing on major investment in superconducting rf technologies Eliminating significant operational risks inherent in existing linac Siting consistent with eventual replacement of the Booster as the source of

protons for injection into Main Injector

5

Page 6: PIP-II*:  Overview, Goals , Status , and Strategy

Performance Goals

Performance Parameter PIP-II  

Linac Beam Energy 800 MeV

Linac Beam Current 2 mA

Linac Beam Pulse Length 0.6 msec

Linac Pulse Repetition Rate 15  Hz

Linac Beam Power Capability (10-15% DF) ~200  kW

Mu2e Upgrade Potential (800 MeV) >100 kW

Booster Protons per Pulse  6.4×1012  

Booster Pulse Repetition Rate 15 Hz

Booster Beam Power @ 8 GeV 120 kW

Beam Power to 8 GeV Program (max) 40 kW

Main Injector Protons per Pulse 7.5×1013  

Main Injector Cycle Time @ 120 GeV 1.2 sec

Main Injector Cycle Time @ 80 GeV 0.8 sec

LBNE Beam Power @ 80-120 GeV 1.2 MW

LBNE Upgrade Potential @ 60-120 GeV >2 MW

S. Henderson, CERN Visit6

Page 7: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit

Options

• Plan A - Superconducting Linac 800 MeV pulsed SC linac Constructed from CW-capable accelerating modules Operated initially at low duty factor Sited in close proximity to Booster and to significant existing

infrastructure• Plan B - Afterburner

400 MeV pulsed linac appended to existing 400 MeV linac 805 MHz accelerating modules Requires physical relocation of existing linac upstream ~50 m ~1 year interruption to operations Less expensive than Plan A

7

Page 8: PIP-II*:  Overview, Goals , Status , and Strategy

Pluses and Minuses of these Options

S. Henderson, CERN Visit8

Plan A: PIP-II Plan B

Beam power to LBNE 1.2 MW 1.2 MW

Cost to DOE (FY2020 $M) $350-400 $250

R&D aligned with efforts to date Y N

Upgradable to 2 MW to LBNE Y Y

High Duty Factor Capable Y NProton Driver for Muon Facility Y N

Upgrade paths utilize 1.3 GHz infrastructure & capabilities Y N

Retires significant reliability risks Y N

Interruption to operations ~2 months >12 monthsInternational contribution & collaboration Significant MinimalReutilization of existing infrastructure Significant Modest

Status of technical development/understanding Advanced conceptual

Pre-conceptual

Page 9: PIP-II*:  Overview, Goals , Status , and Strategy

Site Layout (provisional)

S. Henderson, CERN Visit9

Page 10: PIP-II*:  Overview, Goals , Status , and Strategy

Linac Technology Map

S. Henderson, CERN Visit10

Section Freq Energy (MeV) Cav/mag/CM Type

RFQ 162.5 0.03-2.1

HWR (opt=0.11) 162.5 2.1-11 8/8/1 HWR, solenoid

SSR1 (opt=0.22) 325 11-38 16/8/ 2 SSR, solenoid

SSR2 (opt=0.51) 325 38-177 35/21/7 SSR, solenoid

LB 650 (G=0.61) 650 177-480 30/20/5 5-cell elliptical, doublet

HB 650 (G=0.9) 650 480-800 24/10/4 5-cell elliptical, doublet

=0.11 =0.22 =0.51 =0.61 =0.9

325 MHz11-177 MeV

650 MHz177-800 MeV

SC

162.5 MHz0.03-11 MeV

LEBT RFQ MEBT

RT

IS

Page 11: PIP-II*:  Overview, Goals , Status , and Strategy

Booster/Recycler/MI Requirements

• Booster New injection girder to accept 800 MeV and enable

transverse beam painting Additional rf voltage (3-4 cavities) to support

transition crossing manipulations Upgrades to damper and collimator systems

• Recycler RF cooling upgrade for operations at <1.2 sec cycle Collimator upgrade

• Main Injector RF power upgrade; new power amplifiers

S. Henderson, CERN Visit11

Page 12: PIP-II*:  Overview, Goals , Status , and Strategy

R&D Strategy

• The goal is to mitigate risk: technical/cost/schedule• Technical Risks

Front End (PXIE) Systems test:Ion Source through SSR1

Booster/Recycler/Main Injector beam intensity 50% per pulse increase over current operations Longitudinal emittance from Booster for slip-stacking Beam loss/activation

High Power targets Will become provenance of LBNE starting FY15

• Cost Risks Superconducting rf

Cavities, cryomodules, rf sources represent 46% of construction costs

Þ Goal: Be prepared for a construction start in 2018

S. Henderson, CERN Visit 12

Page 13: PIP-II*:  Overview, Goals , Status , and Strategy

P5http://www.usparticlephysics.org/p5

• Fermilab meeting established goal of >1 MW to LBNE at start of operations

• PIP-II whitepaper and presentation at BNL meeting Overview of concept and estimated cost

• Subsequent interactions PIP-II Project Worksheet

$380M cost to DOE, assuming $160M international in-kind contribution

$80M of off-project costs for srf development and AIPs (Booster/Recycler/Main Injector)

FY18-22 construction period

S. Henderson, CERN Visit13

Page 14: PIP-II*:  Overview, Goals , Status , and Strategy

P5http://www.usparticlephysics.org/p5

• Subsequent interactions Funding plan based on redirection of Fermilab

internal funding. Two versions: FY18-22 construction period FY19-23 construction period

• P5 will provide “preliminary comments” to HEPAP in March, final report in May

S. Henderson, CERN Visit14

Page 15: PIP-II*:  Overview, Goals , Status , and Strategy

Collaborative Aspects• Organized as a “national project with international participation”

Fermilab as lead laboratory

• Collaboration MOUs for the RD&D phase :National IIFC

ANL ORNL/SNS BARC/MumbaiBNL PNNL* IUAC/DelhiCornell UTenn* RRCAT/IndoreFermilab TJNAF VECC/KolkataLBNL SLACMSU ILC/ARTNCSU*

• *Recent additions bringing capabilities needed for experimental program development, in particular neutron targets and materials applications

• We are eager to establish a collaborative relationship with CERN for PIP-II

S. Henderson, CERN Visit15

Page 16: PIP-II*:  Overview, Goals , Status , and Strategy

Flexible Platform for the Future

• PIP-II Inherent Capability ~200 kW @ 800 MeV (2 ma × 800 MeV × 15%) × 10 Mu2e sensitivity

• Extentions 2 MW to LBNE CW operations at >1 MW Neutrino Factory/Muon

Collider

S. Henderson, CERN Visit16

Page 17: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit17

RF parameters of SCL cavitiesSection Freq.

MHzGain per

cavity,MeV

Gradient*, MeV/m

Peak electric field,

MV/m

Peak magnetic field,

mT

R/Q, Ohm

Q0@2K(1010)

RF load per

cavity, W

HWR (G=0.11)

162.5 1.7 8.2 38 41 272 0.5 2.1

SSR1 (G=0.22)

325 2 10 38 58 242 0.5 3.3

SSR2 (G=0.51)

325 5.3 11.2 39 70 275 1.2 8.5

LB650 (G=0.61)

650 11.7 16.6 38 70 378 1.5 24

HB650 (G=0.9)

650 17.7 17 34 64 638 2.0 25

• Epeak ≤ 40 MV/m (Field emission); *Leff=Gn/2,

• Bpeak ≤ 75 mT (medium field Q-slope) n is number of cells

Page 18: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit18

• RF load:o ILC: <5 W/CM (0.5 % duty cycle, Eacc = 35 MeV/m);o Project X: ~200 W/CM (100% duty cycle, Eacc = 17 MeV/m).• For CW operation RF load and thus, Q0 is an issue.• High Q0 allows lower capital cost (cryosystem) and operational cost (few MW reduction of power consumption).• High Q0 allows higher gradient at CW and, thus, allows lower capital cost of the linac.• Increase of Q0 ~two times may save many tens of M$ for a billion-scale project.

Q0 Improvement*: Improvement of cavity processing recipes; High Q0 preservation in CM.

CW Operational Aspects

Page 19: PIP-II*:  Overview, Goals , Status , and Strategy

162.5 MHz, = 0.11 Half Wave Resonator (HWR): Collaboration with ANL

The cavity parts, coupler and solenoid prototypes are ready, CM design compete Very similar to cavities & CM already manufactured by ANL Optimize to achieve tight packing in PX front end

S. Henderson, CERN Visit19

Page 20: PIP-II*:  Overview, Goals , Status , and Strategy

SRF DevelopmentSSR1 (325 MHz)

• Two prototypes fabricated by industry, processed in collaboration with ANL, and tested at Fermilab as part of HINS program

• One cavity dressed with He vessel, coupler tuner• Two cavities in fabrication at IUAC-Delhi (Q3 FY13 )• Ten cavities fabricated by US industry (all have arrived, 6 tested)

Tests in progress

S. Henderson, CERN Visit 20

Page 21: PIP-II*:  Overview, Goals , Status , and Strategy

SRF DevelopmentSSR1 (325 MHz)

S. Henderson, CERN Visit 21

Bare cavity at 2 K

Microphonics Active Damping: SSR1

dressed cavityGradient/Q0 performance: SSR1 bare cavity at 2 K

Page 22: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit

Microphonics mitigation in 325 MHz SSR1 Cavities

22

“Passive” microphonics damping in a SSR1 cavity:df/dP <10 Hz/Torr; mechanical resonance > 300 Hz.• New He vessel design is ready;• Internal Technical Review was in December 2012;• Expect to dress 10 cavities by January, 2014 for

the first SSR1 cryo-module.

Tuner design

Page 23: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit

SSR1 Cryomodule elements

23

• Maximum design power.– Project X, 5 mA: ~30 kW.

• One ceramic window at room temperature.

• No external adjustment.• Air cooled center conductor.• HP tests of the first prototypes  are 

scheduled for 2013

Conduction cooled 

leads similar to 

CERN and DESY 

Leads (I≤100 A).

Solenoid prototype is ordered, will be tested in 2013.

Page 24: PIP-II*:  Overview, Goals , Status , and Strategy

SSR1 Cryo-module:

S. Henderson, CERN Visit24

• Overall length (CS-GV Flanges)-5230mm

• Number of Spoke resonators-8

• Number of Solenoids-4• Distance between spoke

resonators: 450/800mm• Distance between solenoids-

1250mm

• CM design is ready.

• Internal Technical Review was on Feb 5, 2013;

• CM complete - April, 2016

Page 25: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit

325 MHz, b = 0.51 Single Spoke Resonator (SSR2)

25

Cavity EM design Frequency 325 MHz  Optimal Beta βO=0.51  Beam Aperture 50 mm  Effective length 475.3 mm  Radius, Length 280 mm, 540 mm  Epk/Eacc 3.53  Bpk/Eacc 6.25 [mT/(MV/m)]  G 118 Ω  R/Q 275 Ω  Q0 (at Rs = 10 nΩ) 1.2x1010

  Max Epk 40 MV/m  Max Bpk 70 mT  Max Energy Gain 5.3 MeV  Max Gradient 11.2 MV/m  Pdiss at Max Energy Gain 8.6 WCavity Mech Design He Vessel Material Stainless Steel  Maximum Allowable Pressure 2 bar RT, 4 bar CT  df/dp ≤ 25 Hz/mbarRF Coupler Max forward power at full

reflection20 kW

Tuning System Coarse tuning range 135 kHz  Fine tuning range 500 Hz EM design complete Mechanical design is advanced Prototype (jacketed and tested) in FY 15 RF coupler is the same as for SSR1

H

E

Page 26: PIP-II*:  Overview, Goals , Status , and Strategy

• Prototypes: Two single-cell =0.6 cavities received (JLab) Six single-cell  = 0.9 cavities received; four five-cell on order

(AES) Five single-cell  = 0.9 cavities ordered(PAVAC, ARRA funds) Prototypes at both under fabrication in India

• Infrastructure modifications completed for 650 MHz− Vertical Test Stand− Cavity handling & HPR tooling − Optical inspection system − New electro-polishing tool (ANL)

S. Henderson, CERN Visit 26

SRF Development650 MHz

Page 27: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit27

Single-cell prototypes (photos): 5-cell model, HE650 LE 650 MHz (JLAB version) HE 650 MHz (FNAL)

Elliptical cavities of the high-energy part of CW linac

Parameter LE650 (FNAL) HE650(FNAL)βgeom 0.61 0.9Cavity Length = ncell∙βgeom/2 mm 703 1038R/Q Ohm 378 638G-factor Ohm 191 255Max. Gain/cavity (on crest) MeV 11.7 17.7Acc. Gradient MV/m 16.6 17Max surf. electric field MV/m 37.5 34Max surf. magnetic field, mT 70 61.5Q0 @ 2K 1010 1.5 2.0P2K max [W] 24 24

Page 28: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit 28

Gradient/Q0 performance: 650 MHz, =0.9., single cell at at 2 K

Jan 29: EP only; Feb 15: EP+120C bake; Feb 19: BCP only.

SRF Development650 MHz

Page 29: PIP-II*:  Overview, Goals , Status , and Strategy

He vessel for 650 MHz, =0.9 Cavity

Stiffening rings located to minimize df/dP while maintaining tunability

S. Henderson, CERN Visit29

Blade Tuner – scaled ILC:• High df/dP,• Poor tuning efficiency;

New End Tuner design:• Low df/dP,• Mechanical resonance >60 Hz;• Good tunability;• Less expensive.

Page 30: PIP-II*:  Overview, Goals , Status , and Strategy

CM development for 650 MHz section

S. Henderson, CERN Visit30

• Working on CM engineering design and 3D models of 650 MHz CM;

• Collaboration with India;

• No funds for M&S.

• The baseline design concept includes cryomodules closed at each end, individual insulating vacuums, with warm beam pipe and magnets in between cryomodules;

• Provide the required insulating and beam vacuum reliably; • Minimize cavity vibration and coupling of external sources to cavities; • Provide good cavity alignment (<0.5 mm); • Allow removal of up to 250 W at 2 K per cryomodule;• Provide excellent magnetic shielding for high Q0.

Page 31: PIP-II*:  Overview, Goals , Status , and Strategy

SRF DevelopmentStatus and Plans

S. Henderson, CERN Visit Page 31

Page 32: PIP-II*:  Overview, Goals , Status , and Strategy

Project X Injector ExperimentPXIE

• PXIE is the centerpiece of the PX R&D program Integrated systems test for Project X front end

components Validate concept for Project X front end,

thereby minimizing primary technical riskelement within the Reference Design

Operate at full Project X design parameters

• Systems test goals 1 mA average current with 80% chopping of beam delivered from RFQ Efficient acceleration with minimal emittance dilution through ~30 MeV

• PXIE will utilize components constructed to Project X specifications wherever possible Opportunity to re-utilize selected pieces of PXIE in PX/Stage 1

• Collaboration between Fermilab, ANL, LBNL, SNS, India

S. Henderson, CERN Visit 32

Page 33: PIP-II*:  Overview, Goals , Status , and Strategy

PXIE Layout

PXIE will address the address/measure the following: LEBT pre-chopping Vacuum management in the LEBT/RFQ region Validation of chopper performance Bunch extinction MEBT beam absorber MEBT vacuum management Operation of HWR in close proximity to 10 kW absorber Operation of SSR with beam Emittance preservation and beam halo formation through the front end

S. Henderson, CERN Visit 33

RFQ MEBT HWR SSR1 HEBTLEBT

40 m, ~25 MeV

Page 34: PIP-II*:  Overview, Goals , Status , and Strategy

R&D Hardware Status

• PXIE Ion source operational and characterized (LBNL→FNAL) LEBT emittance scanner procurement initiated (SNS) LEBT solenoids delivered (FNAL) RFQ design complete; fabrication initiated (LBNL) HWR cavity design complete and procurements initiated; CM

design in process (ANL) Nine qualified SSR1 cavities now in hand; CM design in process

(FNAL) Chopper proof-of-principle prototypes and driver development

(FNAL) Shielded enclosure under construction at CMTF

• SRF Major progress on HWR, SSR1, 650 MHz ellipticals, and high Q0

S. Henderson, CERN Visit34

Page 35: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit35

Summary

• The Fermilab accelerator complex can be upgraded to establish LBNE as the leading long-baseline program in the world, with >1 MW at startup (2025)

• The Proton Improvement Plan-II (PIP-II) is a complete, integrated, cost effective concept, that meets this goal, while leveraging U.S. superconducting rf investment, attracting international partners, providing a platform for the long-term future

• PIP-II retains flexibility to eventually realize the full potential of the Fermilab complex LBNE >2 MW Mu2e sensitivity x10 MW-class, high duty factor beams for rare processes experiments

• We look forward to a positive recommendation from P5, and are in a position to move forward expeditiously.

Page 36: PIP-II*:  Overview, Goals , Status , and Strategy

Potential Areas of Collaboration

• Would be desirable to identify a complete system(s)

• Primary candidates of appropriate scale are Low-beta 650 MHz SCL system: 5 CMs Superconducting spoke resonator 2 (SSR2): 7 CMs

• Other (smaller) candidates include Magnets & PS for transfer line Cryogenic distribution system components instrumentation

S. Henderson, CERN Visit36

Page 37: PIP-II*:  Overview, Goals , Status , and Strategy

Backup

S. Henderson, CERN Visit37

Page 38: PIP-II*:  Overview, Goals , Status , and Strategy

Linac Length Compare

• Length of existing linac enclosure 400 MeV: 145 m

• Length of PIP-II 800 MeV: 190 m 540 MeV: 145 m

S. Henderson, CERN Visit38

Page 39: PIP-II*:  Overview, Goals , Status , and Strategy

Flexible Beam Formats

S. Henderson, CERN Visit39

Page 40: PIP-II*:  Overview, Goals , Status , and Strategy

2+ MW

• Require 1.5×1014 particles from MI every 1.2 s @ 120 GeV Every 0.6 sec @ 60 GeV

• Slip-stacking is not an option at these intensities Need to box-car stack 6 x 2.5E13 protons in less

than 0.6 sec Þ >10 Hz rep-rate Either Recycler (8 GeV) or MI (6-8 GeV)

S. Henderson, CERN Visit40

Page 41: PIP-II*:  Overview, Goals , Status , and Strategy

2+ MW

• Booster is not capable of accelerating 2.5×1013 no matter how it is upgraded Requires ~0.1% beam loss High impedance Transition crossing Poor magnetic field quality Poor vacuum Inadequate shielding

Þ Achieving 2+ MW from Main Injector will require construction of a 1.5 GeV linac Can feed Main Injector via either a 6-8 GeV pulsed linac

or rapid cycling synchrotron (RCS)

S. Henderson, CERN Visit41

Page 42: PIP-II*:  Overview, Goals , Status , and Strategy

2+ MW to LBNE

S. Henderson, CERN Visit 42

LinacParticle Type H-

Beam Kinetic Energy 8.0 GeVPulse rate 10 HzPulse Width 6 4.3 msecParticles per cycle to Recycler/MI 2.51013

Beam Power @ 8 GeV 320 kW

Main Injector/RecyclerBeam Kinetic Energy (maximum) 60/120 GeVCycle time 0.6/1.2 secParticles per cycle 1.51014

Beam Power at 60-120 GeV 2400 kW

Page 43: PIP-II*:  Overview, Goals , Status , and Strategy

LBNE Target Facility @ 1.2 MWDevelopment Needs

• The LBNE target needs to accept 1.2 MW beam power• Development proceeding in the following areas:

S. Henderson, CERN Visit43

System Requirements

Primary Beam Window Active cooling @2.3 MW; 1.2?

Target Higher stress

Horns Higher heat load and stress

Hadron Monitor Radiation hardening, active cooling

Remote Handling Additional short term storage facilities

Cooling Systems Expanded capacity

Target Hall Shielding 0.25 m additional concrete shielding (top)

Page 44: PIP-II*:  Overview, Goals , Status , and Strategy

Cost Estimate

• Scope = Linac + beam transfer line + R&D + ProjMan + civil LBNE target/horn system managed/funded by LBNE Booster, Recycler, Main Injector upgrades managed through operating

departments and funded as AIPs• Reutilize components from the PX/PIP-II development program• Estimate of cryogenic systems based on new concept for low

duty factor operations*• Estimate of civil construction based on new siting*• Estimate of rf for lower duty factor operations (modest savings)• Efficient project schedule: 7 years from CD-0 to CD-4• Escalated to FY20 dollars

Þ DOE/TPC metric

S. Henderson, CERN Visit44

*Substantial savings from PX

Page 45: PIP-II*:  Overview, Goals , Status , and Strategy

Cost Estimate

S. Henderson, CERN Visit45

PIP-II Major Cost Component Estimate ($M)R&D $27Project Management $26Accelerating Cavities and Cryomodules $70RF Sources $29 Cryogenic Systems (reuse existing CHL)  $14Civil Construction $66Instrumentation $12Controls $13Mechanical Systems $3Electrical Systems $2Beam Transport $5Sub-total (direct, FY2013 dollars) $266Indirects, Contingency (40%), escalation (18%) $276TOTAL PROJECT COST (FY2020 Dollars) $542

Page 46: PIP-II*:  Overview, Goals , Status , and Strategy

S. Henderson, CERN Visit

International Contributions

• Discussions at agency and laboratory levels indicate that an 800 MeV SC linac could attract significant in-kind contributions from India/Europe/Asia SC accelerating structures RF sources Instrumentation Magnets/power supplies $150-200M (TPC metric) plausible

• Significant R&D collaboration for >5 years with India Discussions at DOE-DAE level on potential Indian in-kind

contributions

46

Page 47: PIP-II*:  Overview, Goals , Status , and Strategy

Mu2e w/ PIP-II

• Can operate PIP-II linac up to ~15% duty factor with cryogenic system as designed

• RF system as designed can support 2 mA (averaged over 1 msec) at 15% duty factor

• RFQ can supply 10 mA• MEBT chopper can provide arbitrary bunch

patterns for separation at downstream end of linac.• Mu2e Operations:

10% micro-duty factor (100 ns×1 MHz) 13.5% macro-duty factor (9 ms×15 Hz) 10%×13.5%×10mA×800 MeV = 108 kW

S. Henderson, CERN Visit47

Page 48: PIP-II*:  Overview, Goals , Status , and Strategy

Mu2e w/PIP-II

S. Henderson, CERN Visit48

9 ms, 1 mA (Mu2e)

1 ms, 2 mA (Boo)

67 ms

                                                                                                                            

                                                                                                                              . . .

1 ms

6 ns

100 ns, 10 mA

                                       

                                                                                                . . .