plan exising head build desk · 2018. 8. 15. · the balcony is bolted onto the new extension at...
TRANSCRIPT
-
fRSI
EIFS
LTBs &
retrofitENERGY ANALYSIS
4
Solid concrete wall improved to0.103W/m2K using ‘KINGSPAN KOOLTHERM K5’ External insulationEPS (A+ rating from BRE Green Guide)
New walls to extensions: ‘KingspanTEK Panel System’, 15mm OSB sheathing 142mm Kingspan EPS rigid insulation(Rating A+ BRE Green Guide) insulatedand vapour checked internally KOOLTHERM insulated plasterboardExterior, ‘Kingspan Nilvent’ non-tentingwind barrier membrane, 50mm externalair layer, vertical battens with plywoodmesh and acrylic render �nishThe plywood sheathing to the exteriorprovides structural stability to theTEK panel extension
New walls to extensions: ‘KingspanTEK Panel System’, 15mm OSB enclosing142mm Kingspan KOOLTHERM EPS rigid insulation(Rating A+ BRE Green Guide) insulatedand vapour-checked internally KOOLTHERM insulated plasterboardExterior, ‘Kingspan Nilvent’ non-tentingwind barrier membrane, 50mm externalair layer, vertical battens with plywood, render�nish
To achieve low air in�ltration within original house, all joints, cracks, breaches, skirtings, window opestaped. All services and �xings through air-tight gromits �xed in place
Y factor....
.055W/m2K
U
Original concrete �oorperimeter reduced torear door, house 2. LTBheat loss will spike at thispoint of access
Party wall (Left)
Some ltbs require3D modelling toexamine how theheat travels acrossd�eresnt planes
Challenging conventions:Avoiding over designby engineering orbuilding habits - calculations for actual size required forraft or strip foundations
New Munster Joinery ‘PASSIVALU-clad’ range ).7W/m2K andmoved to new location toat edge of new insulation
House 2 & 5 performedbest at baseline and retro�t DEAPbut performed lesswith abutting partywalls (no insulationadjoining assumed)
*The end of terracecould realistically becomethe best performing housegiven it’s exposure on1 side only
Each element was modelled in BuildDesk and a hygrothermalappraisel carried out. Any building made air-tight is at highrisk of condensation and mould if moisture cannot be released. In the opposite way of stopping air escaping, moisture from the internal environment must also get to evaporate.
Employing air tight elements (Kingspan TEK panels for the structure)have an internal insulation vapour check plasterboard (KOOLTHERM)The Glaser report sample below refers to highest risk of moistureand oscillating damp in a buildiong - winter months.
Plan EIFS boundary and adjoiningproperties givebadly performing junctions
Primary Energy Bills are reduced from 411 kW|hrm2 to 44 kW|hrm2
which is a reduction of almost
savings to each home
LTB
Surface temperaturesare calculated toassess risk mould and surface condensation internallyFor dwellings, the value of fRsi should be no less or equal to 0.75, For three-dimensional corners of ground �oors this value may be reduced to 0.70, for all points within 10 mm of the point of lowest fRsi. Criticalareas are where furniture is pushed up against the wall and there is little movement of air
JENNY POWER D14123981 PROJECT 4 SUBMISSION 24 | 04| 15 DT774
90%
RETR
OFIT
DEVOLUTION
1 ac|hr (Old 4.65)
New extensions byTEK system reduce Psito negligible levelsdue to tight connection
FUTURE HOMES
2d DETAILS
Schuco balconyextension systemwith glass sepatatingwalls per dwelling
The balcony is boltedonto the new extensionat roof level avoidingall bridges and addingto external living space
TEK Panel system toextension walls reducePsi values (heat loss at junctions)to negligible levels withtight connection detailsat heads and sole platesWith each section ofpanelling, air tightness isachieved. The TEK system wall panel provides 0.19 W/m2Kbefore 90mm ’Kooltherm’ insulation was applied internally with 10mm Kooltherm plasterboard
Each dwelling producesminimum 1000 kW/hrs
free solar electrical powerper year
Increased living spacewithin existing footprint
A+ Rated insulationto walls and roofspaces
(Kooltherm) within
Corbel cut back &Aerogel slip
at eaves
New windows re-located to outer skin
Existing sill cutback and externallyinsulated and resin
pressed metal sill �tted over
Kingspan TEK panelsystem to walls
and roofs
New insulated �oorwith perimeter
insulation greatly reducesheat escape from
�oor junctions
Original �oor retainedand insulated withKingspan Optim-RVacuum Insulation
Panels, glued to concretecovered
A VIP is material that is used for heat preservation. It is made of a type of core �lling material and vacuum protection surface layer compound. It can e�ectively avoid air convection caused by heat transfer. Therefore, coe�cient §of thermal conductivity can be greatly reduced. Lack of movement is critical and the VIP is glued to the receiving surface. This glue is applied by Roller Coating Method and is coated on the whole surface of VIP.
NOT FOR DETAIL: REPRESENTATIONAL ONLY
SUSTAINABILITY DECISIONS CAN BE MADE AT DESIGN STAGE
THERM THRESHOLD SHOWING EXISTING FOUNDNEW GROUND FLOOR | SILL NEW GROUND FLOOR | WALL
The original corbel created a large linear heat loss location so it was cut back to allow the EIFS to continue uninterrupt-ed around to the roof to meet the internal insulation bridged by aerogel at the junction. This avoided the roof being raised
Heat loss junctions along linear lengths (Linear Thermal Bridges) take account of vulnerable areas beyond �anking planar heatloss areasThey are calculated using modelling programmesusing heat �ow resistancesof di�erent build ups
If the junctions don’t work-back to board
BREEAM OUTSTANDING
Worst Months
DEAPEnd of Terrace:411 kWhrm2 | F BER - 44 kWhrm2 A2 BERMid Terrace
314 kWhrm2 | E1 BER - 42 kWhrm2 A2 BERMid Terrace Bay
304 kWhrm2 | E1 BER - 44 kWhrm2 A2 BER
FABRIC|STUDY
Design Strategies:
Maintain existing �oor and insulate by installingVacuum Insulation Panels on original slab
Additional protection and living space is providedby new extensions to front and rear
The external facade is insulated to U beyond regulationThe roof space is insulated to U beyond regulation
Additional living space is provided within theexisting building envelope to add to the residents’ spatial enjoyment
SIPS
Air tightness strategy
Wind tightness strategy
VIPS
The gable end of terrace performed best in the calculation given it’s reduced party wall exposure. This could further be improved with greater insulation on the adjoining properties’ attic spaces.
GROUND FLOOR LAYOUTS FIRST FLOOR LAYOUTS
MOORDEBREWOHSMOORDEB
LIVING DINING
HOME OFFICE
YGE
OMET
RY
Best Months
Kitchen
Bedroom
Shower
Bedroom
Hall
Y-FACTOR INPUT
RE-USE OF EXISTING SERVICES
The cottages comprise solid concrete wallswhich provide low air in�ltration rates (4.65ach|r )but high conductivity and so require highlevels heat for spatial comfort. The roof was insulated with 100mm rockwool. The �oor was 75mm solid concrete
Baseline Change:
Walls OldW/m2KSolid concrete 251mm 2.47 Floors .75Roof 3.91
NewW/m2K.103
U-VALUE
.134
.084
Living
New roof|walls to extensions: ‘KingspanTEK Panel System, 15mm OSB sheathing
142mm Kingspan EPS rigid insulation(Rating A+ BRE Green Guide)
ANALYSIS TOOLS & CALCULATIONS
RETROFIT PROCESSES | STAGES
BUILD DESK | THERM | GLASER
BUILD DESK
KINGSPAN TEK Panellingsystem provides Psivalues for all cruticaljunctions: Ground �oor junctions with a U value = 0.15 W/m2K (used in the KINGSPAN calculation)Jamb, head and sillThese values were takenand also modelled hereby us to con�rmAll other junctions modelledas per constructionACD sill could be used forthe existing �rst �oor sill
Kingspan have increased their thermalperformance by internally insulating their SIPS system using insulated plasterboard bonded directly onto the panel. Theis plasterboard has a vapour check so it will not grow mould from internal moisture. Kingspan allow for services (sockets and cables) to be chased into the SIPS side of the plasterboard to mimimise heat loss.In this situation. given the size of the extension, recommendations would be no services to be �tted on any external wall
Bathroom
The existing boiler is not long installedin the house and has a mid range value in the BREEAM assessment. There should be some savings using good services that comply when assessing the amount of work to be carried out on a retro�t
Air-tight Strategies:New insulated plasterboardtaped at junctions with originalplaster on walls
VENTILATION
Ventilation and air-tightness go hand in hand. Without ventingthe interior, the indoor air qualitystagnates and there will be mouldand condensation.The AERECO V4A Premium is a whole house centralised MechanicallyVentilated system, ducted around the house and routed back to a singleunit located usually in loft spaces
Existing wall
Internal party wall
Plan exising head
Plan existing corner
Plan corner bay and existing
Section SIPS �at roof
Plan existing jamb
Section revamped roof
GLASER
Upon completion of Psi calculations across each house, the average heat loss factor over the entire exposed area of the house equals the
Gable: .063 W/mKMid Terrace: .094 W/mKMid Terrace Bay: .067 W/mK
THERM
Renewables:
PV panels �tted to the south facing roof bringgood A3 BERs acrossthe line to A2 with afuture FIT scheme announced, payback onPV is promisingIn this case, over 1000 kWhrs are generated pa, approx-.over 1/3 yearly water heating needs in delivered energy terms (DEAP source)
FRONT
SOUTH | FRONT REAR | NORTH
kW/m2 yr
kW/m2 yr
kW/m2 yr
F E1
E1
411317
kW/m2 yrA2 44
kW/m2 yrA2 42
kW/m2 yrA2 44
304
DEAP AS A DESIGN TOOL - VENTILATION
? WIN
DO
WS ? SPACE AND WATER HEATING SYS
TEMS ?
RE
NEW
ABLE
S? FA
BRIC
DES
ISIO
NS? B
ER ?
CO2?
DEAP
Biggest linear bridge locatedat chimney breast:
descision made to remove chimney breast
to base of found
Old �oor laid with ‘KingspanOptim-r low U Vacuum InsulationPanels, laid tight to �oor, tapedmetal foil layer, wood �bre boardunder Dalsouple �oor (vapour checkunder VIP)
PART MAcccessibility is examinedin each unit and futureliving needs are cateredfor with level access, widercorridors, accessibleshower / bathrooms atground �oor
Increased �oor areaprovides for greater spatialallocation mindful ofPart M