    Materials Requirements

    Planning

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    2/26

    The McGraw -Hill Companies, Inc., 2004

    2

    OBJECTIVES

    Material Requirements Planning (MRP)

    MRP Logic and Product Structure Trees

    Time Fences

    MRP Example

    MRP II and Lot Sizing

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    3/26

    The McGraw -Hill Companies, Inc., 2004

    3

    Material Requirements Planning

    Defined Materials requirements planning (MRP) is a

    means for determining the number of parts,components, and materials needed to producea product

    MRP provides time scheduling informationspecifying when each of the materials, parts,and components should be ordered orproduced

    Dependent demand drives MRP

    MRP is a software system

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    4/26The McGraw -Hill Companies, Inc., 2004

    4

    Example of MRP Logic and Product

    Structure TreeGiven theproduct structure tree for A and the lead time anddemand information below, provide a materials requirements

    plan that defines the number of units of each component andwhen they will be needed

    Given theproduct structure tree for A and the lead time and

    demand information below, provide a materials requirements

    plan that defines the number of units of each component and

    when they will be needed

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    Product Structure Tree for Assembly A Lead Times

    A 1 dayB 2 daysC 1 dayD 3 daysE 4 days

    F 1 day

    Total Unit DemandDay 10 50 A

    Day 8 20 B (Spares)Day 6 15 D (Spares)

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    5/26The McGraw -Hill Companies, Inc., 2004

    5

    First, the number of units of A are scheduled

    backwards to allow for their lead time. So, in the

    materials requirement plan below, we have to place

    an order for 50 units of A on the 9

    th

    day to receivethem on day 10.

    First, the number of units of A are scheduled

    backwards to allow for their lead time. So, in thematerials requirement plan below, we have to place

    an order for 50 units of A on the 9th day to receive

    them on day 10.

    LT = 1 day

    Day: 1 2 3 4 5 6 7 8 9 10

    A Required 50

    Order Placement 50

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    6/26

    7

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    7/26

    Finally, repeating the process for all components, we have the

    final materials requirements plan:

    Finally, repeating the process for all components, we have the

    final materials requirements plan:

    7

    Day: 1 2 3 4 5 6 7 8 9 10A Required 50

    LT=1 Order Placement 50

    B Required 20 200

    LT=2 Order Placement 20 200

    C Required 100

    LT=1 Order Placement 100

    D Required 55 400 300

    LT=3 Order Placement 55 400 300

    E Required 20 200

    LT=4 Order Placement 20 200

    F Required 200LT=1 Order Placement 200

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    40 + 15 spares

    Part D: Day 6

    The McGraw -Hill Companies, Inc., 2001

    8

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    8/26The McGraw -Hill Companies, Inc., 2004

    8

    Master Production Schedule (MPS)

    Time-phased plan specifyinghow many and

    when the firm plans to build each end item

    Aggregate Plan(Product Groups)

    Aggregate Plan(Product Groups)

    MPS(Specific End Items)

    9

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    9/26The McGraw -Hill Companies, Inc., 2004

    9

    Types of Time Fences

    Frozen

    No schedule changes allowed within this window

    Moderately Firm

    Specific changes allowed within product groups as

    long as parts are available

    Flexible

    Significant variation allowed as long as overall

    capacity requirements remain at the same levels

    10

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    10/26The McGraw -Hill Companies, Inc., 2004

    10

    Exhibit 15.5Exhibit 15.5Example of Time Fences

    8 15 26

    Weeks

    Frozen

    Moderately

    Firm Flexible

    Firm Customer Orders

    Forecast and available

    capacity

    Capacity

    11

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    11/26The McGraw -Hill Companies, Inc., 2004

    11

    Material Requirements Planning System

    Based on a master production schedule, amaterial requirements planning system:

    Creates schedules identifying the specific partsand materials required to produce end items

    Determines exact unit numbers needed

    Determines the dates when orders for those

    materials should be released, based on leadtimes

    12

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    12/26

    From Exhibit 15.6From Exhibit 15.6

    Firm ordersfrom known

    customers

    Forecastsof demand

    from randomcustomers

    Aggregateproduct

    plan

    Bill ofmaterial

    file

    Engineeringdesign

    changes

    Inventoryrecord file

    Inventorytransactions

    Master production

    Schedule (MPS)

    Primary reportsSecondary reports

    Planned order schedule for

    inventory and productioncontrol

    Exception reportsPlanning reports

    Reports for performancecontrol

    Material

    planning(MRP

    computerprogram)

    12

    The McGraw -Hil l Companies, Inc., 2004

    13

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    13/26The McGraw -Hill Companies, Inc., 2004

    Bill of Materials (BOM) File

    A Complete Product Description Materials

    Parts Components

    Production sequence Modular BOM

    Subassemblies Super BOM

    Fractional options

    14

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    14/26

    The McGraw -Hill Companies, Inc., 2004

    Inventory Records File

    Each inventory item carried as a separate file

    Status according to time buckets

    Pegging

    Identify each parent item that created demand

    15

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    15/26

    The McGraw -Hill Companies, Inc., 2004

    Primary MRP Reports

    Planned orders to be released at a future time

    Order release notices to execute the planned

    orders Changes in due dates of open orders due to

    rescheduling

    Cancellations or suspensions of open orders due

    to cancellation or suspension of orders on the

    master production schedule Inventory status data

    16

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    16/26

    The McGraw -Hill Companies, Inc., 2004

    Secondary MRP Reports

    Planning reports, for example, forecasting

    inventory requirements over a period of time Performance reports used to determine

    agreement between actual and programmed

    usage and costs

    Exception reports used to point out serious

    discrepancies, such as late or overdue orders

    17

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    17/26

    The McGraw -Hill Companies, Inc., 2004

    Additional MRP Scheduling Terminology

    Gross Requirements

    Scheduled receipts

    Projected available balance

    Net requirements

    Planned order receipt

    Planned order release

    18

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    18/26

    The McGraw -Hill Companies, Inc., 2004

    MRP Example

    A(2) B(1)

    D(5)C(2)

    X

    C(3)

    Item On-Hand Lead Time (Weeks)

    X 50 2

    A 75 3B 25 1

    C 10 2

    D 20 2

    Requirements include 95 units (80 firm orders and 15 forecast) of X

    in week 10

    Requirements include 95 units (80 firm orders and 15 forecast) of X

    in week 10

    19

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    19/26

    The McGraw -Hill Companies, Inc., 2004

    A(2)

    X

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes

    2 As foreach X

    It takes

    2 As foreach X

    20

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    20/26

    The McGraw -Hill Companies, Inc., 2004

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    B(1)A(2)

    X

    It takes

    1 B for

    each X

    It takes

    1 B foreach X

    21

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    21/26

    The McGraw -Hill Companies, Inc., 2004

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    A(2) B(1)

    X

    C(3)

    It takes 3

    Cs foreach A

    It takes 3

    Cs for

    each A

    22

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    22/26

    The McGraw -Hill Companies, Inc., 2004

    A(2) B(1)

    C(2)

    X

    C(3)

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 2

    Cs foreach B

    It takes 2

    Cs for

    each B

    23

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    23/26

    The McGraw -Hill Companies, Inc., 2004

    A(2) B(1)

    D(5)C(2)

    X

    C(3)

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 5

    Ds foreach B

    It takes 5

    Ds for

    each B

    24

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    24/26

    The McGraw -Hill Companies, Inc., 2004

    Closed Loop MRP

    Production PlanningMaster Production SchedulingMaterial Requirements PlanningCapacity Requirements Planning

    Realistic?No

    Feedback

    Execute:Capacity PlansMaterial Plans

    Yes

    Feedback

    25

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    25/26

    The McGraw -Hill Companies, Inc., 2004

    Manufacturing Resource Planning

    (MRP II)

    Goal: Plan and monitor all resources of a

    manufacturing firm (closed loop):

    manufacturing

    marketing

    finance

    engineering Simulate the manufacturing system

    26

  • 7/29/2019 Planeacion de Requerimientos de Los Materiales

    26/26

    The McGraw -Hill Companies, Inc., 2004

    Lot Sizing in MRP Programs

    Lot-for-lot (L4L)

    Economic order quantity (EOQ) Least total cost (LTC)

    Least unit cost (LUC) Which one to use?

    The one that is least costly!