Page 1: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Agile Coach, CST

Planning and Tracking Petri Heiramo

Page 2: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Exercise: Initial Release Plan

•  As a group, create an initial release plan for the MyBooks.com site.

•  The team has estimated that it can complete •  15 story points worth of functionality in the first sprint •  25 story points in the second sprint •  30 story points indefinitely thereafter

•  Business side constraints

•  The beta release of the site should be up after three sprints

•  The official release should be after 5 sprints •  Development beyond 5 sprints is not considered

•  The plan should optimize value and minimize risks

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 3: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Questions Based on the Plan

•  Is the business target of release after three sprints feasible?

•  How good a feature set can the site get by official release?

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 4: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Exercise: Charting Out the Future

•  As a team, based on your initial release plan, draw value/time diagram for your project

•  Draw the diagram by counting the amount of relative value (to be) delivered in each sprint

•  What does the diagram look like?

•  What conclusions can you draw from it?

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 5: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Exercise: ”Surprise, Surprise”

•  In the middle of the first sprint the ScrumMaster of the team delivering the MyBooks.com comes to you with bad news – three of the developers had been car-pooling and got into a serious accident. They will be out of development until sprint four. The velocity of the team will halve until they come back.

•  Use replanning to evaluate the impact of the situation to your project

•  What options do you have and what would actions would think the most reasonable?

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 6: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Balance Sheet vs. Cash-Flow

Balance sheet thinking •  Delay does not matter •  Just in case is wise •  Work in process has

value •  Queues support better

decisions

Cash flow thinking •  Delay creates waste •  Just in time is wiser •  Work in process is waste •  Queues gum up the

work and slow things down

6  

Mar&ne  Devos  

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 7: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Converging vs. Diverging Burndown

Is this bad? Where might this be expected?

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 8: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Burn-Ups

•  Many Agile practitioners prefer burn-ups when tracking project progress

•  Burndowns make more sense within sprints

•  Starts from zero, just like project implementation

•  Always shows velocity correctly

•  Easier (and more logical) exploration and visualization of different possible scopes and levels of completeness

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 9: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Example Burn-Up with MoSCoW

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 10: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Other Burn-Ups

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 11: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Alternative Diagrams

Progress by number of implemented stories

When would this work nicely?

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 12: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Chart Tracking Work-in-Process

Work-in-Process (WIP) is considered waste as there is already expended effort in it, but it has not yet been realized as business value.

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 13: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Burn-Up Chart with WIP

Cumulative Flow

020406080100120140160180200220240

10-Feb

17-Feb

24-Feb

2-Mar

9-Mar

16-Mar

23-Mar

30-Mar

Time

Feat

ures

Backlog Started Designed Tested Complete

Work-in-Progress (WIP) is shown as the difference between the amount of started work and the amount of complete work

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 14: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Tracking Delivered Business Value

0

200

400

600

800

1,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Months

Cum

ulat

ive

Bus

ines

s Val

ue When would you start considering stopping the development?

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 15: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Gantt Chart?

•  Gantt charts are rarely/never used in adaptive iterative planning (i.e., in Agile Methods), because the content of the next iteration is decided at the last possible moment, to be as risk-driven and value-driven as possible (maximum insight / information) and future iterations are not seriously predicted.

•  If you really wanted to draw one, it would look something like this:

Every sprint and every story in one would always take the full duration of the sprint

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 16: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

SM Shouldn’t Feel Constrained to Burndowns...

# of User Stories Status of Estimation

Based on this, it looks like the project should

step up on estimation...

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 17: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

...But this shows that 70% of the unestimated stories are in low priority stories.

Not so bad after all.

Copyright 2011 CollabNet Inc and Petri Heiramo

Page 18: Planning and Tracking - Planning and Tracking C… · Burn-Ups • Many Agile practitioners prefer burn-ups when tracking project progress • Burndowns make more sense within sprints

Parking-Lot Style Report on Progress

Reports like this can give top management a good view of overall progress in a large project.

Copyright 2011 CollabNet Inc and Petri Heiramo