planning best practices - pmi southern maryland chapter

68
Planning Basics + Planning Best Practices PLANNING BEST PRACTICES John H. Cable, R.A., PMP Copyright 2017, All rights reserved

Upload: others

Post on 09-May-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Planning Basics + Planning Best PracticesPLANNING BEST PRACTICES

John H. Cable, R.A., PMPCopyright 2017, All rights reserved

Page 2: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Isn’t this a great day to study Project Management!

Page 4: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Webster• Plan – “A method or scheme for achieving or doing

something.”

• Planning – “To formulate a way to achieve or do.”

“Devising and maintaining a workable scheme to accomplish the business need that the project was undertaken to address.”

Page 5: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Process Groups*

* PMBOK ® Guide, 5th Edition

Page 6: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Planning Attributes

• Occurs throughout – ongoing process• Uses multiple time horizons• Detail varies ~ uncertainty and phase• Provides the foundation:

– Performance measurement– Communication

Page 7: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Good Planning• Establishes direction for team

• Defines:– What must be done– When it must be done– Resources required– Deliverables– Risks

• Coordinates the work of all parties• Provides the central communication system

Page 8: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Without a Plan• Control (steering the course) is impossible!

• You must plan in order to accomplish goals and objectives.

• Planning nurtures the opportunity to ANTICIPATE!

Page 9: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Avoid the Two Extremes

• “Ready, Fire, Aim”

• “Paralysis by analysis”

Page 10: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

What about fire drills?

Page 11: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Isn’t it Obvious!

• Planning• Scheduling• Cost estimating / budgeting• Resource allocation

All integrally intertwined. Not separate / independent functions but are totally interdependent.

Page 12: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Potential Problems i.e. Risk• Long lead delivery items• Technical breakthroughs required• Resource limitations (the market)• Critical task timing /sequences• International support / shipping• Complex coordination requirements• Regulatory approvals

Page 13: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Initial Planning is More Efficient

Delayed or reactive planning will increase the total time, effort and cost of:– Discovery– Planning– Project work

Do it once! Do it right!– Only possible through successive iteration

planning

Poor Planning

Effective Planning

Project WorkProject Work

ReRe -- PlanningPlanning

DiscoveryDiscovery

Project WorkProject Work

Response Response

PlanningPlanning

DiscoveryDiscovery

Project WorkProject Work

Initial Initial

Planning

Planning

Project WorkProject Work

DiscoveryDiscoveryRe

Re-

-Planning

PlanningProject Work

Project Work

Total

Proje

ct Ov

erhea

dTo

tal Pr

oject

Overh

ead

Page 14: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Key Thoughts• Successive elaboration! Multiple time horizons

• Include key team & downfield reps in planning process

• Identify what you do know and what you don’t know and take action to stabilize uncertainty!

• Manage to milestones

Page 15: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Why do Projects Fail?

Page 16: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Project Management Problems

• Insufficient planning • Poor Communication• Inadequate resources• Meeting deadlines• Unclear goals / directions• Changes in goals & resources• Uncommitted team members• Conflicts between departments / functions

Page 17: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Failing to Plan!

Page 18: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Old Perceptions / The New Reality!

Page 19: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Planning Best Practices

1. Systematic and Integrative Planning

2. Timely Decisions Adjusted to Uncertainty

3. Isolation and Absorption

Page 20: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

1. Systematic and Integrative Planning

“Start planning as early as possible. Set project objectives and employ a diverging/converging, multiphase process. At each phase, prepare all

functional plans simultaneously and interdependently.”

Page 21: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

• Advocates a systematic, formal, and disciplined approach to planning

• Not new - is historical approach

• Key to project success –“invest quality time in systematic planning at early

stage”

Systematic and Integrative Planning

Page 22: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Some Key Ideas in S&IP

• Focus on Customer’s needs• Understand business objective• Early interaction / all players• Clearly articulate undefined needs• Review “must-halves” w/ desires• Develop a clear vision• Begin with the end in mind

Page 23: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Five Major Elements

1. Set project objectives

2. Employ a multiphase planning process

3. Start planning as early as possible

4. Adopt a diverging/converging planning process

5. Prepare integrated functional plans

Page 24: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

a. Focus on Customer’s Needs

• Translate undefined needs into clear, precise requirements and objectives.

• In setting objectives, each major activity begins with end in mind.

Page 25: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Key Effect

Early interaction of problem setters & problem solvers:– Project team focuses on customer’s needs– Sets tone for customer team communication throughout

project– Team understands more about context

Page 26: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Definition of Requirements• Primarily customers responsibility

• Does customer have capability to define?

• Designers often involved? Maybe!

• Poor scope definition is source of:– Changes, Rework, & Schedule delays– Cost overruns– Unhappy customers & unhappy service providers– Unprofitable project for everyone

Page 27: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Problems w/ Definitions

• Customer frequently doesn’t have expertise• Prescriptive vs. performance based• Needs vs. desires• Unstated assumptions• Unstated constraints• Dynamic nature of the market

Page 28: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Requirements Walk-Through

• Customer & contractor go through requirements line by line

• Yes, it is onerous!

• MISTAKE – don’t have the right people participate

See Notes!

Page 29: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

The Right Business FocusCleveland Plant Consolidation Project

Page 30: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

2. Timely Decisions Adjusted to Uncertainty

“Adjust the timing of decisions and their degree of detail to the completeness and stability of information. Plan for multiple time horizons and selectively accelerate implementation to obtain fast feedback for further planning.”

Page 31: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

1st PrincipleProblem:

Systematic and Integrative Planning ignores / underestimates project:

1. Uncertainty,2. Speed, and3. Manager’s scarcity of attention.

Page 32: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

2. Timely Decisions Adjusted to Uncertainty

Focus of 2nd principle ~ factors of uncertainty, speed, and scarcity of attention

Page 33: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

1. Uncertainty

Information Required – Information Possessed= Uncertainty

Page 34: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Opportunity to Influence

PMBOK® 5th Edition

Page 35: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

2. Speed

Speed is the single most significant basis for competitive advantage.

Page 36: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Why Speed is Key?

• Dramatic increase in global competition.

• Accelerated pace of technological development

• Market share and profit margins are increased by being first to market

Page 37: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

3. Scarcity of AttentionManager’s activities are typified by:• Brevity,

• Variety, and

• Fragmentation.

Page 38: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Executives

• ½ of their activities last < 9 minutes

• Only 10% > 1 hour

• Leaves little time for analysis and reflection!

Page 39: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

2.1 Postpone Planning Details

By postponing details of uncertain tasks, teams can proceed with only partial information.

Page 40: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

“Defining the Problem by

Exploring the Solutions”

Page 41: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

3. Isolation & Absorption

Isolate tasks plagued by very high uncertainty and loosen connections between uncertain tasks. In both cases you absorb uncertainty by selectively employing redundant resources. Divide large projects into independent subprojects and group tasks within projects according to uncertainty.

Consists of 3 major steps:1. Isolate highly uncertain tasks,2. Loosen connections between uncertain tasks, and3. Divide project according to uncertainty

Page 42: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

3.1 Isolate Highly Uncertain Tasks

• Isolating tasks is NEVER w/o cost

• Redundancy can provide reliability

• Counter to concept of efficiency

• Most effective = most efficient

Page 43: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

“Overhead is Not Evil”

May 26, 2016

Title by Author

Slide 43

Page 44: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Key Principles• Plan before starting work• Use multiple time horizons• Subdivide when appropriate• Involve people/skills who will

actually do the work• Include all aspects of project • Build flexibility into the plan• Manage to milestones• Keep the plan simple• Communicate the plan

Page 45: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter
Page 46: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Discussion?

Page 47: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

“Customers Are Loyal toQuality Performance ... Not the Organization!”

Page 48: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Planning Phase Sequence 1

1. Create scope and scope management plan2. Determine project team3. Create work breakdown structure4. Create resource management plan5. Create WBS dictionaries6. Create network diagram

PMP Exam Prep, by Rita Mulcahy, PMP

Page 49: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Planning Phase Sequence 2

7. Estimate time and cost8. Determine critical path9. Develop schedule and schedule management plan10. Develop budget11. Create communications plan12. Create quality management plan

PMP Exam Prep, by Rita Mulcahy, PMP

Page 50: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Planning Phase Sequence 3

13. Develop risk management plan14. Create procurement management plan15. Create stakeholder management plan16. Create project control plan17. Develop a formal project plan18. Gain formal acceptance and approval19. Hold kickoff meeting

PMP Exam Prep, by Rita Mulcahy, PMP

Page 51: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

1. Project Charter

• Formally authorizes project• Issued by external manager• Authority for resources• Business need project undertaken to address

& product description• Assigns project manager• Identifies constraints + assumptions

Page 52: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

2. General Approach

• Managerial approach– Note deviation from standard– Team structure– In-house vs via contract

• Technical approach– Relationship to available technologies– Critical assumptions

Page 53: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Contractual Aspects• Procurement strategy• Reporting requirements• Customer-supplied resources• Liaison arrangements• Advisory committees• Review & cancellation procedures• Proprietary requirements• Management agreements

Page 54: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

3. Scope Statement

• Documented basis for making future project decisions

• Projects: – Justification– Deliverables– Objectives

• Profit target• Competitive aims (market goals)• Technical goals

Page 55: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter
Page 56: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Project Plan Development

Project Management Plan

Scope

Procure-ment

Time

Cost

Quality

Re-source

Communica

tions

Risk

Page 57: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Project Plan

• Used to coordinate among internal & external participants

• Basis for signoff and approval internally & with client

• Dynamic – should be current, record of key assumptions and decisions

Page 58: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Project Plan Contents 1

1. Project charter2. Approach or strategy3. Scope statement4. Work breakdown structure5. Estimates, schedules, & responsibility6. Measurement baselines

Page 59: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Project Plan Contents 2

7. Milestones / target dates8. Staff required + key9. Key risks, constraints, responses10. Subsidiary management plans11. Open + pending issues12. Supporting details

Page 60: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Work Breakdown Structure

• A deliverable-oriented grouping of project components that organizes and defines total project scope.

• Subdivides project work into smaller, more manageable pieces.

• Work not in the WBS is outside the scope of the project.

See Notes!

Page 61: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

W B S

• Concept: A larger complicated task is subdivided into smaller tasks.

• Hierarchical task and subtask listing organized into work packages.

• Fundamental tool for project planning.

• Foundation of a project management system.

See Notes!

Page 62: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

WBS Sequence

• List tasks and subtasks in sequence.• Continue until all meaningful tasks or work

packages are identified.• Prepare responsibility matrix.• Review with people doing the work.• Refine – even as project is underway.• Move into scheduling / budgeting.

See Notes!

Page 63: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Even Planning Process*

*Figure 3-2, page 86“Project Management in Practice”

Page 64: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Even Planning Process• List activities in general order (2-20)• Break each level 1 into (2-20)• Break each level 2 into (2-20)

• Roughly same level of task generality• Discipline keeps plan focused on deliverables• Maintain uniform level of detail

Page 65: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

Key Question

• When to stop breaking down the work into subunits?

Stop when you can estimate to the desired degree of accuracy.

• WBS does not have to be symmetrical.

See Notes!

Page 66: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter

WBS Concept

Page 67: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter
Page 68: PLANNING BEST PRACTICES - PMI Southern Maryland Chapter