Manhours for CS piping erection including fitup: Take: Size of CS pipe spool: 6", spools: 2 Nos., each of 4 Mtr Qty of erection: 48 IM, at elevation of 10 Mtr Sr. No. Activity Craft Qty Time (Hrs.) MHrs Remarks 1 Scaffolding Scaffolders 6 8 48 2 Rigging of spool and placement in place Foreman: 0.5 Rigger: 4 4 3 12 3 Bevelling of pipe Gascutter: 0.5 Grinder: 0.5 1 1 1 4 Alignment & Tack welding Fitter : 1 Helper: 1 Tack welder: 1 3 2 6 5 Contingency @ 20%* 13.4 Total 80.4For 48 IM A MHrs. Per IM: 1.7

Upload: safarudin-ramli

Post on 13-Dec-2015

5 views

Category:

Documents


0 download

DESCRIPTION

norms

TRANSCRIPT

Page 1: Planning Norm

Manhours for CS piping erection including fitup:

Take: Size of CS pipe spool: 6", spools: 2 Nos., each of 4 Mtr

Qty of erection: 48 IM, at elevation of 10 Mtr

Sr. No. Activity Craft Qty Time

(Hrs.) MHrs Remarks

1 Scaffolding Scaffolders 6 8 48

2 Rigging of spool and

placement in place

Foreman: 0.5

Rigger: 4 4 3 12

3 Bevelling of pipe Gascutter: 0.5

Grinder: 0.5 1 1 1

4 Alignment & Tack welding

Fitter : 1

Helper: 1

Tack welder: 1

3 2 6

5 Contingency @ 20%* 13.4

Total 80.4For 48 IM

A MHrs. Per IM: 1.7