Version 3/ August 2018 Installing instructions DW-MAMMUT 1 INSTALLING INSTRUCTIONS Double wall flue system with ceramic inner tube type DW-MAMMUT

Upload: others

Post on 14-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

1

INSTALLING INSTRUCTIONS

Double wall flue system with ceramic inner tube type DW-MAMMUT

Page 2: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

2

Double wall flue system with ceramic inner tube type DW-MAMMUT

Certification 0036 CPD 9174 039 nach EN 13063-1 (dry operation mode) Certification 0036 CPD 9174 040 nach EN 13063-2 (wet operation mode)

Building authority approval Z-7.1-3351 (W3G)

(For further information see Declaration of Performance or Building authority approval of system DW-MAMMUT)

Page 3: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

3

Double wall flue system with ceramic inner tube type DW-MAMMUT

Page 4: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

4

Double wall flue system with ceramic inner tube type DW-MAMMUT

Contents: 1. System overview .............................................................. Page 5

2. Mounting and regulations .............................................. Page 6

3. Mounting heights ……………………………………………..…….... Page 6

4. Minimum distance to combustible materials .………... Page 8

5. Installation of the vertical part of flue system

5.1 Construction of pipes ……………………..………………. Page 9

5.2 Application of the acid-resistant paste ………….. Page 9

5.3 Wall brackets made of stainless steel ……………. Page 12

5.4 Telescopic support …………………………………….……. Page 12

5.5 Concrete socket ………………………………………….…… Page 12

5.6 Base plate …………………………………………………………. Page 13

5.7 Clean-out element .………………………..……………….... Page 13

5.8 Connection element to the upright part ………... Page 13

5.9 Supports …………………………………………………..…….. Page 13

5.10 Intermediate support ………………………………………. Page 14

5.11 Flashing kit ………….…………………………………………... Page 15

5.12 Mounting above the roof ………………………………… Page 15

5.13 Protection against accidental contact …………... Page 16

5.14 Lightning protection …………………………………..…... Page 16

5.15 Inside applications ……….………………………………..... Page 16

5.16 Inclined run …..………………………………………………….. Page 17

6. Condensate drain

6.1 General notes ………………………………………….……..… Page 18

6.2 Neutralization of condensate ..……………………….. Page 18

6.3 Condensate return to the heat generator ……... Page 18

6.4 Condensation guide at the bottom …………….….. Page 18

7. Example ………………….…………………………………………………. Page 19

8. Final notes …………………….……………………………………..…... Page 20

9. Labeling after installation …………….…………………..…...... Page 20

Page 5: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

5

SYSTEM OVERVIEW

CE-Certification 0036 CPD 9174 039

Multi wall exhaust system with ceramic inner tube for all standard fireplaces (oil-, gas- and solid fuel1) in negative pressure for dry operation mode. Possible fields of application: open fireplaces, ovens, oil- and gas boilers, pellet boilers etc. The diameter calculation according to EN 13384 must ensure, that the temperature of the interior wall at the chimney top in steady-state conditions remains above the water vapor dew point temperature of the exhaust gas. Classification acc. to EN 13063-1: Exhaust gas system EN 13063-1 T400 - N1 - D - 3 - G50

CE-Certification 0036 CPD 9174 040

Multi wall exhaust system with ceramic inner tube for all fireplaces (oil- and gas) in negative pressure for wet operation mode. Possible fields of application: oil- and gas boilers, ventilating systems, ovens, air heaters, industrial facilities etc. The proof that the temperature of the interior wall of the system’s upper end is above the water vapor dew point temperature of the exhaust gas at a constant temperature can be abandoned. Classification acc. to EN 13063-2: Exhaust gas system EN 13063-2 T400 - N1 - W - 2 - O20

Building authority approval Z-7.1-3351 (only in Germany)

Multi wall exhaust system with ceramic inner tube for all standard fireplaces (oil-, gas- and solid

fuel1) in negative pressure for wet operation mode, also after soot fire. Possible fields of application: open fireplaces, ovens, oil- and gas boilers, Pellet boilers etc. The proof that the temperature of the interior wall of the system’s upper end is above the water vapor dew point temperature of the exhaust gas at a constant temperature can be abandoned. Classification acc. to DIN V 18160-1: Exhaust gas system DIN V 18160-1 T400 - N1 - W - 3- G50 - L00 1 excluding anthracite coal from Ibbenbüren, Germany

1

Page 6: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

6

MOUNTING AND REGULATIONS

The installing has to be performed professionally according to the installing instructions

respectively according to the valid national regulations.

In Germany in particular DIN V 18160-1, as well as the applicable rules of regional building

(LBauO), firing regulations (FeuVO), relevant DIN standards and all other building- and safety

regulations.

The required cross section has to be determined according to DIN EN 13384 and has to be

rechecked by the executing specialist firm.

Before the installation the design of the system has to be clarified with the concerned

district chimney sweeper. The suitability and safe usability of the exhaust system is to

be certified by a competent district chimney sweeper before commissioning.

MOUNTING HEIGHTS

Measure a max.

distance between

wall supports

Measure b free

standing height

above last support

Measure c height above

support

Measure d height above

pipe tee connection /

clean-out element

Clamp Inside – Ø in mm

dw 21 dw21

120 4 3 37 30

140 4 3 35 30

160 4 3 32 30

180 4 3 27 30

200 4 3 24 30

Figure 1: Mounting heights

c

Table 1: Mounting heights (in mm)

2

3

2

Page 7: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

7

STRENGTH OF THE DOWEL CONNECTION in kN

Important advice to the Table of dowel-connection strength:

The dowel-connection strength in the Table is the angular tensile force per dowel.

The wall space of the chimney system is allowed to be up to 40 cm.

The dowel strengths for the wall spacers are valid at heights above territory up to 20 m.

For heights above territory up to 8 m a reduction factor of 0.63 is valid.

For heights above territory between 20 m and 100 m an extension factor of 1.38 has to be

observed.

At wall spaces >40 cm special attachments / wall brackets are to be used according to the static

confirmatory test.

Wall brackets dwm 01 Wall spacer dwm 21

Inner pipe Ø in mm

Wall space Wall space Length of cantilever

50 – 120 mm

250 mm

400 mm

50 – 120 mm

250 mm

400 mm

m

120 0,93 1,34 1,84 1,27 1,99 2,82 3,00

140 1,03 1,446 1,97 1,48 2,22 3,09 3,00

160 1,03 1,446 1,97 1,48 2,22 3,09 3,00

180 0,88 1,18 1,56 1,37 2,00 2,75 3,00

200 0,96 1,27 1,66 0,88 1,27 1,71 3,00

Number of dowel per support

6 6 6 2 2 2

Table 2: Strength of the dowel connection

Page 8: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

8

MINIMUM DISTANCE TO COMBUSTIBLE MATERIALS in the vertical

part

When used as exhaust gas line (oil, gas) a minimum distance to combustible materials of 20 mm

(T400) to a max. nominal diameter of inner tube up to 200 mm, is valid. Bei Anschluss von For

solid fuel fireplaces T400 a minimum distance to combustible materials of 50 mm to a max.

nominal diameter of inner tube up to 200 mm applies (see Table 3)!

The distance to combustible materials refers to a ventilated installation throughout the

whole length (see Figure 2)!

Note:

For wall ducts the local resp. national regulations apply, you can also use the Jeremias certificated

wall-, ceiling-, roof penetration LUX-ECO and LUX-NOVA. These wall ducts are only approved in

Germany, Austria and Switzerland.

Please also note the installing instructions of the above mentioned penetrations!

Mo

de

l

Te

mp

era

ture

le

ve

l

Pre

ssu

re l

ev

el

Co

nd

en

sa

te r

esis

tan

ce

Co

rro

sio

n r

esis

tan

ce

an

d

Flu

e l

ine

r m

ate

ria

l

sp

ecif

ica

tio

n

So

otf

ire

re

sis

tan

ce

an

d

dis

tan

ce

to

co

mb

usti

ble

ma

teri

als

No

min

al

dia

me

ter

(Ø-i

nn

er

tub

e)

Ap

pli

cati

on

0036 CPD 9174 039 T400 N1 D 3 G50 (= 50 mm) Ø120- 200 Oil, gas and solid fuel firing installations for

dry operation mode

0036 CPD 9174 040 T400 N1 W 2 O20 (= 20 mm) Ø120- 200 Oil & gas firing installations for wet and dry

operation mode

Z-7.1-3351 T400 N1 W 3 G50 (= 50 mm) Ø120- 200 Oil, gas and solid fuel firing installations for

wet and dry operation mode

Figure 2

XX

XX

Distance ventilated along the whole length incl. roof penetration

Distance dimension xx see Table 3

Combustible material e.g. wood wall

Exhaust gas system DW-MAMMUT

Table 3: Distances to combustible materials

4

Page 9: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

9

INSTALLATION OF THE VERTICAL PART OF FLUE SYSTEM 5.1 CONSTRUCTION OF PIPES

All components have to be mounted in a way, that the nozzle of the inner pipe is above or rather

in flow direction of the exhaust gas, while the nozzle of the outer pipe has to show converse to

the flow direction of the exhaust gas.

Every surge is protected by a locking band (see Figure 5, 6, 7, 8, 11 and 12).

You can choose between elements with a length of 1000 mm (usable length 940 mm)

720 mm (usable length 660 mm) and 390 mm (usable length 330 mm).

5.2 APPLYING THE ACID RESISTANT PASTE 2010 AND CONNECTING THE ELEMENTS

The under sides of the ceramic elements (insertion ends see Figure 4) are to be moistened. The

acid-resistant cement is properly mixed and then applied wedge-shaped on the under sides of the

elements. Then, the elements must be joined together, the excess acid-resistant paste, on the

inside of connection is smoothened with a sponge. This operation must be repeated for each

element.

Also note the product data sheet of the acid resistant paste!

Figure 3: Detail Straight pipe element

overa

ll len

gth

usa

ble

len

gth

5

Page 10: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

10

Notes for mixing the acid resistant paste:

Please note the hazard warnings and the product data of the acid resistant paste!

Mix:

Put 7 cups of putty powder and a cup of water in a clean container and mix to a homogeneous

mass (prescribed mixing ratio = 100g putty powder: 12g water)

Attention note waiting time:

After proper mixing, a soil-moist, crumbly mass is produced, which, after a maturing time (waiting

period) of 5 minutes and by mixing again becomes a supple homogeneous putty and only then is

it ready for usage.

Never re-use a hardened acid-resistant paste by adding water!

Processing time (open time):

Blended Nisott-acid putty 2010 is usable for approx. 1 hour.

Processing:

Do not prepare Nisott acid putty 2010 at temperatures below 5°C.

Moisten the fireclay pipes under side surface, apply Nisott acid cement 2010 with a suitable

spatula or trowel.

After fitting the fireclay pipe, smooth it out at the butt joint of the pipes with a suitable sponge.

Freshly fitted pipes should be protected from rain and frost until the Nisott acid cement 2010

hardens.

Curing time:

The acid resistant paste has a hardening time of 24 hours at 20°C. The complete hardening is

achieved after approx. 10 days. To shorten the hardening time, heated water can be used approx..

40 – 50°C.

Storage:

Nisott acid resistant paste 2010 should be stored away from moisture. In cool seasons, it is

necessary to store the acid resistant paste in warm place.

Note:

Element joints must be processed very carefully to avoid possible complaints!

Page 11: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

11

Acid resistant paste 2010 – approval number - Z-7.4-1587

Important information for the operator of the exhaust system:

Commissioning of the exhaust system DW-MAMMUT:

• The used acid resistant paste requires at least 10 days to bind the ceramic inner tubes.

Only after this time the exhaust system may put into operation.

Only fireplaces with a maximum exhaust temperature of 400°C may be connected. Please

check the details of the stove manufacturer.

• First commissioning:

So as to expel the building moisture, please heat slowly, an increase of 50°C / minute must not

be exceeded. This is especially true in temporary fireplaces with poor efficiency and

correspondingly high exhaust gas temperatures. Quick heating up can lead to cracking and/or

flaking of the inner tubes, which could jeopardize the operational safety of the system.

• In the ceramic connecting piece, the flue pipe (connecting piece) must never be plugged in

force-fitting manner. The existing annular gap must be filled with a ceramic fibre cord or

mineral fibre so that there is no pressure or drag on the ceramic smoke pipe socket, otherwise

there is a risk that the smoke pipe socket will be blown up.

Please note in your own interest the above points,

so as not to endanger the operational and fire safety of your exhaust system!

After moistening the bead surfaces of the elements, the acid cement is applied in a wedge shape to the mating ends of the element

Figure 4: Applying the acid-resistant paste

Page 12: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

12

Figure 7: Mounting with telescopic support

5.3 WALL BRACKETS MADE OF STAINLESS STEEL

When chimney is supported at a load-bearing wall,

mounting is possible blade upwards (Figure 5) and

blade downwards (Figure 6).

Please note the strength of the dowel connection.

For the installation wall brackets have to be used which

stable enough for the mentioned mounting heights in Table 1!

5.4 TELESCOPIC SUPPORT

If chimney is supported at bottom –

the height of the support is adjustable (see Figure 7).

5.5 CONCRETE SOCKET

If mounted on a concrete socket a

base plate for socket mounting has to be used (see Figure 8).

Figure 5: mounting base plate with lateral condensate drain and “upward wall bracket”

Figure 6: mounting base plate with condensate drain at bottom and “downward wall bracket”

Figure 8: Setup with base plate for socket mounting

Page 13: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

13

5.6 BASE PLATE

The insulated base plate with condensate drain below or laterally for connection to the drainage

pipe has to be armed on the support. The open base plate is used as base plate for intermediate

support or as direct bonnet of the chimney system on a support (e.g. open fireplace, industrial

plant).

5.7 CLEAN-OUT ELEMENT

The element with clean-out opening is set on the base plate.

The position of the clean-out and inspection opening has to be planned

according to the valid standards or rather the local regulations.

Note:

In order to be able to carry out cleaning and inspection work from the bottom of

the exhaust system more easily, it is recommended to install the cleaning

element offset by approx. 90° to the T connection (see Figure 9).

5.8 CONNECTION ELEMENT TO THE UPRIGHT PART

The connection of the connection line to the exhaust gas system

can be realised with the pipe tee connection 87° (see Figure 10).

If the storm collar has to be placed on a locking band, then the assembly is only possible with a specially produced storm collar made according to customer specifications!

Figure 10: Connecting to a vertical exhaust gas system

Pipe tee 87°

Figure 9: Cleaning element offset to the T-connection

Page 14: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

14

5.9 SUPPORTS

The wall spacers act as fixation of the exhaust gas system at the wall or at steel-support

constructions. Die einzuleitenden Kräfte in das Gebäude, sind bauseits zu prüfen.

The rigid wall spacer has a wall space of 50 mm (DWM21). Bei größeren Wandabständen werden

verstellbare Wandabstandshalter verwendet.

Grundsätzlich ist über jedem T-Anschluss direkt ein Wandabstandshalter anzubringen.

The maximum distances between the single attachments and the dowel-connection strengths

have to be observed at all wall attaching bands (see Table 1).

The supports should always be mounted near to an element surge.

5.10 INTERMEDIATE SUPPORT

If the maximum mounting heights are

exceeded (see Figure 1 and Table 1),

intermediate supports should be considered,

which are stable enough to absorb the static

load. This is ensured through the stainless steel

wall brackets and the base plate for

intermediate support (see Figure 11).

It’s advisable to put a wall spacer after the

last intermediate support to dervive the

expected wind loads before.

Figure 11: mounting with intermediate support

wall spacer

end cap

base plate for intermediate support

wall brackets

straight pipe element 1000/ 720 / 480 / 390 mm wall spacer

pipe tee 87°

inspection element

base plate

wall brackets

Page 15: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

15

cantilever

5.11 FLASHING KIT

Flashing kits are available for all slopes (with grading of

10°, with sealing zones made of stainless steel or lead). These

guarantee the temperature-independent linear expansion

of the chimney.

The storm collar (included in scope of delivery) has to be

screwed to the chimney element and to be sealed

(see Figure 12). To achieve a suffice ventilation in the roof

area the storm collar has to be fixed about 3 cm above

of the stainless steel flashing kit.

The storm collar must be sealed accordingly.

Note:

Please also note the installing instructions of the flashing kit

for DW-systems.

However the storm collar must not be mounted

on the locking band above the roof flashing!

5.12 MOUNTING ABOVE THE ROOF

During planning of the exhaust gas system the minimum height above

the roof has to be considered. The double wall systems of Jeremias can

be executed freestanding up to 3.0 m (see Table 1) from the last attachment.

Due to the bonded ceramic inner tubes, a greater height above the last

Clamped connection can be only realized with a cantilever arm (see Figure 13).

Figure 13: Mounting with cantilever

Figure 12: Flashing kit

end cap

storm collar

flashing kit

Page 16: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

16

5.13 PROTECTION AGAINST ACCIDENTAL CONTACT

At an exhaust gas temperature above 200°C, a surface temperature of more than 70°C can be

expected and therefore a contact protection in the accessible area (except the installation area) is

required up to a height of 2 m above the floor e.g. one also needs to have contact protection in

public places.

The contact protection must not obstruct the rear ventilation.

5.14 LIGHTNING PROTECTION

Lightning protection has to be performed according to the relevant technical regulations.

Requirements result in Germany from DIN EN 62205-3 (VDE 0185-305-3) (Protection of structural

works with persons), DIN VDE 0100-410 (Construction of low-voltage systems: protective

measures; Protection against electric shock) and DIN VDE 0100-540 (Construction of low-voltage

systems part 5 to 54: Selection and erection of electrical equipment – earth termination service

and protective conductors)

Execution has to be done by a specialised firm!

5.15 INSIDE APPLICATIONS

For applications installed inside ventilated elements

with integrated exhaust air leading can be mounted

as penetration (see Figure 14). If the height above

the last support exceeds 3m,

the 3-point-guy wire bracket can achieve a higher mounting.

Figure 14: Setup ventilated element with Integrated exhaust air leading

Page 17: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

17

max.

3000m

m

max. 3000

mm

max. 3000

mm

max. 3000 mm

2

2

1

1

11

11

1

2

2

2

1

1

5.16 INCLINED RUN

If the exhaust gas system is to be moved, the maximum dimensions of the following drawing (see

Figure 15) should be observed. Please also note that after an offset intermediate supports with

wall brackets have to be used (see Figure 15).

After an inclined run the weight of the elements must be intercept with a base plate for

intermediate support and cantilevers & cross rail or wall brackets.

Please note that during high exhaust gas temperatures and/ or great lengths, ahead of

an inclined run appropriate actions have to be taken to compensate the thermal

elongation e. g. with a compensator

Please consider that the clean-out openings have to be according to the national regulations

(in Germany according to DIN V 18160-1).

Figure 15: Structure inclined run

Attachment with wall spacer dw 20-24

Intermediate support and wall bracket

Inclined run 87°

Inclined run 15° / 30° / 45°

Page 18: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

18

CONDENSATE DRAIN 6.1 GENERAL NOTES

The discharge of condensation and rainwater to the sewage is to be provided by the customer

(connect sewage connection point to the exhaust system)!

Especially when solid fuel burners are connected, the condensate drain should be cleaned

regularly and the deposits must be cleared in order to ensure the discharge of rainwater and

condensate.

Note:

If there is no or slight accumulation of condensate and rainwater then dust can be removed from

the condensate drain during cleaning work on the exhaust system.

It is advisable to take measures which prevent the freezing of outdoor condensate drain or

siphon, in particular if regular condensation is expected.

6.2 CONDENSATE NEUTRALISATION

Please observe the national as well as the local regulations.

If condensation neutralization is necessary then our neutralization units are available.

6.3 CONDENSATE RETURN TO THE HEAT GENERATOR

In case of a humid operation in the connection line, at least 3° slope to the heat generator is to be

laid. The resulting condensate can be dissipated via this, if this is suitable, otherwise measures

must be taken to ensure to complete drainage of the condensate, e. g. by a condensation trap

with siphon.

6.4 CONDENSATION GUIDE AT THE BOTTOM

Condensate and rainwater from the vertical part of the exhaust system flows into the base plate

with condensate drain via the inner wall and from there into the condensate discharge or in the

neutralization unit, which can be drained via the house drain.

Note:

If the exhaust system is intended for wet operation then the closing cap must be removed from

the condensate drain in order to ensure complete drainage of accumulated condensate and

rainwater. In this way a possible moisture penetration of the insulation as well as the freezing of

bottom in the winter can be avoided.

6

Page 19: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

19

EXAMPLE

End cap DWM32

Straight pipe element e.g. 1000mm DWM1246

Flashing kit with storm collar e. g. with stainless steel cover frame for roof pitch 36°-45° DW83

Adjustable wall spacer e.g. 50-150mm DWM22

Base plate for intermediate support DWM07 and wall brackets adjustable e.g. 50-150mm DWM01

Pipe tee 87° DWM11

Inspection length with expansion compensation DWM10

Base plate with ½“ nozzle, cover cap and condensate drain below DWM05

Adjustable wall brackets e.g. 50-150mm DWM01

7

Figure 16: Example

Page 20: PLANUNGS- UND MONTAGEANLEITUNG SYSTEM FU · Version 3/ August 2018 Installing instructions DW-MAMMUT 2 Double wall flue system with ceramic inner tube type DW-MAMMUT Certification

Version 3/ August 2018 Installing instructions DW-MAMMUT

20

GENERAL NOTES

The exhaust gas system DW-MAMMUT was developed and tested for gas leaks, corrosion

resistance and secure installation. Therefore, only original parts of the system Jeremias DW-

MAMMUT must be used. In addition the manufacturer’s specifications and installation instructions

have to be met.

Technical changes are reserved!

LABELING AFTER INSTALLATION

The installed exhaust gas system has to be fitted depending on the application with the following

nameplate: Figure 17: System label DW-MAMMUT

Opfenrieder Str. 11-14 · 91717 Wassertrüdingen Tel.: 09832 68 68 50 · Fax: 09832 68 68 68 [email protected] · www.jeremias.de

8

9