pom assignment 1
TRANSCRIPT
-
8/12/2019 POM Assignment 1
1/7
1
Production and Operations Management
Assignment No.1
Submitted to: Dr. Irshad Khan
Submitted by: Oozema Zafar
ID: 9883
Dated: 20thmarch 2014
-
8/12/2019 POM Assignment 1
2/7
2
Question 01:
Estimate Project Cost and outline a plan for financing of the project?
Answer:
Project Cost = Capital Cost + Working Capital Cost
Capital Cost:
Cost of Plant Rs. 30,000,000
Land, Building & other facilities Rs. 10,000,000
Pre-Operational Expenses Rs. 5,000,000
Total Capital Cost Rs. 45,000,000
Working Capital:
Assumption: 15 days of FG and 30 days Raw Materials are kept in stock and Production is
assumed as 100 tons per month.
- You will further see the elaboration of Working Capital in Part06.
FG (15 days) Selling Price x no. of units
needed to produce for the
next 15 days = (85.1x50,000)
Rs. 4,255,000
RM (30 days) Price of RM x RM Required
to yield 1 Kg of FG x
assumed production = (10 x6.66 x 100,000)
Rs. 6,660,000
Total Working Capital Cost
(01 Month)
Rs. 10,915,000
Total Annual Working Capital Cost = 10,915,000 x 12 = Rs. 130,980,000
Hence, Project Cost would be: Rs. 45,000,000 + 130,980,000 = Rs. 175,980,000
Finances of Project:
The partners will be investing Rs. 5 Million each, which makes it Rs 15 Million. The rest of the
amount i.e. Rs. 160,980,000 would be taken as a loan from bank at an interest of 10% per year.
-
8/12/2019 POM Assignment 1
3/7
3
Question 02:What should be the installed capacity of the plant?
Answer: 1500 tons should be the installed capacity.
Question 03:Prepare a monthly sale and production plan for first year of project.
Answer:
Assumptions: Closing stock is 10% of every months sale. The sales of the product would be
fluctuating between 90 to 110 tons.
Month Opening
Inventory
Production Sales Closing
Inventory
1 0 99 90 9
2 9 101 100 10
3 10 100 100 10
4 10 89 90 95 9 101 100 10
6 10 111 110 11
7 11 99 100 10
8 10 111 110 11
9 11 110 110 11
10 11 99 100 10
11 10 89 90 9
12 9 101 100 10
Yearly Sales = 1200 tons
Question 04:Determine Manpower Cost, Unit Variable Cost of product and fixed Cost.
Answer:
a) Manpower Cost:Categories Monthly Salary Requirement Salary of Required
Personnel
Managers Rs. 30,000 04 Rs. 120,000
Supervisors Rs. 12,000 06 Rs. 72,000
Skilled Workers Rs. 8,000 10 Rs. 80,000
SemiSkilledWorkers
Rs. 5,000 30 Rs. 150,000
Unskilled Workers Rs. 3,000 40 Rs. 120,000
Grand Total Salary Rs. 542,000
-
8/12/2019 POM Assignment 1
4/7
4
b) Unit Variable Cost: Manufacturing Cost + Cost of RM to Produce 1 Kg of FG + Direct
Labour Cost
i) Manufacturing Cost = Given Manufacturing Cost is Rs. 15 per Kg.
ii) Cost of RM to Produce 1 Kg of FG:
1 Kg of RM = 0.15 Kg of FG
1 Kg of FG = (1/0.15) Kg of RM
1 Kg of FG = 6.66 Kg of RM
Cost of 1 KG of RM = Rs. 10 per Kg
Therefore, Cost of 6.66 Kg of RM which will produce 01 Kg of FG will be: 6.66 x 10 = Rs.66.66
iii) Direct Labour Cost:
Categories Monthly Salary Requirement Salary of Required
Personnel
Skilled Workers Rs. 8,000 10 Rs. 80,000
SemiSkilledWorkers
Rs. 5,000 30 Rs. 150,000
Unskilled Workers Rs. 3,000 40 Rs. 120,000
Total Direct Labour
Cost
Rs. 350,000
As already stated, assumed production is 100 tons.
Therefore, Direct Labour per Unit Cost will be: (350,000/100,000) = Rs. 3.5 per unit.
Now, Unit Variable Cost = 15 + 66.66 + 3.5 = Rs. 85.16
c) Fixed Cost:
Interest Rs. 16,098,000
Depreciation of Plant Rs. 3,000,000
Depreciation of Building Rs. 500,000
Depreciation of Fixtures & Fittings Rs. 1,000,000
Salaries Rs. 2,304,000
-
8/12/2019 POM Assignment 1
5/7
5
(30000x04+12000x06)x12
Total Fixed Cost (Annual) Rs. 22,902,000
Assumptions: Pre-Operational expenses are considered as the cost of fixtures and fittings.
Question 05:For 10 million profits per year what should be the sale price of product.
Answer:
Sales[Variable Cost + Fixed Cost] = Profit
[(1,200,000S){(1,200,000 x 85.16) + 22,902,000} = 10,000,000
[1,200,000S(102,192,000+22,902,000)] = 10,000,000
1,200,000S125,094,000 = 10,000,000
1,200,000S = 10,000,000 + 125,094,000
1,200,000S = 135,094,000
S = (135,094,000/1,200,000)
Selling Price = Rs. 112.57 = Rs. 113 per Kg.
Question 06:How much working capital will be required? Assume that 15 days of finished product and 30
days requirement of raw material are kept in stock.
Answer:
Total Working Capital = 15 days of FG + 30 days requirement of Raw Material.
i) 15 days of FG: Selling Price x 15 days FG in Units
15 days FG = 85.16 x 50,000 units (assuming 100 tons production in a month)
15 days FG = Rs. 4,258,000
ii) 30 days requirement of Raw Materials: Price of RM x 100 tons x RM required to produce 1
kg of FG
30 days requirement of RM = 10 x 100,000 x 6.66 = Rs. 6,660,000
-
8/12/2019 POM Assignment 1
6/7
6
Total Working Capital = 4,258,000 + 6,660,000 = Rs. 10,918,000
Question 07:What will be the yearly profit in next three years? What will be the breakeven
sale volume?
Year 1:
Assumption: 1200,000 units are sold in the year.
Profit = IncomeExpenses
Profit = (1,200,000 x 113)[(1,200,000 x 85.16) + 22,902,000]
Profit = 135,600,000[102,192,000 + 22,902,000]
Profit = 135,600,000125,094,000
Profit = Rs. 10,506,000
Year 2:
Assumption 1250,000 units are sold in the year.
Profit = IncomeExpenses
Profit = (1,250,000 x 113)[(1,250,000 x 85.16) + 22,902,000]
Profit = 141,250,000[106,450,000 + 22,902,000]
Profit = 141,250,000129,352,000
Profit = Rs. 11,898,000
Year 3:
Assumption 1150,000 units are sold in the year.
Profit = IncomeExpenses
Profit = (1,150,000 x 113)[(1,150,000 x 85.16) + 22,902,000]
Profit = 129,950,000[97,934,000 + 22,902,000]
Profit = 129,950,000120,836,000
-
8/12/2019 POM Assignment 1
7/7
7
Profit = Rs. 9,114,000
Breakeven Volume: (Fixed Cost/ Contribution Margin)
& Contribution Margin = Unit Selling PriceUnit Variable Cost
Therefore,
Breakeven Volume = [22,902,000/(113-85.16)]
Breakeven Volume = (22,902,000/27.84)
Breakeven Volume = 822,629.31 units = 822,630 units approx.
Breakeven in Rs. = Breakeven Volume x Unit Selling Price
Breakeven in Rs. = 822,630 x 113 = Rs. 92,957,190