pom assignment 1

Upload: almira-naz-butt

Post on 03-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 POM Assignment 1

    1/7

    1

    Production and Operations Management

    Assignment No.1

    Submitted to: Dr. Irshad Khan

    Submitted by: Oozema Zafar

    ID: 9883

    Dated: 20thmarch 2014

  • 8/12/2019 POM Assignment 1

    2/7

    2

    Question 01:

    Estimate Project Cost and outline a plan for financing of the project?

    Answer:

    Project Cost = Capital Cost + Working Capital Cost

    Capital Cost:

    Cost of Plant Rs. 30,000,000

    Land, Building & other facilities Rs. 10,000,000

    Pre-Operational Expenses Rs. 5,000,000

    Total Capital Cost Rs. 45,000,000

    Working Capital:

    Assumption: 15 days of FG and 30 days Raw Materials are kept in stock and Production is

    assumed as 100 tons per month.

    - You will further see the elaboration of Working Capital in Part06.

    FG (15 days) Selling Price x no. of units

    needed to produce for the

    next 15 days = (85.1x50,000)

    Rs. 4,255,000

    RM (30 days) Price of RM x RM Required

    to yield 1 Kg of FG x

    assumed production = (10 x6.66 x 100,000)

    Rs. 6,660,000

    Total Working Capital Cost

    (01 Month)

    Rs. 10,915,000

    Total Annual Working Capital Cost = 10,915,000 x 12 = Rs. 130,980,000

    Hence, Project Cost would be: Rs. 45,000,000 + 130,980,000 = Rs. 175,980,000

    Finances of Project:

    The partners will be investing Rs. 5 Million each, which makes it Rs 15 Million. The rest of the

    amount i.e. Rs. 160,980,000 would be taken as a loan from bank at an interest of 10% per year.

  • 8/12/2019 POM Assignment 1

    3/7

    3

    Question 02:What should be the installed capacity of the plant?

    Answer: 1500 tons should be the installed capacity.

    Question 03:Prepare a monthly sale and production plan for first year of project.

    Answer:

    Assumptions: Closing stock is 10% of every months sale. The sales of the product would be

    fluctuating between 90 to 110 tons.

    Month Opening

    Inventory

    Production Sales Closing

    Inventory

    1 0 99 90 9

    2 9 101 100 10

    3 10 100 100 10

    4 10 89 90 95 9 101 100 10

    6 10 111 110 11

    7 11 99 100 10

    8 10 111 110 11

    9 11 110 110 11

    10 11 99 100 10

    11 10 89 90 9

    12 9 101 100 10

    Yearly Sales = 1200 tons

    Question 04:Determine Manpower Cost, Unit Variable Cost of product and fixed Cost.

    Answer:

    a) Manpower Cost:Categories Monthly Salary Requirement Salary of Required

    Personnel

    Managers Rs. 30,000 04 Rs. 120,000

    Supervisors Rs. 12,000 06 Rs. 72,000

    Skilled Workers Rs. 8,000 10 Rs. 80,000

    SemiSkilledWorkers

    Rs. 5,000 30 Rs. 150,000

    Unskilled Workers Rs. 3,000 40 Rs. 120,000

    Grand Total Salary Rs. 542,000

  • 8/12/2019 POM Assignment 1

    4/7

    4

    b) Unit Variable Cost: Manufacturing Cost + Cost of RM to Produce 1 Kg of FG + Direct

    Labour Cost

    i) Manufacturing Cost = Given Manufacturing Cost is Rs. 15 per Kg.

    ii) Cost of RM to Produce 1 Kg of FG:

    1 Kg of RM = 0.15 Kg of FG

    1 Kg of FG = (1/0.15) Kg of RM

    1 Kg of FG = 6.66 Kg of RM

    Cost of 1 KG of RM = Rs. 10 per Kg

    Therefore, Cost of 6.66 Kg of RM which will produce 01 Kg of FG will be: 6.66 x 10 = Rs.66.66

    iii) Direct Labour Cost:

    Categories Monthly Salary Requirement Salary of Required

    Personnel

    Skilled Workers Rs. 8,000 10 Rs. 80,000

    SemiSkilledWorkers

    Rs. 5,000 30 Rs. 150,000

    Unskilled Workers Rs. 3,000 40 Rs. 120,000

    Total Direct Labour

    Cost

    Rs. 350,000

    As already stated, assumed production is 100 tons.

    Therefore, Direct Labour per Unit Cost will be: (350,000/100,000) = Rs. 3.5 per unit.

    Now, Unit Variable Cost = 15 + 66.66 + 3.5 = Rs. 85.16

    c) Fixed Cost:

    Interest Rs. 16,098,000

    Depreciation of Plant Rs. 3,000,000

    Depreciation of Building Rs. 500,000

    Depreciation of Fixtures & Fittings Rs. 1,000,000

    Salaries Rs. 2,304,000

  • 8/12/2019 POM Assignment 1

    5/7

    5

    (30000x04+12000x06)x12

    Total Fixed Cost (Annual) Rs. 22,902,000

    Assumptions: Pre-Operational expenses are considered as the cost of fixtures and fittings.

    Question 05:For 10 million profits per year what should be the sale price of product.

    Answer:

    Sales[Variable Cost + Fixed Cost] = Profit

    [(1,200,000S){(1,200,000 x 85.16) + 22,902,000} = 10,000,000

    [1,200,000S(102,192,000+22,902,000)] = 10,000,000

    1,200,000S125,094,000 = 10,000,000

    1,200,000S = 10,000,000 + 125,094,000

    1,200,000S = 135,094,000

    S = (135,094,000/1,200,000)

    Selling Price = Rs. 112.57 = Rs. 113 per Kg.

    Question 06:How much working capital will be required? Assume that 15 days of finished product and 30

    days requirement of raw material are kept in stock.

    Answer:

    Total Working Capital = 15 days of FG + 30 days requirement of Raw Material.

    i) 15 days of FG: Selling Price x 15 days FG in Units

    15 days FG = 85.16 x 50,000 units (assuming 100 tons production in a month)

    15 days FG = Rs. 4,258,000

    ii) 30 days requirement of Raw Materials: Price of RM x 100 tons x RM required to produce 1

    kg of FG

    30 days requirement of RM = 10 x 100,000 x 6.66 = Rs. 6,660,000

  • 8/12/2019 POM Assignment 1

    6/7

    6

    Total Working Capital = 4,258,000 + 6,660,000 = Rs. 10,918,000

    Question 07:What will be the yearly profit in next three years? What will be the breakeven

    sale volume?

    Year 1:

    Assumption: 1200,000 units are sold in the year.

    Profit = IncomeExpenses

    Profit = (1,200,000 x 113)[(1,200,000 x 85.16) + 22,902,000]

    Profit = 135,600,000[102,192,000 + 22,902,000]

    Profit = 135,600,000125,094,000

    Profit = Rs. 10,506,000

    Year 2:

    Assumption 1250,000 units are sold in the year.

    Profit = IncomeExpenses

    Profit = (1,250,000 x 113)[(1,250,000 x 85.16) + 22,902,000]

    Profit = 141,250,000[106,450,000 + 22,902,000]

    Profit = 141,250,000129,352,000

    Profit = Rs. 11,898,000

    Year 3:

    Assumption 1150,000 units are sold in the year.

    Profit = IncomeExpenses

    Profit = (1,150,000 x 113)[(1,150,000 x 85.16) + 22,902,000]

    Profit = 129,950,000[97,934,000 + 22,902,000]

    Profit = 129,950,000120,836,000

  • 8/12/2019 POM Assignment 1

    7/7

    7

    Profit = Rs. 9,114,000

    Breakeven Volume: (Fixed Cost/ Contribution Margin)

    & Contribution Margin = Unit Selling PriceUnit Variable Cost

    Therefore,

    Breakeven Volume = [22,902,000/(113-85.16)]

    Breakeven Volume = (22,902,000/27.84)

    Breakeven Volume = 822,629.31 units = 822,630 units approx.

    Breakeven in Rs. = Breakeven Volume x Unit Selling Price

    Breakeven in Rs. = 822,630 x 113 = Rs. 92,957,190