port of airlie marina: delivering on commitments claire …

20
1 PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire Gronow Introduction Coastal development in Queensland is challenging Particularly high coastal environmental values World Heritage Areas Ramsar Wetlands Marine Parks Particularly high demand for coastal development Lifestyle Tourism and recreation

Upload: others

Post on 12-May-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

1

PORT OF AIRLIE MARINA:DELIVERING ON COMMITMENTS

Claire Gronow

Introduction •Coastal development in Queensland is challenging

•Particularly high coastal environmental values• World Heritage Areas

• Ramsar Wetlands

• Marine Parks

•Particularly high demand for coastal development• Lifestyle

• Tourism and recreation

Page 2: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

2

Project Overview Town of Airlie Beach, Whitsunday region, Queensland

High demand for coastal development:

• Tourism

• Residential

• Key sensitivities in and around project site:

• Great Barrier Reef – Whitsunday region

• World Heritage Area

• Marine Park

• Close proximity to residential and tourist accommodation

• Cyclones/extreme weather

• Mangrove and seagrass habitat – degraded but highly valued

• Iconic species - turtles, dugongs

• Contaminated sediments

• Potential for acid sulfate soils

Project Overview

Page 3: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

3

Boathaven Bay

Project Overview

• Project site was modified and degraded:

• Contaminated sediments

• Road construction – entire coastal frontage had been moved seawards

• Formal and informal boat maintenance activities

• Former landfill

• Former sewage treatment plant outfall

• Stormwater outfalls

Project Overview

Page 4: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

4

Project Overview

Project Overview

•Project required:

• Construction of marina basin and land in tidal waters

• Footprint ~40 hectares

• ~1,000,000 cubic metres of earthworks

• Excavate marina basin

• Create land

• Dredge access channel

• 2-3 ha of mangroves to be removed

• 8-10 ha of seagrass (maximum extent) to be removed

Page 5: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

5

Project Overview

Impact Assessment & Approval Process

• Port of Airlie triggered Environmental Impact Assessment:

• Queensland State Development and Public Works Organisation Act 1971 “Significant Project Process”

• Environmental Protection and Biodiversity Conservation Act 1999 “Controlled Action”.

• Strong support from community (about time!)

• Some vocal opposition – anti-development

Page 6: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

6

Impact Assessment & Approval Process

• Lengthy negotiations with State agencies

• Concern that project could not be constructed without “significant” impact on water quality and seagrass habitat

• Concern that direct loss of seagrass/mangrove habitat would reduce fish productivity

• Negotiated hard to ensure conditions were:

• Practical and implementable

• Provided adequate safeguards

Key Proponent Commitments

• Prepare a Construction Environmental Management Plan• Address compliance with permit conditions and

commitments made in EIS• Submit to Federal and State for approval

• Fund $350,000 of fisheries resources research• Conduct extensive seagrass monitoring (~$400,000 over

5 years)• Internal and external environmental audits

• Reports provided to EPA• Extensive water quality management and monitoring• Interactive noise management plan• Community Reference Group

Page 7: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

7

Design Concept and Construction Method

• Full enclosure of construction area by sheet pile or rock revetment walls

• Temporary sheet pile across mouth of marina basin – full containment during excavation

• Excavate marina basin, place excavated material behind sheet pile/rock walls to create land component

• Sheet pile/rock walls become permanent structural features around land

• Dredge access channel (~1 km) and pump dredge spoil to marina basin

• On completion, marina basin flooded and temporary sheet pile removed

Design Concept and Construction Method• Maintenance dredge area constructed as water treatment

cell for tailwater

• Potential acid sulfate soils (25,000m3) reburied below lowest astronomical tide

• Contaminated sediments excavated and reburied in specially constructed cells

• Cut/fill balance minimise material transport:

• No material removed from site for disposal

• Only material brought on to site was armour rock, sand and sheet piles

• Vibratory piles instead of hammer piles where possible

• Controls on hours for pile driving

Page 8: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

8

Earth/Rock Wall Sheet Pile

Marina basin

Design Concept and Construction Method•August 2007

Design Concept and Construction Method

Page 9: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

9

Design Concept and Construction Method

Marina basin

Temporary Sheet Pile

September 2007

Design Concept and Construction Method

Tailwater Management Pond

Page 10: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

10

Design Concept and Construction Method

Design Concept and Construction Method

Page 11: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

11

Design Concept and Construction Method

Design Concept and Construction Method

Page 12: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

12

Design Concept and Construction Method

Design Concept and Construction Method

Page 13: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

13

Design Concept and Construction Method

• Concept design and construction method:

• Allowed tight control on water quality, contaminated sediment and potential acid sulfate soils

• Made excavation easier (dry excavation)

• Allowed development of stable landform

• Allowed a cut/fill balance to be achieved (no import or disposal of material)

• Satisfied engineering and environmental requirements

Construction Environmental Management Plan

• Developed in conjunction with construction contractor

• Reviewed by relevant government agencies

• Approved by Federal and State environment agencies

• Contractor provided full time Environmental Manager

• Proponent had an environmental advisor

Page 14: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

14

Potentially Significant Impacts

• Most significant construction impacts:

• Water quality impacts

• Turbidity

• Acid sulfate soils

• Contaminated sediments – Tributyl tin

• Noise and traffic impacts on community/tourists

CEMP• Key activities managed by CEMP

• Water quality:

• Discharges

• Receiving water

• Testing and validation of removal of contaminated sediments.

• Acid Sulfate Soils

• “Groundwater” monitoring

• Noise and vibration

• Seagrass monitoring

• Weekly, daily and rain event checklists

• Internal and external audits

Page 15: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

15

CEMP

• Water quality:

• Continuous monitoring of discharges from from water retention basin

• pH, turbidity, DO

• Heavy metals and TBT at certain stages

• Receiving environment water quality at reference sites in Boathaven Bay

• pH, DO, Turbidity

• Weekly or daily depending on activities being undertaken

CEMP

• Testing and validation of removal of contaminated sediments.

• Acid Sulfate Soils

• Mostly self neutralising – calcium carbonate

• Predicted 25,000 m3 not self-neutralising

• Volumetric testing throughout

• Increased intensity near area of non-self-neutralising PASS

Page 16: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

16

CEMP

• “Groundwater” monitoring:

• To confirm self neutralising capacity of PASS

• To check for leaching of TBT or other metals

• Monitor groundwater in fill areas

• Weekly – levels, pH, salinity

• Monthly – metals

• Quarterly – TBT

CEMP

• Noise and vibration

• Three full time noise loggers

• Monthly reviews of noise data

• Schedule construction to avoid concentration of machinery near noise sensitive receptors

• Quietest equipment available

• Option for residential class mufflers

• Restricted hours for hammer piling and vibratory piling

• Extensive community liaison

Page 17: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

17

CEMP

• Seagrass monitoring:

• Annual event every November

• Commenced pre construction (2 rounds)

• Continue 3 years post construction

• Additional events during channel dredging

• Minor sediment deposition observed

• Impacts within the range of natural variations

CEMP

• Weekly, daily and rain event checklists

• Monitoring equipment in place and operating properly

• Waste management

• Hazardous materials management

• Flora/fauna observations

• Water quality data and checklists reviewed by Environmental Advisor weekly/monthly and forwarded to EPA

Page 18: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

18

CEMP

• Internal and external audits

• 3 internal and 4 external (independent)

• Reports forwarded to EPA and DEWHA

• Reports presented to Community Reference Group

• Results ranged from 88% compliance to 97% compliance

• Non-compliances generally minor in nature

• Signs on fuel storage

• Noise complaints

• Bunding of chemical storage

• Contractor reports against KPIs monthly

Community Reference Group

• Commitment made by proponent in EIS

• Proponent funded and appointed a Chairman and Secretary

• Membership from:

• Local government elected representatives

• Private business sector

• Community

• Construction Manager

• Proponent’s Environmental Advisor

• Proponent’s Development Manager

Page 19: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

19

Community Reference Group

• Monthly meetings• Proponent/contractor reported against pre-agreed Key

Performance Indicators• CRG discussed issues arising and agreed on

appropriateness of response• CRG released newsletters and other information to

community • Effective in:

• Minimising complaints• Promptly addressing community concerns• Benchmarking acceptability of management measures• Ensuring community remained well informed

Summary • Address environmental impacts and risks through design

and construction method • Early contractor involvement and “buy in” is critical • Management measures must be practical, clear,

implementable and measurable • Ensure adequate resources to implement CEMP • Ensure adequate accountability, checks and balances:

• CRG• Monthly KPI reports• Internal and external audits • Contractor reports to CRG

• Close and proactive relationship with local community

Page 20: PORT OF AIRLIE MARINA: DELIVERING ON COMMITMENTS Claire …

20