MPI Business StreamReview for 2015 & 2016 Forecast

Page 2: Power Project Review

Power Swap Project

Page 3: Power Project Review

Strategy for 2016

Power Swap ProjectObjective: Deploy Hybrid Power Systems across the IHS network to stabilise power supply across the network and reduce OPEX by 50% through reduced diesel consumption.Both Technology Partner and Managed Services have skin in the game and must guarantee contractual threshold of diesel consumed per month (litres per Month)

Scope:• Audit Scope: 2255 Telecommunication Sites• Design & Build of Hybrid Power Solution that will guarantee a fixed threshold of diesel

consumption.(Advanced Efficient Power System)• Deploy & Commission solution across 1970 sites across three regions• Handover new Systems to MPI operations and Maintenance Dept. to Manage for 10 years.• Operational readiness: Fleet, Regional Warehouse/Offices, Resources, Training, logistics• RMS Installation and Commissioning• Replacement CAPEX every 4 years• 18 month ProjectDeliverables

Page 4: Power Project Review

Strategy for 2016

Timescales

Insert graphic deployment plan

Jan Feb Mar Apr May Jun Jul Aug Sep Nov Dec0

50

100

150

200

250Deployment Plan Nov. 2015 - Sep. 2016

Total

Page 5: Power Project Review

Strategy for 2016

Issues • Large Scale Project with numerous complexities and dependencies• Lack of in depth subject matter expertise and experienced resources• OEM Partner management• Changes in solution BOM resulting in budget variations• Lack of adherence to project management controls• Material availability delays due to wrong shipping documentation and LC discrepancies.• OEM having cash flow challenges which leads to import delays/Equipment Availability• Delays in Customer providing PO’s in long lead items• Lack of cross functional project maturity• Lack of trained personnel to maintain operate new power solutions• Quality of Supervisors and deployment SBC’s

Risks:• That technology solution fails and does not deliver on expectations• Foreign Exchange restrictions affect funding of the project and MPI unable to establish Letter

of credit and pay overseas suppliers.• Customs and excise Polices hike up import tariffs beyond budget• Trained resources get poached to the competition• .Poor installation invalidate warranty and affect client equipment

Page 6: Power Project Review

Strategy for 2016

Detail a Strategy plan to drive growth in your business unit/country

Page 7: Power Project Review
Page 8: Power Project Review
Page 9: Power Project Review

Q&A