ppmo (hsdu)
TRANSCRIPT
-
7/28/2019 PPMO (HSDU)
1/29
FACULTY OF
ENGINEERING
Assignment 1
Course LecturerMuriel Lezama
Health Sector Development Unit
Design & Implementation of Project Management Office
Submitted in Partial Fulfilment of the Requirements to the
Degree of Master of Science in Project Management Of
The University of the West Indies
Name Student ID#
Juanelle Marks 811006458
Date Submitted:
THE UNIVERSITY OF THE
WEST INDIES 2013
(GUYANAS CONTINGENT)
-
7/28/2019 PPMO (HSDU)
2/29
Table of Contents
General Information 1
Executive Summary 2
Background 3
Charter for the Health Sector Development Unit (PMO) 4
Layout of PMO-
Structural
Functional
Operational Plan
Critical Success Factors
Impact Indicators
References
-
7/28/2019 PPMO (HSDU)
3/29
GENERAL INFORMATION
Project
Name:
Health Sector
Development unit (Project
Management Office)
Project Definition
Report2013/09/18
Project ID: HS005130Pre-Feasibility Study
completed2013/10/18
Executing
AgencyThe Ministry of Health
Feasibility Study
completed2013/11/15
Project
DescriptionImplementation of GRA
Commencement of
works2014/01/02
Project
DirectorAubrey Thompson
Expected Completion
Date2014/06/30
APPROVAL AUTHORITIES
Project Sponsor 1 The Global Fund AkintundeWatson
A DA AwM
Project Sponsor 2Inter-American
Development Bank
Keith
Burrowes
A DA AwM
Project Sponsor 3International Labour
OrganizationPaul Clarke
A DA AwM
CONTACT-MINISTRY OF HEALTH
Shinel Evelyn- Giovanni Garnett Jainarine Rameshwar
(592) 644-2141 (592) 644-0766 (592)621-6340
[email protected] [email protected] [email protected]
Raine Erkskine Quacy Larose Kecia Carrington
(592)654-8722 (592)612-6585 (592)629-3049
[email protected] [email protected] [email protected]
DOCUMENT HISTORY
Version Date Author(s) Revision Notes
APMO 1.0Document Ready for
distribution
APMO 2.0
Incorporated changes.
Document ready fordistribution.
mailto:[email protected]:[email protected] -
7/28/2019 PPMO (HSDU)
4/29
1.0 Abstract
A PMO is a centralised, co-ordinating body within an organisation (or project) that provides a
focal point for the field of project management. It can identify and address project management
issues to support and facilitate the achievement of organisational project outcomes. According to
Gartner (2008), investments in a Project Management Office (PMO) as a work management
discipline can provide common planning and reporting processes and bring structure and support
to evaluating, justifying, defining, planning, tracking and executing projects. It also encourages
the resolution of conflicts caused by limited resources and other constraints. We've all seen
renegade projects that seem to run according to their own agenda. A PMO can help organisations
create effective control and oversight of projects and integrate them with the overall business
outcomes. Benefits of a PMO include: establishing an enterprise focus on improvement inproject management competency; developing or enhancing project management skills and
knowledge through training or mentoring; ensuring consistency and uniformity in project
delivery; reducing project overruns and increasing delivery speed; increasing customer
satisfaction through achievement of outcomes; archiving project operational and performance
data.; providing a centralised point of reference for the project management practice.
This paper elucidates Charter and proposed implementation and operational plans for the Project
Portfolio Management Office (HSDU) of the Ministry of Health.
-
7/28/2019 PPMO (HSDU)
5/29
2.0 Background
According to the Millennium Development Goals (MDGs) Report 2007, Guyana has the
potential to attain the goals related to eradicating hunger and combating HIV/AIDS, but is
unlikely to reach the goals pertaining to child mortality, maternal health, and malaria and
tuberculosis. More recently, in common with many other countries worldwide, Guyana has
experienced a significant increase in food prices, resulting in a serious challenge to its ability to
ensure food security, especially for the most economically vulnerable which might further
complicate the attainment of the MDGs.
Constant fluctuations of economic forces coupled with politics and intense racism undermines
the achievement of the foregoing goals. Undoubtedly donor financing is absolutely necessary for
Guyana to attempt projects aimed at achieving the MDGs. Thus, the Ministry of Health works
with various development agencies and proGRAms, including PAHO/WHO, GAVI, UNICEF,
UNFPA, Centre for Disease Control (CDC/FXB), USAID, and the Guyana Red Cross Society
(GRC), as well as the IDB.
As laid out in the National Health Sector Strategy 2008-2016, in the near future the GOG expects
to combine financing for the health sector from all donor and lending sources, to ensure that
external funding is aligned with its priorities and contributes to the strengthening of the health
system as a whole.
Funds for all ministries are channeled through the (NCF) National Consolidated Fund
(Government Account). To avoid donor financing being placed in the NCF the Health Sector
Development Unit will be created as the project arm and project portfolio management office of
the Ministry of Health, to assist in planning, implementing and managing the health sector
portfolio of programs; safeguard donor funds so that funds through accountable and transparent
in project expenditure.
HSDU will be a collaborative effort amongst the Guyana Government, MOH and multiple donor
agencies in particular the Global Fund. This project portfolio office will be a centralized
operation located in the Georgetown Public Hospital Compound, East Street, Georgetown.
-
7/28/2019 PPMO (HSDU)
6/29
485175, 102247 1078335, 97551 110 http://searchcio.t 1288934
inlineoptin 1
3.0 Charter for the Health Sector Development Unit
3.1 Introduction:
Upon gaining the approval of the National Assembly the Ministry of Health will establish the
Health Sector Development Unit as its central project management office to implement and
manage all projects within the health sector portfolio. The development of this Unit was
mentioned in the National Development Strategy 1995-200, National Health Sector Reform
Strategy 1998 and the National Health Plan 2000. GRA will be a physical location as well as a
conglomerate of project experts and other personnel.
3.2 Justification:
The Health Sector is plagued by diseases; lack of funds and technological infrastructure to do
research as well as to offer advance health care to the public. In order to target and tackle
diseases like Malaria, HIV/AIDS, Tuberculosis and Anemia, the Ministry of Health will partner
with international lending agencies to plan and implement a portfolio of projects.
Hence it is vital that an independent project management unit is established to do donor
coordination and manage donor funds. The potencies of having a centralized project office will
include: consolidated administrative office; providing project management consulting and
mentoring; resource allocation; project coordination and vendor management.
3.3 Vision:
The Health Sector Development unit of MOH is the central project management office, that
manages coordinated donor financing to drive the health sectors portfolio by identifying,
managing, and eliminating problems so that projects succeed, deliver high quality results on time
and within budget."
3.4 Mission
Strategic
The HSDU of MOH will plan, implement, manage, monitor and report on the national health
project portfolio, through holistic project planning; procurement of technical assistance;
cooperation and coordination with stakeholders and general administration of the for the national
portfolio, accountable structure with contemporary management systems and standardized
processes.
Tactical
-
7/28/2019 PPMO (HSDU)
7/29
i. Centralize project management so as to foster better alignment of project activity to thehealth sector strategy
ii. Implement a more consistent project management process and methodologyiii. Facilitate better collaboration and knowledge and best-practice sharingiv. Ensure resource pool is trained and competent to meet evolving IT and business needsv. Better manage resource utilization and capacity
vi. Provide executive visibility to project, program and portfolio-level status, issues, risks,costs, etc.
3.6 Objectives:
i. Create and maintain a consistent world class project management methodology andprocess for all project management engagements.
ii. Train, certify if possible, coach, and mentor project managers in not only projectmanagement, but also project delivery to ensure skill mastery and consistency in planning
and execution
iii. Manage strategic and project priorities matching project goals with appropriatetechnology solutions and provide increased resource utilization across the organization by
matching skills to project needs
iv. Provide centralized control, coordination, and reporting of scope, change, cost, risk, andquality across all projects
v. Increase collaboration across projectsvi. Provide increased stakeholder satisfaction with project-related work through increased
communications, collaboration, training, and awareness
vii. Reduce time to market by providing better coordination and the right resources with theright skills for the projects
viii.
Reduce project costs because common tasks and redundant projects could be eliminatedor managed at the central level
ix. Holistically reduce project risk3.7 Scope: The Scope of HSDU (PMO) encompasses;
Component 1 Component 2 Component 3
Feasibility Study of
centralizing operations with a
project portfolio management
office
Construction of the building
to house the HSDU
Staffing of functional areas within
HSDU
Project Definition ReportCommission of building by Create and implement operational
-
7/28/2019 PPMO (HSDU)
8/29
3.8 Key Success Factors
i. Sponsors supportii. Executive management team involved and measured through defined performance
parameters
iii. Changes in the measurement system to be consistent across the PMOiv. Adaptation of reward and incentive systemv. Sponsorship capability development
vi. Resource alignment which adequately reflects your current needs.vii. A comprehensive Expectations management plan.
viii. Strong Project Management Infrastructure which addresses:ix. Strong change control processx. Standardised project management methodology
xi. Ability to measure and report.3.8Tools Required
Portfolio
Management
&
Performance
Monitoring
Pipeline
Management
Financial
Management
Personnel
Management
Quality
Assurance
Operational
Procedures
Project
Support
Cost-BenefitAnalysis,
ChangeManagement
Log
ProjectRelations
ManagementSoftware
PortfolioBudget
ResourcePlanning
Software
CertifiedAuditing
Techniques
Whitepapers:i.Project
ManagementMethods
ii.CompetencyDevelopmentFramework
ii. IT ServiceManagement
v.Thefundamentalsof Financial
Managementv.Portfolio
Governancei.Monitoring
& Evaluation
Projectmanagement
InformationSystem
Application
PortfolioManagement
Cost
ManagementPlan
Responsibility
Matrix
White
Papers onAuditing
Project
Dashboards
Project &
PortfolioManagement9.2
Portfolio
AppropriationsRequest
Staff
ManagementPlan
IIA
Advisories
Correspondence
Data base
Earned Value
analysis
Procurement
Plan
IIA
Newsletters
Vehicles
VarianceReports,Performance
Reports
VendorDatabase
IIAJournals
-
7/28/2019 PPMO (HSDU)
9/29
Implementation Plan for the Health Sector Development Unit
Identify
Sponsor
Determinefunctions &
staffing
Prepare
Communications
Plan
Prepare
plan &
target
Conduct
Assessment
Obtainfunding
&
staffing
ConductPilot test
Roll out
-
7/28/2019 PPMO (HSDU)
10/29
Layout for Health Sector Development Unit
4.1 Structural
.
GRA
PMO
Financial
Magt
Personnel
Development
Project
Support
Project
Coordinator
Project
Coordinator
Project
Coordinator
The Global Fund
Inter-American
Develo ment Bank
World Bank
Government of
Gu ana
Minister of Health
National Health
Committee
Quality
Assurance
Operational
Procedures
Portfolio
Management
Pipeline
Magt
Project A
Project B
Project C
Project H
Project I
Project J
Project O
Project P
Project Q
-
7/28/2019 PPMO (HSDU)
11/29
4.2 Functional
S
PMO
(GRA)
Portfolio
Management
Operational
Procedures
Financial
Management
Quality
Assurance Pipeline
Management
Personnel
Development
Project
Support
Project G Project NProject U
-
7/28/2019 PPMO (HSDU)
12/29
Operations Plan for the Health Sector Development Unit
The GRA will serve as the Project Portfolio Management and it will support the following:-
Portfolio Strategic Management Portfolio Governance Management Portfolio Performance Management Portfolio Communication Management Portfolio Risk Management
Project Portfolio Management Office
GRA (PPMO) will function as a corporate operational support for all health sector projects. GRA
will obtain and implement a Project Portfolio Management software application to allow the
Section to manage projects at a strategic, tactical and operational level, providing stakeholders
with key information to make informed decisions in a timely manner. All processes, procedures
and methods involved in the operations of GRA will standardize in alignment with the best
practices of specific areas of expertise. The PMO will inteGRAte Project tools to support the
Standard Operating Procedures and ensure that all staff conforms to same. Lastly,
GRA Service Portfolio
Service Service Details
Portfolio Management,
PerformanceMonitoring
The largest section within HSDU will be the Portfolio Management &
Performance Monitoring Section will:-
1. Create and coordinate portfolio work plan; identify portfolio workprogramme commitments and time frames, set monthly targets,
prioritize projects & portfolio monitoring
2. Portfolio change management3. Portfolio integration4. Stakeholder & donor coordination5. Portfolio evaluation6. Risk Management- An analysis of the risk sensitivities residing
within each project, as the basis for determining confidence levels
across the portfolio. The integration of cost and schedule risk
management with techniques for determining contingency and risk
response plans, enable organizations to gain an objective view of
project uncertainties and to develop a risk adjusted schedule.
-
7/28/2019 PPMO (HSDU)
13/29
with finite resources in a specified time.
Financial Management GRA will have a Finance Section that will do:-
1. Financial planning for the portfolio2. Establish financial controls to maintain accountability, transparency
and operate in alignment with the conditional ties of the donor
agencies.
3. Project Cost Management4. Procurement & Vendor Management
Operational Procedures GRA will have an Operational Procedures Section which will create
Standard Operating Procedures which define and implement the
processes, procedures & methods to govern operations and will beextended to project activities. The Section will continuously educate
project staff of project management fundamentals, best practices, and
project management methodology. Activities will include formulating
project operational & reporting guidelines; project management maturity
models, outlining performance indicators & benchmarks; Collaborate
with Human Resource Development Section to formulate Policies;
Create templates, forms, maintain the History Repository and document
publication.
Quality Assurance The Quality Assurance Section will:-
1. Define Quality Standards2. Identify Quality Benchmarks3. Conduct Audit & Special Investigations to identify and report
irregularities then formulate the respective controls mitigate
irregularities.
Personnel
Development
GRA will have a Personnel Development Section which focuses on:-
1. Efficient and effective hiring human resources with the technicalexpertise
2. Training & development of Human Resources; deployment ofhuman resources where and when they are needed.
3. Develop technical skills of PMO staff as well as project staff.4. Resource allocation, by matching competence with required job
skills5. Certification tracking
-
7/28/2019 PPMO (HSDU)
14/29
Financial Management Section
All activities within the Finance will be guided Standard Operating Procedures. SOPs will be
created in conformity with the Fiscal Management & Accountability Act Law of Guyana and
International Best Practices. Below is an example of an SOP to be used by the Financial
Management Section.
STANDARD OPERATING PROCEDURE
To ensure that Payment Vouchers are accurately prepared for the disbursement of funds
to acquire items
Description Responsible
1 Receive an Invoice, Subsistence, Quotation from the FinanceManager or other Unit
Supervisor/ExaminationOfficer
2 Examine the document Supervisor/ExaminationOfficer
3 Are all necessary signatures and approvals in place? If yesproceed to Step 4. If no go to Step 3.1
Supervisor/ExaminationOfficer
3.1
Return for correction and re-submission Supervisor/ExaminationOfficer
4 Forward to Clerk for voucher to be prepared Supervisor/ExaminationOfficer
5 F d h E i i Offi f i i S i /E i i
Finance
Executive
Finance
Manager
SalariesSupervisor (1)
Clerk (1)
PaymentsSupervisor (1)
Clerk (1)
VoucherPreparation
Supervisor (1)
Clerk (1)
Reconciliation
Supervisor (1)
Clerk (1)
Capital PlanningSupervisor (1)
Clerk (2)
http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/ -
7/28/2019 PPMO (HSDU)
15/29
Personnel Development & Management Section
All activities within the Personnel Development & Management Section will be guided
Standard Operating Procedures. SOPs will be created in conformity with the Labour
Laws of Guyana and International Best Practices. Hereunder is a sample of an SOP to be
used by the Section.
STANDARD OPERATING PROCEDURE
To process applications for advertised vacant positions
Step No. Description Responsible
1 Receive application being submitted to Personnel Development Recruitment
Clerk
2 Vet the application to determine whether there is a reference number
affixed
Recruitment
Clerk
3 Does the application have a reference number affixed? If yes proceedto Step 4. If no go to Step 3.1 RecruitmentClerk
3 1 S d h li i h E i Di ffi f h Cl k R i
Human ResourceExecutive
Employment
Administration
Manager
Training&
Development
Manager
Compensation
& Benefits
Clerk (1)
Leave
Clerk (1)
NIS Claims &
gratuity
Pa ments 1
Recruitment
Clerk (1)
Training
OfficerTraining
Officer
http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepno%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepno%27%29/ -
7/28/2019 PPMO (HSDU)
16/29
Training
STANDARD OPERATING PROCEDURE
To compile a summary of the training needs of the functional areas within the HSDU andprepare an The Training Requirement Plan
Steps Description Responsible
1 Analyse the Work Programmes for the Functional Areas of the
HSDU
Training Officer
2 Extract the training needs from each Work Programme Training Officer
3 Compile HSDU's Annual Training Requirement Report by
including all the training needs extracted from the variousWork Programmes
training Officer
4 Generate HSDUs Annual Training Requirements Report Training Officer
5 Prepare a memorandum and attach HSDU's Annual TrainingRequirement Report
Training Officer
6 Forward memorandum and attachment to the Senior Manager,Training and Development Section
Training Officer
STANDARD OPERATING PROCEDURE
To ensure that planned developmental programmes and training opportunities are provided to all
HSDU employees for the purpose of providing them with the necessary additional skills,
knowledge, abilities, and attitudes to accommodate change policies, new technologies andinternal needs to meet HSDU's future personnel requirements.
Description Responsible
1 Collect all relevant information on the proposed training programme -
name of programme, target group, duration, venue and prepare a memo for
the Executive Director seeking his approval
Manager
2 Forward the memo to the Executive Director Manager
3 Has the Executive Director given his approval for the programme? If yes
proceed to Step 4. If no go to Step 3.1
Manager
3.1 Take no further action Manager
4 Forward the approval to the Functional Head for a list of participants TrainingOfficer
5 Forward the list of participants to the Senior Manager or Officer in Charge,
Training Division
Training
Officer
6 Schedule a meeting with facilitator and Functional Heads to discuss the Manager
http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/ -
7/28/2019 PPMO (HSDU)
17/29
10 Is it necessary to order water, snacks or meals for the training activity? If
yes proceed to Step 11. If no go to Step 10.1
Training
Officer
10.1
Place no orders TrainingOfficer
11 Contact caterer(s) and order the necessary refreshments TrainingOfficer
12 Arrange time for the Office Assistant and Driver to collect and deliver therefreshments
TrainingOfficer
13 Call participants to remind them of the details of the training activity andconfirm their attendance
TrainingOfficer
14 Prepare Training Room or other venue for the training activity, and
position name cards on table(s), Attendance Register at the entrance for
participants' signature, projector etc
Manager
15 Make arrangements for an official to give the Opening Remarks at the start
of the training activity and introduce the Facilitator
Training
Officer
16 Check the eating preferences of the participants, confirm time of arrival for
refreshments in accordance with scheduled breaks and inform caterer,
Office Assistant and Driver of any special requirements or changes
Training
Officer
17 Receive refreshments, assist with and monitor their distribution to the
participants
Training
Officer
18 Assist with the distribution of Evaluation Sheets and collect them at the endof the programme
TrainingOfficer
19 Collect all extra copies of training materials and check Attendance Register
to ensure that all participants have signed it
Training
Officer
20 Is assistance needed in organizing a Closing Ceremony? If so proceed to
Step 21. If no go to Step 20.1
Training
Officer
20.
1
Activity ends when participants bid the Facilitators(s) goodbye Training
Officer
21 Provide any assistance required Manager
22 After the end of the programme ensure that the room is cleaned inpreparation for the next training activity
TrainingOfficer
23 Prepare a report on the programme after it is completed TrainingOfficer
24 Compile a folder with all related training materials - handouts, worksheets,examination paper, report, list of attendees and file away
TrainingOfficer
-
7/28/2019 PPMO (HSDU)
18/29
Operations Plan for the Health Sector Development Unit
Quality Assurance Section
All activities within the Quality Assurance Section will be guided Standard Operating
Senior Manager
Manager
Auditor
(5)
Routine
Audits
Special
Investigations
Random
Spot
Checks
Implementation
Audits
Quarterly reviews &
asset verification
Risk
Based
Define Quality
Standards
Supervise audits &
report to Snr.
Audit Officer
-
7/28/2019 PPMO (HSDU)
19/29
STANDARD OPERATING PROCEDURE
To conduct a Special Report/Investigation
Description Responsible
1 Receive a memorandum to conduct a special audit from the ExecutiveDirector, or primary stakeholder SeniorManager
2 Select a team to conduct the special audit/investigation SeniorManager
3 Plan the assignment and assign auditor accordingly SeniorManager
4 Prepare an audit programme Auditor
5 Conduct internal and external visits to collect relevant information for the
audit/investigation
Auditor
6 Examine and analyse the information collected Auditor
7 Apply the relevant audit approaches to verify the information collected Auditor
8 Ensure that adequate support of communication is reflected in theworking papers
Auditor
STANDARD OPERATING PROCEDURE
To conduct an audit
Steps Description Responsible
1 Proceed to the Project location to be audited Auditor
2 Request in writing the pertinent documents from the Project Manager,through the Project Coordinator
Auditor
3 Collect the pertinent documents such as registers and spread sheets Auditor
4 Commence examination and select a sample of the documents for further
examination
Auditor
5 Document population and sample size in working paper Auditor
6 Examine the sample documents in greater detail to ensure that the
relevant information is recorded, necessary forms submitted for evidence
that internal controls are in place for example, supervisory checks,
completeness and accuracy
Auditor
7 Document the information obtained from the sample documents Auditor
8 Conduct exit interview with Project Manager Auditor
http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/ -
7/28/2019 PPMO (HSDU)
20/29
9 Conduct an exit interview to verify accuracy of communication Auditor
10 Prepare a report on the material findings and recommendations for
submission to the Manager-Quality Assurance Section
Auditor
11 Is the report accceptable? If yes proceed to Step 12. If no go to Step 11.1 Manager
11.1 Note corrections and re-submit to the auditor for inclusion Manager
11.2 Make corrections and re-submit the report to the Manager Quality
Assurance for review
Auditor
12 Submit the report to the Senior Manager-Quality Assurance for review Manager
13 Review the report and submit to the Executive Director and primary
stakeholders
Senior
Manager
STANDARD OPERATING PROCEDURE
In Review
Description Responsible
1 Prepare a Query Sheet from finding of audit Auditor
2 Forward Query Sheet to Manager for review and approval Auditor
3 Is the Query Sheet acceptable? Manager
3.1 Make correction and re-submit Auditor
4 Forward Query Sheet to the Functional Head of the Unit/Section that
was audited
Auditor
5 Manager and Auditor conduct discussion with the Functional Head and
record explanations provided on the points listed on the Query Sheet.
Auditor/Manager
http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/ -
7/28/2019 PPMO (HSDU)
21/29
Portfolio Management, Performance Monitoring Section
All activities within the Portfolio Management & Performance Section will be guided
Standard Operating Procedures. Hereunder is a SOP of the Portfolio Management,
Performance Monitoring Section.
STANDARD OPERATING PROCEDURE
To Create and coordinate portfolio work plan; identify portfolio work programme
commitments and time frames, set monthly targets, prioritize projects & portfolio
monitoring
steps Description Responsible
Portfolio
Management &
Performance
Communication
Officer (1)
Planning Officer (3)Coordination
Officer (1)
Integration
Analyst Officer (1)
Monitoring &
Evaluation
Officer
Project
Inspector
Operations
Analysts(4)
Portfolio
Planning
Senior
Manager
http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/ -
7/28/2019 PPMO (HSDU)
22/29
1 Receive & review amendments to the health sector strategy from
Minister of Health
Senior Manager
2 Refine health sector prospectus and develop health sectorportfolio and submit to minister for review
Senior Manager
3 Upon approval of portfolio and funding, disseminate projectportfolio, develop work programme commitments for each
project
Senior Manager
1 Disseminate project portfolio work plan and work programme
commitments & collaborate with all Sections to prepare sectional
work programmes to match project needs.
Senior
Manager/Planning
Officer
2 In the event a Functional Head fails to submit their sectional work
plan; a reminder memorandum outlining the Functional Heads/ of
the Sections that did not submit Work Programme(s) and requestthe outstanding Work Programme(s) will be submitted to the
Executive Director for signing
Senior
Manager/Planning
Officer
2.2 Receive signed memorandum from the Executive Director and
photocopy same for each Functional Head outlined therein &
Record memoranda in Dispatch Book and dispatch same theFunctional Heads/Senior Managers
Planning Officer
3 Review Work Programmes to ensure the following:1. Work Programmes are in consistency with the approved
format.
2. Targets are clearly stated.3. Targets are realistic and achievable.4. Key activities are clearly stated.
5. Time lines have been clearly outlined
Planning Officer
4 Review to determine whether the Work Programmes are
consistent with the approved format and do they contain therequired information? If yes proceed to Step 6. If no go Step 5.1
and
Planning Officer
5 Inform Functional Heads via phone call/ outlook message of the
Work ProGRAmme(s) that are not in consistency with theapproved format and outline the required information
Planning Officer
5.1 Forward additional/ amended information to the assigned Officer
for perusal/examination
Planning Officer
6 Submit to Executive Director Planning Officer
-
7/28/2019 PPMO (HSDU)
23/29
The Operational Procedures Section will define the methodologies to be utilized
throughout the PPMO.
STANDARD OPERATING PROCEDURE
To provide the step-by-step guide of activities for conducting a business process during thenormal course of the GRAs operations
Description Responsible
1 Receive a request via memorandum or e-mail to prepare an SOP from the
Executive Director
Senior Manager
2 Determine with the Manager-Operational Procedures Section, the
Business Process for which the SOP is to be written, i.e. confirm the
Business Function under which the Business Process operates then
determine its Name (starts with a Verb) and Objective.
Senior Manager
3 Assign the task to an Operational Procedures Officer/Clerk Manager
4 Interview the relevant personnel from the Unit/Division as often as
necessary to obtain the steps to formulate the SOP. Ensure that a draft
flowchart is prepared and the recommended process name is agreedbefore the interview concludes
Operational
Procedures
Officer/Clerk
5 Use the information obtained to prepare the draft Flowchart using the Operational
Operational
Procedures
Senior Manager
Procedures
Officer
Procedures
Officer
Procedures
Officer
Clerk
http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/ -
7/28/2019 PPMO (HSDU)
24/29
Microsoft Visio template provided which governs its standard look and
feel. Save the Flowchart in its respective folder in the path: \\vat-
fileserver\HSDU_Public_Documents\SOP_MANAGEMENT\TRIPS_BU
SINESS_PROCESS_FLOWCHARTS
Procedures
Officer/Clerk
6 Use the HSDU Report Management Website to confirm if the Business
Function exists in order to create the process
Operational
ProceduresOfficer/Clerk
7 Is there an existing Business Function under which the process can becreated? If yes proceed to Step 9. If no go to Step 8.1
OperationalProcedures
Officer/Clerk
Discuss the issue with the Manager, Operational Procedures Section andagree on a suitable Business Function
OperationalProcedures
Officer/Clerk
8.
2
Create the new Business Function using the HSDU Report Management
Website ensuring that the grammar/spelling is perfect.
Operational
Procedures
Officer/Clerk
9 Enter the Steps, Responsibilities and Locations using the HSDU Report
Management Website ensuring that the grammar/spelling is perfect
Operational
ProceduresOfficer/Clerk
10 Create the Business Process with the status 'In Review' ensuring that thegrammar/spelling is perfect.
OperationalProcedures
Officer/Clerk
11 Preview the SOP using the system to verify that there are no grammatical
or spelling mistakes.
Operational
Procedures
Officer/Clerk
12 Are there any grammatical or spelling mistakes? If yes proceed to Step
13. If no go to Step 12.1
Operational
Procedures
Officer/Clerk
12.1
Make corrections where necessary OperationalProcedures
Officer/Clerk
13 Notify the Manager, Operational Procedures that the draft SOP has beencompleted
OperationalProcedures
Officer/Clerk
14 View the draft SOP using the HSDU Report Management Website and
determine the accuracy of its logic and content.
Manager
15 Has the draft SOP been approved? If yes proceed to Step 16. If no go to Manager
-
7/28/2019 PPMO (HSDU)
25/29
Step 15.1
15
.1
Inform the Operational Procedures Officer/Clerk of the necessary
corrections to be made to the narratives
Manager
15.2
Make the necessary corrections and re-submit OperationalProceduresOfficer/Clerk
16 Notify the Senior Manager/Manager of the Unit/Division that the draftSOP has been completed and that they can be viewed using the HSDU
Report Management Website. Request comments/recommendations via
e-mail
SeniorManager/Manag
er
-
7/28/2019 PPMO (HSDU)
26/29
Project Support
The operations of the Project Support Section will be guided by standardized
methodologies as well. Hereunder is the SOP for the Mail Room.
STANDARD OPERATING PROCEDURE
To process the receipt of Sectional & Project Mail, Memoranda and Correspondence
Steps Description
Responsible
1 Receive mail/memoranda correspondence and sign Delivery Book Office
Assistant
2 Stamp and number mail/memoranda correspondence Office
Assistant
3 Enter mail/memoranda correspondence in Mail Receipt Book
and/or electronically in the Computer
Office
Assistant
4 Forward mail/memoranda correspondence to Senior
Manager/Manager/Supervisor of the Section/Section
Office
Assistant
5 File a copy of the mail/memoranda correspondence Office
Assistant
Administrative
Manager
Transportation
(4) Drivers
Maintenance &
cleaning
(3) Cleaners
InformationTechnology
Hard & software
expert
(3) Technicians
Mail Room
(3)office assistants
http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepresp%27%29/http://__dopostback%28%27ctl00%24contentplaceholder1%24gridview1%27%2C%27sort%24sopstepdesc%27%29/ -
7/28/2019 PPMO (HSDU)
27/29
Schedule of Meetings
Type of
Meeting
Attendees Frequency Issues
Discussed
Objective Duration
Stakeholders Stakeholder
-The Global Fund
-IADB-World Bank
GOGMinistry of Health
National Health
Committee
Executive
Director
Quarterly -Portfolio work-
in progress
-Project-
Implementation
statusPerformance
-Expenditure
Reviews
-GRAgovernance
effectiveness
To inform
stakeholders of
portfolio work-in-progress
Strategic
decisionmaking
Strategic
decision
makingPerformance &
risk monitoring
Expenditure
2
Executive
Management
Executive
Director,Senior Functional
Heads
Monthly Strategic To
Implementationof strategic
decisions
Translatingstrategy into
action
2
GeneralManagement
Functional Heads& Managers
Monthly Implementation& operations
To ascertainWork program
commitments
and resultsachieved;
reasons for
variances
2
Operational
Areas
Sectional Staff Monthly Operational Daily
operations;monthly
progress
2
Projects Project Meeting Monthly Operational Daily
operations;
monthlyprogress
2
-
7/28/2019 PPMO (HSDU)
28/29
Review the PPMO
Of course change is definite. As HSDU matures, methodologies will emerge and structures will
evolve, the role and scope of the PPMO must change as well. It is important to work with the
executive to regularly review the PPMO's performance and scope so it remains current and
relevant to the health sector portfolios needs.
-
7/28/2019 PPMO (HSDU)
29/29
References
Bucero, Alfonso, PMP Implementing The Project Office Case Study
Walton. Jane. Creating A Project Management Office (PMO). Serena 2007