pre-feasibility study for roof pv power system

Upload: ante-tojcic

Post on 06-Apr-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    1/12

    Pre-feasibility study for roof PV powersystem in Split, Croatia

    By

    Ante Toji & Stjepan Galambo

    for

    ME3114 Renewable Energy

    Teacher: Sandra Godoy

    London, December 2011

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    2/12

    1

    Contents:

    1. Executive summary ............................................................................................................... 2

    2. PV technology ....................................................................................................................... 2

    3. Pre-feasibility analysis using RETScreen software ................................................................... 4

    1) RETScreen .................................................................................................................................... 4

    2) Energy model ............................................................................................................................... 4

    3) Cost analysis ................................................................................................................................ 6

    4) Emission analysis ......................................................................................................................... 8

    5) Financial analysis ......................................................................................................................... 9

    4. References .......................................................................................................................... 11

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    3/12

    2

    1. Executive summary

    Within this mini-project we decided to do a pre-feasibility analysis of roof PV system in Split, Croatia.As Split is relatively south in comparison with rest of the Europe and as from our own experience weknew it had lot of sunny days we decided to analyze viability of installing roof PV system.

    The brief analysis with RETScreen software show that, due to high incentives for PV in Croatia, itwould be a very profitable investment with equity payback time of just 2,8 years and 5,67 benefit-cost ratio.

    Calculation used is probably too optimistic, but projects viability is unquestionable. Complete analysisis explained in detail in section 3.

    2.

    PV technology

    Due to high increase in energy consumption and also increased awareness of environmentalprotection, renewable energy production is currently subsidized all over the world.Photovoltaic systems represent one of renewable energy sources. PV modules are used fordirect conversion of solar radiation into electricity, which is most widely used form of energy. That conversion is based on photovoltaic that effect was first discovered by MrEdmond Becquerel in 1839. The photovoltaic effect is actually generation of voltagedifference in material due to its exposure to the light. A solar cell consists of layers of semiconductor materials with different electronic properties. When light hits the solar cell,some of the photons are absorbed in the silicon and thus generate voltage difference. Thephotovoltaic process is completely solid-state and self-contained and the PV cells produceno emissions and use no fuel.

    Main components of the general PV system:

    - PV modules (arrays)

    - Control panel

    - Power storage system (batteries)

    - Inverter

    - Backup power supply (generator, grid)

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    4/12

    3

    Industry of PV panel manufacturing is one of the fastest growing industries at the moment.Cause of increased production is both technological progress in material, concept andproduction process research and strong political support through high incentives for PVsystems installation.

    The most important material for production of solar cells is silicon. Silicon feedstock ismelted in a crucible to form either monocrystalline or multicrystalline silicon. Themonocrystalline type of silicon cells has high manufacturing cost, because the crystal growthprocess is very expensive. The polycrystalline or multicrystalline cells are less expensive toproduce than Mono-Si cells, but are less efficient. Analysts have predicted that prices of polycrystalline silicon will drop as companies are building additional manufacturing capacityquicker than the industry's projected demand. Silicon used in PV modules is non-toxic.

    Figure 1- Examples of monocrystalline and polycrystalline cells

    Thin-film solar cells are made by depositing one or more thin layers of PV material onsubstrate, and are usually divided according to PV material used into:

    - Amorphous (a-Si) and other thin-film silicon (TF-Si)

    - Cadmium Telluride (CdTe)

    - Copper indium gallium selenide (CIS or CIGS)

    - Dye-sensitized solar cell and other organic solar cells

    Their main advantage over traditional panels is that they are low in weight, are not subjectto wind lifting and can be walked on. But they have increased cost and reduced efficiency.

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    5/12

    4

    Lifespan

    Most commercially available solar panels are capable of producing electricity for at leasttwenty years. The typical warranty given by panel manufacturers is over 90% of rated outputfor the first 10 years and over 80% for the first 20 years. Panels are expected to function fora period of about 30 to 40 years.

    3. Pre-feasibility analysis using RETScreen software

    1) RETScreenFor our analysis we used RETScreen 4 Clean Energy Project Analysis software tool. It is free-of-chargeexcel-based software provided by the Government of Canada for evaluation of energy production,savings, costs, emission reductions, financial viability and risk for various renewable energytechnologies.

    2) Energy model

    After brief comparison of efficiencies and prices of available PV modules we decided to use Shottspoly-Si Poly 230W modules for analysis.

    Model with modules fixed at optimal annual inclination is used for cheapest mounting structure andmaintenance costs i.e. lowest initial costs.

    As Split is located at 4330N latitude, optimal annual tilt of modules is 30, with 0 azimuth.

    In order to prevent mutual shading of PV modules, with given module dimensions (Table 1.),calculation (Figure 2) has been made to show how many modules can be installed on hypotheticalflat roof of 300 m 2, fixed at optimal annual tilt. Angle of 23is the lowest solar altitude for a givenlocation throughout the year. It showed that each module uses approx. 3,46 m 2 of the roof.

    Length [mm] 1685

    Width [mm] 993

    Table 1. Dimensions of Shott poly 230W module

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    6/12

    5

    30

    L = 1 . 6

    8 5 m

    D 1 =1.46 m D 2 =2 m

    23

    Figure 2- Calculation of distance between modules in order to eliminate mutual shading

    Therefore we could theoretically install 86,7 modules on 300 m 2 of flat surface, but we decided touse 80 modules (18.4 kW) in order to maybe avoid any possible restrictions on roof and to easy laterserial-parallel connection of modules (because of given number, 80).

    Capacity factor, optimal annual tilt and lowest solar altitude are taken from Solar radiationhandbook of Croatia written by EIHP.

    At the moment, Croatia has strong system of incentives for PV power plants with feed-in tariffs up to4-6 times (depending on installed capacity) higher than the average price of electricity. Currently, forsystems with 10-30 kW installed capacity (as one analyzed) feed-in tariff is approximately 610 USdollars. For this reason only, we decided to analyze this system as central-grid i.e. selling all of produced electricity at incentive price to grid operator. The off-grid system would make sense only inthe areas without possible grid connection (such as some mountains or islands). The other advantageof this is reduction of initial costs as there is no need for batteries and charge-controller.

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    7/12

    6

    3) Cost analysis

    Financial inputs for analysis are calculated from data taken from the study by Fractal d.o.o. companyfrom Split. Within that study they calculated current average values for individual components of costs for investment in roof PVPP in Croatia.

    Average costs from their data are as listed below:

    a) FN modules: 1.250 euro/kWb) Inverter(s): 260 euro/kWc) Construction: 350 euro/kWd) Other works: 250 euro/kW

    By converting that values to US dollars and multiplying them with 18,4 kW we got our inputparameters. Cost of other works we separated into Transportation and Training and commissioningwith 1:3 ratio.

    Annual maintenance has been calculated as 2% and insurance premium as 0.8% of initial investment.

    Only one periodic cost occurring at the half of projects lifetime (13 years) is the replacement of inverter(s) which is calculated as 60% of initial inverter cost.

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    8/12

    7

    Due to complicated legislation, preparing of all required documentation (preliminary design, maindesign,...) and issuing of all necessary permits, approvals and agreements, project developmentcosts are estimated at 10 000$. Afterwards they are divided into Development and Engineering (6:4).

    Also the contingencies are set to 5% for initial and 10% for annual costs.

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    9/12

    8

    4) Emission analysis

    As there are no emissions from PV system these views are given only to show what would be theequal annual GHG emission for the production of the same energy using:

    a) Oil 14 tCO2 (according to RETScreen it is equivalent to 1,3 hectares of forest absorbing carbon)

    b) Coal 20,5 tCO2 (equivalent to 1,9 hectares of forest absorbing carbon)

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    10/12

    9

    5) Financial analysis

    Inflation rate and debt interest rate are taken as they can currently be expected in Croatia, and it ispredicted that investor uses 12 year debt to cover 80% of the investment.

    Expected electricity escalation rate given by Fractal d.o.o. is 3,5%, but by reducing it to 3% we aresimulating annual degradation of PV modules.

    Financial analysis shows great results with equity payback time of just 2,8 years and 5,67 benefit-costratio.

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    11/12

    10

    Nevertheless, this is very optimistic calculation because incentive feed-in tariff is currentlyguaranteed just for first 12 years of operation. In this calculation it is assumed that the feed-in tariff will be the same (taking into account escalation rate) throughout the whole lifetime. But even if weassume that after 12 years producer will have to sell electricity at market value (5-6 times less), stillthe annual income would exceed expenditures and there would be no loss, just smaller profit. Lineon the cumulative cash flow graph would still be going up, just with smaller slope.

  • 8/3/2019 Pre-Feasibility Study for Roof PV Power System

    12/12

    11

    4. References

    All technical and financial data used in analysis have been taken from:

    a) Roof PV power plants in Croatia, basic regulatory, technical and economic conditions , Fractald.o.o., October 2011.

    b) Solar radiation handbook of Croatia , EIHP, March 2007.c) www.shottsolar.com d) www.retsreen.net e) en.wikipedia.org/wiki/