Preparations for Linac Commissioning. Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11, 2011. Introduction. Linac Commissioning is scheduled to start November 7, 2011. It is anticipated to last until the end of the year. - PowerPoint PPT PresentationTRANSCRIPT
1 BROOKHAVEN SCIENCE ASSOCIATES
Preparations for Linac Commissioning
Ray Fliller, Associate Physicist8th ASAC meeting for NSLS-II Project
May 10-11, 2011
2 BROOKHAVEN SCIENCE ASSOCIATES
Introduction
• Linac Commissioning is scheduled to start November 7, 2011. It is anticipated to last until the end of the year.
• Obtaining authorization is required prior to commissioning. The authorization process involves the NSLS-II project, the lab ESH committee, lab management and the DOE.
• The focus of this talk is path to authorization.
3 BROOKHAVEN SCIENCE ASSOCIATES
Linac Commissioning Task Force• On December 15, Ferdinand appointed the Linac Commissioning Task Force who’s task is to coordinate
commissioning of the NSLS-II linac• Members:
• Ray Fliller – Injection Systems, Task Force Lead• Brett Parker – Injection Systems• Joe Delong – Controls• Feng Gao – RF• Om Singh – Diagnostics• Bob Casey – ESH• Andrew Ackerman – ESH• Mike Buckley – ESH• Randy Church – Operations• Mike Santana – Operations• Timur Shaftan – Injection Systems Group Leader• Jim Rose – RF Systems Group Leader• Ferdinand Willeke – Accelerator Systems Division Head
• Meetings are held bi-weekly and as needed.• Current focus has been the Authorization Basis documentation required for linac commissioning in
culminating in the Accelerator Readiness Review.
4 BROOKHAVEN SCIENCE ASSOCIATES
Zoom in to linac vault
Equipment installation proceeds through the penetration and ends at a gate valve.
This section will not see beam during commissioning End of Linac
ICT
LB-B2
LB-B1
5 BROOKHAVEN SCIENCE ASSOCIATES
Operation Authorization Process
We are here,Send to DDO this week
Courtesy of Steve Hoey.
May 28, 2011
May 31, 2011
October 17, 2011
November 7, 2011
April 12, 2011~2009
6 BROOKHAVEN SCIENCE ASSOCIATES
Linac Commissioning Schedule
• Lab ESH committee reviews the Authorization Basis (AB) Documentation – April 12, 2011 – finished.
• Deputy Director of Operation approval of AB documentation – package to DDO this week
• BHSO receive AB Documentation for Review – May 28, 2011• ARR Team Appointment – May 31, 2011• BHSO Approval of AB documentation – July 8, 2011• Injector Building Beneficial Occupancy Date - July 28, 2011• Linac Installation Begins - August 11, 2011• Linac ARR - October 17, 2011• Linac Commissioning Begins – November 7, 2011
7 BROOKHAVEN SCIENCE ASSOCIATES
Immediate Next Steps• Develop the Linac Commissioning Plan and other necessary
documentation• Linac Commissioning Plan outlines what needs to occur to be ready for commissioning.
• Get necessary AB documentation approvals from DDO and BHSO.• Interface with Research Instruments to develop a linac commissioning
sequence• A draft sequence exists.• I will travel to RI in late June with this as one of my tasks.
• Finish High Level application requirements and specifications• Prepare to the ARR
8 BROOKHAVEN SCIENCE ASSOCIATES
Linac Beam Parameters
9 BROOKHAVEN SCIENCE ASSOCIATES
Diagnostics Available for Commissioning
Flag
Flag
Flag
FlagFlagFlag
ICTBPMBPM
Faraday Cup
Faraday Cup
FCT
Installed but sees no beam
Safety Shutter
10 BROOKHAVEN SCIENCE ASSOCIATES
Linac Parameters and Measurements necessary for commissioning
Beam Parameter Value Measurement
Energy 200 MeV Dipole & Flag
Current 0.5nC/bunch in SPM and 15 nC train in LPM
Wall Current Monitors in Linac, Integrating Current Transformer at Linac output, Faraday cup in both beam
dumps.Fill Pattern 1 bunch in SPM, 80-150 bunches
separated by 2 ns, 10% relative charge difference per bunch in LPM
Wall Current Monitors in Linac, Fast Current Transformer at Linac output, Faraday cup in Dump on straight ahead
transport lineEnergy Spread 0.5% Dipole and 2 flags
Transverse Emittance 4sxsx’=155nm Three Screens and Quadrupole scan in transport line
11 BROOKHAVEN SCIENCE ASSOCIATES
List of High Level Applications(not exhaustive)
•operators panel•vacuum status•PS status•Temperature measurement
•beam loading compensation
•Water/ Compressed air status•synchronization panel/ bunch select•bunch pattern monitor•RF feedbacks•charge/ trajectory/ beam size measurements
•energy/ energy spread measurement•emittance measurement (3 screen + quad scan)
•charge/ bunch pattern measurements
•interlock status + shutters status
•rad monitors status•loss measurement system•Linac current monitor panel
Want to have specifications for all high level applications by the end of May
12 BROOKHAVEN SCIENCE ASSOCIATES
Conclusion• Linac Commissioning Task Force has been assembled to coordinate
commissioning tasks.• Task force’s main focus to date has been on developing the AB
documents with ESH. • This is on schedule
• The path to commissioning is clear both from ESH and physics point of view.