University Teknologi MARA(UiTM)Faculty of Architecture, Planning & Surveying,Bachelor of Construction Management (Hons)
Partially Demolition
Prepared by:
Shah Hafifie Bin Hamzah 2009449854Mat Ismail Bin Mustafa 2009208548Noraimi Binti Bachok 2009663882Nur Amira Sariyana Binti Syamsudin 2009439860
![Page 2: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/2.jpg)
Introduction• Demolition can be defined as part of construction on site,
which involved, upgrading the existing structures, renovation works and refurbishment .
• Partially demolition is a method of taking down the building with carefully preserving the valuable element of the building.
• For demolition type it can divided into two categories first is fully demolition and the second it is a partially demolition
![Page 3: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/3.jpg)
Case study
No, 68-70 , Jalan Meru ,41050 Klang , Selangor Darul Ehsan,
Malaysia
![Page 4: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/4.jpg)
Site Introduction• kedai pakaian Ying (Chinese Owner)
• Build in 1923 ( 88 years )
• The road opposite the building is the main road to
enter to Klang town.
• the structure is made from concrete
(beam) and the floor is made from
wooden.
• The neighbour besides the building
is the cyber café
![Page 5: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/5.jpg)
Requirement and sequence for demolition work
![Page 6: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/6.jpg)
Safety Requirement• The location of the area is the congested area. So the safety
precaution is important to be carry out. The area of site is dangerous and tend to risk for the public.
• All the safety precaution such as fence and the temporary road must be build by the contractor.
• The existing road besides the building must be temporary close because to allow the machineries to do the work.
![Page 7: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/7.jpg)
Equipment & Machineries
![Page 8: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/8.jpg)
University Teknologi MARA(UiTM)Faculty of Architecture, Planning & Surveying,Bachelor of Construction Management (Hons)
METHOD AND SEQUENCE OF
DEMOLITION WORK
![Page 9: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/9.jpg)
1923
KEDAI PAKAIAN YI NG
SAFETY FIRST
![Page 10: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/10.jpg)
![Page 11: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/11.jpg)
![Page 12: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/12.jpg)
![Page 13: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/13.jpg)
Dust control
• For demolition work, it produce large volume of dust and can be dangerous to public.
• Water spraying is used to control dust in demolition work.
![Page 14: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/14.jpg)
Removal debris• Demolition will generate huge amount of debris. • In this case, before and during demolition, the
following provision should thus be provided:• Overall debris disposal planning• Traffic routing for debris handling and vehicular
access etc.• Sorting of non-structural materials such as timber
and metal for recycling. • When material is being dropped, a lookout man shall
be deployed to ensure general safety. • Clear the site using backhoe and lorry
![Page 15: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/15.jpg)
Traffic control
• Consult with proper authorities• Must provide safety signage• Close the road near the demolition site and
make alternative road to avoid hazard causes by dust near site area
• Protection for pedestrian may be required before demolition can begin
![Page 16: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/16.jpg)
Traffic control
![Page 17: Presentation 1 Demolition Work (Edited)](https://reader031.vdocument.in/reader031/viewer/2022013003/546a7f60b4af9f83288b4b0a/html5/thumbnails/17.jpg)