presentation relating to earned value

23
Earned Value Management is for the management of “projects” A contract or a budget is a “project” A project has specific scope of work A project requires authorized budget A project requires a master schedule

Upload: johngwhiting

Post on 06-Dec-2014

1.220 views

Category:

Business


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Presentation Relating to Earned Value

Earned Value Management is forthe management of “projects”

• A contract or a budget is a “project”• A project has specific scope of work• A project requires authorized budget• A project requires a master schedule

Page 2: Presentation Relating to Earned Value

Earned Value is 3 dimensional

Planned Value1. What work has been authorized? (from PMS)2. What is the budget for the work authorized?

Earned Value3. What work has been accomplished? (from PMS)4. What was the budget for work accomplished?

Actual Costs5. What are the actual costs for the EV?

Page 3: Presentation Relating to Earned Value

1) Scope the entire project before...

You must define 100% of the project scope,using a Work Breakdown Structure (WBS).

Page 4: Presentation Relating to Earned Value
Page 5: Presentation Relating to Earned Value

3) Integrate all project processes

You must decompose the project scopeinto manageable cells which integrates

scope + schedule + resources

Page 6: Presentation Relating to Earned Value

4) Plan and schedule the project

Earned value management requires scheduling:1. A formal Project Master Schedule (PMS)2. Vertical traceability (PMS to all schedules)3. Horizontal relationships linked (CPM)

Page 7: Presentation Relating to Earned Value

5) Identify the measurement metrics

You must define how you will convertPlanned Value into Earned Value

Page 8: Presentation Relating to Earned Value

6) Plan and schedule the projectEarned value management requires scheduling:

1. A formal Project Master Schedule (PMS)2. Vertical traceability (PMS to all schedules)3. Horizontal relationships linked (CPM)

Page 9: Presentation Relating to Earned Value

7) Identify the measurement metrics

You must define how you will convertPlanned Value into Earned Value

Page 10: Presentation Relating to Earned Value

8) Form a project baseline

You must establish a time-phasedperformance measurement baselinemade up from CAPs, providing the basisfor measuring project performance.

Page 11: Presentation Relating to Earned Value

9) Record project direct costs

You must inform the project managerswhat they have spent…to compare against

the Earned Value

---the trend is to weekly measurement…of hours---

Page 12: Presentation Relating to Earned Value

10) Measure project performance

EVM requires 3 dimensional measurement:• Planned Value• Earned Value• Actual Costs• EV – PV = Schedule Variance (SV)• EV ÷ PV = Schedule Performance Index (SPI)• EV – AC = Cost Variance (CV)• EV ÷ AC = Cost Performance Index (CPI)

Page 13: Presentation Relating to Earned Value

11) Periodic estimates at completion

You must periodically estimatea statistical “range” of final cost results,

based on earned value performance data

---which provides the “early warning”---

Page 14: Presentation Relating to Earned Value

12) Manage all changes to the project

You must manage all changes to the project,either approving or rejecting each changeand incorporating the approved changes

into a revised project baseline.

Page 15: Presentation Relating to Earned Value

The “rewards” from the use ofEarned Value Management

Page 16: Presentation Relating to Earned Value

# 1 You join a select group of projectswhich are predicting their final resultsfrom the 15% 20% completion point...

...in time to make a difference.

Page 17: Presentation Relating to Earned Value

# 2 You will employ a “single”management control system

to provide enterprise-wide data onall capital projects

---the CPI is the common metric on any project---

Page 18: Presentation Relating to Earned Value

# 3 You will use an “integrated”management control system

to combine the project’s

technical + time + resources

Page 19: Presentation Relating to Earned Value

# 4You will employ

“Management by Exception” (MBE)principles to monitor performance

against the approved baseline

---the “CPI” and “SPI” constitute the exceptions---

Page 20: Presentation Relating to Earned Value

# 5 You will know your project’strue “cost efficiency”

the Cost Performance Index(e)based on actual performance

---the CPI never completely recovers!!!---

Page 21: Presentation Relating to Earned Value

# 6 You will know the project’sSchedule Performance Index (SPI) to

isolate & quantify & manage the workscheduled...but not performed

Page 22: Presentation Relating to Earned Value

# 7 You can useEarned Value Management datato monitor the remaining effort

within management’s expectations

Page 23: Presentation Relating to Earned Value

Earned Value providesfundamental Project Management

You can practice goodproject management without EVM,

you cannot practice EVM effectivelywithout good project management”