Presentation to the
IT Directional
Meeting
July 14, 2004Mike J. Ressler, Deputy CIO
& Director of ITD
2
Agenda
1. ITD’s Annual Report - Mike Ressler2. Attorney General Opinion’s – Mike Ressler3. Update-Desktop RFP / EA Activities – Pat Forster4. IT Plans & Projects – Jeff Swank5. ConnectND Report – Dirk Huggett6. Project Management Service – Vern Welder7. Biennium Planning – Vern Welder8. Testing Tools – Vern Welder9. Work Management System Update - Vern Welder10. Application Server Changes – Vern Welder11. Mainframe Migration Study - Dean Glatt12. Telecommunication Topics – Jerry Fossum13. Budget Rate Review - Dan Sipes
3
4
Attorney General Opinions
• Special Funds Transfer
• ITD Savings – Agency Charges
• Rule Making – Technology Standards and Policies
5
Update-Desktop
RFP / EA
Activities
Presented by:Pat Forster
IT Policy & Planning
6
Desktop RFP ProjectBackground:
• PTI Recommendation “Move to a highly standardized workstation environment on a statewide basis with ITD managing the replacement cycle”.
• Enterprise Architecture- ARB Direction:1. Prepare and execute an RFP to begin aggregated single
brand PC acquisition for the office automation PC.2. Standardize the specifications for PCs to be used in state
government to reduce the total cost of ownership.3. Adopt a four year replacement cycle for office automation
PCs to reduce the total cost of ownership.4. Continue to study how to best manage the replacement
cycle process.
7
Desktop RFP Project
EA Desktop Acquisition Project Team:
Tax Dept. Cathie Forsch (ARB Sponsor)
NDAC Chris Brown
ITD Pat Forster
ITD Dean Glatt
WSI Dave Hoenke
DHS Kelly Klein
Office of AG Nancy Lewis
OMB Sherry Neas
DOT
JSND
Erv Zimprich
Larry Zubke
8
Desktop RFP ProjectMajor goals for the Desktop RFP project:
1. Confirm PC equipment specifications as developed by the Desktop Acquisition Study team (ratification by Desktop Domain team).
2. Using the PC specifications, conduct a survey of State agencies to obtain purchasing volumes.
3. Management tool specifications and evaluation criteria (developed by Desktop Domain subgroup).
4. Draft Request for Proposals (RFP) document. 5. Conduct the RFP solicitation process within
WSCA pool of vendors. 6. Milestone Reports and Recommendations back to
EA (Architecture Team, ARB)
9
Desktop RFP Project
• A new national WSCA contract will be awarded (lead state is Minnesota) starting Sept 1, 2004. The new contract will allow states to compete standard specifications and volume purchases within the framework of WSCA approved suppliers.
• Team decided to stay within WSCA, if possible, because we can leverage much of the contract work completed by Minnesota such as: Financial stability and evaluations. Reporting and service level capacity. Ability to support large enterprise level
demands.
10
Desktop RFP Project
• Two Classes of Desktop and Laptop PCs have been defined for the RFP: Office Automation Desktop
• CPU – 3GHz P4, Memory – 512MB
Power User Desktop • CPU – 3.2GHz P4, Memory 1GB
Mainstream Laptop• CPU – 1.6GHz PM, Memory 512MB
Power User Laptop• CPU – 1.7GHz PM, Memory 1GB
11
Desktop RFP Project
• Ongoing review of Specifications
Quarterly reviews with vendor
Changes to standard specifications
Pricing reviews
Customer service
Contract performance
Improvements to the process
12
Desktop RFP Project
RFP Schedule:
Issue RFP July 12 Proposals Due Aug 12 Vendor Presentations September RFP evaluation complete October 15 Recommend to ARB October Recommend to SITAC November Notice of Intent to Award November Contract Starts Dec 1
13
EA Activities
• Study Teams / Projects: Desktop Acquisition Team
• RFP in progress– ARB Sponsor: Cathie Forsch
Desktop Support Study Team• Define the ideal model for desktop support for ND State
government – ARB Sponsor: Pat Kelly
Interactive Voice Response (IVR) Team• Identify a replacement solution for the States current
proprietary IVR systems that will work within the states technology infrastructure
– ARB Sponsor: Vern Welder
14
EA Activities
• Study Teams / Projects (cont.): Functional Testing Tools Team
• Evaluate state agency's needs for functional testing tools and determine what the best fit is for ND State Government's enterprise
• RFP in progress– ARB Sponsor: Phyllis Lasher
Time and Labor Study Team• Complete a requirements/needs assessment to
determine additional time and labor functionality beyond that currently available in ConnectND.
– ARB Sponsor: Doug Faiman
15
EA Activities
• Study Teams / Projects (cont.):
The EA website has been updated to add links and content for the EA Study Teams.
Access the Study Team links from the “Teams” link on the EA home page
• http://www.state.nd.us/ea/teams/
16
EA Activities
EA Coordination within ITD Policy & Planning:
Jenny Witham has taken IT Director position at DHS (Congrats, Jenny!)
EA Enterprise Architecture position is currently being advertised
Interim EA coordination:• Standards process, domain teams, and
Architecture Team coordination – Pat Forster• EA Initiatives, study teams, and Architecture
Review Board coordination– Jeff Swank
17
18
IT Plans &
Projects
Presented by:Jeff Swank
IT Policy & Planning
19
IT Plans & Projects
• Plans are due on the 15th
– 10 have been received
– Plans will be reviewed in the order
received
• EPM Website / Project Sharing System
20
IT Plans & Projects
• Project Ranking– 10-12 projects have been identified – Ranking worksheets are due August 1st
• 1 have been received
– SITAC will meet on Sept 8th to rank projects
– Project details from IT Plan, Ranking worksheet and a short presentation on each project will be presented to the SITAC
21
ConnectND
Report
Presented by:Dirk Huggett
IT Policy & Planning
22
ConnectND
• Higher Ed
– 7 of 11 Campuses will be fully implemented
by August
– UND, NDSU, MiSU & MiSU-B delayed due
to complexity of grants process
– Currently completing timeline for Grants
module
23
ConnectND
• State– Currently on track for a Sept 1
implementation of Financials– Recruit Workforce and Training
Administration now live– Benefits Administration to go live Aug 1– Draft of special review completed. To be
finalized and released this Friday.• Largest Risks: reports & queries, large complex
agencies
• State Project Admin – Jan Lund 8-5400
24
Project
Management
Services
Presented by:Vern Welder
Software Development
25
Project Management Service
• Is now an official ITD service
• In addition to: – IT Policy and Planning Division’s large
project oversight– Managing Software Development projects
• Software Development Division service
• Administered by our PMO
• 4 Project Managers on Staff
• Chargeable at Senior Developer rate ($56.25 / hour)
26
Project Management Service
• Projects in progress or completed– ConnectND – CJIS – Tax Dept - ZyTax– CJIS - LERMS– Job Service ND - EDMS
• Projects do not have to be IT related
• Does not have to be entire projects
• Request PM services via Software Development Service Request
27
Biennium Planning
• THE END of the biennium IS NEAR
• 11 months remain
• The last 4 – 6 months are always hectic
• Please request this biennium’s projects
early
28
Testing Tool Project
• Test Tool Definition
– Records test scripts
– Plays scripts back
– Allows changes to scripts
– Manages versions of files
• Enterprise Architecture project
• Phyllis Lasher (BND) is the EA sponsor
29
Testing Tool Project
• Project Goal
– Research and select an enterprise solution
that will provide more complete testing and
reduce the resource requirements as
software changes are deployed to
production thereby improving the quality of
the software being deployed
30
Testing Tool Project
• Project Tasks– EA subgroup discussed agency needs – Request For Proposal – Select an Enterprise solution that provides
a test management process and a test tool for the following environments
• HTML• PeopleSoft• Client/Server (desirable)
– Provide recommendation to Architecture Review Board
31
Testing Tool Project
• Schedule– July 9 – Issue RFP– July 19 – Deadline for Questions and Intent
to Bid– July 30 – RFP responses– August 13- Vendor Demonstrations and
Proof of Concept– August 27 – Complete Product Evaluation– September 1 – Recommendation to ARB
• Contact – Kyle Forster @ ITD 8-4323
32
Work Management System Update
• WMS is in production• Your Feedback is collected and compiled• Maintenance work on items that had to be
fixed is completed• Will start on enhancements in late July• WMS Governance/Maintenance group has
been established – Customers (DOT and DHS)– Various divisions of ITD
• More training sessions are planned • Current Work Systems end-of-life December
31,2004
33
Application Server Update
• SilverStream will be discontinued in
January, 2005
– 21 of the 25 SilverStream applications are
re-written
– 1 is in our work queue to be re-written
– 1 will not be re-written
– 1 is pending a ConnectND decision
– There may be one exception request
34
Application Server Update
• Conversion from Websphere v4.x to
v5.0 in late July
– Benefit of v5.0 is Web Services support
– Phased as applications are tested
• Minor application changes were required.
• After cutover please test as soon as you can
35
Mainframe
Migration
Study
Presented by:L. Dean Glatt
Computer Systems
36
Mainframe Study
Future State
– Enterprise Architecture
• Server and Operating Systems Domain Team
• Criticality of Agency Applications
– ITD
• Staffing Issues
• Software and Hardware Licensing Charges
37
Studies
• Multiple Platforms of differing criticality
• Gartner studies
Migration vs. Application Rewrite
• Growing Scarcity of skill sets
38
Choices
• Continue hosting the mainframe
internally
• Outsource
• Migrate to another platform
39
Mainframe Applications
• Essential to State Business
• Rewrites would take years and $M’s
• Migrations to other platforms different
than a rewrite
• Rewrite = brand new application
• Migration less costly than Rewrite
40
Realistic?
• The simple answer is “yes”
• Many details currently being studied
• Destination platforms likely will be
Windows, Linux and AIX
41
Telecommunication
Topics
Presented by:Jerry Fossum
Telecommunications
42
New Wiring Contract
• Awarded to Data Technologies
based out of Fargo
• Contract became effective July 1,
2004
43
Public Safety Radio
• Intent to award was issued to
Motorola
• Will begin formal contract
negotiations
44
Bismarck Fiber Update
• Expected completion of September 1– Bismarck State College– SW Medical Education Center– Burleigh County Extension Office– 2 Fire Stations– Waste Facility/Landfill– Banking & Finance– BCI – Bismarck – Redundant Fiber– BCI Task Force– Insurance Department– Law Enforcement Training Academy– Raymond J Bohn Armory– Retirement & Investment Office– Workers Comp at Interiors by France– Century High School– Bank of ND – Redundant Fiber
45
Bismarck Fiber Update Cont.
• Converting 4 sites from 100 Mbps
fiber connectivity to 1 Gbps fiber
connectivity
– Missouri Office Building
– State Pen
– State Lab/BCI
– DOT
46
VoIP Pilot Project with DOT
• Currently in the Planning Stage
– Testing Equipment
– Review of Connections
• The 1st two locations – Bismarck &
Fargo to be activated in late July
• Would like to add two sites a month
after that