presented by public resources management group, inc. recreation impact fee study prepared on october...

11
Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th , 2013

Upload: cleopatra-bennett

Post on 18-Jan-2018

219 views

Category:

Documents


0 download

DESCRIPTION

3 Comprehensive Plan Master Plan Funding / Fee Plan Recreation Planning Process City of Palm Coast Recreational Impact Fees

TRANSCRIPT

Page 1: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

Presented By

Public Resources Management Group, Inc.

RECREATION IMPACT FEE STUDYPrepared on October 10th, 2013

Page 2: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

2

The City of Palm Coast is a Growth-Oriented Community

2000 Population – 32,732 (Census)

2010 Population – 75,180 (Census)

Current Population Estimate (2012 BEBR) – 77,068

Projected Population at Buildout – 203,000

City of Palm CoastRecreational Impact Fees

Page 3: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

3

Comprehensive Plan

Master Plan

Funding / Fee Plan

Recreation Planning Process

City of Palm CoastRecreational Impact Fees

Page 4: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

4

Impact Fee Methods: Standards Vs. Needs (Improvements) Approach

Standards Approach:• Simple to Calculate• Based on established

standards or historical service levels

• Uses primarily for areas such as Roadways, Libraries, Police and Fire

Needs (Improvements) Approach• Forward Looking• Based on Capital Facility Plan• Typically used for Water,

Sewer, and Recreational Impact Fees

City of Palm CoastRecreational Impact Fees

Page 5: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

5

City of Palm CoastRecreational Impact Fees

Description Amount Basis

Existing City Investment in Recreational Facilities and Activities $13,895,201 Less Grant Funding (2,005,176)Net City Investment in Recreational Facilities and Activities $11,890,025

Future City Investment in Recreational Facilities and Activities (Capital Plan)Parks $12,450,000 Neighborhood Parks 34,500,000 Community Centers 13,900,000 Community Parks 32,812,500 Resource Based Parks (Passive Parks) 3,000,000 Trails and Trail Amenities 3,475,000 Contingency / Safety Improvements 750,000 Park Renovations 825000Special Use Facilities 30,735,000 Adjustments to Capital Plan 0

Total Future City Investment in Recreational Facilities and Activities $132,447,500

Total Costs of Existing and Future Investments in Recreational Facilities, Activities and Parklands $144,337,525Total City Buildout Population 203,000Total Cost to be Recovered Per Capita $711.02

Page 6: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

6

City of Palm CoastRecreational Impact Fees

DescriptionAmount Basis

Total Current Population 77,068

Total Buildout Population 203,000

Current Population as Percentage of Buildout Population 37.96%

Alternative Funding Credit Calculation Total Costs of Existing and Future Investments in Recreational Facilities,

Activities, etc. $144,337,525

Minus Net City Investment in Recreational Facilities and Activities (11,890,025)

Adjusted Costs to be Recovered $132,447,500

Adjusted Costs to be Recovered $132,447,500

Current Population as Percentage of Buildout 37.96%

Portion of Future Asset Costs to be Credited $50,277,071

Total City Buildout Population 203,000

Total Credit Per Capita $247.67

Page 7: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

7

City of Palm CoastRecreational Impact Fees

Description Impact Fee

Cost Per Capita $711.02

Alternative Funding Credit (247.67)

Cost to be Recovered per Capita $463.35

Persons per Household 2.51

Proposed Impact Fee $1,163.01

Page 8: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

8

City of Palm CoastRecreational Impact Fees

DescriptionAmount per

Dwelling Unit

Existing Recreation Impact Fee $1,264.06

Proposed Recreation Impact Fee $1,163.01

Fee Increase / (Decrease) ($101.05)

Page 9: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

9

City of Palm CoastRecreational Impact Fees

Page 10: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

10

Amendments to Park Impact Fee Ordinance Changes will incorporate the study and reflect the

calculation of Impact Fees using the new methodology.

Impact Fee Resolution Establish Impact Fee based on new methodology and

calculation

City of Palm CoastRecreational Impact Fees

Page 11: Presented By Public Resources Management Group, Inc. RECREATION IMPACT FEE STUDY Prepared on October 10 th, 2013

11

Next Steps November 5th City Council - 1ST Reading of Park Impact

Fee Ordinance

November 19th City Council:

2nd Reading of Park Impact Fee Ordinance

Resolution for Park Impact Fee

City of Palm CoastRecreational Impact Fees