prev-maintenance-.pptx

152
1 Preventive Maintenance

Upload: tahat22

Post on 18-Jan-2016

24 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Prev-Maintenance-.pptx

1

Preventive Maintenance

Page 2: Prev-Maintenance-.pptx

2

OBJECTIVES

Explain the importance of maintenance in production systems.

Describe the range of maintenance activities.

Discuss preventive maintenance and the key issues associated with it.

Discuss breakdown maintenance and the key issues associated with it.

State how the Pareto phenomenon pertains to maintenance discussions.

Page 3: Prev-Maintenance-.pptx

3

DEFINITION

WHAT IS MEANT BY THE TERM “MAINTENANCE” ?

Maintenance encompasses all those activities that maintain facilities & equipment in good working order so that a system can perform as intended.

Maintenance can also be termed as asset management system which keeps them in optimum operating condition.

Page 4: Prev-Maintenance-.pptx

4

APPROACH TO MAINTENANCE.

Maint.

Planned

Unplanned

PM

BM

CM

TBM

CBM

Daily ChecksPeriodic ChecksPeriodic InspectPeriodic Service

PM: Preventive MaintenanceTBM: Time Based MaintenanceCBM: Condition Based Maint.BM: Breakdown maintenanceCM: Corrective Maintenance

Visual

Instrument

NOTE:- Structured recording of all the activities is vital.

Page 5: Prev-Maintenance-.pptx

5

GOAL OF MAINTENANCE

The goal of maintenance is to keep the production system in good working order at minimal cost.

Decision makers have 2 basic options with respect to maintenance. They are: -BREAKDOWN MAINTENANCE.PREVENTIVE MAINTENANCE.

Page 6: Prev-Maintenance-.pptx

6

TYPES OF MAINTENANCE

BREAKDOWN MAINTAINANCE:- Real approach, Dealing with breakdowns or problems

when they occur… PREVENTIVE MAINTENANCE:-

Proactive approach; Reducing breakdowns through a

program of lubrication, adjustment, cleaning, inspection, and replacement of worn parts.

Page 7: Prev-Maintenance-.pptx

7

The best approach is to seek a balance between preventive maintenance and breakdown maintenance. The same concept applies to maintaining production systems.

The age and condition of facilities and equipment, the degree of technology involved,

The type of production process,

The decision of how much preventive maintenance is desirable.

Page 8: Prev-Maintenance-.pptx

8

PREVENTIVE MAINTENANCE

More and more organizations are taking a cue from the Japanese and transferring routine maintenance (e.g., cleaning, adjusting, inspecting) to the users of equipment, in an effort to give them a sense of responsibility and awareness of the equipment they use & cut down the abuse & misuse of the equipment.

Page 9: Prev-Maintenance-.pptx

9

PREVENTIVE MAINTENANCE

Preventive maintenance extends back to the design and selection stage of equipment and facilities.

Poor design can cause equipment to wear out at an early age or experience a much higher than expected breakdown rate.

Durability and ease of maintenance can have long term implications for preventive maintenance programs.

Training employees in proper operating procedures and in how to keep equipment in good operating order – and providing the incentive to do so – are also important.

Page 10: Prev-Maintenance-.pptx

10

PREVENTIVE MAINTENANCE

The goal of preventive maintenance Preventive maintenance is periodic. Preventive maintenance is generally

scheduled using some of the following contributions:- The result of planned inspections that

reveal a need for maintenance. According to the calendar (passage of

Time). After a predetermined no. of operating

hours.

Page 11: Prev-Maintenance-.pptx

11

PREDICTIVE MAINTENANCE

PREDICTIVE MAINTENANCE This is an attempt to determine

when best to perform preventive maintenance.

The better the predictions of failures are, the more effective preventive maintenance will be.

Page 12: Prev-Maintenance-.pptx

Preventive Maintenance

Page 13: Prev-Maintenance-.pptx

Preventative Maintenance

• What is a Preventive Maintenance?

– Preventive Maintenance is planned maintenance that is designed to improve Equipment life and avoid breakdowns on the plant.

Page 14: Prev-Maintenance-.pptx

SAP AG 1999

Preventive Maintenance: Basics

Basics

Task list

Single cycle plan

Strategy plan

Maintenance plan scheduling

Page 15: Prev-Maintenance-.pptx

SAP AG 1999

Time-based Performance-based Condition-based

Preventivemaintenance

Temperature

Thickness

PressurePressure

10102020

3030 4040 50506060

70708080

Pressure

2000

Types of Preventive Maintenance

Page 16: Prev-Maintenance-.pptx

Preventive Maintenance

• An Equipment can require maintenance activities to be performed based upon either time or a certain condition being met.

External visual inspection

1 month4Wks

Internal visual inspection

12 Wks

Check gear teeth for wear

52wks

Page 17: Prev-Maintenance-.pptx

SAP AG 2001

Preventive Maintenance: Phases and Roles

Maintenancetechnician

Maintenanceorder

Process maintenance orders4

Maintenanceplanner

Maintenanceplanner

Maintenancesupervisor

MaintenanceplannerTask list

Maintenanceplan

Schedule

Technicalcompletion

Create maintenance plans

Schedule maintenance plans

Technically completemaintenance orders5

2

3

1 Create task lists for differentobjects

Phase Contents Roles

Page 18: Prev-Maintenance-.pptx

SAP AG 1999

Preventive Maintenance: Task List

Basics

Task list

Single cycle plan

Strategy plan

Maintenance plan scheduling

Page 19: Prev-Maintenance-.pptx

SAP AG 1999

What?

Why?

For preventive maintenance (maintenance and inspection)

For routine maintenance (planned repairs)

For preventive maintenance (maintenance and inspection)

For routine maintenance (planned repairs)

Operations

Maintenance work centers

Material components

Production resources/tools

Maintenance packages

Task List

Page 20: Prev-Maintenance-.pptx

SAP AG 1999

Task list header

Operation 10Operation 20Operation 30

Planner group

Maintenancestrategy

3 months

3 months6 months

6 months12 months

12 months

Work center

Production resources/tools

Components

Maintenance Task Lists: Structure

Page 21: Prev-Maintenance-.pptx

Maintenance Strategy

• What is a Maintenance strategy?

– A Maintenance Strategy defines the frequency and scheduling data for Planned Maintenance activities.

Page 22: Prev-Maintenance-.pptx

Maintenance Strategy

4 Week 12 Weeks 24 Weeks

Time

Strategy

Package definition

2000

Scheduling parameters

What is a Maintenance Package?

Page 23: Prev-Maintenance-.pptx

Maintenance Package

3 months12

Weeks

Package number

Description

Cycle length

Unit of measurement

HierarchyOffset

• Maintenance packages define the frequency at which specific operations are executed. You can assign maintenance packages to the operations in a task list.

• Maintenance packages are part of a maintenance strategy.

Page 24: Prev-Maintenance-.pptx

12 Wks12 Wks

24 Wks

12 Wks

Strategy

12 wks12 wks

24 Wks

12 wks

Strategy

Same hierarchy levels

Different hierarchy levels

12 Wks

24 Wks

10

10

12 Wks

24 Wks

20

10 X

Maintenance Package Hierarchy

Page 25: Prev-Maintenance-.pptx

SAP AG 1999

Basics

Task list

Single cycle plan

Strategy plan

Maintenance plan scheduling

Preventive Maintenance: Single Cycle Plan

Page 26: Prev-Maintenance-.pptx

SAP AG 1999

I must perform thesame inspections atregular intervals.

1999

1997

Inspection of"Portable fire extinguishers"

every 2 years

94 96

98

2000

CHECKED

Single Cycle Plan: Business Process

Page 27: Prev-Maintenance-.pptx

Single Cycle Plan

• Simple and quick way to create a preventive or inspection plan.

• Includes only one cycle or frequency.• Can be either time or performance based.• All operations on the Task list will be

performed.• More than one Maintenance item can be

included.

What is a Maintenance Item -- ?

Page 28: Prev-Maintenance-.pptx

Maintenance Item• Every Maintenance plan will have at least one Maintenance item.• A Maintenance item can only belong to one maintenance plan.• The Maintenance item contains the following information:

– Description (Becomes the Maintenance order description)– Technical object– Task list– Planning Data

• Order or notification type• Planner group• Priority• Main work center• Maintenance activity type

– Object list

Page 29: Prev-Maintenance-.pptx

Maintenance Item (Cont.)

• A Maintenance item can contain more than one Technical object.• The Technical object can be an Equipment, Functional location or Assembly.• The Maintenance item description becomes the description of the Maintenance

notification or order.• For Maintenance items that are part of a Strategy based plan a Maintenance

strategy must be included within the item.• The Task list for this Maintenance item will also need to be linked to the same

Maintenance strategy.

Page 30: Prev-Maintenance-.pptx

Single Cycle Plan Steps

• Three steps in creating a single cycle plan.

Task List

Task List GroupPRTsComponents

Maintenance Item

Technical ObjectTask ListPlanning Data Maintenance Plan

Maintenance ItemScheduling Param.Cycle (Frequency)

Page 31: Prev-Maintenance-.pptx

SAP AG 2001

Scheduling Data and Maintenance Item

Responsibilities/Planning data

Referenceobject

Task list(optional)

3 months

Interval (cycle)

Maintenance item

Maintenance plan

Scheduling data

Maintenance item

Page 32: Prev-Maintenance-.pptx

SAP AG 2001

Using a Task List to Include an Operation List

Maintenance plan

Scheduling data

Maintenance item0010 Switch off

0020 Safety check

0030 External visual check

0040 Change seal

0050 Exchange H9 casing

0060 Check Z7 wire

Task list

Page 33: Prev-Maintenance-.pptx

Single Cycle Scheduling

Cycle Start

15.06.2004

15.03.2004

Cycle12 Weeks

Maintenance plan

Scheduling data

Maintenance item

Planned Date

15.09.2004

1

Page 34: Prev-Maintenance-.pptx

SAP AG 1999

Preventive Maintenance: Strategy Plan

Basics

Task list

Single cycle plan

Strategy plan

Maintenance plan scheduling

Page 35: Prev-Maintenance-.pptx

SAP AG 1999

Which parts must bemaintained at whichintervals?

External visual inspection

1 month1 month

Internal visual inspection

3 months3 months

Check gear teeth for wear

1 year1 year

Strategy Plan: Business Process

Page 36: Prev-Maintenance-.pptx

Maintenance Plan Steps

Task List

Task List GroupMaint. PackagesMaint. Strategy

Maintenance Item

Maint. StrategyTechnical ObjectTask List

Maintenance Plan

Maint. StrategyMaintenance ItemScheduling Param.

Strategy

Maintenance Packages

The Task List checks the Package to ensure the Strategy still exists.

The Item checks the Task List to make ensure that the same Strategy is used

The Plan checks the Item to make ensure that the same Strategy is used

Page 37: Prev-Maintenance-.pptx

SAP AG 1999

Task List and Maintenance Strategy

6 months6 months

3 months3 months

3 months3 months

6 months

3 months

Strategy

0010 Switch off

0020 Safety check

0030 External visual check

0040 Change seal

0050 Exchange H9 casing

0060 Check Z7 wire

Task list

Page 38: Prev-Maintenance-.pptx

SAP AG 1999

Creating a Time-Based Strategy Plan

3 months3 months

6 months

3 months

Strategy

0010 Switch off

0020 Safety check

0030 External visual check

0040 Change seal

0050 Exchange H9 casing

0060 Check Z7 wire

Task list

3 months3 months6 months

6 months

Maintenance plan

Scheduling data

Maintenance item

Page 39: Prev-Maintenance-.pptx

SAP AG 1999

Preventive Maintenance: Maintenance Plan Scheduling

Basics

Task list

Single cycle plan

Strategy plan

Maintenance plan scheduling

Page 40: Prev-Maintenance-.pptx

SAP AG 2001

ManualManualcallcall

NewNewstartstart

Start inStart incurrentcurrentcyclecycle

ScheduleSchedule

Last actual dateLast maintenancepackage

Last actual date

Nextplanned dateNext maintenancepackage

Cycle start

*

* Only for strategy plan

Schedule Maintenance Plans

Page 41: Prev-Maintenance-.pptx

SAP AG 2001

Cycle Start and Planned Date

Planned date

Order exactlyon planned date?

Cycle3 months

Cycle start

14.04. 2000

15.01.2000

Order 901760Maintenance plan

Scheduling data

Maintenance item

1

Page 42: Prev-Maintenance-.pptx

SAP AG 1999

Maintenance item report, sorted by equipment (no.)

1998 1999

Maintenance Scheduling Overview

... or as a listWith display variantsWith general list viewer

... as a graphicWith maintenance plan simulationWith/without details

Page 43: Prev-Maintenance-.pptx

43

Predictive Maintenance

Predictive Maintenance is one of the four tactical options available to ensure the reliability of any asset to ensure it fulfils its function and it focuses primarily on maintaining equipment based on its known condition. Each of these strategies: on-failure, fixed time, predictive and design out, has a place in an optimized maintenance plan, the distribution of the mix being dependent on many factors.

Page 44: Prev-Maintenance-.pptx

44

Predictive Maintenance

Predictive maintenance is often the most attractive concept, since action is only undertaken when knowledge of the asset indicates that failure or underperformance is imminent, making it a cost effective asset management option.

Many other benefits, some intangible such as the increased motivation of the workforce through increased competency, exist. Others include:

Equipment may be shut down before severe damage occurs or can be run to failure if required.

Production can be modified to extend the asset's life i.e. until the next planned shutdown.

Required maintenance work can be planned

All of the above lead to increased safety, plant output and availability and lead to improvements in final product quality.

Page 45: Prev-Maintenance-.pptx

45

Predictive maintenance is a process that requires clear roles and responsibilities. As such we develop company appropriate predictive maintenance processes, supported by definitions of responsibilities, and communication paths, which integrate into the Reliability effort as a whole.

Condition monitoring facilitates Predictive Maintenance.

Condition monitoring is a knowledge-based activity, so for it to be successful and sustainable, it requires comprehensive skills training. Any successful predictive maintenance program, not only has a technology element, but requires a measurement system that continuously accounts for the benefits.

Predictive Maintenance

Page 46: Prev-Maintenance-.pptx

46

Asset Performance Troubleshooting

Often it is a couple of poor performing assets with a chronic repeated failure condition that absorb the majority of the maintenance budget. Some commentators state that approximately 80% of a typical maintenance budget is stored away for chronic failures, making these the most cost depletive of all maintenance expenditures.

The following methodologies are key in any multi-technology condition monitoring program :

Root Cause Failure Analysis

Tribology And Lubrication Engineering Services

Specialist Condition Monitoring Services

Page 47: Prev-Maintenance-.pptx

47

ROOT CAUSE FAILURE ANALYSIS

Root Cause Failure Analysis (RCFA) is both a process and a set of technical skills, which in combination find out why a particular failure or problem exists and sets in place a set of defense actions correcting those causes.

Typically, when assets fail most organizations have always found some understanding and rational leading to an explanation as to why it broke. But root cause failure analysis takes you beyond that to the latent roots, which are the management system weaknesses. Once you've found these, you have the means to solve many other potential problems that haven't yet occurred.

Page 48: Prev-Maintenance-.pptx

48

Tribology And Lubrication

Tribology is the study of wear and lubrication.Tribology as it is estimated that component wear and lubrication problems are responsible for at least 70 % of mechanical failures.

Page 49: Prev-Maintenance-.pptx

49

Tribology And Lubrication

Page 50: Prev-Maintenance-.pptx

50

Condition Monitoring

In industry, condition monitoring is the measurement of parameters which may indicate a fault condition either by an increase or decrease in overall measured value or by some other change to a characteristic value.

When used as part of a pro-active maintenance plan, the use of condition monitoring enables the operation of a predictive maintenance policy and provides major improvements in productivity.

Condition monitoring depends on selecting the right mix of parameters that match expected faults and using the correct measurement technique, location interval and processing, it is also important to record enough information in order to be able to carry out monitoring and diagnosis.

Page 51: Prev-Maintenance-.pptx

51

Condition Monitoring

Considerations include: • Type of measurement

• Measurement interval

• Accuracy of measurement

• Repeatability Condition monitoring falls into two distinct classes: Monitoring which can be carried out without interruption to

the operation of the machine

Monitoring which requires the shutdown of the unit, or at least the releases of the machine from its prime duty

The range of methods in use is very wide, from simple techniques such as visual surface inspections to more complicated procedures like spectral vibration analysis.

Page 52: Prev-Maintenance-.pptx

52

PREVENTIVE MAINTENANCE

TOTAL PREVENTIVE MAINTENANCE JIT approach where workers perform

preventive maintenance on the machines they operate.

This approach is consistent with JIT systems and lean production, where employees are give greater responsibility for quality, productivity and the general functioning of the system.

Page 53: Prev-Maintenance-.pptx

53

The TPM Concept

Develop a Company-wide philosophy to maximize the effectiveness of production systems.

Build an organization that prevents every type of loss zero accidents zero defects zero failures

Involve all departments in TPM implementation.

Involve everyone from top management to shop-floor operators

Use small groups (teams) to make improvements.

Page 54: Prev-Maintenance-.pptx

54

The “Total” in TPM

Total effectiveness: pursuit of economic efficiency and profitability

Total PM: establishing a maintenance plan for the life of

the equipment - preventative maintenance - improved maintainability

Total Participation: autonomous maintenance by operators and

team based approach to problem solving

Page 55: Prev-Maintenance-.pptx

55

Before TPM Implementation

Maintenance OperationsEngineering

Page 56: Prev-Maintenance-.pptx

56

After TPM Implementation

WasteDowntime

Defects

The Common Enemies

A Team EffortOperations + Engineering + Maintenance

Page 57: Prev-Maintenance-.pptx

57

Before TPM Implementation: Barriers

Operations

Maintenance

Engineering

Page 58: Prev-Maintenance-.pptx

58

TPM Builds Bridges

Operations

Maintenance

Engineering

Page 59: Prev-Maintenance-.pptx

59

The TPM Prerequisite

Only by adopting a proactive approachand putting in the time, effort, and resources

required can TPM be profitable for anOrganization

Page 60: Prev-Maintenance-.pptx

60

A Model for TPM Development

Formal TPM Announcement

TPM Awareness Education

Form TPM Steering Group

Establish TPM Goals

Prepare Implementation Plan

Phase I

Preparation

Page 61: Prev-Maintenance-.pptx

61

The TPM Development Model Continued

Conduct Focused Improvement Activities

Establish an Autonomous Maintenance Program

Implement a Planned Maintenance Program

Conduct Operation and Maintenance Skill Training

Build an Effective Administrative Support System

Phase II

Implementation

Page 62: Prev-Maintenance-.pptx

62

Core TPM Activities Focused Improvement Projects Autonomous Maintenance Planned (Preventive) Maintenance Education and Training Early Management (Equipment Design and

Installation) Quality Maintenance Administrative and Support Activities Safety and Environmental Management Diagnostic and Predictive Maintenance

Page 63: Prev-Maintenance-.pptx

63

The Major Plant Losses

Equipment Failures Process and Equipment Set-ups And

Adjustments Idling and minor stoppages Reduced Processing Speed Quality Defects Reduced Yield

Page 64: Prev-Maintenance-.pptx

64

Ultimate Improvement Goals for Chronic Losses

Type of Loss Goal Explanation1. Equipment Failures 0 Reduce to zero for all equipment

2. Setup and Adjustments minimize Continuous effort to reduce setup times

3. Idling and minor stops 0 Reduce to zero for all equipment

4. Reduced ProcessingSpeed

0 Bring operating speed to design speed;then improve speed beyond design level

5. Quality Defects 0 Small levels might be acceptable (6-sigma)

6. Yield Losses minimize

Page 65: Prev-Maintenance-.pptx

65

Measurement

Measurement Is Necessary for Improvement.

People Do How They Are Measured!

Page 66: Prev-Maintenance-.pptx

66

Basic TPM Outcome Measures

Productivity

Units per labor hourValue added per person

Throughput Downtime

Number of Breakdowns

Quality

Product DefectsWarranty Costs

Customer Satis. Index Re-worked units

Scrap/Waste

Costs

Labor CostsMaintenance Costs

Energy Costs

Delivery

On-time shipments

Safety

Lost time AccidentsIncidents

Near Misses

Employee Satisfaction

Number of Improvement IdeasNumber of Teams

Employee Satisfaction Index

Page 67: Prev-Maintenance-.pptx

67

Measuring Effectiveness

Overall Equipment Effectiveness --

OEE

OEE = Availability x Performance Rate x Quality Rate

OEE: A Measure of the Percentage of Time that the Equipmentis Adding Value

Page 68: Prev-Maintenance-.pptx

68

Calculating OEE

OEE = A x P x Qwhere:

A (Availability) = planned time - downtimeplanned time

P (Performance rate) = (standard time/unit)(units produced) Operating time

Operating Time = (planned time - downtime)

Q (quality rate) = (total production) - (number of defectives)total production

Page 69: Prev-Maintenance-.pptx

69

OEE Example

The Plant operates 1,440 minutes per day (3 shifts) Downtime averages 120 minutes per day. Daily production averages 900 units with a 20 % defect rate. The standard time per unit is .8

minutes. (Assume that A, P, and Q are equally weighted.)

Compute OEE

Page 70: Prev-Maintenance-.pptx

70

Computing OEEWeightings on A, P, and Q

In many instances Availability, Performance rate and Quality rate arenot considered to be equal in importance. Instead they are weighteddifferently. For example:

kA = .3 kP = .2 kQ = .5

OEE = A.3 x P.2 x Q.5

Compute OEE using these weights.

Page 71: Prev-Maintenance-.pptx

71

OEE Component Targets

Availability (A) > .90 Performance Rate (P) > .95 Quality Rate (Q) > .99

Availability (A) > .90 kA

Performance Rate (P) > .95 kP

Quality Rate (Q) > .99 kQ

unweighted targets

weighted targets

}}

Page 72: Prev-Maintenance-.pptx

72

OEE ExamplesSource: Japan Institute of Planned

Maintenance

Criteria AutomatedMachinery

AutomaticAssemblers

AutomaticPackers

1. Overall Effectivess

2. Availability

3. Performance

4. Operating Speed Rate

5. Net Operating Rate

51.3 - 78.4

95-98

54-80

90-100

60-80

38.0 - 80.7

95

40-85

100

40-85

72.0

90

80

100

80

Remarks: 20-40% of lossesdue to idling andminor stoppages

15-60% oflosses due to

idling and minorstoppages

20% of lossesdue to idling andminor stoppages

Page 73: Prev-Maintenance-.pptx

73

Overall Equipment Effectiveness-- OEE

OEE Is OEE Is Not

• A Measure of TPM Progress

• Manufacturing Contribution to Quality Improvement

• A Method to Identify Opportunities for Improvement

• Synonymous with TPM

• To be used to compare facilities

• The same as utilization

• Easy to calculate

Page 74: Prev-Maintenance-.pptx

MB 533 Shannon/Fry October, 200074

Chronic and Sporadic Losses

Chronic Losses: Losses that occur repeatedly within some range of distribution

Sporadic Losses: Sudden occurrences that go beyond the normal range

Sporadic Loss

Chronic Loss

Defect rate

Time

OptimalCondition

Page 75: Prev-Maintenance-.pptx

75

Chronic and Sporadic Losses

Sporadic Losses Chronic Losses

Latency

Causation

Types ofAction

EconomicImpact

Conspicuous Hidden

Cause-and-effect Often unclear - rarelyeasy to determine a single cause

Direct Fixes can May take many triesbe made

Can be very costly Cumulative effect cancan be very costly

Page 76: Prev-Maintenance-.pptx

76

How Chronic Losses are Reduced

Increasing Equipment Reliability

Restoring Equipment to its Original Condition

Identify and Establish Optimal Operating Conditions

Eliminating Small Defects that are Often Overlooked

Page 77: Prev-Maintenance-.pptx

77

Reliability Issues

Intrinsic Reliability Operational Reliability

Design Reliability

Manufacturing Reliability

Installation Reliability

Operation Reliability

Maintenance Reliability

Based on Equipment Design Based on Use (conditions)

Page 78: Prev-Maintenance-.pptx

78

Learning to Use Equipment Fully and Make Basic Improvement

Study ofEquipment

Usage

Techniquesfor Making Useof Equipment

Techniquesfor Managing

Equipment

Restoration

Search forOptimal Conditions

Eliminate MinorEquipment Defects

Physical AnalysisP-M Analysis

Eliminate TamperingTrial-and-Error

Gather Operators’Experiences

Design Reliability

FabricationReliability

InstallationReliability

OperationReliability

MaintenanceReliability

Intr

insi

cR

elia

bil

ity

Op

erat

ion

alR

elia

bil

ity

Page 79: Prev-Maintenance-.pptx

79

P-M AnalysisP Phenomena- physical-problem—M machinery-manpower-material

All pertinent factors in a chronic loss are efficientlyidentified and eliminated.

Clarify the Problem

Conduct a PhysicalAnalysis of the

Problem

List Every ConditionPotentially Related

to the Problem

Evaluate Equipment,Materials, and

Methods

Plan the Investigation

InvestigateMalfunctions

FormulateImprovement

Plans

Page 80: Prev-Maintenance-.pptx

80

Raising Employee Skills Through TPMA TPM Goal is to Improve Employee Skill

Levels

Attention concentration, discernment

Judgment logical thinking, make sound decisions

Take Correct Action and provide Appropriate Treatment Prompt action, pride of ownership

Preventative understanding of equipment, measurement

Prediction Skills subtle signs, knowledge of equipment

Page 81: Prev-Maintenance-.pptx

81

Focused Improvement

Focused Improvement is an active priorityof any TPM program - It begins simultaneously

with the start of TPM

“Focused Improvement includes all activities that maximize the overall

effectiveness of equipment, processes, and plants throughuncompromising elimination of losses and improvement of

performance.”

Page 82: Prev-Maintenance-.pptx

82

Focused Improvement

Select a Project

Form a Project Team

Register the Project

Follow the P-M AnalysisCycle

A High PriorityDoableShort-term

4-7 peopleCross-functionalEmpowered

Establish StatusAccess to ResourcesCommitment ongoing training and

educationMeasure Progress and results

Page 83: Prev-Maintenance-.pptx

83

Preparation by Improvement TeamsTeams should prepare in the

following ways.

• Understand the philosophy of focused improvement• Understand the significance of losses and the rationale of

improving overall effectiveness• Understand the production process well• Gather data on failures, trouble, and losses and plot

over time• Clarify the basic conditions necessary to assure proper

functioningof equipment and define what factors contribute to its optimalstate• Understand the necessary techniques for analyzing and

reducingfailures and losses

Page 84: Prev-Maintenance-.pptx

84

Focused ImprovementStep-by-Step Procedure

Activity/Step Detailed Outline

Step 0: Select the Project Select and Register the ProjectForm the Project TeamPlan Activities

Step 1: Understand Situation Identify bottleneck processesMeasure failures, defects, and other

lossesUse baseline to set targets

Step 2: Expose and Eliminate Carefully Expose all Abnormalities Abnormalities Restore deterioration and correct

minor flawsEstablish basic equipment conditions

Step 3: Analyze Causes Stratify and Analyze CausesApply analytical techniques (P-M Analysis)Conduct experiments

Page 85: Prev-Maintenance-.pptx

85

Focused ImprovementStep-by-Step Procedure (continued)

Activity/Step Detailed Outline

Step 4: Plan Improvement Draft Improvement ProposalsCompare cost-effectiveness of alternative proposalsList disadvantages of each alternative

Step 5: Implement Improvement Carry out improvement plan

Provide instruction related to implemented changes

Step 6: Check Results Evaluate improvement over time and the project proceedsCheck whether targets have been achievedIf not, go to step 3 and continue

Step 7: Consolidate Gains Draw up control standards to sustain resultsFormulate work standardsFeed information back into themaintenance prevention program

Page 86: Prev-Maintenance-.pptx

86

Analytical Techniques for Improvement

P-M Analysis Ask Why 5 times Fault tree Analysis (FTA) Failure Mode and Effect Analysis Industrial Engineering Value Analysis Seven Basic Tools of Quality The “New Seven” Tools of Quality

Page 87: Prev-Maintenance-.pptx

87

Autonomous MaintenanceMaintenance Performed By the Equipment

Operators

One of the most important basic buildingblocks in any TPM Program

Goals of Autonomous Maintenance:• Prevent equipment deterioration through

correct operation and daily checks• Bring equipment to its ideal state through

restoration and proper management• Establish the basic conditions needed to keep

equipment well-maintained

Page 88: Prev-Maintenance-.pptx

88

Autonomous MaintenanceStep-by-Step Implementation

Activity/Step Detailed Outline

Step 1: Perform Initial Cleaning Eliminate Dust, Dirt, and Grime Expose any irregularities Correct minor flaws

Step 2: Eliminate Sources of Contamination Reduce housekeeping by eliminating sources of dirt . Improve access to difficult areas

Step 3: Establish cleaning and checking Formulate standards for cleaning, standards lubricating, and tightening with minimal

time and effort. Improve efficiency of checking gauges and visual display controls

Step 4: Conduct General Equipment Provide inspection skills training Inspections Modify equipment to facilitate inspection

Chart inspection results - quantify when Possible.

Page 89: Prev-Maintenance-.pptx

89

Autonomous MaintenanceStep-by-Step Implementation (continued)

Activity/Step Detailed Outline

Step 5: Perform General Process Train and Educate Operators to Inspections achieve process-competent operators

Prevent inspection duplications and omissions by incorporating individual equipment inspection standards into

process or area inspection plans.

Step 6: Do Systematic Autonomous Establish clear procedures for auto- Maintenance nomous maintenance

Reduce Setup ProceduresEstablish system for self-management

for spares, tools, data, etc.

Step 7: Practice Full Self-Management Keep accurate maintenance recordsPerform proper data analysisTake appropriate action

Page 90: Prev-Maintenance-.pptx

90

Necessary Accomplishments forProcess-Competent Operators

Level 1: Understand Process Performance and

Function Operates Process Correctly

Level 2: Understands the properties of the materials

handled Performs correct adjustment and settings

Level 3: Detects abnormalities promptly Takes emergency action against abnormalities

Level 4: Recognizes sign of abnormality Deal with abnormalities correctly Performs periodic overhaul checking and parts

replacement

Page 91: Prev-Maintenance-.pptx

91

Keys to Successful Autonomous Maintenance

Introductory Education and Training TPM Objectives, TPM Benefits, TPM Overview

Cooperation Between Departments and Shifts Consensus agreement on how to support TPM

and AM Group Activities

small groups with leadership from shop floor to management

AM is not voluntary mandatory and necessary management must provide leadership and

support

Page 92: Prev-Maintenance-.pptx

92

Keys to Successful AM (continued)

Practice practical application versus conceptual understanding

Progressive Education and Training gradual skill development - step-by-step - as needed

Aim for Measurable Results clear, appropriate measures (and goals)

Operators Should Determine Standards to Follow operators set standards and criteria for maintenance

consistent with organizational objectives Management Should Audit the AM Progress

provide guidance, support and critique

Page 93: Prev-Maintenance-.pptx

93

Keys to Successful AM (continued)

Use Model Projects Use as examples for the rest of the

organization Correct Equipment Problems Promptly

Maintenance department must react quickly to fix problems uncovered by AM activities - will require commitment and appropriate staffing

Take Time to Perfect AM Don’t rush the process - make sure the

skills are there

Page 94: Prev-Maintenance-.pptx

94

Measures of Preventive Maintenance Results

Downtime Trend Operating Rate Failure Frequency Failure Severity (length of failure downtime) Maintenance Time per Incident Quality Defect Rate Failure Costs Emergency Repair Time Ratio of Maintenance Cost to Unit

Production Cost

Page 95: Prev-Maintenance-.pptx

95

IMPLEMENTATION SUMMARY OF PM

Step 1: Evaluate Equipment and Understand Current Conditions.

Step 2: Restore Deterioration and Correct Weaknesses.

Step 3: Build an Appropriate Information System.

Step 4: Build a Periodic Maintenance System Step 5: Build a Predictive Maintenance

System. Step 6: Evaluate the Preventive Maintenance

System.

Like everything associated with TPM, successful implementation of apreventive maintenance system will take time and support.

Page 96: Prev-Maintenance-.pptx

96

BREAKDOWN MAINTENANCE

The risk of a breakdown can be greatly reduced by an effective preventive maintenance program.

The major approaches used to deal with breakdowns are:- Standby or backup equipment can be quickly

pressed into service. Inventories of spare parts. Operators who are able to perform at least

minor repairs on their equipment. Repair people who are well trained and readily

available to diagnose and correct problems with equipment.

Page 97: Prev-Maintenance-.pptx

97

BREAKDOWN MAINTENANCE

Breakdown programs are most effective when they take into account the degree of importance a piece of equipment has in the production system

The ability of the system to do without it for a period of time.

Page 98: Prev-Maintenance-.pptx

98

Review of Equipment Maintenance

The Review of Equipment Maintenance (REM) is an incremental approach, designed to deliver financially driven results at minimum cost and time. It provides optimum results when a review of equipment maintenance is required to ensure that:

The most effective maintenance plan is adopted

Preventive, scheduled, design put and on-failure maintenance are integrated into a cohesive strategy

The maintenance plan needs to respond to changes in plant operation

The review may also be required to introduce a new technique, such as condition monitoring, or to adjust changes in maintenance resources. Typically REM requires only 30-50% of the resource input that would be required for RCM, while achieving similar results.

Page 99: Prev-Maintenance-.pptx

99

Review of Equipment Maintenance

REM focuses primarily on maintenance strategy arising from business drivers, such as demand and operating patterns and can be considered in two major stages:

Reliability and criticality analysis

Maintenance review

Page 100: Prev-Maintenance-.pptx

100

The output of a REM study is an optimized maintenance plan, where the appropriate risk based defence of the asset is defined. This takes in

to account the goals of the organisation, the criticality of the

asset, the resources available, and the level of technology employed by the organization. This is a working document, which can be translated

into the physical reality of conducting operational maintenance.

Review of Equipment Maintenance

Page 101: Prev-Maintenance-.pptx

101

PARETO DIAGRAMS

Pareto diagram is an important quality tool used in prioritizing & deciding the course of action in maintenance management.

Of all the problems that occur, only a few are quite frequent/costly.

The others seldom occur/cost less. The problems are grouped and

labeled as vital few and trivial many.

Page 102: Prev-Maintenance-.pptx

102

PARETO DIAGRAMS

Pareto principle lends support to the 80/20 rule.

Pareto diagrams help quickly identify the critical areas for management’s attention.

Page 103: Prev-Maintenance-.pptx

103

STEPS FOR CONSTRUCTING PARETO DIAGRAMS

STEP 1Decide on data categorization system by problem type, type of conformity (critical, major, minor) or whatever else seems appropriate.

STEP 2 Determine how relative importance is to be judged i.e., whether it should be based on cost or frequency of occurrence.

STEP 3 Rank the categories from most important to least important.

STEP 4 Compute the cumulative frequency of the data categories

in their chosen order. STEP 5

Plot a bar graph showing the relative problem of each problem area in descending order.

Page 104: Prev-Maintenance-.pptx

104

STEP 6

Identify the vital few that deserve immediate attention.

STEPS FOR CONSTRUCTING PARETO DIAGRAMS

Page 105: Prev-Maintenance-.pptx

105

PARETO DIAGRAMS

PROBLEM TYPE

DESCRIPTION % OF OCCURENCE

ANNUAL COST (IN

$1000)

CUMMALITIVE % OF

OCCURENCE

A Substandard quality of raw material

40 20 40

B Improper setting of machine

20 6 60

C Inadequate operator training

14 3 74

D Poor storage of finished parts

10 2 84

E Drop in hydraulic pressure impresses

8 2 92

F Cutter not sharp 5 1.5 97

G Electrical breakdowns 3 1.8 100

Page 106: Prev-Maintenance-.pptx

106

PARETO DIAGRAMS

A B C D E F GPROBLEM TYPE

% OF

TOTAL

100

80

60

40

20

0

40.0

60.0

74.0

84.0

92.097.0

100.0

Page 107: Prev-Maintenance-.pptx

MAINTENANCEMANAGEMENT

SYSTEM

Page 108: Prev-Maintenance-.pptx

ContentIntroductionIntroduction to Life Cycle CostObjectives of Maintenance and Maintenance CostMaintenance DefinitionHow to get unplanned repair jobs plannedMaintenance ProceduresFailure DevelopmentTotal Productivity MaintenanceMaintenance Management Systems

Page 109: Prev-Maintenance-.pptx

IntroductionModern maintenance management is not to repair broken equipment rapidly. Modern maintenance management is to keep the equipment running at high capacity and produce quality products at lowest cost possible.

Page 110: Prev-Maintenance-.pptx

Introduction contd…Maintenance, then and nowMany years ago, the manufacturing and production work was

done with relatively simple technical equipment and the involvement of more manpower.

Maintenance was of course simple and impact to certain extent to the function of machines.

During the industrialization, production equipment has been more developed. In connection with the high technical development the impact of productivity and quality has moved from man to machine.

The importance of maintenance has considerably increased.

Page 111: Prev-Maintenance-.pptx

Introduction contd…There are many reasons why maintenance is becoming more and

more important. In developing countries , where many old machines are operating, the spare part problem are arising. Some times it is difficult to find spare parts for equipment and if it is possible to find them, they are usually very expensive and must be paid on foreign currency.

Due to long lead times of supply of spares, it is common that the spare part inventory is growing bigger than necessary. A very essential part in maintenance management is developing countries to reduce the need of spare parts, as well as to maintain the minimum level of shock to save foreign currency, but still keeping the productivity high.

Page 112: Prev-Maintenance-.pptx

Introduction to Life Cycle Cost(LCC)

Maintenance has to be taken into consideration in very early stage of work of procuring new equipment to ensure a good and cheap operation.High quality equipment will give high reliability and maintainability which secure high productivity and equipment efficiency.The lifetime of the equipment can be spilt up in six phases1. Idea2. Specification3. Design4. Procurement(Manufacturing)5. Operation6. Windup

Page 113: Prev-Maintenance-.pptx

LCC ContdBath Tub CurveThe bath tub curve describes the cost of equipment over its lifespan. From commissioning to winding up.

Cost

100% Life Time

Page 114: Prev-Maintenance-.pptx

LCC – What Dose It Stand For?

LCC – Life Cycle Cost – is commonly understood to be the customer’s total cost and other sacrifice during the actual life time of the product. Hence LCC includes the acquisition cost as well as all future costs for operation and support of the product until it is finally discard.

Page 115: Prev-Maintenance-.pptx

LCC Is Used For….

Comparison of alternative products.

Improvements of products.

Adaptation of the maintenance and support organization.

Page 116: Prev-Maintenance-.pptx

Objectives of Maintenance and Maintenance Cost

Objectives of MaintenanceDuring the years the maintenance function has not been seen as a condition for production output. The previous approach has been that maintenance is the necessary evil, one among the cost generators in the organization. Very often the maintenance strategy in plants has been to reduce the maintenance cost as much as possible without thinking of the consequences.Objective of the maintenance is , as priority one , to create an availability performance which is suitable for production demands in the organization. No mechanized/atomized company has yet succeeded to produce with stopped equipment. Production buy availability performance from maintenance.

Page 117: Prev-Maintenance-.pptx

Contd…1.

Keep up the planned availability performance

2.At the lowest cost

Above allWithin the safety prescriptions

Page 118: Prev-Maintenance-.pptx

Maintenance CostAll enterprises and organizations are interested in lowering maintenance costs. A very common delusion is that

THE PRODUCT GIVES THE INCOME

MAINTENANCE COSTS MONEY

Page 119: Prev-Maintenance-.pptx

Contd…MAINTENANCE WICH IS NOT CARRIED OUT ,WILL COST EVEN

MORE THAN MONEY !!!!!!

Page 120: Prev-Maintenance-.pptx

Contd…There are two ways of managing the maintenance costs

Cost or Result Controlled

Maintenance

Page 121: Prev-Maintenance-.pptx

Contd… The cost controlled maintenance is not considered as modern maintenance

management, The reason why maintenance has been treated as a cost controlled activity, Is often that engineers and technical staff have had some dilemma to measure the results of investments in maintenance in total economical terms. It is simple to find the direct cost for maintenance but it could be difficult to see the results.

The upper priority in the objectives of maintenance is to “keep up planned availability performance at the lowest cost possible” . This means that the long term results are important. The maintenance cost must be put in relationship with overall results achieved by maintenance in production facility.

Page 122: Prev-Maintenance-.pptx

PRODUCTION LOSSES

The Hidden Possibility

LOST MARKET

WORKENVIORME

NT

CAPACITYLOSSES

ENERGYLOSSES

QUALITYLOSSES

CAPITALCOSTS

INCREASED

INVESTMENT

MAINTENANCE

Page 123: Prev-Maintenance-.pptx

Indirect & Direct MaintenanceCosts

The maintenance cost can be split up in two different categories.

Direct maintenance costs -

Indirect maintenance costs -

The costs are directly related to the performance of the maintenance works

Losses due to maintenance

Page 124: Prev-Maintenance-.pptx

Contd…Direct maintenance costs• Wages & Salaries• Material Costs• Administration Costs• Costs for training• Spare parts costs• Contracted work forces• Modification Costs

Indirect Costs• Loss of revenue or other losses as a result of interruption

to production as a result of maintenance.

Page 125: Prev-Maintenance-.pptx

Measurement of Maintenance Efficiency

Many times there are needs to measure the maintenance efficiency. However, maintenance can not be measured by the cost it creates. There must be an connection to the production out put some way. It is naturally impossible to determine anything about the size of the direct costs. One method to control the direct maintenance is to use the PM-factor.”P” stands for prime product produce and “M” stands for maintenance cost. When using the PM-factor, the result of the maintenance impact on the production is measured. How many products are produced per a 1000 units of “maintenance money”.

PM – Factor = X Prime Production

Maintenance Cost

1000

Page 126: Prev-Maintenance-.pptx

Availability Performance& Productivity

AVAILABILITY PERFORMANCE

The ability of equipment to function properly,Despite occurrence of failures, disturbances and

Limitations in the maintenance resources.

Page 127: Prev-Maintenance-.pptx

Contd…

Availability performance can be divided in to tree parts:

Reliability Performance

Maintenance Support Performance

Maintainability Performance

Page 128: Prev-Maintenance-.pptx

Reliability Performance

The ability of an item, under statedConditions of use, to perform a requiredFunction under stated conditions for a

stated period of time.

Page 129: Prev-Maintenance-.pptx

Maintenance Support Performance

The ability of a maintenance organization,Under stated condition, to provide upon

Demand the resources required toMaintain an equipment.

Page 130: Prev-Maintenance-.pptx

Maintainability Performance

The ability of an equipment, under started conditions of use, To be retained or

restored to state in which it can perform a required function, when maintenance is performed under stated conditions and using stated procedure and resources.

Page 131: Prev-Maintenance-.pptx

Maintenance DefinitionIn order to set up maintenance strategy for an enterprise, it is necessary for every body in a company to understand the maintenance concept and speak the same language.

MAINTENANCE

The term maintenance covers allActivities undertaken to keep equipment in a

Particular condition or returnIt to such condition

Page 132: Prev-Maintenance-.pptx

Contd…The term maintenance consists of three main parts

Corrective maintenance

Preventive maintenance

Improvement maintenance

Page 133: Prev-Maintenance-.pptx

CORRECTIVE MAINTENANCE (CM)

Corrective maintenance covers allMaintenance which is carried out inOrder to correct (repair) a fault in

equipment

Page 134: Prev-Maintenance-.pptx

WHAT IS FALIURE ?

Digress of demands of a certainquality

Page 135: Prev-Maintenance-.pptx

Planned & unplanned corrective maintenanceCorrective maintenance is divided in

CORRECTIVEMAINTERANCE

UNPLANNED PLANNED

Break DownEmergency Repairs

UrgentNot possible to ControlYou are controlled by

the equipment

Planned MaintenancePrepared ProperlyPossible to Control

You control the Equipment

Page 136: Prev-Maintenance-.pptx

PREVENTIVE MAINTERANCE (PM)

Preventive maintenance covers allProgrammed maintenance which is carried out in order to prevent theOccurrence of failures before they

Develop to a breakdown orInterruption in production.

Page 137: Prev-Maintenance-.pptx

Preventive Maintenance is Divided In

INDIRECT

Condition BasedMaintenance (CBM)

Detection of failuresBefore break down

PREVENTIVE MAINTENANCE

Page 138: Prev-Maintenance-.pptx

Indirect Maintenance

Subjective

Using human sensesLook , feel , listen , smell

, taste

INDIRECT PM

Page 139: Prev-Maintenance-.pptx

IMPROVEMENT MAINTENANCE (IM)Improvement maintenance is used

When to modify the equipment so theCondition improves. Improvement

Maintenance includes activities which are carried out once. The objectives of

improvement maintenance are toDesign out the failure i.e. the failureWill never occur again or extend the

life time of parts.

Page 140: Prev-Maintenance-.pptx

How to Get Unplanned Repair Jobs Planned

One of the objectives of the maintenance job is to get them plannedThis gives increased availability performance and lower direct maintenance costs and a lot of other advantages. The load on the maintenance department will for instance be lower and the quality of the jobs higher.• Use of condition monitoring Through condition monitoring the failure development and it is therefore possible to plane the forthcoming jobs before a break down occurs. By condition monitoring the unplanned jobs are transferred to planned job.

• Planned maintenance resulting in lower costs for maintenance and lesser down time.

Page 141: Prev-Maintenance-.pptx

MAINTENANCE

CORRECTIVEMAINTENANCE

UNPLANNED

-EXPENCIVE MAINTENANCE

-LOW AVAILABILITY

PLANNED-

CONTROLLED

-REDUCED COST FOR

MAINTENANCE-INCREASEDAVAILABILITY

PREVENTIVE MAINTENANCE

INDIRECT CONDITION

MONITORING

DIRECT-CLEANING

-LUBRICATING-

PROGRAMMED

REPLACEMENT AND

REPAIRS

DECREASED-CORRECTIVE MAINTENANCE

INCREASED-AVAILABILITY

Preventive Maintenance-Reduce number of break downs & urgent repairs-More planning and control of corrective maintenance

Result-Increased availability performance & efficiency-Decreased cost of maintenance

Page 142: Prev-Maintenance-.pptx

Proper PlanningResults in the correct maintenance work is carried out

At the right time In the right way By the right professional With the right spare parts

“Real maintenance management is impossible without condition based preventive maintenance”

Page 143: Prev-Maintenance-.pptx

Maintenance ProceduresWhen a maintenance strategy is going to be formulated, there are many maintenance procedures that could be chosen, From sophisticated procedures to low level procedures.

Operate to break down (unplanned corrective maintenance), O.T.B.D

Fixed-time maintenance, F.T.MCondition-based maintenance, C.B.MDesign out maintenance, D.O.MLife-time extension, L.T.ERedundancy, RED

Page 144: Prev-Maintenance-.pptx

Failure Development INDIVIDUAL LIFE TIME

Machines, spare parts, all types of equipment, have their own individual lifetime. The individual life time is different from part to part and is influenced by the quality of the product but also by other outside factors such as environment, handling etc.Some failures are occurring after a certain, expected time, and can almost be predicted. Some failures are occurring completely unexpected.

Page 145: Prev-Maintenance-.pptx

FAILURES

RandomFailures

Regular Failures

Non-Predictable Predictable

Page 146: Prev-Maintenance-.pptx

Failure Developing time(FDT)Some failures either they are random or regular, have longer or shorter failure development time. The failure development time is the deterioration time from the moment condition departs from the normal condition until the moment of break down occurs.

Failures with failure development time is easier to handle than the failures without failure development time.

Shorter FDT – Continuous on line condition monitoring has to be applied

Longer FDT – Off-line condition monitoring has to be applied

Page 147: Prev-Maintenance-.pptx

Total Productivity MaintenanceTotal Productivity Maintenance (TPM)

TPM is a way of organizing maintenance to support productivity & quality through increased equipment efficiency and to reduce costs.

TPM concept means that all employees work in small groups to maximize the improvement of equipment efficiency.

Operators are working independently with all maintenance activities of their own equipment and have also the total responsibility of operation and maintenance.

Page 148: Prev-Maintenance-.pptx

Fundamental Goals of TPMIncreased productivity and qualityZero defectsReduced cost of maintenance and productionIncreased motivation among all employeesZero accidentShorter lead timeZero unplanned stopsDevelopment of staff through trainingImprovement of work environment

Page 149: Prev-Maintenance-.pptx

Incentives for MMS or CMMS (rule of thumb)

Reduction on MDT about 20%

Increased machine life about 20 %

Saving on labour and spares 10 – 20%

Savings on maintenance budget 10 – 20%

Page 150: Prev-Maintenance-.pptx

Maintenance Management Systems

General of maintenance systemsThe maintenance function must also have necessary aids to manage the maintenance activities to coop up to the main target of the enterprise. Maintenance management means a better control of the maintenance organization and the related area. To properly control the maintenance of a facility, information is required to analyze what is occurring.

To be able to manage the maintenance activities in the right way, a maintenance management system is necessary. The system can be either manual or computerized. The main purpose of a maintenance management system is in operation and works properly.

Page 151: Prev-Maintenance-.pptx

The Basic MaintenanceCycle

PLANNING

PERFORMANCE

RECORDING

ANALYSIS

Page 152: Prev-Maintenance-.pptx

The basic function of a maintenance management system can be :

1. Preventive maintenance2. Plant and unit record(Equipment)3. Inventory and spare parts control system,

Purchasing system4.Document record5.Planning system for maintenance and work order

routines6.Technical/economic analysis of plant history,

maintenance and machine availability