probabilistic user's guide in construction.pdf
TRANSCRIPT
![Page 1: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/1.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 1/20
1 Determinist ic and Probabilistic Analysis
CA4PRS estimates can be produced from two types of analysis methods: deterministic
and probabilistic. Deterministic estimation treats all of the input parameters as constants
during productivity calculation, which does not capture the variations frequently seen
during construction. In contrast, probabilistic analysis treats all input parameters as
variables that change according to an assigned probability distribution function. The
probability distribution predicts the likely behavior of an input parameter over a range of
potential input parameter values. Probabilistic estimation is the preferred means of
CA4PRS analysis because this type of estimation can define and incorporate the
uncertainty associated with determining each scheduling or resource input parameter.
Probabilistic analysis also yields a more comprehensive estimate than deterministic
analysis by providing a range of likely construction productivity, but requires more
information about expected variable behavior and the likely variable probability
distributions. Included in this documentation is a general description and guide on
selecting and using appropriate distribution functions for the different CA4PRS input
parameters. Distribution and distribution parameter recommendations are based on data
collected from rehabilitation projects on I-15 Devore and I-10 Pomona in California and
the I-5 James to Olive Streets Pavement Rehabilitation project completed in Seattle,
Washington.
2 Monte Carlo Simulation
In a probabilistic analysis, CA4PRS combines probability distribution functions with
Monte Carlo simulation. Monte Carlo simulations refer to a stochastic problem-solving
process that is used for solving complex problems. The process is referred to as stochastic
because it is dependent upon the use of random numbers. Modeling construction
productivity is suited to Monte Carlo simulation because construction productivity is
based upon input parameters that will likely vary within a range of values. A Monte Carlo
simulation consists of a series of iterations, or individual simulations which are used to
produce a most likely representation of contractor productivity. During one simulation
iteration, random values are assigned to each input parameter according to their specified
![Page 2: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/2.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 2/20
probability distribution function. The random input parameters generated during one
Monte Carlo simulation iteration are placed into a CA4PRS estimate. This estimate
generates a contractor productivity estimate in lane-miles for that specific iteration. By
running up to as many as several thousand iterations during a Monte Carlo simulation,
CA4PRS produces an overall figure for the most likely production as well as a
distribution of likely productivity.
3 Probabili ty Distribut ion Functions
CA4PRS probabilistic estimation requires users to assign a probability distribution
function to the input parameters in both the scheduling and resource profiles. Probability
distributions are statistical functions that describe the probable behavior of a variable. In
a CA4PRS analysis, the variables are the input parameters. Input parameters assigned a
probabilistic function will not have one precise value, but rather a range of possible or
potential values. The probability distribution function describes the probability of an
input parameter being assigned a particular value in this range of potential values.
Probability distributions are commonly described using graphical representation. Figure 1
depicts the behavior of an unknown input parameter over a range of possible values. For
this example, a common distribution called a normal distribution is depicted. Normal
distributions are defined through two statistical parameters: the mean (µ) and the standard
deviation (σ). The mean value is the most likely or probable value in the probability
distribution being modeled. The standard deviation describes the width of the distribution
and how far values are likely to be from the mean. Standard deviations can be used for
assigning the probability of a value for being within a range. For instance, for a normal
distribution, 68.2% of the area under the curve is within one standard deviation whereas
95.4% of the area under the curve is within two standard deviations. Other distributions
will have different shapes and descriptive parameters but are used for describing the probability of an input parameter having different values within a specified range.
![Page 3: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/3.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 3/20
![Page 4: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/4.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 4/20
Figure 2 – A uniform distribution (Wikipedia contributors, 2006)
3.3 Normal Distribution
Normal distributions are one of the most frequently used forms of distribution and are
commonly known as bell curves (Weisstein, 2004). A normal distribution is a distribution
that is symmetric about the mean. The distribution of values around the mean is described
by the standard deviation of the sample data being represented. Assigning a normal
distribution to any of the CA4PRS inputs requires input of both the mean and the
standard deviation for the input being modeled. Normal distributions typically arise
where a large number of small effects act additively or independently upon a variable
(Wikipedia contributors, 2006). In using this type of distribution, users are required to
identify an appropriate standard deviation that will describe how the input parameter will
vary. If the input parameter is predicted to be fairly consistent, then a smaller standard
deviation should be used. At greater levels of uncertainty, the standard deviation should
be increased for CA4PRS input parameters. A recommended arbitrary starting point for
unknown data is to assume the value of the standard deviation will be 10-20% of the
expected input parameter mean.
![Page 5: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/5.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 5/20
![Page 6: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/6.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 6/20
3.5 Triangular Distribution
A triangular distribution is a continuous probability distribution that can be used when
relatively little information exists about the behavior of an input parameter (Wikipedia
contributors, 2006). To use this type of distribution, only the maximum and minimum
values for a range of potential input parameters values need to be known or
approximated. This type of distribution can be used with almost any construction input as
long as the user has a reasonable estimate for maximum and minimum input parameter
values.
Figure 5 - Triangular distribution (Wikipedia contributors, 2006)
3.6 Beta Distribution
Beta distributions are most commonly used to describe intervals defined by the maximum
and minimum value of a variable. Beta distributions can be used to describe the
relationship between two variables, commonly referred to as the α variable and β
variable. Modeling this type of distribution in CA4PRS requires inputting values for both
α and β. Because of its complexity and potential for different shapes, the beta distribution
in CA4PRS should only be used where necessary and if the more commonly used
normal, lognormal, and triangular distributions do not apply.
![Page 7: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/7.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 7/20
Figure 6 - Beta distribution (Wikipedia contributors, 2006)
3.7 Geometric Distribution
A geometric distribution refers to a unique type of distribution that is modeled with the
statistical equation:
P(X=n) = (1- p)n-1
p
This equation describes the probability of achieving a success or outcome “ p”, for a
statistical event on the nth attempt. The probability of a failure on the first try would be 1-
p. The probability of a failure on n-1 trials would be (1-p)n-1
. Accordingly, the probability
of a success on the nth attempt would be p, leading to the distribution described by the
previously depicted equation. This distribution is commonly described through a coin flip
analogy. The probability of flipping heads on any trial is ½, so p = 0.5. A success P will
be defined as flipping the coin with the head up. The probability of a success P on the
first trial is 0.5. The probability of seeing a success on the second trial is:
P = (1-0.5)(2-1) × 0.5.
The probability of a success on the third trial would be:
P= (1-0.5)(3-1)
× 0.5.
The probability for achieving a success on trials one through six are displayed in Table 1.
Input parameters that display this type of behavior can be graphically modeled with the
![Page 8: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/8.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 8/20
distribution shape shown in Figure 7. None of the CA4PRS input parameters will likely
be modeled by this type of distribution.
Table 1 - Geometric Distribution Probability Distribution For A Coin Toss
nth TrialProbability of a
Success on nth trial
1 0.5
2 0.25
3 0.125
4 0.0625
5 0.0313
6 0.0156
0
0.1
0.2
0.3
0.4
0.5
0.6
1 2 3 4 5 6
Trial Number
P r o b a b i l i t y o f S u c c e s s O n
n t h
T r i a l
Figure 7 - Graphical representation of a geometric distribution.
3.8 Truncated Normal Distribution
A truncated normal distribution is very similar to a normal distribution, but is confined
between an upper and a lower limit. To use this type of distribution CA4PRS requires
inputting the mean, standard deviation, maximum and minimum values for an input
parameter. This type of distribution could be used to describe an input parameter such as
truck arrival rates when a minimum or maximum number of truck arrivals is known.
3.9 Truncated Log Normal Distribution
A truncated log normal distributions is very similar to a log normal distribution, but is
confined between an upper and a lower limit. The value of a variable will change
![Page 9: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/9.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 9/20
logarithmically according to the probability function, but input parameter values will be
confined to an upper and lower limit.
4 Assigning Probability Distributions Functions
Assigning a distribution to an input parameter is dependent upon how much information
is known about the input parameter being modeled or how confidently a user can predict
input parameter behavior. In general, the most commonly used distributions will likely be
the triangular, normal, and log normal distributions. If additional information such as a
maximum and a minimum value are known for an input, users can begin applying
truncated normal, truncated log normal, and beta distributions. The geometric and
uniform distributions do not appear to have as much relevance for modeling input
behavior as the previously mentioned distributions.
While developing an estimate for a new project, most users will only have an expected
mean rate or approximate input parameter value. Assigning productivity rates,
distributions and distribution parameters can be a difficult task without information from
past construction projects. This section provides input parameter distribution information
collected from three construction projects: (1) I-10 Pomona California (2) I-15 Devore
California and (3) I-5 James to Olive Streets in Seattle, Washington. Distribution data
presented from these projects can be applied with user assumptions to assign proper input
parameter distributions and distribution parameters for new estimates. Distribution
information is first presented for the input parameters found in the scheduling profile
window, followed by data for the resource profile input parameters.
4.1 Scheduling Input Parameter Profile
The scheduling profile is the second tab or window that a program user is required to fill
complete during development of a CA4PRS estimate. The scheduling profile window
contains 5 input parameters that can be assigned probability distributions:
(1) Mobilization time
(2) Demobilization time
(3) Demolition to new base lag time(4) New base to PCCP installation lag time
![Page 10: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/10.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 10/20
(5) Demolition to PCCP installation lag time
The type of distribution and distribution parameters applied to the input parameters will
be strongly influenced by many factors including the type of construction closure and
construction sequencing. Readers should note that the data presented in the following
sections is specific to one project and is not necessarily applicable to a future projects
with significantly different conditions.
4.1.1 Mobilization
The documentation reviewed on the Californian reconstruction projects in Devore and
Pomona does not contain any information on the distribution of mobilization time
requirements. On the I-5 James to Olive Streets Pavement Rehabilitation project WSDOT
construction inspection personnel collected mobilization time requirements from four closure windows. A data sample from four construction closures does not provide a large
or comprehensive representation of input parameter variability and behavior. The
mobilization times observed on this project are depicted in Table 2. This limited data
does not depict an easily recognizable distribution. Mobilization times could be logically
assumed to have either a triangular, normal, and log-normal distributions.
Table 2 - Mobilization Times From The I-5 James
To Olive Pavement Reconstruction Project.
Construction
Closure
Mobilization
Time (hrs.)
Stage 1 0:30
Stage 2 1:00
Stage 3 1:00
Stage4 1:15
4.1.2 Demobilization
Minimal distribution data exists for demobilization times similar to mobilization times.
Recorded demobilization times from the I-5 James to Olive Streets Pavement
Rehabilitation project are presented in Table 3. Demobilization times have been
calculated as the time that elapsed between the conclusion of PCC paving and the
completion of temporary barrier removal. The four available demobilization times do not
depict an easily recognizable distribution. Dependent on available information,
![Page 11: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/11.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 11/20
demobilization times are suggested to be modeled with triangular, normal and log-normal
distributions.
Table 3 - Demobilization Times From The I-5 James
To Olive Pavement Reconstruction Project.
Construction
Closure
Demobilization
Time (hrs.)
Stage 1 13:30
Stage 2 11:00
Stage 3 11:00
Stage4 11:00
4.1.3 Demoli tion to New Base Installation
Conclusive distribution data has not been collected on demolition to new base installation
lag times. Users are recommended to apply either a triangular, normal or log-normal
distributions. The lag times observed during the four closures on the I-5 James to Olive
Streets Rehabilitation project are presented in Table 4 to provide program users an
indication of the magnitude and variability of this input parameter.
Table 4 - Demolition To New Base Installation Lag Times Observed On The
I-5 James To Olive Streets Pavement Rehabilitation Project.
Construction
Closure
End of Demo. To
Start of HMA
Paving (hrs)
Stage 1 4.5
Stage 2 0.55
Stage 3 3.25Stage4 4.08
4.1.4 New Base Installation to PCCP Installation
Conclusive distribution data has not been collected on demolition to new base installation
lag times. Users are recommended to apply triangular, normal and log-normal
distributions. The lag times observed during the four closures on the I-5 James to Olive
Streets Rehabilitation project are presented in Table 4 to provide program users an
indication of the magnitude and variability of this input parameter.
![Page 12: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/12.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 12/20
Table 5 – End Of Base Paving To Start OF PCCP Lag Times Observed On The
I-5 James To Olive Streets Pavement Rehabilitation Project
Construction
Closure
End of HMA Paving to Start
of PCCP Paving (hrs.)
Stage 1 7:40
Stage 2 2:33
Stage 3 0:54Stage4 2:35
4.1.5 Demolit ion to PCCP Installation
Conclusive distribution data has not been collected on demolition to new base installation
lag times. Users are recommended to apply triangular, normal and log-normal
distributions.
4.2 Resource Input Parameter Profi le
The scheduling profile is the second tab or window that a program user is required to fill
complete during development of a CA4PRS estimate. The scheduling profile window
contains 10 input parameters that can be assigned probability distributions:
(1) Demolition trucks per team
(2) Demolition packing efficiency
(3) Number of demolition teams
(4) Demolition team efficiency(5) Base delivery truck arrival rate
(6) Base delivery efficiency
(7) Batch plant capacity(8) Concrete delivery truck arrival rate
(9) Concrete packing efficiency(10) Paver speed
The distribution information presented in the following sections has been collected from
only three construction projects and represents only a small fraction of possible
construction conditions and equipment. This guide only presents distribution
recommendations based on these projects. Users of this guide should make certain that
conditions, construction operations, equipment and other factors are similar between
referenced projects and future projects when applying distribution recommendations.
![Page 13: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/13.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 13/20
4.2.1 Demoli tion Hauling Trucks
4.2.1.1 Trucks Per Hour Per Team
Researchers working during construction on I-10 collected demolition truck distribution
information based on 466 truck trips. Analysis of the data showed that on average, 9
demolition trucks arrived per hour per team with a 2.3 truck standard deviation. The
graphical distribution of truck arrival rates shows something like normal or log-normal
behavior. Based on these findings, future program users are recommended to apply
normal or log-normal distributions to demolition truck arrival rates.
Figure 8 - Distribution of demolition truck arrival rates recorded during construction
of the I-10 Pomona, California project.
4.2.1.2 Packing Efficiency
During construction on I-10 in Pomona, California, researchers found that demolition
trucks with a 22-ton capacity (9m3
or 2.7 slabs) carried loads that ranged from 8 to 12
metric tons (3.3m3
to 4.9m3). The observed decrease in capacity was due to the inefficient
packing caused by large bulky pavement sections. Although researchers collected
detailed information, no data is provided for the distribution or the distribution
parameters associated with demolition truck packing efficiency. Program users are
recommended to apply triangular, normal and log-normal distributions.
![Page 14: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/14.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 14/20
4.2.1.3 Number of Teams
On most construction projects the number of demolition teams will be best represented as
a deterministic quantity. In order to efficiently manage costs and resources, the number of
demolition teams will most likely remain constant.
4.2.1.4 Team Efficiency
CA4PRS provides users with the option of establishing a team efficiency and team
efficiency distribution. On the I-10 Pomona project, team efficiency was calculated based
upon loading rates and the number of trucks loaded per hour. The average loading time
for a demolition truck was found to be 5.5 minutes, or 10.90 demolition trucks per hour.
Because each team loaded an average of 9 trucks per hour, team efficiency was
calculated as 82.5% (9/10.9). Because team efficiency calculation is based upon loading
rate, the distribution of team efficiency can be related to the distribution of demolition
loading rates. The average load time of 5.5 minutes was found to have a standard
deviation of 0.9 minutes. Based upon the distribution of truck loading times shown in
Figure 9, team efficiency can accurately be represented by a log-normal distribution.
Figure 9 - The distribution of demolition loading times observed
on the I-10 project in Pomona, California.
![Page 15: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/15.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 15/20
4.2.2 Base Delivery Truck
4.2.2.1 Trucks Per Hour
A distribution of base delivery truck arrivals can be seen in the data collected from the I-5
James to Olive Streets pavement rehabilitation project. On this project base paving
progressed relatively rapidly, which limited the calculation of truck arrivals on an hourly
basis. Instead, HMA truck arrival rates have been modeled using minutes between truck
arrivals as opposed to truck arrivals per hour. Truck arrivals should exhibit the same
arrival distribution regardless if arrival rates are considered using either minutes or hours.
HMA truck arrival behavior depicts a distinctly lognormal distribution (Figure 10).
0
2
4
6
8
10
12
14
0 3 6 9 12 15 18 21 24 27 30 33 More
Time Between Truck Arrivals In Minutes
F r e q u e n c y
Figure 10 -HMA truck arrival rates for trucks carrying 26.5 to 33.5 tons of HMA.
The distribution seen in Figure 10 has a mean time of nine minutes between truck
arrivals with a standard deviation of about eight minutes. If the distribution could be
accurately calculated on an hourly basis, the standard deviation would not likely be as
large. On an hourly basis, the extremes in fast or slow arrival times would probably be
more balanced with one another. The high deviation associated with truck arrivals in
minutes should be ignored. Because the distribution of HMA truck arrivals is similar to
that of demolition trucks shown in 4.2.1.1, HMA trucks arrivals should be assigned an
![Page 16: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/16.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 16/20
![Page 17: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/17.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 17/20
average load and the maximum load is 0.2 tons. For HMA trucks carrying 31.9 to 33.5
tons of HMA, truck load sizes are consistent, and by correlation, packing efficiencies
should also be consistent. The tight clustering of HMA loads can be explained by the fact
that trucks are probably loaded close to the legal axle weight limit permissible on
Washington State roads. Because of the minimal variation, HMA packing efficiency
should be assigned a deterministic distribution with a mean value of 100%.
0
5
10
15
20
25
31.9 32.1 32.3 32.5 32.7 More
HMA Truck Load Size (tons)
N u m b e r o f O c c u r r e n c e s
Figure 12 - Distribution of HMA truck load size.
4.2.3 Batch Plant Capacity
For most rapid rehabilitation projects, large stationary concrete plants will likely have a
production capacity that exceeds the material handling capacity of the contractor.
Equipment availability, access, space restrictions and other factors will limit how much
material a contractor can place. The contractor who completed the paving work on the I-
10 rehabilitation project only utilized half the hourly capacity of a plant capable of
producing 170m3
of material per hour. The tight specifications and high costs associated
with rapid construction projects also decrease production variability. Contractors will
likely have backup production plants and access to sufficient material supplies to meet
contract quantities. Batch plant capacity should be treated as deterministic or a normal
distribution with only small variation (low standard deviation).
![Page 18: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/18.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 18/20
4.2.4 PCC Delivery Trucks
4.2.4.1 Trucks Per Hour
Data collected during construction of the I-10 project completed in Pomona, California, is
presented in Figure 13. The data depicts an average truck arrival rate of 10 mixer trucks
per hour, with a standard deviation of 2.1.
Figure 13 - Distribution of PCC delivery truck arrivals.
On the I-5 James to Olive Streets Pavement Rehabilitation project, PCC paving took
place over extended periods of time, producing a large data set of truck tickets. The large
collection of truck ticket data facilitated the calculation of truck arrival rates on an hourly
basis from multiple construction stages (Table 6). The hourly arrival rates in Table 6 have
been used to create a graphical representation for the distribution of truck arrival rates
(Figure 14). The distribution in Figure 14 shows a distinct normal distribution. The
modeled distribution has a mean of 12.5 truck arrivals per hour and a standard deviation
of 2.7 trucks per hour.
![Page 19: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/19.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 19/20
Table 6 - PCC Truck Arrival Rates Per Hour Based Upon Truck Ticket Information
6/28/2005
1:00AM -
2:00AM
2:00AM -
3:00AM
3:00AM -
4:00AM
4:00AM -
5:00AM
5:00AM -
6:00AM
Trucks Per Hour 12 13 15 17 15
6/18/20057:00PM -8:00PM
8:00PM -9:00PM
9:00PM -10:00PM
Trucks Per Hour 10 9 9
6/25/2005
8:00PM -
9:00PM
9:00PM -
10:00PM
10:00PM -
11:00PM
11:00PM -
12:00AM
12:00AM -
1:00AM
1:00AM -
2:00AM
Trucks Per Hour 14 14 11 12 13 13
6/28/2005
6:00PM -
7:00PM
7:00PM -
8:00PM
8:00PM -
9:00PM
9:00PM -
10:00AM
10:00AM -
11:00AM
11:00AM -
12:00PM
12:00PM -
1:00PM
Trucks Per Hour 8 14 9 11 16 11 15
7/16/2005
5:00PM -
6:00PM
8:00PM -
9:00PM
Trucks Per Hour 16 17
0
1
2
3
4
5
6
7
8 10 12 14 16 18 More
Truck Arrivals Per Hour
F r e
q u e n c y o f O c u r r e n c e
Figure 14 - The distribution of hourly arrival rates for PCC delivery trucks.
Data collection from two different PCC paving projects depicts lognormal distribution for
PCC truck arrival behavior. Users developing estimates for future are recommended to
apply lognormal distributions with arrival distributions that have a standard deviation
approximately 20% of the mean value.
4.2.4.2 Packing Efficiency
CA4PRS includes a packing efficiency to address material buildup issues with Fast
Setting Hydraulic Cement (FSHC). The I-10 project completed in California used a
concrete pavement mix that had a four hour cure time. Due to the rapid set time, material
![Page 20: Probabilistic User's Guide in construction.pdf](https://reader036.vdocument.in/reader036/viewer/2022081806/577cd7e11a28ab9e789fe5e5/html5/thumbnails/20.jpg)
7/27/2019 Probabilistic User's Guide in construction.pdf
http://slidepdf.com/reader/full/probabilistic-users-guide-in-constructionpdf 20/20
would tend to set and adhere to the inside of the mixing drum. As more material
accumulated in the drum, less space was available for material. Because of the material
buildup and expense of these materials, future construction projects are not likely to use
these types of materials exclusively. For non-FSHC projects users are recommended to
use a deterministic distribution and a packing efficiency of 1. For FSHC projects, a value
less than one with a 10% standard deviation is advised.
4.2.5 Paver Speed
For users developing future estimates on projects that contain hand and machine paving,
PCC paver speed should be represented by a deterministic rate or a probabilistic
distribution with a small standard deviation. Paving machines produces the best ride and
pavement quality in terms of a roughness index when they maintain a consistent speed. Ineffort to deliver a high quality project, most contractors will try to maintain a constant
paver speed.