Procurement OverviewProcurement Overview
Dec 2010
IntroductionIntroduction
Purchasing goods, services and works (procurement) is a critical element of project implementation. . .
2
• Inefficient or ineffective procurement may have serious consequences:
expected project results & impact not achieved delays in project implementation higher cost of implementation
• Procurement is a sensitive activity: can be conducive to corruption & fraud
complexity of certain procurement actions combined use of national & IFAD regulations
/guidelines
Importance of Procurement – IFAD GuidelinesImportance of Procurement – IFAD Guidelines
Proper use of loan funds: IFAD must ensure financing proceeds
are used only for intended purpose: specifically CPM & support staff
oversight
Economy & efficiency requirements in project implementation in
general & procurement in particular: IFAD must ensure contract
awards result from a competitive process
IFAD must ensure equity, integrity, transparency & good
governance in procurement process
Concept of “no objection”
IFAD’s fiduciary responsibilities:
3
ResponsibilitiesResponsibilities
Implementation of project/ programme including award & administration of contracts
BorrowerBorrower/ / RecipientRecipient
IFAD supervises the Borrower’s procurement actions in order to ensure that funds are used for the purpose of the Financing agreement with due attention to considerations of economy, efficiency & social equity
IFADIFAD
4
Role of Borrower/ PMU in Role of Borrower/ PMU in Procurement Procurement
Procurement planning (in line with project objectives & AWPB)
Preparation & issuance of bidding documents & invitation to bid
Opening & evaluation of offers
Negotiation, award & signature of contract
Monitoring of contract execution (technical & financial/ administrative)
Delivery of goods/ works/ services
Payment
PMU has overall responsibility for Procurement
5
Role of IFAD in ProcurementRole of IFAD in Procurement
Ensure coherence of procurement actions with project objectives, AWPB & procurement plan, & timing within implementation period
Ensure funds availability: cost of procurement must not exceed funds allocated in Financing agreement & AWPB
Ensure transparency & equity: procurement must be conducted in compliance with applicable rules & procedures
Ensure best value for money: procurement must be the result of a competitive process
Review procurement plan, prequalification of bidders, perform procurement review – prior & ex-post
CPM must:CPM must:
• IFAD staff must maintain neutrality & impartiality
• Flexibility is a must – but know rules & regulations
• IFAD staff must maintain neutrality & impartiality
• Flexibility is a must – but know rules & regulations6
Formation of Bid Evaluation Committee; N-O by IFAD
Prepare Specifications and tender documents (Advertisement/ ITBs/ RFPs/
RFQs as applicable)
Bid Evaluation and draft contract IFAD Prior Review & No-Objection
(if required)
Contract Award to best evaluated bid
ITB – ITB – InvitationInvitation to to BidBid
RFP – Request for RFP – Request for Proposal Proposal
RFQ – RFQ – RequestRequest for for QuotationQuotation
KeyKey
Tendering ProcessTendering Process
7
Procurement MethodsProcurement Methods
Different methods (ranging from International Competitive Bidding to Direct Contracting) are used for the different categories of procurement depending on nature, amount & other criteria - guiding principle being economy, efficiency & social equity
8
Common Procurement MethodsCommon Procurement MethodsInternational Competitive Bidding (ICB): for high value requirementsInternational Competitive Bidding (ICB): for high value requirements
• Advertise in widely circulated newspapers, local representatives, Embassies, UN Development Forum
• Pre-qualification
• Public bid opening
• Bid evaluation based on point scoring system (technical & financial)
• Advertise in widely circulated newspapers, local representatives, Embassies, UN Development Forum
• Pre-qualification
• Public bid opening
• Bid evaluation based on point scoring system (technical & financial)
National Competitive Bidding (NCB): public procurement in Borrower’s countryNational Competitive Bidding (NCB): public procurement in Borrower’s country
• Advertise in local newspapers (note: foreign suppliers may bid)
• Pre-qualification
• Public bid opening
• Bid evaluation based on point scoring system (technical & financial)
• Advertise in local newspapers (note: foreign suppliers may bid)
• Pre-qualification
• Public bid opening
• Bid evaluation based on point scoring system (technical & financial)
9
Common Procurement MethodsCommon Procurement Methods
International ShoppingInternational Shopping
• short-list at least 3 reputable suppliers in at least 2 member countries of IFAD• issue ITB to the short-listed suppliers• receive bids in original form (not faxed)• bid evaluation based on lowest cost for compliant offers• sign contract
• short-list at least 3 reputable suppliers in at least 2 member countries of IFAD• issue ITB to the short-listed suppliers• receive bids in original form (not faxed)• bid evaluation based on lowest cost for compliant offers• sign contract
Local ShoppingLocal Shopping
• prepare specifications and request for quotations• short-list at least 3 reputable suppliers• issue request for quotations to the short-listed suppliers• receive bids in original form (not faxed)• bid evaluation based on lowest cost for compliant offers• sign contract
Direct ContractingDirect Contracting
• Extension of/ addition to an existing contract• Standardisation of goods with existing project assets
Note: Competitive process is not required. 10
Project Specific PrinciplesProject Specific Principles
Procurement is carried out in accordance with Financing Agreement &/or Letter to the Borrower
Procurement is now not limited to suppliers/ manufacturers from IFAD Member States (since September 2010)
Procurement is to be conducted within the project implementation period
Procurement must not exceed availability of funds duly allocated by Financing Agreement
Procurement must be consistent with approved AWPB
Procurement should provide best value for money
11
Regulatory FrameworkRegulatory Framework
Procurement rules and procedures applicable to a particular project come from different sources:
• national procurement rules & regulations
• IFAD Procurement Guidelines
• project design report
• financing agreement
Applicable rules, methods & procedures are specified in Letter to the Borrower, as well as IFAD procurement review requirements
Must adhere to regulatory framework . . .
12
Compatibility with National Rules & IFAD’s Compatibility with National Rules & IFAD’s GuidelinesGuidelines
NATIONAL RULES & REGULATIONS MAY BE ADOPTED IF THEY ARE ASSESSED TO BE COMPATIBLE WITH IFAD’S GUIDELINES
Compatible means that they respect the main basic principles of IFAD’s guidelines
N.B. In the unlikely case that some provisions in Schedule 4 of the Financing Agreement/ LTB are not in line with IFAD’s Procurement guidelines, the provisions of Schedule 4 shall prevail
13
IFAD Prior ReviewIFAD Prior Review
Schedule 4 of the Financing Agreement/ LTB lists all major
procurement contracts to be awarded on the Project, their estimated
value, category (goods, works, services), the monetary threshold for
IFAD’s prior review
The thresholds may always be modified from time to time as notified
by the Fund to the Borrower/ Recipient (needs agreement by both
parties if the threshold is decreased)
14
Mis-ProcurementMis-Procurement
When procurement has not been conducted in accordance
with the procedures adopted (national and/or IFAD)
When a contract has been awarded based on incomplete,
inaccurate or misleading information furnished by the
borrower, even in the case where a NO OBJECTION has been
granted
When a contract has been modified without IFAD’s approval
15
Review of Prequalification of Review of Prequalification of BiddersBidders
16
Review of Draft Prequalification DocumentsReview of Draft Prequalification Documents
a) a brief description of the goods & works to be procuredb) the contract conditionsc) who is financing the projectd) eligibility requirements for potential bidders, suppliers & contractorse) the time and place where prequalification documents can be obtained
The advertisement & invitation for prequalification should contain:
Prequalification documents should contain further information:
a) the proposed procurementb) the estimated value of the contract & major quantities of workc) location of the workd) procurement scheduling of goods or works to be procurede) abbreviated specifications & conditions of contractf) main quantities to be procuredg) delivery or implementation schedulesh) requirements for bid & performance securitiesi) how the project is to be financedj) payment terms, price adjustment provisionsk) the language & governing law of the contractl) other information in sufficient detail to enable bidders, suppliers or contractors to assess
their interest & respond appropriately17
Procurement Process for Goods, Services & WorksProcurement Process for Goods, Services & Works
Best use of competitive bidding
Step 1Step 1
Step 2Step 2
Procurement List And Bulk PurchaseProcurement List And Bulk Purchase
Procurement PlanProcurement Plan
Model of Procurement plan: proposed minimum contents and to be updated periodically (See Procurement Handbook)
Annex 1
18
Step 3Step 3 Preparation of Bidding DocumentsPreparation of Bidding Documents
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
GOODS SERVICES WORKSBidding documents or Request for quotations
Request for Proposals from shortlisted firms
Bidding documents or Request for quotations
Invitation to bidLetter of invitation & general and specific conditions
Invitation to bid
Instructions to bidders with:* Bid security (Lumpsum)* Bid evaluation method and process etc.
Instructions to Consultants with:* Proposal preparation info* Proposal evaluation method and process etc.
Instructions to bidders with:* Bid security (Lumpsum)* Bid evaluation method and process etc.
Conditions of contract (general and special)
Acceptable to IFAD
Conditions of contract (general and special)- International Federation of Consulting Engineers (FIDIC) for large contracts above 10 million USD
Schedule of requirements and technical specifications
Terms of Reference (TORs)Scope of works, Bill of quantities and drawings
Prices schedules Breakdown of costs Prices schedulesContract form Contract form Contract formAnnexes for bid bonds and performance security, tax clearance, etc..;
No proposal or performance securities
19
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
TECHNICAL SPECIFICATIONS (TS) FOR GOODS:
Inappropriate, irrelevant, too many details lead to a restriction of competition: reference to an exclusive mark/ model (IT equipment), too many technical details (computers/ laptops), project or country specifications (give explanations), limit to essential criteria (adherence to TS evaluation), warranty & upgraded equipment, check specialists, visit potential suppliers
Crucial StepsCrucial Steps
70 – 80% OF THE PROBLEMS OF A BID EVALUATION COME FROM A BAD DEFINITION OF TECHNICAL SPECIFICATIONS
TERMS OF REFERENCE (TORs) FOR CONSULTANCY SERVICESTo be done by the final user of the services and not by the procurement officer or the financial controller
SCOPE OF WORKS, Bill of Quantities (BoQ), DRAWINGS: use the services of an engineering expert or office
20
Review of Draft Bidding DocumentsReview of Draft Bidding Documents
Is the procurement: In accordance with the loan agreement & any subsequent changes reflected in mission reports within the availability of funds? consistent with the approved AWPB (procurement plan)?
General
Adequacy and Quality of the Bidding Documents
Bidding documents should provide all the information necessary for a bidder to prepare its bid for the goods or works to be provided. This includes:Instruction to the biddersproposed pricing (e.g. unit prices or lump sum), currency arrangementsqualification standards set out for bidder (where no prequalification)Terms of Reference (TOR) or Statement of Work (SOW) describing contract requirementsevaluation criteria by which the award will be determinedclarity and propriety of the borrower’s use of preferences (e.g. the method by which domestic bidders may be favoured)insurance or bond requirements
unusual provisions (e.g. large advance payments) proposed attachments to be included in the bidding documents borrowers’ list of proposed bidders to receive the invitation of bids draft contract to be awarded
Other Issues
21
Review of Draft RFPReview of Draft RFP
Is the procurement: in accordance with financing agreement & any subsequent changes reflected in mission reports within availability of funds (cost estimate by submitted by borrower) consistent with approved AWPB (& procurement plan)
General
Adequacy and Quality of the RFP
The RFP should provide all the information necessary for a consulting firm to prepare its proposal:instruction to consultant (including applicable forms and data sheets)requirements to specification of pricing (e.g. time-based, lump sum, reimbursable)currency arrangementsterms of reference (TOR) describing contract requirements, overall as well as for individual personnelselection methodevaluation criteria (technical & financial) by which the award will be determinedclarity and propriety of the Borrower’s use of preferences (e.g. the method by which domestic consultants may be favoured)insurance or bond requirements
Unusual provisions Proposed attachments to be included in RFP Borrowers’ shortlist of consultants to receive RFP Draft contract to be awarded
Other Issues
22
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
Contract FormsContract Forms
FOR GOODS: Standard forms OK but attention should be given to the conditions of payment (avoid Letter of Credit & special commitment, direct payment if possible, advance payment against bank or insurance guarantee*)
FOR SERVICES: depends on scope of services & duration of these services
FOR WORKS: Standard form but specific model for community intervention
* Specific criteria are being developed for use of insurance guarantees, which are acceptable only in specific circumstances including wording, whether World Bank permits, regulatory framework, and depend on country context
23
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
Each request of No Objection (NO) should be numbered in a continuous manner with the name of project, country code and date, for example: NO 08/RWA/PAPSTA/28022011 = 8th request of NO from PAPSTA project in Rwanda dated 28th February 2011
Step 4Step 4 Prior Review and ApprovalPrior Review and Approval
o Procurement process approved in AWPB & in line with Procurement plan
o Open or limited tender or prequalification documentation
o Advert of publication & list of newspapers, magazines, etc.
o Letter of invitation
o List of pre selected bidders with justifications
o Instructions to bidders, rules of evaluation, conditions of payment
o TS or TORs or BoQ adequacy
o Contract form
o General & special conditions of contract
o Bid security & other bonds24
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
Step 5Step 5
Step 6Step 6
Open Tender PublicationOpen Tender Publication
Opening Session of BidsOpening Session of Bids
Recommended: a box for the deposit of bids
Step 7Step 7 Evaluation of Bids/ Request for Evaluation of Bids/ Request for ProposalProposal
Crucial StepsCrucial Steps
o Composition of the evaluation committee (procurement, financial, technical)
o The report should be structured as follows: Background, reference to NO, publication, list of bidding documents purchased or sent, bids or proposals received, minutes of opening session, technical & evaluation steps with recommendation
o The evaluation process for goods should be conducted as follows:25
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorksFirst StepFirst Step
o Before proceeding to the detailed evaluation, the evaluators appointed by Project have to declare the bids received as acceptable & responsive.
o Acceptability: The bids are acceptable if:
1. submitted before the deadline
2. from a duly solicited supplier (in case of Selective bidding)
3. written in English (or in the requested language)
4. sealed in an envelope in conformity with Instructions to Bidders
o Responsiveness: The bids are responsive if:
1. they include a bid security (if requested)
2. the quoted prices are fixed not subject to variation if so stipulated in the Bidding Docs; (v) the quoted prices are valid for the period requested
3. they are duly signed and initialed
4. the prices quoted are for one or several complete lot(s)
26
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorksSecond Step – Preliminary Second Step – Preliminary operations:operations:
The Evaluators will proceed to:
o conversion to a single currency of all bids quoted in foreign currency by
using official selling rate of exchange of recipient country on closing date
of bids
o multiplication of unit price by quantity to verify total price quoted by item &
grand total for all items. In case of discrepancy between unit price & total,
unit price shall prevail
o verification of actual quantities of goods proposed & possible modification
as above in case of obvious arithmetical errors
27
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
Third Step – Third Step – Specific & detailed technical & financial Specific & detailed technical & financial evaluationevaluation::
The Annex attached to tendering & contracting procedures should include
some specific, detailed evaluation (technical & financial) of goods
28
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorksEVALUATION OF RFP FOR SERVICESEVALUATION OF RFP FOR SERVICES
Technical Technical ProposalProposal
A two-stage procedure is adopted in evaluating proposals. The technical
evaluation shall be carried out first, followed by financial evaluation
o The evaluation committee appointed by Project shall carry out evaluation,
applying evaluation criteria & point system specified in Data Sheet. Each
responsive proposal is attributed a technical score
o Proposals by other firms (scoring below quality threshold) shall be rejected
& financial proposals returned unopened
o Request for IFAD’s No-Objection for Technical Evaluation Report
29
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
Financial Financial ProposalProposal
o Public Opening of Financial Proposals, disclosure of respective Technical Scores
o The evaluation committee, after determining whether the financial proposals are
complete and without arithmetic errors, shall convert prices in various currencies to
common currency specified in the Data Sheet
o The official selling rates used shall be provided by indicated source
o The financial proposals shall be ranked with lowest proposal ranked first
o The maximum of points is allocated to lowest price proposal
o All other financial proposals will receive points inversely proportional to those of
lowest price: e.g. [total financial component points] x [US$ lowest]/[US$ other] =
points for other financial proposal
o Negotiation: Prior to expiration of the validity of proposal, the Client shall notify the
Consultant who submitted the No. 1 ranking proposal in writing & invite them to
negotiate scope of contract, duration, reimbursables, etc.
30
Step 8Step 8 Evaluation Review & Contract ApprovalEvaluation Review & Contract Approval
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
IFAD does not require a specific format of the evaluation report, but the report should include as a minimum:
a) a listing of all applicants
b) their ratings keyed to specific criteria & items of information requested
c) the list of rejected applicants with a detailed justification for rejection
d) the resulting proposed list of prequalified applicants
31
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
• receipt & opening of bids (including minutes of the public bid opening)
• examination of bids
• substantially non-responsive bids
• correction of arithmetic errors & currency conversion
• adjustment for non-material deviations
• bids subject to detailed evaluation
• evaluation & comparison of bids
• lowest evaluated responsive bid
• post qualification
• award recommendation
There is no standard format for the bid evaluation report, but the report should to the extent possible cover & reflect the logical sequence of a standard bid evaluation process in the following manner:
There is no standard format for the bid evaluation report, but the report should to the extent possible cover & reflect the logical sequence of a standard bid evaluation process in the following manner:
32
Step 9Step 9 Contract NotificationContract Notification
Step 10Step 10 Contract Execution & ManagementContract Execution & Management
Procurement Process for Goods, Services & Procurement Process for Goods, Services & WorksWorks
33
Procurement in Project Completion Procurement in Project Completion ProcessProcess
To ensure that all goods are delivered/ works completed/ services rendered
by project completion date
• Closely review & monitor the final procurement plan & progress
reports during last year of Project
• Take measures to facilitate completion of physical execution of
contracts
• Cancel contracts that cannot be executed within completion date
Ensure that only contracts executed by project completion date are paid
Ensure that procurement files are complete & obtain missing documents
from Project
Report on lessons learned & make recommendations for future projects
34
Key Tools for Successful Key Tools for Successful ProcurementProcurement
A complete financial & administrative procedures manual (Implementation/ Operations Manual)
A well-prepared start-up workshop with technical session
The technical session should include discussions about importance of quality submissions, frequent causes of delays, timing issues
A ‘procurement plan’ summarising procurement methods, applicable rules & prior review requirements as per Financing agreement
Assessment of procurement capacity at national/ project level
Training of relevant PMU & national partners
Procurement expertise at national/ project level (complemented by on-going capacity building)
Procurement expertise at IFAD level (procurement specialist to assist CPM)
35
How to avoid delays in procurementHow to avoid delays in procurement
Lack of procurement plan or inadequate/incomplete procurement plan Poorly designed and/or unrealistic AWPB Imprecise and ambiguous terms or documents for bid evaluation method & selection
criteria Absence of confidentiality at various stages of bid evaluation process &/or selection
of winning bid Failure to justify rejection of bids or non-selection of a competitive bid Political interference in the procurement process Corruption, fraud, conflicts of interest & mis-procurement Poor qualification of evaluation committee members Lack of procurement capacity at borrower &/or project level Poor understanding of IFAD procedures at borrower &/or project level Confusion between national procedures & IFAD guidelines/ loan agreement
procedures Cumbersome procedures & bureaucracy for approval of procurement documents at
borrower level Long delays in issuance of no-objections by IFAD Long response time by IFAD to queries from PMU
36