Date : 03 Decem Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012 #DIV/0! Start Completion 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 UZR-1.1 Improvement of Ghior-Jabra Road and construction of appurtenant structures. 8.00 Km The Slice UZR-1.1 of Package Man/UZR-1 has been merged into Package Man/UZR-49 (Sl. No. 49) as a part of single package and transferred from 1st Phase to 2nd Phase. 01. Man/UZR-1 UZR-1.2 Improvement of Balirteck-Harirampur Road and construction of appurtenant structures. 3.01 Km 3.01 Km 14.07 14.07 NCB Yes 1 1/18/2004 7/21/2005 7/21/2005 10/25/2003 M/S Good Luck Trading Corporation 100% 100% UZR-2.1 Improvement of Kaliganj - Jamalpur road and construction of appurtenant structures. 3.65 Km The Slice UZR-2.1 of Package Gaz/UZR-2 has been shifted to Package Gaz/UZR-32, Slice No. UZR-32.3 (Sl. No. 32) and transferred from 1st Phase to 2nd Phase. 02. Gaz/UZR-2 UZR-2.2 Improvement of Kapasia - Monohordi Road and construction of appurtenant structures. 14.23 Km 14.23 Km 74.31 74.31 NCB Yes 12/5/2003 6/7/2005 10/31/2007 12/1/2003 Joint Venture of 1. Sarker Golam Mohammad Co. Ltd. & 2. Ismail Hossain 100% 100% 03. Mun/UZR-3 UZR-3.1 Improvement of Lauhajang-Goalimandra Hat and construction of appurtenant structures. 2.20 Km 14.22 Km 16.17 92.92 NCB Yes 3/24/2004 9/25/2005 7/30/2006 3/18/2004 M/S. Columbia Engineers Ltd 100% 100% UZR-3.2 Improvement of Betka - Tongibari road and construction of appurtenant structures. 3.85 Km 15.67 15.67 12/14/2003 6/16/2005 8/10/2005 11/22/2003 M/S. Columbia Engineers Ltd 100% 100% UZR-3.3 Improvement of Sreenagar - Tantar Road and construction of appurtenant structures. 8.17 Km 61.09 12/14/2003 6/16/2005 12/31/2006 12/1/2003 Joint Venture of 1. Sarker Golam Mohammad Co. Ltd. & 2. Ismail Hossain 84% 84% 04. Nar/UZR-4 UZR-4.1 Improvement of Shibpur - Jallara bazar-Belabo road and construction of appurtenant structures. 13.19 Km 19.21 Km 32.61 61.10 NCB Yes 1/6/2004 7/9/2005 2/28/2007 12/3/2003 Project Builders Ltd. 100% 100% UZR-4.2 Improvement of Madhabdi - Kharia road and construction of appurtenant structures. 6.02 Km 28.49 11/17/2003 5/20/2005 8/20/2005 11/10/2003 Joint Venture of 1. M/S. Amzad Traders & 2. Shuchi Enterprise Ltd. 100% 100% 1 It was cleared by IDA as 1st phase contract. Estimated Cost (in million Taka) OR Actual Contract Price (with Contract Currency) Contract Package Number* Sl. No. Name of Contract (Brief Description) Financial Progress as of 30 June'12 PROCUREMENT PLANNING AND MONITORING FORMAT Planned Date Procedure/ Method Prior Review** (Yes/No) Actual Completion Date Date of Contract Signing Quantity/ Number Supplier's Name OR Contractor's Name OR Consultant's Name Progress of Procurement as of 30 June'12 1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 01-Feb-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Date : 03 December, 2005

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

UZR-1.1 Improvement of Ghior-Jabra Road and construction of

appurtenant structures.

8.00 Km The Slice UZR-1.1 of Package Man/UZR-1 has been merged into Package Man/UZR-49 (Sl. No. 49) as a part of single package and transferred from 1st Phase to 2nd Phase.

01. Man/UZR-1 UZR-1.2 Improvement of Balirteck-Harirampur Road and

construction of appurtenant structures.

3.01 Km 3.01 Km 14.07 14.07 NCB Yes1 1/18/2004 7/21/2005 7/21/2005 10/25/2003 M/S Good Luck

Trading Corporation

100% 100%

UZR-2.1 Improvement of Kaliganj - Jamalpur road and

construction of appurtenant structures.

3.65 Km The Slice UZR-2.1 of Package Gaz/UZR-2 has been shifted to Package Gaz/UZR-32, Slice No. UZR-32.3 (Sl. No. 32) and transferred from 1st Phase to 2nd Phase.

02. Gaz/UZR-2 UZR-2.2 Improvement of Kapasia - Monohordi Road and

construction of appurtenant structures.

14.23 Km 14.23 Km 74.31 74.31 NCB Yes 12/5/2003 6/7/2005 10/31/2007 12/1/2003 Joint Venture of

1. Sarker Golam

Mohammad Co. Ltd. &

2. Ismail Hossain

100% 100%

03. Mun/UZR-3 UZR-3.1 Improvement of Lauhajang-Goalimandra Hat and

construction of appurtenant structures.

2.20 Km 14.22 Km 16.17 92.92 NCB Yes 3/24/2004 9/25/2005 7/30/2006 3/18/2004 M/S. Columbia

Engineers Ltd

100% 100%

UZR-3.2 Improvement of Betka - Tongibari road and construction

of appurtenant structures.

3.85 Km 15.67 15.67 12/14/2003 6/16/2005 8/10/2005 11/22/2003 M/S. Columbia

Engineers Ltd

100% 100%

UZR-3.3 Improvement of Sreenagar - Tantar Road and

construction of appurtenant structures.

8.17 Km 61.09 12/14/2003 6/16/2005 12/31/2006 12/1/2003 Joint Venture of

1. Sarker Golam

Mohammad Co. Ltd. &

2. Ismail Hossain

84% 84%

04. Nar/UZR-4 UZR-4.1 Improvement of Shibpur - Jallara bazar-Belabo road

and construction of appurtenant structures.

13.19 Km 19.21 Km 32.61 61.10 NCB Yes 1/6/2004 7/9/2005 2/28/2007 12/3/2003 Project Builders Ltd. 100% 100%

UZR-4.2 Improvement of Madhabdi - Kharia road and

construction of appurtenant structures.

6.02 Km 28.49 11/17/2003 5/20/2005 8/20/2005 11/10/2003 Joint Venture of

1. M/S. Amzad Traders

&

2. Shuchi Enterprise

Ltd.

100% 100%

1 It was cleared by IDA as 1st phase contract.

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

1

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

05. Raj/UZR-5 UZR-5.1 Improvement of Anulia - Mohanganj road and

construction of appurtenant structures.

9.09 Km 22.48 Km 42.34 93.24 NCB Yes 12/27/2003 6/29/2005 11/30/2006 12/10/2003 AML-BCPL JV 100% 100%

UZR-5.2 Improvement of Rajabari - Kakonhat Road (Kundolia)

and construction of appurtenant structures.

13.39 Km 50.91 12/27/2003 6/29/2005 12/15/2006 12/6/2003 Joint Venture of

1. Md Fazlur Rahman

&

2. Md Azizul Alam

100% 100%

06. Nat/UZR-6 UZR-6.1 Improvement of Gurudaspur - Dharabarisha Road and

construction of appurtenant structures.

6.85 Km 20.50 Km 39.41 104.21 NCB Yes 12/15/2003 6/17/2005 2/28/2007 12/8/2003 Padma Associates and

Engineers Ltd.

100% 100%

UZR-6.2 Improvement of Chowgram - Kaliganj GC and

construction of appurtenant structures.

7.95 Km 38.03 12/15/2003 6/17/2005 10/31/2006 12/8/2003 Padma Associates and

Engineers Ltd.

100% 100%

UZR-6.3 Improvement of Dorappur R&H - Laxmipur GC and

construction of appurtenant structures.

5.70 Km 26.78 12/31/2003 7/3/2005 12/15/2005 12/21/2003 Kh. Mainul Islam 100% 100%

07. Naw/UZR-7 UZR-7.1 Improvement of Kansarghat - Khaser hat and

construction of appurtenant structures.

8.56 Km 15.79 Km 47.24 72.89 NCB Yes 1/5/2004 7/8/2005 3/31/2006 12/13/2003 M/S Rising

Construction

100% 100%

UZR-7.2 Improvement of Bongpur - Dobar Mohr road and

construction of appurtenant structures.

7.23 Km 25.66 12/20/2003 6/22/2005 11/30/2005 12/4/2003 Joint Venture of

1. The Stone Steel &

2. Md Kamal Uddin

100% 100%

08. Nao/UZR-8 UZR-8.1 Improvement of Abadpukur hat-Kaliganj hat Road and

construction of appurtenant structures.

5.65 Km 19.18 Km 25.35 91.79 NCB Yes 1/1/2004 7/4/2005 6/20/2005 12/14/2003 Joint Venture of

1. Rising Construction

&

2. PTSL

100% 100%

UZR-8.2 Improvement of Chatra - Mohadebpur (Konjobon) road

and construction of appurtenant structures.

13.53 Km 66.45 1/1/2004 7/4/2005 6/20/2005 12/18/2003 M/S Ataur Rahman

Khan

100% 100%

09. Bog/UZR-9 UZR-9.1 Improvement of Sultanganj - Perirhat road and

construction of appurtenant structures.

4.63 Km 9.95 Km 22.67 40.75 NCB Yes 11/30/2003 6/2/2005 9/15/2006 11/20/2003 M/S Rupayan

Prakaushali

100% 100%

UZR-9.2 Improvement of Birgram - Khoma - Majira hat and

construction of appurtenant structures.

5.32 Km 18.08 11/15/2003 5/18/2005 6/30/2006 11/13/2003 Joint Venture of

1. M/S Ethen

Enterprise &

2. M/S Joya

Construction

100% 100%

2

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

10. Bog/UZR-10 UZR-10.1 Improvement of Dupchanchia - Tindighi Road and

construction of appurtenant structures.

13.13 Km 26.11 Km 54.30 116.78 NCB Yes 12/18/2003 6/20/2005 7/30/2005 12/8/2003 M/S Islam Trading

Consortium Ltd.

100% 100%

UZR-10.2 Improvement of Shariakandi - Chandanbasia Road and

construction of appurtenant structures.

12.98 Km 62.48 12/30/2003 7/2/2005 6/30/2006 12/23/2003 M/S Reza Construction

Ltd.

100% 100%

11. Sir/UZR-11 UZR-11.1 Improvement of Boalia R&H - Solanga GC Road and

construction of appurtenant structures.

6.43 Km 15.72 Km 31.91 79.00 0 Yes 2/20/2004 8/23/2005 8/31/2006 12/3/2003 M/S Haider

Construction Pvt. Ltd.

100% 100%

UZR-11.2 Improvement of Horinathpur - Dhekuria GCM and

construction of appurtenant structures.

6.04 Km 29.85 2/19/2004 8/22/2005 5/15/2006 12/1/2003 M/S Rising

Construction

100% 100%

UZR-11.3 Improvement of Sealcola R&H - Bohuli hat and

construction of appurtenant structures.

3.25 Km 17.23 2/11/2004 8/14/2005 4/30/2006 12/3/2003 Joint Venture of

1. M/S Syed Nurul

Huda &

2. M/S Abdul Motaleb

Sheikh

100% 100%

12. Syl/UZR-12 UZR-12.1 Improvement of Atgram - Zakiganj Road and

construction of appurtenant structures.

11.95 Km 16.48 Km 69.80 92.42 NCB Yes 1/12/2004 7/15/2005 1/15/2007 12/15/2003 Joint Venture of

1. Md. Sayhid Hasan &

2. M/S. Mortoza

Enterprise

100% 100%

UZR-12.2 Improvement of Kumargaon - Badaghat-Shiber bazar

and construction of appurtenant structures.

4.53 Km 22.62 1/12/2004 7/15/2005 12/15/2005 12/3/2003 The Nirmitee Ltd 100% 100%

13. Dha/UZR-13 Improvement of Dhaka Aricha highway-Kalatipara GC

via Vakurta bazar. and construction of appurtenant

structures.

8.13 Km 12.43 Km 19.59 19.59 NCB Yes 1/6/2004 7/9/2005 3/30/2006 12/15/2003 M/S Columbia

Engineers

30% 30%

Improvement of Dhaka Aricha RHD-Mugrakanda-

M.pur.city prot. Embank. Road and construction of

appurtenant structures.

4.30 Km 0.00 0% 0%

14. Nara/UZR-14 Improvement of Taltola-Ananda bazar extended up to

RHD-Dhaka-Chittagong road and construction of

appurtenant structures.

15.86 Km 23.94 Km 188.15 188.15 NCB Yes 7/14/2005 1/15/2007 5/30/2008 7/7/2005 JV of Reza

Construction Ltd &

MBEL

100% 100%

Improvement of Kanchan GC Somakhali bazar-

Chanpara R&H Road and construction of appurtenant

structures.

8.08 Km 0.00

3

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

15. Raj/UZR-15 Improvement of Jholmolia hat - Mollahpara hat and

construction of appurtenant structures.

14.58 Km 16.08 Km 77.28 77.28 NCB Yes 12/27/2003 6/29/2005 12/30/2006 12/10/2003 ITCL-SEL -JV 96% 96%

Improvement of Arani - Galimpur Ferry ghat and

construction of appurtenant structures.

1.50 Km 0.00 0% 0%

16. Pab/UZR-16 Improvement of Santhia 24 - Mile Azahar Afshar Road

and construction of appurtenant structures.

4.29 Km 14.32 Km 58.54 58.54 NCB Yes 1/1/2004 7/4/2005 2/15/2006 12/14/2003 M/S Pubali

Construction Co. Ltd

100% 100%

Improvement of Dubila - Sreekol Road -Ataikula road

and construction of appurtenant structures.

10.03 Km 0.00 100% 100%

17. Mou/UZR-17 Improvement of Gobindapur - Atghar - Ratgaon road

and construction of appurtenant structures.

8.76 Km 19.42 Km 131.08 131.08 NCB Yes 12/21/2003 6/23/2005 3/31/2007 12/6/2003 100% 100%

Improvement of Munshi bazar-Mokam bazar via

Sonatiki road and construction of appurtenant

structures.

10.66 Km 0.00 100% 100%

18. Com/UZR-18 Improvement of Homna - Dulalpur Road and

construction of 40 m bridge at chainage 9180 m

including other appurtenant structures.

8.00 Km 48.80 Km 401.58 401.58 ICB Yes 2/7/2008 8/10/2009 6/30/2010 1/31/2008 JV of Monico-ABC 100% 100%

Improvement of Homna - Meghna HQ upto Ferryghat

Road and construction of appurtenant structures.

10.00 Km 0.00

Improvement of Batakandi - Raipur Road and

construction of 45 m bridge at chainage 3700 m

including other appurtenant structures.

14.22 Km 0.00

Improvement of Chandina - Dollai Nowabpur and

construction of appurtenant structures.

11.45 Km 0.00

Improvement of Balutupa - Khaish Road and

construction of appurtenant structures.

5.13 Km 0.00

Joint Venture of

1. The Nirmitee Ltd

2. M/S Abdus Samad &

3. M/S Abdul Hafiz

4

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

19. Bra/UZR-19 Improvement of B.Baria - Nabinagar via Sadekpur

Road. and construction of appurtenant structures.

14.00 Km 37.37 Km 323.07 323.07 ICB Yes 11/21/2007 5/24/2009 11/30/2011 11/12/2007 CEC-NAS JV 100% 100%

Improvement of Nasirnagar Fundauk - Chatiain and

construction of appurtenant structures.

8.70 Km 0.00

Improvement of Bottali - Bitghar Road and construction

of 50 m bridge at chainage 3650 m including other

appurtenant structures.

7.68 Km

Improvement of Ashugonj - Talshahar Road and

construction of appurtenant structures.

4.55 Km 0.00

Improvement of B.Baria - Talshahar Bazar and

construction of appurtenant structures.

10.12 Km 0.00

20. Cha/UZR-20 Improvement of Sepaikandi-Kalir Bazar-Bashurchar-

Baushia Ferryghat-Dhaka : Ctg RHD Road (Chandpur

Portion) and construction of appurtenant structures.

19.39 Km 39.52 Km 138.43 138.43 ICB Yes 10/7/2007 4/9/2009 5/31/2010 10/1/2007 Islam Trading

Consortium Ltd.

60% 60%

Improvement of Faridganj - Brahmanpara Road and

construction of appurtenant structures.

5.62 Km 0.00

Improvement of Ibrahim B.T. Road (Chandpur-Lalpur

GC) and construction of 30 m bridge at chainage 5766

m including other appurtenant structures.

10.13 Km 0.00

Improvement of Sepaikandi - Beltali Road and

construction of appurtenant structures.

4.39 Km 0.00

21. Sun/UZR-21 Improvement of Sunamgonj - Chhatak Road via

Dowarabazar Road and construction of 40 m bridge at

chainage 10910 m including other appurtenant

structures.

32.54 Km 48.49 Km 121.15 121.15 ICB Yes 2/15/2008 8/18/2009 10/10/2009 1/28/2008 Islam Trading

Consortium Ltd.

34% 34%

Construction of 30 m bridge at chainage 13580 m

including other appurtenant structures.

30.00 m 0.00

5

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

Construction of 50 m bridge at chainage 21525 m

including other appurtenant structures.

50.00 m 0.00

Construction of 35 m bridge at chainage 23035 m

including other appurtenant structures.

35.00 m 0.00

Improvement of Kaitak R&H - Sirajganj Bazar and

construction of 30 m bridge at chainage 8000 m

including other appurtenant structures.

7.35 Km 0.00

Improvement of Kalipur - Haidarpur Road 8.60 Km 0.00

6

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

22. Syl/UZR-22 Improvement of Tajpur - Balagonj Road and

construction of appurtenant structures.

15.18 Km 17.19 Km 61.75 61.75 NCB Yes 7/10/2005 1/11/2007 12/31/2007 7/2/2005 JV of TBL-PTSL Ltd. 65% 65%

Improvement of Doyameer - Dewan Bazar and

construction of appurtenant structures.

2.01 Km 0.00 0% 0%

23. Naw/UZR-23 Improvement of Kalinagar Bairagipara - Sundarpur U.P.

road and construction of appurtenant structures.

5.45 Km Major portion of the road has been eroded by the adjacent river, for that reason the road is excluded from RTIP.

24. Man/UZR-24 Improvement of Singair - Charigram Road (extension

upto Jamsha ghat) and construction of 36 m bridge at

chainage 1100 m including other appurtenant

structures.

10.59 Km 16.68 Km 154.56 154.56 NCB Yes 4/27/2005 10/29/2006 6/30/2009 4/20/2005 Pubali Construction

Company Ltd.

80% 80%

Improvement of Joymontop (at Binnadingi) -

Maniknagar and construction of appurtenant structures.

6.09 Km 0.00

25. Mun/UZR-25 Improvement of Serajdikhan - Shaperchar Bazar and

construction of 51 m bridge at chainage 600 m

including other appurtenant structures.

7.24 Km 7.24 Km 31.93 31.93 NCB Yes 2/12/2005 8/16/2006 6/30/2007 2/2/2005 M/S Ismail Hossain 45% 45%

Construction of 54 m bridge at chainage 4545 m

including other appurtenant structures.

54.00 m 0.00 0% 0%

7

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

26. Sun/UZR-26 Improvement of Dharmapassa - Joysree Road and

construction of 90 m bridge at chainage 5500 m

including other appurtenant structures.

11.03 Km The Package UZR-26 has been shifted to from 2nd Phase to 4th Phase and renamed as Package Sun/UZR-314 dividing into two slices, (Slice No. UZR-314.1 and 314.2).0% 0%

27. Bog/UZR-27 Improvement of Dhunat - Shariakandi Road and

construction of 30 m bridge at chainage 7250 m

including other appurtenant structures.

19.00 Km 19.00 Km 172.62 172.62 NCB Yes 4/16/2006 10/18/2007 2/28/2009 4/10/2006 Mir Akhter Hossain 100% 100%

Construction of 30 m bridge at chainage 11030 m

including other appurtenant structures.

30.00 m 0.00

Construction of 100 m bridge at chainage 6800 m

including other appurtenant structures.

100.00 m 0.00

28. Sun/UZR-28 Improvement of Biswamverpur - Shaktiarkhola via HQ

Road and construction of 90 m bridge at chainage

5080 m including other appurtenant structures.

7.33 Km 7.33 Km 97.66 97.66 NCB Yes 10/19/2005 4/22/2007 3/31/2008 9/29/2005 Monico Ltd. 100% 100%

29. Bog/UZR-29 UZR-29.1 Improvement of Tarnihat - Chandonbaisha Road and

construction of 35 m bridge at chainage 4140 m

including other appurtenant structures.

11.19 Km 11.19 Km 72.44 72.44 NCB Yes 5/17/2005 11/18/2006 4/28/2008 5/7/2005 M/S A.S. Construction 100% 100%

UZR-29.2 Improvement of Naruamala - Matidhali Road and

construction of appurtenant structures.

9.50 Km The Slice UZR-29.2 of Package Bog/UZR-29 has been shifted to Package Bog/UZR-307, Slice UZR-307.1 (Sl. No. 307) and transferred from 2nd Phase to 3rd Phase.

UZR-29.3 Improvement of Baluahat - Sukhanpukur and

construction of appurtenant structures.

3.50 Km The Slice UZR-29.3 of Package Bog/UZR-29 has been shifted to Package Bog/UZR-307, Slice UZR-307.2 (Sl. No. 307) and transferred from 2nd Phase to 3rd Phase.

30. Nao/UZR-30 UZR-30.1 Improvement of Mirapara hat - Nithpur hat and

construction of appurtenant structures.

5.10 Km 10.41 Km 30.62 63.22 NCB Yes 5/3/2005 11/4/2006 10/15/2006 4/13/2005 M/S Ataur Rahman

Khan

100% 100%

UZR-30.2 Improvement of Gopinathpur - Mirapara hat and

construction of appurtenant structures.

5.31 Km 32.60 5/3/2005 11/4/2006 2/28/2007 4/13/2005 M/S Ataur Rahman

Khan

100% 100%

31. Bra/UZR-31 UZR-31.1 Improvement of Saydabad - Kullahpathar Road and

construction of appurtenant structures.

14.20 Km 14.20 Km 63.99 63.99 NCB Yes 3/13/2005 9/14/2006 3/31/2008 2/12/2005 Joint Venture of

i) M/S Rising

Construction

ii) Parisha Trade

System Ltd.

100% 100%

UZR-31.2 Improvement of Akhaura Bara Bazar GC - Comilla -

Sylhet RHD and construction of 30 m bridge at

chainage 4500 m including other appurtenant

structures.

5.94 Km This slice (UZR-31.2) has been excluded from RTIP as the road has already being improved under another project (RDP-20) of LGED.

8

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

UZR-31.3 Improvement of Sahabajpur - Sahajadpur Road and

construction of 30 m bridge at chainage 6620 m

including other appurtenant structures.

8.50 Km This slice (UZR-31.3) has been excluded from RTIP as the road has already being improved under another project (RDP-20) of LGED.

32. Gaz/UZR-32 UZR-32.1 Improvement of Joydebpur - Pubali Road and

construction of appurtenant structures.

6.50 Km 16.75 Km 41.90 104.30 NCB Yes 4/8/2005 10/10/2006 12/31/2007 3/31/2005 Joint Venture of HCL &

RC

100% 100%

UZR-32.2 Improvement of Kaliganj - Jangalia and construction of

appurtenant structures.

6.50 Km 40.09 5/2/2005 11/3/2006 11/4/2006 3/24/2005 JV of SHK & FEL Ltd. 100% 100%

UZR-32.3 Improvement of Kaliganj - Jamalpur road and

construction of appurtenant structures.

3.75 Km 22.32 5/2/2005 11/3/2006 6/10/2008 4/24/2005 Joint Venture of M/S of

Amzad Traders &

Suchi Enterprise

100% 100%

33. Com/UZR-33 UZR-33.1 Improvement of Birallah R&H - Dhampti hat GC. Road

and construction of appurtenant structures.

7.77 Km 13.27 Km 42.31 54.04 NCB Yes 4/7/2005 10/9/2006 3/31/2008 4/4/2005 Md. Abdul Mannan 77% 77%

UZR-33.2 Improvement of Noagaon - Panchkitta Road and

construction of 45 m bridge at chainage 3060 m

including other appurtenant structures.

5.45 Km 11.74 5/26/2005 11/27/2006 6/30/2007 4/21/2005 Arab Contractor's (BD)

Ltd.

29% 29%

Construction of 45 m bridge at chainage 3500 m

including other appurtenant structures.

45.00 m 0.00 0% 0%

9

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

UZR-34.1 Improvement of Kachua - Raghunathpur GC and

construction of appurtenant structures.

3.00 Km This slice (UZR-34.1) has been excluded from RTIP as the road has already being improved under another project (RDP-20) of LGED. 0% 0%

34. Cha/UZR-34 UZR-34.2 Improvement of Sendra - Palishara Bazar and

construction of appurtenant structures.

2.61 Km 2.61 Km 14.29 14.29 NCB No2 2/26/2005 8/30/2006 12/30/2006 2/19/2005 Mark Builders Ltd. 100% 100%

35. Joy/UZR-35 UZR-35.1 Improvement of Boiragipara - Matrai Hat Road and

construction of appurtenant structures.

3.06 Km 15.59 Km 14.29 66.74 NCB Yes 4/7/2005 10/9/2006 3/30/2008 4/4/2005 Ram Babu 100% 100%

UZR-35.2 Improvement of Kalai - Moslemgonj Road and

construction of appurtenant structures.

8.07 Km 30.46 4/6/2005 10/8/2006 3/31/2009 4/3/2005 Joint Venture of

(i) M/S Parisha Trade

& System Ltd.

(ii) M/S Ethen

Enterprise

75% 75%

UZR-35.3 Improvement of Itakhola - Shirotti and construction of

appurtenant structures.

4.46 Km 22.00 4/3/2005 10/5/2006 11/30/2007 3/19/2005 Ram Babu 100% 100%

0% 0%2 Previously it was shown as a prior review contract alongwith Slice No. UZR-34.1. 0% 0%

10

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

36. Mou/UZR-36 UZR-36.1 Improvement of Rathuli - Azimgonj and construction of

36 m bridge at chainage 2450 m including other

appurtenant structures.

2.54 Km 27.15 Km 20.50 135.83 NCB Yes 4/17/2005 10/19/2006 10/18/2006 3/17/2005 China Geo-

Engineering

Corporation

100% 100%

UZR-36.2 Improvement of Sarker Bazar - Gurarai Bazar. and

construction of appurtenant structures.

9.65 Km 37.70 5/12/2005 11/13/2006 6/30/2007 4/2/2005 China Geo-

Engineering

Corporation

100% 100%

UZR-36.3 Improvement of Brahman Bazar - Fenchugonj and

construction of appurtenant structures.

14.96 Km 67.14 4/30/2005 11/1/2006 4/30/2007 3/17/2005 China Geo-

Engineering

Corporation

100% 100%

UZR-36.4 Construction of 48 m bridge at chainage 8300 m on

Gobindapur-Atghar-Ratgaon Road.

48.00 m 10.49 4/17/2005 10/19/2006 10/18/2006 3/28/2005 China Geo-

Engineering

Corporation

100% 100%

37. Nar/UZR-37 UZR-37.1 Improvement of Raipura Upazila HQ - Narsingdi District

HQ Road and construction of appurtenant structures.

8.20 Km 11.51 Km 60.85 80.04 NCB Yes 3/11/2006 9/12/2007 6/30/2009 2/28/2006 Orient Trading &

Builder's Ltd

100% 100%

UZR-37.2 Improvement of Narsingdi - Putia Road. and

construction of appurtenant structures.

3.31 Km 19.19 4/5/2005 10/7/2006 11/29/2006 3/29/2005 M/S Amzad Traders 100% 100%

38. Sir/UZR-38 UZR-38.1 Improvement of Someshpur R&H - Randhunibari hat

and construction of 60 m bridge at chainage 200 m

including other appurtenant structures.

2.74 Km 14.40 Km 31.94 59.95 NCB Yes 5/26/2005 11/27/2006 2/28/2009 5/11/2005 M/S Khondaker

Shaheen Ahamed

100% 100%

UZR-38.2 Improvement of Songacha R&H - Bohuli Hat and

construction of appurtenant structures.

4.68 Km 16.08 5/20/2005 11/21/2006 12/31/2007 5/5/2005 Joint Venture of DJS

Consortium Ltd.

100% 100%

UZR-38.3 Improvement of Dhamai kandi R&H - Solonga GC and

construction of appurtenant structures.

6.98 Km 11.93 5/24/2005 11/25/2006 6/30/2007 5/9/2005 Islam Trading

Consortium Ltd.

24% 24%

UZR-39.1 Improvement of Lalpur - Gopalpur Railway gate. and

construction of appurtenant structures.

6.55 Km Dropped from the project 0% 0%

11

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

39. Nat/UZR-39 UZR-39.2 Improvement of Dattapara-Halsha UP to Chira Kola and

construction of appurtenant structures.

4.24 Km 4.24 Km 28.33 28.33 NCB No 7/25/2005 1/26/2007 6/30/2007 7/18/2005 M/S Rahaman

Construction

100% 100%

40. Syl/UZR-40 UZR-40.1 Improvement of Salutikar - Shaheber Bazar - Horipur

and construction of appurtenant structures.

7.26 Km 10.91 Km 31.55 47.54 NCB Yes 2/15/2006 8/19/2007 6/30/2008 12/29/2005 JV of Taher Brothers

Ltd & Parisha Trade

System Ltd.

51% 51%

UZR-40.2 Improvement of Zakiganj - Dubag Bazar and

construction of appurtenant structures.

3.65 Km 15.99 11/27/2005 5/31/2007 2/29/2008 11/10/2005 PTSL-ATCO (JV) 72% 72%

41. Raj/UZR-41 UZR-41.1 Improvement of Bhawanigonj - Bandaikhara and

construction of 90 m bridge at chainage 9110 m

including other appurtenant structures.

9.28 Km 15.78 Km 62.05 65.14 NCB Yes 3/28/2005 9/29/2006 3/31/2008 3/20/2005 AML-BCPL (JV) 88% 88%

12

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

UZR-41.2 Improvement of Mundumala Hat to Hat bakoil (GCM)

road and construction of appurtenant structures.

6.50 Km 3.09 3/15/2005 9/16/2006 9/11/2006 3/5/2005 TE-SA-NH (JV) 18% 18%

42. Bog/UZR-42 Improvement of Omarpur - Dhupchanchia via Talora

Road. and construction of appurtenant structures.

24.00 Km The road has been transferred from LGED to RHD and consequently the package Bog/UZR-42 has been dropped from RTIP. 0% 0%

43. Mun/UZR-43 Improvement of Sepaikandi-Kalir Bazar-Bashurchar-

Baushia Ferryghat-Dhaka : Ctg RHD Road (Munshigonj

Portion) and construction of appurtenant structures.

4.85 Km 4.85 Km 33.27 33.27 NCB Yes 2/8/2006 8/12/2007 6/30/2010 1/16/2006 Project Builders Ltd. 65% 65%

44. Mun/UZR-44 Improvement of Dhaka Mawa RHD at Tegharia-Bibir

Bazar-Shaper Bazar-Taltala hat GC-Betka Road

(Munshigonj Portion) and construction of appurtenant

structures.

9.75 Km 9.75 Km 62.64 62.64 NCB Yes 6/6/2005 12/8/2006 6/30/2007 5/29/2005 Pubali Construction

Limited

100% 100%

45. Hab/UZR-45 Improvement of Madhabpur R&H Nasirnagar Road and

construction of appurtenant structures.

3.12 Km As this road is improved by another project of LGED, so it is dropped. 0% 0%

Improvement of Mouzpur-ChangarBazar and

construction of appurtenant structures.

5.00 Km As this road is improved by another project of LGED, so it is dropped. 0% 0%

Improvement of Madhabpur - Chowmohani Bazar and

construction of appurtenant structures.

6.60 Km Major rehabilitation was found essential, so it has been taken under Maintenance program of RTIP. 0% 0%

Improvement of Monohorodi H/Q - Panchabati Ferry

Ghat Road and construction of appurtenant structures.

11.35 Km Major rehabilitation was found essential, so it has been taken under Maintenance program of RTIP. 0% 0%

46. Nar/UZR-46 Improvement of Brajerkandi R&H - Lakhpur Bazar and

construction of appurtenant structures.

6.23 Km 6.23 Km 27.12 27.12 NCB No 12/1/2005 6/4/2007 6/30/2008 11/14/2005 Bangladesh Business

Corporation

100% 100%

13

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

47. Nat/UZR-47 Improvement of Jonailhat -Dharabarisha hat Road and

construction of 30 m bridge at chainage 3900 m

including other appurtenant structures.

7.60 Km As the both GCMs are connected with all-weather road & cost of the road is abnormally high, so it is dropped. 0% 0%

48. Nao/UZR-48 Improvement of R&H Road Khalshi - Raigaon up to

Matazi and construction of appurtenant structures.

8.20 Km Dropped from the project 0% 0%

49. Man/UZR-49 Improvement of Uthali - Paturia via Nali Road and

construction of appurtenant structures.

7.45 Km 14.76 Km 127.30 127.30 NCB Yes 10/2/2005 4/5/2007 11/30/2008 9/25/2005 100% 100%

Improvement of Ghior-Jabra Road and construction of

appurtenant structures.

7.31 Km 0.00

JV of Orient Trading

and Builders Ltd.

(OTBL) & Kazi

International

Construction Ltd.

(KICL)

14

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

50. Pab/UZR-50 Improvement of Mohela GCM - Sharatgonj GC via

Parshadanga Hat Road and construction of appurtenant

structures.

6.78 Km 11.37 Km 13.80 13.80 NCB Yes 3/5/2006 9/6/2007 9/5/2007 2/22/2006 JV of TBL-PTSL 35% 35%

Improvement of Chatmohar R&H at Janata Bank-

Astomonisha GCCM via Noornagar and construction of

50 m bridge at chainage 4195 m including other

appurtenant structures (100m & 158m bridge were

include).

4.59 Km 0.00 0% 0%

51. Hab/UZR-51 Improvement of Baniachang - Azmirigonj Road via

Shibpasha Road. and construction of appurtenant

structures.

15.53 Km 15.53 Km 4.77 4.77 NCB No 7/5/2006 1/6/2008 6/30/2008 6/5/2006 PCCL-BBC JV 10% 10%

52. Syl/UZR-52 Improvement of Zakigonj - Vingair Bazar-Laxmi Bazar-

Dubag Bazar and construction of appurtenant

structures.

13.40 Km 13.40 Km 72.71 72.71 NCB Yes 5/23/2005 11/24/2006 4/30/2007 5/16/2005 Concord Pragatee

Consortium Ltd.

100% 100%

53. Nao/UZR-53 UZR-53.1 Improvement of Bottali - Srimantapur Road and

construction of appurtenant structures.

6.36 Km 6.36 Km 0.00 0.00 NCB No Oct'06 Apr'08 0% 0%

15

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

UZR-53.2 Improvement of Niamatpur - Kharibari Chowbaria Road

and construction of appurtenant structures.

4.31 Km This Slice (UZR-53.2) has been excluded from RTIP as the road is being improved under another project (RIDP-3) of LGED. 0% 0%

54. Nar/UZR-54 UZR-54.1 Improvement of Bajnabo RHD - Putia Bazar via Palpara

bazar and construction of 60 m bridge at chainage

6500 m including other appurtenant structures.

6.35 Km 6.35 Km 22.62 22.62 NCB No 12/1/2005 6/4/2007 6/30/2008 10/31/2005 Orient Trading &

Builder's Ltd

100% 100%

UZR-54.2 Improvement of Baniadi R&H - Shibpur Bazar and

construction of appurtenant structures.

2.00 Km Major rehabilitation was found essential, so it has been taken under Maintenance program of RTIP. 0% 0%

UZR-55.1 Improvement of Dhaka Mawa RHD at Tegharia-Bibir 5.00 Km The Slice UZR-55.1 of Package Dha/UZR-55 has been shifted to Package Dha/UZR-309 (Sl. No. 309) as a single package and transferred from 3rd Phase to 2nd Phase,

Bazar-Shaper Bazar-Taltala hat GC-Betka Road

(Dhaka Portion) and construction of 65 m bridge at

chainage 6720 m including other appurtenant

structures.

because the other portion of the same road (15 Km.) in Munshigonj district (package no. Mun/UZR-44) has also been shifted from 3rd phase to 2nd phase.

55. Dha/UZR-55 UZR-55.2 Improvement of Kalatia - Amin Bazar via Hazratpur UP

and construction of appurtenant structures.

8.50 Km 20.79 Km 58.17 187.73 NCB Yes 5/21/2006 11/22/2007 6/30/2008 5/10/2006 JV of BTI-MMBE 100% 100%

UZR-55.3 Improvement of Hasnabad Power Station - Doleshar

Bibir Bazar and construction of appurtenant structures.

12.29 Km 129.56 5/20/2006 11/21/2007 5/7/2008 5/8/2006 Orient Trading &

Builder's Ltd

100% 100%

56. Bog/UZR-56 UZR-56.1 Improvement of Sonahata-Bagbari Road via Berebari

and construction of 45 m bridge at chainage 875 m

including other appurtenant structures.

7.14 Km 36.20 Km 23.74 135.46 NCB Yes 4/26/2005 10/28/2006 12/30/2007 4/10/2005 M/S S. S. Engineers 43% 43%

16

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

UZR-56.2 Improvement of Simabari - Ranir hat Road and

construction of appurtenant structures.

15.20 Km 24.84 6/12/2005 12/14/2006 6/30/2007 6/2/2005 M/S Ismail Hossain 35% 35%

UZR-56.3 Improvement of Durgapur - Jamadarpukur Road and

construction of appurtenant structures.

13.86 Km 86.88 7/5/2005 1/6/2007 11/30/2007 6/26/2005 Islam Trading

Consortium Ltd.

100% 100%

17

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

57. Gaz/UZR-57 UZR-57.1 Improvement of Giaspur Bazar - Aral Bazar and

construction of appurtenant structures.

9.47 Km 19.65 Km 64.98 108.69 NCB Yes 6/7/2006 12/9/2007 6/20/2010 5/31/2006 M/S Rising

Construction

92% 92%

UZR-57.2 Improvement of Sreepur - Gusahinga Bazar and

construction of appurtenant structures.

6.78 Km 23.04 6/8/2006 12/10/2007 8/31/2008 6/1/2006 JV of M/S Moyen

Uddin Bashi & LM

Traders

60% 60%

UZR-57.3 Improvement of Baliadi R&H to Chandabaha and

construction of appurtenant structures.

3.40 Km 20.66 6/1/2006 12/3/2007 6/30/2009 5/25/2006 JV of M/S SH & Akhter 65% 65%

58. Com/UZR-58 UZR-58.1 Improvement of Doulkhar - Boxgonj Road and

construction of appurtenant structures.

15.00 Km 24.38 Km 71.52 114.56 NCB Yes 4/12/2005 10/14/2006 7/15/2008 4/6/2005 M/S Surma

International

87% 87%

18

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

UZR-58.2 Improvement of Barura bazar - Adda GC Road and

construction of appurtenant structures.

9.38 Km 43.04 6/11/2005 12/13/2006 7/30/2008 4/21/2005 JV of

i) Alhaj Abdul Haque

ii) M/S. Taher & Sons

and

iii) Rana International

Builders

100% 100%

UZR-59.1 Improvement of Katakhali - Gondamara Road and

construction of appurtenant structures.

10.45 Km This Slice (UZR-59.1) has been excluded from RTIP as the road is being improved under another project (RDP-20) of LGED. 0% 0%

59. Cha/UZR-59 UZR-59.2 Improvement of Haimchar - Rampur Bazar GC and

construction of appurtenant structures.

4.30 Km 4.30 Km 26.58 26.58 NCB No 3/21/2006 9/22/2007 4/30/2008 2/28/2006 Md. Moshiur Rahman

Chowdhury

100% 100%

60. Mun/UZR-60 UZR-60.1 Improvement of Kanakshar - Nagerhat Bazar and

construction of appurtenant structures.

3.12 Km 5.64 Km 4.93 14.10 NCB No 11/27/2005 5/31/2007 12/31/2008 11/20/2005 Haider Construction

Pvt. Ltd.

32% 32%

UZR-60.2 Improvement of Khanbari-Goalimandra and

construction of appurtenant structures.

2.52 Km 9.17 4/20/2006 10/22/2007 10/15/2007 4/4/2006 M.S Bashundhara 40% 40%

61. Nao/UZR-61 UZR-61.1 Improvement of Nischintapur - Mirapara hat and

construction of appurtenant structures.

2.19 Km 8.76 Km 10.13 10.13 NCB No 4/2/2006 10/4/2007 2/28/2008 3/22/2006 Milon-Bhuiyan JV 100% 100%

UZR-61.2 Improvement of Deluabari-Chalk Gowri Road and

construction of appurtenant structures.

6.57 Km 0.00 Oct'06 Apr'08 0% 0%

0% 0%

19

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

0% 0%

UZR-62.1 Improvement of Sonaichandi - Chuthipur Road and

construction of appurtenant structures.

2.15 Km As this road has been transffered to RHD, so it is dropped. 0% 0%

62. Naw/UZR-62 UZR-62.2 Improvement of Dobarmore - Akkelpur hat Road. and

construction of appurtenant structures.

8.05 Km 8.05 Km 44.40 44.40 NCB Yes 1/30/2006 8/3/2007 8/3/2007 1/19/2006 Kh. Shaheen Ahmed 100% 100%

UZR-63.1 Improvement of Sreekal - Ataikola and construction of

appurtenant structures.

7.00 Km As this road is improved by another project of LGED, so it is dropped. 0% 0%

63. Pab/UZR-63 UZR-63.2 Improvement of Bera - Natiabari R&H Road. and

construction of appurtenant structures.

4.08 Km 4.08 Km 15.60 15.60 NCB No 12/12/2005 6/15/2007 6/15/2007 11/27/2005 Sarkar Golam

Mohammad

100% 100%

64. Raj/UZR-64 UZR-64.1 Improvement of Tetulia - Bagha and construction of

appurtenant structures.

7.60 Km 7.60 Km 33.52 33.52 NCB Yes 1/11/2006 7/15/2007 4/30/2008 1/3/2006 Sarkar Golam

Mohammad

100% 100%

UZR-64.2 Improvement of Mirzagonj Bazar - Harirampur Hat and

construction of appurtenant structures.

3.60 Km As this road has been transferred to RHD, so it is dropped. 0% 0%

65. Syl/UZR-65 UZR-65.1 Improvement of Beali Bazar - BrhammonBazar and

construction of appurtenant structures.

4.15 Km 8.58 Km 19.82 47.42 NCB Yes 4/24/2005 10/26/2006 2/29/2008 4/17/2005 The Joint Venture of

(i) M/S Mahmud

Mamun &

(ii) Suchi Enterprise

Ltd.

100% 100%

UZR-65.2 Improvement of Gowainghat - Radhanagor and

construction of appurtenant structures.

4.43 Km 27.60 2/15/2005 8/19/2006 1/31/2008 2/8/2005 CEC-RC, JV 100% 100%

66. Joy/UZR-66 UZR-66.1 Improvement of Hitchmi - Madhainagar road and

construction of appurtenant structures.

3.93 Km 10.00 Km 18.13 35.59 NCB Yes 10/19/2005 4/22/2007 3/30/2008 10/12/2005 Md. Nazir Hossain 100% 100%

UZR-66.2 Improvement of Itkhola - Jamalgonj and construction of

appurtenant structures.

6.07 Km 17.47 11/9/2005 5/13/2007 7/31/2008 11/2/2005 JV of (i) Parisha Trade

System Ltd.

(ii) Ethen Enterprise

65% 65%

67. Hab/UZR-67 UZR-67.1 Improvement of Nabigonj - Inathgonj Road and

construction of appurtenant structures.

8.83 Km 8.83 Km 50.98 50.98 NCB Yes 12/13/2005 6/16/2007 4/30/2008 11/30/2005 M/S Basic Engineering

& Azad and Brother

100% 100%

20

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

UZR-67.2 Improvement of Chunarughat - Assampara - Balla Road

and construction of appurtenant structures.

4.40 Km Major rehabilitation was found essential, so it has been taken under Maintenance program of RTIP. 0% 0%

68. Gaz/UR-1 Azmatpur-Narun road 3.06 Km 3.06 Km 10.30 10.30 NCB No 6/3/2005 12/5/2006 12/31/2007 4/26/2005 JV of M/S FEL-SHK 100% 100%

69. Gaz/UR-2 Baliadi-Dhaljoria Dubail road 5.07 Km 5.07 Km 15.11 15.11 NCB No 4/12/2005 10/14/2006 4/30/2008 4/4/2005 JV of M/S Olive & Rifat

Enterprise

100% 100%

70. Nara/UR-3 Haijadi UP-Probhakordi road 6.00 Km 6.00 Km 15.55 15.55 NCB No 3/31/2005 10/2/2006 9/30/2006 3/22/2005 Joint Venture of

(i) M/S SCM

Construction

(ii) M/S Ratna

Enterprise

(iii) Mohammadi

Traders

100% 100%

71. Nara/UR-4 Sanmandi UP Office-Kaikertek bazar Darikandi,

Sonakhali, Panchpir Darga road

3.03 Km 3.03 Km 11.02 11.02 NCB No 3/31/2005 10/2/2006 9/30/2006 3/22/2005 M/S SCM-Ahasan-

Ratna

100% 100%

72. Man/UR-5 Upazila HQ (Bhatara)-Dighulia UP Office via Enam

Bengrua road

7.30 Km 7.30 Km 24.71 24.71 NCB No 3/31/2005 10/2/2006 3/30/2009 3/24/2005 JV of M/S Garpara

Construction

100% 100%

73. Man/UR-6 Teota UP Office-Jafargonj GC (Poyla) road 5.80 Km 5.80 Km 18.77 18.77 NCB No 4/10/2005 10/12/2006 6/30/2007 4/3/2005 M/S M. R. Enterprise 100% 100%

74. Sir/UR-7 Dubil-Amsara road 7.24 Km 7.24 Km 18.43 18.43 NCB No 5/6/2005 11/7/2006 4/30/2007 4/21/2005 M/S Turna Enterprise 100% 100%

75. Sir/UR-8 Songacha DR-Songacha UP road 6.28 Km 6.28 Km 12.38 12.38 NCB No 5/19/2005 11/20/2006 12/31/2007 5/4/2005 M/S A. S. Construction 100% 100%

76. Bog/UR-9 Bihigram hat-Baldakuri road 5.26 Km 5.26 Km 2.88 2.88 NCB No 5/14/2005 11/15/2006 6/30/2007 5/7/2005 M/S SRF Joint Venture 37% 37%

77. Bog/UR-10 Palikukrul (Nungola UP)-Uchalbaria hat road 3.60 Km 3.60 Km 8.92 8.92 NCB No 4/5/2005 10/7/2006 2/25/2007 3/29/2005 M/S Pabons 100% 100%

78. Bog/UR-11 Perirhat-Tarnihat via Mohishban UP road 5.00 Km 5.00 Km 13.39 13.39 NCB No 5/14/2005 11/15/2006 11/14/2006 5/4/2005 M/S Ataur Rahaman

Khan

100% 100%

21

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

79. Bog/UR-12 Malancha hat-Jamgram UP 4.30 Km 4.30 Km 3.84 3.84 NCB No 4/30/2005 11/1/2006 6/30/2007 4/25/2005 M/S Mahmud & Badrul

Joint Venture

42% 42%

80. Raj/UR-13 Goalpara-Pakri UP 3.50 Km 3.50 Km 7.61 7.61 NCB No 5/24/2005 11/25/2006 11/18/2006 5/15/2005 Khandakar Mainul

Islam

100% 100%

81. Raj/UR-14 Hatgangopara-Gobindapara UP 6.20 Km 6.20 Km 17.35 17.35 NCB No 5/25/2005 11/26/2006 1/20/2007 5/18/2005 M/S Khandakar Shahin

Ahmed

100% 100%

82. Raj/UR-15 Gaonpara Bazar-Bhalukgachi UP road via Sharishabari

hat

13.89 Km 13.89 Km 31.40 31.40 NCB Yes 6/14/2005 12/16/2006 9/30/2008 6/7/2005 Md. Fazlur Rahman &

Md. Kamal Uddin JV

100% 100%

83. Raj/UR-16 Darshanpara UP-Baghdhani road 8.50 Km 8.50 Km 9.30 9.30 NCB No 5/16/2005 11/17/2006 4/30/2008 4/23/2005 Parisha Trade System

Ltd.

68% 68%

84. Nat/UR-17 Lalpur Bonpara R&H-Madhubari Chowhat (Moniruddin

Akand)-Kadimchilan UP Office road

10.40 Km 10.40 Km 33.59 33.59 NCB Yes 7/25/2005 1/26/2007 10/30/2007 7/18/2005 M/S Mita Construction 100% 100%

85. Nat/UR-18 Patulhat-Khajura UP Office 7.40 Km 7.40 Km 30.18 30.18 NCB Yes 12/18/2005 6/21/2007 6/18/2007 12/8/2005 M/S Habib Ahsan Babu 100% 100%

86. Naw/UR-19 Radhanagar UP-Akkelpur GC via Jamil road 1.15 Km 1.15 Km 4.51 4.51 NCB No 4/25/2005 10/27/2006 10/26/2006 4/20/2005 Md. Kamal Uddin 100% 100%

87. Naw/UR-20 Nachole UP Office (Bholar more)-Pirpur hat 6.70 Km 6.70 Km 19.10 19.10 NCB No 4/30/2005 11/1/2006 10/31/2006 4/24/2005 Md. Fazlur Rahman 100% 100%

88. Pab/UR-21 Chhaikhola Upazila road-Kachihata UP road 2.20 Km 2.20 Km 5.33 5.33 NCB No 4/16/2005 10/18/2006 9/16/2006 4/9/2005 M/S Orin Engineers 100% 100%

22

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

89. Pab/UR-22 Shayamnagar GC-Raninagar UP road 6.47 Km 6.47 Km 4.86 4.86 NCB No 6/22/2005 12/24/2006 10/31/2008 6/18/2005 Habib Traders &

Shamsuzzaman JV

36% 36%

90. Joy/UR-23 Balighata UP Office-Jibonpur-Baghjana UP road 9.25 Km 9.25 Km 29.46 29.46 NCB Yes 4/10/2005 10/12/2006 10/31/2008 4/1/2005 Md. Nazir Hossain 100% 100%

91. Joy/UR-24 Akkelpur-Rukindipur UP Office via Jamalgonj

Charmatha road

9.14 Km 9.14 Km 26.34 26.34 NCB No 4/9/2005 10/11/2006 12/30/2007 4/3/2005 JV of (i) M/S Parisha

Trade System Ltd.

(ii) M/S Ethen

Enterprise

100% 100%

92. Nao/UR-25 Bakroil-Mandain-Ustihat road 8.62 Km 8.62 Km 13.93 13.93 NCB No 5/3/2005 11/4/2006 3/31/2008 4/12/2005 M/S Parisha Trade

System Ltd.

81% 81%

93. Nao/UR-26 Shihara UP-Ladipur road 4.17 Km 4.17 Km 11.65 11.65 NCB No 4/25/2005 10/27/2006 11/15/2007 4/6/2005 Md. Fazlur Rahman 100% 100%

94. Dha/UR-27 Sutarpara UP Office-Halerbazar road 1.26 Km 1.26 Km 3.84 3.84 NCB No 4/9/2005 10/11/2006 10/31/2006 3/24/2005 M/S United Builders 100% 100%

95. Dha/UR-28 Shikaripara UP-Jamsha bazar via Bishompur road 9.00 Km 9.00 Km 30.43 30.43 NCB Yes 3/7/2005 9/8/2006 12/30/2006 2/24/2005 J.V of Delco

Engineering & Jewel

Engineering

100% 100%

23

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

96. Dha/UR-29 Gangutia UP Office-Kawali bazar road 8.14 Km 8.14 Km 17.29 17.29 NCB No 3/7/2005 9/8/2006 4/30/2008 2/24/2005 J.V of Delco

Engineering & Jewel

Engineering

100% 100%

97. Nar/UR-30 Charsindur UP-Jamtala bazar via Chalana road 3.25 Km 3.25 Km 10.80 10.80 NCB No 4/6/2005 10/8/2006 12/31/2006 3/21/2005 M/S Hossain & Sons 100% 100%

98. Nar/UR-31 Bajnabo UP Office-Bhangarghat-Belabo road 2.58 Km 2.58 Km 6.10 6.10 NCB No 6/1/2005 12/3/2006 8/20/2007 5/17/2005 M/S Shahil Enterprise 100% 100%

99. Mun/UR-32 Chander bazar-Subachani road 3.35 Km 3.35 Km 9.22 9.22 NCB No 4/4/2005 10/6/2006 3/15/2007 3/28/2005 Pearl Engineering &

Construction

100% 100%

100. Mun/UR-33 Masadgaon-Kahetara-Nagerhat road 2.71 Km 2.71 Km 4.25 4.25 NCB No 3/23/2005 9/24/2006 6/30/2007 3/14/2005 M/S Serajul Islam 54% 54%

101. Mun/UR-34 Bakultala-Banglabazar road 3.72 Km 3.72 Km 11.83 11.83 NCB No 4/10/2005 10/12/2006 3/31/2008 3/30/2005 Haider Construction

(Pvt) Ltd.

85% 85%

102. Com/UR-35 Nabagram-Munshirhat-Kadoir road 9.80 Km 9.80 Km 24.13 24.13 NCB No 3/20/2005 9/21/2006 6/30/2007 3/14/2005 Eva Overseas

Corporation

100% 100%

24

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

103. Com/UR-36 Monohargonj-Hasnabad road 8.06 Km 8.06 Km 13.92 13.92 NCB No 3/21/2005 9/22/2006 6/30/2008 3/12/2005 M/S Tushar Enterprise 45% 45%

104. Com/UR-37 Pipulia-Hazatkhola-Bagmara road 1.64 Km 1.64 Km 1.86 1.86 NCB No 3/19/2005 9/20/2006 9/13/2006 3/14/2005 Desh Development

Corporation

26% 26%

105. Com/UR-38 Pipulia-Hazatkhola road 2.10 Km 2.10 Km 1.14 1.14 NCB No 3/21/2005 9/22/2006 9/13/2006 3/14/2005 M/S Kamal

Construcrion

25% 25%

25

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

106. Com/UR-39 Pipulia-Bagmara via Hazatkhola road 6.55 Km 6.55 Km 16.67 16.67 NCB No 4/20/2005 10/22/2006 5/30/2007 4/13/2005 Eva Overseas

Corporation

77% 77%

107. Com/UR-40 Sanchail-Bangura road 8.47 Km 8.47 Km 16.72 16.72 NCB No 4/9/2005 10/11/2006 7/30/2008 3/28/2005 Shah Islam

Corporation Ltd.

55% 55%

108. Bra/UR-41 Naogaon Bazar-Pattar UP Office upto 2.90 Km 2.90 Km 7.81 7.81 NCB No 3/25/2005 9/26/2006 9/19/2006 3/5/2005 M/S Azad & Brothers 100% 100%

109. Bra/UR-42 Binauti UP Office (Rauth hat bazar)-Tinlakhpir via

Nemtabad bazar road

6.99 Km 6.99 Km 26.13 26.13 NCB No 10/22/2005 4/25/2007 10/31/2008 10/12/2005 Project Builders Ltd. 100% 100%

26

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

110. Bra/UR-43 Akhaura (Fire Brigade)-Khalajura-Gazir bazar-

Abdullahpur (Checkpost) road

4.16 Km 4.16 Km 5.15 5.15 NCB No 7/24/2005 1/25/2007 6/30/2008 7/12/2005 Mr. Sayedur Rahman 37% 37%

111. Cha/UR-44 Palakhal-Aliara road 3.38 Km 3.38 Km 11.97 11.97 NCB No 4/9/2005 10/11/2006 12/30/2007 4/3/2005 M/S Property

Construction

100% 100%

112. Cha/UR-45 Shahapur-Aliara road 3.15 Km 3.15 Km 10.33 10.33 NCB No 5/11/2005 11/12/2006 3/30/2007 5/2/2005 M/S. Shahid Brothers 100% 100%

113. Syl/UR-46 Bandhaghat-Mogalgaon UP Office road 4.95 Km 4.95 Km 16.56 16.56 NCB No 5/1/2005 11/2/2006 12/31/2006 4/24/2005 The Nirmitee Ltd. 100% 100%

114. Syl/UR-47 Tajpur-Charishabpur-Mandaruka-Khadimpur road 12.50 Km 12.50 Km 41.45 41.45 NCB Yes 6/8/2005 12/10/2006 4/3/2007 5/28/2005 China Geo-

Engineering

Corporation

100% 100%

115. Syl/UR-48 Nakikhali-Chanpur-Singerkach bazar road 9.80 Km 9.80 Km 25.43 25.43 NCB No 6/9/2005 12/11/2006 6/15/2008 6/2/2005 M/S M. Alam 100% 100%

116. Mou/UR-49 Amtail-Kadupur road 2.45 Km 2.45 Km 6.86 6.86 NCB No 5/7/2005 11/8/2006 11/6/2006 4/21/2005 M/S. Md. Ilias 100% 100%

117. Mou/UR-50 Paschim Kadamhata MP bazar-Syamerbhanga road 3.98 Km 3.98 Km 8.91 8.91 NCB No 5/9/2005 11/10/2006 11/10/2006 4/19/2005 Md. Monayem Khan 100% 100%

118. Mou/UR-51 Asian RHD-Uttarbag UP Office road 1.13 Km 1.13 Km 2.17 2.17 NCB No 4/17/2005 10/19/2006 10/18/2006 4/2/2005 M.A. Matin 90% 90%

119. Mou/UR-52 Bauli-Nijbahadurpur road 8.85 Km 8.85 Km 16.13 16.13 NCB No 5/12/2005 11/13/2006 11/30/2008 4/27/2005 M.A.H.A.I JV 75% 55%

27

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

120. Hab/UR-53 Chunarughat-Paikpara UP Office 6.50 Km 6.50 Km 21.99 21.99 NCB No 3/24/2005 9/25/2006 12/12/2006 3/15/2005 M/S Azad and Brothers 100% 100%

121. Hab/UR-54 Islampur-Gulgaon via Chichircoat-Chalkrampur road 7.20 Km 7.20 Km 24.29 24.29 0 No 6/5/2005 12/7/2006 3/31/2010 5/23/2005 JV of AMR Consortium 100% 100%

122. Sun/UR-55 Palash-Salukabad-Jinarpur road 5.80 Km 5.80 Km 16.19 16.19 NCB No 5/10/2005 11/11/2006 12/15/2008 5/6/2005 Joint Venture of (i) M/S

Belal Enterprise

(ii) M/S Mahbub

Enterprise

(iii) M/S Priti Enterprise

100% 100%

123. Sun/UR-56 Pagla-Birgaon road 4.50 Km 4.50 Km 10.43 10.43 NCB No 5/10/2005 11/11/2006 4/30/2007 5/4/2005 Joint Venture of

(i) Royal Trading

Corporation

(ii) Badrul Huda Mukul

(iii) M/S F. Islam

Construction

100% 100%

124. Sun/UR-57 Shahpur-Teranagar-Lalbazar road 2.56 Km 2.56 Km 4.99 4.99 NCB No 5/10/2005 11/11/2006 4/30/2007 4/29/2005 Joint Venture of

(i) A.T.M. Misbah

(ii) M/S Nurul Islam

100% 100%

125. Sun/UR-58 Dewrai-Sewra road 4.15 Km 4.15 Km 8.36 8.36 NCB No 5/10/2005 11/11/2006 1/11/2008 4/29/2005 Joint Venture of

(i) Soweb Enterprise

(ii) Shamim Ahmed

(iii) Nazrul Islam

100% 100%

126. Raj/UR-59 Alipur hat-Puran Taherpur Kekarutala via Noapara UP

road

10.22 Km 10.22 Km 25.61 25.61 NCB No 5/7/2005 11/8/2006 11/10/2006 4/7/2005 TSL-RIB JV 100% 100%

127. Nao/UR-60 Rasulpur UP Badmallikpur hat-Sarakdanga hat road 7.20 Km 7.20 Km 19.60 19.60 NCB No 5/3/2005 11/4/2006 3/30/2007 4/13/2005 Mr. Moyen Uddin

(Bashi)

100% 100%

128. Dha/UR-61 Bismile(at Dhaka- Aricha Hway)-Zirabo-Eaarpur UP

Office

5.65 Km 5.65 Km 10.45 10.45 NCB No 7/5/2005 1/6/2007 11/28/2007 6/27/2005 J.V of Delco

Engineering & Jewel

Engineering

100% 100%

129. Dha/UR-62 Jalsa RHD-Suapur GC via Sutipara UP Office 6.00 Km 6.00 Km 11.27 11.27 NCB No 12/15/2005 6/18/2007 3/28/2008 11/27/2005 Can Enterprise 100% 100%

28

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

130. Gaz/UR-63 Nagori UP Office-Amarul bazar 4.30 Km 4.30 Km 12.56 12.56 NCB No 12/13/2005 6/16/2007 6/11/2006 12/5/2005 The Joint Venture of

M/S Olive & Rifat

Enterprise

100% 100%

131. Man/UR-64 Pakuria bazar-Pucca UZR via Baliakhora UP road 2.00 Km 2.00 Km 5.67 5.67 NCB No 12/14/2005 6/17/2007 6/17/2007 12/7/2005 M/S Good Luck

Trading Corporation

100% 100%

132. Man/UR-65 Paila UP-Singiuri UP 3.29 Km 3.29 Km 2.85 2.85 NCB No 2/20/2006 8/24/2007 6/30/2008 2/13/2006 M/S M. M. Traders 35% 35%

133. Man/UR-66 Boyra UP-Kanthapara Bazar via Lesergonj Bazar 3.05 Km 3.05 Km 6.21 6.21 NCB No 12/14/2005 6/17/2007 12/30/2007 12/7/2005 M/S Good Luck

Trading Corporation

76% 76%

134. Nara/UR-67 Chowdhuribari GC-Kalagachia UP Office road 3.10 Km As this road is improved by another project of LGED, so it is dropped. 0% 0%

135. Nar/UR-68 Shilmandi UP Office RHD-Madhabdi GC road via

Fultala bazar road

4.65 Km 4.65 Km 15.79 15.79 NCB No 4/11/2006 10/13/2007 10/9/2007 4/5/2006 M/S Amzad Traders 100% 100%

136. Nar/UR-69 Kathalia UP Office-Rangpur bazar via Fazurkandi bazar

road

4.50 Km 4.50 Km 13.29 13.29 NCB No 12/19/2005 6/22/2007 12/31/2007 11/29/2005 Haider Construction

(Pvt.) Ltd.

100% 100%

137. Mun/UR-70 Kolapara UP Office-Dakhin Paiksha bazar via

Samaspur

2.00 Km 2.00 Km 6.11 6.11 NCB No 2/8/2006 8/12/2007 5/31/2009 1/23/2006 Proxima International 100% 100%

138. Mun/UR-71 Baligaon Baily bridge-Norpur road 3.60 Km 3.60 Km 11.42 11.42 NCB No 8/21/2006 2/22/2008 6/30/2009 7/26/2006 M/S Fair Builder's 100% 100%

139. Raj/UR-72 Bargachi UP-Haider hat via Talgachi 4.50 Km Dropped as the scheme did not seem technically feasible 0% 0%

29

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

140. Nao/UR-73 Manda UP Office-Pirpali Gopalparhat road 7.65 Km 7.65 Km 20.61 20.61 NCB No 11/21/2005 5/25/2007 1/15/2008 11/13/2005 Parisha Trade system

Ltd.

100% 100%

141. Nao/UR-74 Dhamoirhat UP office-Biharinagar Bazar 4.77 Km 4.77 Km 13.19 13.19 NCB No 11/21/2005 5/25/2007 6/15/2009 11/6/2005 Road & Bridge Eng.

Co. Ltd.

100% 100%

142. Nat/UR-75 Arjunpur Boromhat UP Office-Durgapur hat 8.25 Km 8.25 Km 26.15 26.15 NCB No 3/6/2006 9/7/2007 5/30/2008 2/25/2006 Md. Zamilur Rahman

Khan

100% 100%

143. Naw/UR-76 Ranihati UO Office-Golaperhat via Vama 2.95 Km 2.95 Km 7.91 7.91 NCB No 9/25/2005 3/29/2007 3/28/2007 9/18/2005 Md. Saidur Rahman

Consturction Ltd.

100% 100%

144. Sir/UR-77 Dhangora UP Office-Baikanthapur bazar 6.00 Km 6.00 Km 16.95 16.95 NCB No 11/22/2005 5/26/2007 5/24/2007 11/14/2005 JV of M/S Alpona

Construction , M/S SI

Construction and Joy

Traders

100% 100%

145. Pab/UR-78 Ruppur UP Office-Kanpur bazar 2.00 Km As this road is improved by another project of LGED, so it is dropped. 0% 0%

146. Pab/UR-79 Handial UP Office-Shamaj bazar 6.00 Km 6.00 Km 11.26 11.26 NCB No 2/7/2006 8/11/2007 9/30/2008 1/28/2006 JV of M/S Pabon's &

The Bhuiya Engineer's

70% 70%

147. Pab/UR-80 Dhulauri UP-Boalmari bazar 4.20 Km 4.20 Km 12.57 12.57 NCB No 12/31/2005 7/4/2007 6/5/2007 12/20/2005 M/S Abdul Kader 100% 100%

148. Bog/UR-81 Mothurapur UP-Gopalnagar UP 4.39 Km 4.39 Km 10.46 10.46 NCB No 2/18/2006 8/22/2007 8/18/2007 2/9/2006 M/S Alam Construction 100% 100%

149. Joy/UR-82 Joypurhat-Nurpur road via Kuisabar 5.00 Km 5.00 Km 13.12 13.12 NCB No 8/17/2005 2/18/2007 4/30/2008 8/10/2005 M/S Alam Construction 100% 100%

30

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

150. Cha/UR-83 Kalipur-Gazra Bazar 5.22 Km 5.22 Km 4.89 4.89 NCB No 1/10/2006 7/14/2007 4/30/2008 1/1/2006 M/S Bashundhara 31% 31%

151. Cha/UR-84 Tamta UP-Khudra Ferry Ghat 3.00 Km 3.00 Km 11.58 11.58 NCB No 1/3/2006 7/7/2007 2/28/2008 12/5/2005 Peal Engineering &

Construction

100% 100%

152. Cha/UR-85 Ashrafpur-Payelgacha road 2.92 Km 2.92 Km 7.72 7.72 NCB No 2/21/2006 8/25/2007 5/31/2008 2/14/2006 M/S Proma

International

100% 100%

153. Mou/UR-86 Ohanlghat-Raysres-Shimultala bazar road 4.00 Km 4.00 Km 10.01 10.01 NCB No 12/8/2005 6/11/2007 4/15/2008 11/23/2005 M.A. H.M.I JV 100% 100%

154. Sun/UR-87 Patharia-Banglabazar(Up to Bhatipara UP Office) 5.00 Km 5.00 Km 22.34 22.34 NCB No 10/15/2007 4/17/2009 6/16/2009 5/29/2007 JV of (i) M/S Mahbub

Enterprise & (ii) M/S.

Hasan Enterprise

100% 100%

155. Sun/UR-88 Adabazar-Horinathpur(Up to Laxmipur UP) 2.50 Km 2.50 Km 6.96 6.96 NCB No 12/12/2005 6/15/2007 12/30/2007 12/4/2005 M/S. Humayun Kabir 100% 100%

156. Hab/UR-89 Anwarpur-Gopalgonj bazar road 8.03 Km 8.03 Km 12.95 12.95 NCB No 11/6/2005 5/10/2007 4/30/2008 10/26/2005 S.S.A.A. Brothers 100% 100%

157. Gaz/UR-90 Bormi-Vatipara road 5.00 Km 5.00 Km 16.00 16.00 NCB No 1/23/2006 7/27/2007 12/30/2007 1/15/2006 M/S. Parisha Trade

System Ltd

100% 100%

158. Syl/UR-91 Pirijpur-Sonarhat Monortal road 5.00 Km 5.00 Km 24.72 24.72 NCB No 9/12/2007 3/15/2009 11/15/2009 8/28/2007 M/S Unnayan

Engineers &

Associates

100% 100%

159. Nat/UR-92 Ratal-Behas road 7.45 Km 7.45 Km 20.76 20.76 NCB No 5/17/2006 11/18/2007 3/31/2008 5/10/2006 JV of M/S North

Bengal Enterprise, M/S

Islam Construction &

Mir Habibul Alam

100% 100%

160. Bog/UR-93 Chandihara hat-Raynagar UP road 6.16 Km 6.16 Km 16.65 16.65 NCB No 11/30/2005 6/3/2007 5/29/2007 11/17/2005 M/S Ataur Rahman

Khan

100% 100%

161. Sir/UR-94 Someshpur-Baniagati College (Bhangabari UP)-

Mukundogati bazar road

4.60 Km 4.60 Km 13.16 13.16 NCB No 3/7/2006 9/8/2007 3/30/2008 3/1/2006 M/S Md.

Shamsuzzaman

100% 100%

31

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

162. Sir/UR-95 Ekdala-Sunamukhin via Sattikri road 2.09 Km 2.09 Km 5.80 5.80 NCB No 1/27/2005 7/31/2006 6/29/2007 1/20/2005 M/S Sakil Enterprise 100% 100%

163. Mun/UR-96 Aldi R&H-K. Shimulia UP Office road 1.50 Km 1.50 Km 5.19 5.19 NCB No 4/26/2006 10/28/2007 10/21/2007 4/18/2006 M/S Punam Enterprise 100% 100%

164. Nara/UR-97 Pagla-Godnail UP Office 3.20 Km 3.20 Km 10.99 10.99 NCB No 1/6/2006 7/10/2007 7/6/2007 12/28/2005 M/S S. Islam &

Brothers

100% 100%

165. Pab/UR-98 Manik hat-Bikramaditta via Daspara 5.30 Km 5.30 Km 4.86 4.86 NCB No 8/7/2006 2/8/2008 2/8/2008 8/1/2006 S.S Engineering &

Construction Ltd.

30% 30%

166. Dha/UR-99 (a) Saver GC-CRP-Laltech-Saver UP office road

(b) From Monu Baperir Dhal-Rajabari Bazar via

Borhanibag road

4.90 Km 4.90 Km 17.18 17.18 NCB No 7/12/2006 1/13/2008 11/30/2008 6/28/2006 M/S Orient Trade

International

71% 71%

167. Man/UR-100 Balirteck hat-Shatti hat road 1.75 Km 1.75 Km 3.15 3.15 NCB No 5/22/2006 11/23/2007 5/21/2007 5/15/2006 M/S Hossain

Construction

100% 100%

168. Joy/GCM-1 Improvement of Puranapail Hat under Joypurhat-S

Upazila

1 No. 1 No. 4.07 4.07 NCB No 5/15/2005 5/15/2006 12/31/2006 5/8/2005 M/S S. A. Traders 100% 100%

169. Joy/GCM-2 Improvement of Hope Hat under Khetlal Upazila 1 No. 1 No. 4.75 4.75 NCB No 5/10/2005 5/10/2006 12/31/2006 4/27/2005 M/S Rabi & Brothers 100% 100%

170. Joy/GCM-3 Improvement of Matri Hat under Kalai Upazila 1 No. 1 No. 4.38 4.38 NCB No 4/30/2005 4/30/2006 3/25/2008 4/23/2005 Khan Brothers 100% 100%

171. Nat/GCM-4 Improvement of Rajapur under Baraigram Upazila 1 No. 1 No. 4.51 4.51 NCB No 7/25/2005 7/25/2006 3/31/2008 7/17/2005 Md. Aminul Haque 100% 100%

172. Nat/GCM-5 Improvement of Jonail under Baraigram Upazila 1 No. 1 No. 4.24 4.24 NCB No 8/14/2005 8/14/2006 3/31/2008 8/7/2005 M/S Podder

Construction

100% 100%

173. Nat/GCM-6 Improvement of Kaliganj under Singra Upazila 1 No. 1 No. 4.16 4.16 NCB No 8/14/2005 8/14/2006 3/31/2008 8/7/2005 M/S. Hira Enterprise 100% 100%

32

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

174. Naw/GCM-7 Improvement of Shonaichondi Hat under Nachole

Upazila

1 No. 1 No. 4.20 4.20 NCB No 9/7/2005 9/7/2006 9/6/2006 8/31/2005 M/S Mona

Construction

100% 100%

175. Naw/GCM-8 Improvement of Rajbari Hat under Nachole Upazila 1 No. 1 No. 4.14 4.14 NCB No 3/21/2005 3/21/2006 3/20/2006 3/15/2005 Md. Saidur Rahman &

Co. (Pvt.) Ltd.

100% 100%

176. Naw/GCM-9 Improvement of Kansat under Shibganj Upazila 1 No. 1 No. 4.17 4.17 NCB No 2/15/2005 2/15/2006 2/14/2006 2/1/2005 M/S Alam Construction 100% 100%

177. Gaz/GCM-10 Improvement of Shaoraid Bazar under Kaliganj Upazila 1 No. 1 No. 0.00 0.00 NCB No 5/15/2005 5/15/2006 5/15/2006 4/8/2005 0% 0%

178. Sun/GCM-11 Improvement of Rajaniganj Bazar under Derai Upazila 1 No. 1 No. 0.00 0.00 NCB No 8/15/2006 8/15/2007 8/15/2007 3/25/2005 0% 0%

179. Sun/GCM-12 Improvement of Derai Bazar under Derai Upazila 1 No. 1 No. 0.00 0.00 NCB No 8/15/2006 8/15/2007 8/15/2007 3/25/2005 0% 0%

180. Sun/GCM-13 Improvement of Shyamarchar Bazar under Derai

Upazila

1 No. 1 No. 5.72 5.72 NCB No 4/23/2009 4/23/2010 10/22/2009 4/13/2009 M/S Mamun

Construction

100% 100%

181. Sun/GCM-14 Improvement of Selimganj Bazar under Jamalganj

Upazila

1 No. 1 No. 1.57 1.57 NCB No 8/1/2008 8/1/2009 8/31/2009 6/24/2008 Scheme Properties

Ltd.

21% 21%

182. Sun/GCM-15 Improvement of Mongalkata Bazar under Sunamganj-S

Upazila

1 No. 1 No. 2.56 2.56 NCB No 7/1/2005 7/1/2006 6/30/2007 6/18/2005 M/S Mobarak Hossain 100% 100%

183. Sun/GCM-16 Improvement of Paglabazar under Sunamganj-S

Upazila

1 No. 1 No. 2.48 2.48 NCB No 7/1/2005 7/1/2006 6/30/2006 6/18/2005 M/S Milon Kanti Dey 100% 100%

184. Sun/GCM-17 Improvement of Joynagar Bazar under Sunamganj-S

Upazila

1 No. 1 No. 4.98 4.98 NCB No 11/20/2008 11/20/2009 11/19/2009 11/9/2008 Future Castle

Construction

100% 100%

185. Com/GCM-18 Improvement of Homna Bazar under Homna Upazila 1 No. 1 No. 3.10 3.10 NCB No 11/22/2005 11/22/2006 6/30/2007 11/2/2005 M/S Basharat Ahmed 100% 100%

186. Com/GCM-19 Improvement of Dhalua Bazar under Nangalkot Upazila 1 No. 1 No. 3.20 3.20 NCB No 4/30/2005 4/30/2006 6/30/2007 4/16/2005 M/S. M.I. Construction 100% 100%

187. Com/GCM-20 Improvement of Nangalkot Bazar under Nangalkot

Upazila

1 No. 1 No. 2.12 2.12 NCB No 3/15/2006 3/15/2007 6/30/2007 2/8/2006 M/S Surma

International

100% 100%

33

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

188. Com/GCM-21 Improvement of Jhalom Bazar under Barua Upazila 1 No. 1 No. 0.69 0.69 NCB No 3/28/2006 3/28/2007 12/31/2007 3/21/2006 M/S M. A. Zaher 32% 32%

189. Com/GCM-22 Improvement of Langnashar Bazar under Barua Upazila 1 No. 1 No. 1.13 1.13 NCB No 3/28/2006 3/28/2007 12/31/2007 3/21/2006 M/S. Choudhury

Traders

50% 50%

190. Com/GCM-23 Improvement of Chouddagram Bazar under

Chauddagram Upazila

1 No. 1 No. 3.30 3.30 NCB No 4/27/2005 4/27/2006 8/31/2007 4/20/2005 Md. Faizullah 100% 100%

191. Com/GCM-24 Improvement of Gouripur Hat under Daudkandi Upazila 1 No. 1 No. 4.29 4.29 NCB No 6/18/2005 6/18/2006 3/30/2008 6/12/2005 Md. Faizullah 100% 100%

192. Com/GCM-25 Improvement of Masimpur under Daudkandi Upazila 1 No. 1 No. 0.00 0.00 NCB No Aug'06 Aug'07 0% 0%

193. Com/GCM-26 Improvement of Batakandi Hat under Daudkandi

Upazila

1 No. 1 No. 1.40 1.40 NCB No 6/10/2005 6/10/2006 3/6/2006 5/16/2005 The Engineer's &

Construction Ltd.

40% 40%

194. Cha/GCM-27 Improvement of Sachar Hat under Kachua Upazila 1 No. 1 No. 3.85 3.85 NCB No 5/21/2005 5/21/2006 12/30/2006 5/14/2005 M/S Khan Traders 100% 100%

195. Cha/GCM-28 Improvement of Rahimanagar Hat under Kachua

Upazila

1 No. 1 No. 3.79 3.79 NCB No 6/11/2005 6/11/2006 12/30/2007 6/4/2005 M/S Nur Hossain

Traders

100% 100%

196. Cha/GCM-29 Improvement of Khila Bazar under Shaharasti Upazila 1 No. 1 No. 2.73 2.73 NCB No 6/25/2005 6/25/2006 6/30/2007 4/18/2005 M/S Zia Enterprise 100% 100%

197. Cha/GCM-30 Improvement of Takhor Bazar under Shaharasti Upazila 1 No. 1 No. 2.08 2.08 NCB No 10/10/2005 10/10/2006 9/29/2006 9/11/2005 M/S Rabbi Traders 100% 100%

34

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

198. Cha/GCM-31 Improvement of Rupsha Hat under Faridganj Upazila 1 No. 1 No. 3.31 3.31 NCB No 5/14/2005 5/14/2006 5/14/2006 5/7/2005 M/S Zia Enterprise 100% 100%

199. Cha/GCM-32 Improvement of Kalir Bazar under Faridganj Upazila 1 No. 1 No. 1.96 1.96 NCB No 7/30/2005 7/30/2006 12/31/2006 3/16/2005 The Sun Flower 100% 100%

200. Cha/GCM-33 Improvement of Rampur Hat under Faridganj Upazila 1 No. 1 No. 4.62 4.62 NCB No 8/14/2005 8/14/2006 12/30/2006 6/2/2005 M/S Zia Enterprise 100% 100%

201. Cha/GCM-34 Improvement of Ishanbala Hat under Haimchar Upazila 1 No. 1 No. 5.77 5.77 NCB No 10/12/2005 10/12/2006 12/30/2006 5/11/2005 M/S Rokib Enterprise 100% 100%

202. Cha/GCM-35 Improvement of Bakila Bazar under Haziganj Upazila 1 No. 1 No. 2.83 2.83 NCB No 5/10/2005 5/10/2006 9/28/2006 5/3/2005 Mizanur Rahman Liton 100% 100%

203. Bra/GCM-36 Improvement of Mogra Rajdhargonj Bazar under

Akhaura Upazila

1 No. 1 No. 2.62 2.62 NCB No 8/21/2005 8/21/2006 6/30/2007 8/8/2005 M/S Tushi Enterprise 100% 100%

204. Bra/GCM-37 Improvement of Sarail Bazar under Sarail Upazila 1 No. 1 No. 3.69 3.69 NCB No 4/18/2005 4/18/2006 3/31/2007 4/7/2005 Fazle Azim Engineers

Ltd.

100% 100%

205. Bra/GCM-38 Improvement of Aurail Bazar under Sarail Upazila 1 No. 1 No. 3.84 3.84 NCB No 4/18/2005 4/18/2006 3/31/2007 4/7/2005 Sawdagar Traders 100% 100%

206. Bra/GCM-39 Improvement of Nurpur Bazar under B.Baria-S Upazila 1 No. 1 No. 4.03 4.03 NCB No 5/14/2005 5/14/2006 8/31/2006 4/10/2005 M/S Nilu Enterprise 100% 100%

207. Bra/GCM-40 Improvement of Singarbeel Hat under B.Baria-S Upazila 1 No. 1 No. 3.10 3.10 NCB No 5/14/2005 5/14/2006 8/31/2006 4/3/2005 M/S Khaled Enterprise 100% 100%

208. Dha/GCM-41 Improvement of Nannar Bazar under Dhamrai Upazila 1 No. As this GCM is improved by another project of LGED, so it is dropped.

209. Dha/GCM-42 Improvement of Kushura Hat under Dhamrai Upazila 1 No. 1 No. 5.20 5.20 NCB No 2/16/2006 2/16/2007 7/31/2008 2/1/2006 M/S Jewel Engineers 100% 100%

210. Dha/GCM-43 Improvement of Amin Bazar under Keraniganj Upazila 1 No. 1 No. 5.37 5.37 NCB No 5/20/2005 5/20/2006 7/20/2006 5/17/2005 M/S Bikalpa Trade

International

100% 100%

211. Dha/GCM-44 Improvement of Bebir Bazar under Keraniganj Upazila 1 No. 1 No. 5.68 5.68 NCB No 5/20/2005 5/20/2006 8/7/2006 5/17/2005 JV of M/S Janata

Trade International and

M/S Abdur Rashid &

Brothers

100% 100%

212. Man/GCM-45 Improvement of Shamganj under Daulatpur Upazila 1 No. 1 No. 0.00 0.00 NCB No Jul'07 Jul'08 0% 0%

35

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

213. Man/GCM-46 Improvement of Singair Hat under Singair Upazila 1 No. 1 No. 0.00 0.00 NCB No 8/15/2006 8/15/2007 8/15/2007 8/6/2005 0% 0%

214. Bog/GCM-47 Improvement of Zianagar Hat under Dupchanchia

Upazila

1 No. 1 No. 4.94 4.94 NCB No 5/2/2005 5/2/2006 2/28/2008 4/25/2005 JV of M/S S.A. Runa 100% 100%

215. Bog/GCM-48 Improvement of Kumari Pandithpukur Hat under

Nandigram Upazila

1 No. Dropped from the project

216. Bog/GCM-49 Improvement of Kharna Hat under Bogra-S Upazila 1 No. 1 No. 4.58 4.58 NCB No 5/15/2005 5/15/2006 6/30/2007 5/4/2005 Md. Fazlul Haque 100% 100%

217. Bog/GCM-50 Improvement of Bihar Hat under Shibganj Upazila 1 No. 1 No. 3.49 3.49 NCB No 4/2/2005 4/2/2006 9/30/2006 3/20/2005 M/S. S.M. Construction

JV.

100% 100%

218. Bog/GCM-51 Improvement of Daridaha Hat under Shibganj Upazila 1 No. 1 No. 4.71 4.71 NCB No 8/17/2005 8/17/2006 1/31/2007 8/6/2005 M/S Islam Brothers 100% 100%

219. Bog/GCM-52 Improvement of Horikhali Hat under Sonatola Upazila 1 No. 1 No. 4.14 4.14 NCB No 8/14/2005 8/14/2006 5/30/2007 8/7/2005 M/S. Shafiq Traders 100% 100%

220. Bog/GCM-53 Improvement of Bibirpukur Hat under Kahalo Upazila 1 No. 1 No. 4.28 4.28 NCB No 8/17/2005 8/17/2006 4/30/2008 8/8/2005 M/S. Shmoun

Enterprise

100% 100%

221. Nao/GCM-54 Improvement of Shabai Hat under Manda Upazila 1 No. 1 No. 4.99 4.99 NCB No 12/18/2005 12/18/2006 12/31/2007 8/9/2005 GR-NE JV 100% 100%

222. Nao/GCM-55 Improvement of Samajpara Hat under Atrai Upazila 1 No. 1 No. 4.33 4.33 NCB No 10/10/2006 10/10/2007 5/31/2008 8/9/2005 SRI-MU JV 100% 100%

223. Nao/GCM-56 Improvement of Chalkgoari under Mohadebpur Upazila 1 No. 1 No. 4.18 4.18 NCB No 8/13/2006 8/13/2007 3/31/2009 9/8/2005 SAMRR JV 100% 100%

224. Nao/GCM-57 Improvement of Ganguria Hat under Porsha Upazila 1 No. 1 No. 4.63 4.63 NCB No 12/7/2005 12/7/2006 3/15/2007 8/9/2005 M/S JE & SI JV 100% 100%

225. Nao/GCM-58 Improvement of Madail Hat under Patnitala Upazila 1 No. 1 No. 4.50 4.50 NCB No 2/2/2006 2/2/2007 4/25/2007 8/9/2005 SA-MRR JV 100% 100%

226. Nao/GCM-59 Improvement of Fatepur Hat under Naogaon-S Upazila 1 No. 1 No. 3.90 3.90 NCB No 2/25/2006 2/25/2007 6/30/2007 8/9/2005 M/S Momin Const 100% 100%

227. Nao/GCM-60 Improvement of Mangalbari Hat under Dhamoirhat

Upazila

1 No. 1 No. 4.11 4.11 NCB No 3/7/2006 3/7/2007 12/31/2007 8/9/2005 Md. Tarek Hossain 100% 100%

228. Nao/GCM-61 Improvement of Khoribari under Niamatpur Upazila 1 No. 1 No. 4.51 4.51 NCB No 12/5/2005 12/5/2006 12/4/2006 8/9/2005 M.S JE&SI JV 100% 100%

229. Pab/GCM-62 Improvement of Shelonda Bazar under Santhia Upazila 1 No. 1 No. 0.00 0.00 0% 0%

230. Pab/GCM-63 Improvement of Bera Hat under Bera Upazila 1 No. 1 No. 2.97 2.97 NCB No 2/18/2007 2/18/2008 12/31/2008 2/11/2007 Afzal Hossain 100% 100%

36

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

231. Raj/GCM-64 Improvement of Kaliganj under Tanore Upazila 1 No. 1 No. 4.89 4.89 NCB No 8/7/2006 8/7/2007 8/30/2008 9/18/2005 M/S Raka Enterprise 100% 100%

232. Raj/GCM-65 Improvement of Bidirpur Hat under Godagari Upazila 1 No. 1 No. 3.99 3.99 NCB No 1/7/2006 1/7/2007 5/30/2007 11/2/2005 Md. Abdur Razzak 100% 100%

233. Raj/GCM-66 Improvement of Dopaghata Hat under Mohanpur

Upazila

1 No. 1 No. 4.61 4.61 NCB No 10/1/2007 9/30/2008 10/30/2008 9/25/2005 M/S Raka Enterprise 100% 100%

234. Raj/GCM-67 Improvement of Hatgangapara under Bagmara Upazila 1 No. 1 No. 4.17 4.17 NCB No 1/3/2007 1/3/2008 1/2/2008 9/25/2005 Md. Musleh Uddin 100% 100%

235. Sir/GCM-68 Improvement of Horinathpur under Kazipur Upazila 1 No. 1 No. 3.90 3.90 NCB No 12/13/2005 12/13/2006 12/31/2007 12/6/2005 Md. Abdul Kuddus 100% 100%

236. Sir/GCM-69 Improvement of Tarash under Tarash Upazila 1 No. 1 No. 3.80 3.80 NCB No 11/1/2005 11/1/2006 1/31/2007 10/25/2005 Sree Prokash Chandra

Sarker

100% 100%

237. Sir/GCM-70 Improvement of Baruhash under Tarash Upazila 1 No. 1 No. 0.00 0.00 NCB No Aug'07 Jul'08 0% 0%

238. Sir/GCM-71 Improvement of Udhonia Hat under Ullapara Upazila 1 No. 1 No. 5.27 5.27 NCB No 10/2/2005 10/2/2006 12/31/2007 9/25/2005 S. M. Liaquat Ali 100% 100%

239. Sir/GCM-72 Improvement of Dhangara under Raiganj Upazila 1 No. 1 No. 2.97 2.97 NCB No 1/16/2006 1/16/2007 11/30/2007 1/9/2006 M/S Pias Construction 100% 100%

240. Mun/GCM-73 Improvement of Kalma Bazar under Lauhajong Upazila 1 No. 1 No. 4.10 4.10 NCB No 6/29/2006 6/29/2007 6/21/2007 3/16/2006 M/S Ata Traders 100% 100%

241. Mun/GCM-74 Improvement of Dighirpar Hat under Tongibari Upazila 1 No. 1 No. 5.80 5.80 NCB No 4/16/2006 4/16/2007 8/30/2007 3/14/2006 M/S Ata Traders 100% 100%

242. Nar/GCM-75 Improvement of Barochapa Hat under Monohardi

Upazila

1 No. 1 No. 4.10 4.10 NCB No 3/21/2006 3/21/2007 8/30/2008 3/14/2006 M/S Scan Associates

Pvt. Ltd.

100% 100%

243. Sun/GCM-76 Improvement of Sirajganj Bazar under Chattak Upazila 1 No. 1 No. 0.31 0.31 NCB No 1/5/2006 1/5/2007 1/4/2007 12/18/2005 M/S Moni Construction 7% 7%

244. Sun/GCM-77 Improvement of Syedpur Bazar under Jaganathpur

Upazila

1 No. 1 No. 2.12 2.12 NCB No 2/5/2006 2/5/2007 2/4/2007 12/19/2005 JCM & Engineers Ltd. 100% 100%

245. Sun/GCM-78 Improvement of Biswamberpur under Biswamberpur

Upazila

1 No. 1 No. 0.00 0.00 NCB No Aug'07 Jul'08 0% 0%

246. Mou/GCM-79 Improvement of Adampur Bazar under Kamalganj

Upazila

1 No. 1 No. 4.18 4.18 NCB No 1/30/2006 1/30/2007 1/16/2007 1/17/2006 Md. Abdul Mukith 100% 100%

247. Mou/GCM-80 Improvement of Digirpar Bazar under Moulvibazar-S

Upazila

1 No. 1 No. 4.41 4.41 NCB No 5/16/2006 5/16/2007 5/2/2008 5/3/2006 Md Tufalel Ahmed 100% 100%

37

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

248. Mou/GCM-81 Improvement of Sarkar Bazar under Moulvibazar-S

Upazila

1 No. 1 No. 5.12 5.12 NCB No 5/22/2006 5/22/2007 9/15/2007 3/9/2006 M/S. Bafdul Alam 100% 100%

249. Mou/GCM-82 Improvement of Braman Bazar under Kulaura Upazila 1 No. 1 No. 3.00 3.00 NCB No 1/16/2006 1/16/2007 3/31/2008 1/3/2006 Kamal Uddin 77% 77%

250. Mou/GCM-83 Improvement of Rabir Bazar under Kulaura Upazila 1 No. 1 No. 5.69 5.69 NCB No 4/18/2006 4/18/2007 10/30/2007 1/17/2006 Md Muhibur Rahman 100% 100%

251. Mou/GCM-84 Improvement of Rajnagar under Rajnagar Upazila 1 No. 1 No. 0.00 0.00 NCB No 4/14/2006 4/14/2007 4/3/2007 1/1/2006 0% 0%

252. Mou/GCM-85 Improvement of Munshibazar under Rajnagar Upazila 1 No. 1 No. 1.41 1.41 NCB No 8/17/2006 8/17/2007 3/31/2008 1/9/2006 Md. Habibur Rahman 40% 40%

253. Mou/GCM-86 Improvement of Dubar Hat under Sreemangal Upazila 1 No. 1 No. 4.57 4.57 NCB No 1/30/2006 1/30/2007 1/16/2007 1/17/2006 Md. Nazrul Islam 100% 100%

254. Hab/GCM-87 Improvement of Azmiriganj Bazar under Azmiriganj

Upazila

1 No. 1 No. 5.51 5.51 NCB No 10/22/2006 10/22/2007 3/30/2008 7/27/2006 M/S Azad & Brothers 100% 100%

255. Hab/GCM-88 Improvement of Bahubal under Bahubal Upazila 1 No. 1 No. 4.64 4.64 NCB No 1/7/2006 1/7/2007 4/30/2007 10/31/2005 M/S Shaid Brothers 100% 100%

256. Dha/GCM-89 Improvement of Dhamrai Hat under Dhamrai Upazila 1 No. This GCM is dropped.

257. Hab/GCM-90 Improvement of Chunarughat Puran Bazar under

Chunarughat Upazila

1 No. 1 No. 4.51 4.51 NCB No 5/7/2006 5/7/2007 10/30/2007 12/12/2005 M/S Shahid Brothers 100% 100%

258. Hab/GCM-91 Improvement of Bulla Bazar under Lakhai Upazila 1 No. 1 No. 4.11 4.11 NCB No 11/7/2007 11/6/2008 2/28/2009 7/27/2006 M/S Azad & Brothers 100% 100%

259. Cha/GCM-92 Improvement of Roghunathpur Hat under Kachua

Upazila

1 No. 1 No. 4.96 4.96 NCB No 10/14/2007 10/13/2008 10/13/2008 10/8/2007 M/S Nur Hossain

Traders

100% 100%

260. Cha/GCM-93 Improvement of Palakhal Bazar under Kachua Upazila 1 No. 1 No. 3.82 3.82 NCB No 11/13/2005 11/13/2006 12/30/2007 9/29/2005 M/S Al-Amin Traders 100% 100%

261. Cha/GCM-94 Improvement of Chitoshi Bazar under Shaharasti

Upazila

1 No. Dropped from the project

38

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

262. Cha/GCM-95 Improvement of Faridganj Bazar under Faridganj

Upazila

1 No. 1 No. 2.29 2.29 NCB No 2/9/2006 2/9/2007 2/8/2007 12/26/2005 M/S Zia Enterprise 100% 100%

263. Cha/GCM-96 Improvement of Chandra Bazar under Faridganj Upazila 1 No. This Package (GCM-96) has been excluded from RTIP as the GCM is being improved under another project (RDP-20) of LGED.

264. Cha/GCM-97 Improvement of Charbhairabi Bazar under Haimchar

Upazila

1 No. 1 No. 6.76 6.76 NCB No 11/7/2007 11/6/2008 3/30/2009 3/18/2007 M/S Khair Enterprise 100% 100%

265. Cha/GCM-98 Improvement of Rajargaon Bazar under Haziganj

Upazila

1 No. This Package (GCM-98) has been excluded from RTIP as the GCM is being improved under another project (RDP-20) of LGED.

266. Syl/GCM-99 Improvement of Shahgoli Bazar under Zakiganj Upazila 1 No. 1 No. 4.42 4.42 NCB No 12/21/2006 12/21/2007 3/30/2008 12/5/2006 M/S Helal Uddin 100% 100%

267. Syl/GCM-100 Improvement of Chatul Bazar under Kanaighat Upazila 1 No. 1 No. 3.89 3.89 NCB No 2/5/2006 2/5/2007 4/6/2008 1/2/2006 ATCL International 100% 100%

268. Syl/GCM-101 Improvement of Rakuar Bazar under Golapganj Upazila 1 No. 1 No. 5.00 5.00 NCB No Nov'07 Oct'08 0% 0%

269. Syl/GCM-102 Improvement of Jaintapur Bazar under Jaintapur

Upazila

1 No. 1 No. 4.93 4.93 NCB No 12/31/2008 12/31/2009 12/31/2009 12/21/2008 M/S Ripon Traders 100% 100%

270. Syl/GCM-103 Improvement of Sharapar Bazar under Beanibazar

Upazila

1 No. 1 No. 5.00 5.00 NCB No Nov'07 Oct'08 0% 0%

271. Syl/GCM-104 Improvement of Goainghat under Goainghat Upazila 1 No. 1 No. 5.00 5.00 NCB No Nov'07 Oct'08 0% 0%

272. Syl/GCM-105 Improvement of Goala Bazar under Balaganj Upazila 1 No. 1 No. 2.34 2.34 NCB No 5/7/2007 5/6/2008 10/31/2008 4/16/2007 M/S Tisha & Tushar

Trade International

37% 37%

273. Syl/GCM-106 Improvement of Balaganj Bazar under Balaganj Upazila 1 No. 1 No. 1.32 1.32 NCB No 3/16/2008 3/16/2009 3/15/2009 3/10/2008 M/S Tisha & Tushar

Trade International

85% 85%

274. Bra/GCM-107 Improvement of Kuti Hat under Kasba Upazila 1 No. 1 No. 5.83 5.83 NCB No 5/3/2007 5/2/2008 11/30/2008 3/28/2007 M/S Haroonur Rashid 100% 100%

275. Bra/GCM-108 Improvement of Nayanpur Hat under Kasba Upazila 1 No. 1 No. 6.27 6.27 NCB No 6/18/2007 6/17/2008 12/31/2008 4/8/2007 M/S Nilu Enterprise 100% 100%

276. Bra/GCM-109 Improvement of Morichakandi Bazar under

Bancharampur Upazila

1 No. 1 No. 0.00 0.00 NCB No Nov'07 Oct'08 0% 0%

277. Dha/GCM-110 Improvement of Doleshwar Bazar under Keraniganj

Upazila

1 No. 1 No. 5.00 5.00 NCB No Nov'07 Oct'08 0% 0%

278. Dha/GCM-111 Improvement of Nawabganj Bazar under Nawabganj

Upazila

1 No. 1 No. 4.26 4.26 NCB No 8/13/2006 8/13/2007 3/30/2008 8/3/2006 M/S Rafique Traders 100% 100%

39

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

279. Man/GCM-112 Improvement of Machain Hat under Horirampur Upazila 1 No. 1 No. 0.00 0.00 NCB No Nov'07 Oct'08 0% 0%

280. Man/GCM-113 Improvement of Joymantop Hat under Singair Upazila 1 No. 1 No. 4.06 4.06 NCB No 8/31/2006 8/31/2007 8/30/2008 8/24/2006 M/S Dalan Traders Ltd. 100% 100%

281. Bog/GCM-114 Improvement of Omarpur Hat under Nandigram Upazila 1 No. 1 No. 6.04 6.04 NCB No 12/26/2006 12/26/2007 1/31/2009 12/19/2006 M/S Nana Nati Welding

Workshop

100% 100%

282. Bog/GCM-115 Improvement of Namuja Hat under Bogra-S Upazila 1 No. 1 No. 4.93 4.93 NCB No 12/6/2005 12/6/2006 3/15/2007 11/24/2005 M/S Rakib Traders 100% 100%

283. Bog/GCM-116 Improvement of Mokamtola Hat under Shibganj Upazila 1 No. 1 No. 4.96 4.96 NCB No 4/23/2005 4/23/2006 5/25/2008 4/11/2005 Nana Nati Mahmud

Bulbul (JV)

100% 100%

284. Bog/GCM-117 Improvement of Shimabari Hat under Sherpur Upazila 1 No. 1 No. 4.10 4.10 NCB No 3/17/2008 3/17/2009 8/30/2009 3/11/2008 M/S Shamoli Traders 100% 100%

285. Nao/GCM-118 Improvement of Bandaikhara Hat under Atrai Upazila 1 No. 1 No. 6.57 6.57 NCB No 4/1/2007 3/31/2008 6/30/2008 3/25/2007 M/S Brothers

Enterprise

100% 100%

286. Nao/GCM-119 Improvement of Kashiabari Hat under Atrai Upazila 1 No. 1 No. 6.00 6.00 NCB No 5/6/2007 5/5/2008 5/5/2008 4/22/2007 S. M. Rejaul Islam 100% 100%

287. Nao/GCM-120 Improvement of Pathakata Hat under Mohadebpur

Upazila

1 No. 1 No. 0.00 0.00 0% 0%

288. Nao/GCM-121 Improvement of Betgari Hat under Raninagar Upazila 1 No. 1 No. 5.99 5.99 NCB No 16f/04/07 15f/04/08 4/15/2008 3/21/2007 Golam Rabbani 100% 100%

289. Nao/GCM-122 Improvement of Katkhair Hat under Naogaon-S Upazila 1 No. 1 No. 5.99 5.99 NCB No 4/1/2007 3/31/2008 3/31/2008 3/25/2007 M/S Nasif Construction 100% 100%

290. Nao/GCM-123 Improvement of Rangamati Hat under Dhamoirhat

Upazila

1 No. 1 No. 5.96 5.96 NCB No 5/22/2007 5/21/2008 7/31/2008 5/15/2007 M/S JE & SI JV 100% 100%

291. Nao/GCM-124 Improvement of Shibpur Hat under Niamatpur Upazila 1 No. 1 No. 6.00 6.00 NCB No 5/22/2007 5/21/2008 5/21/2008 5/15/2007 M/S JE & SI JV 100% 100%

292. Pab/GCM-125 Improvement of Dogashi Hat under Pabna-S Upazila 1 No. 1 No. 0.00 0.00 NCB No Nov'07 Oct'08 0% 0%

293. Pab/GCM-126 Improvement of Chaikola Hat under Chatmohor Upazila 1 No. 1 No. 2.75 2.75 NCB No 12/5/2007 12/4/2008 11/28/2008 11/29/2007 M/S Tushar Enterprise 100% 100%

294. Raj/GCM-127 Improvement of Godagari Hat under Godagari Upazila 1 No. 1 No. 5.78 5.78 NCB No 9/17/2008 9/17/2009 9/10/2009 8/20/2008 M/S Hossain

Enterprise

100% 100%

40

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

295. Raj/GCM-128 Improvement of Mohonganj Hat under Bagmara Upazila 1 No. 1 No. 0.00 0.00 NCB No Nov'07 Oct'08 0% 0%

296. Sir/GCM-129 Improvement of Katagari Hat under Tarash Upazila 1 No. 1 No. 5.23 5.23 NCB No 6/7/2007 6/6/2008 6/6/2008 5/31/2007 M/S Piash

Construction

100% 100%

297. Sir/GCM-130 Improvement of Hatpangashi under Raiganj Upazila 1 No. 1 No. 5.68 5.68 NCB No 6/3/2007 6/2/2008 11/30/2010 5/27/2007 S. M. Liaquat Ali 100% 100%

298. Mun/GCM-131 Improvement of Noapara Hat under Lauhajong Upazila 1 No. 1 No. 0.00 0.00 NCB No Nov'07 Oct'08 0% 0%

299. Mun/GCM-132 Improvement of Shaper Bazar under Sirajdikhan

Upazila

1 No. 1 No. 2.46 2.46 NCB No 1/6/2008 1/5/2009 1/5/2009 12/4/2007 M/S S Sarker

Enterprise

100% 100%

300. Sun/GCM-133 Improvement of Tahirpur Bazar under Tahirpur Upazila 1 No. 1 No. 0.00 0.00 NCB No Nov'07 Oct'08 0% 0%

301. Sun/GCM-134 Improvement of Daurai Hat under Jaganathpur Upazila 1 No. 1 No. 5.58 5.58 NCB No 4/20/2009 4/20/2010 6/15/2010 4/12/2009 M/S Hasan Enterprise 100% 100%

302. Com/GCM-135 Improvement of Jafarganj Bazar under Debidwar

Upazila

1 No. 1 No. 4.22 4.22 NCB No Nov'07 Oct'08 0% 0%

303. Com/GCM-136 Improvement of Muradnagar Bazar under Muradnagar

Upazila

1 No. 1 No. 5.00 5.00 NCB No Nov'07 Oct'08 0% 0%

304. Mou/GCM-137 Improvement of Shamsernagar Bazar under Kamalganj

Upazila

1 No. 1 No. 1.25 1.25 ` No 8/14/2007 8/13/2008 8/28/2008 7/24/2007 M/S Nesar Ahmed &

Co.

26%

305. Mou/GCM-138 Improvement of Office Bazar under Moulvibazar-S

Upazila

1 No. 1 No. 0.00 0.00 NCB No Nov'07 Oct'08 0% 0%

306. Mou/GCM-139 Improvement of Fultola Bazar under Kulaura Upazila 1 No. 1 No. 0.00 0.00 NCB No 9/2/2007 9/1/2008 9/11/2008 8/28/2007 0% 0%

307. Mou/GCM-140 Improvement of Dasher Bazar under Baraleka Upazila 1 No. 1 No. 0.00 0.00 NCB No Nov'07 Oct'08 0% 0%

41

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

308. Mou/GCM-141 Improvement of Sindurkham Bazar under Sreemangal

Upazila

1 No. 1 No. 5.43 5.43 NCB No 3/6/2008 3/6/2009 6/5/2009 2/20/2008 M/S K. M. Mamunul

Haque

100% 100%

309. Hab/GCM-142 Improvement of Kakailsew Chowdhuri Bazar under

Azmiriganj Upazila

1 No. 1 No. 3.81 3.81 NCB No 3/28/2007 3/27/2008 3/27/2008 3/18/2007 Aviram Das 100% 100%

310. Hab/GCM-143 Improvement of Dubai Bazar under Bahubal Upazila 1 No. 1 No. 4.52 4.52 NCB No 9/5/2007 9/4/2008 12/31/2008 8/23/2007 M/S Chowdhury

Enterprise

100% 100%

311. Hab/GCM-144 Improvement of Chatain Bazar under Madubpur Upazila 1 No. 1 No. 3.96 3.96 NCB No 3/28/2007 3/27/2008 3/31/2009 3/4/2007 Md.Taj Uddin 100% 100%

312. Syl/GCM-145 Improvement of Kaliganj Bazar under Zakiganj Upazila 1 No. 1 No. 1.58 1.58 NCB No 5/7/2007 5/6/2008 5/7/2008 4/25/2007 M/S Koli Enterprise 100% 100%

313. Syl/GCM-146 Improvement of Ramda Bazar under Beanibazar

Upazila

1 No. 1 No. 5.00 5.00 NCB No Nov'07 Oct'08 0% 0%

314. Syl/GCM-147 Improvement of Radanagar Bazar under Goainghat

Upazila

1 No. 1 No. 3.87 3.87 NCB No 7/30/2007 7/29/2008 7/16/2008 7/15/2007 Shahin Ahmed (JV) 100% 100%

315. Syl/GCM-148 Improvement of Dayamir Bazar under Balaganj Upazila 1 No. 1 No. 3.76 3.76 NCB No 5/7/2007 5/6/2008 5/7/2008 4/16/2007 Fazle Azim Engineers

Ltd.

100% 100%

316. Hab/GCM-149 Improvement of Inatganj Bazar under Nabiganj Upazila 1 No. 1 No. 6.26 6.26 NCB No 7/18/2007 7/17/2008 4/30/2009 6/4/2007 Shahidul Islam

Builders

100% 100%

317. Syl/GCM-150 Improvement of Fenchuganj Bazar under Fenchuganj

Upazila

1 No. 1 No. 0.93 0.93 NCB No 7/20/2007 7/19/2008 7/20/2008 6/26/2007 M/S. Continental

Construction

14% 14%

318. Gaz/RJ-1 Improvement of Kaliganj Bazar Ghat (RJ) under

Kaliganj Upazila

1 No. 1 No. 4.97 4.97 NCB No 4/24/2005 10/26/2006 1/31/2007 4/24/2005 M/S Amzad Traders 100% 100%

319. Gaz/RJ-2 Improvement of Chabagan Bazar Ghat (RJ) under

Kaliakoir Upazila

1 No. 1 No. 3.55 3.55 NCB No 4/5/2005 10/7/2006 12/31/2006 3/24/2005 Joint Venture of

M/S SP Consortium

100% 100%

42

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

320. Gaz/RJ-3 Improvement of Raghunathpur Hat Ghat (RJ) under

Kaliakoir Upazila

1 No. 1 No. 0.00 0.00 NCB No 8/1/2007 2/1/2009 0% 0%

321. Gaz/RJ-4 Improvement of Toknayan Bazar Ghat (RJ) under

Kapasia Upazila

1 No. 1 No. 5.38 5.38 NCB No 4/2/2005 10/4/2006 4/30/2007 3/24/2005 M/S Associate Builders 100% 100%

322. Gaz/RJ-5 Improvement of Kapasia Bazar Ghat (RJ) under

Kapasia Upazila

1 No. 1 No. 6.08 6.08 NCB No 5/25/2005 11/26/2006 10/30/2007 5/17/2005 M/S Shaki Enter prise 100% 100%

323. Nat/RJ-6 Improvement of Kaliganj Bazar Ghat (RJ) under Singra

Upazila

1 No. 1 No. 3.25 3.25 NCB No 7/25/2005 1/26/2007 3/31/2008 7/17/2005 M/S Hira Enterprise 100% 100%

324. Sun/RJ-7 Improvement of Derai Hat Ghat (RJ) under Derai

Upazila

1 No. 1 No. 0.00 0.00 NCB No 0% 0%

325. Sun/RJ-8 Improvement of Rajaniganj Hat Ghat (RJ) under Derai

Upazila

1 No. 1 No. 0.00 0.00 NCB No 0% 0%

326. Sun/RJ-9 Improvement of Joynagar Hat Ghat (RJ) under

Sunamganj-S Upazila

1 No. 1 No. 3.86 3.86 NCB No 5/28/2005 11/29/2006 12/31/2007 3/29/2005 JV of ATM. Misbah 81% 81%

327. Com/RJ-10 Improvement of Daudkhandi Bazar Ghat (RJ) under

Daudkhandi Upazila

1 No. 1 No. 4.48 4.48 NCB No 5/26/2005 11/27/2006 5/30/2007 5/21/2005 Md. Faizullah 100% 100%

328. Syl/RJ-11 Improvement of Khosrupur Ghat Ghat (RJ) under

Balaganj Upazila

1 No. 1 No. 3.81 3.81 NCB No 12/11/2005 6/14/2007 12/31/2008 6/27/2005 M/S. M. Alam 57% 57%

329. Syl/RJ-12 Improvement of Zokiganj Custom Bazar Ghat (RJ)

under Zokiganj Upazila

1 No. 1 No. 0.00 0.00 NCB No Aug'06 Feb'08 0% 0%

330. Cha/RJ-13 Improvement of Dalir Ghat (RJ) under Chandpur-S

Upazila

1 No. 1 No. 5.01 5.01 NCB No 12/29/2005 7/2/2007 10/30/2007 8/9/2005 M/S. Mizanur Rahman

Liton

100% 100%

331. Cha/RJ-14 Improvement of Chandra Ghat (RJ) under Faridganj

Upazila

1 No. 1 No. 4.37 4.37 NCB No 11/30/2005 6/3/2007 5/31/2007 4/10/2005 The Sun Flower 100% 100%

43

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

332. Bra/RJ-15 Improvement of Kuti Ghat (RJ) under Kasba Upazila 1 No. 1 No. 6.58 6.58 NCB No 11/5/2005 5/9/2007 12/31/2007 4/28/2005 M/S Bhuban

Prokoushali & M/S

Khaled Enterprise JV

100% 100%

333. Raj/RJ-16 Improvement of Bidirpur Ghat (RJ) under Godagari

Upazila

1 No. 1 No. 3.77 3.77 NCB No 9/24/2005 3/28/2007 4/25/2008 6/18/2005 Taher Brothers Ltd. 100% 100%

334. Com/RJ-17 Improvement of Batakandi Ghat (RJ) under Daudkhandi

Upazila

1 No. 1 No. 0.00 0.00 NCB No Oct'07 Apr'09 0% 0%

335. Syl/RJ-18 Improvement of Balaganj Bazar Ghat (RJ) under

Balaganj Upazila

1 No. 1 No. 7.90 7.90 NCB No 8/12/2009 8/12/2010 2/12/2011 8/5/2009 Md. Nowshad Miah 100% 100%

336. Cha/RJ-19 Improvement of Khila Ghat (RJ) under Shahrasti

Upazila

1 No. 1 No. 3.59 3.59 NCB No 4/16/2006 10/18/2007 12/30/2007 10/19/2005 Md. Abdul Haque 100% 100%

337. Cha/RJ-20 Improvement of Charbhairabi Ghat (RJ) under

Haimchar Upazila

1 No. Dropped from the project

338. Cha/RJ-21 Improvement of Faridganj Ghat (RJ) under Faridganj

Upazila

1 No. 1 No. 2.58 2.58 NCB No 12/22/2005 6/25/2007 5/26/2007 10/12/2005 M/S Zia Enterprise 100% 100%

339. Cha/RJ-22 Improvement of Haziganj Ghat (RJ) under Haziganj

Upazila

1 No. 1 No. 5.15 5.15 NCB No 10/16/2005 4/19/2007 6/30/2008 10/9/2005 M/S. Selim Enterprise 100% 100%

340. Bra/RJ-23 Improvement of Nasirnagar Ghat (RJ) under Nasirnagar

Upazila

1 No. 1 No. 6.38 6.38 NCB No 6/8/2006 12/10/2007 9/30/2008 1/19/2006 M/S Nilu Enterprise 100% 100%

341. Bra/RJ-24 Improvement of Arual Ghat (RJ) under Sarail Upazila 1 No. 1 No. 4.55 4.55 NCB No 11/2/2005 5/6/2007 2/29/2008 10/19/2005 M/S G.M. Enterprise 100% 100%

342. Syl/RJ-25 Improvement of Ramda Bazar Ghat (RJ) under

Beanibazar Upazila

1 No. 1 No. 7.73 7.73 NCB No 8/16/2007 2/16/2009 5/30/2009 7/31/2007 M/S Helal Uddin 100% 100%

343. Dha/RJ-26 Improvement of Kartikpur Ghat (RJ) under Dohar

Upazila

1 No. 1 No. 4.98 4.98 NCB No 9/22/2005 3/26/2007 10/25/2007 9/15/2005 M/S Eastland

Engineers

100% 100%

344. Man/RJ-27 Improvement of Jamshaha Ghat (RJ) under Singair

Upazila

1 No. Dropped from the project

345. Bog/RJ-28 Improvement of Chamarpathalia Ghat (RJ) under

Sherpur Upazila

1 No. 1 No. 5.24 5.24 NCB No 9/13/2005 3/17/2007 6/30/2007 9/5/2005 S.S. Engineering &

Consortium Ltd.

100% 100%

346. Pab/RJ-29 Improvement of Sannsibandha Ghat (RJ) under Bera

Upazila

1 No. 1 No. 0.00 0.00 NCB No Oct'07 Apr'09 0% 0%

44

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

347. Nar/RJ-30 Improvement of Hasnabad Ghat (RJ) under Raipura

Upazila

1 No. 1 No. 4.80 4.80 NCB No 12/12/2006 6/14/2008 12/30/2009 2/25/2006 M/S Prokalpo

Bastobayon Ltd.

100% 100%

348. Nar/RJ-31 Improvement of Algi Bazar Ghat (RJ) under Raipura

Upazila

1 No. 1 No. 0.00 0.00 NCB No Dec'07 Jun'09 0% 0%

349. Nar/RJ-32 Improvement of Sreenagar Ghat (RJ) under Narsingdi-S

Upazila

1 No. 1 No. 6.72 6.72 6.72 No 12/12/2006 6/14/2008 6/11/2008 12/6/2006 M/S Hossain

Construction

100% 100%

350. Nar/RJ-33 Improvement of Bakhonnagar Ghat (RJ) under

Narsingdi-S Upazila

1 No. 1 No. 6.82 6.82 NCB No 9/20/2006 3/23/2008 6/30/2009 9/11/2006 JV of (i) M/S Hossain

Construction & (ii) M/S

Mojibur Traders

100% 100%

351. Nar/RJ-34 Improvement of Alokbali Ghat (RJ) under Narsingdi-S

Upazila

1 No. 1 No. 0.00 0.00 NCB No Dec'07 Jun'09 0% 0%

352. Nara/RJ-35 Improvement of Tarabo Ghat (RJ) under Rupganj

Upazila

1 No. 1 No. 0.00 0.00 NCB No Dec'07 Jun'09 0% 0%

353. Nara/RJ-36 Improvement of Belde Bazar Ghat (RJ) under Rupganj

Upazila

1 No. 1 No. 6.40 6.40 NCB No 3/7/2007 9/7/2008 9/7/2008 3/1/2007 M/S Yousuf &

Associates

100% 100%

354. Nara/RJ-37 Improvement of Sabdi Bazar Ghat (RJ) under Bandor

Upazila

1 No. 1 No. 5.97 5.97 NCB No 4/11/2007 10/12/2008 10/11/2008 4/4/2007 M/S Darbar Trading

Corporation

100% 100%

355. Nara/RJ-38 Improvement of Panchami Ghat (RJ) under Sonargaon

Upazila

1 No. 1 No. 3.01 3.01 NCB No 12/15/2007 6/17/2009 6/6/2009 11/29/2007 M/S Ratna Enterprise 100% 100%

356. Mou/RJ-39 Improvement of Fgazipur Ghat (RJ) under Baraleka

Upazila

1 No. 1 No. 0.00 0.00 NCB No Dec'07 Jun'09 0% 0%

357. Mou/RJ-40 Improvement of Chandgram Ghat (RJ) under Baraleka

Upazila

1 No. 1 No. 0.00 0.00 NCB No Dec'07 Jun'09 0% 0%

358. Mou/RJ-41 Improvement of Kalar Ghat (RJ) under Rajnagar

Upazila

1 No. 1 No. 0.00 0.00 NCB No Dec'07 Jun'09 0% 0%

359. Hab/RJ-42 Improvement of Azmiriganj Ghat (RJ) under Azmiriganj

Upazila

1 No. 1 No. 9.33 9.33 NCB No 2/17/2008 8/20/2009 8/20/2009 1/17/2008 M/S Azad & Brothers 100% 100%

360. Hab/RJ-43 Improvement of Paharpur Ghat (RJ) under Azmiriganj

Upazila

1 No. 1 No. 7.96 7.96 NCB No 2/17/2008 8/20/2009 8/20/2009 1/17/2008 M/S Azad & Brothers 100% 100%

361. Mun/RJ-44 Improvement of Shaperchar Ghat (RJ) under

Sirajdikhan Upazila

1 No. 1 No. 0.00 0.00 NCB No Dec'07 Jun'09 0% 0%

45

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

362. Mun/RJ-45 Improvement of Aldi Bazar Ghat (RJ) under Tongibari

Upazila

1 No. 1 No. 0.00 0.00 NCB No Dec'07 Jun'09 0% 0%

363. Gaz/RPM-1 Maintenance of Kaliganj-Kapasia Road 16.00 Km 16.00 Km 25.81 25.81 NCB No 4/26/2004 4/26/2005 6/30/2006 4/26/2004 Joint Venture of

1. Amzad Traders

2. Suchi Enterprise

100% 100%

364. Nar/RPM-2 Maintenance of Chalakchar bazar-Kotiadi GC via

Charmanadalia Ferryghat Road.

8.15 Km 8.15 Km 4.76 4.76 NCB No 4/10/2004 4/10/2005 9/28/2004 4/1/2004 M/S Project Builders

Ltd.

100% 100%

365. Nar/RPM-3 Maintenance of Shibpur-Charsindur Road. 9.53 Km 9.53 Km 8.51 8.51 NCB No 11/7/2004 11/7/2005 5/25/2005 6/20/2004 Joint Venture of

1. Amzad Traders

2. Suchi Enterprise

100% 100%

366. Man/RPM-4 RPM-4.1 Maintenance of Singair-Baira Road. 7.70 Km 17.70 Km 5.55 20.88 NCB No 5/2/2004 5/2/2005 10/30/2004 4/21/2004 M/S M. R. Construction 100% 100%

RPM-4.2 Maintenance of Betila-Balirteck Road. 10.00 Km 15.33 5/2/2004 5/2/2005 2/28/2005 4/21/2004 M/S M. R. Construction 100% 100%

367. Mun/RPM-5 RPM-5.1 Maintenance of Tongibari-Dighirpar Road 5.00 Km 15.57 Km 7.40 22.62 NCB No 12/1/2004 12/1/2005 11/24/2005 11/25/2004 Parisha Trade System

Ltd.

100% 100%

RPM-5.2 Maintenance of Serajdikhan-Taltala GC Road 7.97 Km 9.73 7/24/2004 7/24/2005 2/28/2006 7/17/2004 Desh Corporation Ltd. 69% 69%

RPM-5.3 Maintenance of Nimtala-Shekhernagar Road 2.60 Km 5.50 5/30/2004 5/30/2005 11/30/2005 5/20/2004 M/S. Punam-Robel JV 100% 100%

368. Sun/RPM-6 RPM-6.1 Maintenance of Sunamgonj-Narayantala (Mongolkata)

Road.

4.30 Km 20.26 Km 4.11 27.48 NCB No 5/4/2004 5/4/2005 10/30/2005 4/15/2004 M/S Belal Enterprise 100% 100%

RPM-6.2 Maintenance of Jagannathpur-Biswanath Road 3.50 Km 5.85 5/4/2004 5/4/2005 9/4/2004 4/12/2004 M/S Abdus Samad 100% 100%

RPM-6.3 Maintenance of (a) Bhaberbazar-Syedpur-Goalabazar

Road Ch. 00-2210m (b) Maintenance of Bhaberbazar-

Syedpur-Goalabazar Road Ch. 2210-9460m.

9.46 Km 14.98 8/1/2004 8/1/2005 1/31/2006 7/29/2004 JV of M/S Nurul Islam 100% 100%

46

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

RPM-6.4 Maintenance of Kaitak-Sirajgonj Road 3.00 Km 2.53 5/4/2004 5/4/2005 8/4/2005 4/15/2004 M/S Alam Construction 100% 100%

369. Bra/RPM-7 RPM-7.1 Maintenance of Kasba-Akhaura Road 7.50 Km 27.19 Km 11.85 43.80 NCB Yes 8/25/2004 8/25/2005 12/31/2005 8/17/2004 M/S Nilu Enterprise 100% 100%

RPM-7.2 Maintenance of Akhaura Bara bazar-Singer bill GCC

Road.

5.45 Km 7.38 8/17/2004 8/17/2005 8/10/2005 8/10/2004 M/S Azad & Brothers 100% 100%

RPM-7.3 Maintenance of Mogra bazar-Kasba-Puran bazar GCC

Road

4.08 Km 5.46 8/25/2004 8/25/2005 8/18/2005 8/17/2004 M/S Haroonur Rashid 100% 100%

RPM-7.4 Maintenance of Chandura-Nurpur Road 10.16 Km 19.11 8/25/2004 8/25/2005 8/18/2005 8/17/2004 M/S Ashraf & Sons 100% 100%

370. Raj/RPM-8 RPM-8.1 Maintenance of Baya-Kashimbazar Road (Paba portion) 9.50 Km 25.20 Km 13.38 30.22 NCB Yes 9/19/2004 9/19/2005 9/11/2005 9/11/2004 SEL & BCPL- JV 100% 100%

RPM-8.2 Maintenance of Baya-Kashimbazar Road (Tanore

portion)

8.00 Km 10.46 9/15/2004 9/15/2005 9/7/2005 8/23/2004 Md. Fazlur Rahman 100% 100%

RPM-8.3 Maintenance of Court-Darusha Road 7.70 Km 6.38 9/15/2004 9/15/2005 9/7/2005 8/23/2004 Mr. Tarek Hossain 100% 100%

371. Nat/RPM-9 RPM-9.1 Maintenance of Halsa GC-Haybatpur RHD Road 4.55 Km 22.30 Km 9.67 39.14 NCB Yes 9/15/2004 9/15/2005 12/15/2005 9/7/2004 M/S Mamun 100% 100%

RPM-9.2 Maintenance of Raina mour-Jonail GC road 8.10 Km 16.03 5/17/2004 5/17/2005 5/10/2005 5/10/2004 Mita Construction 100% 100%

RPM-9.3 Maintenance of Gurudaspur GC-Soykhola road 9.65 Km 13.44 5/17/2004 5/17/2005 5/10/2005 5/10/2004 M/S Rahman

Construction

100% 100%

372. Pab/RPM-10 RPM-10.1 Maintenance of Nazirgonj-Kashinathpur via Aminpur

Road

13.00 Km 22.40 Km 13.28 18.97 NCB No 4/17/2004 4/17/2005 12/27/2006 4/7/2004 Md. Shamsuzzaman 100% 100%

RPM-10.2 Maintenance of Chatmohar R&H-Jonail GCCR via

Haripur UP Road

4.70 Km 2.90 4/17/2004 4/17/2005 4/10/2005 4/8/2004 Mohd. Ali Ahsan 100% 100%

RPM-10.3 Maintenance of Pabna D.H.Q old Polytechnic-Padma

river ghat Road

4.70 Km 2.80 4/17/2004 4/17/2005 6/30/2005 4/8/2004 Md. Abdul Kader 100% 100%

373. Cha/RPM-11 RPM-11.1 Maintenance of Chandra-Ramgonj Road 19.00 Km 23.08 Km 13.76 18.31 NCB No 6/23/2004 6/23/2005 6/22/2005 6/15/2004 M/S Zia Enterprise 100% 100%

RPM-11.2 Maintenance of Chandpur-Chandra Road 4.08 Km 4.54 6/30/2004 6/30/2005 6/30/2005 6/24/2004 Mizanur Rahman Liton 100% 100%

374. Nao/RPM-12 Maintenance of Raninagar-Abadpukur Road 14.20 Km 14.20 Km 12.14 12.14 NCB No 7/15/2004 7/15/2005 2/28/2006 5/31/2004 Joint Venture of

Md. Fazlur Rahaman &

M/S. Alam

Construction Ltd.

100% 100%

375. Sir/RPM-13 RPM-13.1 Maintenance of Muradpur Riverghat-Nagarpur Thana

Border road

6.00 Km 13.90 Km 7.03 21.01 NCB No 11/12/2004 11/12/2005 6/30/2005 11/1/2004 M/S Doyel

Construction

100% 100%

RPM-13.2 Maintenance of Dhangara-Bagbati road 7.90 Km 13.98 7/22/2004 7/22/2005 7/19/2005 7/10/2004 JV of NA-FEAHB 100% 100%

47

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

376. Joy/RPM-14 Maintenance of Akkelpur-Tilokpur Road. 12.85 Km 12.85 Km 28.01 28.01 NCB No 4/4/2004 4/4/2005 8/10/2005 3/20/2004 M/S Hoque Enterprise 100% 100%

377. Naw/RPM-15 RPM-15.1 Maintenance of Bholahat-Argarahat Road 18.40 Km 29.70 Km 10.31 17.20 NCB No 5/20/2004 5/20/2005 5/29/2005 5/11/2004 Md. Fazlur Rahman 100% 100%

RPM-15.2 Maintenance of Shibgonj GC-Khasherhat GC via

Monakashahat Road

11.30 Km 6.89 5/5/2004 5/5/2005 6/30/2006 4/20/2004 Ram Babu 100% 100%

378. Bog/RPM-16 RPM-16.1 Maintenance of Matidali-Pirgacha Road 9.16 Km 29.21 Km 13.68 43.69 NCB Yes 9/15/2004 9/15/2005 11/30/2005 8/26/2004 M/S.Ataur Rahaman

Khan

100% 100%

RPM-16.2 Maintenance of Shibgonj-Charbakra Road 14.98 Km 22.71 9/30/2004 9/30/2005 5/20/2008 9/5/2004 The Bhuiyan

Engineers Ltd.

100% 100%

RPM-16.3 Maintenance of Adamdighi-Abadpukur Road 5.07 Km 7.30 9/29/2005 9/29/2006 1/25/2006 9/16/2004 M/S. S. S. Engineers 100% 100%

379. Dha/RPM-17 RPM-17.1 Maintenance of Dhamrai-Dhantara Road 16.50 Km 24.49 Km 22.06 37.80 NCB Yes 7/28/2004 7/28/2005 7/28/2005 7/8/2004 M/S Fair Construction 100% 100%

RPM-17.2 Maintenance of Jirani Bazar-Shimulia Bazar Road 7.99 Km 15.74 7/27/2004 7/27/2005 7/27/2005 7/7/2004 Joint Venture of SM-

Ahasan-Ratna

Consortium

100% 100%

380. Com/RPM-18 Maintenance of Muradnagar-Elliotgonj Road 15.69 Km 15.69 Km 30.37 30.37 NCB Yes 7/25/2004 7/25/2005 1/30/2008 7/18/2004 M/S. Arab Contractors

(BD) Ltd.

100% 100%

381. Com/RPM-19 RPM-19.1 Maintenance of Suagonj-Pipulia-South Bijoypur Road 16.10 Km 28.09 Km 26.80 46.12 NCB Yes 8/24/2004 8/24/2005 12/31/2007 8/12/2004 Eva Overseas

Corporation

100% 100%

RPM-19.2 Maintenance of Laksam-Monohargonj Road 11.99 Km 19.32 9/5/2004 9/5/2005 9/30/2006 8/31/2004 M/S Al-Haj Abdul

Haque

90% 90%

RPM-19.3 Maintenance of Barkota-Nayergaon via Pitambardi 3.75 Km The road was severely affected by the last flood-2004, major flood damage rehabilitation is found essential, so recently it has been proposed to IDA for Flood Damage

Rehabilitation (FDR) Program instead of previous proposal sent to IDA for re-bidding.

48

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

382. Mou/RPM-20 RPM-20.1 Maintenance of Kucharmahal Dighirpar-Kagabala-

Athangiri Road

11.00 Km 15.80 Km 11.21 14.44 NCB No 8/7/2004 8/7/2005 5/31/2005 7/19/2004 Md. Ilias 100% 100%

RPM-20.2 Maintenance of Daulotpur-Latu Sharoper Road 4.80 Km 3.23 8/7/2004 8/7/2005 5/31/2005 7/19/2004 Md. Monayem Khan 100% 100%

383. Syl/RPM-21 RPM-21.1 Maintenance of Bairagir Bazar GC-Singerkanch Bazar

GC Road

2.80 Km 17.57 Km 6.38 20.96 NCB No 8/30/2004 8/30/2005 8/30/2005 8/23/2004 M/S Chowhdury & Co. 100% 100%

RPM-21.2 Maintenance of Rampasha-Bairagir Bazar Road 2.10 Km 3.80 8/30/2004 8/30/2005 8/30/2005 8/23/2004 M/S Chowhdury & Co. 100% 100%

RPM-21.3 Maintenance of Dayamir GC-Dewanbazar GC Road 5.20 Km 5.65 8/30/2004 8/30/2005 8/30/2005 8/23/2004 Joint Venture of

i) Mahmud Mamun ii)

Suchi Enterprise Ltd.

100% 100%

RPM-21.4 Maintenance of Goalabazar GC-Khadimpur-

Jagannathpur GC Road

7.47 Km 5.13 8/30/2004 8/30/2005 8/30/2005 8/23/2004 M/S Chowhdury & Co. 100% 100%

384. Syl/RPM-22 RPM-22.1 Maintenance of Dhaka Dakhin-Chandarpur-Beanibazar

Road

2.33 Km

Both of the roads was severely affected by the last flood-2004, major flood damage rehabilitation is found essential, so recently it has been

RPM-22.2 Maintenance of Beanibazar-Chandarpur Road 3.85 Km proposed to IDA for Flood Damage Rehabilitation (FDR) Program instead of previous proposal sent to IDA for re-bidding.

385. Hab/RPM-23 RPM-23.1 Maintenance of Paikpara-Sadhurbazar Road 4.80 Km 11.80 Km 4.85 18.89 NCB No 7/21/2005 7/21/2006 7/13/2006 7/10/2005 Md. Golam Faruk 100% 100%

RPM-23.2 Maintenance of Syedpur-Innathgonj Road 7.00 Km 14.04 9/5/2004 9/5/2005 12/31/2005 8/24/2004 Concord Pragatee

Consortium Ltd.

100% 100%

386. Nara/RPM-24 RPM-24.1 Maintenance of Fatulla Post Office-Hazigonj Road 4.50 Km 18.10 Km 7.64 21.64 NCB No 7/24/2004 7/24/2005 7/24/2005 7/17/2004 Joint Venture of

(i) SCM Construction

(ii) M/S Ratna

Enterprise

(iii) M/S Ahasan

Enterprise

100% 100%

RPM-24.2 Maintenance of Rupshi R&H-Kanchan GC via Murapara

GC Road

13.60 Km 14.00 5/6/2004 5/6/2005 5/6/2005 4/29/2004 M/S Abul Hossain 100% 100%

387. Nara/RPM-25 Maintenance of Uchitpura GC-Gopaldi GC via Gohordi-

Khaserkandi-Ramchandradi Road

5.00 Km 5.00 Km 7.44 7.44 NCB No 5/25/2004 5/25/2005 11/30/2005 5/12/2004 M/S Farazi Four Star &

Brothers

100% 100%

388. Gaz/RPM-26 RPM-26.1 Kapasia GC-Kaligonj GC 9.50 Km 17.00 Km 6.15 20.07 NCB No 5/10/2005 5/10/2006 5/9/2006 5/9/2005 M/S L. M. Traders 100% 100%

RPM-26.2 Kapasia-Ranigonj GC road 7.50 Km 13.91 4/28/2005 4/28/2006 4/21/2006 4/21/2005 M/S Akter & SH JV 100% 100%

49

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

389. Dha/RPM-27 RPM-27.1 Kalatia-Balurtek-Bishaw road via Ramerkanda-Ruhitpur

road

13.70 Km 19.55 Km 28.40 35.38 NCB Yes 4/30/2005 4/30/2006 8/24/2006 4/28/2005 M/S A.H Enterprise 100% 100%

RPM-27.2 Kartikpur RHW - Barrah Hat GC. 5.85 Km 6.98 6/15/2005 6/15/2006 6/15/2006 6/8/2005 M/S Eastland

Engineers

100% 100%

390. Man/RPM-28 RPM-28.1 Baliati-Lowhati GC via Pakutia (Delduar UZ) Road 10.86 Km 20.31 Km 14.75 29.38 NCB Yes 3/9/2005 3/9/2006 9/30/2006 3/3/2005 M/S Goodluck Trading

Corporatoin

100% 100%

RPM-28.2 Uthuli-Jaforgonj GC road 9.45 Km 14.63 3/9/2005 3/9/2006 2/26/2007 3/3/2005 Joint Venture of

M/S M. R. Construction

& Lucky Construction

100% 100%

391. Raj/RPM-29 Biraldaha Mazar-Noapara via Singa 13.40 Km 13.40 Km 3.87 3.87 NCB No 7/18/2005 7/18/2006 6/13/2006 7/9/2005 Bishway Construction

Pvt. Ltd.

30% 30%

392. Raj/RPM-30 Kanpara GC-Alipur RHD via Durgapur 15.48 Km 15.48 Km 9.53 9.53 NCB No 7/18/2005 7/18/2006 10/30/2006 7/9/2005 Bishway Construction

Pvt. Ltd.

42% 42%

393. Joy/RPM-31 RPM-31.1 Mongalbari-Shalpara road 5.54 Km 14.14 Km 10.57 17.20 NCB No 3/1/2005 3/1/2006 3/1/2006 2/9/2005 Md. Tarek Hossain 100% 100%

50

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

RPM-31.2 Kalai-Boiragipara-Matrai road 6.60 Km 5.16 3/1/2005 3/1/2006 3/1/2006 2/12/2005 Ram Babu 100% 100%

RPM-31.3 Itakhola-Molamgari GC 2.00 Km 1.47 3/1/2005 3/1/2006 3/1/2006 2/9/2005 Zia International

Enterprise

100% 100%

394. Bog/RPM-32 RPM-32.1 Amtali-Daridaha-Fasitola road 14.80 Km 21.30 Km 28.17 41.31 NCB Yes 7/18/2005 7/18/2006 1/31/2008 7/6/2005 The Bhuiyan Engineer

Ltd.

100% 100%

RPM-32.2 Katham-Kaligonj RHD-Ponditpukur GC via Bhatra UP

Office road

6.50 Km 13.13 6/26/2005 6/26/2006 4/30/2007 6/23/2005 M/S SRF Joint Venture 100% 100%

395. Bog/RPM-33 RPM-33.1 Bogra-Tornihat road (Sadar part) 5.90 Km 16.85 Km 8.81 19.17 NCB No 5/16/2005 5/16/2006 6/30/2006 5/9/2005 Mir Shariful Alam 100% 100%

RPM-33.2 Bogra-Tornihat road (Gabtali part) 4.15 Km 3.52 5/14/2005 5/14/2006 6/15/2006 4/30/2005 SR Joint Venture 100% 100%

RPM-33.3 Santahar-Tilokpur road 6.80 Km 6.84 4/30/2005 4/30/2006 4/29/2006 4/24/2005 M/S Milon Traders 100% 100%

396. Nao/RPM-34 RPM-34.1 Mamudpur R&H-Shibpur GC road 10.00 Km 13.37 Km 8.61 14.36 NCB No 4/19/2005 4/19/2006 3/30/2006 3/30/2005 Road & Bridge

Engineering Co. Ltd.

100% 100%

RPM-34.2 Kashiabari GC (Naoduli)-Kaligonj GC 3.37 Km 5.76 5/5/2005 5/5/2006 12/30/2006 4/20/2005 K. H. Mainul Islam 100% 100%

397. Sir/RPM-35 RPM-35.1 Tarash-Ranir hat Road 6.90 Km 20.65 Km 4.35 18.65 NCB No 6/20/2005 6/20/2006 6/19/2006 6/5/2005 JV of Md. Abu Bakkar

Sk. (Khoka)

M/S Haque

Construction and

K. M. Hossain Ali

100% 100%

RPM-35.2 Jamtail GC-Ullapara GC 5.55 Km 4.70 6/30/2005 6/30/2006 7/30/2006 6/15/2005 M/S Munir Enterprise 100% 100%

RPM-35.3 Raipur Mour-Kandapara 2.25 Km 2.52 6/20/2005 6/20/2006 6/19/2006 6/5/2005 S.M. Liaquat Ali 100% 100%

RPM-35.4 Dariapur GC-Kaizuri GC 5.95 Km 7.07 6/20/2005 6/20/2006 1/31/2007 6/5/2005 JV of Ismail Hossain

and

M/S Pias Construction

(IH- PC JV)

100% 100%

398. Hab/RPM-36 RPM-36.1 Chunarughat-Assampara Road 14.10 Km 26.12 Km 13.07 32.08 NCB Yes 11/17/2005 11/17/2006 6/30/2007 10/30/2005 M/S Provatee

Enterprise.

100% 100%

RPM-36.2 Madhabpur-Chowmohani Bazar Road 12.02 Km 19.01 7/6/2005 7/6/2006 3/31/2007 6/25/2005 JV of S.Islam & Jamil

Iqbal.

100% 100%

399. Naw/RPM-37 Nachole-Mollikpur road 17.60 Km 17.60 Km 7.34 7.34 NCB No 3/22/2005 3/22/2006 3/21/2006 3/15/2005 M/S Shafique Traders 100% 100%

51

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

400. Nat/RPM-38 RPM-38.1 Lalpur-Bilmaria-Durduria Road 10.00 Km 18.20 Km 15.85 27.98 NCB No 8/13/2005 8/13/2006 6/30/2007 8/4/2005 M/S Padma Associates

& Engineers Ltd.

100% 100%

RPM-38.2 Bonapara GC - Moukhara GC 8.20 Km 12.14 7/27/2005 7/27/2006 10/31/2007 7/20/2005 JV of

(i) A. H. M. Tazamel

Haque &

(ii) Md. Abdur Rakib

100% 100%

401. Pab/RPM-39 RPM-39.1 Bharamara-Dhanuaghata GCM road(Faridpur Upazila

Part)

6.24 Km 20.00 Km 6.63 23.37 NCB No 5/4/2005 5/4/2006 5/4/2006 4/16/2005 M/S PABON's 100% 100%

RPM-39.2 Santhia GC-24 Mile R&H road 7.10 Km 9.12 4/17/2005 4/17/2006 8/31/2008 4/12/2005 Md. Ataur Rahman 100% 100%

RPM-39.3 Bera Upazila HQ (GC)-Nakalia GCM Road 5.16 Km 5.93 5/5/2005 5/5/2006 12/31/2006 4/28/2005 M/S Sunny Traders 100% 100%

RPM-39.4 Chatmohar RHD (Bypass)-Jonail GC via Haripur road 1.50 Km 1.69 4/16/2005 4/16/2006 12/31/2006 4/9/2005 M/S Orin Engineers 100% 100%

402. Nara/RPM-40 RPM-40.1 Chaowrapara R&H-Langalbandh GC Road 4.60 Km 22.60 Km 6.10 28.90 NCB No 3/30/2005 3/30/2006 3/30/2006 3/12/2005 The Joint Venture of

(i) M/S Ahasan

Enterprise

(ii) M/S Ratna

Enterprise

100% 100%

RPM-40.2 Araihazar-Elomdi-Jangalia Bazar-Uchitpura Road 11.00 Km 14.39 3/30/2005 3/30/2006 3/30/2006 3/12/2005 The Joint Venture of

(i) M/S SCM

Construction

(ii) M/S Four Star &

(iii) M/S Ratna

Enterprise

100% 100%

RPM-40.3 Mograpara GC - Shubdi Bazar via Hossainpur Road 7.00 Km 8.42 3/30/2005 3/30/2006 3/30/2006 3/12/2005 The Joint Venture of

(i) M/S SCM

Construction

(ii) M/S Ahasan

Enterprise &

(iii) M/S Ratna

Enterprise

100% 100%

403. Nar/RPM-41 RPM-41.1 Monohardi HQ-Panchabati Ferryghat Road 10.74 Km 27.51 Km 13.93 30.19 NCB Yes 5/22/2005 5/22/2006 2/28/2007 4/27/2005 M/S Prokalpo

Bastobayon Ltd.

100% 100%

52

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

RPM-41.2 Gopinathpur-Hasnabad upto Thana Border Road 7.84 Km 6.44 5/13/2005 5/13/2006 12/31/2006 4/27/2005 M/S Prokalpo

Bastobayon Ltd.

100% 100%

RPM-41.3 Baniadi R&H-Shibpur bazar 2.00 Km 2.28 5/22/2005 5/22/2006 5/15/2006 5/8/2005 M/S Bhuiyan & Sons 100% 100%

RPM-41.4 Madhabdi GC-Araihazar Upazila via Kharia bazar Road 2.43 Km 2.51 5/22/2005 5/22/2006 5/15/2006 5/9/2005 M/S Bikalpa Trade

International

100% 100%

RPM-41.5 Charnagardi GC-Purandia RHD via Sukundirghat Road 4.50 Km 5.03 5/16/2005 5/16/2006 5/10/2006 5/8/2005 M/S Khaleque

Construction

100% 100%

404. Mun/RPM-42 RPM-42.1 Munshirhat-Chitulia Road 4.65 Km 14.53 Km 4.86 13.44 NCB No 3/22/2005 3/22/2006 3/14/2006 3/14/2005 Nasir-Jasim JV 100% 100%

RPM-42.2 Kalma-Baligaon Road 3.88 Km 3.08 3/22/2005 3/22/2006 3/14/2006 3/10/2005 Khan-Punam JV 100% 100%

RPM-42.3 Kalma-Baligaon Road 3.00 Km 2.61 3/22/2005 3/22/2006 3/14/2006 3/12/2005 M/S Sarder 100% 100%

RPM-42.4 Meghna Bridge-Hossaindi Bazar Road 3.00 Km 2.88 3/13/2005 3/13/2006 3/5/2006 2/28/2005 Pearl Engineering &

Construction

100% 100%

405. Cha/RPM-43 RPM-43.1 Kachua-Kashempur- Matlab Road 10.64 Km 20.49 Km 17.06 34.32 NCB Yes 5/17/2005 5/17/2006 3/30/2007 5/10/2005 M/S. Partner incharge

(JV of M/S. Patwary

Trade International &

M/S. G.K. Enterprise)

100% 100%

RPM-43.2 Matlab Bazar-Sengarchar Road 9.85 Km 17.26 5/24/2005 5/24/2006 12/30/2006 5/17/2005 M/S Bashundhara 100% 100%

406. Bra/RPM-44 RPM-44.1 Nurpur-Singerbeel Road 7.18 Km 20.18 Km 8.18 21.98 NCB No 5/14/2005 5/14/2006 5/6/2006 4/10/2005 M/S Ashraf & Sons 100% 100%

RPM-44.2 Saydabad C&B Road-DC Road-Mondabagh Road 5.50 Km 6.05 5/18/2005 5/18/2006 5/10/2006 5/3/2005 M/S. Nilu Enterprise 100% 100%

RPM-44.3 Bancharampur GC-Ujanchar GC via Dariachar bazar

Road

7.50 Km 7.76 5/14/2005 5/14/2006 7/31/2006 4/19/2005 M/S Azad & Brothers 100% 100%

407. Com/RPM-45 RPM-45.1 Comilla-Fakir Bazar-Saldanadi Road under

Brahmanpara Upazila

6.59 Km 24.54 Km 19.85 51.88 NCB Yes 6/17/2005 6/17/2006 10/31/2006 6/11/2005 M/S. Golden Traders 100% 100%

RPM-45.2 Comilla-Fakir Bazar-Saldanadi Road under Burichong

Upazila

11.30 Km 18.43 6/30/2005 6/30/2006 9/30/2006 6/18/2005 M/S Toaa Enterprise 100% 100%

RPM-45.3 Comilla (Chandpur Bridge)-Fakir Bazar-Saldanadi

(B.Para)Road under Comilla-S Upazila

6.65 Km 13.61 8/2/2005 8/2/2006 7/15/2007 7/19/2005 M/S Al-Haj Abdul

Haque

100% 100%

408. Com/RPM-46 Chandina-Dollai Nawabpur Road 9.27 Km 9.27 Km 13.49 13.49 NCB No 7/29/2005 7/29/2006 8/31/2007 7/12/2005 M/S Surma

International

100% 100%

53

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

409. Mou/RPM-47 RPM-47.1 Shahbandar - Dighirpar - Gobindapur Road 3.00 Km 17.42 Km 3.45 21.72 NCB No 4/11/2005 4/11/2006 4/10/2006 3/17/2005 Joint Venture of S.M.

Consotium

100% 100%

RPM-47.2 Agunshi-Aguin-Podinapur-Baburbazar Road 2.70 Km 3.60 4/11/2005 4/11/2006 4/10/2006 3/17/2005 Joint Venture of A.M.

Consotium

100% 100%

RPM-47.3 Shahbandar-Shomshargonj Road 1.00 Km 1.39 4/17/2005 4/17/2006 3/6/2007 1/27/2005 Misbah Uddin Ahmed 100% 100%

RPM-47.4 Dewandighi (RHD)-Paulpur Road 10.72 Km 13.28 4/4/2005 4/4/2006 3/31/2007 3/17/2005 Md. Monayem Khan 100% 100%

410. Syl/RPM-48 RPM-48.1 Salutikar-Gowainghat Road 6.35 Km 13.72 Km 7.72 16.56 NCB No 7/3/2005 7/3/2006 6/26/2006 6/21/2005 Tower Enterprise Ltd. 100% 100%

RPM-48.2 Horripur-Shaheberbazar-Salutikar Road 2.71 Km 3.53 12/27/2005 12/27/2006 12/27/2006 12/20/2005 A.T. M. Belayet

Hossain

100% 100%

RPM-48.3 Horripur-Shaheberbazar-Salutikar Road 4.66 Km 5.31 7/4/2005 7/4/2006 6/27/2006 6/27/2005 M/S Md. Jamil Iqbal 100% 100%

411. Syl/RPM-49 RPM-49.1 Kumargaon-Badaghat-Shiberbazar Road 3.01 Km 12.01 Km 3.54 14.52 NCB No 7/9/2005 7/9/2006 7/1/2006 7/2/2005 A. K. M. Delwar

Hossain

100% 100%

RPM-49.2 Beanibazar-Sharupar Road 4.00 Km 2.61 7/9/2005 7/9/2006 7/1/2006 7/2/2005 A. K. M. Delwar

Hossain

100% 100%

RPM-49.3 Fenchugonj GC-Gillachara GC Road 5.00 Km 8.37 7/3/2005 7/3/2006 6/26/2006 6/26/2005 Mahmud Mamun 100% 100%

412. Sun/RPM-50 RPM-50.1 Sunamgonj-Mongalkata road 2.00 Km 31.20 Km 2.22 24.38 NCB Yes 2/12/2006 2/12/2007 6/11/2007 1/5/2006 Moni Construction 100% 100%

RPM-50.2 Sunamgonj-Bitgonj Road 4.85 Km 6.85 2/5/2006 2/5/2007 12/30/2007 1/8/2006 JV of (i) M/S Belal

Enterprise (ii) Alam

Construction

100% 100%

RPM-50.3 Derai-Shyamerchar Road 9.40 Km 8.65 9/1/2005 9/1/2006 2/28/2008 8/8/2005 JV of i) M/S. Sayed

Enterprise

ii) M/S. Nural Islam

100% 100%

RPM-50.3 Keshabpur-Rasulgonj-Tuker Bazar-Panaullah Bazar

Road

14.95 Km 6.66 3/7/2006 3/7/2007 11/30/2007 2/26/2006 JV of M/S Badrul Huda

Mukal

60% 60%

54

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

413. Nao/RPM-51 Badalgachi GC-Paharpur-Durgadaha GC (Joypurhat) 13.70 Km 13.70 Km 7.22 7.22 NCB No 12/18/2005 12/18/2006 6/30/2007 4/12/2005 ATCO-Ethen Joint

venture.

46% 46%

414. Dha/RPM-52 Uttar Budda Pragati Shrani-Baried road 7.00 Km 7.00 Km 14.55 14.55 NCB No 12/14/2005 12/14/2006 11/23/2006 11/23/2005 M/S Rahman Brothers 100% 100%

415. Gaz/RPM-53 RPM-53.1 a) Kapasia GC-Sreepur Road.

b) Aral GC-Hatirdia GC Road

11.58 Km 35.00 Km 21.93 48.69 NCB Yes 7/19/2006 7/19/2007 6/30/2008 7/12/2006 M/S Orient Trading &

Builders Ltd

100% 100%

RPM-53.2 Shafipur- Boraibri Road 4.10 Km 6.47 7/19/2006 7/19/2007 12/31/2007 7/12/2006 JV of M/S SH & Akhter 100% 100%

RPM-53.3 Mowchak- Fulbaria Road 9.07 Km 10.92 7/19/2006 7/19/2007 2/25/2008 7/12/2006 JV of M/S Olive, Refat

& Siraj Enterprise

100% 100%

RPM-53.4 Sreepur College-Kapasia Road. 10.25 Km 9.37 7/19/2006 7/19/2007 7/18/2007 7/12/2006 M/S LM Traders 100% 100%

416. Dha/RPM-54 RPM-54.1 Kalatia GC-Taranagar UP office via Chapara Bariakandi

Road.

2.40 Km 18.83 Km 4.19 17.87 NCB No 4/10/2006 4/10/2007 4/3/2007 3/29/2006 Bikalpa Trade

International

100% 100%

RPM-54.2 Nawabgonj -Paragramhat GC Road. 16.43 Km 13.68 4/16/2006 4/16/2007 12/15/2007 4/6/2006 JV of M/S Friends

Construction & M/S

Janani Traders &

International

100% 100%

55

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

417. Man/RPM-55 RPM-55.1 Doulatpur-Kolia hat Road. 9.30 Km 28.40 Km 0.87 12.09 NCB No 9/6/2006 9/6/2007 3/31/2008 8/31/2006 M/S Unnayan

Engineers &

Associates

15% 15%

RPM-55.2 Mahadebpur-Jhikta GC via Gangasagar Road 9.10 Km 2.66 11/1/2006 11/1/2007 6/30/2008 8/20/2006 M/S Sugandha

Enterprise

45% 45%

RPM-55.3 Nayadingi NHR-Katigram Road 4.00 Km 3.40 9/6/2006 9/6/2007 11/6/2007 8/31/2006 M/S Unnayan

Engineers &

Associates

100% 100%

RPM-55.4 Saturia GC-Dargram GC Road 6.00 Km 5.16 8/28/2006 8/28/2007 7/31/2008 8/20/2006 M/S Sugandha

Enterprise

100% 100%

418. Nara/RPM-56 RPM-56.1 Rupganj-Debori-Beldi Bazar-Kaliganj Road. 8.80 Km 18.65 Km 8.88 23.77 NCB No 4/17/2006 4/17/2007 4/17/2007 4/10/2006 M/S Yousuf &

Associates

100% 100%

RPM-56.2 Uchitpura GC-Jangalia Bazar-Shantir Bazar-Barodi GC

Road.

2.85 Km 7.78 4/12/2006 4/12/2007 4/12/2007 4/4/2006 M/S Hasina Enterprise

& M/S Mohammadi

Traders (JV)

100% 100%

RPM-56.3 Noyapur-Panchmighat GC Road 2.50 Km 4.00 4/23/2006 4/23/2007 4/29/2007 4/17/2006 M/S Khandakar Shahin

Ahamed

100% 100%

RPM-56.4 Demra-Narshingdi R&H Borpa Mazerchara via Pakunda-

Taltala-Mahajompur Road

4.50 Km 3.11 4/19/2006 4/19/2007 4/19/2007 4/12/2006 M/S SCM Construction 100% 100%

419. Mun/RPM-57 RPM-57.1 Mowaghat-Bhagyakul road 4.20 Km 22.31 Km 2.59 32.89 NCB Yes 5/25/2006 5/25/2007 5/24/2007 5/16/2006 Authentic Enterprise 100% 100%

RPM-57.2 Bejgoan RHD-Kukutia-Nagerhat-Kanakshar road 4.86 Km 18.47 1/11/2007 1/11/2008 4/30/2009 1/4/2007 Yousuf & Associates 100% 100%

RPM-57.3 National Highway-Bhaberchar GC road 1.20 Km 1.33 6/21/2006 6/21/2007 6/13/2007 5/25/2006 M/S Hema

Construction

100% 100%

56

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

RPM-57.4 Munshigonj HQ (Loharpur)-Aldi RHD road 6.00 Km 5.13 6/21/2006 6/21/2007 4/30/2008 5/23/2006 M/S Bashundhara 75% 75%

RPM-57.5 Dhaka Mawa RHD-Kuchiamara-Shekernagar GC via

Sayedpur-Chittrakot UP road

6.05 Km 5.36 5/25/2006 5/25/2007 5/31/2008 5/15/2006 Nazma Construction

Co.

70% 70%

420. Nar/RPM-58 RPM-58.1 Monohordi HQ-Drinerghat RHD road 1.63 Km 25.79 Km 5.53 27.05 NCB No 1/23/2008 1/22/2009 4/30/2009 1/17/2008 M/S Scan Associates

Pvt. Ltd.

100% 100%

RPM-58.2 Monohordi GC-Shavardi R&H road 5.50 Km 1.96 7/20/2006 7/20/2007 7/12/2007 7/9/2006 M/S S & S Co. 100% 100%

RPM-58.3 Upazila HQ-Charsindur GC road 2.25 Km 6.29 7/20/2006 7/20/2007 10/31/2007 7/9/2006 M/S Khaleque

Construction

100% 100%

RPM-58.4 Sreerampur Railgate R&H-Monipura GC road 16.41 Km 13.27 12/4/2006 12/4/2007 12/30/2009 11/28/2006 M/S Good Luck

Trading Corporation

100% 100%

421. Com/RPM-59 RPM-59.1 Upazila HQ (Nabagram)-Munshirhat-Kadir bazar-

Kashinagarbazar road

6.71 Km 38.24 Km 9.16 51.02 NCB Yes 9/18/2006 9/18/2007 9/17/2007 9/10/2006 M/S A & Z Construction 78% 78%

RPM-59.2 Kongshanagar bazar-Abidpur road 1.74 Km 2.56 9/25/2006 9/25/2007 12/30/2007 9/12/2006 M/S Islam Traders 100% 100%

57

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

RPM-59.3 B.Para-Dulalpur GC road 4.54 Km 3.71 3/16/2008 3/16/2009 3/22/2009 3/16/2008 M/S Toaa Enterprise 48% 48%

RPM-59.4 Madhaiya GC-Punchpukuria GC (Debidwar Portion) 8.00 Km 10.67 6/6/2007 6/5/2008 6/5/2008 5/29/2007 JV of M.S.T.C. & M.I.T 100% 100%

RPM-59.5 Laksam-Mudaffargonj road 5.10 Km 2.68 4/17/2007 4/16/2008 4/16/2008 4/11/2007 M/S Pappu Traders 39% 39%

RPM-59.6 Balutupa-Suagonj-Bijoypur-Adinamura-Bataichari-

Barura

6.75 Km 10.19 9/10/2006 9/10/2007 9/9/2007 9/3/2006 M/S Moni Roni

Enterprise

100% 100%

RPM-59.7 Nangalkot-Khila road 5.40 Km 12.04 9/26/2006 9/26/2007 5/30/2008 9/18/2006 M/S Surma

International

100% 100%

422. Bra/RPM-60 RPM-60.1 Singerbeel-Harashpur road via Paharpur UP 2.80 Km 16.95 Km 2.78 24.55 NCB No 7/2/2006 7/2/2007 6/24/2007 5/22/2006 TE-MB Joint Venture 100% 100%

RPM-60.2 Tinlacpur R&H-Simrail GC road via Chargas Bazar 9.15 Km 13.91 5/14/2006 5/14/2007 3/31/2008 5/7/2006 Kamal Associates 100% 100%

RPM-60.3 Bitghar hat-Tinlacpur via Kitala bazar road 5.00 Km 7.85 5/23/2006 5/23/2007 5/15/2007 5/15/2006 Urmi Enterprise 100% 100%

423. Cha/RPM-61 RPM-61.1 a) Faridgonj R&H-Rampur Sollakhali road

b) Rampur GC-Haimchar Upazila road

17.20 Km 27.73 Km 18.85 33.49 NCB Yes 4/2/2007 4/1/2008 8/30/2008 8/3/2006 The Sun Flower 100% 100%

RPM-61.2 Chandpur Puran bazar-Haimchar-Char Bhairabi road 10.53 Km 14.64 8/27/2006 8/27/2007 12/30/2007 8/21/2006 Mizanur Rahman Liton 100% 100%

58

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

424. Syl/RPM-62 RPM-62.1 Hetimgonj-Dhaka Dakshin Chandarpur-Beanibazar

road (Golapganj Portion)

12.48 Km 17.48 Km 19.15 21.19 NCB No 6/17/2006 6/17/2007 10/30/2007 6/10/2006 NA-JI (JV) 100% 100%

RPM-62.2 Hetimgonj-Dhaka Dakshin Chandarpur-Beanibazar

road (Beanibazar Portion)

5.00 Km 2.04 4/27/2006 4/27/2007 4/27/2007 4/10/2006 M/S Md. Jahed Iqbal 100% 100%

425. Sun/RPM-63 RPM-63.1 Mongalkata-Narayantala-Kapua (Chinakandi-

Moheshkhola) road

6.70 Km 9.19 Km 12.69 16.07 NCB No 9/26/2007 9/25/2008 10/7/2008 9/6/2007 Mark International 100% 100%

RPM-63.2 Anwarpur-Badaghat-Kawkandi road 2.49 Km 3.38 9/26/2007 9/25/2008 10/7/2008 9/6/2007 Mark International 100% 100%

426. Hab/RPM-64 RPM-64.1 Nabiganj-Rudragram Road. 8.40 Km 10.30 Km 10.99 12.80 NCB No 4/24/2006 4/24/2007 6/30/2007 4/9/2006 Rathindra Chandra

Roy

100% 100%

RPM-64.2 Dhuliakhal - Kotiadi road 1.90 Km 1.81 4/24/2006 4/24/2007 4/23/2007 4/9/2006 Chowdhury Enterprise 100% 100%

427. Mou/RPM-65 RPM-65.1 Lwayuni-Munshibazar road 3.30 Km 9.90 Km 6.04 9.95 No 8/14/2006 8/14/2007 3/31/2008 6/27/2006 M/S Ali Prokoushali 100% 100%

RPM-65.2 Muraul RHD-Chandgram GC road 6.60 Km 3.91 7/23/2006 7/23/2007 7/9/2007 7/10/2006 M/S Ali Prokoushali 100% 100%

428. Raj/RPM-66 RPM-66.1 Bagha Bus stand-Mirgonj (R&H) via Harirampur GC

road

7.35 Km 44.12 Km 9.29 32.80 NCB Yes 9/25/2006 9/25/2007 9/17/2007 9/14/2006 Md. Fazlur Rahman 100% 100%

RPM-66.2 Kamarpara-Gangopara UZR road 7.85 Km 8.05 9/7/2006 9/7/2007 4/30/2008 8/31/2006 M/S Rana International

Builders

100% 100%

RPM-66.3 (a) Tanore-Chowbaria UZR road

(b) Kakonhat GC-Kaligonj road

21.17 Km 4.54 9/7/2006 9/7/2007 8/30/2007 8/31/2006 M/S Taher Brothers 100% 100%

RPM-66.4 Darusha-Kakon GC via Darshanpara road 7.75 Km 10.92 9/7/2006 9/7/2007 12/31/2007 8/31/2006 Md. Fazlur Rahman 100% 100%

429. Bog/RPM-67 RPM-67.1 Sonatala-Naruamala road 21.06 Km 32.06 Km 13.98 23.54 NCB No 6/13/2006 6/13/2007 2/28/2008 6/1/2006 M/S OK Enterprise Pvt.

Ltd.

100% 100%

RPM-67.2 Shariakandi-Chandanbaisha road 2.45 Km Dropped from the project

RPM-67.3 Namajgor-Namuja road 11.00 Km 9.56 6/25/2006 6/25/2007 10/31/2007 6/15/2006 M/S Ataur Rahman

Khan

100% 100%

430. Nao/RPM-68 RPM-68.1 Hapania-Katkhur road 11.21 Km 28.10 Km 12.54 27.96 NCB No 1/7/2008 1/6/2009 2/28/2009 12/31/2007 M/S Ataur Rahman

Khan

100% 100%

RPM-68.2 Modhuil GC-Shibpur GC road 8.55 Km 7.15 1/7/2008 1/6/2009 1/6/2009 12/31/2007 M/S Ataur Rahman

Khan

100% 100%

RPM-68.3 Ahsangonj GC-Kaligonj GC via Kasiabari GC road 8.35 Km 8.26 10/5/2006 10/5/2007 3/31/2009 8/9/2006 Ram Babu 100% 100%

431. Sir/RPM-69 RPM-69.1 (a) Dhangora GC-Bhuyaganti NHW

(b) Nimgachi-Salangha GC road

5.65 Km 30.65 Km 7.88 37.11 NCB Yes 2/27/2007 2/27/2008 6/30/2008 2/20/2007 Md. Amirul Islam 100% 100%

59

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

RPM-69.2 (a) Ullapara-Mohonpur GC

(b) Ullapara-Goyhatta GC road

8.35 Km 7.33 9/5/2007 9/4/2008 3/4/2009 8/29/2007 M/S Mita Consruction 100% 100%

RPM-69.3 (a) Harinatpur GC to Sonamukhi GC

(b) Alokdiar DR-Bolorampur GC

(c) Enayetpur GC-KG School DR road

16.65 Km 21.90 8/20/2006 8/19/2007 9/30/2008 8/13/2006 M/S Munir Enterprise 100% 100%

60

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

432. Naw/RPM-70 RPM-70.1 Nawabgonj-Shibgonj R&H-Ramchandrapur GC road 2.20 Km 9.40 Km 2.52 6.95 NCB No 3/22/2006 3/22/2007 3/21/2007 3/8/2006 Md. Saidur Rahman

Consturction Ltd.

100% 100%

RPM-70.2 Bholahat (Chawmohany)-Futani bazar road 7.20 Km 4.43 3/22/2006 3/22/2007 3/21/2007 3/8/2006 M/S Shafique Traders 100% 100%

433. Pab/RPM-71 RPM-71.1 Dublia GCM-Kuchiamora RHD road 5.95 Km 18.39 Km 8.41 29.43 NCB Yes 8/12/2006 8/12/2007 8/12/2007 8/6/2006 Binoy Joty Kundu 100% 100%

RPM-71.2 Pabna-Pakshi RHD (Zero Point) at Library Bazar-

Khayerbagan GCM via Char Shibrampur Sluice gate

road

2.44 Km 4.23 10/18/2006 10/17/2007 12/31/2007 10/10/2006 M/S Shafique Traders 100% 100%

RPM-71.3 Bhangura H/Q at Baral River ghat Mondotos at R&H

road

2.75 Km 4.82 8/8/2006 8/8/2007 1/31/2008 7/24/2006 Sarker Golam

Mohammad & Co. Ltd.

100% 100%

RPM-71.4 Nakalia GC-Nalkhola GC road 7.25 Km 11.96 7/17/2006 7/17/2007 7/16/2007 7/4/2006 Sarker Golam

Mohammad & Co. Ltd.

100% 100%

434. Nat/RPM-72 Chowgarm RHD-Kaligonj GCM Road 8.04 Km 8.04 Km 15.98 15.98 NCB No 5/17/2006 5/17/2007 5/10/2007 5/10/2006 JV of Md. Anisur

Rahman, Md. Abdul

Motin Mia & M/S Khan

Traders

100% 100%

435. Nat/RPM-73 Jamtoli RHD-Bamihal-Ranirhat GCM Road 9.70 Km 9.70 Km 24.86 24.86 NCB No 5/22/2006 5/22/2007 5/15/2007 5/15/2006 Mita Construction 100% 100%

436. Dha/RPM-74 Matuyal Mirdhabari-Golokata road via Konapara Hazi

nogor Road.

6.00 Km 6.00 Km 14.32 14.32 NCB No 4/13/2006 4/13/2007 4/6/2007 4/6/2006 JV of M/S Joney

Enterprise & M/S

Mohuya Enterprise

100% 100%

437. Nao/RPM-75 Mohadevpur GCM-Matajee hat GCM road 12.37 Km 12.37 Km 11.49 11.49 NCB No 10/5/2006 10/5/2007 11/30/2009 8/8/2006 Ram Babu 100% 100%

438. Nao/RPM-76 Maintenance of Chatra GC - Shibpur GC Road. 3.38 Km 3.38 Km 10.39 10.39 NCB No 7/22/2007 7/21/2008 12/31/2008 7/15/2007 M/S JE & MSH JV 100% 100%

439. Gaz/RPM-77 Maintenance of Mouchak-Fulbaria road 7.50 Km 7.50 Km 38.92 38.92 NCB Yes 11/1/2007 10/31/2008 3/15/2009 10/25/2007 M/S Amzad Traders 100% 100%

440. Gaz/RPM-78 Maintenance of Jaina Bazar-Batajor road 5.50 Km 5.50 Km 16.95 16.95 NCB No 12/30/2007 12/29/2008 12/31/2009 12/23/2007 SHK & Co & Dhiman

Construction

100% 100%

441. Nat/RPM-79 Maintenance of Koyen RHD-Jonail road (Ch. 0+000-

6+016km)

6.02 Km 6.02 Km 30.29 30.29 NCB Yes 2/27/2008 2/26/2009 12/31/2009 2/7/2008 M/S. Padma

Associates &

Engineers Ltd.

100% 100%

442. Nao/RPM-80 Maintenance of Abadpukur GC-Kaligonj GC road 2.75 Km 2.75 Km 6.51 6.51 NCB No 7/22/2007 7/21/2008 11/30/2008 7/12/2007 Mrs. Jesmin BHB JV 100% 100%

61

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

443. Sir/RPM-81 Maintenance of Baruhash RHD-Ranirhat GC road 2.23 Km 2.23 Km 7.46 7.46 NCB No 7/17/2007 7/16/2008 12/31/2008 7/12/2007 M/S Jumuna

Construction JV M/S

Ashraf & Sons

100% 100%

444. Pab/RPM-82 Maintenance of Debuttor RHD-Ekdanta GC road 5.20 Km 5.20 Km 20.71 20.71 NCB No 10/16/2007 10/15/2008 6/30/2009 9/30/2007 Md. Shahjahan Ali 100% 100%

445. Cha/RPM-83 Maintenance of Chandpur (Raghunathpur)-Balia GC-

Chandra GC road

2.68 Km 2.68 Km 4.43 4.43 NCB No 5/10/2007 5/9/2008 5/6/2008 5/7/2007 M/S. Property

Construction

100% 100%

446. Bra/RPM-84 Maintenance of Singerbeel-Harashpur via Paharpur UP 7.95 Km 7.95 Km 21.81 21.81 NCB No 9/23/2007 9/22/2008 9/22/2008 9/9/2007 M/S. TE-MB & NI

Brothers JV

100% 100%

447. Hab/RPM-85 Maintenance of Dhuliakhal-Mirpur road (Sadar Part) 5.10 Km 5.10 Km 13.65 13.65 NCB No 7/23/2007 7/22/2008 1/31/2009 7/5/2007 Farazi-Akbar JV 100% 100%

448. Syl/RPM-86 Maintenance of Kanaighat-Gachbari-Sylhet road 22.13 Km 22.13 Km 0.00 0.00 NCB No May'07 Nov'08 0% 0%

449. Bog/UZR-307 UZR-307.1 Improvement of Naruamala - Matidhali Road and

construction of appurtenant structures.

8.15 Km 18.31 Km 60.46 136.19 NCB Yes 10/22/2006 4/24/2008 5/31/2009 10/8/2006 M/S Ataur Rahman

Khan

100% 100%

UZR-307.2 Improvement of Baluahat - Sukhanpukur and

construction of appurtenant structures.

10.16 Km 75.72 12/26/2006 6/28/2008 8/30/2009 12/17/2006 Islam Trading

Consortium Ltd.

100% 100%

450. Com/UZR-308 UZR-308.1 Improvement of Dulalpur-Bancharampur Road and

construction of appurtenant structures.

3.00 Km This slice (UZR-308.1) has been excluded from RTIP as a parallel road including a large bridge on "Titas River" has already being improved by RHD.

UZR-308.2 Improvement of Comilla-Rasulpur Road and

construction of appurtenant structures.

4.22 Km This slice (UZR-308.2) has been excluded from RTIP as the road has already been rehabilitated by other project of LGED.

451. Dha/UZR-309 Improvement of Dhaka Mawa RHD at Tegharia-Bibir

Bazar-Shaper Bazar-Taltala hat GC-Betka Road

(Dhaka Portion) and construction of 65 m bridge at

chainage 6720 m including other appurtenant

structures.

5.00 Km 5.00 Km 54.37 54.37 NCB Yes 5/8/2005 11/9/2006 9/30/2007 5/5/2005 M/S Ali & Co. 100% 100%

452. Dha/UZR-312 Improvement of Dhaka Mawa RHD at Tegharia-Bibir

Bazar-Shaper Bazar-Taltala hat GC-Betka Road

(Dhaka Portion Part-2)

3.01 Km 3.01 Km 39.36 39.36 NCB Yes 11/1/2007 5/4/2009 3/30/2010 6/25/2007 M/S Ali & Co. 100% 100%

62

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

453. Dha/UZR-313 a) Improvement of Dhaka Aricha highway-Kalatipara

GC via Vakurta bazar. and construction of appurtenant

structures.

8.63 Km 12.93 Km 56.42 56.42 NCB Yes 9/25/2007 3/28/2009 12/31/2009 9/18/2007 JV of Sarker Golam

Mohammad Co. Ltd.

and M/S N. N. Traders

55% 55%

b) Improvement of Dhaka Aricha RHD-Mugrakanda-

M.pur.city prot. Embank. Road and construction of

appurtenant structures.

4.30 Km 0.00

454. Sun/UZR-314 UZR-314.1 Improvement of Dharmapasha-Joysree Road(Chainage

: 0+000-6+150 km)

6.15 Km 10.95 Km 98.18 199.53 NCB Yes 10/8/2007 4/10/2009 5/30/2011 9/25/2007 Project Builders Ltd. 100% 100%

UZR-314.2 Improvement of Dharmapasha-Joysree

Road.(Chainage : 6+150-10+950 km)

4.80 Km 101.35 10/8/2007 4/10/2009 6/30/2009 9/25/2007 Project Builders Ltd. 25% 25%

455. Gaz/UZR-315 UZR-315.1 Improvement of Mouchak- Fulbaria Road (Ch.11500m-

Ch.16350m)

4.85 Km 9.72 Km 32.57 64.73 NCB Yes 6/20/2007 12/21/2008 12/19/2008 6/13/2007 JV of i) M/S Amzad

Traders ii) M/S Reefat

Enterprise

100% 100%

63

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

UZR-315.2 Improvement of Mouchak- Fulbaria Road (Ch.16350m-

Ch.21220m)

4.87 Km 32.16 NCB Yes 5/23/2007 11/23/2008 2/26/2009 5/15/2007 M/S Sarker Golam

Mohammad Co. Ltd.

100% 100%

456. Nat/UZR-316 Improvement of Koyen RHD-Jonail GC Road 7.47 Km 7.47 Km 48.79 48.79 NCB Yes 4/15/2007 10/16/2008 10/13/2008 4/8/2007 M/S Shafique Traders 100% 100%

457. Nao/UZR-317 Improvement of Chatra GC-Shibpurhat GC Road 8.93 Km 8.93 Km 55.12 55.12 NCB Yes 4/22/2007 10/23/2008 11/30/2008 4/1/2007 M/S Ataur Rahman

Khan

100% 100%

458. Sir/UZR-318 UZR-318.1 Improvement of Baruhash RHD-Ranirhat Road (Ch.

0+000-5+600 km)

5.60 Km 12.75 Km 42.98 103.16 NCB Yes 3/15/2007 9/15/2008 12/31/2009 3/8/2007 Alpana-Joy-M.H JV 100% 100%

UZR-318.2 Improvement of Baruhash RHD-Ranirhat Road (Ch.

5+600-12+750 km)

7.15 Km 60.19 NCB Yes 2/2/2008 8/5/2009 12/30/2009 1/17/2008 M/S Ataur Rahman

Khan

100% 100%

459. Raj/UZR-319 Improvement of Bidhirpur GC-Basantapur R&H road 5.90 Km 5.90 Km 40.05 40.05 NCB Yes 7/15/2007 1/15/2009 1/9/2009 6/17/2007 Md. Fazlor Rahman 100% 100%

460. Pab/UZR-320 Improvement of Debottor RHD-Ekdanta GC Road. 7.30 Km 7.30 Km 51.59 51.59 NCB Yes 7/6/2007 1/6/2009 12/26/2008 6/12/2007 JV of Mag Trade

System and Others

100% 100%

461. Syl/UZR-321 UZR-321.1 Improvement of Sylhet-Gachbari GC-Kanaighat Upazila

HQ road (Chainage : 0+000-9+000 km)

9.00 Km 17.35 Km 48.85 102.01 NCB Yes 6/13/2007 12/14/2008 3/31/2011 5/29/2007 Project Builders Ltd. 100% 100%

UZR-321.2 Improvement of Sylhet-Gachbari GC-Kanaighat Upazila

HQ road (Chainage : 9+000-17+350 km)

8.35 Km 53.16 NCB 6/1/2007 12/2/2008 6/30/2010 5/29/2007 Project Builders Ltd. 100% 100%

462. Hab/UZR-322 UZR-322.1 Improvement of Inathgonj (Kazir Bazar)-Kadirgonj

(Chainage : 4+200-13+000 km)

8.80 Km 19.56 Km 57.95 159.18 NCB Yes 4/23/2008 10/25/2009 2/28/2011 4/9/2008 21st Century-Maitry JV 100% 100%

UZR-322.2 Improvement of Inathgonj (Kazir Bazar)-Kadirgonj

(Chainage : 13+000-23+760 km)

10.76 Km 101.23 NCB 1/6/2008 7/9/2009 6/30/2010 12/23/2007 21st Century-Maitry JV 100% 100%

463. Cha/UZR-323 Improvement of Chandpur (Raghunathpur)-Balia GC-

Chandra GC road

5.44 Km 5.44 Km 27.62 27.62 NCB No 7/18/2007 1/18/2009 1/17/2009 7/15/2007 The Sun Flower 100% 100%

464. Mou/UZR-324 Improvement of RHD-Bhairob bazar-Munshibazar via

Mirtinga Tea Garden road

4.18 Km 4.18 Km 31.58 31.58 NCB Yes 8/15/2007 2/15/2009 6/30/2010 8/5/2007 M.A.H.M.I JV 100% 100%

465. Mou/UZR-325 Improvement of Munshibazar-Mirtinga-Bhairobbazar

RHD road

6.83 Km 6.83 Km 35.57 35.57 NCB Yes 8/15/2007 2/15/2009 6/30/2010 7/31/2007 M.A.H.M.I JV 100% 100%

466. Bra/UZR-326 Improvement of Singerbeel-Harashpur via Paharpur UP 7.55 Km 7.55 Km 54.71 54.71 NCB Yes 6/11/2007 12/12/2008 12/31/2009 5/29/2007 JV of 21st Century

Housing Ltd.-M/S.

Maitry Builders

100% 100%

467. Bra/UZR-327 Improvement of Bottali-Bitghar road 7.68 Km 7.68 Km The road has been dropped from ICB package of B.Baria district and the techno-economic feasibility report has sent to IDA for clearance.

After receiving clearance fresh bid will be invited

64

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

468. Nao/UZR-328 Improvement of Chatra GC-Mohadevpur GC road

including construction of 100 m RCC Bridge

1.16 Km 1.16 Km 50.46 50.46 NCB Yes 1/15/2008 7/18/2009 3/31/2010 1/8/2008 M/S S. F & M.B JV 100% 100%

469. Sir/UZR-330 Improvement of Dhamai kandi R&H - Solonga GC and

construction of appurtenant structures.

6.98 Km 6.98 Km 24.42 24.42 NCB No 6/4/2008 12/6/2009 6/30/2010 5/20/2008 Mir Shariful Alam 57% 57%

470. Mun/UZR-25A UZR-25A.1 Improvement of Shirajdikhan-Shaperchar road (Ch.

0+000-4+700 km)

4.70 Km 7.23 Km 51.50 79.64 NCB Yes 6/26/2008 12/28/2009 6/30/2010 6/15/2008 JV of 21st Century

Housing Ltd.-M/S.

Maitry Builders

100% 100%

UZR-25A.2 Improvement of Shirajdikhan-Shaperchar road (Ch

4+700-7+235 km)

2.53 Km 28.15 NCB Yes 6/22/2008 12/24/2009 6/30/2010 6/15/2008 Md. Rashaduzzaman 100% 100%

65

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

471. Com/UZR-33.2A Improvement of Noagaon - Panchkitta Road and

construction of 45 m bridge at chainage 3060 m

including other appurtenant structures.

5.45 Km 5.45 Km 55.61 55.61 NCB Yes 4/28/2008 10/30/2009 6/30/2010 4/21/2008 JV of M/S A.B.M.

Delwar Hossain and

M/S Ashraf & Sons

100% 100%

472. Raj/UZR-41.2A Improvement of Mundumala Hat to Hat bakoil (GCM)

road and construction of appurtenant structures.

6.50 Km 6.50 Km 39.30 39.30 NCB Yes 6/30/2008 1/1/2010 5/30/2010 6/2/2008 JV of M/S Md. Saidur

Rahman & Co. and

M/S Shahriar Ahmed

100% 100%

473. Bog/UZR-56.2A UZR-56.2A.1 Improvement of Simabari - Ranir hat Road 7.50 Km 15.20 Km 47.75 90.43 NCB Yes 2/16/2008 8/19/2009 8/15/2009 2/6/2008 M/S Ataur Rahman

Khan

100% 100%

UZR-56.2A.2 Improvement of Simabari - Ranir hat Road 7.70 Km 42.68 2/16/2008 8/19/2009 8/15/2009 2/6/2008 M/S Ataur Rahman

Khan

100% 100%

66

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

474. Bog/UR-9A Bihigram hat-Baldakuri road 5.26 Km 5.26 Km 14.29 14.29 NCB No 2/16/2008 8/19/2009 8/15/2009 2/4/2008 M/S Alam Construction 100% 100%

475. Bog/UR-12A Malancha hat-Jamgram UP 4.30 Km 4.30 Km 7.28 7.28 NCB No 1/27/2008 7/30/2009 7/26/2009 1/17/2008 M/S Runa Enterprise 100% 100%

476. Raj/RPM-29A Biraldaha Mazar-Noapara via Singa 13.40 Km 13.40 Km 28.04 28.04 NCB No 03/7/08 03/7/09 5/30/2010 6/17/2008 M/S Padma Associates

& Engineers Ltd.

100% 100%

477. Raj/RPM-30A Kanpara GC-Alipur RHD via Durgapur 15.48 Km 15.48 Km 17.45 17.45 NCB No 4/9/2008 4/9/2009 11/30/2009 3/30/2008 Md. Shahjahan Ali 100% 100%

67

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

478. Mun/RPM-5.2A Maintenance of Serajdikhan-Taltala GC Road 6.15 Km 6.15 Km 4.14 4.14 NCB No 6/12/2007 6/11/2008 6/11/2008 5/28/2007 M/S Punam Enterprise 100% 100%

479. Com/UR-38A Pipulia-Hazatkhola road 1.88 Km 1.88 Km 6.48 6.48 NCB No 3/31/2009 10/2/2010 3/24/2010 3/24/2009 M/S Mainamoti

Builders

100% 100%

480. Nao/RPM-51A Badalgachi GC-Paharpur-Durgadaha GC (Joypurhat) 13.70 Km 13.70 Km 24.18 24.18 NCB No 3/19/2008 3/19/2009 3/18/2009 3/12/2008 M/S Ataur Rahman

Khan

100% 100%

481. Syl/UZR-22A Improvement of Tajpur-Balagonj & Doyameer-

Dewanbazar road

15.00 Km 15.00 Km 73.29 73.29 NCB Yes 11/13/2008 5/17/2010 6/30/2010 11/9/2008 JV of M/S Intraco (BD)

Associate Ltd. & M/S.

Islam Traders (IBAL-IT

JV)

100% 100%

68

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

482. Raj/UZR-15A Improvement of Jholmolia-Mollapara Hat and Arani-

Galimpur Ferighat road

16.74 16.74 Km 18.76 18.76 NCB No 11/12/2008 5/16/2010 4/14/2010 9/22/2008 Anisur Rahman

Chowdhury

100% 100%

483. Pab/UZR-50A UZR-50A.1 Improvement of Chatmohar R&H Janata Bank-

Astomonisha GCM via Noornagar (Ch. 0+000-3+337

km) including 100 m RCC girder bridge

3.34 Km 9.89 Km 36.69 139.28 NCB Yes 3/20/2009 9/21/2010 9/25/2010 3/16/2009 Sarker Golam

Mohammad Co. Ltd.

100% 100%

UZR-50A.2 Improvement of Astomonisha GCM to Mirzapur GCM

road (Ch. 0+000-1+254 km) including 158.60 m RCC

girder bridge

1.25 Km 11.42 NCB Yes 11/1/2008 5/5/2010 5/4/2010 8/21/2008 Foundation Engineers

Ltd.

25% 25%

UZR-50A.3 Improvement of Mohela GCM-Sharatgonj GC via

Parshadanga hat road (Ch. 0+000-6+780 km)

5.30 Km 54.57 NCB Yes 11/1/2008 5/5/2010 5/4/2010 8/21/2008 Foundation Engineers

Ltd.

100% 100%

UZR-50A.4 100 m RCC girder bridge on Mohela GCM-Sharatgonj

GC via Parshadanga hat road

100.00 m 36.60 NCB Yes 3/20/2009 9/21/2010 9/25/2010 3/16/2009 Sarker Golam

Mohammad Co. Ltd.

90% 90%

484. Joy/GCM-1(A) Improvement of Puranapail Hat (Women Corner) 1 No. 1 No. 1.12 1.12 NCB No 2/25/2007 2/25/2008 2/24/2008 2/13/2007 M/S Duke Construction 100% 100%

485. Gaz/RJ-2(A) Improvement of Ramp for Chabagan Bazar Ghat 1 No. 1 No. 1.63 1.63 NCB No 3/4/2009 3/4/2010 5/20/2010 2/25/2009 M/S Associate Builders 100% 100%

486. Bog/RJ-28(A) Improvement of Ramp of Chamarpathalia Ghat 1 No. 1 No. 2.06 2.06 NCB No 3/5/2008 9/6/2009 5/28/2010 2/25/2008 M/S Masfa Enterprise 100% 100%

487. Nao/UR-25A Improvement of Bakrail-Mandain-Ustihat road 8.66 Km 8.66 Km 20.53 20.53 NCB No 2/24/2009 6/4/2010 6/15/2010 2/17/2009 Md. Aminul Haque &

BHB JV

100% 100%

488. Syl/UZR-40.2A Improvement of Zakiganj - Dubag Bazar and

construction of appurtenant structures.

3.65 Km 3.65 Km 14.57 14.57 NCB No 3/1/2009 6/4/2010 2/28/2010 2/26/2009 M/S Md. Jamil Iqbal 100% 100%

69

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

489. Bog/UZR-56.1A Improvement of Sonahata-Bagbari Road via Berebari

road

7.14 Km 7.14 Km 54.51 54.51 NCB Yes 3/18/2009 9/19/2010 5/30/2011 3/9/2009 JV of Kamal

Associates & SA

Construction (KA-SA

Consortium)

100% 100%

490. Pab/UR-98A Improvement of Manik hat-Bikramaditta via Daspara 5.30 Km 5.30 Km 19.13 19.13 NCB No 11/17/2008 5/21/2010 4/6/2010 10/30/2008 Md. Anisur Rahman 100% 100%

491. Raj/UR-16A Improvement of Darshanpara UP-Baghdhani road 9.10 Km 9.10 Km 19.69 19.69 NCB No 1/6/2009 7/10/2010 7/4/2010 12/17/2008 M/S Hossain

Enterprise

100% 100%

492. Cha/UR-83A Improvement of Kalipur-Gazra Bazar 4.43 Km 4.43 Km 13.11 13.11 NCB No 4/7/2009 4/7/2010 4/6/2010 4/1/2009 M/S Shohagi

Enterprise

100% 100%

493. Com/UZR-33.1A Improvement of Birallah R&H - Dhampti hat GC. Road

and construction of appurtenant structures.

7.77 Km 7.77 Km 6.59 6.59 NCB No 5/28/2009 5/28/2010 5/21/2010 5/21/2009 Funka Industries Ltd. 100% 100%

494. Com/UR-36A Monohargonj-Hasnabad road 8.06 Km 8.06 Km 43.59 43.59 NCB Yes 6/10/2009 6/10/2010 6/3/2010 6/3/2009 JV of Md. Abdul

Mannan and Tushar

Enterprise

100% 100%

70

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

495. Com/GCM-22A Improvement of Langnashar Bazar under Barua Upazila 1 No. 1 No. 5.17 5.17 NCB No 3/31/2009 3/31/2010 3/24/2010 3/24/2009 M/S Mainamoti

Builders

100% 100%

496. Com/UZR-58.1A Improvement of Nangalkot-Doulkhar - Boxgonj Road

and construction of appurtenant structures.

15.00 Km 15.00 Km 14.04 14.04 NCB No 5/20/2009 5/20/2010 5/20/2010 5/20/2009 M/S M. I. Construction 100% 100%

497. Mun/UR-34A Bakultala-Banglabazar road 3.72 Km 3.72 Km 3.17 3.17 NCB No Jan'09 Jan'10 0%

498. Dha/UR-29A Gangutia UP Office-Kawali bazar road 8.20 Km 8.20 Km 12.01 12.01 NCB No 2/17/2009 2/17/2010 6/5/2010 1/28/2009 JV of M/S United

Builders & Surma

Enterprise

100% 100%

499. Mun/UR-33A Masadgaon-Kahetara-Nagerhat road 2.71 Km 2.71 Km 8.91 8.91 NCB No 3/25/2009 3/25/2010 3/24/2010 3/17/2009 M/S Dulal Enterprise 100% 100%

500. Joy/UZR-66.2A Improvement of Itkhola - Jamalgonj and construction of

appurtenant structures.

6.07 Km 6.07 Km 31.45 31.45 NCB No 3/15/2009 3/15/2010 1/31/2011 3/5/2009 JV of (i) SA Traders &

(ii) Md. Nazir Hossain

100% 100%

501. Syl/UZR-40.1A Improvement of Salutikar - Shaheber Bazar - Horipur

and construction of appurtenant structures.

7.26 Km 7.26 Km 33.53 33.53 NCB No 5/23/2009 5/23/2010 5/23/2010 5/14/2009 IT-LE (JV) 100% 100%

502. Raj/UZR-41.1A Improvement of Bhawanigonj - Bandaikhara and

construction of 90 m bridge at chainage 9110 m

including other appurtenant structures.

9.28 Km 9.28 Km 15.15 15.15 NCB No 3/23/2009 3/23/2010 8/8/2010 3/11/2009 Joint Venture of (i)

M/S. Mozahar

Enterprise & (ii) M/S.

A.B Construction

100% 100%

503. Gaz/UZR-57.2A Improvement of Sreepur - Gusahinga Bazar and

construction of appurtenant structures.

6.44 Km 6.44 Km 15.10 15.10 NCB No 3/4/2009 3/4/2010 5/10/2011 2/25/2009 M/S M. L. Enterprise 100% 100%

504. Pab/UR-22A Shayamnagar GC-Raninagar UP road 6.47 Km 6.47 Km 29.29 29.29 NCB No 7/21/2009 7/21/2010 6/12/2010 7/15/2009 M/S Tushar Enterprise

& Rafiqul Islam (JV)

100% 100%

505. Com/UR-37A Pipulia-Hazatkhola-Bagmara road 1.64 Km 1.64 Km 4.36 4.36 NCB No 3/31/2009 3/31/2010 3/24/2010 3/24/2009 M/S Mainamoti

Builders

100% 100%

506. Com/UR-39A Pipulia-Bagmara via Hazatkhola road 6.55 Km 6.55 Km 11.00 11.00 NCB No 5/3/2009 5/3/2010 4/26/2010 4/26/2009 M/S AKC & MAR JV 100% 100%

507. Com/UR-40A Sanchail-Bangura road 8.47 Km 8.47 Km 23.76 23.76 NCB No 5/3/2009 5/3/2010 4/26/2010 4/26/2009 M/S AL Aksha

Construction

100% 100%

71

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

508. Bra/UR-43A (a) Akhaura (Fire Brigade)-Khalajura-Gazir bazar-

Abdullahpur (Checkpost) road

(b) Construction of 20m RCC girder bridge on Ch.

6628m of Tinlacpur R&H-Simrail via Chargach

Ballabpur road

4.16 Km 4.16 Km 20.58 20.58 NCB No 10/21/2009 10/21/2010 4/30/2011 10/14/2009 JV of M/S. Raj

Construction & M/S.

Mostafa Kamal (MRC

& MMK JV)

100% 100%

509. Mou/UR-51A Asian RHD-Uttarbag UP Office road 1.13 Km 1.13 Km 2.35 2.35 NCB No Jan'09 Jan'10 0%

510. Man/UR-65A Paila UP-Singiuri UP 1.62 Km 1.62 Km 10.03 10.03 NCB No 10/6/2009 10/6/2010 1/10/2011 9/30/2009 M/S Chowdhury

Construction

100% 100%

511. Man/UR-66A Boyra UP-Kanthapara Bazar via Lesergonj Bazar 2.21 Km 2.21 Km 7.14 7.14 NCB No 2/23/2009 2/23/2010 6/30/2010 2/16/2009 M/S Palash Enterprise 100% 100%

512. Dha/UR-99A Monu Baperir Dhal-Rajabari Bazar via Borhanibag road

(Ch. 0+400-4+650 km)

4.26 Km 4.26 Km 7.06 7.06 NCB No 9/28/2010 9/28/2011 3/21/2011 9/22/2010 M/S Bashori Enterprise 100% 100%

513. Com/GCM-21A Improvement of Jhalom Bazar under Barua Upazila 1 No. 1 No. 2.48 2.48 NCB No 3/31/2009 3/31/2010 3/24/2010 3/24/2009 M/S Pinki Enterprise 100% 100%

514. Mou/GCM-82A Improvement of Braman Bazar under Kulaura Upazila 1 No. 1 No. 1.72 1.72 NCB No 11/20/2009 11/20/2010 2/27/2010 11/1/2009 Md. Zafor Ahmed

Gilman

100% 100%

515. Syl/GCM-105A Improvement of Goala Bazar under Balaganj Upazila 1 No. 1 No. 0.00 0.00 0%

516. Syl/GCM-150A Improvement of Fenchuganj Bazar under Fenchuganj

Upazila

1 No. 1 No. 3.64 3.64 NCB No 7/26/2009 7/26/2010 7/25/2010 7/15/2009 M/S J. B. Construction 100% 100%

517. Syl/RJ-11A Improvement of Khosrupur Ghat Ghat (RJ) under

Balaganj Upazila

1 No. 1 No. 4.49 4.49 NCB No 7/16/2009 7/16/2010 12/31/2010 7/8/2009 M/S Kushiara Trading 100% 100%

518. Man/RPM-55.1A Doulatpur-Kolia hat Road. 9.30 Km 9.30 Km 28.90 28.90 NCB No 6/23/2009 6/23/2010 10/31/2011 6/17/2009 M/S Good Luck

Trading Corporation

100% 100%

519. Mun/RPM-57.5A Dhaka Mawa RHD-Kuchiamara-Shekernagar GC via

Sayedpur-Chittrakot UP road

6.05 Km 6.05 Km 7.05 7.05 NCB No 5/10/2009 5/10/2010 1/31/2011 4/27/2009 M/S Chowdhury

Construction

100% 100%

72

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

520. Com/RPM-59.1A Upazila HQ (Nabagram)-Munshirhat-Kadir bazar-

Kashinagarbazar road

6.71 Km 6.71 Km 15.73 15.73 NCB No 1/18/2009 1/18/2010 1/11/2010 1/11/2009 M/S Majumdar Traders 100% 100%

521. Com/RPM-19.2A Maintenance of Laksam-Monohargonj Road 11.99 Km 11.99 Km 11.40 11.40 NCB No 9/1/2009 9/1/2010 9/1/2010 9/1/2009 M/S Meghna Traders 100% 100%

522. Pab/UR-79A Handial UP Office-Shamaj bazar 6.00 Km 6.00 Km 16.60 16.60 NCB No 9/28/2010 11/27/2011 6/30/2011 9/21/2010 M/S Tusher Enterprise

& Mahbabul Enterprise

(JV)

100% 100%

523. Joy/UZR-35.2A Improvement of Kalai - Moslemgonj Road and

construction of appurtenant structures.

8.07 Km 8.07 Km 14.17 14.17 NCB No 1/7/2010 3/8/2011 1/7/2011 12/29/2009 JV of JE & MSH 100% 100%

524. Gaz/UZR-57.3A Improvement of Baliadi R&H to Chandabaha and

construction of appurtenant structures.

3.40 Km 3.40 Km 24.82 24.82 NCB No 3/25/2010 5/24/2011 3/17/2011 3/18/2010 M/S Nipa Enterprise 100% 100%

525. Mun/UZR-60.1A Improvement of Kanakshar - Nagerhat Bazar and

construction of appurtenant structures.

3.12 Km 3.12 Km 20.99 20.99 NCB No 3/27/2010 5/26/2011 12/31/2010 3/16/2010 M/S Shahil Enterprise 100% 100%

526. Com/RPM-59.3A B.Para-Dulalpur GC road 4.54 Km 4.54 Km 10.30 10.30 NCB No 9/18/2010 11/17/2011 2/3/2011 3/29/2010 M/S Azharul Monir 100% 100%

527. Pab/UZR-50A.2A Improvement of Astomonisha GCM to Mirzapur GCM

road (Ch. 0+000-1+254 km) including 158.60 m RCC

girder bridge

1.25 Km 1.25 Km 50.55 50.55 NCB Yes Oct'09 Dec'10

73

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

528. Mou/UR-52A Bauli-Nijbahadurpur UP Office via Behaidohor Road. 8.85 Km 8.85 Km 19.68 19.68 NCB No 7/7/2010 9/5/2011 7/1/2011 6/27/2010 Md. Shueb Ahmed 100% 100%

529. Syl/GCM-106A Improvement of Balaganj Bazar under Balaganj Upazila 1 No. 1 No. 0.00 0.00

530. Sun/RPM-50.4A Keshabpur-Rasulgonj-Tuker Bazar-Panaullah Bazar

Road

14.95 Km 14.95 Km 0.00

531. Sun/RJ-9A Improvement of Joynagar Hat Ghat (RJ) under

Sunamganj-S Upazila

1 No. 1 No. 0.00 0.00

532. Com/RPM-87 Maintenance of Gunabati-Akadia Road (Part-A: Safua

NHW-Nalgar Bazar Chowmouhony Modina Bazar via

Sreepur UP office (Padua) Road (Ch. 0+000-4+500km)

4.50 Km 4.50 Km 33.39 33.39 NCB No 11/1/2009 11/1/2010 10/26/2010 10/26/2009 M/S Mazumder

Traders

100% 100%

533. Com/RPM-88 Maintenance of Gunabati-Akadia Road (Part-A: Safua

NHW-Nalgar Bazar Chowmouhony Modina Bazar via

Sreepur UP office (Padua) Road (Ch. 4+500-9+396km)

4.90 Km 4.90 Km 32.48 32.48 NCB No 11/1/2009 11/1/2010 10/26/2010 10/26/2009 Md. Abul Hossem 100% 100%

534. Com/RPM-89 Maintenance of Barura Bazar-Ebdarpur road via

Rammohon Bazar road (Nimshar College-Chitoshi

Railway Station via Kedarpur bazar Barura ourashava-

Poyalgacha College Natua Chandpur road) (Ch. 0+000-

4+920km)

4.92 Km 4.92 Km 17.26 17.26 NCB No 11/30/2009 11/30/2010 11/23/2010 11/23/2009 M/S R. Ta. Enterprise 100% 100%

535. Com/RPM-90 Maintenance of Barura Bazar-Ebdarpur road via

Rammohon Bazar road (Nimshar College-Chitoshi

Railway Station via Kedarpur bazar Barura ourashava-

Poyalgacha College Natua Chandpur road) (Ch. 4+920-

6+290km)

1.37 Km 1.37 Km 7.08 7.08 NCB No 12/2/2009 12/2/2010 11/26/2010 11/26/2009 Mir Shariful Alam 100% 100%

536. Com/RPM-91 Maintenance of Barura Bazar-Ebdarpur road via

Rammohon Bazar road (Horipur Bazar-Aganagar-

Kalirbazar GC road) (Ch. 0+000-3+750km)

3.75 Km 3.75 Km 20.72 20.72 NCB No 11/26/2009 11/26/2010 11/22/2010 11/22/2009 Funka Industries Ltd. 100% 100%

537. Com/RPM-92 Maintenance of Fakirbazar-Salda river road

(Kalekharpara-Janata bazar-Golabari road) (Ch. 0+000-

6+000km)

6.00 Km 6.00 Km 10.57 10.57 NCB No 4/4/2010 4/4/2011 9/28/2010 3/28/2010 M/S. Rodela

International

100% 100%

538. Com/RPM-93 Maintenance of Nangalkot-Tuguria road (Ch. 5+860-

10+760km)

4.90 Km 4.90 Km 17.06 17.06 NCB No 3/15/2010 3/15/2011 3/6/2011 3/6/2010 M/S R. Ta. Enterprise 100% 100%

74

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

539. Pab/GCM-126A Improvement of Chaikola Hat under Chatmohor Upazila 1 No. 1 No. 3.54 3.54 NCB No 3/18/2010 3/18/2011 11/2/2010 3/11/2010 Md. Afzal Hossain 100% 100%

540. Com/RPM-94 Maintenance of Madhaiya-Dollai Nowabpur-

Rahimanagar road (Ch. 16+500-21+200km)

4.70 Km 4.70 Km 21.92 21.92 NCB No 3/15/2010 3/15/2011 3/6/2011 3/6/2010 M/S Mainamoti

Builders

100% 100%

541. Nao/RPM-95 Maintenance of Raninagar-Abadpukur GC road (Ch.

0+000-7+400km)

7.40 Km 7.40 Km 13.75 13.75 NCB No 4/14/2010 4/14/2011 5/31/2011 3/23/2010 Ethen Enterprise 100% 100%

542. Nao/RPM-96 (a) Maintenance of Raninagar-Abadpukur GC road (Ch.

7+400-14+000 km) (b) Maintenance of Kashiabari GC-

Kaliganj GC (Kaliganj bridge approach inclusive) road

(Ch. 13+640-13+945 km)

6.91 Km 6.91 Km 13.16 13.16 NCB No 4/14/2010 4/14/2011 4/13/2011 3/29/2010 M/S Hossain

Enterprise

100% 100%

543. Bog/RPM-97 Maintenance of Kahaloo UP office-Eruil Bazar (via

Aghorsha) road (Ch. 1+773-3+935 km and 4+935-

5+900 km)

3.13 Km 3.13 Km 13.26 13.26 NCB No 5/13/2010 5/13/2011 5/12/2011 5/4/2010 Mir Habibul Alam 100% 100%

544. Pab/RPM-98 Maintenance of Bheramara-Dhanuaghata road (Ch.

0+000-3+000 Km)

3.00 Km 3.00 Km 28.74 28.74 NCB No 6/23/2010 6/23/2011 6/30/2011 6/16/2010 Md. Shajahan Ali 100% 100%

545. Pab/RPM-99 Maintenance of Bheramara-Dhanuaghata road (Ch.

3+000-4+900 Km)

4.90 Km 4.90 Km 27.36 27.36 NCB No 8/8/2010 8/8/2011 5/31/2011 8/1/2010 M/S Tusher Enterprise

& Rafiqul Islam (JV)

100% 100%

546. Mou/GCM-85A Improvement of Munshibazar under Rajnagar Upazila 1 No. 1 No. 4.50 4.50 NCB No Jul'10 Jul'11 0%

547. Hab/UZR-51A Improvement of Baniachang - Azmirigonj Road via

Shibpasha Road (Ch. 1+900-3+570 km)

1.67 Km 1.67 Km 29.88 29.88 NCB No 7/6/2010 7/6/2011 11/15/2011 5/26/2010 M/S. R.R Enterprise

(JV)

100% 100%

548. Hab/UZR-51B Improvement of Baniachang - Azmirigonj Road via

Shibpasha Road (Ch. 3+570-6+000 km)

2.43 Km 2.43 Km 35.74 35.74 NCB No 8/29/2010 8/29/2011 12/15/2011 8/19/2010 M/S. M.R.A (JV) 100% 100%

549. Hab/UZR-51C Improvement of Baniachang - Azmirigonj Road via

Shibpasha Road (Ch. 6+000-8+500 km)

2.50 Km 2.50 Km 37.11 37.11 NCB No 7/6/2010 7/6/2011 11/15/2011 5/26/2010 M/S. R.R Enterprise

(JV)

100% 100%

550. Hab/UZR-51D Improvement of Baniachang - Azmirigonj Road via

Shibpasha Road (Ch. 8+500-10+800 km)

2.30 Km 2.30 Km 37.08 37.08 NCB No 8/29/2010 8/29/2011 12/15/2011 8/19/2010 M/S M.R.A (JV) 100% 100%

551. Dha/RPM-100 Maintenance of Zirani Bazar - Shimulia Bazar Road

(CH: 580-6023m)

5.44 Km 10.14 Km 23.07 23.07 NCB No 5/23/2010 5/23/2011 12/31/2011 5/17/2010 Gazi Enterprise-Aunica

International (JV)

100% 100%

Maintenance of Dhaka Aricha Highway to Ashulia GC

Road (CH:1000-4300m)

3.30 Km 0.00

Maintenance of Joupura Bazar - Sombag UP Office

Road (CH:00-1400m)

1.40 Km 0.00

75

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

552. Nara/RPM-101 Maintenance of Araihazar-Purinda Road (CH:5500-

8500m)

3.00 Km 19.83 Km 23.17 23.17 NCB No 7/5/2010 7/5/2011 7/4/2011 6/28/2010 M/S S. S. Corporation 100% 100%

Maintenance of Baliapara Bazar - Eidbordi Road

(CH:00-4130m)

4.13 Km 0.00

Maintenance of Uchitpura Gc-Gopaldi Road via

Ramchandradi Ghordi (CH:00-5000m)

5.00 Km 0.00

Maintenance of Porshi GC-Rupgonj-Kayetpara-Demra

RHD Road (CH:00-7720m)

7.70 Km 0.00

553. Mun/RPM-102 Muktarpur RHD-Rekabi Bazar road (CH:00-1800m) 1.80 Km 7.90 Km 32.63 32.63 NCB No 8/1/2010 8/1/2011 12/20/2011 7/25/2010 M/S Niaz Traders-The

Sages (JV)

100% 100%

Baroikhali GC-Gobindapur GC (Sreenagar Portion)

(CH:00-1460m)

1.46 Km 0.00

Sreenagar-Baraikhali GC Road (CH:00-1000m) 1.00 Km 0.00

Sreenagar GC-Satvita Hat (Dohar) via Gadighat bazar,

Chatrabough Bazar (Sreenagar Portion) road (CH:460-

4100m)

3.64 Km 0.00

554. Man/RPM-103 Maintenance of Uthali-Jafargonj Road (CH:2850-

6800m)

3.95 Km 6.02 Km 16.01 16.01 NCB No 7/5/2010 7/5/2011 6/15/2011 6/28/2010 JV of M/S. Debesh

Traders & Rata

Construction

100% 100%

Maintenance of Ghior GC-Kolia GC via Banglabazar

Road (CH:00-2070m)

2.07 Km 0.00

555. Nar/RPM-104 Maintenance of Bhelanagar Bazar (Jelkhanar Mour)-

Rajadigram Sarak via Titas Gas Office (CH:00-2100m)

2.10 Km 8.68 Km 10.57 10.57 NCB No 5/31/2010 5/31/2011 8/30/2011 5/25/2010 Combined

Development

Corporation

100% 100%

Maintenance of Sreerampur GC to Gokulnagar bus

stand Road (CH:00-0975, 1000-2975, 4143-8650m)

6.58 Km 0.00

556. Gaz/RPM-105 Maintenance of Kapasia GC-Kaligong GC Road (CH:00-

9300m)

9.30 Km 9.30 Km 34.29 34.29 NCB No 6/20/2010 6/20/2011 6/9/2011 6/13/2010 M/S S. A. Engineering-

M. M. Builders (JV)

100% 100%

557. Raj/RPM-106 Maintenance of Godagari-Kakonhat GC Road (CH:00-

7000m)

7.00 Km 17.60 Km 33.22 33.22 NCB No 6/7/2010 6/7/2011 5/31/2011 5/31/2010 M/S Shafique Traders 100% 100%

Maintenance of Keshore Hat-Mochmoil Hat Road

(CH:00-5000m)

5.00 Km 0.00

Maintenance of Tanore-Amnura via Mondumala Hat

Road (CH:11500-17100m)

5.60 Km 0.00

76

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

558. Nat/RPM-107 Maintenance of Tebaria GC-Bagatipara Upazila HQ

Road (CH:00-7450m)

7.45 Km 15.68 Km 15.35 15.35 NCB No 6/13/2010 6/13/2011 6/12/2011 6/7/2010 M/S. Das Traders 100% 100%

Maintenance of Bonbeldharia RHD-Taherpur GC via

Mominpur Hat Road (CH:00-3500m)

3.50 Km 0.00

Maintenance of Jamtoil-Bamihal-Ranir Hat Road (CH:00-

4730m)

4.73 Km 0.00

559. Nao/RPM-108 Maintenance of Naogaon RHD-Shoilgachi GC Road at

Link Road from Calkpran GPS - Arzi Naogaon Road

(CH:00-2200m)

2.20 Km 12.15 Km 11.07 11.07 NCB No 6/6/2010 6/6/2011 6/5/2011 5/30/2010 M/S Jewel Electronics 100% 100%

Maintenance of Nazirpur Natunhat GC (Girls School)-

Gaganpur GC Road (CH:3150-6400m)

3.25 Km 0.00

Maintenance of Kola GC-Kirtipur GC (Badalgach Part)

(CH: 00-2500m)

2.50 Km 0.00

Maintenance of Matajee GC-Kalushahar RHD Mour

Road (CH: 4400-8600m)

4.20 Km 0.00

560. Bog/RPM-109 a) Maintenance of Bogra-Taroni Hat Road (Sadar Part)

(CH: 2200-5600m)

3.40 Km 14.75 Km 28.69 28.69 NCB Yes 7/25/2010 7/25/2011 7/24/2011 7/15/2010 KA-SA Consortium

(JV)

100% 100%

b) Maintenance of Bogra-Taroni Hat Road (Gabtoli Part)

(CH: 5600-16950m)

11.35 Km 0.00

561. Joy/RPM-110 Maintenance of R&H (Jamalgonj Charmatha)-

Rukindipur GC (Jamalgonj Hat) (CH:00-2100m)

2.10 Km 11.10 Km 15.65 15.65 NCB No 5/24/2010 5/24/2011 5/28/2011 5/24/2010 Ram Babu 100% 100%

Maintenance of Kichok-Moslemgonj Road (CH:00-

9000m)

9.00 Km 0.00

562. Pab/RPM-111 (a) Maintenance of Chatmohar UZ HQ (High School

More) -Mohela GC via Bri-Guakhara road (Ch. 0+000-

8+200 Km)

8.20 Km 14.93 Km 14.65 14.65 NCB No 1/27/2011 1/27/2012 6/25/2011 1/20/2011 M/S Tusher Enterprise 100% 100%

(b) Maintenance of Mulgram RHD-Dashuria GC via D.B.

gram UP Office road (Ch. 0+000-6+725 Km)

6.73 Km 0.00

563. Sir/RPM-112 Maintenance of Belkuchi UZ HQ-Balarampur GC via

Bangabari UP Chowbari Bazar Road (CH: 3000-5710m)

2.71 Km 9.26 Km 13.54 13.54 NCB No 6/10/2010 6/10/2011 6/9/2011 5/26/2010 IA-NI-AS (JV) 100% 100%

Maintenance of Panchakushi-Shahajanpur Road

(CH:00-6550m)

6.55 Km 0.00

564. Com/RPM-113 Maintenance of Dayapur-Chowara-Kanashtola Road

(CH:2200-2800m & 4800-7000m)

2.80 Km 7.10 Km 14.99 14.99 NCB No 6/15/2010 6/15/2011 6/14/2011 6/15/2010 M/S Ananto Enterprise 100% 100%

77

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

Maintenance of Dakkhin Shilmuri UP Office-Bataichari

Bazar Road (CH:00-4300m)

4.30 Km 0.00

565. Cha/RPM-115 Maintenance of Hanarchar UP-Chandra GC Road

(CH:00-3630m)

3.63 Km 10.93 Km 15.42 15.42 NCB No 5/31/2010 5/31/2011 5/30/2011 5/26/2010 Mizanur Rahaman

Liton

100% 100%

Maintenance of Kallyanpur UP (Baburhat GC)-UZ HQ

(Bishnadi) Road via Kashim Bazar (CH:00-6250m)

6.25 Km 0.00

Maintenance of Sandra R&H-Palishara Bazar Road

(CH:00-1046m)

1.05 Km 0.00

566. Bra/RPM-116 Maintenance of Salimabad UP (Asrafbad)-Rupasdi

bazar Road via Hoglakanda (Towards Rupasdi

Hospital) road (CH:00-2200m)

2.20 Km 9.20 Km 4.26 14.27 NCB No Jul'10 Jul'11

Maintenance of Bitgar Hat-B. Baria RHD Road via

Kurighar Hat (CH:00-6000m)

6.00 Km 8.26

Maintenance of Talsahar Bazar-Bahadurpur Bazar

Road via Talshahar UP, Kamaura Road (CH:00-1000m)

1.00 Km 1.75

567. Syl/RPM-117 Maintenance of RHD (Shalutikar)-Shaheber Bazar-

Haripur Road (Sadar Part) (CH:00-6400m)

6.40 Km 14.02 Km 12.13 12.13 NCB No 5/16/2010 5/16/2011 11/15/2011 5/16/2010 Sharif Uddin Ahmed 100% 100%

Maintenance of Lakhanbondh UP-Fulshaind-

Porokayestha bazar Road (CH:00-3620m)

3.62 Km 0.00

Maintenance of Hetimgonj-Chandarpur-Beanibazar

Road (CH:00-4000m)

4.00 Km 0.00

568. Sun/RPM-118 Maintenance of Jagannathpur-Biswanath Road (CH:00-

13330m)

13.33 Km 13.33 Km 15.62 15.62 NCB No 5/27/2010 5/27/2011 5/26/2011 5/19/2010 JV of (1) Mamun

Construction, (2) Basu

Nirman Sangastha &

(3) Md. Abul Kalam

100% 100%

569. Mou/RPM-119 Maintenance of Saifur Rahman Circular Road

(Sadarpart) (CH:00-5000m)

5.00 Km 30.42 Km 13.89 13.89 NCB No 6/10/2010 6/10/2011 6/3/2011 5/25/2010 Md. Muhibur Rahman 100% 100%

Maintenance of Moulvibazar-Kulaura RHD (Chadnighat)-

Sylhet-Dhaka RHD(Kamalpur) Road (CH:00-10200m)

10.20 Km 0.00

Maintenance of Baharmardan-Office bazar-

Mokambazar Road (CH:00-8500m)

8.50 Km 0.00

78

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

Maintenance of Dewan dighi (Tengra)-Paulpur-

Shamsernagar road (CH:4000-10720m)

6.72 Km 0.00

570. Gaz/RPM-121 Bormi-Joina via Kawraid Road (CH:8000-13000m) 5.00 Km 5.00 Km 21.92 21.92 NCB No 8/12/2010 8/12/2011 12/15/2011 8/2/2010 M/S Jaman

Construction & Coronet

Builders Ltd.

Consortium

100% 100%

571. Dha/UZR-313A Improvement of Dhaka Aricha highway-Kalatipara GC

via Vakurta bazar road (Ch. 00-4000 m)

4.00 Km 4.00 Km 33.34 33.34 NCB No 5/22/2010 5/22/2011 10/13/2011 5/16/2010 M/S. Shakil & Sabbir

Brothers

100% 100%

572. Dha/UZR-313B Improvement of Dhaka Aricha highway-Kalatipara GC

via Vakurta bazar road (Ch. 4000-8130 m)

4.13 Km 4.13 Km 25.30 25.30 NCB No 6/8/2010 6/8/2011 12/31/2011 6/2/2010 M/S. Bashori Trader’s

& M/S. Rajib

Construction (BT &

RC-JV)

100% 100%

573. Dha/UZR-313C Improvement of Dhaka Aricha RHD-Mugrakanda-

M.pur.city prot. Embank. Road (Ch. 00-3600 m)

3.60 Km 3.60 Km 34.00 34.00 NCB Yes 7/28/2010 7/28/2011 12/25/2011 7/22/2010 Pranto International &

Bithi Enterprise (JV)

100% 100%

574. Dha/UZR-313D Improvement of Dhaka Aricha RHD-Mugrakanda-

M.pur.city prot. Embank. Road (Ch. 3600-5140 m)

1.50 Km 1.50 Km 35.75 35.75 NCB No 7/24/2010 7/24/2011 2/28/2012 7/19/2010 M/S Babul Traders 100% 100%

575. Dha/UZR-313E Improvement of Dhaka Aricha RHD-Mugrakanda-M.pur

city port Embank. Road (Ch. 5140-6135 m)

2.24 Km 2.24 Km 8.78 8.78 NCB No 8/10/2010 8/10/2011 12/31/2011 8/4/2010 M/S Bashori Trader’s &

M/S Rajib Construction

(BT & RC JV)

100% 100%

576. Bra/UR-101 Improvement of (a) Salimabad UP (Asrafbad)-Rupusdi

Bazar road-via-Hogla Kanda (Towards Rupasdi

Hospital) (Ch. 0+000-2+200 km), (b) Sonarampur UP-

Marichakandi GC Road (Ch. 0+000-0+500 km) & (c)

Landing ram at (1) Imamnagar Jame Mosque, (2)

Bakhanagar Dakhinpara riiver ghat, (3) Dorikandi near

vorerbazar Mosque, (4) Hijlakandi Kala Mia's

houseghat, (5) Darivelanagar rivr ghat, (6) Salimabad

Shahebnagar Mohammad Dano bari ghat, (7)

Charshibpur Bhuyea bari ghat, (8) Domrakandi Jame

Mosque ghat, (9) Bancharampur Mollah bari river ghat,

(10) Ropasdi Madhapara river ghat beside R&H.

2.70 Km 2.70 Km 6.97 6.97 NCB No 8/11/2010 8/11/2011 8/10/2011 7/27/2010 M/S. Shaki Enterprise 100% 100%

79

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

577. Bra/RPM-125 Maintenance of Nasirnagar-Chaiarkuri GC–Madabpur

Road (Ch. 00-4100 m)

4.10 Km 4.10 Km 17.00 17.00 NCB No 8/11/2010 8/11/2011 8/10/2011 7/25/2010 Intraco (BD)

Associates Ltd.

100% 100%

578. Cha/RPM-122 Maintenance of (a) Waruk Bazar (Sursail) GC-

Rahimanagar GC via Guilpura Road (Ch. 0+500-4+686

km) (b) Chandpur-Comilla R&H-Kumrardugi Jaforbari-

Ketua Joi Shaheb Bari Road (Ch. 0+000-1+525km)

5.72 Km 5.72 Km 11.37 11.37 NCB No 7/4/2010 7/4/2011 7/4/2011 7/4/2010 Mohammad Ali Zinnah 100% 100%

579. Com/RPM-114 Maintenance of Amjader Bazar - Zagjur via Kankapaith

Bazar UP office (CH:00-5700m)

5.70 Km 5.70 Km 22.84 22.84 NCB No 6/15/2010 6/15/2011 11/30/2011 6/15/2010 M/S Biplob Syndicate 100% 100%

580. Com/RPM-123 Maintenance of Amjader Bazar - Zagjur via Kankapaith

Bazar UP office (CH:00-5700m)

8.08 Km 8.08 Km 15.33 15.33 NCB No 6/15/2010 6/15/2011 11/15/2011 6/15/2010 M/S Abul Hasem 100% 100%

581. Bra/RPM-124 Maintenance of Tinlacpur of R&H-Shimrail G.C.via

Chargas Bazar Road (Ch. 0+000-6+600km) under

Nasirnagar upaizla.

6.60 Km 6.60 Km 16.04 16.04 NCB No 9/12/2010 8/18/2011 9/4/2011 9/5/2010 M/S. TE-NI Brothers 100% 100%

582. Com/RPM-128 (a) Kabila-Kalir Bazar Road (Ch. 3100-5400m), (b) Kalir

Bazar (Fanua)-Ozirpur-Nazir Bazar Road (Ch. 00-

5400m) & (c) Kalir Bazar-Galakatha-Haripur Road (Ch.

00-1350m).

9.05 Km 9.05 Km 19.83 19.83 NCB No 8/24/2010 7/30/2011 8/30/2011 8/24/2010 M/S Ananto Enterprise 100% 100%

583. Com/UR-102 Improvement of Kachiatoly Bhuiyan Bari-Banashoa

Bridge via Alekharchar Road (Ch. 2500-4800m).

2.30 Km 2.30 Km 10.75 10.75 NCB No 10/1/2010 6/8/2011 11/1/2011 8/12/2010 P.E Consortium 100% 100%

584. Com/RPM-134 Maintenance of Nangalkot-Bangadda Road (Ch. 0+000-

8+600 km)

8.60 Km 8.60 Km 21.41 21.41 NCB No 12/3/2010 8/10/2011 5/20/2011 11/28/2010 M/S. Bhuiyan & Haque

Construction Co.

100% 100%

585. Com/RPM-139 Maintenance of (a) EPZ-Beltoli-Hossainpur-Hazirkamar-

Bangamura (Start from Naogaon Chowmohani) Road

(Ch. 0+000-7+000 km), (b) Bissa road-Vatpara-

Goalgaon-Narvoypur (Mathurapur Bop) Road (Ch.

0+000-3+250 km) & (c) Bijoypur-Chamber Bazar-

Khashkamar Road (Ch. 0+000-3+000 km).

13.25 Km 13.25 Km 23.62 23.62 NCB No 12/19/2010 8/26/2011 6/30/2011 12/13/2010 M/S Zaman Traders 100% 100%

80

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

586. Mou/RPM-135 Maintenance of Kamalgonj-Adampur Road (Ch. 0+000-

8+000 km)

8.00 Km 8.00 Km 31.78 31.78 NCB No 9/12/2010 8/18/2011 9/5/2011 8/24/2010 JV of (i) Md. Tufayel

Ahmed, (ii) Md. Saiful

Islam & (iii) M.

Musaddik Ahmed

Manik (F.T.S-JV)

100% 100%

587. Com/UZR-329 Improvement of Homna-Meghna HQ upto Ferryghat

Road (Ch. 2+548-9+970 km)

7.42 Km 7.42 Km 83.46 83.46 NCB Yes 11/10/2010 7/18/2011 12/31/2011 11/10/2010 Rana Builders (Pvt.)

Ltd. & M/S Ananta

Enterprise (JV)

100% 100%

588. Dha/RPM-136 Maintenance of Dhaka-Aricha (R&H)-20 Mile-Jirabo

bazar via Earpur UP road (Ch. 0+000-5+550 Km)

5.55 Km 5.55 Km 7.15 7.15 NCB No 9/22/2010 8/28/2011 5/30/2011 9/16/2010 M/S Pronto

International

100% 100%

589. Man/RPM-127 Maintenance of Singair GC to Baria GC Road (Ch.

0+000-7+500 km)

7.50 Km 7.50 Km 12.52 12.52 NCB No 12/5/2010 8/12/2011 5/31/2011 11/28/2010 JV of M/S Debesh

Traders & M/S S.R.

Enterprise

100% 100%

590. Sun/RPM-138 Maintenance of Biswambarpur-Shaktiarkhola Road (Ch.

4+900-5+330 km)

0.43 Km 0.43 Km 11.45 11.45 NCB No 9/27/2010 9/2/2011 7/21/2011 9/20/2010 Md. Abul Kalam 100% 100%

591. Sun/UZR-314.2A Improvement of Dharmapasha-Joysree Road

(Chainage : 6+150-10+950 km)

4.80 Km 4.80 Km 132.36 132.36 NCB Yes 12/15/2010 8/22/2011 11/30/2011 12/8/2010 M/S Manjurul Ahsan &

Co.

100% 100%

592. Man/UZR-24B Improvement of Busta (Joymontop)- Maniknagar road

(Ch. 00-3886m)

3.88 Km 3.88 Km 37.05 37.05 NCB Yes 11/18/2010 7/26/2011 5/30/2011 11/11/2010 JV of Bikolpo Trade

International (BTI) and

Nirman Prokowshali

(NP)

100% 100%

593. Com/RPM-59.5A Laksam-Mudaffargonj road 10.35 Km 10.35 Km 30.17 30.17 NCB No 11/1/2010 7/9/2011 8/28/2011 8/22/2010 M/S Abu Bokkar

Siddique

100% 100%

594. Cha/UZR-20.1C Improvement of Sepaikandi-Kalir Bazar-Bashurchar-

Baushia Ferryghat-Dhaka : Ctg RHD Road (Ch. 13+000-

16+900km)

3.90 Km 3.90 Km 32.37 32.37 NCB No 12/20/2010 8/27/2011 6/10/2011 12/14/2010 M/S Niaz Traders 100% 100%

595. Cha/UZR-20.1D Improvement of Sepaikandi-Kalir Bazar-Bashurchar-

Baushia Ferryghat-Dhaka : Ctg RHD Road (Ch. 16+900-

19+385km)

2.49 Km 2.49 Km 27.94 27.94 NCB No 1/12/2011 9/19/2011 6/10/2011 1/5/2011 JV of AB-SE 100% 100%

596. Man/UZR-24A (a) Improvement of Singair-Charigram road

(b) Improvement of Busta (Joymontop)- Maniknagar

road

15.20 Km 15.20 Km 19.81 19.81 NCB No 11/11/2010 7/19/2011 5/30/2011 11/8/2010 M/S Orient Trading &

Builders Ltd

100% 100%

81

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

597. Nara/RPM-145 Maintenance of (a) Pakundia-Baliapara-Monohardi-

Binarchar RHD Road (Ch. 00-4850m), (b) Mullarchar

R&H-Gopaldi GC Road (Ch. 00-4300m) & (c) Uchitpura

GC-Gopaldi Road (Ch. 00-10950m).

20.10 Km 20.10 Km 21.16 21.16 NCB No 11/10/2010 7/18/2011 4/30/2011 11/3/2010 M/S S. S. Corporation 100% 100%

598. Com/RPM-141 Maintenance of (a) Chitoshy Railway Station-Barura via

Janora Road (Ch. 0+000-4+700 km) & (b) Barura-

Laxmipur-Beky Road (Ch. 0+000-3+750 km)

8.45 Km 8.45 Km 23.37 23.37 NCB No 10/20/2010 6/27/2011 8/11/2011 10/13/2010 M/S Zaman Traders 100% 100%

599. Com/RPM-144 Maintenance of Chitoshi R&H (Nurul Amin College)-

Jhalom (N) UP-Pomgao Jhalom (S) UP Office Road

(Ch. 0+0-6+650 km)

6.65 Km 6.65 Km 18.50 18.50 NCB No 10/21/2010 6/28/2011 6/30/2011 10/21/2010 M/S R-TA Enterprise 100% 100%

600. Com/UR-103 Improvement of Subupur UP Office Kadoir Bazar-

Potkora-Nowapara-Rajapur-Chownuhuni Bazar Road

(Ch. 3+600-6+740 km).

3.14 Km 3.14 Km 13.63 13.63 NCB No 10/12/2010 6/19/2011 8/11/2011 10/5/2010 M/S Mazumder

Traders

100% 100%

601. Com/UR-104 Improvement of (a) Joypukuria-Sholapukuria-Dewatoli

Road (Ch. 0+000-3+000 km) & (b) Kairagaon-Agrogram

Road (Ch. 0+000-2+500 km)

5.50 Km 5.50 Km 24.88 24.88 NCB No 10/20/2010 6/27/2011 8/11/2011 10/13/2010 M/S Hoque Enterprise 100% 100%

602. Nar/RPM-143 Maintenance of Khanepur Bazar-Charsindur UP road

via Fouji Jute Mill road (Ch. 0+000-1+050 km)

1.05 Km 1.05 Km 7.42 7.42 NCB No 10/3/2010 9/8/2011 7/29/2011 9/19/2010 M/S Udayan Enterprise 100% 100%

603. Cha/RPM-140 Maintenance of Sengarchar-Eklaspur Road (Ch. 0+000-

8+600 km)

8.60 Km 8.60 Km 12.61 12.61 NCB No 10/13/2010 9/18/2011 10/13/2011 10/6/2010 M/S Active

International

100% 100%

604. Mun/UZR-60.2A Improvement of Khanbari-Goalimandra road (remaining

portion)

2.52 Km 2.52 Km 29.08 29.08 NCB No 11/29/2010 8/6/2011 6/30/2011 11/21/2010 M/S Shahil Enterprise 100% 100%

605. Mun/RPM-130 Maintenance & Road Safety of Betka-Tongibari Road

(Ch. 0+000-3+850 km)

3.85 Km 3.85 Km 5.51 5.51 NCB No 9/29/2010 9/29/2011 5/31/2011 9/23/2010 M/S Azad and Brothers-

Angira Electronics JV

100% 100%

606. Nat/RPM-147 Maintenance of Bonbelghoria RHD to Taherpur GC via

Mominpur Hat road (Ch. 3+500-10+250 Km)

6.75 Km 6.75 Km 10.71 10.71 NCB No 1/1/2011 9/8/2011 4/30/2011 12/26/2010 Md. Anisur Rahman

Chowdhury

100% 100%

607. Pab/RPM-132 Maintenance & R.S. of Chatmohar-Jonail Road (Ch.

0+000-9+500 Km).

9.50 Km 9.50 Km 6.46 6.46 NCB No 12/5/2010 8/12/2011 6/30/2011 11/21/2010 M/S Azad & Brothers-

Anzira Electronics (JV)

100% 100%

82

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

608. Sir/RPM-148 Maintenance of Kamarkhand R&H Nandinamadhu

Amtola-Chala Bazar Road (Ch. 0+000-3+000 Km)

3.00 Km 5.70 Km 15.30 15.30 NCB No 12/14/2010 8/21/2011 5/30/2011 11/29/2010 M/S Sandhi Traders 100% 100%

Maintenance of Belkuchi R&H-Ambaria Bus Stand-

Aguria Bazar Road (0+000-2+700 Km) and

Construction of 4x4.5x5.0m RCC Box culvert at Ch.

0+000-0+150 km

2.70 Km 0.00

609. Pab/UR-105 Improvement of Handial UP Office-Naogaon GC via

Hashupur Baro Belayi road (Ch. 0+000-1+000km) and

construction of a 3-vent 5.0mx5.0m RCC Box Culvert at

Ch. 1+300 on Handial UP Office-Shamaji Bazar road

1.00 Km 1.00 Km 7.63 7.63 NCB No 1/5/2011 1/5/2012 5/31/2011 1/2/2011 M/S Khandaker Shahin

Ahamed

100% 100%

610. Sun/UZR-21.1A Improvement of Sunamgonj - Chhatak Road via

Dowarabazar Road (Ch. 0+000-6+500 km)

6.50 Km 6.50 Km 39.42 39.42 NCB Yes 12/20/2010 8/27/2011 12/15/2011 12/14/2010 JV of Nurul Islam, M/S

Mubarok Hossain &

Humayon Kabir

100% 100%

611. Sun/UZR-21.1B Improvement of Sunamgonj - Chhatak Road via

Dowarabazar Road (Ch. 6+500-13+500 km)

7.00 Km 7.00 Km 61.81 61.81 NCB Yes 12/15/2010 8/22/2011 11/30/2011 12/8/2010 M/S Md. Matiar

Rahman

100% 100%

612. Sun/UZR-21.1C Improvement of Sunamgonj - Chhatak Road via

Dowarabazar Road (Ch. 13+500-17+500 km)

4.00 Km 4.00 Km 77.13 77.13 NCB Yes 12/29/2010 9/5/2011 12/15/2011 12/22/2010 JV of M/S Mahbub

Enterprise, M/S Prity

Enterprise & M/S

Hasan Enterprise

100% 100%

613. Sun/UZR-21.1D Improvement of Sunamgonj - Chhatak Road via

Dowarabazar Road (Ch. 17+500-27+200 km)

9.70 Km 9.70 Km 65.13 65.13 NCB Yes 12/15/2010 8/22/2011 11/30/2011 12/8/2010 M/S Md. Matiar

Rahman

100% 100%

614. Sun/UZR-21.2A Improvement of Kaitak R&H-Sirajganj Bazar Road (Ch.

0+000+7+350 km).

7.35 Km 7.35 Km 50.65 50.65 NCB Yes 12/15/2010 8/22/2011 11/30/2011 12/8/2010 M/S Md. Matiar

Rahman

100% 100%

615. Sun/UZR-21.3A Improvement of Kalipur-Haidarpur Road (Ch.

0+000+3+597 km).

3.60 Km 3.60 Km 26.62 26.62 NCB No 12/20/2010 8/27/2011 12/15/2011 12/14/2010 JV of Nurul Islam, M/S

Mubarok Hossain &

Humayon Kabir

100% 100%

616. Naw/RPM-146 Maintenance of Shibgonj GC to Khasherhat GC road via

Monakasa Hat (Ch. 0+000-11+400 Km).

11.40 Km 11.40 Km 12.38 12.38 NCB No 10/21/2010 6/28/2011 6/29/2011 10/21/2010 RE-RAB (JV) 100% 100%

617. Raj/RPM-137 Maintenance of Kakonhat-Kaligonj hat road (Ch. 0+000-

10+200 Km) .

10.20 Km 10.20 Km 20.14 20.14 NCB No 12/25/2010 9/1/2011 6/11/2011 12/12/2010 ME & AB Construction

(JV)

100% 100%

83

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

618. Bog/UR-106 Improvement of Muruil R&H-Gohail GC Via Eruil Bazar

road (Ch. 3+940-7+250 km).

3.31 Km 3.31 Km 16.65 16.65 NCB No 12/3/2010 8/10/2011 12/31/2011 11/24/2010 M/S Masuma Beguma 100% 100%

619. Com/RPM-149 Maintenance of Mahini-Boxganj Road (Ch. 1+000-

8+900 km)

7.90 Km 7.90 Km 15.76 15.76 NCB No 12/30/2010 9/6/2011 5/30/2011 12/23/2010 M/S ABM Delowar

Hossain

100% 100%

620. Cha/UZR-20.1A Improvement of Sepaikandi-Kalir Bazar-Bashurchar-

Baushia Ferryghat-Dhaka : Ctg RHD Road (Ch. 0+000-

7+375km)

7.38 Km 7.38 Km 29.36 29.36 NCB No 12/12/2010 6/30/2011 6/10/2011 12/5/2010 M/S. Sikder Enterprise 100% 100%

621. Cha/UZR-20.1B Improvement of Sepaikandi-Kalir Bazar-Bashurchar-

Baushia Ferryghat-Dhaka : Ctg RHD Road (Ch. 7+375-

13+000km)

5.63 Km 5.63 Km 29.62 29.62 NCB No 12/20/2010 8/27/2011 6/10/2011 12/13/2010 Mohammed Enuns &

Brothers (Pvt.) Ltd.

100% 100%

622. Cha/UZR-20.2A Improvement of Ibrahim B.T. Road (Ch. 0+000-

9+000km)

9.00 Km 9.00 Km 36.37 36.37 NCB No 12/12/2010 8/19/2011 6/10/2011 12/5/2010 M/S Aziz & Brothers 100% 100%

623. Cha/UZR-20.3A Improvement of Sepaikandi - Beltali Road (Ch. 0+000-

3+597 km)

4.39 Km 4.39 Km 31.22 31.22 NCB No 1/12/2011 9/19/2011 6/10/2011 1/5/2011 SA-VB-AL (JV) 100% 100%

624. Gaz/RPM-142 Maintenance of Bartuil-Shom-Tumulia Mision Road

(Ch. 1300-5850m).

4.55 Km 4.55 Km 15.26 15.26 NCB No 11/22/2010 11/22/2011 8/23/2011 11/4/2010 M/S Probal Engineers 100% 100%

625. Pab/UR-22B Shayamgonj GC-Raninagar UP via Vatshala bazar road

(Ch. 00-1559m)

1.56 Km 1.56 Km 7.70 7.70 NCB No 1/30/2011 10/7/2011 6/25/2011 1/23/2011 Md. Saidur Rahman &

Co Pvt. Ltd.

100% 100%

626. Gaz/RPM-153 Maintenance of Hatimara Bazar-Mouchak Bazar Road

(Ch. 0+000-3+200 km)

3.20 Km 5.20 Km 18.75 18.75 NCB No 2/1/2011 10/9/2011 6/15/2011 1/27/2011 M/S Amzad Traders 100% 100%

Maintenance of Mouchak-Lohakoir Mazar Road (Ch.

0+000-2+000 km)

2.00 Km 0.00

627. Com/RPM-151 Maintenance of Kashinagar Bazar (UP Office)-

Jugirkandi-Joymangalpur-Suagonj Road (Ch. 0+000-

3+900 km)

3.90 Km 3.90 Km 13.23 13.23 NCB No 1/30/2011 10/7/2011 6/30/2011 1/23/2011 M/S Mahabub

Enterprise

100% 100%

628. Com/RPM-154 Maintenance of Charbakar-Nobiabad Road (Ch. 0+500-

9+100 km)

8.60 Km 8.60 Km 13.01 13.01 NCB No 1/27/2011 10/4/2011 6/30/2011 1/20/2011 A S Trader

International

100% 100%

629. Com/RPM-155 Maintenance of Shahidnagar NHW-Goalmari GC Road

(Ch. 0+000-8+000 km)

8.00 Km 8.00 Km 12.75 12.75 NCB No 3/20/2011 11/25/2011 11/30/2011 3/13/2011 M/S Liberty Traders 100% 100%

630. Com/RPM-156 Maintenance of Dhalua-Kankirhat Road (Ch. 0+000-

8+000 km & 8+800-10+950 km)

10.15 Km 10.15 Km 19.09 19.09 NCB No 1/23/2011 9/30/2011 6/30/2011 1/16/2011 M/S M. I. Construction 100% 100%

631. Com/RPM-157 Maintenance of Laksam-Mudafforgonj via Sreeyang

road (Ch. 0+000-11+700 km).

11.70 Km 11.70 Km 14.77 14.77 NCB No 2/13/2011 10/21/2011 11/15/2011 2/6/2011 M/S Golden Traders 100% 100%

632. Com/RPM-158 Maintenance of Mahini-Boxganj road (Ch. 8+900-

16+900 km)

8.00 Km 8.00 Km 13.12 13.12 NCB No 2/4/2011 10/12/2011 6/30/2011 1/27/2011 M/S Zaman Traders 100% 100%

84

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

633. Com/RPM-160 Maintenance of (a) Shalder river ghat-Shiber bazar GC-

Kotashar-Amratali bazar Road (Ch. 0+000-3+300 km) &

(b) Nandirbazar-Panchthubi UP Office-Subarnnapur

bazar-Golabari bazar road (Ch. 1+340-6+665 km)

8.62 Km 8.62 Km 20.22 20.22 NCB No 1/5/2011 9/12/2011 6/30/2011 12/28/2010 M/S Tajwar Builders 100% 100%

634. Com/RPM-161 Maintenance of Brahmanpara-Shidlai bazar via Shidlai

UP Office road (Ch. 1+380-6+440km & 6+680-

6+750km)

5.13 Km 5.13 Km 15.84 15.84 NCB No 2/6/2011 10/14/2011 6/30/2011 1/30/2011 P. S. Consortium 100% 100%

635. Com/RPM-162 Maintenance of (a) Shahebabad UP Office (R&H)-

Ramnagar Bazar road (Ch. 2+600-6+570km) (b)

Brahmanpara-Chatiani-Chandipur-Malapara UP Office

(Ch. 4+600-8+700km) & (c) Brahmanpara UP Office-

Horimongal bazar road (Ch. 0+000-4+500km).

12.57 Km 12.57 Km 11.32 11.32 NCB No 1/30/2011 10/7/2011 6/30/2011 1/26/2011 M/S Bhuiyan Builders 100% 100%

636. Com/RPM-163 Maintenance of Bhomar Kandi-Kaduti via

Mohammadpur road (Ch. 0+000-2+130km)

2.13 Km 2.13 Km 9.35 9.35 NCB No 1/26/2011 10/3/2011 6/30/2011 1/19/2011 M/S Ananta Enterprise 100% 100%

637. Nat/RPM-131 Maintenance & Road Safety of Royna More-Jonail Road

(Ch. 0+000-10+500 Km).

10.50 Km 10.50 Km 7.49 7.49 NCB No 1/8/2011 9/15/2011 11/30/2011 1/4/2011 M/S Azad & Brothers-

Angira Electronics JV

100% 100%

638. Gaz/RPM-159 Maintenance of Baraipara-Chandabaha GC Road (Ch.

0+0000-4+400 km).

4.40 Km 4.40 Km 14.09 14.09 NCB No 2/7/2011 10/15/2011 6/15/2011 2/3/2011 M/S Olive Enterpise 100% 100%

639. Mun/RPM-126 Maintenance of Betka-Tongibari Road (Ch. 0+000-

3+850 km)

3.85 Km 3.85 Km 6.21 6.21 NCB No 1/12/2011 9/19/2011 5/1/2011 1/4/2011 M/S Khan Enterprise 100% 100%

640. Bra/RPM-165 (a) Maintenance of Bancharampur GC-Ujanchar GC

Road Via Dhariarchar Bazar (Ch. 0+000-6+000km) &

(b) Maintenance of Bancharampur HQ-Marichakandi

GC Via Doriadaulat UP and Kadamtoli Road (Ch. 0+900-

3+750km)

8.85 Km 8.85 Km 16.24 16.24 NCB No 2/17/2011 10/25/2011 12/31/2011 2/9/2011 M/S Azad & Brothers 100% 100%

641. Com/RPM-129 Maintenance of (a) Shashangacha Bus Stand-

Dharmapur Chowmohani-Dharmapur Degree Collage-

Comilla Kotbari RHD Road (Ch. 0+000-2+100 km) & (b)

Monagram-Haripur-Boura Bazar Road (Ch. 0+000-

3+000 km).

5.10 Km 5.10 Km 15.00 15.00 NCB No 1/5/2011 9/12/2011 11/30/2011 12/28/2010 MS & MKR (JV) 100% 100%

642. Bog/UR-107 Improvement of Kundar GC-Panditpukur via

Kallyannagar (Deota-Katlagari) road (Ch. 6+760-

10+600 km)

3.84 Km 3.84 Km 21.14 21.14 NCB No 2/3/2011 10/11/2011 11/15/2011 1/25/2011 M/S Masuma Begum 100% 100%

85

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

643. Com/RPM-167 Maintenance of (a) Suagonj Bazar-Banipur Road (Ch.

0+000-3+000 km) & (b) Gandamaty-Gabtaly-Maddam

Bijoypur Road (Ch. 0+000-1+500 km)

4.50 Km 4.50 Km 5.12 5.12 NCB No 4/4/2011 12/10/2011 6/30/2011 3/27/2011 M/S Tajwar Builders 100% 100%

644. Com/RPM-168 Maintenance of Chitoshiy Rly. Station-Barura via Janora

Road (Ch. 12+415-20+600 km).

8.19 Km 8.19 Km 27.94 27.94 NCB No 3/10/2011 11/15/2011 6/30/2011 3/2/2011 M/S Zaman Traders 100% 100%

645. Com/RPM-169 Maintenance of Barura Bazar-Ebadpur via Rammohon

Bazar Road (Ch. 0+000-6+050 & 11+015-12+115 km)

7.15 Km 7.15 Km 21.80 21.80 NCB No 3/20/2011 11/25/2011 6/30/2011 3/13/2011 M/S Ananto Enterprise 100% 100%

646. Com/RPM-164 Maintenance of Comilla (Chandpur Bridge to Rajgonj

Bazar)-Fakir Bazar-Saldanadi-Bagra Bazar Road.

Ch. 0+000-1+640 km = 1.640 km (Part-1)

Ch. 0+000-1+730 km = 1.627 km (Part-2)

3.27 Km 3.27 Km 11.31 11.31 NCB No 3/20/2011 11/25/2011 6/30/2011 3/13/2011 M/S Tajwar Builders 100% 100%

647. Com/RPM-171 Maintenance of Misree Jame Mosque-Darbeshpara-

Belgor-Gaiebanga Road (Ch. 0+000-8+000 km)

8.00 Km 8.00 Km 15.42 15.42 NCB No 3/20/2011 11/25/2011 10/30/2011 3/13/2011 MKC & MAR-JV 100% 100%

648. Bra/RPM-172 Maintenance of (a) Salimabad-Purba Rupashdi UP

Fardabad Road (Ch. 11+364-11+931 km), (b) Paschim

Saifullakandi UP-Rupshadi (S) Bazar Road (Ch. 3+236-

4+220 km), (c) Masimnagar Bazar R&H-Dariadaulat UP

Road via Madhyanagar Bazar & Domrakandi Road (Ch.

2+100-3+890 km) & (d) Bahadurpur-Velanagar Dafadar

Bari Road (Ch. 0+000-0+700 km)

3.94 Km 3.94 Km 7.58 7.58 NCB No 4/3/2011 12/9/2011 8/25/2011 3/27/2011 M/S Mohsinul Hassan 100% 100%

649. Mun/RPM-173 Maintenance of Bejgaon R&H-Kukutia-Nagerhat-

Kanaksar Road (Ch. 1+270-5+800 km)

4.53 Km 4.53 Km 11.80 11.80 NCB No 3/12/2011 11/17/2011 5/1/2011 3/6/2011 M/S Noor Construction 100% 100%

650. Com/RPM-174 Maintenance of Rajar Bazar-Alkora (Shafakruddin)

Road (Ch. 19+000-23+218 km)

4.22 Km 4.22 Km 13.36 13.36 NCB No 3/22/2011 11/27/2011 12/15/2011 3/15/2011 M/S Mazumder

Traders

100% 100%

651. Com/RPM-175 Maintenance of Mandra Bazar-Mokora Sarkar Bazar-

Narandia-Kankapoith road (Ch. 0+000-6+500 km)

6.50 Km 6.50 Km 17.99 17.99 NCB No 3/20/2011 11/25/2011 6/30/2011 3/13/2011 M/S Buhan & Haque

Construction

100% 100%

86

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012#DIV/0!

Start Completion

Estimated Cost

(in million Taka) OR Actual

Contract Price (with Contract

Currency)

Contract Package Number*Sl.

No.

Name of Contract (Brief Description) Financial

Progress as

of 30

June'12

PROCUREMENT PLANNING AND MONITORING FORMAT

Planned DateProcedure/

Method

Prior

Review**

(Yes/No)

Actual

Completion

Date

Date of

Contract

Signing

Quantity/ Number Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Progress of

Procurement

as of 30

June'12

652. Com/RPM-176 Maintenance of (a) Kakairtala-Juctikhula road (Ch.

0+000-2+750 km) & (b) Bissha-Lalbag-Rajashpur (Eco

Park) road (Ch. 0+000-2+915 km)

5.67 Km 5.67 Km 15.48 15.48 NCB No 3/13/2011 11/18/2011 6/30/2011 3/6/2011 M/S Abul Hasham 100% 100%

653. Sir/UR-109 Improvement of Bagati UP Office to Bezgati Hat Road

road (Ch. 0+000-2+ 400 Km).

2.40 Km 2.40 Km 7.84 7.84 NCB No 3/23/2011 11/28/2011 5/31/2011 3/8/2011 Md. Riaz Uddin 100% 100%

654. Cha/UR-108 Improvement of Algi (North) UP-Bangla Bazar Road via

Gazir Bazar, Anondo Bazar (Ch. 0+000-3+810 km)

3.81 Km 3.81 Km 17.78 17.78 NCB No 7/3/2011 3/9/2012 6/10/2011 3/1/2011 M/S Hossain Traders 100% 100%

655. Cha/RPM-177 Maintenance of Sachar UP-Ragdoil Bazar road (Ch.

0+000-3+714 km)

3.71 Km 3.71 Km 16.73 16.73 NCB No Apr'11 Dec'11

656. Naw/RPM-152 Maintenance of (a) Nawabganj-Shibganj R&H-Kalinagar

GC road (Ch. 0+000-5+382 km) & (b) Nawabganj-

Rajshahi R&H Upazila HQ-Amnura GC via Dogachi

Kansina road (Ch. 17+500-19+500 km).

7.38 Km 7.38 Km 13.46 13.46 NCB No 1/7/2011 9/14/2011 6/30/2011 12/30/2010 Md. Saidur Rahman &

Co. Pvt. Ltd.

100% 100%

Sub-Total (Civil Works) : #REF!

1 Mandatory for all contracts under the project regardless of value. SM: Staff Month, PQ: Prequalification

* Contract Package Number shall remain frozen, i.e. not be changed during the project period. NS : National Shopping, CP : Community Participation

** Procurement Processing Schedule for Prior review contracts shall have to be submitted to IDA (Prior Review limit for works contracts > US$ 500,000) QCBS: Quality and Cost-Based Selection

*** Procurement Plan Format shall be updated annually and be submitted to IDA for review. ICB : International Competitive Bidding; NCB: National Competitive Bidding;

2 This is also a typical example for guidance. QBS: Quality-Based Selection; FBS: Fixed Budget Selection

Note : All costs related to EMP including environmental mitigation and enhancement measures have been included in the UZR contracts.

87

Date : 03 December, 2005

18

Completed

Final bill paid

Final bill paid

Final bill paid

Cancelled &

payment

finalized

Final bill paid

Final bill paid

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

88

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Completed

Final bill paid

Final bill paid

Completed

Completed

89

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Completed

Completed

Contract

cancelled &

remaining works

executed

through package

no. Dha/UZR-

313. Final bill

paidFinal bill paid

90

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Completed

Final bill paid

Final bill paid

Contract

cancelled &

remaining works

executed

through package

no. Raj/UZR-

15A. Payment

finalized

91

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled &

remaining works

executed

through package

no. Sun/UZR-

21.1A, Sun/UZR-

21.1B, Sun/UZR-

21.1C, Sun/UZR-

21.1D, Sun/UZR-

21.2A &

Sun/UZR-21.3A

Contract

cancelled &

remaining works

executed

through package

no. Cha/UZR-

20.1A, Cha/UZR-

20.1B, Cha/UZR-

20.1C, Cha/UZR-

20.1D, Cha/UZR-

20.2A &

Cha/UZR-20.3A

92

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled &

remaining works

executed

through package

no. Sun/UZR-

21.1A, Sun/UZR-

21.1B, Sun/UZR-

21.1C, Sun/UZR-

21.1D, Sun/UZR-

21.2A &

Sun/UZR-21.3A

93

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

After

cancellation of

this contract, the

remaining work

implemented

through package

no. Mun/UZR-

25A. Payment

finalized

Cancelled and

remaining works

executed

through

Man/UZR-24A,

Man/UZR-24B.

Payment

finalized

Contract

cancelled &

remaining works

executed

through package

no. Syl/UZR-22A

94

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Completed

Final bill paid

Final bill paid

Final bill paid

95

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Contract

cancelled and

the remaining

work executed

through new

contract

package

no.Com/UZR-

33.1A. Payment

finalized

Contract

cancelled and

the remaining

work executed

through new

contract

package

no.Com/UZR-

33.2A. Payment

finalized

96

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Cancelled and

remaining work

completed

through a new

package

Joy/UZR-35.2A.

Payment

finalized

Final bill paid

97

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Sir/UZR-330.

Payment

Finalized

98

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Cancelled and

remaining works

executed

through Syl/UZR-

40.1A. Payment

finalized

Cancelled and

remaining works

executed

through Syl/UZR-

40.2A. Payment

finalized

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Raj/UZR-41.1A.

Payment

finalized

99

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Raj/UZR-41.2A.

Payment

finalized

Contract

cancelled &

payment

finalized

Final bill paid

Final bill paid

100

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Completed

101

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Hab/UZR-51A,

Hab/UZR-51B,

Hab/UZR-51C &

Hab/UZR-51D

Completed

Dropped

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Pab/UZR-50A,

Slice No. UZR-

50A.1, UZR-

50A.2, UZR-

50A.3 & UZR-

50A.4

102

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Bog/UZR-56.1A

103

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Bog/UZR-56.2A,

Slice no. UZR-

56.2A.1 & UZR-

56.2A.2

Completed

104

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Cancelled &

payment

finalized

Cancelled and

remaining works

executed

through

Package No.

Gaz/UZR-57.2A.

Payment

finalized

Cancelled and

remaining work

completed

through package

Gaz/UZR-57.3A.

Payment

finalized

Cancelled &

remaining work

executed

through package

no. Com/UZR-

58.1A. payment

finalized

105

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Cancelled and

remaining works

completed

through new

package

Mun/UZR-60.1A.

Payment

finalized

Cancelled &

remaining work

executed

through package

no. Mun/UZR-

60.2A. payment

finalized

Final bill paid

Dropped

106

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Completed

Completed

Final bill paid

Completed

Completed

Final bill paid

Cancelled and

remaining work

executed

through package

no. Joy/UZR-

66.2A. Payment

finalized

Final bill paid

107

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Completed

Final bill paid

Final bill paid

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Bog/UR-9A

Completed

Completed

108

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Bog/UR-12A

Final bill paid

Final bill paid

Final bill paid

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Raj/UR-16A.

Payment

finalized

Final bill paid

Final bill paid

Completed

Completed

Completed

109

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Cancelled and

remaining work

executed

through package

no. Pab/UR-

22A. Payment

finalized

Final bill paid

Final bill paid

After

cancellation of

this contract, the

remaining work

implemented

through package

no. Nao/UR-

25A. Payment

finalized

Final bill paid

Final bill paid

Final bill paid

110

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Cancelled and

remaining work

executed

through Dha/UR-

29A. Final bill

paid

Final bill paid

Final bill paid

Final bill paid

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Mun/UR-33A.

Payment

finalized

Cancelled &

Payment

finalized

Final bill paid

111

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Cancelled &

remaining work

executed

through package

no. Com/UR-

36A. Payment

finalized

Cancelled &

remaining work

executed

through package

no. Com/UR-

37A. Payment

finalized

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Com/UR-38A.

Payment

finalized

112

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Com/UR-39A.

Payment

finalized

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Com/UR-40A.

Payment

finalized

Final bill paid

Final bill paid

113

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Bra/UR-43A.

Payment

finalized

Final bill paid

Final bill paid

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Cancelled

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Mou/UR-52A.

Payment

finalized

114

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

115

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Completed

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Man/UR-65A.

Payment

finalized

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Man/UR-66A.

Payment

finalized

Final bill paid

Final bill paid

Final bill paid

Final bill paid

116

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Completed

Final bill paid

Cancelled and

remaining work

completed

through a new

package

Pab/UR-79A.

Payment

finalized

Completed

Completed

Final bill paid

117

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Cancelled and

remaining work

completed

through a new

package

Cha/UR-83A.

Payment

finalized

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Final bill paid

Completed

Final bill paid

118

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Cancelled and

remaining works

completed

through new

package

Pab/UR-98A

Cancelled and

remaining works

completed

through new

package

Dha/UR-99A.

Final bill paid

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

119

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Completed

Completed

Completed

Dropped due to

land problem

Dropped due to

local

contribution

Dropped

Final bill paid

Cancelled.

Payment

finalized

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

120

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Cancelled &

remaining

work

executed

through

package no.

Com/GCM-

21A.

Payment

finalized

Cancelled &

remaining

work

executed

through

package no.

Com/GCM-

22A.

Payment

finalized

Final bill paid

Final bill paid

Dropped, LC

unavailable

Cancelled &

payment

finalized

Final bill paid

Final bill paid

Final bill paid

Final bill paid

121

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Dropped due to

non-availibility of

Local

Contribution

122

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Cancelled due

to land problem

Completed

Completed

Completed

Completed

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Dropped

Completed

123

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Dropped

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Cancelled.

Payment

finalized

Final bill paid

Dropped

Final bill paid

Final bill paid

124

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Cancelled &

remaining

work

executed

through

package no.

Mou/GCM-

82A.

Payment

finalized

Final bill paid

Dropped

Cancelled &

Payment

finalized

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

125

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Completed

Completed

Dropped

Completed

Dropped

Dropped

Cancelled and

payment

finalized

Cancelled and

payment

finalized

Final bill paid

Final bill paid

Dropped

Dropped

Final bill paid

126

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Dropped due to

non-availability

of Local

contribution

Completed

Completed

Completed

Completed

Final bill paid

Final bill paid

Dropped

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Dropped

Completed

Final bill paid

127

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Dropped

Final bill paid

Final bill paid

Local

contribution not

yet received

Final bill paid

Dropped

Final bill paid

Dropped due to

non-availibility of

Local

Contribution

Dropped due to

non-availibility of

Local

Contribution

Dropped due to

court case.

Dropped due to

L/C problem

Writ petition

under High

Court Division

Dropped due to

L/C problem

128

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Dropped due to

L/C problem

Completed

Completed

Final bill paid

Cancelled &

remaining

work

executed

through

package no.

Syl/GCM-

150A.

Payment

finalized

Final bill paid

Final bill paid

129

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Dropped due to

non-availibility of

Local

Contribution

Final bill paid

Final bill paid

Final bill paid

Dropped

Dropped

Cancelled.

Payment

finalized

Final bill paid

Cancelled &

remaining

work

executed

through

package no.

Com/RJ-11A.

Payment

finalized

Dropped

Final bill paid

Final bill paid

130

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Dropped due to

lack of local

contribution

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Final bill paid

Completed

Dropped due to

lack of local

contribution

131

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Dropped

Final bill paid

Final bill paid

Dropped

Dropped

Final bill paid

Final bill paid

Final bill paid

Dropped due to

L/C problem

Dropped due to

L/C problem

Dropped due to

L/C problem

Final bill paid

Final bill paid

Dropped due to

land problem

132

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Dropped due to

land problem

Final bill paid

Final bill paid

Final bill paid

Completed

Completed

Final bill paid

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Mun/RPM-

5.2A.Payment

finalized

Final bill paid

Final bill paid

Final bill paid

Final bill paid

133

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

134

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Completed

Completed

Completed

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Com/RPM-

19.2A.Payment

finalized

135

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Completed

Completed

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

136

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Completed

Completed

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Raj/RPM-29A.

Payment

finalized

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Raj/RPM-30A.

Payment

finalized

Final bill paid

137

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Completed

Completed

Completed

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

138

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Completed

Completed

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

139

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

140

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Completed

Completed

Completed

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Cancelled.

Payment

finalized

141

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Nao/RPM-51A.

Payment

finalized

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

142

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Contract

cancelled and

the remaining

work executed

through new

contract

package no.

Man/RPM-

55.1A.Payment

finalized

Cancelled and

remaining works

taken under

Flood

Component

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

143

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Cancelled.

Payment

finalized

Cancelled &

remaining work

executed

through package

no. Mun/RPM-

57.5A. Payment

finalized

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Cancelled and

remaining work

implemented

through a new

contract

Com/RPM-

59.1A. Payment

finalized

Final bill paid

144

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Cancelled and

remaining work

implemented

through a new

contract

Com/RPM-

59.3A. Payment

finalized

Final bill paid

Cancelled and

remaining work

implemented

through a new

contract

Com/RPM-

59.5A. Payment

finalized

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

145

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

146

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Ullapara-

Mohonpur GC

road is dropped

from the project.

Final bill paid

Final bill paid

147

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Completed

Completed

Completed

Completed

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

148

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Completed

Final bill paid

Final bill paid

Final bill paid

This package

has been

dropped from

maintenance

work

Final bill paid

Final bill paid

149

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

0%

Remaining

works of

contract

package

Sun/UZR-314.2

implemented

through this

contract.

Payment

finalized

Final bill paid

Cancelled and

remaining work

implemented

through a new

contract

Dha/UZR-313A,

Dha/UZR-313B,

Dha/UZR-313C,

Dha/UZR-313D

& Dha/UZR-

313E. Payment

finalized

150

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Completed

Completed

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

151

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Remaining

works of

contract

package

Sir/UZR-38.3

implemented

through this

contract.

Payment

finalized

Original contract

package

Mun/UZR-25

was cancelled

and this

package is for

the remaining

works. Final bill

paid

Original contract

package

Mun/UZR-25

was cancelled

and this

package is for

the remaining

works. Final bill

paid

152

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Original contract

slice Raj/UZR-

41.2 was

cancelled and

this package is

for the

remaining

works. Final bill

paid

Original contract

slice Bog/UZR-

56.2 was

cancelled and

this package is

for the

remaining

works.

153

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Original contract

package

Bog/UR-9 was

cancelled and

this package is

for the

remaining works

Original contract

package

Bog/UR-12 was

cancelled and

this package is

for the

remaining

works.

Original contract

package

Raj/RPM-29 was

cancelled and

this package is

for the

remaining

works. Final bill

paid

Original contract

package

Raj/RPM-30 was

cancelled and

this package is

for the

remaining

works. Final bill

paid

154

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Original contract

Mun/RPM-5.2

was cancelled

and this

package is for

the remaining

works. Final bill

paid

Final bill paid

Final bill paid

Original contract

Syl/UZR-22 was

cancelled and

this package is

for the

remaining

works.

Completed

155

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Original contract

Raj/UZR-15 was

cancelled and

this package is

for the

remaining

works. Final bill

paid

Completed

Dropped

Scope reduced

Final bill paid

Final bill paid

Final bill paid

Completed

156

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Original contract

Bog/UZR-56.1

was cancelled

and this

package is for

the remaining

works.

Original contract

Pab/UR-98A

was cancelled

and this

package is for

the remaining

works .

Completed

Original contract

Raj/UR-16 was

cancelled and

this package is

for the

remaining

works. Final bill

paid

Final bill paid

Final bill paid

Final bill paid

157

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Dropped

Work completed

Final bill paid

Final bill paid

Completed

Final bill paid

Final bill paid

Completed

Final bill paid

Final bill paid

Final bill paid

158

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Bidding

document sent

XEN, but tender

not yet invited

Work completed

Final bill paid

Final bill paid

Dropped

Completed

Completed

Final bill paid

Final bill paid

159

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Original contract

Joy/UZR-35.2

was cancelled

and this

package is for

the remaining

works.

Cancelled

Original contract

Gaz/UZR-57.3

was cancelled

and this

package is for

the remaining

works. Final bill

paid.

Final bill paid

Bid cancelled

and re-bid not

concurred by

IDA

160

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Dropped

Dropped

Dropped

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

161

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Completed

Dropped

Final bill paid

Final bill paid

Completed

162

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Completed

Completed

Final bill paid

Final bill paid

163

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

164

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Dropped

Completed

Final bill paid

Final bill paid

165

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

166

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

167

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Scope reduced

Completed

Final bill paid

Final bill paid

Final bill paid

Completed

168

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

169

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

170

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

171

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

172

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

Final bill paid

173

Remarks

PROCUREMENT PLANNING AND MONITORING FORMAT

Final bill paid

Final bill paid

Final bill paid

174

Date : 03 December, 2005

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012

Start Completion

1 2 3 4 6 7 8 9 10 11 12 13 14 15

01. G1 Road Pavement Cutter for Maintenance Works 21 2.50 ICB No 10/30/2004 5/23/2005 6/25/2005 12/8/2004 M/S Sarker Kabir Ahmed 100 % Completed

02. G2 Vibrating Rammer for Maintenance Works 7 0.95 ICB No 10/30/2004 5/23/2005 6/20/2005 12/8/2004 M/S Sarker Kabir Ahmed 100 % Completed

03. G3 Bitumen Mixing Plant 6 12.00 ICB No 10/30/2004 5/23/2005 5/5/2005 1/5/2005 Universal Industrial

Kolkata, India

100 % Completed

04. G3.1 Bitumen Mixing Plant 15 30.00 ICB Yes Mar'10 Dec'10 Dropped

05. G4 Nuclear Densometer 25 This Contract (Package No. G4) has been dropped

06. G5 Pick up for Field Test 8 8.25 ICB No 10/30/2004 5/23/2005 2/10/2005 8/18/2004 Nissan Motors, Japan 100 % Completed

07. G6 Mini Truck (1.5 - 3.0 Ton) for Maintenance Works 7 This Contract (Package No. G6) has been dropped 0 %

08. G7 Motor Cycle for Field Supervision 67 6.14 ICB No 6/1/2004 12/23/2004 12/27/2004 9/30/2005 Atlas Bangladesh Ltd. 100 % Completed

09. G7a Motor Cycle for Field Supervision 20 2.50 NS No 3/1/2004 3/31/2004 04/06/04 &

27/03/05

4/24/2004 Atlas Bangladesh Ltd. 100 % Completed

10. G7b Motor Cycle for Field Supervision 113 11.93 ICB No 1/1/2006 7/25/2006 6/20/2006 5/15/2006 Karnophuli Industries Ltd. 100 % Completed

11. G8 Computer and Accessories (inc 5 Laptops) 100 9.98 ICB No 10/30/2004 5/23/2005 5/26/2005 12/8/2004 Information Technology

System (ITS)

100 % Completed

12. G8a Computer and Accessories 90 9.00 ICB No 9/30/2005 4/23/2006 3/13/2006 2/13/2006 Daffodil Computers 100 % Completed

13. G8b Computer and Accessories 10 0.65 NS No 3/1/2004 4/30/2004 5/15/2004 4/24/2004 Saud Enterprise 100 % Completed

14. G9 Photocopier 70 6.00 ICB No 4/1/2004 10/23/2004 3/7/2005 8/14/2004 Toshiba Singapore Pte.

Ltd.

100 % Completed

15. G9a Photocopier 2 1.20 NS No 2/1/2004 4/1/2004 4/15/2004 26/02/04

& 31/03/04

International Office

Machines Ltd.

100 % Completed

16. G10 Levelling sets 71 1.42 NCB No 5/1/2004 10/13/2004 11/7/2004 9/7/2004 M/S Kohinoor Trading 100 % Completed

17. G11 Theodolite 7 This Contract (Package No. G11) has been dropped 0 %

18. G12 Bump Integrators (for Road Roughness Measurement) 21 4.70 NCB No 5/1/2004 10/13/2004 10/7/2004 9/7/2004 M/S Sarker Kabir Ahmed 100 % Completed

19. G13 Merlin (For measuring Road Roughness and Calibrating Bump

Integrators)

0 This Contract (Package No. G13) has been dropped 0 %

Quantity/

Number

Actual

Completion

Date

Date of

Contract

Signing

Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Estimated Cost

(in million Taka) OR

Actual Contract

Price (with Contract

Currency)

Procedure/

Method

Prior

Review**

(Yes/No)

Planned Date

PROCUREMENT PLANNING AND MONITORING FORMAT

Progress of

Procurement

as of 31

July'09

RemarksSl.

No.

Contract

Package

Number*

Name of Contract (Brief Description)

175

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012

Start Completion

Quantity/

Number

Actual

Completion

Date

Date of

Contract

Signing

Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Estimated Cost

(in million Taka) OR

Actual Contract

Price (with Contract

Currency)

Procedure/

Method

Prior

Review**

(Yes/No)

Planned Date

PROCUREMENT PLANNING AND MONITORING FORMAT

Progress of

Procurement

as of 31

July'09

RemarksSl.

No.

Contract

Package

Number*

Name of Contract (Brief Description)

20. G14 Multimedia Video Projector 1 0.26 NS No 4/15/2005 6/14/2005 5/30/2005 5/15/2005 Techno Test 100 % Completed

21. G15 Overhead Projector (OHP) 2 0.50 NS No 8/12/2005 10/11/2005 9/30/2005 9/13/2005 Unique Business 100 % Completed

22. G16 Video Camera 2 0.18 NS No 8/12/2005 10/11/2005 9/30/2005 9/13/2005 Shahil Enterprise 50 % 1 No. Completed and remaining are

dropped

23. G17 Local Area Network (LAN)

(online UPS & other related accessories)

- 0.92 NS No 8/15/2004 10/14/2004 10/13/2004 9/16/2004 Green Power Electronics 100 % Completed

24. G17.1 Local Area Network (LAN)

(LAN equipment)

- 2.08 NS No Jun'08 Dec'08 Various Various 75 % Partly Completed and remaining are

dropped

25. G17.2 Local Area Network (LAN)

(LAN software)

- 2.00 NS No Jun'08 Dec'08 6/16/2009 BME&SHOVIC Enterprise 10 % Partly Completed and remaining are

dropped

26. G18 GIS Accessories

(Computer & Other related accessories)

- 0.92 NS No 3/1/2004 12/30/2004 12/30/2004 Various Various 100 % Completed

27. G18.1 GIS Accessories

(GIS equipment)

- 2.08 NS No Jun'08 Dec'08 Various Various 40 % Partly Completed

28. G18.2 GIS Accessories

(GIS software)

- 2.00 NS No Jun'08 Dec'08 BME&ANNI 20 % Partly Completed

29. G19 Air Conditioner 2 0.40 NS No 5/1/2005 6/30/2005 6/25/2005 6/12/2005 Rakin Enterprise 100 % Completed

30. G20 Office Equipments and others for selected UPs (LGIP) - 3.00 NCB No Mar'10 Dec'10 0 % Dropped

31. G20a Office Equipments and others for selected UPs (LGIP) - 1.20 NS No Mar'10 Dec'10 0 % Dropped

32. G21.1 ICT & GIS Equipments and Software

(1 no. photocopier)

- 0.44 NCB No 3/1/2006 8/13/2006 7/18/2006 6/21/2006 Sunrise International 100 % Completed

33. G21.2 ICT & GIS Equipments and Software

(1 no. plotter & 1 no. scanner)

- 2.36 NCB No 3/1/2006 8/13/2006 8/28/2006 7/30/2006 Flora Ltd. 100 % Completed

34. G21.3 ICT & GIS Equipments and Software

(1 no. online printer)

- 0.67 NCB No 3/1/2006 8/13/2006 7/18/2006 6/21/2006 Libra Computer Services 100 % Completed

35. G21.4 ICT & GIS Equipments and Software

(Video conferencing equipment with software)

- 6.53 NCB No Jun'08 Dec'08 11/30/2008 10/7/2008 Narban Communication

Ltd.

60 % Partly Completed and remaining are

dropped

36. G21.5 ICT & GIS Equipments and Software

(WAN equipment)

- 15.00 NCB No Mar'10 Dec'10 0 % Not done

37. G21a.1 ICT & GIS Equipments and Software

(DDN Modem & Router)

- 0.76 NS No 5/1/2005 6/30/2005 6/27/2005 6/12/2005 Shahil Enterprise 100 % Completed

176

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012

Start Completion

Quantity/

Number

Actual

Completion

Date

Date of

Contract

Signing

Supplier's Name OR

Contractor's Name

OR Consultant's

Name

Estimated Cost

(in million Taka) OR

Actual Contract

Price (with Contract

Currency)

Procedure/

Method

Prior

Review**

(Yes/No)

Planned Date

PROCUREMENT PLANNING AND MONITORING FORMAT

Progress of

Procurement

as of 31

July'09

RemarksSl.

No.

Contract

Package

Number*

Name of Contract (Brief Description)

38. G21a.2 ICT & GIS Equipments and Software

(Multimedia Video Projector, Computer & other related

accessories)

- 2.04 NS No Mar'10 Dec'10 0 % Not done

39. G21a.3 ICT & GIS Equipments and Software

(Video conferencing equipment)

- 2.10 NS No Mar'10 Dec'10 0 % Not done

40. G21a.4 ICT & GIS Equipments and Software

(DDN line equipment with line charge)

- 2.10 NS No Jun'08 Dec'08 6/10/2008 55 % Partly Completed and remaining are

dropped

Sub-Total (Equipment & Goods) : 131.42

1 Mandatory for all contracts under the project regardless of value. SM: Staff Month, PQ: Prequalification

2 This is also a typical example for guidance. QCBS: Quality and Cost-Based Selection

* Contract Package Number shall remain frozen, i.e. not be changed during the project period. ICB : International Competitive Bidding; NCB: National Competitive Bidding

** Procurement Processing Schedule for Prior review contracts shall have to be submitted to IDA (Prior Review limit for works contracts > US$ 300,000) QBS: Quality-Based Selection; FBS: Fixed Budget Selection

*** Procurement Plan Format shall be updated annually and be submitted to IDA for review.

**** As per discussion with the 3rd WB Supervision Mission, 21 Nos. of Total Station and 21 Nos. Merlin (instead of 1) have been included in the Procurement Plan.

177

Date : 03 December, 2005

Name of the Project : Rural Transport Improvement Project IDA Credit No. : 3791-BD

Credit Effective Date : July 30, 2003 Credit Closing Date : June 30, 2012

Start Completion

1 2 3 4 5 6 7 8 9 10 11 12 13 1401. S1 Design, Supervision, Monitoring and Management

Consultant for Northwestern and Central Part.

270 SM**** 312.72 QCBS Yes Jan'04 Jun'08 12/31/2003 JV of HIFAB Intl. AB &

DHV Env. and Infra.

BV

100%

02. S2 Design, Supervision, Monitoring and Management

Consultant for Eastern and Central Part.

270 SM**** 294.45 QCBS Yes Jan'04 Jun'08 12/31/2003 SMEC International

Pty. Ltd.

100%

03. S3 Procurement Audit Services 48 SM 0.00 FB No Jan'07 Jun'08 Dropped

04. S4 Quality Audit Services 72 SM 19.92 FB Yes Jan'05 Jun'08 12/31/2004 Joint Venture of SNC-

Lavalin & Sheladia

Associates

100%

05. S5 Financial Audit Services/Financial Management

Services (UFMS rollout)

20 SM 4.50 FB No Mar'11 Jun'11 Dropped

06. S6 Impact Study-BIDS 30 SM 6.86 Single Source Yes Jul'04 Jun'08 BIDS 100%

07. S7 Project Preparation of Follow up Project 150 SM 39.29 FB Yes Sep'10 Apr'11 JV of HIFAB Intl. AB 100%

08. S8 Institutional Strengthening Action Plan (ISAP) 100 SM 49.73 FB Yes Nov'04 Dec'06 12/4/2004 Joint Venture of WSA,

RPMC, Kranti & Divine

Associates

100%

09. S9 Short-term Consultancy (Example : LGIP etc.) 25 SM 1.98 IC No Jan'04 Jun'04 26/12/03

(LGIP)

Kranti Associates and

EADS

100% Completed

10. S10 Other Studies (Example : IS Impact Study, Study on

Community Road Safety, ICT, EMP, ECP and others)

100 SM 11.81 FB Yes Mar'10 Dec'10 100%

11. S11 Training for LGED Officials/Contractors/UP

representatives (In a number of small packages)

80,000 PD 92.34 Through LGED

& other

Institutes

Yes Jan'04 Jun'10 100%

PROCUREMENT PLANNING AND MONITORING FORMAT

Sl.

No.

Contract

Package

Number*

Name of Contract (Brief Description) Quantity/

Number

Progress of

Procurement

as of 30

June'12

RemarksPlanned Date Actual

Completion

Date

Date of

Contract

Signing

Supplier's Name

OR Contractor's

Name OR

Consultant's

Name

Estimated Cost

(in million Taka) OR

Actual Contract

Price (with Contract

Currency)

Procedure/

Method

Prior

Review**

(Yes/No)

178

Start Completion

Sl.

No.

Contract

Package

Number*

Name of Contract (Brief Description) Quantity/

Number

Progress of

Procurement

as of 30

June'12

RemarksPlanned Date Actual

Completion

Date

Date of

Contract

Signing

Supplier's Name

OR Contractor's

Name OR

Consultant's

Name

Estimated Cost

(in million Taka) OR

Actual Contract

Price (with Contract

Currency)

Procedure/

Method

Prior

Review**

(Yes/No)

12. S12 Environmental Audit 10 SM 6.87 FB No Aug'05 Jun'08 M/S Sheladia

Associates &

Consultants (Pvt) ltd.

100%

13. SM-1 Supervision and Monitoring Consultancy Services 10 M 31.86 Single Source Yes Jul'08 Mar'09 JV of HIFAB Intl. AB 100%

14. SM-2 Supervision and Monitoring Consultancy Services 10 M 31.03 Single Source Yes Jul'08 Mar'09 SMEC International

Pty. Ltd.

100%

15. SA-1 Supervision and Monitoring Consultancy Services 15 M 92.90 QCBS Yes Apr'09 Jun'10 JV of HIFAB Intl. AB 100%

16. SA-2 Supervision and Monitoring Consultancy Services 15 M 72.70 QCBS Yes Apr'09 Jun'10 SMEC International

Pty. Ltd.

100%

17. SA-3 Supervision and Monitoring Consultancy Services 30 M 30.70 Single Source No Jul'10 Jun'11 JV of HIFAB Intl. AB 100%

18. SA-4 Supervision and Monitoring Consultancy Services 30 M 38.01 Single Source No Jul'10 Jun'11 SMEC International

Pty. Ltd.

100%

19. Baseline Survey 2.49 FB No Jun'05 Jun'06 Yusuf Associates 100%

20. Independent Review of Resettlement under RTIP-

BIDS

2.58 FB No Jun'08 Jun'10 BIDS 100%

Sub-Total (Consultancy & Other Studies) : 1,142.74

Grand Total : #REF!

1 Mandatory for all contracts under the project regardless of value. QCBS: Quality and Cost-Based Selection

2 This is also a typical example for guidance. ICB : International Competitive Bidding; NCB: National Competitive Bidding

* Contract Package Number shall remain frozen, i.e. not be changed during the project period. QBS: Quality-Based Selection; FBS: Fixed Budget Selection

** Procurement Processing Schedule for Prior review contracts shall have to be submitted to IDA (Prior Review limit for works contracts > US$ 100,000) PD : Person Days, SM: Staff Month, PQ: Prequalification

*** Procurement Plan Format shall be updated annually and be submitted to IDA for review. IC : Individual Consultant

**** Excluding Staff Month of Mid-level and Junior Staff.

179