National Business and Management Conference 2015 | p. 377 Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao University; and Marites Khanser, University of San Carlos ABSTRACT The case study evaluated the procurement process of Central Mindanao University based on RA 9184 “Government Procurement Reform Act.” It looked at the four major stages of procurement processes, planning, public bidding and alternative methods of procurement, contract implementation, and post-implementation using the four pillars of national public procurement system. These are: (1) compliance with the legislative and regulatory framework, (2) agency institutional framework and management capacity, (3) procurement operations and market practices, and (4) integrity and transparency of the agency procurement system. Aimed to produce a proposed university procurement manual, this case study sought to answer how procurement processes is implemented using the pillars of national public procurement system; if there are non-compliance, why are these occurring; and what are the challenges faced by the University in attaining full compliance. Data were gathered using surveys, interview, focus group discussion, document search, and report extraction using purposive sampling. Data gathered were transcribed, tallied, tabulated and analyzed using weighted means and qualitative ratings. Results revealed that compliance of the University procurement practices is very satisfactory. Correlations across pillars show that each pillar affects one another; hence issues that affect all the four pillars are being examined and analyzed. Eleven issues were identified affecting the four pillars, its indicators and sub-indicators. These are: (1) continued use of alternative method of procurement, particularly shopping; (2) few suppliers acquire bid documents and join the biding; (3) lack of feedback mechanism; (4) items purchased that are not in accordance with the specifications indicated in the PPMP; (5) occurrence of failed biddings; (6) delay in the procurement of goods, services and infrastructure projects; (7) lack of performance evaluation system specific for procurement personnel; (8) the need to improve the system of documents and records keeping; (9) lack of written procedures for quality control, acceptance and inspection of goods and services; (10) very few to no observer present during the bidding process; and (11) specific anti-corruption programs are not perceptible. These issues occur due to weaknesses found in multifarious activities and processes in the University. Despite collective efforts in its pursuit of achieving full compliance to the national procurement system requirements, the University still encountered impediments obstructing the achievement of its goals. These challenges include timing differences between project timeframes and release of funds, stringent timeframe allotted for projects, manual workflow, and budgetary and funding constraints, among others. These inherent constraints increases difficulty in achieving full compliance. This case study recommends adoption of the proposed University procurement manual and

Upload: others

Post on 11-Feb-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 377

Procurement processes in a state university in Mindanao: A case study

by Sheila Mae L. Lupian-Poliran, Central Mindanao University;

and Marites Khanser, University of San Carlos

ABSTRACT

The case study evaluated the procurement process of Central Mindanao University based

on RA 9184 “Government Procurement Reform Act.” It looked at the four major stages of

procurement processes, planning, public bidding and alternative methods of procurement, contract

implementation, and post-implementation using the four pillars of national public procurement

system. These are: (1) compliance with the legislative and regulatory framework, (2) agency

institutional framework and management capacity, (3) procurement operations and market

practices, and (4) integrity and transparency of the agency procurement system.

Aimed to produce a proposed university procurement manual, this case study sought to

answer how procurement processes is implemented using the pillars of national public

procurement system; if there are non-compliance, why are these occurring; and what are the

challenges faced by the University in attaining full compliance.

Data were gathered using surveys, interview, focus group discussion, document search,

and report extraction using purposive sampling. Data gathered were transcribed, tallied, tabulated

and analyzed using weighted means and qualitative ratings.

Results revealed that compliance of the University procurement practices is very

satisfactory. Correlations across pillars show that each pillar affects one another; hence issues that

affect all the four pillars are being examined and analyzed. Eleven issues were identified affecting

the four pillars, its indicators and sub-indicators. These are: (1) continued use of alternative method

of procurement, particularly shopping; (2) few suppliers acquire bid documents and join the

biding; (3) lack of feedback mechanism; (4) items purchased that are not in accordance with the

specifications indicated in the PPMP; (5) occurrence of failed biddings; (6) delay in the

procurement of goods, services and infrastructure projects; (7) lack of performance evaluation

system specific for procurement personnel; (8) the need to improve the system of documents and

records keeping; (9) lack of written procedures for quality control, acceptance and inspection of

goods and services; (10) very few to no observer present during the bidding process; and (11)

specific anti-corruption programs are not perceptible. These issues occur due to weaknesses found

in multifarious activities and processes in the University.

Despite collective efforts in its pursuit of achieving full compliance to the national

procurement system requirements, the University still encountered impediments obstructing the

achievement of its goals. These challenges include timing differences between project timeframes

and release of funds, stringent timeframe allotted for projects, manual workflow, and budgetary

and funding constraints, among others. These inherent constraints increases difficulty in achieving

full compliance.

This case study recommends adoption of the proposed University procurement manual and

Page 2: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 378

addressing the weaknesses in the process. The ACTION Plan, which stands for A – Appoint, C –

Create, T – Trim down, I – Inform, O – On-time completion, and N – Noteworthy monitoring, can

be used in the implementation. It also recommends that GPPB should tap the relevant accredited

professional organizations to institutionalize observer representation.

Keywords: procurement, public procurement, pillars of public procurement system,

State Universities and Colleges (SUCs)

RATIONALE OF THE STUDY

Procurement is a vital component of public service. In many countries including the

Philippines, the government is the single largest procuring entity in the economy making

sustainable procurement essential.

The Philippine government spends billions of taxpayers’ money annually to acquire goods and

services for its projects and deliver services to its citizens. In 2015, government procurement is

projected to reach Php650 billion or 25% of the proposed budget and 4.6% of the country’s

Gross Domestic Product (GDP) (Department of Budget and Management [DBM], 2015).

Certainly, public procurement system is at the center of the way public money is spent since

budgets get translated into services largely through procurement of goods and services by the

government.

Like many member countries of the United Nations (UN), the Philippine government

devised rules and mechanisms like Republic Act (RA) No. 9184 or the Government Procurement

Reform Act (GPRA) of 2003 and engaged into the use of Information Technology through the use

of Electronic Procurement System to answer call for greater uniformity and transparency (United

Nations Environmental Programme [UNEP], 2013). Strengthened by the issuance of rules and

regulations to reiterate its implementation (Executive Order No. 40, 2001, DBM, 2013a,

Administrative Order No. 17, 2011), these initiatives emphasize the substantial savings brought

by a more uniform and transparent procurement process (Ambat & Ycasiaco, 2008, and Bombay,

2011). These regulations aim to enhance transparency, emphasize accountability, improve

efficiency through competitiveness and streamlined processes, and widen public participation and

monitoring.

Despite the so-called world class regulation and recent developments, public procurement in the

Philippines never escapes scandals and controversies (Bombay, 2011, Jones, 2011, Ambat &

Ycasiano, 2008). Whether the perpetrators simply do not fear because the laws do not seem to

have fangs for the rich and influential; or these scandals came out in the open as a result of the

efforts of the government to promote transparency and good governance; or this is simply a domino

effect and chain reactions of the mortified few who wish to implicate others as the mastermind or

accomplice. For whatever reason there is, the fact remains that these scandals and corrupt practices

exist and must be addressed.

Gonzalez (2014) emphasized that a law is only as good as its implementation. However,

Commission on Audit (COA) (2012), the World Bank (Gonzales, 2014), and Philippine

Page 3: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 379

Government Electronic Procurement System (PhilGEPS) (2014) reports affirm Jones’ (2011)

observation that effective implementation is lacking in the Philippines. Among the government

agency classifications, State Universities and Colleges (SUCs) are reported as most compliant.

SUCs in the Philippines are public institutions of higher learning created by an act passed

by the Philippine Congress. Central Mindanao University (CMU), a premier SUC in Mindanao,

had been instrumental in transforming the lives of the people living in the depressed, deprived, and

disadvantaged sectors of Region 10, specifically in Bukidnon and adjacent provinces through the

delivery of quality services in the area of Instruction, Research, Extension and Production (M.

Poliran, 2013). The procurement processes of CMU are key factors that affect its delivery of

quality services, yet Ortega (2010) cited delay in procurement as a major problem encountered by

different income generating projects of the University.

This study was conceptualized to evaluate the procurement processes of CMU based on

RA 9184 or the GPRA in order to propose a University Procurement Manual. Procurement

processes were evaluated in four key areas called “Pillars” that characterize the basic elements of

procurement of CMU as patterned after the national public procurement, to wit: 1) compliance

with the legislative and regulatory framework, 2) agency institutional framework and management

capacity, 3) procurement operations and market practices, and 4) integrity and transparency of the

agency procurement system. These pillars are further defined by sixteen (16) indicators and forty

(40) sub-indicators against which the existing elements of the procurement system of a government

agency will be evaluated (Organization for Economic Co-operation and Development [OECD],

2010, and Government Procurement Policy Board [GPPB], 2012). Strengths and weaknesses

would be identified, as well as the issues, causes and challenges that deter the university from

attaining full compliance.

Presently, the university is preparing to secure an International Organizational Standard

(ISO) certification. Having written policies and procedures not only meet the ISO requirements

but also warrant that best practices and reforms will be sustainable despite manpower movements

and that the university procurement process operates within the purview of RA 9184 and relevant

laws and regulations. These give rise to a need for a university procurement manual to document

both the university best practices and streamlined procurement processes.

REVIEW OF RELATED LITERATURE

Procurement is the acquisition of goods, consulting services, and the contracting for

infrastructure projects by the procuring entity (GPRA, 2003, and GPPB, 2009). Public

procurement is where the procuring entity is a government branch, constitutional commission or

office, agency, department, bureau, office or its instrumentality.

In the global context, public procurement significantly affects the economy accounting up

to 30 percent of GDP (UNEP, 2013 citing OECD), significant enough to pave the way for

sustainable public procurement to gain popularity in the global arena. Sustainable procurement meet the needs of organizations while achieving value for money, generating benefits to the society

and economy and putting emphasis on ethics. Countries like Chile emphasizes integrity, the United

Kingdom on value for money, Lebanon on basic low cost vis-à-vis lifecycle cost, Japan and Sweden

on transparency (UNEP, 2013) and the Philippines on transparency, competitiveness, streamlined

Page 4: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 380

process, accountability, and public monitoring (GPRA, 2003, and GPPB, 2009).

The Philippine government procurement increasingly becomes a significant component of

the overall budget and the economy accounting for an average of 3.6% of GDP and 21% of total

government spending in 2010-2014. Nominal value crossed the half a trillion mark in 2014 and is

projected to reach approximately P650 billion in 2015 or 25% of the proposed budget and 4.6% of

GDP (DBM, 2010-2015).

The Procurement Process

In order to systematize the procurement process, avoid confusion and ensure transparency,

GPRA (2003) and its revised Implementing Rules and Regulations (IRR) (GPPB, 2009) require

standardization of the procurement process and forms to be used. Procurement activities have to

undergo uniform phases which include procurement planning, the bidding process or procurement

through an alternative method, contract implementation and completion, and post-implementation

and warranty period. The bidding documents shall also be prepared using standard forms and

manuals prescribed by the GPPB. Additional documents and specifications may be prepared and

required by the procuring entity when deemed necessary to complete the information required for

the bidders to prepare and submit their bids.

Procurement Planning. The GPRA (2003) and GPPB (2009) require linkage between

procurement planning and budgeting. Government agencies are required to prepare an Annual

Procurement Plan (APP) where all procurement of the agency shall be based.

Modes of Procurement. GPRA (2003) also requires that all procurement shall be done

through competitive bidding or public bidding which is open to participation by any interested

party. It takes 28-170 days to complete from the pre-procurement conference, posting of

advertisement on invitation to bid, pre-bid conference, posting/payment of bid security, the receipt

and opening of bids, eligibility screening of bids, bid evaluation, post-qualification, issuance of

notice of award, posting/payment of performance security, contract signing and approval, until the

issuance of notice to proceed (GPPB, 2009).

Price and quality are often the primary consideration in procurement. In many countries,

price is considered the dominant awarding rule, followed by “value for money” which is a broader

concept that allows other criteria and oftentimes considers life cycle/ whole life cycle costing,

commonly known as “cradle to grave” (UNEP, 2013). Several studies also advocate quality,

experience and responses to technical specifications (Singh et al., 2012, European Commission,

2011, O’Riordan et al., 2011, and Bergman, 2011).

In the Philippines, there is a concern on the quality of product and reliability of suppliers

and contractors. To address this, the eligibility of bidders are determined and bids are evaluated

based on compliance to the required specifications using pass or fail criteria based on the technical

component of the bid submitted. The financial capacity of the supplier or contractor is also

evaluated based on its recently completed contracts, cash facility, line of credit, or net financial

contracting capacity. Only the bids that pass the technical component will be evaluated in terms of

financial component to determine the “Lowest Calculated Bid” for procurement of goods and

services and “Highest Rated Bid” in case of consulting services (GPRA, 2003, GPPB, 2009, and

Page 5: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 381

Jones, 2011).

A Notice of Award will be issued to the winning bidder who will then post a performance security before formally entering into a contract with the procuring agency. Notice to Proceed will then

be issued within seven days from signing of the contract (GPRA, 2003, and GPPB, 2009).

Alternative modes of procurement such as limited source bidding, direct contracting, repeat

order, shopping, and negotiated procurement are allowed in certain cases in order to promote

economy and efficiency (GPRA, 2003, and GPPB, 2009). These alternatives, however, involved

less or no competition (Jones, 2011), thus, can be resorted to only when specific conditions are

met (GPRA, 2003, and GPPB, 2009).

Contract Implementation and Completion. Contract implementation commences when

the procuring agency issues the Notice to Proceed to the winning bidder (GPRA, 2003, and GPPB,

2009). A procurement contract is considered completed when there is complete delivery in

accordance with the specifications in case of procurement of goods, supplies and materials;

complete work rendered based on the total prescribed period in case of services; time period has

lapsed or the objectives are achieved in case of consultancy; and reaching at least 95% work done

in case of infrastructure projects.

Post-Implementation and Warranty. The procurement process extends beyond

completion until the end of warranty period called the post-implementation. Minimum warranty

period shall be three months for expendable supplies, one year for nonexpendable supplies, one

year from project completion up to final acceptance or the defects liability period for construction

defects on infrastructure projects. In case of structural defects on infrastructure projects, warranty

period shall be fifteen (15) years for permanent structures, five years for semi-permanent

structures, and two years for other structure (GPPB, 2009, and GPRA, 2003).

Pillars of Public Procurement System

There are four key areas - called "Pillars" – that characterize the basic elements of an

agency’s procurement as patterned after the national public procurement system. These “pillars”

are further defined by sixteen (16) baseline indicators and forty (40) sub-indicators against which

the existing elements of the agency’s procurement system may be assessed. These are: Pillar I -

Compliance with the Legislative and Regulatory Framework, Pillar II - Agency Institutional

Framework and Management Capacity, Pillar III - Procurement Operations and Market Practices,

Pillar IV - Integrity and Transparency of the Agency Procurement System (OECD, 2010, and

GPPB, 2012).

These pillars look at compliance to key legal requirements under RA 9184 as it relates to

competitiveness, how the procurement system is operational through the management systems in

the agency, the operational effectiveness and efficiency of the procurement system at the agency

level, and indicators of the procurement system that contribute to integrity and transparency,

respectively (OECD, 2010, and GPPB, 2012). These embrace the entire procurement process that

if any of them is broken, the entire procurement system will fall down. The same pillars are used

by the Indonesian government in evaluating compliance of public procurement in the country;

however, performance indicators are slightly changed and tailored to conform to Indonesian

Page 6: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 382

environment (National Public Procurement Agency of Indonesia, 2011).

Compliance with Legislative and Regulatory Framework. The quest for procurement

reform that conforms to global standards led to the enactment of RA 9184, otherwise known as

the GPRA. The law is a compendium of international best practices and standards and over a

hundred laws, rules and regulations in the past. It standardizes bidding procedures and documents,

increases the accountability of bidding organizations, streamline the procurement system,

enhances end-product quality and contractor reliability, and ensures proper planning and

budgeting. It provides for the modernization, standardization and regulation of the procurement

activities of the government envisioned to deal with the shortcomings of the old procurement

system, fight graft and corruption, address the lack of transparency and competition, eliminate

collusion and political interference, and lessen delays in the procurement process (Jones, 2011,

Bombay, 2011 and Ambat & Ycasiano, 2008).

Compliance with legislative and regulatory framework looks at compliance to key legal

requirements under RA 9184 as it relates to competitiveness which has three indicators and twelve

sub-indicators. The indicators are: Indicator 1 Competitive bidding as default method of

procurement, Indicator 2 Limited use of alternative methods of procurement, and Indicator 3

Competitiveness of the bidding process (OECD, 2010, and GPPB, 2012).

Agency Institutional Framework and Management Capacity. Pillar II Agency

institutional framework and management capacity looks at how the procurement system is

operational through the management systems in the agency which has four base indicators and

eight sub-indicators. The indicators are: Indicator 4 Presence of procurement organization,

Indicator 5 Procurement planning and implementation, Indicator 6 Use of Government Electronic

Procurement System or the PhilGEPS, and Indicator 7 System of disseminating and monitoring

procurement information (GPPB, 2012).

The State recognizes the vital role of information and communication technology (ICT) in

nation-building thus institutionalizing the use of PhilGEPS (Electronic Commerce Act, 2000,

GPRA 2003, Bombay, 2011). However, compliance is problematic in terms of registration and use

of its functionalities (Gonzalez, 2014), thus monitoring is necessary or risk mandates and targets

remain “in name only” (UNEP, 2013).

Procurement Operations and Market Practices. The third Pillar looks at the operational

effectiveness and efficiency of the procurement system at the agency level. It has five

base indicators with fourteen (14) sub-indicators. The indicators are: Indicator 8 Efficiency of

procurement processes, Indicator 9 Compliance with procurement timeframes, Indicator 10

Capacity building for government personnel and private sector participants, Indicator 11

Management of Procurement and Contract Management Records, and Indicator 12 Contract

management procedures (GPPB, 2012).

Integrity and Transparency of the Agency Procurement System. Pillar IV looks at

indicators of the procurement system that contribute to integrity and transparency having four base

indicators and six sub-indicators. The indicators are: Indicator 13 Observer participation in public

bidding, Indicator 14 Internal and external audit of procurement activities, Indicator 15 Capacity

to handle procurement related complaints, and Indicator 16 Anti-corruption programs related to

Page 7: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 383

procurement (GPPB, 2012). This is intended to fight the rising corruption index in the Philippines

(Martin & Flores, 2014, and SWS, 2013). Ackerman (2006) relates corruption to moral category

that signifies putrefaction and rot which significantly impact resource allocation.

Aside from GPRA, laws such as the Anti-Graft and Corrupt Practices Act in 1960, the

Philippine Constitution of 1987, the Act Establishing a Code of Conduct and Ethical Standards for

Public Officials and Employees in 1989, and the Act Defining and Penalizing the Crime of Plunder

in 1991 are passed to prohibit corruption and prevent conflict of interest in the procurement

process. Key watchdog institutions are also established and empowered such as the COA,

Ombudsman Office, GPPB, Presidential Anti-Graft Commission, Sandiganbayan, and

Procurement Transparency Board (Jones, 2011).

Non-compliance of Public Procurement Processes

There has been a worldwide plethora of public procurement policy and regulatory

frameworks but policies and action plans do not always translate into clear changes in how

procurement is implemented. Challenges are prevalent and a gap exist between what the

government agencies are doing and what broader stakeholders think that they are doing (UNEP,

2013).

In theory, the GPRA gained world class distinction but serious weaknesses in the

implementation is prevalent (Jones, 2011). Gonzales (2014) cited that a law is only as good as its

implementation, making GPRA not enough to prevent the notorious corruption cases in the country

(Ambat & Ycasiano, 2008). Problems persist like outdated manual workflows, lack of clear guidelines

in some steps of the process (Bombay, 2011), lack of transparency, absence of accountability, elitist

culture (Jones, 2011), continued preference to alternative modes of procurement (COA, 2012),

misguided priorities, international financial institutions’ disagreement on some provisions, and delays

in the process (Ambat & Ycasiano, 2008). Weak budget allocation process, intricate and non-

transparent budget execution and the predominance of patron-client relationships in politics and the

bureaucracy facilitate corruption in public procurement.

Challenges in Public Procurement

The government procurement system is decentralized, where responsibility and control

rests with each agency. It is perceived to be cumbersome, fragmented and inefficient process with

many loopholes that are prone to corruption (Bombay, 2011). The World Bank (cited in Jones,

2011) reports that waste, inefficiency, lack of transparency, widespread corruption, low levels of

capacity, and the absence of accountability in public procurement greatly affects public

administration, resulting to poorly resourced public services and under-developed infrastructure.

Despite the so-called world class regulation and recent developments, public procurement

in the Philippines never escapes scandals and controversies – among them are the infamous

National Broadband Network or NBN-ZTE deal involving US$329 million (Php16.7 billion) in

2007, the decade-old Php728 million fertilizer fund scam (Ambat & Ycasiaco, 2008), the rigging

of the bidding for the construction of Makati City Hall (Salaverria & Burgonio, 2014), alleged

bribery on the MRT 3 project (Tiglao, 2014), and purchase of information technology equipment

by the Military and Other Law Enforcement Offices Division of the anti-graft agency,

Page 8: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 384

Ombudsman, without public bidding (Punongbayan, 2014). Multiple petitions filed and dismissed

but resurrected when it linked to the Php10 billion pork barrel scam (Ramirez & Rosario, 2014,

Raymundo, 2014, Reyes, 2013, and Valente, 2014). Jones (2011) citing Quah, stressed that these

could be attributed by the lack of effective monitoring and enforcement by watchdog institutions,

the slow phase of investigations and resolution of cases.

STATEMENT OF THE PROBLEM

This case study evaluated the procurement processes of Central Mindanao University based

on RA 9184 “Government Procurement Reform Act” in order to propose a university procurement

manual.

Specifically, this study sought answers to the following questions:

1. How is procurement processes implemented using the pillars of national public

procurement system?

2. If there are non-compliance with the national procurement system, why are these

occurring?

3. What are the challenges faced by the University in attaining full compliance?

4. Based on the findings of the study, what can be incorporated in a proposed university

procurement manual?

RESEARCH METHODOLOGY

This paper is a case study research and used both quantitative and qualitative information.

A case study research poses “how” and “why” questions where the investigator has little control

over events and focuses on contemporary phenomenon within a real-life context (Yin, 2009).

Quantitative information refers to linear attributes, measurements and statistical analysis, while

qualitative information relies primarily on human perception and understanding (Stake, 2010).

This case study used a combination of survey, interview, focus group discussion,

document-search, extraction, and data analyses using financial tools. Semi-structured interviews

and focus group discussions are qualitative data collection methods that are commonly used in

policy research (Harrell & Bradley, 2009). Triangulation was used in data gathering to confirm,

validate and increase confidence in the evidence (Stake, 2010).

The study was conducted at CMU, one of the premier SUCs in the Philippines created by

virtue of RA 4498 (CMU, 2014). Located at Musuan, Maramag, Bukidnon, CMU has been

considered a leading state university in Region 10 with a total appropriation of Php367 million in

2014; second highest and close to the combined appropriations of other five out of seven SUCs in

the region (RA 10633, 2013). It also has gross income amounting to Php93 million from the

University Income Generating Program and Php127 million from tuition and other school fees in

fiscal year 2013 (CMU, 2014). These funds are intended to be utilized for personnel services,

maintenance and other operating expenses (MOOE), capital expenditures, and financial expenses

Page 9: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 385

of the University that are necessary to carry out its mandate. Expenditures classified under MOOE

and capital outlay usually give rise to procurement processes.

A total of fifty-one (51) respondents are chosen using purposive sampling, forty-six (46) are

personnel of the university while five are representatives of select suppliers. Seventy-four (74) percent

of the CMU personnel respondents participate in more than one activity in the procurement

process. This was due to a personnel’s designation to administrative functions or committees that

partakes in the entire procurement cycle.

As to position, 37 percent are heads of units or committee chairpersons while 63 percent

are staff or committee members. End-users comprise 58 percent, while finance personnel comprise

14 percent, technical inspectorate eight percent, and the remaining are members of the budget

committee, the Bids and Awards Committee (BAC), BAC Secretariat, Internal Audit Services, and

Supply and Property Management Offices (SPMO).

Sixty-three (63) percent of end-users were from administrative offices, 13 percent from

colleges, 12 percent from production, and 12 percent spread from research, extension and others.

As to length of service in present position, a majority 52 percent served for 1-5 years, 14 percent

for 11-15 years, 12 percent each for less than one year and more than twenty (20) years, and 10

percent for 6-10 years. As to length of service in CMU, 61 percent served for more than twenty

years, followed by ‘6-10 years’ at 13 percent, ‘16-20 years’ at 11 percent, ‘11-15 years’ at 9

percent, and ‘1-5 years’ at 6 percent.

RESULTS AND DISCUSSIONS

Implementation of Procurement Processes Using the Pillars of National Public Procurement

System

In line with the quest of the national government for more transparent and efficient

procurement process, CMU continue to work on improving its processes through streamlining of

personnel and processes. Though improvements in the process are evident, challenges persist

requiring continued reforms and monitoring. The use of the four pillars of national public

procurement system is important in monitoring the effectiveness of reforms and implementation

of measures to identify strengths and weak areas and to address the weaknesses.

Table 1 shows how respondents perceived the University procurement processes in terms

of the four Pillars and its indicators. Data reveal that overall compliance of the University with the

four pillars is very satisfactory which means that it substantially complied with the requirements

of the national public procurement system. Further scrutiny, however, leads to the formulation of

eleven issues that hinder the University from achieving full compliance.

Compliance with Legislative and Regulatory Framework. Despite the very satisfactory

result as perceived by respondents, verification of records revealed that the use of public bidding

vis-a-vis other modes of procurement is still below the acceptable level, thus giving rise to issue

#1 continued use of alternative method of procurement, particularly shopping (COA, 2014).

Page 10: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 386

Alternative modes of procurement shall be used only in certain cases to promote economy and

efficiency (GPRA, 2003, and GPPB, 2009). This reconciles with the report of UNEP (2013) that

there is a gap between what the government is doing and what the broader stakeholders think that

they are doing. Another issue which thwarts the university in achieving full compliance is issue #2

few suppliers acquire bid documents and join the bidding.

Agency Institutional Framework and Management Capacity. Results in the second

pillar is indicative of the efforts of management to stabilize the organizational structure knowing

how a strong, well-planned environment and so-called ‘tone-at-the-top’ principle influence the

achievement of its objectives. Compliance to this pillar underscores emphasis to planning (GPRA,

2003, and GPPB, 2009) and upholds uniform and transparent procurement process (Ambat &

Ycasiano, 2008, and Bombay, 2011). While the University appears to be strong in this pillar, a

weak point still prompts issue #3, lack of feedback mechanism.

Procurement Operations and Market Practices. The University procurement process

performs the least in pillar 3 where the University posted a mediocre result. Though still within

the acceptable level, many weaknesses are imminent giving rise to six issues – more than all the

other three pillars combined, to wit: issue #4, there are items purchased not in accordance with the

specifications indicated in the Project Procurement Management Plan (PPMP); issue #5,

occurrence of failed biddings; issue #6, delay in procurement of goods, services and infrastructure

projects; issue #7, lack of performance evaluation system specific for procurement personnel; issue

#8, there is a need to improve the system of documents and records keeping; and issue #9, the

University has no written procedures for quality control, acceptance and inspection of goods,

services and works.

Table 1

Pillars of National Pubic Procurement System and its Indicators Weighted Mean (n=46)

Pillar Indicator Weighted Mean Interpretation

1

Competitive bidding as a default method

of 4.31 Extensively Practiced

procurement

2

Limited use of alternative methods of

procurement 4.32 Extensively Practiced

3 Competitiveness of the bidding process 4.07 Extensively Practiced

1 Compliance with Legislative and Regulatory Framework 4.17 Extensively Practiced

4 Presence of organizational procurement 4.72

Very Extensively

Practiced

5

Procurement planning and

implementation 4.57

Very Extensively

Practiced

6

Use of Government Electronic Procurement

System 4.62

Very Extensively

Practiced

(PhilGEPS)

7 System of disseminating and monitoring 3.99 Moderately Practiced

procurement information

2 Agency Constitutional Framework and Management

Capacity 4.54

Very Extensively

Practiced

8 Efficiency of procurement processes 3.79 Moderately Practiced

Page 11: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 387

9 Compliance with procurement timeframe 3.59 Moderately Practiced

10

Capacity building for government personnel

and 3.41 Moderately Practiced

private sector participants

11

Management of procurement and

contract 3.69 Moderately Practiced

management records

12 Contract management procedures 3.80 Moderately Practiced

3 Procurement Operations and Market Practices 3.67 Moderately Practiced

13 Observer participation in public bidding 3.35 Moderately Practiced

14

Internal and external audit of

procurement 4.58

Very Extensively

Practiced

15 Capacity to handle procurement related 3.94 Moderately Practiced

complaints

16

Anti-corruption programs related to

procurement 3.74 Moderately Practiced

4 Integrity and Transparency of the Agency Procurement

System 4.00 Extensively Practiced

Overall Weighted Mean 4.09 Extensively Practiced

Integrity and Transparency of the Agency Procurement System. Results reveal how

the University upholds integrity and transparency in the procurement system. Importance is given

by the administration to both internal and external audit findings. Weak areas give rise to issue

#10, very few to no observer present during the bidding process and issue #3, lack of feedback

mechanism in terms of internal procurement complaints. This, however, does not apply to protests

by bidders since the University receives no procurement protest in the past three years. Results are

also evident of issue #11, specific anti-corruption programs are not perceptible. The University

implemented specific programs but many do not realize the purpose of these programs or activities.

Among the good governance programs implemented are the revival of the internal audit service,

the creation of quality assurance office, and the streamlining of personnel assignments and

functions. Anti-corruption programs include conduct of investigative audits on anonymous

complains, taking appropriate actions on audit findings, empowerment of processors conducting

pre-audit of disbursements before payment is made, and so on.

The Journey towards Full Compliance

The results clearly indicate that though there was no area that is non-compliant, full

compliance is yet to be achieved. This means that the University should not rest on its laurels but

continue to implement reforms not only to further strengthen the weaker areas but also to maintain

its strong points. There is also a need to ensure that reforms implemented and will be implemented

are sustainable.

All the four pillars have positive linear relationship which means that these tend to increase

together. Pairing pillars 1 and 2, 1 and 3, and 3 and 4 have a statistically significant linear relationship

(p < .001) and strong association (.5 < |r| ...). Pairing pillars 2 and 3, 1 and 4, and 2 and 4 resulted to

moderate association (.3 < |r| < .5). This means that when the University fails in one pillar, the rest will

also be strongly or moderately affected. The success of one will be a success of all, but the failure of

one will also cause the failure of the entire system. Hence, any flaw must

be promptly addressed before it can cause damage to the entire system. As suggested by Ambat &

Page 12: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 388

Ycasiano (2008), issues need to be looked into and addressed promptly, otherwise reforms will

remain theoretical.

The CMU administration made remarkable efforts to resolve some issues uncovered during

the course of data gathering such as fixing issues on incompatible functions and the quest towards

ISO 9001:2008, International Standard on Quality Management Systems certification. Yet, full

compliance was not achieved due to diverse reasons affirming the claim of Jones (2011) that

weaknesses in the implementation is prevalent.

The interdependence of the four pillars resulted to intertwined factors and circumstances

that caused the eleven issues identified. These include lack of orientation of newly hired personnel

and continued capability building to existing personnel on key processes, policies and procedures;

lack of established processes to ensure coordination by project leaders with the appropriate offices;

absence of Registry of Accredited Suppliers; absence of written policies and procedures; lack of

avenue to raise written complaints; absence of registry of routinely procured items; and lack of

feedback mechanism among others. The manual process flow also caused these issues, prompting

the need to develop software and databases to automate key activities like the preparation of PPMP,

consolidation of APP, preparation of Purchase Request, bid documents, and so on. In addition, the

present condition like the lack of spacious warehouse, absence of facilities, manpower shortage,

and lack of mobility and telephone in the SPMO also create adverse effect to the entire

procurement process.

Boulders in Achieving Full Compliance

Inasmuch as the University administration desire to address all the issues and problems

affecting its procurement activities and achieve full compliance to requirements of the law, it is

hindered by circumstances that are beyond its control. Such challenges affect how these issues are

resolved. In some cases, these challenges require the administration to make decisive actions or

implement countermeasures to ensure that best results are achieved while laws and rules are still

being followed.

The challenges faced by the University in achieving full compliance include approval and

release of funds by external agencies that do not coincide with the period of preparation of PPMPs

and APP; stringent timeframe of externally-funded projects; absence of interested suppliers to

apply for accreditation; lack of bidder understanding on some eligibility requirements; unique

nature of production operations and research requirements; manual workflow and tedious

processes; budgetary and funding constraints; limited manpower capabilities and technology

literacy; taking balance between efficiency and compliance with laws, rules and regulations; and

resistance to change.

CONCLUSION

Based on the results, the researcher concluded that the University still has a lot of things to

do in order to achieve full compliance with the requirements of national public procurement

system. There are deficiencies in the implementation that give rise to issues that hinder the

University from achieving a streamlined procurement process that is transparent, competitive, and

uphold proper accountability and public monitoring. Despite efforts that emanate from top

Page 13: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 389

management, internal problems and challenges posed by external factors remain inevitable and

need to be dealt with. Nevertheless, it cannot be undermined that management had done a good

job in improving the system.

RECOMMENDATIONS

Based on the foregoing facts, the researcher come up with various recommendations and

reiterates the recommendations given by the respondents during the course of data gathering.

In order to address the weaknesses in the University procurement processes, it is highly

recommended to orient and re-orient newly hired and existing personnel on key policies and

procedures; establish mechanisms to ensure proper flow and diligent submission of documents and

records to pertinent offices, as well as proper filing and retention of documents and records;

prepare written policies and procedures and ensure its wide distribution to University personnel;

enhance and restore the document tracking system; and create a centralized database for inventory

and property management. It is also recommended to utilize and consult experts in the University

on matters related to procurement, hire supply personnel to replace the retired ones, construct

warehouse equipped with basic warehousing paraphernalia, assign a vehicle or motorcycle for

buyers to improve their mobility, install a working telephone or assign a cellphone to the SPMO,

design performance evaluation specifically designed for procurement personnel and anchored on

the provisions of GPPB Circular No. 10-2012 and related guidelines; establish programs to address

complaints; and establish a whistleblower program.

The BAC is also recommended to create Registry of Suppliers and encourage tested

suppliers to register, prepare registry of routinely procured items with the latest purchase cost,

track requests not yet purchased, and invite more observers aside from those regularly invited.

It is further recommended that SPMO should track deliveries and undelivered items,

schedule a regular follow-up with suppliers, control issuances of supplies to various units, and

maintain stock cards for all supplies and materials. The budget and planning offices shall also

identify projects to be funded from University income prior to the year of implementation.

In addition, it is recommended that the University adopt the proposed University procurement

manual produced as an output of this case. The proposed manual is crafted to include

key policies, process flowcharts, authorities and responsibilities, and description of processes. The

ACTION Plan created by M. Poliran (2013) can be used in the implementation. A-C-T-I-O-N Plan

stands for:

A – Appoint. Appoint pool of experts to evaluate the contents of the proposed University

procurement manual.

C – Create. Create a final draft of the University Procurement Manual. This will undergo

the normal approval process by the Administrative Council, and finally the Board of Regents.

T – Trim down. Trim down to high level procedures. Make sure that the manual will

contain only the high level procedures in order not to over-complicate the manual which could

render it less useful.

Page 14: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 390

I – Inform. Inform all key players. All end-users and process owners shall be informed

about its contents and be given easy access thereto. The objectives could not be achieved unless it

is communicated till the lowest level of users.

O – On-time completion. The preparation and approval of the manual must be time-bound.

The sooner it will be made available, the faster its related issues will be resolved and future damage

to the University can be avoided.

N – Noteworthy monitoring. Monitoring of the implementation of the manual must be pro-

active and not passive. The manual shall also be reviewed, evaluated and updated regularly to

maintain conformance to pertinent laws, rules and regulations.

The researcher further recommends that the GPPB should tap relevant accredited

professional organizations like the Philippine Institute of Civil Engineers and Philippine Institute

of Certified Public Accountants to institutionalize their representation as observers in public

bidding proceedings of government agencies. These organizations should establish programs that

would train observer representatives on the requirements of RA 9184, its IRR and other relevant

laws, rules and regulations. Should the representative submits reports about violations observed

during the bidding process, there is also a need to protect the member in case of charges or

countercharges filed by erring officials or prospective bidders. Local chapters may not have the

resources to protect its members, hence the need for intervention at the national level. This will

help maintain the independence of observers while improving observer presence during public

bidding proceedings of government agencies.

Further, this case study should be replicated in other government agency for comparison

purposes and in the same agency at a future date for continual improvement of procurement

processes.

Page 15: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 391

References

Books

Ackerman, S. R. (2006). International handbook on the economics of corruption. USA: Edward

Elgar Publishing, Inc. ISBN-13:978 1 84542 242 2.

Stake, R. E. (2010). Qualitative research: Studying how things work. New York USA: Guilford

Press, Inc. ISBN 978-1-60623-545-4.

Yin, R. K. (2009). Case study research design and methods (4th

ed.). USA: SAGE Publications,

Inc. ISBN 978-1-4129-6099.

Government Documents and Reports

Central Mindanao University. (2014). Notes to financial statements for fiscal year 2013. Central

Mindanao University: Bukidnon, Philippines.

Commission on Audit (COA). (2012, September 27). 2011 Audit Performance Summary Report.

Retrieved from World Wide Web http://www.coa.gov.ph/index.php/reports/audit-

performance-summary-report, accessed November 26, 2014.

COA Office of Audit Team Leader. (2014, February 10). Audit Observation Memorandum (AOM)

No. 2014-04 (2013). Team 3 Audit Group H SUCs.

Department of Budget and Management (DBM). (2011). Budget expenditures and sources of

financing (BESF) for fiscal year (FY) 2012. Table A.1 and B.1. Retrieved November 11,

2014 from http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2012/A/A1.pdf; and

http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2012/B/B1.pdf.

DBM. (2012). BESF for FY 2013. Table A.1 and B.1. Retrieved November 9, 2014 from

http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2013/A1.pdf; and

http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2013/B1.pdf.

DBM. (2013). BESF for FY 2014. Table A.1 and B.1. Retrieved November 9, 2014 from

http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2014/A1.pdf; and

http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2014/B1.pdf.

DBM. (2014). BESF for FY 2015. Table A.1 and B.1. Retrieved November 9, 2014 from

http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2015/A1.pdf; and

http://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2015/B1.pdf.

DBM. (2015). BESF for FY 2016. Table A.1 and B.1. Retrieved September 18, 2015 from

http://www.dbm.gov.ph/?page_id=13354.

Philippine Government Electronic Procurement System (PhilGEPS). (2014). PhilGEPS software

modernization status update. Retrieved November 4, 2014 from

Page 16: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 392

http://www.gov.ph/governance/wp-content/uploads/2013/05/PhilGEPS.pdf.

Laws, Rules and Standards

Administrative Order No. 17. (2011, July 28). Directing the Use of the Procurement Service and

the Philippine Government Electronic Procurement System in Procurement Activities in

Accordance with Republic Act No. 9184, and Improving the Operation of the Procurement

Service.

Executive Order No. 40. (2001, October 8). Consolidating procurement rules and procedures for

all national government agencies, government-owned or controlled corporations and

government financial institutions, and requiring the use of the government electronic

procurement system.

Government Procurement Policy Board (GPPB). (2009). Revised Implementing Rules and

Regulations of Republic Act 9184.

GPPB. (2012, June 1). Resolution approving and adopting the agency procurement compliance

and performance indicators (APCPI) as standard procurement monitoring and assessment

tool. Resolution No. 10-2012.

Republic Act No. 8792: Electronic commerce act of 2000. (2000). An act providing for the

recognition and use of electronic commercial and non-commercial transactions and

documents, penalties for unlawful use thereof and for other purposes.

Republic Act No. 9184: Government Procurement Reform Act (GPRA). (2003, January 10). An

act providing for the modernization, standardization and regulation of the procurement

activities of the government and for other purposes.

Republic Act No. 10633: General Appropriations Act (GAA) for Fiscal Year 2014. (2013,

December 27). An act appropriating funds for the operation of the Government of the

Republic of the Philippines from January one to December thirty-one, two thousand and

fourteen, and for other purposes.

Online Journals and Commissioned Researches

Ambat, G. H., & Ycasiano, R. K. (2008, August). Plugging the loopholes of the Philippine

procurement system. Senate Economic Planning Office Policy Brief. PB-08-05. Retrieved

from World Wide Web https://www.senate.gov.ph/publications/PB%202008-05%20-

%20Plugging%20the%20Loopholes.pdf, accessed on October 16, 2014.

Bombay, N. M. (2011, June). Philippines: Case study on The Philippine government electronic

procurement system (PhilGEPS). ADB Technical Assistance Consultant’s Report. Project

Number: 43149-01. Retrieved from World Wide Web

http://www.adb.org/sites/default/files/projdocs/2011/43149-012-reg-tacr-01.pdf

accessed on October 16, 2014.

Page 17: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 393

Jones, D. S. (2011). Reforming public procurement in the Philippines: Progress and constraints.

International Public Procurement Conference (IPPC). Retrieved from World Wide Web

http://www.ippa.org/IPPC4/Proceedings/01ComparativeProcurement/Paper1-14.pdf

accessed on October 16, 2014.

National Public Procurement Agency (NPPA). (2011). Compliance and performance indicators of

public procurement in Indonesia. . 2011 Pilot Survey Report. NPPA: Indonesia. Retrieved

from World Wide Web

http://a4des.org/documents/Compliance_and_Performance_Indicators_of_Public_Procur

ement_in_Indonesia.pdf, accessed November 26, 2014.

Organization for Economic Co-operation and Development (OECD). (2010, February).

Methodology for Assessing Procurement Systems (MAPS). Retrieved from World Wide

Web http://www.oecd.org/development/effectiveness/45181522.pdf, accessed November

26, 2014.

O’Riordan, N., Nicholson, D., Hughes, L., & Phear, A. (2011, February). Examining the carbon

footprint and reducing the environmental impact of slope engineering options. Ground

Engineering. 28-30. Retrieved from World Wide Web

http://www.nce.co.uk/Journals/2014/06/17/s/f/d/GE-Feb-2011-Examining-the-carbon-

footprint-and-reducing-the-environmental-impact-of-slope-engineering-options-

ORiordan-Nicholson-Hughes-Phear.pdf, accessed September 17, 2014.

Singh, R. K., Murty, H. R., Gupta, S. K., & Dikshit, A. K. (2012). An overview of sustainability

assessment methodologies. Ecological Indicators. 15 (2012), 281-299. Retrieved from

World Wide Web http://ac.els-cdn.com/S1470160X11000240/1-s2.0-

S1470160X11000240-main.pdf?_tid=3dfe2e18-3d78-11e4-9f01-

00000aacb35e&acdnat=1410854917_7ab9b55ba8cf11c2c5a1d23ed12b4beb, accessed

September 16, 2014. Doi: 10-1016/j.ecolind.2011.01.007.

United Nations Environmental Programme (UNEP). (2013, December). Sustainable public

procurement: A global review. Final Report. Retrieved from World Wide Web

http://www.unep.org/resourceefficiency/Portals/24147/SPP_Full_Report_Dec2013_v2%

20NEW%20%282%29.pdf, accessed December 2, 2014. ISBN: 978-92-807-3332-7.

Other Sources

Bergman, M. A. (2011). Tender Evaluation and Award Methodologies in Public Procurement.

Retrieved from World Wide Web

http://www.researchgate.net/profile/Mats_Bergman2/publication/228176298_Tender_E

valuation_and_Award_Methodologies_in_Public_Procurement/links/02e7e52120515ab

d65000000, accessed October 16, 2014.

European Commission. (2011, April 27). Green accounting as the path to a sustainable future

Page 18: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 394

(European Commission Environmental Technologies in Action Plan). Retrieved from

World Wide Web http://www.greenbiz.com/blog/2011/04/27/green-accounting-path-

sustainable-future, accessed September 4, 2014.

Gonzales, I. C. (2014). Public procurement: Implementation, not law, is the problem. Citizen

Action Network for Accountability. Retrieved from World Wide Web

http://www.citizenaction.net/index.php/component/content/article?id=101:public-

procurement-implementation-not-law-is-the-problem, accessed October 16, 2014.

Harrell, M.C. & Bradley, M.A. (2009). Data collection methods: Semi-structured interviews and

focus groups. Training Manual. RAND National Defense Research Institute, Pittsburgh,

PA.

Martin, K. & Flores, H. (2014, December 4). Corruption index: Phl improves rank. The

Philippine Star. Retrieved from World Wide Web

http://www.philstar.com/headlines/2014/12/04/1398765/corruption-index-phl-improves-

rank, accessed December 7, 2014.

Ortega, A. V. (2010). Performance evaluation of the business management resources development

projects at Central Mindanao University. Unpublished dissertation. Central Mindanao

University, Bukidnon.

Poliran, M. C. (2013). Evaluation of internal control of the income generating projects in a state

university in Mindanao. Unpublished thesis. University of San Carlos, Cebu City.

Punongbayan, M. (2014, March 17). Ombudsman violated procurement law – COA. The

Philippine Star. Retrieved from World Wide Web

http://www.philstar.com/headlines/2014/03/17/1301792/ombudsman-violated-

procurement-law-coa, accessed on October 16, 2014.

Ramirez, J. & Rosario, B. R. (2014, May 9). Ombudsman clears GMA in fertilizer fund scam.

Manila Bulletin. Retrieved from World Wide Web http://www.mb.com.ph/ombudsman-

clears-gma-in-fertilizer-fund-scam/, accessed October 16, 2014.

Raymundo, P.T. (2014, January 30). SC junks case vs. ex-Ombudsman Gutierrez on fertilizer fund

scam. Philippines Today. Retrieved from World Wide Web

http://www.philippinestoday.net/archives/13208, accessed October 16, 2014.

Reyes, E. (2013, September 12). Not just pork – 3 Napoles NGOs involved in P728-M fertilizer

scam – Benhur Luy. InterAksyon. Retrieved from World wide Web

http://www.interaksyon.com/article/70577/not-just-pork--3-napoles-ngos-involved-in-

p728-m-fertilizer-scam---benhur-luy, accessed October 16, 2014.

Salaverria, L. B. & Burgonio, T. J. (2014, September 5). Makati building contracts rigged.

Philippine Daily Inquirer. Retrieved from World Wide Web

http://newsinfo.inquirer.net/635445/makati-building-contracts-rigged, accessed October

Page 19: Procurement processes in a state university in Mindanao: A ...Procurement processes in a state university in Mindanao: A case study by Sheila Mae L. Lupian-Poliran, Central Mindanao

National Business and Management Conference 2015 | p. 395

16, 2014.

Social Weather Station (SWS). (2013). The 2013 SWS survey of enterprises on corruption.

Retrieved from World Wide Web

http://www.sws.org.ph/pr20140115b_2013%20Survey%20of%20Enterpises%20Executi

ve%20Summary.pdf, accessed December 7, 2014.

Tiglao, R. (2014). MRT 3 mess the worst kind of corruption. The Manila Times Online. Retrieved

from World Wide Web http://www.manilatimes.net/mrt-3-mess-worst-kind-

corruption/132053/, accessed October 16, 2014.

Valente, C. S. (2014, May 16). Aquino orders review of fertilizer fund scam. The Manila Times.

Retrieved from World Wide Web http://www.manilatimes.net/aquino-orders-review-of-

fertilizer-fund-case/97175/, accessed October 16, 2014.