procurement quality-management pjm400 mod2

24
1 Module 2 Ken Hogan Procurement Process In Construction Industrial Project

Upload: khogan62

Post on 15-Jun-2015

121 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Procurement quality-management PJM400 Mod2

1

Module 2Ken Hogan

Procurement Process In Construction Industrial Project

Page 2: Procurement quality-management PJM400 Mod2

1. Definition 2. Objective 3. Procurement process 4. Performance indictor 5. Improvement 6. Benefits 7. Conclusion

2

Page 3: Procurement quality-management PJM400 Mod2

Definition It is the process required to supply equipment , material , service and other resources needed to carry out a project that satisfy customer

3

Page 4: Procurement quality-management PJM400 Mod2

Item Description Weight

1 Engineering 5%

22 Equipment / Material Equipment / Material 65%65%

33 Construction Construction 15%15%

4 Testing and Commissioning 10%

4

Page 5: Procurement quality-management PJM400 Mod2

1-Setting procurement process requires to supply equipment , materials and other resources to carry out in constructing industrial project right the first time right the first time and every time.and every time.

2- Monitoring performance indictor to help

manager to prevent and reduce problem that can affect the procurement process.

5

Page 6: Procurement quality-management PJM400 Mod2

1. Planning2. Documentation3. Product Evaluation4. Awarded 5. Administration 6. Inspection7. Delivery

6

Page 7: Procurement quality-management PJM400 Mod2

7

Documentation

Product Evaluation

Awarded

Begin

Delivery

Planning

Inspection

Page 8: Procurement quality-management PJM400 Mod2

Input 1. Scope of work2. Specification and drawings 3. Company resource4. Signature mandate 5. Product estimated value

8

Page 9: Procurement quality-management PJM400 Mod2

Output1. Product list 2. Product supplier list3. Type of procurement contract

1. Sole source2. Single source3. Competitive bids

4. Estimated product value5. Approval to proceed with procurement

9

Page 10: Procurement quality-management PJM400 Mod2

Tender documents Standardized forms

Inquiry Invitation letter Purchase order General terms and condition Filing system

10

Page 11: Procurement quality-management PJM400 Mod2

1. Price 2. Delivery time3. Financial capability of supplier 4. Type of product 5. Historical of supplier6. Supplier approaches 7. Workload existing and anticipated 8. Customer feedback

Reference Approval

11

Page 12: Procurement quality-management PJM400 Mod2

1. Notify successful tender and unsuccessfully tender of outcome

2. Compile contract documents3. Formally accepted tender offer

12

Page 13: Procurement quality-management PJM400 Mod2

Monitor supplier progress Inspection Shipment and delivery Payment Check compliance with quality

13

Page 14: Procurement quality-management PJM400 Mod2

1. Cycle times The different activities within PP

2. Milestone events Issuing R.Q - PO Approval of drawings Inspection Customs clearance Delivery

3. Management Project police Project Organization

14

Page 15: Procurement quality-management PJM400 Mod2

4. Cost Indicator No of days in warehouse No of days in customs No of days correction / repair No of changes to air transportation Time from arrival till installation

5. Referential values Amount of PO No and amount of change orders Delivery / invoicing

15

Page 16: Procurement quality-management PJM400 Mod2

16

Page 17: Procurement quality-management PJM400 Mod2

1. Shortage of materials2. Out of specification 3. Incomplete delivery 4. Excess of materials 5. Damage and defective

17

Page 18: Procurement quality-management PJM400 Mod2

18

Page 19: Procurement quality-management PJM400 Mod2

Whether the procurement satisfied the stated objective

Whether needs and expectation have be meets

Whether the procurement process should be improve

How external factors such regulation , standard component have change

Whether the process improve cost saving

19

Page 20: Procurement quality-management PJM400 Mod2

Review of performance indicator Review non conformity report Effect analysis regarding delays Costs and time cycles

20

Page 21: Procurement quality-management PJM400 Mod2

21

Page 22: Procurement quality-management PJM400 Mod2

1. Improve company and project reputation name 2. Achieving customer satisfaction and increase

market share 3. Reduce rework and mistake 4. Standardized forms 5. Reduce warranty period 6. Increase profit7. Lower insurance cost8. Improve cash follow

22

Page 23: Procurement quality-management PJM400 Mod2

The problem present on procurement are of different types and origins. The most detected problem :

Planning Delay on issuing specification for quotation Delay on informing supplier

Supplier To many obstacles and clauses delay

negotiations Poor explanation about items Later purchase makes system expensive , air

freight and urgent

23

Page 24: Procurement quality-management PJM400 Mod2

1. Delay at delivery2. Delay on ordering3. Delay on engineering drawings ( errors) 4. Repair and replacement at job site 5. Poorly planned inspection6. Lack of information on site about arrival for some supplier 7. Changes to air transportation to make faster delivery

Using PP indicator and periodical report is tools to monitor and prevent delays

Using IT ( email , scheduling etc ) will help in reducing delay and closely monitor the product progress for necessary action .

24